Constructing a Network Diagram BUSINESS DECISION ANALYSIS Constructing a Network Diagram Click function key F5 to run this lecture as a Slide Show
Constructing a Network Diagram Are there any pre-requisites for this topic? NO. You may have come across terms like “ critical path ” but no knowledge is pre-supposed.
Constructing a Network Diagram Project management is also referred to as: network analysis critical path analysis PERT   - program evaluation & review technique
Constructing a Network Diagram OK, so what’s a project? Well any managerial activity can be represented as a project. For example: ,[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object]
Constructing a Network Diagram What do your example projects have in common? Each can be decomposed into its constituent parts, called  ACTIVITIES . We can then define a project as a collection of related activities. Three things are important: ,[object Object],[object Object],[object Object]
Constructing a Network Diagram What gives activities structure? But that’s too vague. A roof cannot be erected unless the foundations have been dug. Obviously true! So digging foundations must precede erecting the roof! But what about the walls? So we refer to the   immediately preceding activities . Precedence : some activities have to be completed before others can be started.
Constructing a Network Diagram The first step for any project is to: ,[object Object],[object Object],The project is to build an extension to the Recreation Centre. The table lists the activities and their immediate predecessors – up to the point of starting construction.
Constructing a Network Diagram And here’s another project  ………….  “ purchase of a new car” . Activity Description Preceding  Activity Duration  (days) A Decide feasibility of purchase - 3 B Find buyer for existing car A 14 C Decide on possible models A 1 D Investigate models decided upon C 3 E Discuss with knowledgeable friends C 1 F Get information from dealers C 2 G Put all information together D,E,F 1 H Narrow down to three options G 1 I Test drive all three H 3 J Get warranty & finance information H 2 K Choose one car 1,J 2 L Compare dealers & choose one K 2 M Decide upon colour etc L 4 N Test drive chosen model L 1 O Buy new car B,M,N 3
Constructing a Network Diagram Is activity B a pre-condition for starting activity I? NO Activity Description Preceding  Activity Duration  (days) A Decide feasibility of purchase - 3 B Find buyer for existing car A 14 C Decide on possible models A 1 D Investigate models decided upon C 3 E Discuss with knowledgeable friends C 1 F Get information from dealers C 2 G Put all information together D,E,F 1 H Narrow down to three options G 1 I Test drive all three H 3 J Get warranty & finance information H 2 K Choose one car 1,J 2 L Compare dealers & choose one K 2 M Decide upon colour etc L 4 N Test drive chosen model L 1 O Buy new car B,M,N 3
Constructing a Network Diagram Is activity A a pre-condition for starting activity K? YES  Activity Description Preceding  Activity Duration  (days) A Decide feasibility of purchase - 3 B Find buyer for existing car A 14 C Decide on possible models A 1 D Investigate models decided upon C 3 E Discuss with knowledgeable friends C 1 F Get information from dealers C 2 G Put all information together D,E,F 1 H Narrow down to three options G 1 I Test drive all three H 3 J Get warranty & finance information H 2 K Choose one car 1,J 2 L Compare dealers & choose one K 2 M Decide upon colour etc L 4 N Test drive chosen model L 1 O Buy new car B,M,N 3
Constructing a Network Diagram Can activities E and F take place at the same time? YES  Activity Description Preceding  Activity Duration  (days) A Decide feasibility of purchase - 3 B Find buyer for existing car A 14 C Decide on possible models A 1 D Investigate models decided upon C 3 E Discuss with knowledgeable friends C 1 F Get information from dealers C 2 G Put all information together D,E,F 1 H Narrow down to three options G 1 I Test drive all three H 3 J Get warranty & finance information H 2 K Choose one car 1,J 2 L Compare dealers & choose one K 2 M Decide upon colour etc L 4 N Test drive chosen model L 1 O Buy new car B,M,N 3
Constructing a Network Diagram Precedence tables aren’t that easy to use. Is there some other way of representing a project? Y E S A useful visual representation of a project is obtained by drawing a network diagram.
Constructing a Network Diagram This is how we represent an activity. activity event of starting an activity event of ending an activity get out of bed So somewhere in the project “ Get to University Monday Morning ” will be:
