SlideShare a Scribd company logo
1 of 14
Download to read offline
See discussions, stats, and author profiles for this publication at: https://www.researchgate.net/publication/316429977
DESIGN OF AUTOMATIC WALL PLASTERING MACHINE
Article Ā· April 2017
DOI: 10.5281/zenodo.439237
CITATIONS
2
READS
13,893
2 authors, including:
Some of the authors of this publication are also working on these related projects:
Total Productive Maintenance View project
Development of Fixture View project
Laukik P. Raut
Raisoni Group of Institutions
44 PUBLICATIONSĀ Ā Ā 123 CITATIONSĀ Ā Ā 
SEE PROFILE
All content following this page was uploaded by Laukik P. Raut on 24 April 2017.
The user has requested enhancement of the downloaded file.
ISSN: 2277-9655
[Askar* et al., 6(3): March, 2017] Impact Factor: 4.116
ICā„¢ Value: 3.00 CODEN: IJESS7
http: // www.ijesrt.com Ā© International Journal of Engineering Sciences & Research Technology
[543]
IJESRT
INTERNATIONAL JOURNAL OF ENGINEERING SCIENCES & RESEARCH
TECHNOLOGY
DESIGN OF AUTOMATIC WALL PLASTERING MACHINE
Ankush N. Askar*, Laukik P. Raut
*
Student, M. Tech CAD/CAM, GHRCE Nagpur, India
Department of Mechanical Engineering, GHRCE Nagpur, India
DOI: 10.5281/zenodo.439237
ABSTRACT
Due to manual process of wall plastering on construction site, there is a huge scale requirement of labor and hence
the labor cost is responsible for increasing the price of construction or project work. The quality of work is mostly
depending on the skill of the labor work in manual plastering process.
The solution of these problems is just to automate the process, so that there will be a saving of period and cost
and getting good plaster finishing to the walls. The plastering machine can plaster the walls automatically and
very smoothly. Due to which the process will fast and there will be saving of cost and time this will helps to reduce
the total cost, total time which ultimately responsible for the growth and hence the progress rate of a country is
going to increase.
KEYWORDS: Plastering, Plasterboard, AC/DC motor, gears, wire ropes, labor cost etc.
INTRODUCTION
Construction sector is responsible for a progress of any country, because most of the growth of the nation is
depending upon industrialization, civilization, transportation etc which compulsorily has their initial stage of
building construction or simply construction. It is a biggest economic sector because of it the development trade
in most countries amounts to 10-20% of the total national product, still due to labor demand and most of the work
is repetitive it is a slow manual process [2]. So for improving the economic growth of the country and indirectly
developing the lifestyle of the countryā€™s people there must be need of improving the techniques of working.
Construction sector is unique sector which required more time and money, having very slow and stepwise process.
Presently in construction sector near about all the processes are manual which required more time for their
completion. Due to which the cost of the project is maximum, hence it must be necessary to automate the processes
in the construction work and improve the efficiency of it. Wall plastering is the main procedure among the
processes followed in the building construction, which is used for plaster the walls of the construction to get
smooth and finished wall surfaces. Plastering is also essential to give specified strength to the walls; it protects
the walls from moisture from both the sides. Wall plastering also gives good look to the walls and ultimately
creates best residential condition in the particular room. But in present days wall plastering is being done manually
in most of the part of world i.e. the procedure of wall plastering is being done with the assist of labors. Due to
which the process is lengthy. So this is an initiative towards the automation in plastering technique.
EXISTING TECHNIQUE AND ITS DOWNSIDES
The existing technique for plastering the walls is manual i.e. the labors are used to plaster the walls with their
hand by using some instruments like flat board or other flat surface object which are made by metal, wood or
plastic. Fig. 1 describes the current plastering techniques. In this process the mortar which is the mixture of cement
and sand has been spread on the wall which is to be plaster with the help of these objects. After dispersal the
mortar the labor need to concentrate to make a skinny film of mortar on the wall, which has been smooth and
having good surface finish. Due to which labor need to work repeatedly until he get the required surface finish.
ISSN: 2277-9655
[Askar* et al., 6(3): March, 2017] Impact Factor: 4.116
ICā„¢ Value: 3.00 CODEN: IJESS7
http: // www.ijesrt.com Ā© International Journal of Engineering Sciences & Research Technology
[544]
Fig. 1 Current plastering methods
This process takes long time and consumes additional human power. So due to this slow process the labor cost
has also been increase as the labors are working on daily basis. If the labor is not a skilled person then there have
been a low quality work and there have been wastage of material. Ultimately the manual plastering technique
have some downsides like high cost, more time, material wastage and low quality work due to unskilled labors.
PROBLEM IDENTIFICATION
In the manual plastering technique, the crucial factor is skilled labor because of which plastering has been done
on the walls, but presently there is lack of skilled labors due to which it is very inconvenient to complete this
process. The labor requires more time to finish the process which increases their wages and hence the total
plastering or labor cost increases.
Objectives
From the above discussion about old plastering techniques, problems in old plastering techniques, their downsides,
background of the plastering method and the decided aim to be achieve following are some objective have been
decided.
1. This Machine will reduce the human work.
2. It will be straight forward in construction and simple to control.
3. Higher excellence of the plaster can acquire.
4. It will be move horizontally from to other place. So that it will be portable.
5. It will assist to save labor cost.
6. It will avoid wastages of the mortar, thus to save the cost.
7. Machine cost will be less than existing machines.
8. It can be control with the help of remote controller.
LITERATURE REVIEW
For the modification of the plastering technique lots of work had been done in the past by many people, but due
to some problems or deficiencies in that some machines has not been that much in working condition. For getting
an idea about the work done in the record on plastering technique it is necessary to do the literature survey and
review. According to that following are some vital points which have been taken from the recoded literature and
are very much important for designing new Automatic plastering machine.
History of plastering machine
Ali Al-Hamad, etal [1] stated that the machines were developed firstly have a task of mixing automatically and
made mixture due to which it was easy for plastering. The launching of RUMA 1, Putzmeister 1 and Putzmeister
Gipsomat developed in sixties century. The AMPA machine is the development in machines.
Israe is the country in which ā€˜TAMIRā€™ had been developed. But these innovations have not been capable to give
a step ahead in the plastering industry. Thus even today, the plastering machines developed in the sixties are still
considered to be up to date.
Trowel Technique
Mahesha P.K, etal [2] Experimented the trowel operation procedure which is a customary plastering method. The
exact plastering procedure is dependent on how the trowel is being used and apply coat of mortar on wall.
Receiving a good finish is the grouping of compact force combined with the right angle of trowel, how distant the
foremost edge is with the wall. The foremost edge will be approximately 10-15 mm away apart from the wall.
ISSN: 2277-9655
[Askar* et al., 6(3): March, 2017] Impact Factor: 4.116
ICā„¢ Value: 3.00 CODEN: IJESS7
http: // www.ijesrt.com Ā© International Journal of Engineering Sciences & Research Technology
[545]
Fig. 2 Trowel technique
Arunkumar Biradar, etal [3] Demonstrated the trowel technique. The right layer technique is essential with
exclusively the trowel getting used to use and end the skim coat. Achieving a well-mannered finish is that the
grouping of compact pressure and the correct angle of trowel. So front position of the trowel is an absolute
approach from the wall. With the resultant stroke, the plaster is simply spread with the help of trowel on the wall
surface.
Fig.2 describes the trowel operation technique in early covering technique. The right layering method is vital with
exclusively the trowel used to and finished the skim coat. Achieving a well-mannered end is that the combination
of compact pressure and the correct angle of trowel (how so much the front position is from the wall). Layering
technique for applying plaster is initiated by trowel burdened with plaster, the front position of trowel need to
move step by step addicted to the wall. With resultant hit of trowel used for layering the plaster as only applied.
There'll be no plaster on trowel and it'll be quite flat the forefronts are more or less ten-fifteen millimeter unit
detached from the wall.
Pre-plastering requirements
Mahesha P.K, etal [2] Stated that the brick structure should be developed in proper manner, with the
manufacturerā€™s condition and suggested installation procedure. All pre-requirement must be fulfilled, otherwise
failing to permit the condition to fully cure can result in excess contraction and cracking on the pointing lines after
the walls plastering. 3 mm deviation in surface alignment is allowable over 1200 mm radius.
Components need to be fabricate
Arunkumar Biradar, etal [3] Shows that the structures of a machine are fabricated by using required necessary
components like steel frame, sheet metal, metal bars, lead screw, AC/DC motors, wheels nut and bolts all these
can be well assembled as for the requirement.
Ali Al-Hamad, etal [1] explained that, the components need to be fabricated for the machine are ceiling bean, steel
tube, upper adjustable touch, conveyor belt, plastering board, resist board, supporting bar, lower adjustable touch,
hydraulic base, hydraulic handle, hydraulic pedal, oil window, driving shaft, rollers, driveshaft, gears, pulleys etc.
Drive technology or control components
Mahesha P.K, etal [2] Stated that the microcontroller is family to use on-chip spark recall for program storage, as
opposed to one-time programmable ROM, EPROM, or EEPROM used by other microcontrollers at the time. With
a single cycle instruction RISC CPU and a loaded attribute set, the structural design ensures fast code execution
combined with the lowest possible power consumption.
G. Pritschow, etal [4] Shows that due to small working envelop the controller for mobility of robot should be
accurate, which can be a microcontroller. Thus the movable podium should be able to go up and go down the
staircase. Compact dimensions will allow the robot to pass through doorways and to work in small rooms. A low-
