1. PROJECT PROGRESS REPORT
As of EO March 2012
Project Title: Red and Black School Building Program
Implementing Agency: DepEd -CAR
Donor: (X) GOP Loan/Grant Proceeds:
( ) Loan Peso Counterpart:
( ) Grant Total Project Cost: 146.54 M (CY 2011)
142.7 M (CY 2012)
Location/Area Coverage: Regionwide
Description:
The Regular School Building Program specifically targets schools which are
categorized under the Red Zone or those which have a ratio of 56 or more students to
one classroom: and the Black Zone, or schools which make use of makeshift
classrooms and facilities.
The standard DepEd design is 7m x 9m classroom for rural areas with a classroom-
student ratio of 1:45. This standard also applies to all public secondary schools,
regardless of location and class size.
In CAR, the CY 2011 projects (carry-over) have a total project cost of Php 146.5 M.
The table below shows the details per province/city:
Province/city No. of sites No. of Project Status
(CY 2011) Classrooms Cost (AO Mar
2012)
Abra 18 16 17,436,000 70.56%
Apayao 21 26 15,812,000 85.78%
Benguet 18 28 25,793,000 94.50%
Ifugao 13 21 15,993,000 90.56%
Kalinga 40 64 41,486,000 88.91%
Mt. Province 33 34 20,042,000 89.89%
Baguio 6 10 9,981,000 100%
Total, CAR 149 209 146,543,000 88.44%
Meanwhile, SARO (Php 142.7 M) for CY 2012 projects is yet for release which
caused implementation delay.
2. Project Duration: Start: January End: December
PROJECT PROGRESS
For CY 2012 AO 1 Quarter AO 2nd Quarter AO 3rd Quarter AO 4th Quarter
st
Target
Actual 88.44 %
Slippage
Cumulative Status: Status Physical Financial
(Since start of Target
project) Actual (slippage) 88.44%
Current Late release of project SARO for CY 2012
Implementation
Issues and/or
Problems
Encountered (if any):
Actions Taken/ Followed-up SARO release
Recommendations:
Remarks:
Agency Contact DIR. ELLEN B. DONATO
Person: OIC-Regional Director IV
Wangal, La Trinidad
2601 Benguet
Tel No. 422-1318 (RD)