SlideShare uma empresa Scribd logo
1 de 20
Baixar para ler offline
Texas American Water Works Association

April 2006

ACTIVATED SLUDGE PLANT FIELD & MODEL CAPACITY EVALUATION
Ricky Garrett, PE, Mike Jupe (TCEQ “A” Certified Wastewater Operator) and
Daniel Christodoss, PE, PhD
City of Waco Water Utility Services
P.O. Box 2570
Waco, TX 76702-2570

ABSTRACT
This paper presents results from the model capacity evaluation of an activated sludge
plant at a large municipal wastewater treatment plant. The plant capacity evaluation
(stress test) was performed to evaluate treatment process capacity and efficiencies as a
part of the continuous improvement of the treatment plant for process optimization and
maximization of flow through the plant.
The stress test was performed for 3 months mainly during dry weather with a few wet
weather events that caused equivalent inflows higher than the existing rating of 37.8 mgd.
The stress test was conducted by diverting the entire flow proportionally through 3 of the
5 aeration basins and 3 of the 4 final clarifiers. Since normal operation of the plant is with
5 aeration basins, in terms of true plant capacity, a flow of 28 mgd through these 3
aeration basins during the stress test equates to 22.68 mgd x 5 basins/3 basins = 37.8 mgd
during normal operations (with 5 aeration basins in service). Similarly, a flow of 28.35
mgd through 3 final clarifiers during this stress test is equivalent to 37.8 mgd through 4
final clarifiers during normal operations.
On any given day, the stress tests lasted several hours during periodic, relatively stable,
flow conditions. System performance was evaluated by measuring influent and effluent
BOD, ammonia, and TSS.
The major conclusion is that the plant can treat more than 20% of current permitted flow
effectively, which was established by the stress test and the mathematical model as
shown in Tables 1.
Table 1 - Stress test June thru August 2005
Plant
Flow
(mgd)

Aeration
Flow
EQUIV Inf. BOD5 Inf. TSS Inf. NH3 Eff. CBOD5 Eff. TSS Eff. NH3 LBS-BOD Detention,
(mgd) (mg/L)
(mg/L) (mg/L) (mg/L)
(mg/L) (mg/L) (entering) (hrs)

Average 23.165
37.781
Max

38.43

220.140

224.721 16.884 1.413

1.366

0.164

42,177

5.32

52.33

587.000

614.000 23.000 3.730

4.500

2.220

106,155

6.20

19.641

32.74

62.000

116.000 10.700 0.590

0.000

0.042

12,444

3.88

Min
Texas American Water Works Association

April 2006

KEYWORDS
activated sludge, aeration, stress test, model capacity, final clarifiers, waste water
treatment, nitrification, biological oxygen demand, total suspended solids, ammonia,
anoxic zone, oxygen transfer, operations and maintenance, treated effluent
INTRODUCTION
This field and model capacity evaluation was performed at a time when the plant capacity
was being down-rated from 37.8 MGD down to 31 MGD. The potential for down-rating
raised the following concerns:
•
•
•

Significant loss in capacity
Funding needed to construct additional facilities ($40-$70 million)
Timing for the downgrade invoking an unrealistic accelerated schedule

The operational history of the plant that led to the potential down-rating is described
below.
PLANT COMPONENTS
Features of the WMARSS system include:
1. Primary clarifiers capable of efficient capture of suspended solids, grit and scum
from plant inflows including high short term peak flows.
2. Biological activated sludge treatment using:
a) 5 aeration basins which are designed to facilitate operation in plug flow
with tapered aeration, step aeration (step feeding), or complete mix. The
aeration basins produce a waste activated sludge which is as easy to
separate and dispose of as possible
b) Final clarifiers capable of removing activated sludge and scum promptly
and efficiently, and dividing it into desired return activated sludge (RAS)
and Waste Activated Sludge (WAS) flows
3. Thickeners for combined primary and waste activated sludges, with DAF
thickeners chosen specifically for the mixed sludge involved.
4. Two-stage anaerobic digestion of mixed sludges for effective stabilization and
yield of by-product methane.
5. Two Engine/Generators capable of producing half the plant’s power needs.
6. Anaerobically digested sludge filter pressed to a cake of 18% solids. The cake is
heat dried and pelletized (with heat from the furnace) into a commercial sized
pellet with nutritional and soil conditioning value at slow release. The methane
gas from the digestors powers the furnace to the drier unit and is blended with
natural gas to conserve energy.
Texas American Water Works Association

April 2006

OPERATIONAL HISTORY
The conventional activated sludge Wastewater Treatment Plant for the Waco
Metropolitan Area Regional Sewerage System (WMARSS):
•
•

•
•

•

was constructed in 1983 and
started operation in 1984 under an operating permit which restricted flow to a
maximum 30-day average of 37.8 MGD daily average, 47.9 mgd daily max, 83.2
mgd, 2 hour peak flow, at treated effluent limits of 20 mg/L BOD, and 20mg/L
TSS.
won an EPA award in 1993, for plants treating 10 mgd and higher
had a change in the effluent limits in 1995 to 10 mg/L BOD, 15 mg/L TSS and 3
mg/L NH-3 single stage nitirification at which time, a pellet drying facility was
added to the plant to treat digested sludge. When the ammonia permit was
issued, the fifth aeration basin was constructed to provide the biological
treatment and retain the 37.8 mgd annual average influent, at 250mg/L BOD and
250mg/L TSS.
was being considered for down-rating in 2000-2004 based on performance issues
compounded by design and operational constraints

EPA’s DEFINITION OF PLANT CAPACITY
True capacity of a plant is a function of design, process optimization and management.
In the original 1984 Operations and Maintenance (O&M) Manual, EPA’s findings on 287
plants were quoted as follows:
a) Plant performance depends on the quality of the original design, the
caliber of the plant’s administrators, the effectiveness of the operators and
the quality of the maintenance program.
b) Every treatment plant has its own performance-limiting problems (foulups). This was found whether or not a plant was meeting permit. And if
these problems can be sorted out and defined, then they can be cured, or
made less severe, or (if nothing else) watched constantly.
DESIGN AND OPERATIONAL CONSTRAINTS
EPA’s findings cited above held true for the WMARSS plant. In 1998, the following
operational problems were identified:
a) There were inadequacies in communication between administration and plant
personnel.
Texas American Water Works Association

April 2006

b) The plant side steams had adverse affects on the entire treatment train as a result
of inadequate standard operating procedures to control the effects of the single
stage nitrification cycle and the pellet building wastewater discharge.
At this time, the WMARSS staff started evaluating the treatment system with EPA’s
findings in mind. The evaluation resulting in the following findings:
1. The oxygen transfer efficiency in the aeration basins was inadequate to supply the
oxygen needed for single stage nitrification. The bubbles were coarse and there
was not enough volume to achieve the desired treatment. Following graph depicts
how bubble size affects oxygen transfer.
Figure 1 – Bubble Size vs. Oxygen Transfer Efficiency

2.

The anoxic zones were not mixed nor utilized effectively to reduce the oxygen
demand through BOD reduction utilizing nitrate as the substrate and alkalinity
savings. Following is an introduction to nitrification and de-nitrification for
clarification.

Nitrogen appears in organic wastes in various forms. In wastewater, four types of nitrogen are common:
organic nitrogen, ammonia nitrogen, nitrite nitrogen, and nitrate nitrogen. These different forms constitute
the total nitrogen content. The predominant forms of nitrogen in wastewater are organic nitrogen and
ammonia (NH3). Organic nitrogen is converted to ammonia in the first step of the nitrogen cycle. In order to
remove nitrogen from wastewater, ammonia must be oxidized to nitrate (NO3). This process is commonly
referred to as nitrification. An oxic environment must be maintained for sufficient period of time to promote
nitrification.
The overall reaction of nitrification is:
NH3
NO2
NO3
Oxic conditions are maintained by a number of aerators. In the presence of dissolved oxygen, the
microorganisms convert stored BOD (biochemical oxygen demand) to CO2, water, and increased cell mass.
Biological nitrification occurs, producing nitrite in an intermediate step and ultimately producing nitrate.
Following nitrification, nitrogen can be removed from the wastewater by reducing the nitrate to nitrogen
gas (N2), which is released to the atmosphere. This process is commonly referred to as denitrification.
Denitrification requires anoxic conditions, as well as an organic carbon source, to proceed.
Texas American Water Works Association

NO3nitrate

NO2
nitrite

April 2006

NO
nitric oxide

N2O
nitrous oxide

N2
nitrogen gas

Introducing an anoxic zone into the flow scheme provides de-nitrification of nitrate in the return activated
sludge from the clarifier. In this zone, operated with little to no dissolved oxygen (DO), the endogenous
oxygen demand of mixed liquor suspended solids (MLSS) plus the carryover of BOD (biochemical oxygen
demand) from the primary clarifier causes de-nitrification of the nitrate produced in the aerobic zone.
During anoxic conditions, dissolved oxygen is not available to the microorganisms for respiration. Because
of this, the oxygen molecules are stripped from the nitrate, causing the production of nitrogen gas (N2) .
Carbon dioxide and water are also produced in the process, which results from the degradation of BOD. In
addition, a portion of the alkalinity consumed during the nitrification process is restored through the denitrification process. When the mixed liquor flows to the secondary anoxic zones, there will be a relatively
small concentration of extra cellular BOD in the wastewater. However, de-nitrification will still proceed since
the microorganisms utilize internal storage products to reduce nitrate (endogenous de-nitrification).
Secondary anoxic zones are not present at WMARSS.

Figure 2 – Process Schematics Showing Anoxic-Aeration and Clarifier Sequence

Figure 3 – System Schematics Influent to Effluent

3. The higher waste concentrations from the single stage nitrification had tendencies
to overload the subsequent sludge thickening and anaerobic digestion process.
Texas American Water Works Association

April 2006

4. The inadequately controlled sludge thickening process adversely affected the
single stage nitrification process and anaerobic digester process.
5. The pelletizing process discharged ammonia concentrations that caused
fluctuation in the nitrification process, oxygen demand, chlorine demand and
sulfur dioxide demand.
6. Inadequate screening of the plants influent and sludge flow adversely affected the
sludge thickening process, digestion process and the pelletizing process.
The above six factors influence plant chemistry from an average BOD concentration of
250 mg/l to 350 mg/L, i.e. adding a 28 percent increase in plant BOD loading.
PERFORMANCE IMPROVEMENTS
To transition from re-treating plant foul-ups and collection system waste, the following
improvements were made to optimize plant performance:
•

Secondary Treatment Improvements.
Increased the Oxygen Transfer Efficiency in four aeration basins.
Automated the aeration zone valves to maintain the zones set D.O. level.
Automated three of the blowers to start-up with adjustable loading to
satisfy the biological oxygen demand.
Installed Cipolletti weir aeration influent weirs to control and balance the
aeration feed rate.
Improved the anoxic zone mixing efficiency.
Operated four aeration basins year round to obtain an average five-hour
detention time.
Maintained a minimum 1.5 mg/L D.O. in first aeration zone to obtain
optimal nitrifying growth rate.
Maintained a maximum .3 mg/L D.O. in anoxic zone to obtain optimal denitrifying growth rate.
Adjusted the aeration influent Cipolletti weir daily to balance and control the
aeration basins feed rate.
Adjusted the wasting rates by the 10 percent rule.
Adjusted the activated sludge return rates lower to control the basins F/M
ratio, pounds of nitrates to the anoxic zone with longer detention times.