cost PC depends run system will be used for motion control, sensor signal processing and human machine
interface.
Mechanical Concept
Arivazhagan.B [5], explained the mechanical design of the plastering machine which consists of the motor pump
to push the cement mix, Funnel to load the cement mix, flexible pipe to bear the cement blend to the hopper,
horizontal bar guide to move the plastering unit horizontally, horizontal top to grasp the vertical bar guide and
move beside the horizontal direction, vertical rail guide to move the hopper vertically, vertical head to grasp the
hopper and move beside vertically, cement mix inlet to the hopper, the hopper to hold cement mix provisionally,
cylinder slot to discharges the cement consistently with the pressure from the pump present in hopper, metal sheet
ISSN: 2277-9655
[Askar* et al., 6(3): March, 2017] Impact Factor: 4.116
ICā„¢ Value: 3.00 CODEN: IJESS7
http: // www.ijesrt.com Ā© International Journal of Engineering Sciences & Research Technology
[546]
to evenly smudge the cement on the walls. Basic Concept and Enabling Technologies using a Mobile Robot
Internal Plastering [6], According to paper, for the mobility criteria in a building site environment a mobile
platform capable of hiking and downward stairs is necessary. The best solution is offered by the caterpillar drive
which is robust and capable of overcoming inclines of up to 40į“¼. To facilitate automated plastering and to
compensate positioning errors the degrees of autonomy are required in a robotic arm.
G. Pritschow, etal [4] Stated that the robotic manipulator must have some degrees of autonomy these are, two
degrees of autonomy for plaster application in a plane for a single robot working position. A further degree of
autonomy is required to compensate for tilting of the movable machine and thus enable parallel motion of the
plastering tool with respect to the wall or ceiling.
Working of plastering Machine
Arunkumar Biradar, etal [3], explained that the initially the machine is placed closed to the wall that is to be
plasters.
The plaster is poured into the hopper, with the help of lead screw the machine is raised up and will be lock at
some instance. The exciting force is given by the rope and machine mechanism. In that way the plastering is done
automatically to the wall by automatic plastering machine.
Mahesha P.K, etal [2], demonstrated that the machine has to be located near the wall which has going to plaster.
The machine should be perfectly leveled. Then the mortar is poured into the hopper of the tray. The lifting force
is transferred to tray through power screw, which driven by AC motor.
Ali Al-Hamad, etal [1], explained that, the machine works with conventional cement mortar, it can plaster the
wall mechanically by stirring up and down in straight up direction. It has two rails for rising and moving
automatically, therefore can be used for different height and width of the wall.
Advantages of automated machine over manual plastering
Ali Al-Hamad[1] Mahesha P.K, etal[2], Arunkumar Biradar, [3] Arivazhagan.B[5], G. Pritschow[6], Teng
Long[7] stated that Automatic plastering machine needs less time to complete plastering, no skilled labors
required, quality of plastering is comparatively good than manual plastering process, less wastage of raw material
than manual plastering, automatic plastering has low cost than manual plastering. Less risk of accidents during
construction work.
Sr.
No.
Paper Title Name of Author Findings
1. Plastering Wall
Machine
Ali Al- Hamad, Osaid
Hamdallh, Rand Khraishi,
Sami Yonis.
ļ± The plastering wall machine will help to save
labor cost up to 85%.
ļ± Increase productivity by 10-15 times.
ļ± Get professional quality finishing in less time,
reduce project cost, manufacture wall machine
in low cost.
2. Design and
Fabrication Of
Automatic
Plastering Machine
Prototype
Mahesha P. K. (M-Tech
IAR, Mechanical Engg.
MCE, Hassan, India) ,
Sree Rajendra
(Associate Professor,
Mechanical Engg. MCE
Hassan, India)
ļ± Powerful competition, shortages of trained
labor, increase in labor wages and technical
advances are forcing quick change in the
building structure.
ļ± All these problems can be solve out with
automation in constructive technique. One of
which is plastering, which is extremely slow &
costly when doing manually.
ļ± They use necessary components like steel
frame, sheet metal, metal bars, power screw,
AC/DC motors, different wheels nut & bolts
for assemble it.
ISSN: 2277-9655
[Askar* et al., 6(3): March, 2017] Impact Factor: 4.116
ICā„¢ Value: 3.00 CODEN: IJESS7
http: // www.ijesrt.com Ā© International Journal of Engineering Sciences & Research Technology
[547]
ļ± Through trails it is noted that the machine is
more productive compare to labor with respect
to the plastering work.
3. Automatic Wall
Plastering Machine
Arunkumar Biradar,
Vaibhav Shejwal, Akshay
Barate, Sameer Barate
ļ± The development trade in most countries
amounts to 10ā€“20% of the total nationwide
product, creating it the biggest economic using
sector.
ļ± It's still labor insist and jointly the majority of
the work concerned is cyclic.
ļ± The expansion of any country depends on the
development trade therefore it's of prime
economic significance to several industrial
sectors.
4. On site Mobile
Plastering Robot: A
Practical Design
Concept
G. Pritschow, J. Kurz, J
Zeiher, S. C. McCormac
& M. Dalacker, (Dept. of
Machine & Robot
Systems, University of
Stuttgart, Germany)
ļ± This elaborates basic concepts and
technologies for a movable plastering robot
used on construction site and operated by
skilled worker.
ļ± This paper also explained the kinematic
structure and control system for a working
robot.
5. Automatic
Plastering Machine
Arivazhgan. B. , B. Tech
(ECE) ā€“ IV year,
Manakula Vinayagar
Institute of Technology,
Puducherry.
ļ± Automated plastering machine is exclusive and
maybe one type of automated plastering
machinery suitable for construction industry.
ļ± It makes plastering easy, fast and effortless as
compare to manual use.
6. A Construction
Robot for
Autonomous
Plastering of Walls
and Ceilings.
Johan Forsberg, Roger
Aarenstrup,
(Robotics and
Automation, Lulea
University of Technology,
Sweden)
ļ± The time used for plastering the wall is
expected to be less than 50% of that required
by manual work.
ļ± The reason for developing the robot is mainly
ergonomic. They also discuss about
Mechanical error sources, Navigation errors &
Control errors.
7. Mechanical Design
of A Quadruped
Robot for Horizontal
Ground to Vertical
Wall Movement
Abd Alsalam Sh., Rosbi
Mamat. (University
Technology, Malaysia)
ļ± This paper the highlighting given the
mechanical structure of a quadruped machine
able to walk on ground, go up on vertical walls
and perform the ground-wall movement
automatically.
ļ± It is electrically actuated one.
8. A Service Robot for
Construction
Industry
Pablo Gonzalez De
Santos, Joaquin
Estremera,
E. Garcia.
(CSIC, Spain)
ļ± This explained the required features of the
robot manipulator developed for construction.
ļ± Also discussed main subsystem i.e. Frame,
manipulator, Grasping device, controller &
guiding system.
9. Automatic Wall
Plastering and
Repairing Robot
using Artificial
Intelligence
Dr. S. K. Rajesh Kanna.
(Dept. of Mechanical
Engg, Rajlakshmi
Institute of Technology,
India)
A. D. Jaisaree. (Dept. of
Computer science and
Engg, Mahendra
Engineering College,
India)
ļ± The movement of the poppet is controlled by a
high torque motor.
ļ± The robots have been developed to apply the
mortar on the vertical walls with pressure and
having the capability of self adjusting the
mortar thickness.
ļ± The machine solves the issues like shortage of
labor, raise in labor cost etc. and wastage of
mortar is reduced more than 60% thereby
reduces the raw substance requirement.
ISSN: 2277-9655
[Askar* et al., 6(3): March, 2017] Impact Factor: 4.116
ICā„¢ Value: 3.00 CODEN: IJESS7
http: // www.ijesrt.com Ā© International Journal of Engineering Sciences & Research Technology
[548]
METHODOLOGY
Methodology to be used is as follows for the designing of automatic plastering machine on the basis of literature
survey.
Data and design calculation
Design of plasterboard
By Considering,
1) Horizontal length of plasterboard = 2 feet
= 0.61 m
= 610 mm
2) Length of bottom plate of plasterboard (Trowel) = 0.25 m = 250mm
10. Advanced Dry
Mortar Technology
for Construction
Industry
Ir. Raymond Wan MEng,
CEng, MIM, MICE,
MICT, MHKIE, RPE
ļ± Good quality dry mix products are available in
the market with improved performance.
ļ± Although, dry mortars cannot totally solve all
the construction problems,
ļ± On the contrary, advanced dry mortars are very
complicated powdery mixtures with
sophisticated chemical additives of newest
technology to provide wide range of superior
act to get together complex construction
requirements.
11. Finishing guide
For Thistle plaster
and
Gyproc plasterboard
A Saint-Gobain Company ļ± This guide states the different methods of
finishing the wall surfaces by plastering,
different accessories for plastering,
instruments, techniques etc.
12. Comparative Study
on Mould
Growth on Plaster
Boards
treated with Biocides
Julia Friman
Degree project for Master
of Science (One Year) in
Plant Ecology
30 hec
Department of Plant and
Environmental Science
Gƶteborg University
ļ± This theory aims to match up to the most
capable biocide anti fungal result when use as
a covering on Plaster plates.
ļ± The method contained simple humid boxes,
together with a visual and an agar cultivation as
assessment.
ļ± Dry grass was used as contamination. The
testing was designed to compare the biocides
with the reason of establishing relative mould
growth values.
13. Basic Concept and
Enabling
Technologies using a
mobile Robot for
Internal Plastering.
Reference:- WeiBert M.,
Leixner, Raddsatz.
ļ± The introduction of plastering robots would
resemble the revolution in the plastering
industry in the sixties when plastering
machines helped to improve overall
productivity by more than 30%.
ļ± The machine construction industry will also
have excellent chances at extending their
current markets.
14. A Novel
Measurement and
Control Method for
Automatic
Plastering Machine.
Teng Long, En Li, Zaojun
Fang, Weiqing Zhao and
Zize Liang (Institute of
Automation Chinese
Academy of Sciences,
Beijing 100190, China)
ļ± This research proposes a novel method of
plastering machine measurement and control
method depends on laser triangulation.
ļ± This method canā€™t solve some problems such
as corner is unreached and the power of
vibration canā€™t be compensated.
ISSN: 2277-9655
[Askar* et al., 6(3): March, 2017] Impact Factor: 4.116
ICā„¢ Value: 3.00 CODEN: IJESS7
http: // www.ijesrt.com Ā© International Journal of Engineering Sciences & Research Technology
[549]
3) Length of upper plate of plasterboard = 1*1/2 feet
= 0.46 = 460 mm
4) Universal one coat plaster thickness = 12 mm
5) Trowel leading edge will be approximately 10-15 mm away from the wall surface, so consider = 10
Fig. 3:- 2-Dimensional view of plasterboard
6) Total distance of leading edge from the wall = plaster thickness + leading edge distance
= 12 mm + 10 mm
= 22 mm
Now,
1) In triangle AED,
By Pythagoras theorem,
AE2
= AD2
+ DE2
3002