Constructing a Network Diagram Err .. but we’ll need to link activities together, won’t we. That’s correct.  Sometimes we might want to show: A  B  C
Constructing a Network Diagram Err .. but we’ll need to link activities together, won’t we. That’s correct.  Sometimes we might want to show: M K L
Constructing a Network Diagram Err .. but we’ll need to link activities together, won’t we. That’s correct.  Sometimes we might want to show: A B C
Constructing a Network Diagram Are there any rules to follow when drawing network diagrams? YES ,[object Object],2.  Must have a single starting point. 3.  Also a single ending point.  4.  One arrow (only) per activity. 5.  Must correctly reflect the precedence table.
Constructing a Network Diagram There is one complication that we need to allow for. A dummy activity may be needed: ,[object Object],[object Object],OK, tell me the worst!! Sometimes we have to use  Dummy  activities. We use a dashed arrow to record these.
Constructing a Network Diagram OK. Let’s have a go at drawing a network. We’ll draw the one for the extension to the recreation centre.
Constructing a Network Diagram Where do I start? Once the project has started which activities can be begun? Well, a network must have a single starting point – a circle or node. A  Survey site B  Develop initial proposal
Constructing a Network Diagram A B So we draw arrows for activities A & B running from the starting event. Make sure that you label the activities as you include them in the network. Activity  Preceding Activity C  A,B What comes next?
Constructing a Network Diagram Well is this correct. Does it abide by the rules for drawing network diagrams? That’s no problem. Just do this. Activity  Preceding Activity C  A,B A B C NO Two or more activities may not share the same starting  and  ending event.
Constructing a Network Diagram Use a dummy activity. Here’s one way in which it can be done. It prevents A & B from sharing the same starting  and  ending event. So how do I remedy this error? A B C
Constructing a Network Diagram So we’ll add these to the network. A B C Activities D & E can start when C is finished. E D
Constructing a Network Diagram The table says that F can start when D & E are completed. So can we do this? A B C E D F
Constructing a Network Diagram No. We’ve broken the rules again. So another dummy activity is needed. A B C E D F
Constructing a Network Diagram This will work. A B C E D F
Constructing a Network Diagram Now we can add activity G. G can be started once E is completed. A B C E D F G
Constructing a Network Diagram That leaves activity H.  The start of H requires the completion of F  and  G. A B C E D F G
Constructing a Network Diagram So we bring the arrows for F & G into the starting event for activity H. And this is the finished network. A B C E D F G H
Constructing a Network Diagram Always check the network against the precedence table before continuing. A B C E D F G H
Constructing a Network Diagram Right, now we’ll draw the network for the project of buying a new car. For this project there’s only one starting activity, namely A
Constructing a Network Diagram A Activities B & C can be started once A is completed. B C
Constructing a Network Diagram A And D, E & F can be started when C is completed. B C D E F
Constructing a Network Diagram Activity G requires completion of D, E & F. So two dummy activities are needed to prevent D, E & F having the same starting and ending events. A B C D E F G
Constructing a Network Diagram Activity H can now be added to the network. A B C D E F G H
Constructing a Network Diagram I & J can now start. A B C D E F G H I J
Constructing a Network Diagram Since the start of K needs completion of I & J we need another dummy activity. A B C D E F G H I J K
Constructing a Network Diagram Now we add activity L A B C D E F G H I J K L
Constructing a Network Diagram Activities M & N can now be started. A B C D E F G H I J K L M N
Constructing a Network Diagram That leaves activity O. It can be started when activities B, M & N are completed. A B C D E F G H I J K L M N
Constructing a Network Diagram That leaves activity O. A dummy activity will be needed to separate activities M and N. A B C D E F G H I J K L M N
Constructing a Network Diagram C But remember to check it against the precedence table. A D E F G H I J K L M N The network is now completed. O B
Constructing a Network Diagram What should I now be able to do? Given the precedence table for a project, you should be able to draw its network diagram.
Constructing a Network Diagram That’s the end of this lecture. You should now explore the problems, on drawing networks, that are available within Blackboard.