•

Solids Processing Improvements.
Started feeding polymer to the D.A.F. to increase the capture rate of the
unit, thus lowering the sludge flow to the Digesters that increased their
detention time along with lowering the BTU needed to heat the units and
lowered the run time of the Dryer unit.
Redirected the D.A.F underflow to the solids side final clarifier underflow
wet well, instead of the plants under drains.
Started up the second solids side final clarifier underflow pump to limit
the amount of solids entering the plant under drains.
Texas American Water Works Association

April 2006

Started one of the two side stream trickling filters to reduces the BOD reentering the plants influent.
Installed a two-millimeter opening fine screen in the sludge flow.
Automated the digesters feed valves to balance the unit sludge feed flow.
Redirected the belt press filtrate water to the solids side of the plant to
reduce the ammonia concentration before entering the plants influent.
At this time, effective design and operational controls were introduced, and plant
performance improved consistently, thereby eliminating the need for capacity down
rating which was verified by the stress test which was performed to evaluate treatment
process capacity and efficiencies as a part of the continuous improvement of the
treatment plant for process optimization and maximization of flow through the plant.
The plants stress test was performed under the new standard operating procedures (SOP)
developed from the in-house evaluation thereby validating the SOPs and EPA’s Criteria
for capacity evaluation.
The results of the stress test is now presented with comparison to plant data in 2002
where operational problems were noticeable.
Table 2 - Stress test June thru August 2005 (Duplicate of Table 1)

Plant
Flow
Average 23.165
37.781
Max
Min

19.641

Inf. BOD5 Inf. TSS
(mg/L)
(mg/L)

Inf. NH3
(mg/L)

LBSAeration Flow
Eff.
Detention EQ.
CBOD5 Eff. TSS Eff. NH3 BOD
(mg/L) (mg/L)
37.8
(mg/L) entering (hrs)

220.140

224.721

16.884

1.413

1.366

0.164

42,177

5.32

38.43

587.000

614.000

23.000

3.730

4.500

2.220

106,155 6.20

52.33

62.000

116.000

10.700

0.590

0.000

0.042

12,444

32.74

3.88

Table 3 - Plant data from 2002

Plant
Flow
AVERAGE 25.446
MAX
66.004
MIN
19.019

Inf. BOD5
(mg/L)
322.58
644.00
103.000

Inf. TSS
(mg/L)
419.56
1600.00
54.000

Inf. NH3
(mg/L)
15.78
26.70
6.140

Eff.
CBOD5
(mg/L)
2.81
7.80
1.040

Eff. TSS
(mg/L)
3.06
11.70
0.800

Eff. NH3
(mg/L)
1.446
13.800
0.040

LBS-BOD
(entering)
68,087
170,909
17,778

Areation
Detention
6.58
8.53
2.458

Comparing the data from the 2005 stress test chart to the 2002 chart there was a 38
percent reduction in BOD entering (re-entering) the plant. The stress test substantiates
EPA’s finding and validates the corrective measures taken at the WMARSS plant to
bridge the gaps in communication, operations and process controls. The benefits from the
teamwork far out weigh the effort since subsequent to the performance improvements,
the plant’s electrical usage dropped by 4.5 million kilowatts annually. Presently, the
plant is much easier to operate and has dropped it’s midnight shift under normal
Texas American Water Works Association

April 2006

conditions (not including the pelletizing operations) but now operates an average of five
day a week compared to the average six day weeks which equates to a 20% reduction in
workload.
The major conclusion is that the plant can treat more than 20% design criteria permitted
flow/single stage nitrification loading effectively, which was established by the stress test
and the mathematical model.
STRESS TEST LOCATION AND METHODOLOGY
The site of the tests was a large 37.8 mgd Waste Water Treatment Plant designated the
Waco Metropolitan Area Regional Sewer System (WMARSS). The system serves as the
central plant to treat wastewater from member cities with a total population of about
175,000 residents: Waco, Bellmead, Hewitt, Woodway, Lacy-Lakeview and Robinson.
During the test, the stoichiometrical relationship of
o 1.1 lbs O2 / lb BOD, and
o 4.6 lbs O2 / lb ammonia
was maintained by adding diffusers in the 3 basins to meet the total aeration demands for
influent BOD, ammonia and additionally, the mixed liquor. Average flows and BOD to
these units varied from approximately 25 to 30 MGD and 250 mg/L respectively. This
approach provided loadings and detention times comparable to the future average flows
of 37.8 MGD under mean plus one standard deviation loads. Additional units were put
online to deal with wet weather events. The stress test was conducted by diverting the
entire flow proportionally through 3 of the 5 aeration basins and 3 of the 4 final clarifiers.
Since normal operation of the plant is with 5 aeration basins, in terms of true plant
capacity, a flow of 28 mgd through these 3 aeration basins during the stress test equates
to 22.68 mgd x 5 basins/3 basins = 37.8 mgd during normal operations (with 5 aeration
basins in service). Similarly, a flow of 28.35 mgd through 3 final clarifiers during this
stress test is equivalent to 37.8 mgd through 4 final clarifiers during normal operations.
A dye-tracer study is also in progress to analyze the hydraulic characteristics of the
clarifier and optimize its performance. On any given day, the stress tests lasted several
hours during periodic, relatively stable, flow conditions. System performance was
evaluated by measuring influent and effluent BOD, ammonia, and TSS.
SUMMARY OF THE RESULTS AND DISCUSSION
Graphs from the stress test data described previously are included below and support the
conclusions provided next. The BOD converted to pounds per 1,000 cubic feet of the
aeration unit is shown on Figure 4 and depicts fluctuations during the stress test. The
actual pounds of BOD entering the plant during the stress test is shown on Figure 5. The
influent BOD, TSS, ammonia and the flow equivalent is depicted on Figure 6 and
compared to the effluent loading on Figure 7. The y-axis range is much smaller for
Figure 7 than Figure 6 due to significant drop in influent values for measured parameters
Texas American Water Works Association

April 2006

during treatment. The effluent loading model shown on Figure 8, derived from
regression analysis of the stress test data shows consistency between the modeled and the
actual data. To obtain the model, regression analysis was performed and model equations
(Table 4) for effluent BOD, TSS and ammonia were derived as a function of influent
parameters to calculate the model plot data.

Figure 4 – BOD in lbs per 1,000 cubic feet of the Aeration Unit
A E R A T IO N LB S P E R 10 0 0 c uf t

100
90

Design Areation lbs
Aeration EQUIV. 37.8

80
70
60
50
40
30
20
10
0

Figure 5 – lbs of BOD entering the plant from the collection system
P o unds B O D e nt e ring pla nt

200000
180000

Design BOD entering lbs
BOD EQUIV. 37.8

160000
140000
120000
100000
80000
60000
40000
20000
0
Texas American Water Works Association

April 2006

Figure 6 – Influent BOD, TSS, Ammonia and Flow Equivalent
Influent Loading

Plant Effluent
Equivalent,
mgd
Inf. BOD5
(mg/L)
Inf. TSS
(mg/L)

Figure 7 – Effluent BOD, TSS, Ammonia, Aeration Unit Detention
Effluent Loading
6.5
6
5.5

BOD, mg/L

5
4.5

TSS, mg/L

4

Ammonia, mg/L

3.5
3

Detention, hrs

2.5
2
1
.5
1
0.5
0

T ime in D ays

7/
25

7/
18

7/
11

7/
4

6/
27

6/
20

6/
13

6/
6

Inf. NH3
(mg/L)

5/
30

5/
23

660
640
620
600
580
560
540
520
500
480
460
440
420
400
380
360
340
320
300
280
260
240
220
200
180
160
140
120
100
80
60
40
20
0
Texas American Water Works Association

April 2006

Figure 8 – Effluent Loading Plot Utilizing Model Equation Derived from Stress Test
Data
Effluent Loading Model

6.50

Model BOD, mg/L

6.00
5.50
5.00

Model TSS, mg/L

4.50
4.00
3.50

Model Effluent Ammonia, mg/L

3.00
2.50

Detention, hrs

2.00
1.50
1.00
0.50

3/9

3/7

3/5

3/3

3/1

2/28

2/26

2/24

2/22

2/20

2/18

2/16

2/14

2/12

2/8

2/10

2/6

2/4

2/2

1/31

1/29

1/27

1/25

1/23

1/21

1/19

1/17

1/15

1/13

1/9

1/11

1/7

1/5

1/3

1/1

0.00

Time in Days

Table 4 – Effluent Concentrations Model
Effluent Ammonia Prediction Model
NH3eff =

0.26728219604 + -0.0028310569243*MGD + -0.000041517607405*BODinf + -0.004190273598*NH3inf + 0.0000891630116TSSinf

MGD

BODinf

NH3inf

TSSinf

NH3eff

35.925

214

16.8

138

0.086

Effluent TSS Prediction Model

TSSeff = -3.732857302 + 0.17625048953*MGD + -0.0038607363102*BODinf + -0.010748551178*NH3inf + -0.00044110484113*TSSinf
MGD

BODinf

NH3inf

TSSinf

TSSeff

35.925

214

16.8

138

1.53

Effluent BOD Prediction Model

BODeff = -0.40045564232 + 0.017954249533*MGD + 0.0044010643804BODinf + 0.041444463095*NH3inf + -0.00232059867*TSSinf
MGD

BODinf

NH3inf

TSSinf

BODeff

35.925

214

16.8

138

1.56
Texas American Water Works Association

April 2006

CONCLUSION
The success of the stress test in demonstrating adequate capacity at the current permit
limit of 37.8 mgd plus 20% though full scale data collection and mathematical modeling,
is attributed to the introduction (over a 3-year period) of effective design and operational
controls prior to the stress test, thereby eliminating the need for a down-rating. These
performance improvements are demonstrated in decreasing effluent concentrations for
the parameters monitored shown in the charts below:
Figure 9 – Monthly Average Loading in 2002 (Before Performance Improvements)

100.000

90.000

80.000

70.000

60.000

50.000

40.000

30.000

20.000

10.000

0.000

1

2

3

4

5

6

7

8

9

10

11

12

24.210

0

25.528

28.297

24.675

23.496

24.635

22.171

21.740

27.110

24.723

32.636

Monthly average BOD/1000cuft

42.41284

0

53.15341 60.49677 57.65549 52.14599 39.71627 32.55432 28.03018 42.96607 43.96403 47.30601

Monthly Max bod/1000cuft

70.27615

0

85.79514 89.25527 89.38485 79.22628 98.65793 65.94503 60.58688 84.01449 70.9485 97.49092

Monthly average Flow

1. This chart indicates that the plant was receiving high average aeration loading (8
months over 40 lbs per 1000 cuft and all the monthly max lbs per 1000 cuft were
over 60 lbs)
2. The high aeration loadings were due to foul-ups at the plant. The chart
demonstrates the negative impacts of the plant’s deficient operational practices
leading to where the pounds of BOD originated from. This brings us back to the
EPA’s findings part B related to “foul-ups”, i.e., the WMARSS operational
practices did not effectively process the plants solids thus contaminating the
plant’s side stream flows and leading to high aeration loadings.
Texas American Water Works Association

April 2006

3. The plant was not constantly meeting permit limits, but the cause was not from
the influent loading; it was from the operational practices of the aeration process
and low Oxygen Transfer Efficiency.
Figure 10 – Monthly Average Loading in 2003 (During Performance Improvements)

120.000

100.000

80.000

60.000

40.000

20.000

0.000
Monthly average Flow
Monthly Average BOD/1000cuft
Monthly Max BOD/1000cuf

1.

2.

3.

1

2

3

4

5

6

7

8

9

10

11

12

28.143

32.262

30.102

23.200

22.899

22.839

21.359

21.750

22.514

24.214

22.041

21.053

60.351

71.424

42.637

31.847

33.881

28.086

28.075

23.503

32.923

29.170

25.854

40.141

97.00582 101.54838 57.216447 47.182381 94.029532 45.942959 37.09399 30.131747 45.788252 43.516275 59.324426 69.614266

In 2003 the plant was still receiving high max aeration loading but reduced from
2002 (4 months of high loadings in 2003 vs. 12 months of high loadings over 60
lbs per 1000 cuft in 2002)
The average aeration loading was consistent and lower than 2002, indicating the
plant personnel was properly processing the plants solids aided by implementation
of the use of polymer at the Dissolved Air Floatation unit.
The plant also sustained max loading conditions with only 4/5 of the aeration
capacity in service (5th aeration unit was not used) with no ammonia violations.

Improvements are more noticeable in Figure 10 which documents progressive
improvements in 2004:
1. This chart indicates in 2004 the plant was still receiving high average aeration
loading but reduced from 2002 (6 months in 2004 vs. 8 months over 40 lbs per
1000 cuft in 2002, and 8 months vs. 12 months over 60 lbs per 1000 cuft)
Texas American Water Works Association

April 2006

2. The high loading provided historical data that supports the 37.8 mgd rating, since
the plant effectively treated 61,668 annual average pounds of BOD, which is 80%
of the designed loading with only 4/5 of the aeration units in service.
3. So the plant was operating at 80% of its treatment capacity based on the original
design and confirmed the EPA’s Finding – A. The availability of an additional
20% capacity for emergencies over the 37.8 mgd as demonstrated in these charts
indicate the new SOP’s implemented in concert with mechanical enhancements
have brought the plant closer to it’s original design capacity.