= AD2
+ 102
AD = 299.83 mm
AD = 300 mm
2) In triangle DAE,
sinĪø = opposite side/hypo sinĪø = 10/300
Īø = 20į“¼
3) Now, In triangle EFG,
SinĪø = Opposite side/ Hypo
Sin30 = FG/FE Assume Īø= 30
0.5 = FG/460
FG = 230 mm
4) FH = FG + GH
= 230 + 22
= 352 mm
5) In triangle FGE,
By Pythagoras theorem
FE2
= FG2
+ GE2
4602
= 2302
+ GE2
GE = 398 mm
6) Volume of ā–” CEXY = L * B * H
= 200 * 22 * 610
= 2684000 mm3
= 0.0026 m3
7) Volume of prism EXY = Ā½ * L * B * H
= Ā½ * 200 * 115 * 610
= 7015000 mm3
= 0.0070 m3
8) Total Volume = Volume of ā–” CEXY + Volume of prism EXY
= 0.0026 + 0.0070
= 0.0096 m3
9) The Density of the standard mortar (sand + cement) = 2200 Kg/ m3
10) Mass of mortar = Volume of mortar * density
ISSN: 2277-9655
[Askar* et al., 6(3): March, 2017] Impact Factor: 4.116
ICā„¢ Value: 3.00 CODEN: IJESS7
http: // www.ijesrt.com Ā© International Journal of Engineering Sciences & Research Technology
[550]
= 0.0096 * 220
= 21.12 Kg
11) Load = 21.12 * 9.81 = 207.18 N
12) Mass of plasterboard = 6 Kg
= 6 * 9.81
= 58.86 N
= 59 N
13) Total Load = Load of mortar + Load of plasterboard + Frictional and other load
= 208+ 59 + 200
= 467 N
= 470 N
= 48 kg
14) There are two different sides, so load on single side = 470/2
= 235 N
DC motor specification
Power of motor = 1 hp
= 750 watt
Torque = 240 kg-cm
= 23.54 * 103
N-mm
Fig. 4 DC motor
Frequency = 60 Hz
Now, Power = 2āˆNT/60
750= 2 āˆ*N*23.54/60
N = 304.40 rpm
Design of Shaft
Material for shaft ā€“ Fe 360
Yield Strength (Syt) = 220 N/mm2
Ultimate tensile strength (Sut) = 360 N/mm2
Now according to A.S.M.E (American Society of Mechanical Engineers)
Shear stress Ļ„ = 0.18 * Syt
= 0.18 * 220
= 39.6 N/mm2
Ļ„ = 0.3 * 360
= 0.3 *360
= 108 N/mm2
Total Load = 47.60 kg
= 48 kg
= 48 * 9.81
= 470 N
There are two different sides
So, load on single side = 470/2
= 235 N
RA = 235 N
RB = 235 N
Bending Moment M = RA * 30
=235*30 = 7050 N-mm
So, Twisting moment (Te) = āˆš(Km * M) 2
+ (Kt * T) 2
= āˆš (1.5 * 7050) 2
+ (1 * 23.54 *10 3
) 2
= 25806 N-mm
ISSN: 2277-9655
[Askar* et al., 6(3): March, 2017] Impact Factor: 4.116
ICā„¢ Value: 3.00 CODEN: IJESS7
http: // www.ijesrt.com Ā© International Journal of Engineering Sciences & Research Technology
[551]
For rotating shaft having gradually applied load,
Km ā€“ Combined shock and fatigue factor for bending
= 1.5
Kt ā€“ Combined shock and fatigue fact for torsion
= 1
We know, The torsion equation
T/J = Ļ„/r
Where, T = Twisting moment acting upon the shaft
J = Polar moment of inertia of the shaft about the axis of rotation.
Ļ„ = Torsional shear stress and
r = d/2, d is the diameter of the shaft.
So, Te = āˆ/16 * d3
* 39.6
d = 14.91 mm
So, get standard diameter of the shaft i. e. 15 mm
Design of worm and worm gear
Material for worm wheel ā€“ Phosphor bronze
Material for worm ā€“Cast harden steel
(Sut)worm wheel = 240 N/mm 2
(Sut)worm = 700 N/mm 2
Assume, No. of teeth on worm = Zw = 5
No. of teeth on worm gear = Zg = 25
So, Gear ratio = 25/5 = 5
Beam Strength of worm gear,
By Lewis equation,
Wt = 6ā‚€ * Cv * b * āˆ * m * y
Where, Wt = permissible tangential tooth load or beam strength of gear tooth
6ā‚€ = Allowable static stress
Cv = velocity factor
b = face width
m= module
y = tooth form factor or Lewis factor
6ā‚€ = 105 N/mm2
------For cast iron
Pitch circle dia. Of the worm gear D = 60 mm
Pitch circle (Pc) = āˆD/T
= āˆ * 60/ 25
= 7.54 mm
Outside diameter (Do) = D + 1.0135 Pc
= 60 + 1.0135 * 7.54
= 67.64 mm
Throat diameter (Dt) = D + 0.636 * Pc
= 60 + 0.636 * 7.54
= 64.80 mm
Face width (b) = 2.38 * Pc + 6.5
= 24.44 mm
Radius of gear face (Rf) = 0.882 * Pc + 14
= 20.65 mm
Radius of gear rim (Rr) = 2.2 * Pc + 14
= 30.588 mm
Linear velocity of worm gear
Vg = āˆ * D * N/ 60
= āˆ * 0.06 * 5.06/60
= 0.015 m/s
Velocity factor Cv = 6 / 6 + v
= 0.9978
ISSN: 2277-9655
[Askar* et al., 6(3): March, 2017] Impact Factor: 4.116
ICā„¢ Value: 3.00 CODEN: IJESS7
http: // www.ijesrt.com Ā© International Journal of Engineering Sciences & Research Technology
[552]
Lewis form factor y = 0.124 ā€“ 0.684 / Tg
= 0.0966
Module m, D = m * Tg
m = 2
So, Beam strength of worm gear = 1612.39 N
Now, Wear tooth load for worm gear,
For worm,
Dia. of worm = m * q
= 2 *10
= 20 mm
Axial pitch Pa = āˆ * m = 6.28 mm
Face width = 0.73 * dw = 14.6 mm
Centre distance = dw + D/2 = 40 mm
Addendum = 1m = 2 mm
Deddendum = 1.25m = 2.5 mm
Length of worm = Pa * Zw
= 31.4 mm
Ww = D * b * k
Where, D ā€“ pitch circle diameter of worm gear
b ā€“ face width of the worm gear
k ā€“ load stress factor = 0.345
So, Ww = 505.90 N
Design of Rope
Fig.5 Steel Rope
Type of rope = 6 * 19
Material = Steel wire
Diameter = 3 mm
Minimum breaking stress = 1770 Mpa
Minimum load capacity = 588 kg
Area of wire rope = 0.38 * d2
= 3.42 mm2
Diameter of the pulley or drum = 30 * d
= 90 mm
Tensile strength = 540d 2
= 4860 N/mm 2
Factor of safety = 3.5 i.e. 3.5 * 2 = 7
Stresses in wire rope,
Direct stress 6d = W + w/ A
Where, W = load lifted
w = weight of the rope
A = C/S area of the rope
So, direct stress, 6d = 69.94 N/mm2
Bending stress when wire rope winds round the drum or pulley
6b = Er * dw/ D
= 84 * 103
*3/ 90
= 2800 N/mm2
Where, Er ā€“ Modulus of elasticity of wire rope = 84 * 103
N/mm2
ISSN: 2277-9655
[Askar* et al., 6(3): March, 2017] Impact Factor: 4.116
ICā„¢ Value: 3.00 CODEN: IJESS7
http: // www.ijesrt.com Ā© International Journal of Engineering Sciences & Research Technology
[553]
dw ā€“ dia. Of wire
D ā€“ dia. Of pulley or drum
Total stress = 69.94 + 2800
= 2870 N/mm2
Our design load = F.O.S. * total load
= 7 * 470 = 3290 N
So wire rope of diameter 3 mm, 6 * 19 type is satisfactory
Design of Bearings
Specification:-
Bore diameter d = 15 mm
Outside diameter D = 35 mm
Width B = 11 mm
Greece lubrication = 19000
Oil lubrication = 24000
Dynamic load C = 7800 N
Static load Co = 3550 N
Now, Radial and Axial load,
Radial load Fr = 235 N
Axial load Fa = 0 N
Equivalent dynamic load Fe = [ X * V * Fr + y * Fa] = [1 * 1 * 235 + 1
* 0 ]
Fe = 235 N
Req. dynamic load capacity = L = (Cr/Fe) a
Ball bearing a = 3
So, L = 8000 hrs
8000 = (Cr/235) 3
Cr = 4700 N
Since, Cr < C, so selected bearing is suitable.
2-D drawing and CAD modeling of plastering machine
On the basis of above design calculation the computer aided design (CAD model) of some parts of the plastering
machine and assembly of the plastering machine has been done with the help of Computer Aided Software naming
ā€˜CRE-Oā€™ by applying Bottom-up approach.
Fig.5 drawing of ceiling beam and base of machine
ISSN: 2277-9655
[Askar* et al., 6(3): March, 2017] Impact Factor: 4.116
ICā„¢ Value: 3.00 CODEN: IJESS7
http: // www.ijesrt.com Ā© International Journal of Engineering Sciences & Research Technology
[554]
Fig. 6 CAD model of components of plastering machine
CONCLUSION
By studying all the above literatures and the work done following conclusions are obtained.
1. Automatic plastering machine is one type of unique machine will be used in construction industry.
2. It helps to save the time and money.
3. It works with cement mortar which is conventional one due to which no replacement of the material
required.
4. The machine is more productive than the conventional plastering technique.
5. Higher quality of a plaster can be obtained with this machine.
6. The thickness of the plaster will be constant over the wall which is generally varying 0.5 to 0.75 inches at
different conditions of the wall surface.
7. This machine needs to poured the mortar manually so, it has needed the work automation of loading
mortar.
8. It reduces the wastage of mortar up to 60% and hence required fewer raw materials.
9. Due to saving in time, labor cost, raw material, the overall cost of construction is less hence the machine
is economically efficient
than the conventional plastering technique.
RESULT
Table shows comparative result on different objectives, for a 10 feet*10 feet wall by both existing plastering
method as well as Automatic plastering machine as follows.
Sr.
No.
Objective Existing method Automatic
plastering
machine
1. No. of
labors
required
2 to 3 1 or 2
2. Time
required
(hours)
6 to 7 (hours) 1 to 2 (hours)
3.
Material
More material
required
compared to
plastering
machine as there
is more wastage
of mortar.
Less material
required,
compared to
conventional
method as less
material
wastage is
there.
4.
Cost
Comparatively
high cost. (As
number of labors
and time required
is more)
Comparatively
low cost. (As
no. of labors
and time
required is less)
ISSN: 2277-9655
[Askar* et al., 6(3): March, 2017] Impact Factor: 4.116
ICā„¢ Value: 3.00 CODEN: IJESS7
http: // www.ijesrt.com Ā© International Journal of Engineering Sciences & Research Technology
[555]
REFERENCES
[1] Ali Al-Hamad, Osaid Hamdallah, Rand Khraishi, Sami Yonis, ā€œPlastering Wall Machineā€, An-Najah
National University
[2] Mahesha P.K,Sree Rajendra ā€œDesign and fabrication of automatic wall plasterig machine prototypeā€,
IOSR Journal of mechanical and civil engineering, volume 11,issue 4 ,(Jul-Aug 2014),pp 01-06.
[3] Arunkumar Biradar, Vaibhav Shejwal, Akshay Barate, Sameer Barate, ā€œAutomatic Wall Plastering
Machineā€, International Journal of Engineering and Technical Research (IJETR) ISSN: 2321-0869 (O)
2454-4698 (P), Volume-4, Issue-1, January 2016.
[4] G. Pritschow, J. Kurz, J Zeiher, S. C. McCormac & M. Dalacker, ā€œOn site Mobile Plastering Robot: A
Practical Design Conceptā€, Dept. of Machine & Robot Systems, University of Stuttgart, Germany
[5] Arivazhagan.B, ā€œAutomatic Plastering Machineā€, International Journal of Advanced Research in
Electronics, Communication & Instrumentation Engineering and Development Volume: 2 Issue: 2 28-
Jul-2014,ISSN_NO: 2347 -7210.
[6] Basic Concept and Enabling Technologies using a Mobile Robot Internal Plastering
[7] Johan Forsberg, Roger Aarenstrup, ā€œA Construction Robot for Autonomous Plastering of Walls and
Ceilingsā€. Robotics and Automation, Lulea University of Technology, Sweden
[8] Abd Alsalam Sh., Rosbi Mamat, ā€œMechanical Design of A Quadruped Robot for Horizontal Ground to
Vertical Wall Movementā€. University Technology, Malaysia
[9] Pablo Gonzalez De Santos, Joaquin Estremera, E. Garcia., ā€œA Service Robot for Construction Industryā€,
CSIC, Spain
[10]Dr. S. K. Rajesh Kanna. (Dept. of Mechanical Engg, Rajlakshmi Institute of Technology, India) A. D.
Jaisaree. (Dept. of Computer science and Engg, Mahendra Engineering College, India), Automatic Wall
Plastering and Repairing Robot using Artificial Intelligence.
[11]Advanced Dry Mortar Technology for Construction Industry, Ir. Raymond Wan MEng, CEng, MIM,
MICE, MICT, MHKIE, RPE
[12]Comparative Study on Mould Growth on Plaster Boards treated wit Biocides,Julia Friman Degree project
for Master of Science (One Year) in Plant Ecology 30 hec Department of Plant and Environmental
Science Gƶteborg University
[13]Basic Concept and Enabling Technologies using a mobile Robot for Internal Plastering.
[14]Teng Long, En Li, Zaojun Fang, Weiqing Zhao and Zize Liang (Institute of Automation Chinese
Academy of Sciences, Beijing 100190, China), A Novel Measurement and Control Method for Automatic
Plastering Machine.
[15]R. S. Khurmi and J.K.Gupta, Machine Design,14thedition Eurasia Publishing House (PVT.) Ltd. 2005.
View publication statsView publication stats