More Related Content

What's hot

Scheduling by Primavera - Training
Scheduling by Primavera - TrainingScheduling by Primavera - Training
Scheduling by Primavera - Training
Mohammed Feroze
 
pRIMAVERA - Progress report checklist - Substation
pRIMAVERA - Progress report checklist - SubstationpRIMAVERA - Progress report checklist - Substation
pRIMAVERA - Progress report checklist - Substation
RAMESH PANIGRAHI PMP
 
Project Management PPT
Project Management PPTProject Management PPT
Project Management PPT
bletindia
 
Pert,cpm, resource allocation and gert
Pert,cpm, resource allocation and gertPert,cpm, resource allocation and gert
Pert,cpm, resource allocation and gert
Raj J Das
 

What's hot (20)

Project Management Tools and Techniques
Project Management Tools and TechniquesProject Management Tools and Techniques
Project Management Tools and Techniques
 
Project management and project life cycle
Project management and project life cycleProject management and project life cycle
Project management and project life cycle
 
Scheduling by Primavera - Training
Scheduling by Primavera - TrainingScheduling by Primavera - Training
Scheduling by Primavera - Training
 
Primavera - Tutorial
Primavera - TutorialPrimavera - Tutorial
Primavera - Tutorial
 
Project Time Management
Project Time ManagementProject Time Management
Project Time Management
 
Strategic Planning : the best way to manage EPC Contract Risks
Strategic Planning : the best way to manage EPC Contract RisksStrategic Planning : the best way to manage EPC Contract Risks
Strategic Planning : the best way to manage EPC Contract Risks
 
The Network Diagram and Critical Path
The Network Diagram and Critical PathThe Network Diagram and Critical Path
The Network Diagram and Critical Path
 
Last planner system
Last planner systemLast planner system
Last planner system
 
Practical Project Cost Control for Large Complex Projects
Practical Project Cost Control for Large Complex ProjectsPractical Project Cost Control for Large Complex Projects
Practical Project Cost Control for Large Complex Projects
 
Project management tools and techniques
Project management tools and techniquesProject management tools and techniques
Project management tools and techniques
 
pRIMAVERA - Progress report checklist - Substation
pRIMAVERA - Progress report checklist - SubstationpRIMAVERA - Progress report checklist - Substation
pRIMAVERA - Progress report checklist - Substation
 
Project Management PPT
Project Management PPTProject Management PPT
Project Management PPT
 
Earned Value Analysis
Earned Value AnalysisEarned Value Analysis
Earned Value Analysis
 
Project Management Concepts
Project Management ConceptsProject Management Concepts
Project Management Concepts
 
Project quality management.ppt msm
Project quality management.ppt msmProject quality management.ppt msm
Project quality management.ppt msm
 
Project cost & control
Project cost & controlProject cost & control
Project cost & control
 
Critical path method(cpm)
Critical path method(cpm)Critical path method(cpm)
Critical path method(cpm)
 
Pert,cpm, resource allocation and gert
Pert,cpm, resource allocation and gertPert,cpm, resource allocation and gert
Pert,cpm, resource allocation and gert
 
Construction Planing & Schedule
Construction Planing & ScheduleConstruction Planing & Schedule
Construction Planing & Schedule
 
Project cost stimating
Project cost stimatingProject cost stimating
Project cost stimating
 

Similar to Constructing a network diagram

Scheduling Problems Complete the following problems covering pro.docx
Scheduling Problems Complete the following problems covering pro.docxScheduling Problems Complete the following problems covering pro.docx
Scheduling Problems Complete the following problems covering pro.docx
kenjordan97598
 