Figure 11 – Monthly Average Loading in 2004 (After Performance Improvements)

Monthly Average Loading 2004
180.00

160.00

140.00

120.00

100.00

80.00

60.00

40.00

20.00

0.00
Monthly aver age F low

1

2

3

4

5

6

7

8

9

10

11

12

23.01

28.42

28.08

30.09

29.87

34.30

26.63

22.99

22.23

28.53

41.10

29.02

Monthly Average BOD/1000c uft 44.6077 49.2273 40.4055 45.4173 49.0104 43.4163 33.1035 35.1969 31.0623 36.3775 33.8909 38.4833
Monthly Max BOD/1000cuf

89.2565 71.5787 89.2401 165.456

103

63.6942 53.9691 62.1979 44.0665 49.2875 67.6113 58.8392

Significant improvement in influent loadings are observed when the data from the 3 years
are combined and reviewed side by side as in Figure 12. Following are the significant
Texas American Water Works Association

April 2006

observations that are deduced from the Annual Daily Average Influent Loadings shown
on Figure 12:
1. Controlling the side stream concentrations proved to improve the plants loadings
and 2003 was the more effective year.
2. There is one other side stream that is not included in the influent loading, the
Dryer units flow contains an average daily loading of 1,500lbs of ammonia that is
treated in the aeration basins.
3. This additional ammonia loading is a 30% increase over the plants influent
ammonia loading and this loading is not consistent, because the Dryer unit does
not run 24/7 it operates 24/5.
4. Controlling all side streams in-effect at the plant has proven to be a beneficial
operational practice that is continuing to enhance the operations and capacity of
the aeration units.

Figure 12 – Influent Loadings Decrease with Performance Improvements

Annual Daily Average Influent Loading
100000
80000
60000
40000
20000
0
2002

2003

2004

BO
D

68874

53175

61668

TS
S

88875

59844

72132

nh-3

3343

3889

3388

Significant improvement in Detention Times are observed when the data from the 3 years
are combined and reviewed side by side as in Figure 12. Following are the significant
observations that are deduced from the Annual Average Detention Times shown on
Figure 13:
Texas American Water Works Association

April 2006

1. Finally, in 2004 the plant was at 80% capacity with 80% treatment capacity in
service, 20% additional available for emergencies, at an average detention time of
5.66 hour for the 4 aeration units in service and the annual average flow was at
78% of the 37.8 mgd design flow.
2. Looking at one specific month, especially June of 2004, the plant was at 76%
capacity at 80% treatment capacity in service, at an average detention time of 5.2
hours at 90% of the 37.8 mgd design flow and still maintained effective treatment
at an effluent NH-3 average of 0.15mg/L.
3. Further improvement was observed in Feb 05, when the plant was at 80%
capacity at 80% treatment capacity in service, at an average detention time of 4.8
hours at 92% of the 37.8 mgd design flow with an effluent NH-3 of 0.13mg/L.

Figure 13 – Required Detention Times Decrease with Process Improvements

7.00
6.00
5.00
4.00
3.00
2.00
1.00
0.00

2002

2003

2004

H rs
ou

6.39

6.67

5.66

The significant drop in effluent ammonia, evident from the effectiveness of the anoxic
and aeration zones and control of plant side streams are depicted on Figure 14 which
compares effluent ammonia, TSS and BOD effluent loadings in 2002, 2003 and 2004.
Following highlights are derived from Figure 14:
1. The plant has performed at monthly average detention times of 4.8 hours, with
high aeration loading over 46 lbs/1000 cuft and still produced significantly low
effluent NH-3 concentrations.
Texas American Water Works Association

2.

3.

4.

April 2006

The year 2002 had many ammonia violations, but for the years 2003 and 2004
there were no ammonia violations and the average effluent NH-3 dropped from
1.446 to 0.153mg/L.
As mentioned before, the effluent quality is a result of the implementation of
adjusted operational procedures on the aeration units, increased oxygen transfer
efficiency and blower automation.
With the aeration unit operating efficiently biologically, the plant energy
consumption (kwh) reduced 17% from 2002 to 2003 and an additional 6% in
2004. The automation of the blowers once again confirms the EPA’s finding A
and B on true treatment capacity because of the consistent treatment effectiveness
observed during this period.

Figure 14 – Significant Drop in Effluent Ammonia with Improvements

A n nu al A verage E fflu en t L oad in g
5 .0 0 0
4 .0 0 0
3 .0 0 0
2 .0 0 0
1.0 0 0
0 .0 0 0
200 2

200 3

200 4

B OD

2 . 8 15

2. 638

2. 696

T SS

3. 059

2. 290

2 . 9 19

A mmo n i
a

1 .4 4 6

0. 307

0 . 15 3

More evidence of aeration basin effectiveness during the process improvements is
observed in Figure 15 which shows the correlation. This chart indicates that in February
2002 the effluent average concentrations dropped to the minimum levels. This is due to
the fact that this is the same month in which the WMARSS staff completed the
installation of additional diffusers to the aeration basins to improve aeration
characteristics for effective ammonia removal.
Texas American Water Works Association

April 2006

Figure 15 – Effluent Ammonia Monthly Max Day

Effluent Ammonia Monthly Max Day
14.000

12.000

10.000

8.000

6.000

4.000

2.000

0.000

1

2

3

4

5

6

7

8

9

10

11

12

2002

7.420

0.000

7.620

13.800

2.429

8.350

4.620

3.780

1.660

5.360

13.000

3.680

2003
2004
2005

4.1
1.89

8
4.1

2.31
0.978

0.2
0.548

1.12
1.64

0.239
2.1

0.185
1.63

0.277
0.54

0.492
0.146

1.87
2.1

2.69
0.57

0.109
0.32

1.2

0.057

0.91

0.657

3.8

0.57

0.327

2.2

Average effluent ammonia concentrations are shown on Figure 16 for 2002. This chart
also indicates that in February 2002 the effluent average concentrations dropped to the
minimum levels which is correlated to the completion of the installation of additional
diffusers at the aeration basins.
The conclusions discussed above only discussed average flow to the plant. Peak flow
management is being addressed by the following:
•
•
•

Peak Flow Storage Basin (one downstream of the highest I&I contributor)
I&I Control in process (2 major I&I sites at the E. Bank have been remedied)
Flow Diversion to Satellite Plant (Feasibility Study just completed)
Texas American Water Works Association

April 2006

Figure 16 – Effluent Ammonia Monthly Average

E fflu e n t A m m o n ia M o n th ly A v e ra g e
3 .0 0 0

2 .5 0 0

2 .0 0 0

1 .5 0 0

1 .0 0 0

0 .5 0 0

0 .0 0 0
2 00 2
2 00 3
2 00 4
2 00 5

0 .1 6

0 .1 8

0 .1

0 .1

0 .3 4

0 .1 2

0 .1 1

0 .3 7

2 .0 4 0
1 .1 9 2

0 .0 0 0
1 .0 2

1 .5 9 3
0 .4 2 9

2 .5 3 6
0 .0 7 6

0 .5 2 8
0 .1 9 4

2 .0 4 5
0 .0 7 4

1 .5 0 7
0 .0 6 9

0 .8 6 5
0 .0 8

0 .4 7 9
0 .0 7 7

1 .3 1 9
0 .1 2 8

1 .7 9 6
0 .4 0 3

1 .2 2 1
0 .0 5 9

0 .2 0 5
0 .1 5 5

0 .3 6 5
0 .1 7 9

0 .1 2 5
0 .1 0 4

0 .1 0 5
0 .1 0 2

0 .1 6 4
0 .3 4

0 .1 4 5
0 .1 2 1

0 .1 6 4
0 .1 1 4

0 .1 2 9
0 .3 6 5

0 .0 7 4

0 .1 5 5

0 .0 9 7

0 .1 1 6

Peak flows during wet weather events are being addressed with the construction of a peak
storage tank. The peak storage basin is important, since the limiting unit process in the
treatment train is chlorination. Since it is not cost effective to construct additional
chlorine contact basins, efforts are now focused on maximizing peak flow through
WMARSS by raising the walls of the existing chlorine contact chamber in conjunction
with the new peak storage basin construction. A preliminary hydraulic evaluation has
indicated that raising the walls of the chlorine contact chamber by approximately 1 ft is
feasible.

As part of the I&I Program, studies have been completed for two basins and evaluation is
in process to consider planning for rehabilitation.
The feasibility study of the satellite plant has been completed. The study recommends
two satellite plants at strategic locations to provide maximum benefit for flow diversion
and capture as well as promote the potential for water reuse while providing new
wastewater treatment infrastructure for selected cities in the watershed.
Output from Peak Flow Basin Modeling Calculations are shown on Figure 17.
Texas American Water Works Association

April 2006

Figure 17 – Peak Flow Basin Modeling Output Shown Graphically

ACKNOWLEDGEMENTS
The authors would like to thank all WMARSS employees for their tireless efforts in
making this stress test feasible.
REFERENCES
WMARSS Operation and Maintenance Manual, January 1985

When the flow into the peak flow basin is 155 mgd during wet weather events, a basin
size of 3.9 million gallons (MG) and 4.9 MG will be needed to maintain a plant influent
of 115 mgd and 83.2 mgd respectively. To lower the plant influent to the 83.2 mgd peak,
a peak flow basin of 5 MG is required. By raising the walls of the Chlorine Contact
Chamber, the flow into the plant can be increased, thereby reducing the required size of
the peak flow basin.
ACKNOWLEDGEMENTS
The authors would like to thank all WMARSS employees for their tireless efforts in
making this stress test feasible.
REFERENCES
WMARSS Operation and Maintenance Manual, January 1985

Mais conteúdo relacionado

Mais procurados

lecture on characterization 2015
lecture on characterization 2015lecture on characterization 2015
lecture on characterization 2015Manish Goyal
 
Biofiltration nitrification design overview
Biofiltration nitrification design overviewBiofiltration nitrification design overview
Biofiltration nitrification design overviewYounes Seven
 
Biological wastewater treatment processes
Biological wastewater treatment processesBiological wastewater treatment processes
Biological wastewater treatment processesArvind Kumar
 
Water pollution
Water pollution Water pollution
Water pollution mypptslide
 
ESTIMATION OF DO, BOD AND COD IN CANAL WATER SAMPLE
ESTIMATION OF DO, BOD AND COD IN CANAL WATER SAMPLEESTIMATION OF DO, BOD AND COD IN CANAL WATER SAMPLE
ESTIMATION OF DO, BOD AND COD IN CANAL WATER SAMPLESadia Rahat
 
BIOLOGICAL OXYGEN DEMAND
BIOLOGICAL OXYGEN DEMANDBIOLOGICAL OXYGEN DEMAND
BIOLOGICAL OXYGEN DEMANDHanu Pratap
 
Biochemical oxygen demand(bod)
Biochemical oxygen demand(bod)Biochemical oxygen demand(bod)
Biochemical oxygen demand(bod)Masud Alam Ansari
 
Sewagedisposalunit 8 by K R Thanki
Sewagedisposalunit 8 by K R ThankiSewagedisposalunit 8 by K R Thanki
Sewagedisposalunit 8 by K R ThankiKrunal Thanki
 
Biological Oxygen Demand
Biological Oxygen DemandBiological Oxygen Demand
Biological Oxygen Demandsharonmak
 
COD reduction of aromatic polluted waste water by Advanced Oxidation Process ...
COD reduction of aromatic polluted waste water by Advanced Oxidation Process ...COD reduction of aromatic polluted waste water by Advanced Oxidation Process ...
COD reduction of aromatic polluted waste water by Advanced Oxidation Process ...Wade Bitaraf
 
Advanced oxidation processes
Advanced oxidation processesAdvanced oxidation processes
Advanced oxidation processesMdRomzanAli1
 
advanced oxidation process
advanced oxidation processadvanced oxidation process
advanced oxidation processMahendheran Mech
 
Microbiology of trickling filters
Microbiology of trickling filtersMicrobiology of trickling filters
Microbiology of trickling filtersSubodh Mahanur
 
pollution monitoring and control methods, COD
pollution monitoring and control methods, COD pollution monitoring and control methods, COD
pollution monitoring and control methods, COD lethovik
 