More Related Content

What's hot

Applications of composite materials in automobile
Applications of composite materials in automobileApplications of composite materials in automobile
Applications of composite materials in automobileSazzad Hossain
Ā 
Design and Construction of a Connecting rod
Design and Construction of a Connecting rodDesign and Construction of a Connecting rod
Design and Construction of a Connecting rodFaisal Niloy
Ā 
ENGINEER IN SOCIETY
ENGINEER IN SOCIETYENGINEER IN SOCIETY
ENGINEER IN SOCIETYMahmood Ajabbar
Ā 
some tests on steel
some tests on steel some tests on steel
some tests on steel KAMARAN SHEKHA
Ā 
Concentric springs, surge phenomenon in spring, helical torsion, spiral spring
Concentric springs, surge phenomenon in spring, helical torsion, spiral springConcentric springs, surge phenomenon in spring, helical torsion, spiral spring
Concentric springs, surge phenomenon in spring, helical torsion, spiral springvaibhav tailor
Ā 
Introduction to ANSYS Workbench
Introduction to ANSYS WorkbenchIntroduction to ANSYS Workbench
Introduction to ANSYS Workbenchnagesh surner
Ā 
Mortarless system
Mortarless systemMortarless system
Mortarless systemAglaia Connect
Ā 
Automobile Engineering Notes
Automobile Engineering Notes Automobile Engineering Notes
Automobile Engineering Notes Learn With GeekAlign
Ā 
Applicability of mohr coulomb and drucker prager models for assessment of und...
Applicability of mohr coulomb and drucker prager models for assessment of und...Applicability of mohr coulomb and drucker prager models for assessment of und...
Applicability of mohr coulomb and drucker prager models for assessment of und...IAEME Publication
Ā 
Thermal analysis of brake disc 2015
Thermal analysis of brake disc   2015Thermal analysis of brake disc   2015
Thermal analysis of brake disc 2015Parag Desshattiwar
Ā 
fibre reinforced polymer(FRP)
fibre reinforced polymer(FRP)fibre reinforced polymer(FRP)
fibre reinforced polymer(FRP)Aravind Ganesh
Ā 
single degree of freedom systems forced vibrations
single degree of freedom systems forced vibrations single degree of freedom systems forced vibrations
single degree of freedom systems forced vibrations KESHAV
Ā 
Unit I- general consideration
Unit I- general considerationUnit I- general consideration
Unit I- general considerationYugal Kishor Sahu
Ā 
Vibration Analysis of a Motorbike to find Transmission to Hands and Back
Vibration Analysis of a Motorbike to find Transmission to Hands and Back Vibration Analysis of a Motorbike to find Transmission to Hands and Back
Vibration Analysis of a Motorbike to find Transmission to Hands and Back Muhammad Usman
Ā 
Bearing materials ...
Bearing materials                                                            ...Bearing materials                                                            ...
Bearing materials ...bashar alaqidi
Ā 
Chapter 5 failure theories final
Chapter 5  failure theories finalChapter 5  failure theories final
Chapter 5 failure theories finalKhalil Alhatab
Ā 

What's hot (20)

Applications of composite materials in automobile
Applications of composite materials in automobileApplications of composite materials in automobile
Applications of composite materials in automobile
Ā 
Design and Construction of a Connecting rod
Design and Construction of a Connecting rodDesign and Construction of a Connecting rod
Design and Construction of a Connecting rod
Ā 
ENGINEER IN SOCIETY
ENGINEER IN SOCIETYENGINEER IN SOCIETY
ENGINEER IN SOCIETY
Ā 
some tests on steel
some tests on steel some tests on steel
some tests on steel
Ā 
Shaft
ShaftShaft
Shaft
Ā 
Concentric springs, surge phenomenon in spring, helical torsion, spiral spring
Concentric springs, surge phenomenon in spring, helical torsion, spiral springConcentric springs, surge phenomenon in spring, helical torsion, spiral spring
Concentric springs, surge phenomenon in spring, helical torsion, spiral spring
Ā 
Lecture notes on trusses
Lecture notes on trussesLecture notes on trusses
Lecture notes on trusses
Ā 
Introduction to ANSYS Workbench
Introduction to ANSYS WorkbenchIntroduction to ANSYS Workbench
Introduction to ANSYS Workbench
Ā 
DYNAMICS OF MACHINES UNIT-1 BY Mr.P.RAMACHANDRAN/AP/MECH/KIT/CBE
DYNAMICS OF MACHINES UNIT-1 BY Mr.P.RAMACHANDRAN/AP/MECH/KIT/CBEDYNAMICS OF MACHINES UNIT-1 BY Mr.P.RAMACHANDRAN/AP/MECH/KIT/CBE
DYNAMICS OF MACHINES UNIT-1 BY Mr.P.RAMACHANDRAN/AP/MECH/KIT/CBE
Ā 
Screw jack project_1
Screw jack project_1Screw jack project_1
Screw jack project_1
Ā 
Mortarless system
Mortarless systemMortarless system
Mortarless system
Ā 
Automobile Engineering Notes
Automobile Engineering Notes Automobile Engineering Notes
Automobile Engineering Notes
Ā 
Applicability of mohr coulomb and drucker prager models for assessment of und...
Applicability of mohr coulomb and drucker prager models for assessment of und...Applicability of mohr coulomb and drucker prager models for assessment of und...
Applicability of mohr coulomb and drucker prager models for assessment of und...
Ā 
Thermal analysis of brake disc 2015
Thermal analysis of brake disc   2015Thermal analysis of brake disc   2015
Thermal analysis of brake disc 2015
Ā 
fibre reinforced polymer(FRP)
fibre reinforced polymer(FRP)fibre reinforced polymer(FRP)
fibre reinforced polymer(FRP)
Ā 
single degree of freedom systems forced vibrations
single degree of freedom systems forced vibrations single degree of freedom systems forced vibrations
single degree of freedom systems forced vibrations
Ā 
Unit I- general consideration
Unit I- general considerationUnit I- general consideration
Unit I- general consideration
Ā 
Vibration Analysis of a Motorbike to find Transmission to Hands and Back
Vibration Analysis of a Motorbike to find Transmission to Hands and Back Vibration Analysis of a Motorbike to find Transmission to Hands and Back
Vibration Analysis of a Motorbike to find Transmission to Hands and Back
Ā 
Bearing materials ...
Bearing materials                                                            ...Bearing materials                                                            ...
Bearing materials ...
Ā 
Chapter 5 failure theories final
Chapter 5  failure theories finalChapter 5  failure theories final
Chapter 5 failure theories final
Ā 

Similar to Design of automatic wall plastering machine

Km145 wall plastering machine (wecompress)
Km145 wall plastering machine (wecompress)Km145 wall plastering machine (wecompress)
Km145 wall plastering machine (wecompress)1000kv technologies
Ā 
Modern Method
Modern MethodModern Method
Modern MethodShourya Puri
Ā 
Method Of Modern Construction
 Method Of Modern Construction  Method Of Modern Construction
Method Of Modern Construction Shourya Puri
Ā 
The Design, Construction and Computer ā€“Aided Simulation of a Prototype Roofin...
The Design, Construction and Computer ā€“Aided Simulation of a Prototype Roofin...The Design, Construction and Computer ā€“Aided Simulation of a Prototype Roofin...
The Design, Construction and Computer ā€“Aided Simulation of a Prototype Roofin...IRJET Journal
Ā 
Development OF Low Cost Durable Precast Compound Wall
Development OF Low Cost Durable Precast Compound WallDevelopment OF Low Cost Durable Precast Compound Wall
Development OF Low Cost Durable Precast Compound WallIRJET Journal
Ā 
Ppt summer presentation on finishing Of Police Station Construction Site
Ppt summer presentation on finishing Of Police Station Construction SitePpt summer presentation on finishing Of Police Station Construction Site
Ppt summer presentation on finishing Of Police Station Construction SiteAlok Mishra
Ā 
Ready Mix Concrete
Ready Mix ConcreteReady Mix Concrete
Ready Mix ConcreteAbhishek Shah
Ā 
Cost analysis of precast wall panel and burnt brick masonry wall.
Cost analysis of precast wall panel and burnt brick masonry wall.Cost analysis of precast wall panel and burnt brick masonry wall.
Cost analysis of precast wall panel and burnt brick masonry wall.IRJET Journal
Ā 
om industrial training report.pptx
om industrial training report.pptxom industrial training report.pptx
om industrial training report.pptxRohitYadav530108
Ā 
Presentation [AP14015]
Presentation [AP14015]Presentation [AP14015]
Presentation [AP14015]Rahul Dasgupta
Ā 
R033092097
R033092097R033092097
R033092097ijceronline
Ā 
Time, Cost , Productivity and Quality Analysis of Precast Buildings
Time, Cost , Productivity and Quality Analysis of Precast BuildingsTime, Cost , Productivity and Quality Analysis of Precast Buildings
Time, Cost , Productivity and Quality Analysis of Precast BuildingsIRJET Journal
Ā 
3D CONCRETE PRINTING: MACHINE AND MIX DESIGN
3D CONCRETE PRINTING: MACHINE AND MIX DESIGN3D CONCRETE PRINTING: MACHINE AND MIX DESIGN
3D CONCRETE PRINTING: MACHINE AND MIX DESIGNIAEME Publication
Ā 
3 d concrete printing machine and mix design
3 d concrete printing machine and mix design3 d concrete printing machine and mix design
3 d concrete printing machine and mix designIAEME Publication
Ā 
Abhishek presentation.pptx
Abhishek presentation.pptxAbhishek presentation.pptx
Abhishek presentation.pptxRAKESHPANDEY754083
Ā 
IRJET- Contour Crafting (A Management Tool for Swift Construction)
IRJET-  	  Contour Crafting (A Management Tool for Swift Construction)IRJET-  	  Contour Crafting (A Management Tool for Swift Construction)
IRJET- Contour Crafting (A Management Tool for Swift Construction)IRJET Journal
Ā 
404128086-mivan-ppt-0-pptx.pptx.................
404128086-mivan-ppt-0-pptx.pptx.................404128086-mivan-ppt-0-pptx.pptx.................
404128086-mivan-ppt-0-pptx.pptx.................KeshavaPrajwal
Ā 
Introduction to advanced TUNNEL Formwork system: Case study of ā€˜Rohan - Abhi...
Introduction to advanced TUNNEL Formwork system: Case study of  ā€˜Rohan - Abhi...Introduction to advanced TUNNEL Formwork system: Case study of  ā€˜Rohan - Abhi...
Introduction to advanced TUNNEL Formwork system: Case study of ā€˜Rohan - Abhi...IRJET Journal
Ā 
Automation construction
Automation constructionAutomation construction
Automation constructionDr. Abhijit Zende
Ā 

Similar to Design of automatic wall plastering machine (20)

Km145 wall plastering machine (wecompress)
Km145 wall plastering machine (wecompress)Km145 wall plastering machine (wecompress)
Km145 wall plastering machine (wecompress)
Ā 
A PRESENTATION ON PREFABRICATED STRUCTURES
A PRESENTATION ON PREFABRICATED STRUCTURES A PRESENTATION ON PREFABRICATED STRUCTURES
A PRESENTATION ON PREFABRICATED STRUCTURES
Ā 
Modern Method
Modern MethodModern Method
Modern Method
Ā 
Method Of Modern Construction
 Method Of Modern Construction  Method Of Modern Construction
Method Of Modern Construction
Ā 
The Design, Construction and Computer ā€“Aided Simulation of a Prototype Roofin...
The Design, Construction and Computer ā€“Aided Simulation of a Prototype Roofin...The Design, Construction and Computer ā€“Aided Simulation of a Prototype Roofin...
The Design, Construction and Computer ā€“Aided Simulation of a Prototype Roofin...
Ā 
Development OF Low Cost Durable Precast Compound Wall
Development OF Low Cost Durable Precast Compound WallDevelopment OF Low Cost Durable Precast Compound Wall
Development OF Low Cost Durable Precast Compound Wall
Ā 
Ppt summer presentation on finishing Of Police Station Construction Site
Ppt summer presentation on finishing Of Police Station Construction SitePpt summer presentation on finishing Of Police Station Construction Site
Ppt summer presentation on finishing Of Police Station Construction Site
Ā 
Ready Mix Concrete
Ready Mix ConcreteReady Mix Concrete
Ready Mix Concrete
Ā 
Cost analysis of precast wall panel and burnt brick masonry wall.
Cost analysis of precast wall panel and burnt brick masonry wall.Cost analysis of precast wall panel and burnt brick masonry wall.
Cost analysis of precast wall panel and burnt brick masonry wall.
Ā 
om industrial training report.pptx
om industrial training report.pptxom industrial training report.pptx
om industrial training report.pptx
Ā 
Presentation [AP14015]
Presentation [AP14015]Presentation [AP14015]
Presentation [AP14015]
Ā 
R033092097
R033092097R033092097
R033092097
Ā 
Time, Cost , Productivity and Quality Analysis of Precast Buildings
Time, Cost , Productivity and Quality Analysis of Precast BuildingsTime, Cost , Productivity and Quality Analysis of Precast Buildings
Time, Cost , Productivity and Quality Analysis of Precast Buildings
Ā 
3D CONCRETE PRINTING: MACHINE AND MIX DESIGN
3D CONCRETE PRINTING: MACHINE AND MIX DESIGN3D CONCRETE PRINTING: MACHINE AND MIX DESIGN
3D CONCRETE PRINTING: MACHINE AND MIX DESIGN
Ā 
3 d concrete printing machine and mix design
3 d concrete printing machine and mix design3 d concrete printing machine and mix design
3 d concrete printing machine and mix design
Ā 
Abhishek presentation.pptx
Abhishek presentation.pptxAbhishek presentation.pptx
Abhishek presentation.pptx
Ā 
IRJET- Contour Crafting (A Management Tool for Swift Construction)
IRJET-  	  Contour Crafting (A Management Tool for Swift Construction)IRJET-  	  Contour Crafting (A Management Tool for Swift Construction)
IRJET- Contour Crafting (A Management Tool for Swift Construction)
Ā 
404128086-mivan-ppt-0-pptx.pptx.................
404128086-mivan-ppt-0-pptx.pptx.................404128086-mivan-ppt-0-pptx.pptx.................
404128086-mivan-ppt-0-pptx.pptx.................
Ā 
Introduction to advanced TUNNEL Formwork system: Case study of ā€˜Rohan - Abhi...
Introduction to advanced TUNNEL Formwork system: Case study of  ā€˜Rohan - Abhi...Introduction to advanced TUNNEL Formwork system: Case study of  ā€˜Rohan - Abhi...
Introduction to advanced TUNNEL Formwork system: Case study of ā€˜Rohan - Abhi...
Ā 
Automation construction
Automation constructionAutomation construction
Automation construction
Ā 