1440 pmp exam question bank
1440 pmp exam question bank1440 pmp exam question bank
1440 pmp exam question bank
Baskar El
 
EO notes Lecture 27 Project Management 2.ppt
EO notes Lecture 27 Project Management 2.pptEO notes Lecture 27 Project Management 2.ppt
EO notes Lecture 27 Project Management 2.ppt
yashchotaliyael21
 
C notes by m v b reddy(gitam)imp notes all units notes 5 unit order
C notes by m v b  reddy(gitam)imp  notes  all units notes  5 unit orderC notes by m v b  reddy(gitam)imp  notes  all units notes  5 unit order
C notes by m v b reddy(gitam)imp notes all units notes 5 unit order
Malikireddy Bramhananda Reddy
 

Similar to Constructing a network diagram (20)

Critical path analysis
Critical path analysisCritical path analysis
Critical path analysis
 
Bus 517 final exam – strayer new
Bus 517 final exam – strayer newBus 517 final exam – strayer new
Bus 517 final exam – strayer new
 
Bus 517 final exam – strayer new
Bus 517 final exam – strayer newBus 517 final exam – strayer new
Bus 517 final exam – strayer new
 
Bus 517 final exam – strayer new
Bus 517 final exam – strayer newBus 517 final exam – strayer new
Bus 517 final exam – strayer new
 
Bus 517 final exam – strayer new
Bus 517 final exam – strayer newBus 517 final exam – strayer new
Bus 517 final exam – strayer new
 
Bus 517 final exam – strayer new
Bus 517 final exam – strayer newBus 517 final exam – strayer new
Bus 517 final exam – strayer new
 
Bus 517 final exam – strayer new
Bus 517 final exam – strayer newBus 517 final exam – strayer new
Bus 517 final exam – strayer new
 
Bus 517 final exam – strayer new
Bus 517 final exam – strayer newBus 517 final exam – strayer new
Bus 517 final exam – strayer new
 
Bus 517 final exam – strayer new
Bus 517 final exam – strayer newBus 517 final exam – strayer new
Bus 517 final exam – strayer new
 
The network-diagram-and-critical-path-adapted
The network-diagram-and-critical-path-adaptedThe network-diagram-and-critical-path-adapted
The network-diagram-and-critical-path-adapted
 
Pmp6
Pmp6Pmp6
Pmp6
 
Scheduling Problems Complete the following problems covering pro.docx
Scheduling Problems Complete the following problems covering pro.docxScheduling Problems Complete the following problems covering pro.docx
Scheduling Problems Complete the following problems covering pro.docx
 
Network analysis cpm module3 ppt
Network analysis cpm module3 pptNetwork analysis cpm module3 ppt
Network analysis cpm module3 ppt
 
CPM PERT.pptx
CPM PERT.pptxCPM PERT.pptx
CPM PERT.pptx
 
Project Management
Project Management Project Management
Project Management
 
FINAL REPORT
FINAL REPORTFINAL REPORT
FINAL REPORT
 
1440 pmp exam question bank
1440 pmp exam question bank1440 pmp exam question bank
1440 pmp exam question bank
 
ML, Statistics, and Spark with Databricks for Maximizing Revenue in a Delayed...
ML, Statistics, and Spark with Databricks for Maximizing Revenue in a Delayed...ML, Statistics, and Spark with Databricks for Maximizing Revenue in a Delayed...
ML, Statistics, and Spark with Databricks for Maximizing Revenue in a Delayed...
 