Mais procurados (20)

lecture on characterization 2015
lecture on characterization 2015lecture on characterization 2015
lecture on characterization 2015
 
Ch 3 che of waste water
Ch 3 che of waste waterCh 3 che of waste water
Ch 3 che of waste water
 
Biofiltration nitrification design overview
Biofiltration nitrification design overviewBiofiltration nitrification design overview
Biofiltration nitrification design overview
 
Biological wastewater treatment processes
Biological wastewater treatment processesBiological wastewater treatment processes
Biological wastewater treatment processes
 
sewage determination by bod method
sewage determination by bod methodsewage determination by bod method
sewage determination by bod method
 
Water pollution
Water pollution Water pollution
Water pollution
 
Bod types
Bod typesBod types
Bod types
 
ESTIMATION OF DO, BOD AND COD IN CANAL WATER SAMPLE
ESTIMATION OF DO, BOD AND COD IN CANAL WATER SAMPLEESTIMATION OF DO, BOD AND COD IN CANAL WATER SAMPLE
ESTIMATION OF DO, BOD AND COD IN CANAL WATER SAMPLE
 
BIOLOGICAL OXYGEN DEMAND
BIOLOGICAL OXYGEN DEMANDBIOLOGICAL OXYGEN DEMAND
BIOLOGICAL OXYGEN DEMAND
 
Bod5 copy
Bod5 copyBod5 copy
Bod5 copy
 
Biochemical oxygen demand(bod)
Biochemical oxygen demand(bod)Biochemical oxygen demand(bod)
Biochemical oxygen demand(bod)
 
Sewagedisposalunit 8 by K R Thanki
Sewagedisposalunit 8 by K R ThankiSewagedisposalunit 8 by K R Thanki
Sewagedisposalunit 8 by K R Thanki
 
Biological Oxygen Demand
Biological Oxygen DemandBiological Oxygen Demand
Biological Oxygen Demand
 
Advanced oxidation
Advanced oxidationAdvanced oxidation
Advanced oxidation
 
COD reduction of aromatic polluted waste water by Advanced Oxidation Process ...
COD reduction of aromatic polluted waste water by Advanced Oxidation Process ...COD reduction of aromatic polluted waste water by Advanced Oxidation Process ...
COD reduction of aromatic polluted waste water by Advanced Oxidation Process ...
 
Advanced oxidation processes
Advanced oxidation processesAdvanced oxidation processes
Advanced oxidation processes
 
advanced oxidation process
advanced oxidation processadvanced oxidation process
advanced oxidation process
 
Chemical oxygen demand
Chemical oxygen demandChemical oxygen demand
Chemical oxygen demand
 
Microbiology of trickling filters
Microbiology of trickling filtersMicrobiology of trickling filters
Microbiology of trickling filters
 
pollution monitoring and control methods, COD
pollution monitoring and control methods, COD pollution monitoring and control methods, COD
pollution monitoring and control methods, COD
 

Destaque

Prof Graeme Dandy at the Landscape Science Cluster Seminar, May 2009
Prof Graeme Dandy at the Landscape Science Cluster Seminar, May 2009Prof Graeme Dandy at the Landscape Science Cluster Seminar, May 2009
Prof Graeme Dandy at the Landscape Science Cluster Seminar, May 2009pdalby
 
ICWES15 - Women in Engineering: Are we reinventing the Wheel? Presented by A/P
ICWES15 - Women in Engineering: Are we reinventing the Wheel?  Presented by A/PICWES15 - Women in Engineering: Are we reinventing the Wheel?  Presented by A/P
ICWES15 - Women in Engineering: Are we reinventing the Wheel? Presented by A/PEngineers Australia
 
Business Model Innovation For Water Services
Business Model Innovation For Water ServicesBusiness Model Innovation For Water Services
Business Model Innovation For Water ServicesHeiko Gebauer
 
Design of effluent treatment plant
Design of effluent treatment plantDesign of effluent treatment plant
Design of effluent treatment plantShankar Yelmame
 
Sewage treatment plant design calculation
Sewage treatment plant design calculationSewage treatment plant design calculation
Sewage treatment plant design calculationSharifah Ain
 

Destaque (6)

Prof Graeme Dandy at the Landscape Science Cluster Seminar, May 2009
Prof Graeme Dandy at the Landscape Science Cluster Seminar, May 2009Prof Graeme Dandy at the Landscape Science Cluster Seminar, May 2009
Prof Graeme Dandy at the Landscape Science Cluster Seminar, May 2009
 
ICWES15 - Women in Engineering: Are we reinventing the Wheel? Presented by A/P
ICWES15 - Women in Engineering: Are we reinventing the Wheel?  Presented by A/PICWES15 - Women in Engineering: Are we reinventing the Wheel?  Presented by A/P
ICWES15 - Women in Engineering: Are we reinventing the Wheel? Presented by A/P
 
Business Model Innovation For Water Services
Business Model Innovation For Water ServicesBusiness Model Innovation For Water Services
Business Model Innovation For Water Services
 
L 51 appurtennances (Valves)
L 51 appurtennances (Valves)L 51 appurtennances (Valves)
L 51 appurtennances (Valves)
 
Design of effluent treatment plant
Design of effluent treatment plantDesign of effluent treatment plant
Design of effluent treatment plant
 
Sewage treatment plant design calculation
Sewage treatment plant design calculationSewage treatment plant design calculation
Sewage treatment plant design calculation
 

Semelhante a 37.8 MGD Activated Sludge Wastewater Treatment Plant Field and Model Capacity Evaluation

Low Cost Anaerobic Treatment of Municipal Solid Waste Leachate
Low Cost Anaerobic Treatment of Municipal Solid Waste LeachateLow Cost Anaerobic Treatment of Municipal Solid Waste Leachate
Low Cost Anaerobic Treatment of Municipal Solid Waste Leachateiosrjce
 
Treatability study of cetp wastewater using physico chemical process-a case s...
Treatability study of cetp wastewater using physico chemical process-a case s...Treatability study of cetp wastewater using physico chemical process-a case s...
Treatability study of cetp wastewater using physico chemical process-a case s...eSAT Publishing House
 
Treatability study of cetp wastewater using physico chemical process-a case s...
Treatability study of cetp wastewater using physico chemical process-a case s...Treatability study of cetp wastewater using physico chemical process-a case s...
Treatability study of cetp wastewater using physico chemical process-a case s...eSAT Journals
 
The International Journal of Engineering and Science (The IJES)
The International Journal of Engineering and Science (The IJES)The International Journal of Engineering and Science (The IJES)
The International Journal of Engineering and Science (The IJES)theijes
 
IRJET - Design of Wastewater Treatment Plant in Nagpur City: By Adopting ...
IRJET -  	  Design of Wastewater Treatment Plant in Nagpur City: By Adopting ...IRJET -  	  Design of Wastewater Treatment Plant in Nagpur City: By Adopting ...
IRJET - Design of Wastewater Treatment Plant in Nagpur City: By Adopting ...IRJET Journal
 
IRJET- Characterisation of Grey Water and Treatment using Moving Bed Biof...
IRJET-  	  Characterisation of Grey Water and Treatment using Moving Bed Biof...IRJET-  	  Characterisation of Grey Water and Treatment using Moving Bed Biof...
IRJET- Characterisation of Grey Water and Treatment using Moving Bed Biof...IRJET Journal
 
Sewage water Treatment Using Moving Bed Bio-Film Reactor over SBR
Sewage water Treatment Using Moving Bed Bio-Film Reactor over SBRSewage water Treatment Using Moving Bed Bio-Film Reactor over SBR
Sewage water Treatment Using Moving Bed Bio-Film Reactor over SBRIRJET Journal
 
sewer treatment proposal.pptx
sewer treatment proposal.pptxsewer treatment proposal.pptx
sewer treatment proposal.pptxThushan9
 
Anaerobic-Aerobic Treatment of Sewage
Anaerobic-Aerobic Treatment of SewageAnaerobic-Aerobic Treatment of Sewage
Anaerobic-Aerobic Treatment of SewageAmit Christian
 
Performance Evaluation of Dairy Wastewater Treatment Plant
Performance Evaluation of Dairy Wastewater Treatment PlantPerformance Evaluation of Dairy Wastewater Treatment Plant
Performance Evaluation of Dairy Wastewater Treatment PlantIRJET Journal
 
IRJET- Effect of Biofilm Filling Rates, Various Cycles Duration and Organic L...
IRJET- Effect of Biofilm Filling Rates, Various Cycles Duration and Organic L...IRJET- Effect of Biofilm Filling Rates, Various Cycles Duration and Organic L...
IRJET- Effect of Biofilm Filling Rates, Various Cycles Duration and Organic L...IRJET Journal
 
Ammonia Recovery using membrane distillation
Ammonia Recovery using membrane distillationAmmonia Recovery using membrane distillation
Ammonia Recovery using membrane distillationChristos Charisiadis
 
Analysis for predicting the Input Interactions of HBF Performance at -10 μm P...
Analysis for predicting the Input Interactions of HBF Performance at -10 μm P...Analysis for predicting the Input Interactions of HBF Performance at -10 μm P...
Analysis for predicting the Input Interactions of HBF Performance at -10 μm P...journal ijrtem
 
Kikale_poster_RMWEA 2016
Kikale_poster_RMWEA 2016Kikale_poster_RMWEA 2016
Kikale_poster_RMWEA 2016panukikale
 

Semelhante a 37.8 MGD Activated Sludge Wastewater Treatment Plant Field and Model Capacity Evaluation (20)

Low Cost Anaerobic Treatment of Municipal Solid Waste Leachate
Low Cost Anaerobic Treatment of Municipal Solid Waste LeachateLow Cost Anaerobic Treatment of Municipal Solid Waste Leachate
Low Cost Anaerobic Treatment of Municipal Solid Waste Leachate
 
Treatability study of cetp wastewater using physico chemical process-a case s...
Treatability study of cetp wastewater using physico chemical process-a case s...Treatability study of cetp wastewater using physico chemical process-a case s...
Treatability study of cetp wastewater using physico chemical process-a case s...
 
Treatability study of cetp wastewater using physico chemical process-a case s...
Treatability study of cetp wastewater using physico chemical process-a case s...Treatability study of cetp wastewater using physico chemical process-a case s...
Treatability study of cetp wastewater using physico chemical process-a case s...
 
The International Journal of Engineering and Science (The IJES)
The International Journal of Engineering and Science (The IJES)The International Journal of Engineering and Science (The IJES)
The International Journal of Engineering and Science (The IJES)
 
IRJET - Design of Wastewater Treatment Plant in Nagpur City: By Adopting ...
IRJET -  	  Design of Wastewater Treatment Plant in Nagpur City: By Adopting ...IRJET -  	  Design of Wastewater Treatment Plant in Nagpur City: By Adopting ...
IRJET - Design of Wastewater Treatment Plant in Nagpur City: By Adopting ...
 
IRJET- Characterisation of Grey Water and Treatment using Moving Bed Biof...
IRJET-  	  Characterisation of Grey Water and Treatment using Moving Bed Biof...IRJET-  	  Characterisation of Grey Water and Treatment using Moving Bed Biof...
IRJET- Characterisation of Grey Water and Treatment using Moving Bed Biof...
 
Sewage water Treatment Using Moving Bed Bio-Film Reactor over SBR
Sewage water Treatment Using Moving Bed Bio-Film Reactor over SBRSewage water Treatment Using Moving Bed Bio-Film Reactor over SBR
Sewage water Treatment Using Moving Bed Bio-Film Reactor over SBR
 
SENIOR DESIGN PAPER
SENIOR DESIGN PAPERSENIOR DESIGN PAPER
SENIOR DESIGN PAPER
 
JASER05025
JASER05025JASER05025
JASER05025
 
L43056874
L43056874L43056874
L43056874
 
sewer treatment proposal.pptx
sewer treatment proposal.pptxsewer treatment proposal.pptx
sewer treatment proposal.pptx
 
Anaerobic-Aerobic Treatment of Sewage
Anaerobic-Aerobic Treatment of SewageAnaerobic-Aerobic Treatment of Sewage
Anaerobic-Aerobic Treatment of Sewage
 
20120140504001
2012014050400120120140504001
20120140504001
 
Mbbr
MbbrMbbr
Mbbr
 
Performance Evaluation of Dairy Wastewater Treatment Plant
Performance Evaluation of Dairy Wastewater Treatment PlantPerformance Evaluation of Dairy Wastewater Treatment Plant
Performance Evaluation of Dairy Wastewater Treatment Plant
 
IRJET- Effect of Biofilm Filling Rates, Various Cycles Duration and Organic L...
IRJET- Effect of Biofilm Filling Rates, Various Cycles Duration and Organic L...IRJET- Effect of Biofilm Filling Rates, Various Cycles Duration and Organic L...
IRJET- Effect of Biofilm Filling Rates, Various Cycles Duration and Organic L...
 