More from Laukik Raut

Development of fixture_to_reduce_the_cycle_time_of_c_8_griding_machine
Development of fixture_to_reduce_the_cycle_time_of_c_8_griding_machineDevelopment of fixture_to_reduce_the_cycle_time_of_c_8_griding_machine
Development of fixture_to_reduce_the_cycle_time_of_c_8_griding_machineLaukik Raut
Ā 
Performance analysis of ic engine using air energizer
Performance analysis of ic engine using air energizerPerformance analysis of ic engine using air energizer
Performance analysis of ic engine using air energizerLaukik Raut
Ā 
Computer aided fixture design for machining of key ways
Computer aided fixture design for machining of key waysComputer aided fixture design for machining of key ways
Computer aided fixture design for machining of key waysLaukik Raut
Ā 
Finite element analysis of impact socket used in torque wrench
Finite element analysis of impact socket used in torque wrenchFinite element analysis of impact socket used in torque wrench
Finite element analysis of impact socket used in torque wrenchLaukik Raut
Ā 
Warpage simulation of manhole cover using auto cast x software
Warpage simulation of manhole cover using auto cast x softwareWarpage simulation of manhole cover using auto cast x software
Warpage simulation of manhole cover using auto cast x softwareLaukik Raut
Ā 
Developing a gui based design software in
Developing a gui based design software inDeveloping a gui based design software in
Developing a gui based design software inLaukik Raut
Ā 
Design of a graphical user interface for design
Design of a graphical user interface for designDesign of a graphical user interface for design
Design of a graphical user interface for designLaukik Raut
Ā 
An optimal design approach for adamite hot rolling mill roll
An optimal design approach for adamite hot rolling mill rollAn optimal design approach for adamite hot rolling mill roll
An optimal design approach for adamite hot rolling mill rollLaukik Raut
Ā 
Vibration analysis of ci engine using fft analyzer
Vibration analysis of ci engine using fft analyzerVibration analysis of ci engine using fft analyzer
Vibration analysis of ci engine using fft analyzerLaukik Raut
Ā 
Exceedance level of air pollutants in an urban area as a tool
Exceedance level of air pollutants in an urban area as a toolExceedance level of air pollutants in an urban area as a tool
Exceedance level of air pollutants in an urban area as a toolLaukik Raut
Ā 
Efficiency analysis of hydraulic power steering system
Efficiency analysis of hydraulic power steering systemEfficiency analysis of hydraulic power steering system
Efficiency analysis of hydraulic power steering systemLaukik Raut
Ā 
Implementing 5 s methodology as tool for improving efficiency
Implementing 5 s methodology as tool for improving efficiencyImplementing 5 s methodology as tool for improving efficiency
Implementing 5 s methodology as tool for improving efficiencyLaukik Raut
Ā 
Warpage in casting a review
Warpage in casting a reviewWarpage in casting a review
Warpage in casting a reviewLaukik Raut
Ā 
Failure analysis and redesign of shaft of overhead crane
Failure analysis and redesign of shaft of overhead craneFailure analysis and redesign of shaft of overhead crane
Failure analysis and redesign of shaft of overhead craneLaukik Raut
Ā 
Design, development and fabrication of a compact harvester
Design, development and fabrication of a compact harvesterDesign, development and fabrication of a compact harvester
Design, development and fabrication of a compact harvesterLaukik Raut
Ā 
A review on design and development of eccentric shaft for cotton
A review on design and development of eccentric shaft for cottonA review on design and development of eccentric shaft for cotton
A review on design and development of eccentric shaft for cottonLaukik Raut
Ā 
Finite element analysis of single cylinder engine
Finite element analysis of single cylinder engineFinite element analysis of single cylinder engine
Finite element analysis of single cylinder engineLaukik Raut
Ā 
Implementing total quality management to improve facilities
Implementing total quality management to improve facilitiesImplementing total quality management to improve facilities
Implementing total quality management to improve facilitiesLaukik Raut
Ā 
Design and development of fixture for eccentric shaft a review
Design and development of fixture for eccentric shaft a reviewDesign and development of fixture for eccentric shaft a review
Design and development of fixture for eccentric shaft a reviewLaukik Raut
Ā 
Computer simulation of ci engine for diesel and biodisel blends
Computer simulation of ci engine for diesel and biodisel blendsComputer simulation of ci engine for diesel and biodisel blends
Computer simulation of ci engine for diesel and biodisel blendsLaukik Raut
Ā 

More from Laukik Raut (20)

Development of fixture_to_reduce_the_cycle_time_of_c_8_griding_machine
Development of fixture_to_reduce_the_cycle_time_of_c_8_griding_machineDevelopment of fixture_to_reduce_the_cycle_time_of_c_8_griding_machine
Development of fixture_to_reduce_the_cycle_time_of_c_8_griding_machine
Ā 
Performance analysis of ic engine using air energizer
Performance analysis of ic engine using air energizerPerformance analysis of ic engine using air energizer
Performance analysis of ic engine using air energizer
Ā 
Computer aided fixture design for machining of key ways
Computer aided fixture design for machining of key waysComputer aided fixture design for machining of key ways
Computer aided fixture design for machining of key ways
Ā 
Finite element analysis of impact socket used in torque wrench
Finite element analysis of impact socket used in torque wrenchFinite element analysis of impact socket used in torque wrench
Finite element analysis of impact socket used in torque wrench
Ā 
Warpage simulation of manhole cover using auto cast x software
Warpage simulation of manhole cover using auto cast x softwareWarpage simulation of manhole cover using auto cast x software
Warpage simulation of manhole cover using auto cast x software
Ā 
Developing a gui based design software in
Developing a gui based design software inDeveloping a gui based design software in
Developing a gui based design software in
Ā 
Design of a graphical user interface for design
Design of a graphical user interface for designDesign of a graphical user interface for design
Design of a graphical user interface for design
Ā 
An optimal design approach for adamite hot rolling mill roll
An optimal design approach for adamite hot rolling mill rollAn optimal design approach for adamite hot rolling mill roll
An optimal design approach for adamite hot rolling mill roll
Ā 
Vibration analysis of ci engine using fft analyzer
Vibration analysis of ci engine using fft analyzerVibration analysis of ci engine using fft analyzer
Vibration analysis of ci engine using fft analyzer
Ā 
Exceedance level of air pollutants in an urban area as a tool
Exceedance level of air pollutants in an urban area as a toolExceedance level of air pollutants in an urban area as a tool
Exceedance level of air pollutants in an urban area as a tool
Ā 
Efficiency analysis of hydraulic power steering system
Efficiency analysis of hydraulic power steering systemEfficiency analysis of hydraulic power steering system
Efficiency analysis of hydraulic power steering system
Ā 
Implementing 5 s methodology as tool for improving efficiency
Implementing 5 s methodology as tool for improving efficiencyImplementing 5 s methodology as tool for improving efficiency
Implementing 5 s methodology as tool for improving efficiency
Ā 
Warpage in casting a review
Warpage in casting a reviewWarpage in casting a review
Warpage in casting a review
Ā 
Failure analysis and redesign of shaft of overhead crane
Failure analysis and redesign of shaft of overhead craneFailure analysis and redesign of shaft of overhead crane
Failure analysis and redesign of shaft of overhead crane
Ā 
Design, development and fabrication of a compact harvester
Design, development and fabrication of a compact harvesterDesign, development and fabrication of a compact harvester
Design, development and fabrication of a compact harvester
Ā 
A review on design and development of eccentric shaft for cotton
A review on design and development of eccentric shaft for cottonA review on design and development of eccentric shaft for cotton
A review on design and development of eccentric shaft for cotton
Ā 
Finite element analysis of single cylinder engine
Finite element analysis of single cylinder engineFinite element analysis of single cylinder engine
Finite element analysis of single cylinder engine
Ā 
Implementing total quality management to improve facilities
Implementing total quality management to improve facilitiesImplementing total quality management to improve facilities
Implementing total quality management to improve facilities
Ā 
Design and development of fixture for eccentric shaft a review
Design and development of fixture for eccentric shaft a reviewDesign and development of fixture for eccentric shaft a review
Design and development of fixture for eccentric shaft a review
Ā 
Computer simulation of ci engine for diesel and biodisel blends
Computer simulation of ci engine for diesel and biodisel blendsComputer simulation of ci engine for diesel and biodisel blends
Computer simulation of ci engine for diesel and biodisel blends
Ā 

Recently uploaded

Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
Ā 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionDr.Costas Sachpazis
Ā 
Introduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHIntroduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHC Sai Kiran
Ā 
TechTACĀ® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catchers
TechTACĀ® CFD Report Summary: A Comparison of Two Types of Tubing Anchor CatchersTechTACĀ® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catchers
TechTACĀ® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catcherssdickerson1
Ā 
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)Dr SOUNDIRARAJ N
Ā 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfAsst.prof M.Gokilavani
Ā 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile servicerehmti665
Ā 
8251 universal synchronous asynchronous receiver transmitter
8251 universal synchronous asynchronous receiver transmitter8251 universal synchronous asynchronous receiver transmitter
8251 universal synchronous asynchronous receiver transmitterShivangiSharma879191
Ā 
Study on Air-Water & Water-Water Heat Exchange in a Finned ļ»æTube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned ļ»æTube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned ļ»æTube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned ļ»æTube ExchangerAnamika Sarkar
Ā 
Comparative Analysis of Text Summarization Techniques
Comparative Analysis of Text Summarization TechniquesComparative Analysis of Text Summarization Techniques
Comparative Analysis of Text Summarization Techniquesugginaramesh
Ā 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx959SahilShah
Ā 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidNikhilNagaraju
Ā 
Concrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxConcrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxKartikeyaDwivedi3
Ā 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxJoĆ£o Esperancinha
Ā 
An introduction to Semiconductor and its types.pptx
An introduction to Semiconductor and its types.pptxAn introduction to Semiconductor and its types.pptx
An introduction to Semiconductor and its types.pptxPurva Nikam
Ā 
Churning of Butter, Factors affecting .
Churning of Butter, Factors affecting  .Churning of Butter, Factors affecting  .
Churning of Butter, Factors affecting .Satyam Kumar
Ā 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024Mark Billinghurst
Ā 
Instrumentation, measurement and control of bio process parameters ( Temperat...
Instrumentation, measurement and control of bio process parameters ( Temperat...Instrumentation, measurement and control of bio process parameters ( Temperat...
Instrumentation, measurement and control of bio process parameters ( Temperat...121011101441
Ā 

