Ramakant Kushwaha
D.no:605 L, Loco Colony
Civil Line,
Allahabad( Dist),U.P,
Email ID :ramakant.1980@rediff mail.com
D.O.B – 06/01/1980,
ph#: 7218143423
I T I in Electrical – PROJECT EXECUTION – 11+ EXP
Objective :
To Obtain a position where I can apply acquired knowledge and skills, to strive and excel in
Whatever Works those are undertaken, there by continuously growing and contributing to the
Main objective of the organization.
TECHINICAL QUALIFICATION
1. I T I in WIREMAN
Year of completion : 2002
Institute : Government ITI, Naini, Allahabad.
2. NCVT in WIREMAN
Year of completion : 2005
Institute : Government ITI, Naini, Allahabad.
ACADEMIC QUALIFICATION
1. Passed B.A From University of Allahabad in year of 2001
OTHERS
1. Possessing a Wireman License permit from UP Govt, Lucknow valid from 12/03/2004 to
11/03/2019.
2. One year Apprentice with M/s Alstom Limited, Naini, Allahabad Since 05/03/2004 to
04/03/2005.
TRAINING PROGRAMMS ATTENDED:
1. SAFETY PROCEDURES, PRACTICES & PRECAUTIONS IN CONSTRUCTION
a. Practices to be followed while working in heavy electrical construction division
b. Safety precautions to be followed while working heights.
c. Safety against fire & fire fighting devices.
d. Using of PPE (PERSONAL PROTECTIVE EQUIPMENT) like safety belt, safety helmets
safety shoes etc.
Experience
1).M/s TECHNOLOGICAL ASSOCIATES.
Designation: Site Supervisor maintenance works in UPPCL.
Duration: APRIL-2005 to MAY 2006.
1. As per survey pit marking, with Board officials.
2. Pole Erection STRINGING And DTR erection.
4. Over all Responsible for site activities.
5. Manpower Management.
2).M/S MAYTAS INFRA LIMITED
Designation: Supervisor - Electrical - Project execution & Erection & Commissioning
Duration : June 2006 to July 2010
Projects Done so far :
1) Rural Electrification works at MAU, UP.(PGCIL)
2) Rural Electrification works at Chhindwara, MP (MPPKVVCL)
3) Feeder Separation works at Ujjain, M.P. (MPPKVVCL
3).M/S VIJAI ELECTRICALS LIMITED
Designation: Supervisor - Electrical - Project execution Erection & Commissioning
Duration : August 2010 To Till Date
Projects Done so far
1) Feeder Separation works at Dewas Dist, M.P. (MPPKVVCL).
2) R & M of PSS and Feeder Separation work, BRGF-190 Special plan at west Champaran,
BIHAR (NBPDCIL).
3) Project: INFRA PLAN PHASE – I & II under MSEDCL (MH) Maintenance work running
Activates Organized:
1. Submitting the drawings to the client. Getting the Drawings Approval from client. Necessary Technical
discussions with client and make the necessary changes in the drawings and getting the drawings
approval from client.
2. Detailed study of the drawings and preparing the Bill of Quantities according to the Drawings.
3. Proper planning for the execution of the project.
PROJECT DONE UNDER CLIENT :
1.Project: Rural Electrification RGGVY under PGCIL (UP)
2. Project: Rural Electrification RGGVY under MPPKVVCL,CHHINDWARA(MP)
3. Project: Feeder separation under MPPKVVCL,DEWAS ( MP)
4. Project: BRGF-190Special plan (R &M WORK) under NBPDCL,(BH)
5. Project: INFRA PLAN PHASE – I & II under MSEDCL (MH)
Executing the said job as a Supervisor (Both Site planning and execution) and the following are the high
lights of the project.
Preparation of the cost estimation and arriving at the sub contractor price for different works for
erection.
Preparation of the invoicing schedule for the zone and man power requirement schedules
Survey & Construction of LT & HT Lines
Pole erection as per approved drawing with client.
Erection of stay sets & earthing ( Pipe, spike & coil earthing)
Erection & Commission of PTR/DTR at subs stations & Load location.
Service connections for BPL/APL etc.
Erection of 33kv & 11kv VCB, Bay extension, AB Switch/Isolator, LA etc.
Layout & SLD preparation/estimation of 33/11kv substation equipments.
Complete Planning for Execution of the project at site.
Quantification of all required materials and supply monitoring.
Material follows up with concern dept and ensuring the availability of the material at site for
construction to have an uninterrupted work flow to avoid the man day loss.
Handing over formalities with client and organizing the handing over of the same.
Declaration:
I hereby declare that above furnished information are correct and true to the best of my knowledge and
belief.
Place: Nagpur
Date: RAMAKANT KUSHWAHA