Ge remove oxygen
Ge   remove oxygenGe   remove oxygen
Ge remove oxygen
 
Ammonia Recovery using membrane distillation
Ammonia Recovery using membrane distillationAmmonia Recovery using membrane distillation
Ammonia Recovery using membrane distillation
 
Analysis for predicting the Input Interactions of HBF Performance at -10 μm P...
Analysis for predicting the Input Interactions of HBF Performance at -10 μm P...Analysis for predicting the Input Interactions of HBF Performance at -10 μm P...
Analysis for predicting the Input Interactions of HBF Performance at -10 μm P...
 
Kikale_poster_RMWEA 2016
Kikale_poster_RMWEA 2016Kikale_poster_RMWEA 2016
Kikale_poster_RMWEA 2016
 

Mais de njcnews777

Capping Options for a Low-Level Radioactive Material Storage Pile Formerly Ut...
Capping Options for a Low-Level Radioactive Material Storage Pile Formerly Ut...Capping Options for a Low-Level Radioactive Material Storage Pile Formerly Ut...
Capping Options for a Low-Level Radioactive Material Storage Pile Formerly Ut...njcnews777
 
Streamlining Cleanup Decisions at the Filled Coal Ash Pond Oak Ridge Tennessee
Streamlining Cleanup Decisions at the Filled Coal Ash Pond Oak Ridge TennesseeStreamlining Cleanup Decisions at the Filled Coal Ash Pond Oak Ridge Tennessee
Streamlining Cleanup Decisions at the Filled Coal Ash Pond Oak Ridge Tennesseenjcnews777
 
Preventing Red Water Problems Without Removing Iron and Manganese. Iron and ...
Preventing Red Water Problems Without Removing Iron and Manganese.  Iron and ...Preventing Red Water Problems Without Removing Iron and Manganese.  Iron and ...
Preventing Red Water Problems Without Removing Iron and Manganese. Iron and ...njcnews777
 
Anoxic Selector Single Stage Nitrification Process Waste Water Plant Theory a...
Anoxic Selector Single Stage Nitrification Process Waste Water Plant Theory a...Anoxic Selector Single Stage Nitrification Process Waste Water Plant Theory a...
Anoxic Selector Single Stage Nitrification Process Waste Water Plant Theory a...njcnews777
 
Turning Waste Into Revenue Through BioTransformation
Turning Waste Into Revenue Through BioTransformationTurning Waste Into Revenue Through BioTransformation
Turning Waste Into Revenue Through BioTransformationnjcnews777
 
Industrial Water Treatment Optimization at Kelly Air Force Base
Industrial Water Treatment Optimization at Kelly Air Force BaseIndustrial Water Treatment Optimization at Kelly Air Force Base
Industrial Water Treatment Optimization at Kelly Air Force Basenjcnews777
 
Water Reuse: Technologies for Industrial and Municipal Applications
Water Reuse: Technologies for Industrial and Municipal ApplicationsWater Reuse: Technologies for Industrial and Municipal Applications
Water Reuse: Technologies for Industrial and Municipal Applicationsnjcnews777
 
Cross Flow or Tangential Flow Membrane Filtration (TFF) to Enable High Solids...
Cross Flow or Tangential Flow Membrane Filtration (TFF) to Enable High Solids...Cross Flow or Tangential Flow Membrane Filtration (TFF) to Enable High Solids...
Cross Flow or Tangential Flow Membrane Filtration (TFF) to Enable High Solids...njcnews777
 

Mais de njcnews777 (8)

Capping Options for a Low-Level Radioactive Material Storage Pile Formerly Ut...
Capping Options for a Low-Level Radioactive Material Storage Pile Formerly Ut...Capping Options for a Low-Level Radioactive Material Storage Pile Formerly Ut...
Capping Options for a Low-Level Radioactive Material Storage Pile Formerly Ut...
 
Streamlining Cleanup Decisions at the Filled Coal Ash Pond Oak Ridge Tennessee
Streamlining Cleanup Decisions at the Filled Coal Ash Pond Oak Ridge TennesseeStreamlining Cleanup Decisions at the Filled Coal Ash Pond Oak Ridge Tennessee
Streamlining Cleanup Decisions at the Filled Coal Ash Pond Oak Ridge Tennessee
 
Preventing Red Water Problems Without Removing Iron and Manganese. Iron and ...
Preventing Red Water Problems Without Removing Iron and Manganese.  Iron and ...Preventing Red Water Problems Without Removing Iron and Manganese.  Iron and ...
Preventing Red Water Problems Without Removing Iron and Manganese. Iron and ...
 
Anoxic Selector Single Stage Nitrification Process Waste Water Plant Theory a...
Anoxic Selector Single Stage Nitrification Process Waste Water Plant Theory a...Anoxic Selector Single Stage Nitrification Process Waste Water Plant Theory a...
Anoxic Selector Single Stage Nitrification Process Waste Water Plant Theory a...
 
Turning Waste Into Revenue Through BioTransformation
Turning Waste Into Revenue Through BioTransformationTurning Waste Into Revenue Through BioTransformation
Turning Waste Into Revenue Through BioTransformation
 
Industrial Water Treatment Optimization at Kelly Air Force Base
Industrial Water Treatment Optimization at Kelly Air Force BaseIndustrial Water Treatment Optimization at Kelly Air Force Base
Industrial Water Treatment Optimization at Kelly Air Force Base
 
Water Reuse: Technologies for Industrial and Municipal Applications
Water Reuse: Technologies for Industrial and Municipal ApplicationsWater Reuse: Technologies for Industrial and Municipal Applications
Water Reuse: Technologies for Industrial and Municipal Applications
 
Cross Flow or Tangential Flow Membrane Filtration (TFF) to Enable High Solids...
Cross Flow or Tangential Flow Membrane Filtration (TFF) to Enable High Solids...Cross Flow or Tangential Flow Membrane Filtration (TFF) to Enable High Solids...
Cross Flow or Tangential Flow Membrane Filtration (TFF) to Enable High Solids...
 

Último

Scanning the Internet for External Cloud Exposures via SSL Certs
Scanning the Internet for External Cloud Exposures via SSL CertsScanning the Internet for External Cloud Exposures via SSL Certs
Scanning the Internet for External Cloud Exposures via SSL CertsRizwan Syed
 
TeamStation AI System Report LATAM IT Salaries 2024
TeamStation AI System Report LATAM IT Salaries 2024TeamStation AI System Report LATAM IT Salaries 2024
TeamStation AI System Report LATAM IT Salaries 2024Lonnie McRorey
 
WordPress Websites for Engineers: Elevate Your Brand
WordPress Websites for Engineers: Elevate Your BrandWordPress Websites for Engineers: Elevate Your Brand
WordPress Websites for Engineers: Elevate Your Brandgvaughan
 
Are Multi-Cloud and Serverless Good or Bad?
Are Multi-Cloud and Serverless Good or Bad?Are Multi-Cloud and Serverless Good or Bad?
Are Multi-Cloud and Serverless Good or Bad?Mattias Andersson
 
"ML in Production",Oleksandr Bagan
"ML in Production",Oleksandr Bagan"ML in Production",Oleksandr Bagan
"ML in Production",Oleksandr BaganFwdays
 
Take control of your SAP testing with UiPath Test Suite
Take control of your SAP testing with UiPath Test SuiteTake control of your SAP testing with UiPath Test Suite
Take control of your SAP testing with UiPath Test SuiteDianaGray10
 
TrustArc Webinar - How to Build Consumer Trust Through Data Privacy
TrustArc Webinar - How to Build Consumer Trust Through Data PrivacyTrustArc Webinar - How to Build Consumer Trust Through Data Privacy
TrustArc Webinar - How to Build Consumer Trust Through Data PrivacyTrustArc
 
New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024BookNet Canada
 
What's New in Teams Calling, Meetings and Devices March 2024
What's New in Teams Calling, Meetings and Devices March 2024What's New in Teams Calling, Meetings and Devices March 2024
What's New in Teams Calling, Meetings and Devices March 2024Stephanie Beckett
 
The Fit for Passkeys for Employee and Consumer Sign-ins: FIDO Paris Seminar.pptx
The Fit for Passkeys for Employee and Consumer Sign-ins: FIDO Paris Seminar.pptxThe Fit for Passkeys for Employee and Consumer Sign-ins: FIDO Paris Seminar.pptx
The Fit for Passkeys for Employee and Consumer Sign-ins: FIDO Paris Seminar.pptxLoriGlavin3
 
Commit 2024 - Secret Management made easy
Commit 2024 - Secret Management made easyCommit 2024 - Secret Management made easy
Commit 2024 - Secret Management made easyAlfredo García Lavilla
 
How to write a Business Continuity Plan
How to write a Business Continuity PlanHow to write a Business Continuity Plan
How to write a Business Continuity PlanDatabarracks
 
Streamlining Python Development: A Guide to a Modern Project Setup
Streamlining Python Development: A Guide to a Modern Project SetupStreamlining Python Development: A Guide to a Modern Project Setup
Streamlining Python Development: A Guide to a Modern Project SetupFlorian Wilhelm
 
The Ultimate Guide to Choosing WordPress Pros and Cons
The Ultimate Guide to Choosing WordPress Pros and ConsThe Ultimate Guide to Choosing WordPress Pros and Cons
The Ultimate Guide to Choosing WordPress Pros and ConsPixlogix Infotech
 
Connect Wave/ connectwave Pitch Deck Presentation
Connect Wave/ connectwave Pitch Deck PresentationConnect Wave/ connectwave Pitch Deck Presentation
Connect Wave/ connectwave Pitch Deck PresentationSlibray Presentation
 
Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024BookNet Canada
 
SIP trunking in Janus @ Kamailio World 2024
SIP trunking in Janus @ Kamailio World 2024SIP trunking in Janus @ Kamailio World 2024
SIP trunking in Janus @ Kamailio World 2024Lorenzo Miniero
 
Merck Moving Beyond Passwords: FIDO Paris Seminar.pptx
Merck Moving Beyond Passwords: FIDO Paris Seminar.pptxMerck Moving Beyond Passwords: FIDO Paris Seminar.pptx
Merck Moving Beyond Passwords: FIDO Paris Seminar.pptxLoriGlavin3
 
Developer Data Modeling Mistakes: From Postgres to NoSQL
Developer Data Modeling Mistakes: From Postgres to NoSQLDeveloper Data Modeling Mistakes: From Postgres to NoSQL
Developer Data Modeling Mistakes: From Postgres to NoSQLScyllaDB
 

Último (20)

Scanning the Internet for External Cloud Exposures via SSL Certs
Scanning the Internet for External Cloud Exposures via SSL CertsScanning the Internet for External Cloud Exposures via SSL Certs
Scanning the Internet for External Cloud Exposures via SSL Certs
 
TeamStation AI System Report LATAM IT Salaries 2024
TeamStation AI System Report LATAM IT Salaries 2024TeamStation AI System Report LATAM IT Salaries 2024
TeamStation AI System Report LATAM IT Salaries 2024
 
WordPress Websites for Engineers: Elevate Your Brand
WordPress Websites for Engineers: Elevate Your BrandWordPress Websites for Engineers: Elevate Your Brand
WordPress Websites for Engineers: Elevate Your Brand
 
Are Multi-Cloud and Serverless Good or Bad?
Are Multi-Cloud and Serverless Good or Bad?Are Multi-Cloud and Serverless Good or Bad?
Are Multi-Cloud and Serverless Good or Bad?
 