Recently uploaded (20)

Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
Ā 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Ā 
young call girls in Green ParkšŸ” 9953056974 šŸ” escort Service
young call girls in Green ParkšŸ” 9953056974 šŸ” escort Serviceyoung call girls in Green ParkšŸ” 9953056974 šŸ” escort Service
young call girls in Green ParkšŸ” 9953056974 šŸ” escort Service
Ā 
Introduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHIntroduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECH
Ā 
TechTACĀ® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catchers
TechTACĀ® CFD Report Summary: A Comparison of Two Types of Tubing Anchor CatchersTechTACĀ® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catchers
TechTACĀ® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catchers
Ā 
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
Ā 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
Ā 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Ā 
8251 universal synchronous asynchronous receiver transmitter
8251 universal synchronous asynchronous receiver transmitter8251 universal synchronous asynchronous receiver transmitter
8251 universal synchronous asynchronous receiver transmitter
Ā 
Study on Air-Water & Water-Water Heat Exchange in a Finned ļ»æTube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned ļ»æTube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned ļ»æTube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned ļ»æTube Exchanger
Ā 
POWER SYSTEMS-1 Complete notes examples
POWER SYSTEMS-1 Complete notes  examplesPOWER SYSTEMS-1 Complete notes  examples
POWER SYSTEMS-1 Complete notes examples
Ā 
Comparative Analysis of Text Summarization Techniques
Comparative Analysis of Text Summarization TechniquesComparative Analysis of Text Summarization Techniques
Comparative Analysis of Text Summarization Techniques
Ā 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx
Ā 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfid
Ā 
Concrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxConcrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptx
Ā 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Ā 
An introduction to Semiconductor and its types.pptx
An introduction to Semiconductor and its types.pptxAn introduction to Semiconductor and its types.pptx
An introduction to Semiconductor and its types.pptx
Ā 
Churning of Butter, Factors affecting .
Churning of Butter, Factors affecting  .Churning of Butter, Factors affecting  .
Churning of Butter, Factors affecting .
Ā 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024
Ā 
Instrumentation, measurement and control of bio process parameters ( Temperat...
Instrumentation, measurement and control of bio process parameters ( Temperat...Instrumentation, measurement and control of bio process parameters ( Temperat...
Instrumentation, measurement and control of bio process parameters ( Temperat...
Ā 