EO notes Lecture 27 Project Management 2.ppt
EO notes Lecture 27 Project Management 2.pptEO notes Lecture 27 Project Management 2.ppt
EO notes Lecture 27 Project Management 2.ppt
 
C notes by m v b reddy(gitam)imp notes all units notes 5 unit order
C notes by m v b  reddy(gitam)imp  notes  all units notes  5 unit orderC notes by m v b  reddy(gitam)imp  notes  all units notes  5 unit order
C notes by m v b reddy(gitam)imp notes all units notes 5 unit order
 

Constructing a network diagram

  • 1. Constructing a Network Diagram BUSINESS DECISION ANALYSIS Constructing a Network Diagram Click function key F5 to run this lecture as a Slide Show
  • 2. Constructing a Network Diagram Are there any pre-requisites for this topic? NO. You may have come across terms like “ critical path ” but no knowledge is pre-supposed.
  • 3. Constructing a Network Diagram Project management is also referred to as: network analysis critical path analysis PERT - program evaluation & review technique
  • 4.
  • 5.
  • 6. Constructing a Network Diagram What gives activities structure? But that’s too vague. A roof cannot be erected unless the foundations have been dug. Obviously true! So digging foundations must precede erecting the roof! But what about the walls? So we refer to the immediately preceding activities . Precedence : some activities have to be completed before others can be started.
  • 7.
  • 8. Constructing a Network Diagram And here’s another project …………. “ purchase of a new car” . Activity Description Preceding Activity Duration (days) A Decide feasibility of purchase - 3 B Find buyer for existing car A 14 C Decide on possible models A 1 D Investigate models decided upon C 3 E Discuss with knowledgeable friends C 1 F Get information from dealers C 2 G Put all information together D,E,F 1 H Narrow down to three options G 1 I Test drive all three H 3 J Get warranty & finance information H 2 K Choose one car 1,J 2 L Compare dealers & choose one K 2 M Decide upon colour etc L 4 N Test drive chosen model L 1 O Buy new car B,M,N 3
  • 9. Constructing a Network Diagram Is activity B a pre-condition for starting activity I? NO Activity Description Preceding Activity Duration (days) A Decide feasibility of purchase - 3 B Find buyer for existing car A 14 C Decide on possible models A 1 D Investigate models decided upon C 3 E Discuss with knowledgeable friends C 1 F Get information from dealers C 2 G Put all information together D,E,F 1 H Narrow down to three options G 1 I Test drive all three H 3 J Get warranty & finance information H 2 K Choose one car 1,J 2 L Compare dealers & choose one K 2 M Decide upon colour etc L 4 N Test drive chosen model L 1 O Buy new car B,M,N 3
  • 10. Constructing a Network Diagram Is activity A a pre-condition for starting activity K? YES Activity Description Preceding Activity Duration (days) A Decide feasibility of purchase - 3 B Find buyer for existing car A 14 C Decide on possible models A 1 D Investigate models decided upon C 3 E Discuss with knowledgeable friends C 1 F Get information from dealers C 2 G Put all information together D,E,F 1 H Narrow down to three options G 1 I Test drive all three H 3 J Get warranty & finance information H 2 K Choose one car 1,J 2 L Compare dealers & choose one K 2 M Decide upon colour etc L 4 N Test drive chosen model L 1 O Buy new car B,M,N 3
  • 11. Constructing a Network Diagram Can activities E and F take place at the same time? YES Activity Description Preceding Activity Duration (days) A Decide feasibility of purchase - 3 B Find buyer for existing car A 14 C Decide on possible models A 1 D Investigate models decided upon C 3 E Discuss with knowledgeable friends C 1 F Get information from dealers C 2 G Put all information together D,E,F 1 H Narrow down to three options G 1 I Test drive all three H 3 J Get warranty & finance information H 2 K Choose one car 1,J 2 L Compare dealers & choose one K 2 M Decide upon colour etc L 4 N Test drive chosen model L 1 O Buy new car B,M,N 3
  • 12. Constructing a Network Diagram Precedence tables aren’t that easy to use. Is there some other way of representing a project? Y E S A useful visual representation of a project is obtained by drawing a network diagram.
  • 13. Constructing a Network Diagram This is how we represent an activity. activity event of starting an activity event of ending an activity get out of bed So somewhere in the project “ Get to University Monday Morning ” will be:
  • 14. Constructing a Network Diagram Err .. but we’ll need to link activities together, won’t we. That’s correct. Sometimes we might want to show: A B C
  • 15. Constructing a Network Diagram Err .. but we’ll need to link activities together, won’t we. That’s correct. Sometimes we might want to show: M K L
  • 16. Constructing a Network Diagram Err .. but we’ll need to link activities together, won’t we. That’s correct. Sometimes we might want to show: A B C
  • 17.
  • 18.
  • 19. Constructing a Network Diagram OK. Let’s have a go at drawing a network. We’ll draw the one for the extension to the recreation centre.
  • 20. Constructing a Network Diagram Where do I start? Once the project has started which activities can be begun? Well, a network must have a single starting point – a circle or node. A Survey site B Develop initial proposal
  • 21. Constructing a Network Diagram A B So we draw arrows for activities A & B running from the starting event. Make sure that you label the activities as you include them in the network. Activity Preceding Activity C A,B What comes next?
  • 22. Constructing a Network Diagram Well is this correct. Does it abide by the rules for drawing network diagrams? That’s no problem. Just do this. Activity Preceding Activity C A,B A B C NO Two or more activities may not share the same starting and ending event.
  • 23. Constructing a Network Diagram Use a dummy activity. Here’s one way in which it can be done. It prevents A & B from sharing the same starting and ending event. So how do I remedy this error? A B C
  • 24. Constructing a Network Diagram So we’ll add these to the network. A B C Activities D & E can start when C is finished. E D
  • 25. Constructing a Network Diagram The table says that F can start when D & E are completed. So can we do this? A B C E D F
  • 26. Constructing a Network Diagram No. We’ve broken the rules again. So another dummy activity is needed. A B C E D F
  • 27. Constructing a Network Diagram This will work. A B C E D F
  • 28. Constructing a Network Diagram Now we can add activity G. G can be started once E is completed. A B C E D F G
  • 29. Constructing a Network Diagram That leaves activity H. The start of H requires the completion of F and G. A B C E D F G
  • 30. Constructing a Network Diagram So we bring the arrows for F & G into the starting event for activity H. And this is the finished network. A B C E D F G H
  • 31. Constructing a Network Diagram Always check the network against the precedence table before continuing. A B C E D F G H
  • 32. Constructing a Network Diagram Right, now we’ll draw the network for the project of buying a new car. For this project there’s only one starting activity, namely A
  • 33. Constructing a Network Diagram A Activities B & C can be started once A is completed. B C
  • 34. Constructing a Network Diagram A And D, E & F can be started when C is completed. B C D E F
  • 35. Constructing a Network Diagram Activity G requires completion of D, E & F. So two dummy activities are needed to prevent D, E & F having the same starting and ending events. A B C D E F G
  • 36. Constructing a Network Diagram Activity H can now be added to the network. A B C D E F G H
  • 37. Constructing a Network Diagram I & J can now start. A B C D E F G H I J
  • 38. Constructing a Network Diagram Since the start of K needs completion of I & J we need another dummy activity. A B C D E F G H I J K
  • 39. Constructing a Network Diagram Now we add activity L A B C D E F G H I J K L
  • 40. Constructing a Network Diagram Activities M & N can now be started. A B C D E F G H I J K L M N
  • 41. Constructing a Network Diagram That leaves activity O. It can be started when activities B, M & N are completed. A B C D E F G H I J K L M N
  • 42. Constructing a Network Diagram That leaves activity O. A dummy activity will be needed to separate activities M and N. A B C D E F G H I J K L M N
  • 43. Constructing a Network Diagram C But remember to check it against the precedence table. A D E F G H I J K L M N The network is now completed. O B
  • 44. Constructing a Network Diagram What should I now be able to do? Given the precedence table for a project, you should be able to draw its network diagram.
  • 45. Constructing a Network Diagram That’s the end of this lecture. You should now explore the problems, on drawing networks, that are available within Blackboard.