"ML in Production",Oleksandr Bagan
"ML in Production",Oleksandr Bagan"ML in Production",Oleksandr Bagan
"ML in Production",Oleksandr Bagan
 
Take control of your SAP testing with UiPath Test Suite
Take control of your SAP testing with UiPath Test SuiteTake control of your SAP testing with UiPath Test Suite
Take control of your SAP testing with UiPath Test Suite
 
TrustArc Webinar - How to Build Consumer Trust Through Data Privacy
TrustArc Webinar - How to Build Consumer Trust Through Data PrivacyTrustArc Webinar - How to Build Consumer Trust Through Data Privacy
TrustArc Webinar - How to Build Consumer Trust Through Data Privacy
 
New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
 
What's New in Teams Calling, Meetings and Devices March 2024
What's New in Teams Calling, Meetings and Devices March 2024What's New in Teams Calling, Meetings and Devices March 2024
What's New in Teams Calling, Meetings and Devices March 2024
 
The Fit for Passkeys for Employee and Consumer Sign-ins: FIDO Paris Seminar.pptx
The Fit for Passkeys for Employee and Consumer Sign-ins: FIDO Paris Seminar.pptxThe Fit for Passkeys for Employee and Consumer Sign-ins: FIDO Paris Seminar.pptx
The Fit for Passkeys for Employee and Consumer Sign-ins: FIDO Paris Seminar.pptx
 
Commit 2024 - Secret Management made easy
Commit 2024 - Secret Management made easyCommit 2024 - Secret Management made easy
Commit 2024 - Secret Management made easy
 
How to write a Business Continuity Plan
How to write a Business Continuity PlanHow to write a Business Continuity Plan
How to write a Business Continuity Plan
 
Streamlining Python Development: A Guide to a Modern Project Setup
Streamlining Python Development: A Guide to a Modern Project SetupStreamlining Python Development: A Guide to a Modern Project Setup
Streamlining Python Development: A Guide to a Modern Project Setup
 
The Ultimate Guide to Choosing WordPress Pros and Cons
The Ultimate Guide to Choosing WordPress Pros and ConsThe Ultimate Guide to Choosing WordPress Pros and Cons
The Ultimate Guide to Choosing WordPress Pros and Cons
 
Connect Wave/ connectwave Pitch Deck Presentation
Connect Wave/ connectwave Pitch Deck PresentationConnect Wave/ connectwave Pitch Deck Presentation
Connect Wave/ connectwave Pitch Deck Presentation
 
DMCC Future of Trade Web3 - Special Edition
DMCC Future of Trade Web3 - Special EditionDMCC Future of Trade Web3 - Special Edition
DMCC Future of Trade Web3 - Special Edition
 
Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
 
SIP trunking in Janus @ Kamailio World 2024
SIP trunking in Janus @ Kamailio World 2024SIP trunking in Janus @ Kamailio World 2024
SIP trunking in Janus @ Kamailio World 2024
 
Merck Moving Beyond Passwords: FIDO Paris Seminar.pptx
Merck Moving Beyond Passwords: FIDO Paris Seminar.pptxMerck Moving Beyond Passwords: FIDO Paris Seminar.pptx
Merck Moving Beyond Passwords: FIDO Paris Seminar.pptx
 
Developer Data Modeling Mistakes: From Postgres to NoSQL
Developer Data Modeling Mistakes: From Postgres to NoSQLDeveloper Data Modeling Mistakes: From Postgres to NoSQL
Developer Data Modeling Mistakes: From Postgres to NoSQL
 