Design of automatic wall plastering machine

  • 1. See discussions, stats, and author profiles for this publication at: https://www.researchgate.net/publication/316429977 DESIGN OF AUTOMATIC WALL PLASTERING MACHINE Article Ā· April 2017 DOI: 10.5281/zenodo.439237 CITATIONS 2 READS 13,893 2 authors, including: Some of the authors of this publication are also working on these related projects: Total Productive Maintenance View project Development of Fixture View project Laukik P. Raut Raisoni Group of Institutions 44 PUBLICATIONSĀ Ā Ā 123 CITATIONSĀ Ā Ā  SEE PROFILE All content following this page was uploaded by Laukik P. Raut on 24 April 2017. The user has requested enhancement of the downloaded file.
  • 2. ISSN: 2277-9655 [Askar* et al., 6(3): March, 2017] Impact Factor: 4.116 ICā„¢ Value: 3.00 CODEN: IJESS7 http: // www.ijesrt.com Ā© International Journal of Engineering Sciences & Research Technology [543] IJESRT INTERNATIONAL JOURNAL OF ENGINEERING SCIENCES & RESEARCH TECHNOLOGY DESIGN OF AUTOMATIC WALL PLASTERING MACHINE Ankush N. Askar*, Laukik P. Raut * Student, M. Tech CAD/CAM, GHRCE Nagpur, India Department of Mechanical Engineering, GHRCE Nagpur, India DOI: 10.5281/zenodo.439237 ABSTRACT Due to manual process of wall plastering on construction site, there is a huge scale requirement of labor and hence the labor cost is responsible for increasing the price of construction or project work. The quality of work is mostly depending on the skill of the labor work in manual plastering process. The solution of these problems is just to automate the process, so that there will be a saving of period and cost and getting good plaster finishing to the walls. The plastering machine can plaster the walls automatically and very smoothly. Due to which the process will fast and there will be saving of cost and time this will helps to reduce the total cost, total time which ultimately responsible for the growth and hence the progress rate of a country is going to increase. KEYWORDS: Plastering, Plasterboard, AC/DC motor, gears, wire ropes, labor cost etc. INTRODUCTION Construction sector is responsible for a progress of any country, because most of the growth of the nation is depending upon industrialization, civilization, transportation etc which compulsorily has their initial stage of building construction or simply construction. It is a biggest economic sector because of it the development trade in most countries amounts to 10-20% of the total national product, still due to labor demand and most of the work is repetitive it is a slow manual process [2]. So for improving the economic growth of the country and indirectly developing the lifestyle of the countryā€™s people there must be need of improving the techniques of working. Construction sector is unique sector which required more time and money, having very slow and stepwise process. Presently in construction sector near about all the processes are manual which required more time for their completion. Due to which the cost of the project is maximum, hence it must be necessary to automate the processes in the construction work and improve the efficiency of it. Wall plastering is the main procedure among the processes followed in the building construction, which is used for plaster the walls of the construction to get smooth and finished wall surfaces. Plastering is also essential to give specified strength to the walls; it protects the walls from moisture from both the sides. Wall plastering also gives good look to the walls and ultimately creates best residential condition in the particular room. But in present days wall plastering is being done manually in most of the part of world i.e. the procedure of wall plastering is being done with the assist of labors. Due to which the process is lengthy. So this is an initiative towards the automation in plastering technique. EXISTING TECHNIQUE AND ITS DOWNSIDES The existing technique for plastering the walls is manual i.e. the labors are used to plaster the walls with their hand by using some instruments like flat board or other flat surface object which are made by metal, wood or plastic. Fig. 1 describes the current plastering techniques. In this process the mortar which is the mixture of cement and sand has been spread on the wall which is to be plaster with the help of these objects. After dispersal the mortar the labor need to concentrate to make a skinny film of mortar on the wall, which has been smooth and having good surface finish. Due to which labor need to work repeatedly until he get the required surface finish.
  • 3. ISSN: 2277-9655 [Askar* et al., 6(3): March, 2017] Impact Factor: 4.116 ICā„¢ Value: 3.00 CODEN: IJESS7 http: // www.ijesrt.com Ā© International Journal of Engineering Sciences & Research Technology [544] Fig. 1 Current plastering methods This process takes long time and consumes additional human power. So due to this slow process the labor cost has also been increase as the labors are working on daily basis. If the labor is not a skilled person then there have been a low quality work and there have been wastage of material. Ultimately the manual plastering technique have some downsides like high cost, more time, material wastage and low quality work due to unskilled labors. PROBLEM IDENTIFICATION In the manual plastering technique, the crucial factor is skilled labor because of which plastering has been done on the walls, but presently there is lack of skilled labors due to which it is very inconvenient to complete this process. The labor requires more time to finish the process which increases their wages and hence the total plastering or labor cost increases. Objectives From the above discussion about old plastering techniques, problems in old plastering techniques, their downsides, background of the plastering method and the decided aim to be achieve following are some objective have been decided. 1. This Machine will reduce the human work. 2. It will be straight forward in construction and simple to control. 3. Higher excellence of the plaster can acquire. 4. It will be move horizontally from to other place. So that it will be portable. 5. It will assist to save labor cost. 6. It will avoid wastages of the mortar, thus to save the cost. 7. Machine cost will be less than existing machines. 8. It can be control with the help of remote controller. LITERATURE REVIEW For the modification of the plastering technique lots of work had been done in the past by many people, but due to some problems or deficiencies in that some machines has not been that much in working condition. For getting an idea about the work done in the record on plastering technique it is necessary to do the literature survey and review. According to that following are some vital points which have been taken from the recoded literature and are very much important for designing new Automatic plastering machine. History of plastering machine Ali Al-Hamad, etal [1] stated that the machines were developed firstly have a task of mixing automatically and made mixture due to which it was easy for plastering. The launching of RUMA 1, Putzmeister 1 and Putzmeister Gipsomat developed in sixties century. The AMPA machine is the development in machines. Israe is the country in which ā€˜TAMIRā€™ had been developed. But these innovations have not been capable to give a step ahead in the plastering industry. Thus even today, the plastering machines developed in the sixties are still considered to be up to date. Trowel Technique Mahesha P.K, etal [2] Experimented the trowel operation procedure which is a customary plastering method. The exact plastering procedure is dependent on how the trowel is being used and apply coat of mortar on wall. Receiving a good finish is the grouping of compact force combined with the right angle of trowel, how distant the foremost edge is with the wall. The foremost edge will be approximately 10-15 mm away apart from the wall.
  • 4. ISSN: 2277-9655 [Askar* et al., 6(3): March, 2017] Impact Factor: 4.116 ICā„¢ Value: 3.00 CODEN: IJESS7 http: // www.ijesrt.com Ā© International Journal of Engineering Sciences & Research Technology [545] Fig. 2 Trowel technique Arunkumar Biradar, etal [3] Demonstrated the trowel technique. The right layer technique is essential with exclusively the trowel getting used to use and end the skim coat. Achieving a well-mannered finish is that the grouping of compact pressure and the correct angle of trowel. So front position of the trowel is an absolute approach from the wall. With the resultant stroke, the plaster is simply spread with the help of trowel on the wall surface. Fig.2 describes the trowel operation technique in early covering technique. The right layering method is vital with exclusively the trowel used to and finished the skim coat. Achieving a well-mannered end is that the combination of compact pressure and the correct angle of trowel (how so much the front position is from the wall). Layering technique for applying plaster is initiated by trowel burdened with plaster, the front position of trowel need to move step by step addicted to the wall. With resultant hit of trowel used for layering the plaster as only applied. There'll be no plaster on trowel and it'll be quite flat the forefronts are more or less ten-fifteen millimeter unit detached from the wall. Pre-plastering requirements Mahesha P.K, etal [2] Stated that the brick structure should be developed in proper manner, with the manufacturerā€™s condition and suggested installation procedure. All pre-requirement must be fulfilled, otherwise failing to permit the condition to fully cure can result in excess contraction and cracking on the pointing lines after the walls plastering. 3 mm deviation in surface alignment is allowable over 1200 mm radius. Components need to be fabricate Arunkumar Biradar, etal [3] Shows that the structures of a machine are fabricated by using required necessary components like steel frame, sheet metal, metal bars, lead screw, AC/DC motors, wheels nut and bolts all these can be well assembled as for the requirement. Ali Al-Hamad, etal [1] explained that, the components need to be fabricated for the machine are ceiling bean, steel tube, upper adjustable touch, conveyor belt, plastering board, resist board, supporting bar, lower adjustable touch, hydraulic base, hydraulic handle, hydraulic pedal, oil window, driving shaft, rollers, driveshaft, gears, pulleys etc. Drive technology or control components Mahesha P.K, etal [2] Stated that the microcontroller is family to use on-chip spark recall for program storage, as opposed to one-time programmable ROM, EPROM, or EEPROM used by other microcontrollers at the time. With a single cycle instruction RISC CPU and a loaded attribute set, the structural design ensures fast code execution combined with the lowest possible power consumption. G. Pritschow, etal [4] Shows that due to small working envelop the controller for mobility of robot should be accurate, which can be a microcontroller. Thus the movable podium should be able to go up and go down the staircase. Compact dimensions will allow the robot to pass through doorways and to work in small rooms. A low- cost PC depends run system will be used for motion control, sensor signal processing and human machine interface. Mechanical Concept Arivazhagan.B [5], explained the mechanical design of the plastering machine which consists of the motor pump to push the cement mix, Funnel to load the cement mix, flexible pipe to bear the cement blend to the hopper, horizontal bar guide to move the plastering unit horizontally, horizontal top to grasp the vertical bar guide and move beside the horizontal direction, vertical rail guide to move the hopper vertically, vertical head to grasp the hopper and move beside vertically, cement mix inlet to the hopper, the hopper to hold cement mix provisionally, cylinder slot to discharges the cement consistently with the pressure from the pump present in hopper, metal sheet
  • 5. ISSN: 2277-9655 [Askar* et al., 6(3): March, 2017] Impact Factor: 4.116 ICā„¢ Value: 3.00 CODEN: IJESS7 http: // www.ijesrt.com Ā© International Journal of Engineering Sciences & Research Technology [546] to evenly smudge the cement on the walls. Basic Concept and Enabling Technologies using a Mobile Robot Internal Plastering [6], According to paper, for the mobility criteria in a building site environment a mobile platform capable of hiking and downward stairs is necessary. The best solution is offered by the caterpillar drive which is robust and capable of overcoming inclines of up to 40į“¼. To facilitate automated plastering and to compensate positioning errors the degrees of autonomy are required in a robotic arm. G. Pritschow, etal [4] Stated that the robotic manipulator must have some degrees of autonomy these are, two degrees of autonomy for plaster application in a plane for a single robot working position. A further degree of autonomy is required to compensate for tilting of the movable machine and thus enable parallel motion of the plastering tool with respect to the wall or ceiling. Working of plastering Machine Arunkumar Biradar, etal [3], explained that the initially the machine is placed closed to the wall that is to be plasters. The plaster is poured into the hopper, with the help of lead screw the machine is raised up and will be lock at some instance. The exciting force is given by the rope and machine mechanism. In that way the plastering is done automatically to the wall by automatic plastering machine. Mahesha P.K, etal [2], demonstrated that the machine has to be located near the wall which has going to plaster. The machine should be perfectly leveled. Then the mortar is poured into the hopper of the tray. The lifting force is transferred to tray through power screw, which driven by AC motor. Ali Al-Hamad, etal [1], explained that, the machine works with conventional cement mortar, it can plaster the wall mechanically by stirring up and down in straight up direction. It has two rails for rising and moving automatically, therefore can be used for different height and width of the wall. Advantages of automated machine over manual plastering Ali Al-Hamad[1] Mahesha P.K, etal[2], Arunkumar Biradar, [3] Arivazhagan.B[5], G. Pritschow[6], Teng Long[7] stated that Automatic plastering machine needs less time to complete plastering, no skilled labors required, quality of plastering is comparatively good than manual plastering process, less wastage of raw material than manual plastering, automatic plastering has low cost than manual plastering. Less risk of accidents during construction work. Sr. No. Paper Title Name of Author Findings 1. Plastering Wall Machine Ali Al- Hamad, Osaid Hamdallh, Rand Khraishi, Sami Yonis. ļ± The plastering wall machine will help to save labor cost up to 85%. ļ± Increase productivity by 10-15 times. ļ± Get professional quality finishing in less time, reduce project cost, manufacture wall machine in low cost. 2. Design and Fabrication Of Automatic Plastering Machine Prototype Mahesha P. K. (M-Tech IAR, Mechanical Engg. MCE, Hassan, India) , Sree Rajendra (Associate Professor, Mechanical Engg. MCE Hassan, India) ļ± Powerful competition, shortages of trained labor, increase in labor wages and technical advances are forcing quick change in the building structure. ļ± All these problems can be solve out with automation in constructive technique. One of which is plastering, which is extremely slow & costly when doing manually. ļ± They use necessary components like steel frame, sheet metal, metal bars, power screw, AC/DC motors, different wheels nut & bolts for assemble it.