37.8 MGD Activated Sludge Wastewater Treatment Plant Field and Model Capacity Evaluation

  • 1. Texas American Water Works Association April 2006 ACTIVATED SLUDGE PLANT FIELD & MODEL CAPACITY EVALUATION Ricky Garrett, PE, Mike Jupe (TCEQ “A” Certified Wastewater Operator) and Daniel Christodoss, PE, PhD City of Waco Water Utility Services P.O. Box 2570 Waco, TX 76702-2570 ABSTRACT This paper presents results from the model capacity evaluation of an activated sludge plant at a large municipal wastewater treatment plant. The plant capacity evaluation (stress test) was performed to evaluate treatment process capacity and efficiencies as a part of the continuous improvement of the treatment plant for process optimization and maximization of flow through the plant. The stress test was performed for 3 months mainly during dry weather with a few wet weather events that caused equivalent inflows higher than the existing rating of 37.8 mgd. The stress test was conducted by diverting the entire flow proportionally through 3 of the 5 aeration basins and 3 of the 4 final clarifiers. Since normal operation of the plant is with 5 aeration basins, in terms of true plant capacity, a flow of 28 mgd through these 3 aeration basins during the stress test equates to 22.68 mgd x 5 basins/3 basins = 37.8 mgd during normal operations (with 5 aeration basins in service). Similarly, a flow of 28.35 mgd through 3 final clarifiers during this stress test is equivalent to 37.8 mgd through 4 final clarifiers during normal operations. On any given day, the stress tests lasted several hours during periodic, relatively stable, flow conditions. System performance was evaluated by measuring influent and effluent BOD, ammonia, and TSS. The major conclusion is that the plant can treat more than 20% of current permitted flow effectively, which was established by the stress test and the mathematical model as shown in Tables 1. Table 1 - Stress test June thru August 2005 Plant Flow (mgd) Aeration Flow EQUIV Inf. BOD5 Inf. TSS Inf. NH3 Eff. CBOD5 Eff. TSS Eff. NH3 LBS-BOD Detention, (mgd) (mg/L) (mg/L) (mg/L) (mg/L) (mg/L) (mg/L) (entering) (hrs) Average 23.165 37.781 Max 38.43 220.140 224.721 16.884 1.413 1.366 0.164 42,177 5.32 52.33 587.000 614.000 23.000 3.730 4.500 2.220 106,155 6.20 19.641 32.74 62.000 116.000 10.700 0.590 0.000 0.042 12,444 3.88 Min
  • 2. Texas American Water Works Association April 2006 KEYWORDS activated sludge, aeration, stress test, model capacity, final clarifiers, waste water treatment, nitrification, biological oxygen demand, total suspended solids, ammonia, anoxic zone, oxygen transfer, operations and maintenance, treated effluent INTRODUCTION This field and model capacity evaluation was performed at a time when the plant capacity was being down-rated from 37.8 MGD down to 31 MGD. The potential for down-rating raised the following concerns: • • • Significant loss in capacity Funding needed to construct additional facilities ($40-$70 million) Timing for the downgrade invoking an unrealistic accelerated schedule The operational history of the plant that led to the potential down-rating is described below. PLANT COMPONENTS Features of the WMARSS system include: 1. Primary clarifiers capable of efficient capture of suspended solids, grit and scum from plant inflows including high short term peak flows. 2. Biological activated sludge treatment using: a) 5 aeration basins which are designed to facilitate operation in plug flow with tapered aeration, step aeration (step feeding), or complete mix. The aeration basins produce a waste activated sludge which is as easy to separate and dispose of as possible b) Final clarifiers capable of removing activated sludge and scum promptly and efficiently, and dividing it into desired return activated sludge (RAS) and Waste Activated Sludge (WAS) flows 3. Thickeners for combined primary and waste activated sludges, with DAF thickeners chosen specifically for the mixed sludge involved. 4. Two-stage anaerobic digestion of mixed sludges for effective stabilization and yield of by-product methane. 5. Two Engine/Generators capable of producing half the plant’s power needs. 6. Anaerobically digested sludge filter pressed to a cake of 18% solids. The cake is heat dried and pelletized (with heat from the furnace) into a commercial sized pellet with nutritional and soil conditioning value at slow release. The methane gas from the digestors powers the furnace to the drier unit and is blended with natural gas to conserve energy.
  • 3. Texas American Water Works Association April 2006 OPERATIONAL HISTORY The conventional activated sludge Wastewater Treatment Plant for the Waco Metropolitan Area Regional Sewerage System (WMARSS): • • • • • was constructed in 1983 and started operation in 1984 under an operating permit which restricted flow to a maximum 30-day average of 37.8 MGD daily average, 47.9 mgd daily max, 83.2 mgd, 2 hour peak flow, at treated effluent limits of 20 mg/L BOD, and 20mg/L TSS. won an EPA award in 1993, for plants treating 10 mgd and higher had a change in the effluent limits in 1995 to 10 mg/L BOD, 15 mg/L TSS and 3 mg/L NH-3 single stage nitirification at which time, a pellet drying facility was added to the plant to treat digested sludge. When the ammonia permit was issued, the fifth aeration basin was constructed to provide the biological treatment and retain the 37.8 mgd annual average influent, at 250mg/L BOD and 250mg/L TSS. was being considered for down-rating in 2000-2004 based on performance issues compounded by design and operational constraints EPA’s DEFINITION OF PLANT CAPACITY True capacity of a plant is a function of design, process optimization and management. In the original 1984 Operations and Maintenance (O&M) Manual, EPA’s findings on 287 plants were quoted as follows: a) Plant performance depends on the quality of the original design, the caliber of the plant’s administrators, the effectiveness of the operators and the quality of the maintenance program. b) Every treatment plant has its own performance-limiting problems (foulups). This was found whether or not a plant was meeting permit. And if these problems can be sorted out and defined, then they can be cured, or made less severe, or (if nothing else) watched constantly. DESIGN AND OPERATIONAL CONSTRAINTS EPA’s findings cited above held true for the WMARSS plant. In 1998, the following operational problems were identified: a) There were inadequacies in communication between administration and plant personnel.
  • 4. Texas American Water Works Association April 2006 b) The plant side steams had adverse affects on the entire treatment train as a result of inadequate standard operating procedures to control the effects of the single stage nitrification cycle and the pellet building wastewater discharge. At this time, the WMARSS staff started evaluating the treatment system with EPA’s findings in mind. The evaluation resulting in the following findings: 1. The oxygen transfer efficiency in the aeration basins was inadequate to supply the oxygen needed for single stage nitrification. The bubbles were coarse and there was not enough volume to achieve the desired treatment. Following graph depicts how bubble size affects oxygen transfer. Figure 1 – Bubble Size vs. Oxygen Transfer Efficiency 2. The anoxic zones were not mixed nor utilized effectively to reduce the oxygen demand through BOD reduction utilizing nitrate as the substrate and alkalinity savings. Following is an introduction to nitrification and de-nitrification for clarification. Nitrogen appears in organic wastes in various forms. In wastewater, four types of nitrogen are common: organic nitrogen, ammonia nitrogen, nitrite nitrogen, and nitrate nitrogen. These different forms constitute the total nitrogen content. The predominant forms of nitrogen in wastewater are organic nitrogen and ammonia (NH3). Organic nitrogen is converted to ammonia in the first step of the nitrogen cycle. In order to remove nitrogen from wastewater, ammonia must be oxidized to nitrate (NO3). This process is commonly referred to as nitrification. An oxic environment must be maintained for sufficient period of time to promote nitrification. The overall reaction of nitrification is: NH3 NO2 NO3 Oxic conditions are maintained by a number of aerators. In the presence of dissolved oxygen, the microorganisms convert stored BOD (biochemical oxygen demand) to CO2, water, and increased cell mass. Biological nitrification occurs, producing nitrite in an intermediate step and ultimately producing nitrate. Following nitrification, nitrogen can be removed from the wastewater by reducing the nitrate to nitrogen gas (N2), which is released to the atmosphere. This process is commonly referred to as denitrification. Denitrification requires anoxic conditions, as well as an organic carbon source, to proceed.
  • 5. Texas American Water Works Association NO3nitrate NO2 nitrite April 2006 NO nitric oxide N2O nitrous oxide N2 nitrogen gas Introducing an anoxic zone into the flow scheme provides de-nitrification of nitrate in the return activated sludge from the clarifier. In this zone, operated with little to no dissolved oxygen (DO), the endogenous oxygen demand of mixed liquor suspended solids (MLSS) plus the carryover of BOD (biochemical oxygen demand) from the primary clarifier causes de-nitrification of the nitrate produced in the aerobic zone. During anoxic conditions, dissolved oxygen is not available to the microorganisms for respiration. Because of this, the oxygen molecules are stripped from the nitrate, causing the production of nitrogen gas (N2) . Carbon dioxide and water are also produced in the process, which results from the degradation of BOD. In addition, a portion of the alkalinity consumed during the nitrification process is restored through the denitrification process. When the mixed liquor flows to the secondary anoxic zones, there will be a relatively small concentration of extra cellular BOD in the wastewater. However, de-nitrification will still proceed since the microorganisms utilize internal storage products to reduce nitrate (endogenous de-nitrification). Secondary anoxic zones are not present at WMARSS. Figure 2 – Process Schematics Showing Anoxic-Aeration and Clarifier Sequence Figure 3 – System Schematics Influent to Effluent 3. The higher waste concentrations from the single stage nitrification had tendencies to overload the subsequent sludge thickening and anaerobic digestion process.
  • 6. Texas American Water Works Association April 2006 4. The inadequately controlled sludge thickening process adversely affected the single stage nitrification process and anaerobic digester process. 5. The pelletizing process discharged ammonia concentrations that caused fluctuation in the nitrification process, oxygen demand, chlorine demand and sulfur dioxide demand. 6. Inadequate screening of the plants influent and sludge flow adversely affected the sludge thickening process, digestion process and the pelletizing process. The above six factors influence plant chemistry from an average BOD concentration of 250 mg/l to 350 mg/L, i.e. adding a 28 percent increase in plant BOD loading. PERFORMANCE IMPROVEMENTS To transition from re-treating plant foul-ups and collection system waste, the following improvements were made to optimize plant performance: • Secondary Treatment Improvements. Increased the Oxygen Transfer Efficiency in four aeration basins. Automated the aeration zone valves to maintain the zones set D.O. level. Automated three of the blowers to start-up with adjustable loading to satisfy the biological oxygen demand. Installed Cipolletti weir aeration influent weirs to control and balance the aeration feed rate. Improved the anoxic zone mixing efficiency. Operated four aeration basins year round to obtain an average five-hour detention time. Maintained a minimum 1.5 mg/L D.O. in first aeration zone to obtain optimal nitrifying growth rate. Maintained a maximum .3 mg/L D.O. in anoxic zone to obtain optimal denitrifying growth rate. Adjusted the aeration influent Cipolletti weir daily to balance and control the aeration basins feed rate. Adjusted the wasting rates by the 10 percent rule. Adjusted the activated sludge return rates lower to control the basins F/M ratio, pounds of nitrates to the anoxic zone with longer detention times. • Solids Processing Improvements. Started feeding polymer to the D.A.F. to increase the capture rate of the unit, thus lowering the sludge flow to the Digesters that increased their detention time along with lowering the BTU needed to heat the units and lowered the run time of the Dryer unit. Redirected the D.A.F underflow to the solids side final clarifier underflow wet well, instead of the plants under drains. Started up the second solids side final clarifier underflow pump to limit the amount of solids entering the plant under drains.
  • 7. Texas American Water Works Association April 2006 Started one of the two side stream trickling filters to reduces the BOD reentering the plants influent. Installed a two-millimeter opening fine screen in the sludge flow. Automated the digesters feed valves to balance the unit sludge feed flow. Redirected the belt press filtrate water to the solids side of the plant to reduce the ammonia concentration before entering the plants influent. At this time, effective design and operational controls were introduced, and plant performance improved consistently, thereby eliminating the need for capacity down rating which was verified by the stress test which was performed to evaluate treatment process capacity and efficiencies as a part of the continuous improvement of the treatment plant for process optimization and maximization of flow through the plant. The plants stress test was performed under the new standard operating procedures (SOP) developed from the in-house evaluation thereby validating the SOPs and EPA’s Criteria for capacity evaluation. The results of the stress test is now presented with comparison to plant data in 2002 where operational problems were noticeable. Table 2 - Stress test June thru August 2005 (Duplicate of Table 1) Plant Flow Average 23.165 37.781 Max Min 19.641 Inf. BOD5 Inf. TSS (mg/L) (mg/L) Inf. NH3 (mg/L) LBSAeration Flow Eff. Detention EQ. CBOD5 Eff. TSS Eff. NH3 BOD (mg/L) (mg/L) 37.8 (mg/L) entering (hrs) 220.140 224.721 16.884 1.413 1.366 0.164 42,177 5.32 38.43 587.000 614.000 23.000 3.730 4.500 2.220 106,155 6.20 52.33 62.000 116.000 10.700 0.590 0.000 0.042 12,444 32.74 3.88 Table 3 - Plant data from 2002 Plant Flow AVERAGE 25.446 MAX 66.004 MIN 19.019 Inf. BOD5 (mg/L) 322.58 644.00 103.000 Inf. TSS (mg/L) 419.56 1600.00 54.000 Inf. NH3 (mg/L) 15.78 26.70 6.140 Eff. CBOD5 (mg/L) 2.81 7.80 1.040 Eff. TSS (mg/L) 3.06 11.70 0.800 Eff. NH3 (mg/L) 1.446 13.800 0.040 LBS-BOD (entering) 68,087 170,909 17,778 Areation Detention 6.58 8.53 2.458 Comparing the data from the 2005 stress test chart to the 2002 chart there was a 38 percent reduction in BOD entering (re-entering) the plant. The stress test substantiates EPA’s finding and validates the corrective measures taken at the WMARSS plant to bridge the gaps in communication, operations and process controls. The benefits from the teamwork far out weigh the effort since subsequent to the performance improvements, the plant’s electrical usage dropped by 4.5 million kilowatts annually. Presently, the plant is much easier to operate and has dropped it’s midnight shift under normal
  • 8. Texas American Water Works Association April 2006 conditions (not including the pelletizing operations) but now operates an average of five day a week compared to the average six day weeks which equates to a 20% reduction in workload. The major conclusion is that the plant can treat more than 20% design criteria permitted flow/single stage nitrification loading effectively, which was established by the stress test and the mathematical model. STRESS TEST LOCATION AND METHODOLOGY The site of the tests was a large 37.8 mgd Waste Water Treatment Plant designated the Waco Metropolitan Area Regional Sewer System (WMARSS). The system serves as the central plant to treat wastewater from member cities with a total population of about 175,000 residents: Waco, Bellmead, Hewitt, Woodway, Lacy-Lakeview and Robinson. During the test, the stoichiometrical relationship of o 1.1 lbs O2 / lb BOD, and o 4.6 lbs O2 / lb ammonia was maintained by adding diffusers in the 3 basins to meet the total aeration demands for influent BOD, ammonia and additionally, the mixed liquor. Average flows and BOD to these units varied from approximately 25 to 30 MGD and 250 mg/L respectively. This approach provided loadings and detention times comparable to the future average flows of 37.8 MGD under mean plus one standard deviation loads. Additional units were put online to deal with wet weather events. The stress test was conducted by diverting the entire flow proportionally through 3 of the 5 aeration basins and 3 of the 4 final clarifiers. Since normal operation of the plant is with 5 aeration basins, in terms of true plant capacity, a flow of 28 mgd through these 3 aeration basins during the stress test equates to 22.68 mgd x 5 basins/3 basins = 37.8 mgd during normal operations (with 5 aeration basins in service). Similarly, a flow of 28.35 mgd through 3 final clarifiers during this stress test is equivalent to 37.8 mgd through 4 final clarifiers during normal operations. A dye-tracer study is also in progress to analyze the hydraulic characteristics of the clarifier and optimize its performance. On any given day, the stress tests lasted several hours during periodic, relatively stable, flow conditions. System performance was evaluated by measuring influent and effluent BOD, ammonia, and TSS. SUMMARY OF THE RESULTS AND DISCUSSION Graphs from the stress test data described previously are included below and support the conclusions provided next. The BOD converted to pounds per 1,000 cubic feet of the aeration unit is shown on Figure 4 and depicts fluctuations during the stress test. The actual pounds of BOD entering the plant during the stress test is shown on Figure 5. The influent BOD, TSS, ammonia and the flow equivalent is depicted on Figure 6 and compared to the effluent loading on Figure 7. The y-axis range is much smaller for Figure 7 than Figure 6 due to significant drop in influent values for measured parameters
  • 9. Texas American Water Works Association April 2006 during treatment. The effluent loading model shown on Figure 8, derived from regression analysis of the stress test data shows consistency between the modeled and the actual data. To obtain the model, regression analysis was performed and model equations (Table 4) for effluent BOD, TSS and ammonia were derived as a function of influent parameters to calculate the model plot data. Figure 4 – BOD in lbs per 1,000 cubic feet of the Aeration Unit A E R A T IO N LB S P E R 10 0 0 c uf t 100 90 Design Areation lbs Aeration EQUIV. 37.8 80 70 60 50 40 30 20 10 0 Figure 5 – lbs of BOD entering the plant from the collection system P o unds B O D e nt e ring pla nt 200000 180000 Design BOD entering lbs BOD EQUIV. 37.8 160000 140000 120000 100000 80000 60000 40000 20000 0
  • 10. Texas American Water Works Association April 2006 Figure 6 – Influent BOD, TSS, Ammonia and Flow Equivalent Influent Loading Plant Effluent Equivalent, mgd Inf. BOD5 (mg/L) Inf. TSS (mg/L) Figure 7 – Effluent BOD, TSS, Ammonia, Aeration Unit Detention Effluent Loading 6.5 6 5.5 BOD, mg/L 5 4.5 TSS, mg/L 4 Ammonia, mg/L 3.5 3 Detention, hrs 2.5 2 1 .5 1 0.5 0 T ime in D ays 7/ 25 7/ 18 7/ 11 7/ 4 6/ 27 6/ 20 6/ 13 6/ 6 Inf. NH3 (mg/L) 5/ 30 5/ 23 660 640 620 600 580 560 540 520 500 480 460 440 420 400 380 360 340 320 300 280 260 240 220 200 180 160 140 120 100 80 60 40 20 0
  • 11. Texas American Water Works Association April 2006 Figure 8 – Effluent Loading Plot Utilizing Model Equation Derived from Stress Test Data Effluent Loading Model 6.50 Model BOD, mg/L 6.00 5.50 5.00 Model TSS, mg/L 4.50 4.00 3.50 Model Effluent Ammonia, mg/L 3.00 2.50 Detention, hrs 2.00 1.50 1.00 0.50 3/9 3/7 3/5 3/3 3/1 2/28 2/26 2/24 2/22 2/20 2/18 2/16 2/14 2/12 2/8 2/10 2/6 2/4 2/2 1/31 1/29 1/27 1/25 1/23 1/21 1/19 1/17 1/15 1/13 1/9 1/11 1/7 1/5 1/3 1/1 0.00 Time in Days Table 4 – Effluent Concentrations Model Effluent Ammonia Prediction Model NH3eff = 0.26728219604 + -0.0028310569243*MGD + -0.000041517607405*BODinf + -0.004190273598*NH3inf + 0.0000891630116TSSinf MGD BODinf NH3inf TSSinf NH3eff 35.925 214 16.8 138 0.086 Effluent TSS Prediction Model TSSeff = -3.732857302 + 0.17625048953*MGD + -0.0038607363102*BODinf + -0.010748551178*NH3inf + -0.00044110484113*TSSinf MGD BODinf NH3inf TSSinf TSSeff 35.925 214 16.8 138 1.53 Effluent BOD Prediction Model BODeff = -0.40045564232 + 0.017954249533*MGD + 0.0044010643804BODinf + 0.041444463095*NH3inf + -0.00232059867*TSSinf MGD BODinf NH3inf TSSinf BODeff 35.925 214 16.8 138 1.56
  • 12. Texas American Water Works Association April 2006 CONCLUSION The success of the stress test in demonstrating adequate capacity at the current permit limit of 37.8 mgd plus 20% though full scale data collection and mathematical modeling, is attributed to the introduction (over a 3-year period) of effective design and operational controls prior to the stress test, thereby eliminating the need for a down-rating. These performance improvements are demonstrated in decreasing effluent concentrations for the parameters monitored shown in the charts below: Figure 9 – Monthly Average Loading in 2002 (Before Performance Improvements) 100.000 90.000 80.000 70.000 60.000 50.000 40.000 30.000 20.000 10.000 0.000 1 2 3 4 5 6 7 8 9 10 11 12 24.210 0 25.528 28.297 24.675 23.496 24.635 22.171 21.740 27.110 24.723 32.636 Monthly average BOD/1000cuft 42.41284 0 53.15341 60.49677 57.65549 52.14599 39.71627 32.55432 28.03018 42.96607 43.96403 47.30601 Monthly Max bod/1000cuft 70.27615 0 85.79514 89.25527 89.38485 79.22628 98.65793 65.94503 60.58688 84.01449 70.9485 97.49092 Monthly average Flow 1. This chart indicates that the plant was receiving high average aeration loading (8 months over 40 lbs per 1000 cuft and all the monthly max lbs per 1000 cuft were over 60 lbs) 2. The high aeration loadings were due to foul-ups at the plant. The chart demonstrates the negative impacts of the plant’s deficient operational practices leading to where the pounds of BOD originated from. This brings us back to the EPA’s findings part B related to “foul-ups”, i.e., the WMARSS operational practices did not effectively process the plants solids thus contaminating the plant’s side stream flows and leading to high aeration loadings.
  • 13. Texas American Water Works Association April 2006 3. The plant was not constantly meeting permit limits, but the cause was not from the influent loading; it was from the operational practices of the aeration process and low Oxygen Transfer Efficiency. Figure 10 – Monthly Average Loading in 2003 (During Performance Improvements) 120.000 100.000 80.000 60.000 40.000 20.000 0.000 Monthly average Flow Monthly Average BOD/1000cuft Monthly Max BOD/1000cuf 1. 2. 3. 1 2 3 4 5 6 7 8 9 10 11 12 28.143 32.262 30.102 23.200 22.899 22.839 21.359 21.750 22.514 24.214 22.041 21.053 60.351 71.424 42.637 31.847 33.881 28.086 28.075 23.503 32.923 29.170 25.854 40.141 97.00582 101.54838 57.216447 47.182381 94.029532 45.942959 37.09399 30.131747 45.788252 43.516275 59.324426 69.614266 In 2003 the plant was still receiving high max aeration loading but reduced from 2002 (4 months of high loadings in 2003 vs. 12 months of high loadings over 60 lbs per 1000 cuft in 2002) The average aeration loading was consistent and lower than 2002, indicating the plant personnel was properly processing the plants solids aided by implementation of the use of polymer at the Dissolved Air Floatation unit. The plant also sustained max loading conditions with only 4/5 of the aeration capacity in service (5th aeration unit was not used) with no ammonia violations. Improvements are more noticeable in Figure 10 which documents progressive improvements in 2004: 1. This chart indicates in 2004 the plant was still receiving high average aeration loading but reduced from 2002 (6 months in 2004 vs. 8 months over 40 lbs per 1000 cuft in 2002, and 8 months vs. 12 months over 60 lbs per 1000 cuft)
  • 14. Texas American Water Works Association April 2006 2. The high loading provided historical data that supports the 37.8 mgd rating, since the plant effectively treated 61,668 annual average pounds of BOD, which is 80% of the designed loading with only 4/5 of the aeration units in service. 3. So the plant was operating at 80% of its treatment capacity based on the original design and confirmed the EPA’s Finding – A. The availability of an additional 20% capacity for emergencies over the 37.8 mgd as demonstrated in these charts indicate the new SOP’s implemented in concert with mechanical enhancements have brought the plant closer to it’s original design capacity. Figure 11 – Monthly Average Loading in 2004 (After Performance Improvements) Monthly Average Loading 2004 180.00 160.00 140.00 120.00 100.00 80.00 60.00 40.00 20.00 0.00 Monthly aver age F low 1 2 3 4 5 6 7 8 9 10 11 12 23.01 28.42 28.08 30.09 29.87 34.30 26.63 22.99 22.23 28.53 41.10 29.02 Monthly Average BOD/1000c uft 44.6077 49.2273 40.4055 45.4173 49.0104 43.4163 33.1035 35.1969 31.0623 36.3775 33.8909 38.4833 Monthly Max BOD/1000cuf 89.2565 71.5787 89.2401 165.456 103 63.6942 53.9691 62.1979 44.0665 49.2875 67.6113 58.8392 Significant improvement in influent loadings are observed when the data from the 3 years are combined and reviewed side by side as in Figure 12. Following are the significant
  • 15. Texas American Water Works Association April 2006 observations that are deduced from the Annual Daily Average Influent Loadings shown on Figure 12: 1. Controlling the side stream concentrations proved to improve the plants loadings and 2003 was the more effective year. 2. There is one other side stream that is not included in the influent loading, the Dryer units flow contains an average daily loading of 1,500lbs of ammonia that is treated in the aeration basins. 3. This additional ammonia loading is a 30% increase over the plants influent ammonia loading and this loading is not consistent, because the Dryer unit does not run 24/7 it operates 24/5. 4. Controlling all side streams in-effect at the plant has proven to be a beneficial operational practice that is continuing to enhance the operations and capacity of the aeration units. Figure 12 – Influent Loadings Decrease with Performance Improvements Annual Daily Average Influent Loading 100000 80000 60000 40000 20000 0 2002 2003 2004 BO D 68874 53175 61668 TS S 88875 59844 72132 nh-3 3343 3889 3388 Significant improvement in Detention Times are observed when the data from the 3 years are combined and reviewed side by side as in Figure 12. Following are the significant observations that are deduced from the Annual Average Detention Times shown on Figure 13:
  • 16. Texas American Water Works Association April 2006 1. Finally, in 2004 the plant was at 80% capacity with 80% treatment capacity in service, 20% additional available for emergencies, at an average detention time of 5.66 hour for the 4 aeration units in service and the annual average flow was at 78% of the 37.8 mgd design flow. 2. Looking at one specific month, especially June of 2004, the plant was at 76% capacity at 80% treatment capacity in service, at an average detention time of 5.2 hours at 90% of the 37.8 mgd design flow and still maintained effective treatment at an effluent NH-3 average of 0.15mg/L. 3. Further improvement was observed in Feb 05, when the plant was at 80% capacity at 80% treatment capacity in service, at an average detention time of 4.8 hours at 92% of the 37.8 mgd design flow with an effluent NH-3 of 0.13mg/L. Figure 13 – Required Detention Times Decrease with Process Improvements 7.00 6.00 5.00 4.00 3.00 2.00 1.00 0.00 2002 2003 2004 H rs ou 6.39 6.67 5.66 The significant drop in effluent ammonia, evident from the effectiveness of the anoxic and aeration zones and control of plant side streams are depicted on Figure 14 which compares effluent ammonia, TSS and BOD effluent loadings in 2002, 2003 and 2004. Following highlights are derived from Figure 14: 1. The plant has performed at monthly average detention times of 4.8 hours, with high aeration loading over 46 lbs/1000 cuft and still produced significantly low effluent NH-3 concentrations.
  • 17. Texas American Water Works Association 2. 3. 4. April 2006 The year 2002 had many ammonia violations, but for the years 2003 and 2004 there were no ammonia violations and the average effluent NH-3 dropped from 1.446 to 0.153mg/L. As mentioned before, the effluent quality is a result of the implementation of adjusted operational procedures on the aeration units, increased oxygen transfer efficiency and blower automation. With the aeration unit operating efficiently biologically, the plant energy consumption (kwh) reduced 17% from 2002 to 2003 and an additional 6% in 2004. The automation of the blowers once again confirms the EPA’s finding A and B on true treatment capacity because of the consistent treatment effectiveness observed during this period. Figure 14 – Significant Drop in Effluent Ammonia with Improvements A n nu al A verage E fflu en t L oad in g 5 .0 0 0 4 .0 0 0 3 .0 0 0 2 .0 0 0 1.0 0 0 0 .0 0 0 200 2 200 3 200 4 B OD 2 . 8 15 2. 638 2. 696 T SS 3. 059 2. 290 2 . 9 19 A mmo n i a 1 .4 4 6 0. 307 0 . 15 3 More evidence of aeration basin effectiveness during the process improvements is observed in Figure 15 which shows the correlation. This chart indicates that in February 2002 the effluent average concentrations dropped to the minimum levels. This is due to the fact that this is the same month in which the WMARSS staff completed the installation of additional diffusers to the aeration basins to improve aeration characteristics for effective ammonia removal.
  • 18. Texas American Water Works Association April 2006 Figure 15 – Effluent Ammonia Monthly Max Day Effluent Ammonia Monthly Max Day 14.000 12.000 10.000 8.000 6.000 4.000 2.000 0.000 1 2 3 4 5 6 7 8 9 10 11 12 2002 7.420 0.000 7.620 13.800 2.429 8.350 4.620 3.780 1.660 5.360 13.000 3.680 2003 2004 2005 4.1 1.89 8 4.1 2.31 0.978 0.2 0.548 1.12 1.64 0.239 2.1 0.185 1.63 0.277 0.54 0.492 0.146 1.87 2.1 2.69 0.57 0.109 0.32 1.2 0.057 0.91 0.657 3.8 0.57 0.327 2.2 Average effluent ammonia concentrations are shown on Figure 16 for 2002. This chart also indicates that in February 2002 the effluent average concentrations dropped to the minimum levels which is correlated to the completion of the installation of additional diffusers at the aeration basins. The conclusions discussed above only discussed average flow to the plant. Peak flow management is being addressed by the following: • • • Peak Flow Storage Basin (one downstream of the highest I&I contributor) I&I Control in process (2 major I&I sites at the E. Bank have been remedied) Flow Diversion to Satellite Plant (Feasibility Study just completed)
  • 19. Texas American Water Works Association April 2006 Figure 16 – Effluent Ammonia Monthly Average E fflu e n t A m m o n ia M o n th ly A v e ra g e 3 .0 0 0 2 .5 0 0 2 .0 0 0 1 .5 0 0 1 .0 0 0 0 .5 0 0 0 .0 0 0 2 00 2 2 00 3 2 00 4 2 00 5 0 .1 6 0 .1 8 0 .1 0 .1 0 .3 4 0 .1 2 0 .1 1 0 .3 7 2 .0 4 0 1 .1 9 2 0 .0 0 0 1 .0 2 1 .5 9 3 0 .4 2 9 2 .5 3 6 0 .0 7 6 0 .5 2 8 0 .1 9 4 2 .0 4 5 0 .0 7 4 1 .5 0 7 0 .0 6 9 0 .8 6 5 0 .0 8 0 .4 7 9 0 .0 7 7 1 .3 1 9 0 .1 2 8 1 .7 9 6 0 .4 0 3 1 .2 2 1 0 .0 5 9 0 .2 0 5 0 .1 5 5 0 .3 6 5 0 .1 7 9 0 .1 2 5 0 .1 0 4 0 .1 0 5 0 .1 0 2 0 .1 6 4 0 .3 4 0 .1 4 5 0 .1 2 1 0 .1 6 4 0 .1 1 4 0 .1 2 9 0 .3 6 5 0 .0 7 4 0 .1 5 5 0 .0 9 7 0 .1 1 6 Peak flows during wet weather events are being addressed with the construction of a peak storage tank. The peak storage basin is important, since the limiting unit process in the treatment train is chlorination. Since it is not cost effective to construct additional chlorine contact basins, efforts are now focused on maximizing peak flow through WMARSS by raising the walls of the existing chlorine contact chamber in conjunction with the new peak storage basin construction. A preliminary hydraulic evaluation has indicated that raising the walls of the chlorine contact chamber by approximately 1 ft is feasible. As part of the I&I Program, studies have been completed for two basins and evaluation is in process to consider planning for rehabilitation. The feasibility study of the satellite plant has been completed. The study recommends two satellite plants at strategic locations to provide maximum benefit for flow diversion and capture as well as promote the potential for water reuse while providing new wastewater treatment infrastructure for selected cities in the watershed. Output from Peak Flow Basin Modeling Calculations are shown on Figure 17.
  • 20. Texas American Water Works Association April 2006 Figure 17 – Peak Flow Basin Modeling Output Shown Graphically ACKNOWLEDGEMENTS The authors would like to thank all WMARSS employees for their tireless efforts in making this stress test feasible. REFERENCES WMARSS Operation and Maintenance Manual, January 1985 When the flow into the peak flow basin is 155 mgd during wet weather events, a basin size of 3.9 million gallons (MG) and 4.9 MG will be needed to maintain a plant influent of 115 mgd and 83.2 mgd respectively. To lower the plant influent to the 83.2 mgd peak, a peak flow basin of 5 MG is required. By raising the walls of the Chlorine Contact Chamber, the flow into the plant can be increased, thereby reducing the required size of the peak flow basin. ACKNOWLEDGEMENTS The authors would like to thank all WMARSS employees for their tireless efforts in making this stress test feasible. REFERENCES WMARSS Operation and Maintenance Manual, January 1985