  • 6. ISSN: 2277-9655 [Askar* et al., 6(3): March, 2017] Impact Factor: 4.116 ICā„¢ Value: 3.00 CODEN: IJESS7 http: // www.ijesrt.com Ā© International Journal of Engineering Sciences & Research Technology [547] ļ± Through trails it is noted that the machine is more productive compare to labor with respect to the plastering work. 3. Automatic Wall Plastering Machine Arunkumar Biradar, Vaibhav Shejwal, Akshay Barate, Sameer Barate ļ± The development trade in most countries amounts to 10ā€“20% of the total nationwide product, creating it the biggest economic using sector. ļ± It's still labor insist and jointly the majority of the work concerned is cyclic. ļ± The expansion of any country depends on the development trade therefore it's of prime economic significance to several industrial sectors. 4. On site Mobile Plastering Robot: A Practical Design Concept G. Pritschow, J. Kurz, J Zeiher, S. C. McCormac & M. Dalacker, (Dept. of Machine & Robot Systems, University of Stuttgart, Germany) ļ± This elaborates basic concepts and technologies for a movable plastering robot used on construction site and operated by skilled worker. ļ± This paper also explained the kinematic structure and control system for a working robot. 5. Automatic Plastering Machine Arivazhgan. B. , B. Tech (ECE) ā€“ IV year, Manakula Vinayagar Institute of Technology, Puducherry. ļ± Automated plastering machine is exclusive and maybe one type of automated plastering machinery suitable for construction industry. ļ± It makes plastering easy, fast and effortless as compare to manual use. 6. A Construction Robot for Autonomous Plastering of Walls and Ceilings. Johan Forsberg, Roger Aarenstrup, (Robotics and Automation, Lulea University of Technology, Sweden) ļ± The time used for plastering the wall is expected to be less than 50% of that required by manual work. ļ± The reason for developing the robot is mainly ergonomic. They also discuss about Mechanical error sources, Navigation errors & Control errors. 7. Mechanical Design of A Quadruped Robot for Horizontal Ground to Vertical Wall Movement Abd Alsalam Sh., Rosbi Mamat. (University Technology, Malaysia) ļ± This paper the highlighting given the mechanical structure of a quadruped machine able to walk on ground, go up on vertical walls and perform the ground-wall movement automatically. ļ± It is electrically actuated one. 8. A Service Robot for Construction Industry Pablo Gonzalez De Santos, Joaquin Estremera, E. Garcia. (CSIC, Spain) ļ± This explained the required features of the robot manipulator developed for construction. ļ± Also discussed main subsystem i.e. Frame, manipulator, Grasping device, controller & guiding system. 9. Automatic Wall Plastering and Repairing Robot using Artificial Intelligence Dr. S. K. Rajesh Kanna. (Dept. of Mechanical Engg, Rajlakshmi Institute of Technology, India) A. D. Jaisaree. (Dept. of Computer science and Engg, Mahendra Engineering College, India) ļ± The movement of the poppet is controlled by a high torque motor. ļ± The robots have been developed to apply the mortar on the vertical walls with pressure and having the capability of self adjusting the mortar thickness. ļ± The machine solves the issues like shortage of labor, raise in labor cost etc. and wastage of mortar is reduced more than 60% thereby reduces the raw substance requirement.
  • 7. ISSN: 2277-9655 [Askar* et al., 6(3): March, 2017] Impact Factor: 4.116 ICā„¢ Value: 3.00 CODEN: IJESS7 http: // www.ijesrt.com Ā© International Journal of Engineering Sciences & Research Technology [548] METHODOLOGY Methodology to be used is as follows for the designing of automatic plastering machine on the basis of literature survey. Data and design calculation Design of plasterboard By Considering, 1) Horizontal length of plasterboard = 2 feet = 0.61 m = 610 mm 2) Length of bottom plate of plasterboard (Trowel) = 0.25 m = 250mm 10. Advanced Dry Mortar Technology for Construction Industry Ir. Raymond Wan MEng, CEng, MIM, MICE, MICT, MHKIE, RPE ļ± Good quality dry mix products are available in the market with improved performance. ļ± Although, dry mortars cannot totally solve all the construction problems, ļ± On the contrary, advanced dry mortars are very complicated powdery mixtures with sophisticated chemical additives of newest technology to provide wide range of superior act to get together complex construction requirements. 11. Finishing guide For Thistle plaster and Gyproc plasterboard A Saint-Gobain Company ļ± This guide states the different methods of finishing the wall surfaces by plastering, different accessories for plastering, instruments, techniques etc. 12. Comparative Study on Mould Growth on Plaster Boards treated with Biocides Julia Friman Degree project for Master of Science (One Year) in Plant Ecology 30 hec Department of Plant and Environmental Science Gƶteborg University ļ± This theory aims to match up to the most capable biocide anti fungal result when use as a covering on Plaster plates. ļ± The method contained simple humid boxes, together with a visual and an agar cultivation as assessment. ļ± Dry grass was used as contamination. The testing was designed to compare the biocides with the reason of establishing relative mould growth values. 13. Basic Concept and Enabling Technologies using a mobile Robot for Internal Plastering. Reference:- WeiBert M., Leixner, Raddsatz. ļ± The introduction of plastering robots would resemble the revolution in the plastering industry in the sixties when plastering machines helped to improve overall productivity by more than 30%. ļ± The machine construction industry will also have excellent chances at extending their current markets. 14. A Novel Measurement and Control Method for Automatic Plastering Machine. Teng Long, En Li, Zaojun Fang, Weiqing Zhao and Zize Liang (Institute of Automation Chinese Academy of Sciences, Beijing 100190, China) ļ± This research proposes a novel method of plastering machine measurement and control method depends on laser triangulation. ļ± This method canā€™t solve some problems such as corner is unreached and the power of vibration canā€™t be compensated.
  • 8. ISSN: 2277-9655 [Askar* et al., 6(3): March, 2017] Impact Factor: 4.116 ICā„¢ Value: 3.00 CODEN: IJESS7 http: // www.ijesrt.com Ā© International Journal of Engineering Sciences & Research Technology [549] 3) Length of upper plate of plasterboard = 1*1/2 feet = 0.46 = 460 mm 4) Universal one coat plaster thickness = 12 mm 5) Trowel leading edge will be approximately 10-15 mm away from the wall surface, so consider = 10 Fig. 3:- 2-Dimensional view of plasterboard 6) Total distance of leading edge from the wall = plaster thickness + leading edge distance = 12 mm + 10 mm = 22 mm Now, 1) In triangle AED, By Pythagoras theorem, AE2 = AD2 + DE2 3002 = AD2 + 102 AD = 299.83 mm AD = 300 mm 2) In triangle DAE, sinĪø = opposite side/hypo sinĪø = 10/300 Īø = 20į“¼ 3) Now, In triangle EFG, SinĪø = Opposite side/ Hypo Sin30 = FG/FE Assume Īø= 30 0.5 = FG/460 FG = 230 mm 4) FH = FG + GH = 230 + 22 = 352 mm 5) In triangle FGE, By Pythagoras theorem FE2 = FG2 + GE2 4602 = 2302 + GE2 GE = 398 mm 6) Volume of ā–” CEXY = L * B * H = 200 * 22 * 610 = 2684000 mm3 = 0.0026 m3 7) Volume of prism EXY = Ā½ * L * B * H = Ā½ * 200 * 115 * 610 = 7015000 mm3 = 0.0070 m3 8) Total Volume = Volume of ā–” CEXY + Volume of prism EXY = 0.0026 + 0.0070 = 0.0096 m3 9) The Density of the standard mortar (sand + cement) = 2200 Kg/ m3 10) Mass of mortar = Volume of mortar * density
  • 9. ISSN: 2277-9655 [Askar* et al., 6(3): March, 2017] Impact Factor: 4.116 ICā„¢ Value: 3.00 CODEN: IJESS7 http: // www.ijesrt.com Ā© International Journal of Engineering Sciences & Research Technology [550] = 0.0096 * 220 = 21.12 Kg 11) Load = 21.12 * 9.81 = 207.18 N 12) Mass of plasterboard = 6 Kg = 6 * 9.81 = 58.86 N = 59 N 13) Total Load = Load of mortar + Load of plasterboard + Frictional and other load = 208+ 59 + 200 = 467 N = 470 N = 48 kg 14) There are two different sides, so load on single side = 470/2 = 235 N DC motor specification Power of motor = 1 hp = 750 watt Torque = 240 kg-cm = 23.54 * 103 N-mm Fig. 4 DC motor Frequency = 60 Hz Now, Power = 2āˆNT/60 750= 2 āˆ*N*23.54/60 N = 304.40 rpm Design of Shaft Material for shaft ā€“ Fe 360 Yield Strength (Syt) = 220 N/mm2 Ultimate tensile strength (Sut) = 360 N/mm2 Now according to A.S.M.E (American Society of Mechanical Engineers) Shear stress Ļ„ = 0.18 * Syt = 0.18 * 220 = 39.6 N/mm2 Ļ„ = 0.3 * 360 = 0.3 *360 = 108 N/mm2 Total Load = 47.60 kg = 48 kg = 48 * 9.81 = 470 N There are two different sides So, load on single side = 470/2 = 235 N RA = 235 N RB = 235 N Bending Moment M = RA * 30 =235*30 = 7050 N-mm So, Twisting moment (Te) = āˆš(Km * M) 2 + (Kt * T) 2 = āˆš (1.5 * 7050) 2 + (1 * 23.54 *10 3 ) 2 = 25806 N-mm
  • 10. ISSN: 2277-9655 [Askar* et al., 6(3): March, 2017] Impact Factor: 4.116 ICā„¢ Value: 3.00 CODEN: IJESS7 http: // www.ijesrt.com Ā© International Journal of Engineering Sciences & Research Technology [551] For rotating shaft having gradually applied load, Km ā€“ Combined shock and fatigue factor for bending = 1.5 Kt ā€“ Combined shock and fatigue fact for torsion = 1 We know, The torsion equation T/J = Ļ„/r Where, T = Twisting moment acting upon the shaft J = Polar moment of inertia of the shaft about the axis of rotation. Ļ„ = Torsional shear stress and r = d/2, d is the diameter of the shaft. So, Te = āˆ/16 * d3 * 39.6 d = 14.91 mm So, get standard diameter of the shaft i. e. 15 mm Design of worm and worm gear Material for worm wheel ā€“ Phosphor bronze Material for worm ā€“Cast harden steel (Sut)worm wheel = 240 N/mm 2 (Sut)worm = 700 N/mm 2 Assume, No. of teeth on worm = Zw = 5 No. of teeth on worm gear = Zg = 25 So, Gear ratio = 25/5 = 5 Beam Strength of worm gear, By Lewis equation, Wt = 6ā‚€ * Cv * b * āˆ * m * y Where, Wt = permissible tangential tooth load or beam strength of gear tooth 6ā‚€ = Allowable static stress Cv = velocity factor b = face width m= module y = tooth form factor or Lewis factor 6ā‚€ = 105 N/mm2 ------For cast iron Pitch circle dia. Of the worm gear D = 60 mm Pitch circle (Pc) = āˆD/T = āˆ * 60/ 25 = 7.54 mm Outside diameter (Do) = D + 1.0135 Pc = 60 + 1.0135 * 7.54 = 67.64 mm Throat diameter (Dt) = D + 0.636 * Pc = 60 + 0.636 * 7.54 = 64.80 mm Face width (b) = 2.38 * Pc + 6.5 = 24.44 mm Radius of gear face (Rf) = 0.882 * Pc + 14 = 20.65 mm Radius of gear rim (Rr) = 2.2 * Pc + 14 = 30.588 mm Linear velocity of worm gear Vg = āˆ * D * N/ 60 = āˆ * 0.06 * 5.06/60 = 0.015 m/s Velocity factor Cv = 6 / 6 + v = 0.9978
  • 11. ISSN: 2277-9655 [Askar* et al., 6(3): March, 2017] Impact Factor: 4.116 ICā„¢ Value: 3.00 CODEN: IJESS7 http: // www.ijesrt.com Ā© International Journal of Engineering Sciences & Research Technology [552] Lewis form factor y = 0.124 ā€“ 0.684 / Tg = 0.0966 Module m, D = m * Tg m = 2 So, Beam strength of worm gear = 1612.39 N Now, Wear tooth load for worm gear, For worm, Dia. of worm = m * q = 2 *10 = 20 mm Axial pitch Pa = āˆ * m = 6.28 mm Face width = 0.73 * dw = 14.6 mm Centre distance = dw + D/2 = 40 mm Addendum = 1m = 2 mm Deddendum = 1.25m = 2.5 mm Length of worm = Pa * Zw = 31.4 mm Ww = D * b * k Where, D ā€“ pitch circle diameter of worm gear b ā€“ face width of the worm gear k ā€“ load stress factor = 0.345 So, Ww = 505.90 N Design of Rope Fig.5 Steel Rope Type of rope = 6 * 19 Material = Steel wire Diameter = 3 mm Minimum breaking stress = 1770 Mpa Minimum load capacity = 588 kg Area of wire rope = 0.38 * d2 = 3.42 mm2 Diameter of the pulley or drum = 30 * d = 90 mm Tensile strength = 540d 2 = 4860 N/mm 2 Factor of safety = 3.5 i.e. 3.5 * 2 = 7 Stresses in wire rope, Direct stress 6d = W + w/ A Where, W = load lifted w = weight of the rope A = C/S area of the rope So, direct stress, 6d = 69.94 N/mm2 Bending stress when wire rope winds round the drum or pulley 6b = Er * dw/ D = 84 * 103 *3/ 90 = 2800 N/mm2 Where, Er ā€“ Modulus of elasticity of wire rope = 84 * 103 N/mm2
  • 12. ISSN: 2277-9655 [Askar* et al., 6(3): March, 2017] Impact Factor: 4.116 ICā„¢ Value: 3.00 CODEN: IJESS7 http: // www.ijesrt.com Ā© International Journal of Engineering Sciences & Research Technology [553] dw ā€“ dia. Of wire D ā€“ dia. Of pulley or drum Total stress = 69.94 + 2800 = 2870 N/mm2 Our design load = F.O.S. * total load = 7 * 470 = 3290 N So wire rope of diameter 3 mm, 6 * 19 type is satisfactory Design of Bearings Specification:- Bore diameter d = 15 mm Outside diameter D = 35 mm Width B = 11 mm Greece lubrication = 19000 Oil lubrication = 24000 Dynamic load C = 7800 N Static load Co = 3550 N Now, Radial and Axial load, Radial load Fr = 235 N Axial load Fa = 0 N Equivalent dynamic load Fe = [ X * V * Fr + y * Fa] = [1 * 1 * 235 + 1 * 0 ] Fe = 235 N Req. dynamic load capacity = L = (Cr/Fe) a Ball bearing a = 3 So, L = 8000 hrs 8000 = (Cr/235) 3 Cr = 4700 N Since, Cr < C, so selected bearing is suitable. 2-D drawing and CAD modeling of plastering machine On the basis of above design calculation the computer aided design (CAD model) of some parts of the plastering machine and assembly of the plastering machine has been done with the help of Computer Aided Software naming ā€˜CRE-Oā€™ by applying Bottom-up approach. Fig.5 drawing of ceiling beam and base of machine
  • 13. ISSN: 2277-9655 [Askar* et al., 6(3): March, 2017] Impact Factor: 4.116 ICā„¢ Value: 3.00 CODEN: IJESS7 http: // www.ijesrt.com Ā© International Journal of Engineering Sciences & Research Technology [554] Fig. 6 CAD model of components of plastering machine CONCLUSION By studying all the above literatures and the work done following conclusions are obtained. 1. Automatic plastering machine is one type of unique machine will be used in construction industry. 2. It helps to save the time and money. 3. It works with cement mortar which is conventional one due to which no replacement of the material required. 4. The machine is more productive than the conventional plastering technique. 5. Higher quality of a plaster can be obtained with this machine. 6. The thickness of the plaster will be constant over the wall which is generally varying 0.5 to 0.75 inches at different conditions of the wall surface. 7. This machine needs to poured the mortar manually so, it has needed the work automation of loading mortar. 8. It reduces the wastage of mortar up to 60% and hence required fewer raw materials. 9. Due to saving in time, labor cost, raw material, the overall cost of construction is less hence the machine is economically efficient than the conventional plastering technique. RESULT Table shows comparative result on different objectives, for a 10 feet*10 feet wall by both existing plastering method as well as Automatic plastering machine as follows. Sr. No. Objective Existing method Automatic plastering machine 1. No. of labors required 2 to 3 1 or 2 2. Time required (hours) 6 to 7 (hours) 1 to 2 (hours) 3. Material More material required compared to plastering machine as there is more wastage of mortar. Less material required, compared to conventional method as less material wastage is there. 4. Cost Comparatively high cost. (As number of labors and time required is more) Comparatively low cost. (As no. of labors and time required is less)
  • 14. ISSN: 2277-9655 [Askar* et al., 6(3): March, 2017] Impact Factor: 4.116 ICā„¢ Value: 3.00 CODEN: IJESS7 http: // www.ijesrt.com Ā© International Journal of Engineering Sciences & Research Technology [555] REFERENCES [1] Ali Al-Hamad, Osaid Hamdallah, Rand Khraishi, Sami Yonis, ā€œPlastering Wall Machineā€, An-Najah National University [2] Mahesha P.K,Sree Rajendra ā€œDesign and fabrication of automatic wall plasterig machine prototypeā€, IOSR Journal of mechanical and civil engineering, volume 11,issue 4 ,(Jul-Aug 2014),pp 01-06. [3] Arunkumar Biradar, Vaibhav Shejwal, Akshay Barate, Sameer Barate, ā€œAutomatic Wall Plastering Machineā€, International Journal of Engineering and Technical Research (IJETR) ISSN: 2321-0869 (O) 2454-4698 (P), Volume-4, Issue-1, January 2016. [4] G. Pritschow, J. Kurz, J Zeiher, S. C. McCormac & M. Dalacker, ā€œOn site Mobile Plastering Robot: A Practical Design Conceptā€, Dept. of Machine & Robot Systems, University of Stuttgart, Germany [5] Arivazhagan.B, ā€œAutomatic Plastering Machineā€, International Journal of Advanced Research in Electronics, Communication & Instrumentation Engineering and Development Volume: 2 Issue: 2 28- Jul-2014,ISSN_NO: 2347 -7210. [6] Basic Concept and Enabling Technologies using a Mobile Robot Internal Plastering [7] Johan Forsberg, Roger Aarenstrup, ā€œA Construction Robot for Autonomous Plastering of Walls and Ceilingsā€. Robotics and Automation, Lulea University of Technology, Sweden [8] Abd Alsalam Sh., Rosbi Mamat, ā€œMechanical Design of A Quadruped Robot for Horizontal Ground to Vertical Wall Movementā€. University Technology, Malaysia [9] Pablo Gonzalez De Santos, Joaquin Estremera, E. Garcia., ā€œA Service Robot for Construction Industryā€, CSIC, Spain [10]Dr. S. K. Rajesh Kanna. (Dept. of Mechanical Engg, Rajlakshmi Institute of Technology, India) A. D. Jaisaree. (Dept. of Computer science and Engg, Mahendra Engineering College, India), Automatic Wall Plastering and Repairing Robot using Artificial Intelligence. [11]Advanced Dry Mortar Technology for Construction Industry, Ir. Raymond Wan MEng, CEng, MIM, MICE, MICT, MHKIE, RPE [12]Comparative Study on Mould Growth on Plaster Boards treated wit Biocides,Julia Friman Degree project for Master of Science (One Year) in Plant Ecology 30 hec Department of Plant and Environmental Science Gƶteborg University [13]Basic Concept and Enabling Technologies using a mobile Robot for Internal Plastering. [14]Teng Long, En Li, Zaojun Fang, Weiqing Zhao and Zize Liang (Institute of Automation Chinese Academy of Sciences, Beijing 100190, China), A Novel Measurement and Control Method for Automatic Plastering Machine. [15]R. S. Khurmi and J.K.Gupta, Machine Design,14thedition Eurasia Publishing House (PVT.) Ltd. 2005. View publication statsView publication stats