SlideShare uma empresa Scribd logo
1 de 74
Hydro power and other water borne Renewable energy technologies
UNIT 4
Introduction
Hydroelectric power (often called hydropower)
is considered a renewable energy source. A
renewable energy source is one that is not
depleted (used up) in the production of energy.
Through hydropower, the energy in falling water
is converted into electricity without “using up”
the water. Hydroelectric power (hydropower)
systems convert the kinetic energy in flowing
water into electric energy.
1. Source of power.
2.Interconnected with steam power plants, base
load is supplied by the hydro power plants while the
peak load is supplied by steam power plant, when
stream flow is less than maximum flow demand.
3.When stream flow is more than the maximum
flow demand, base load is supplied by the steam
power plants while the peak load is supplied by
hydro power plant.
Applications
Advantages
1. No fuel charges.
2. Any hydro electric plant is highly reliable
3. Maintenance and operation charges are very low.
4. Running cost of plant is low.
5. It has no standby losses.
6. The plant efficiency doesn’t change with age.
7. It take a few minutes to run and synchronize the plant.
8. Less supervising staff is required.
9. No fuel transportation problem.
10. No ashproblem.
11. In addition to power generation these plants are also used for flood
control and irrigation purposes.
12. The have long life (100-125yrs, 20-45yrs of thermalplant)
Disadvantages
• The initial cost is very high.
• It takes considerable time for the erection of such
plants.
• Such plants are usually located in hilly areas far
away from the load centre and as such they
require long transmission lines to deliver power,
hence the cost of transmission linear and losses in
them will be more.
• Power generation by the hydro-electric plants
depend upon quantity of water hence rain.
Selection of Site
• Availability of water
• Water storage
• Water head
• Accessibility of the site
• Distance from the load centre
• Type of the land of site
1. CatchmentArea
2. Reservoir
3. Dam
4. Spillways
5. Conduits
6. Surge tanks
7. Prime movers
8. Draft Tubes
9. Powerhouse and Equipment
Essential Features & Elements of
Hydro electric Power Plant
1. Catchment area: The
whole area behind the
dam draining into the
stream.
2. Reservoir: Used to
store water.
A. Natural (lake)
B. Artificial (dam, called
pondage)
Dam: barrier to raise water for storage or diversion to
create a hydraulic head.
Types of dams:
A. Fill Dams : Earth dams, Rock Fill Dams
B. Masonary Dams: Solid gravity dams, Butteress dams,Arch dams.
C. Timber Dams
Selection of type of Dam
1. Nature of foundation
Sound rock formation in foundation: any type of dam
Poor rock and earth foundation: earth dam
2. Nature of valley
Narrow valley : arch dam
Rocky bed: Solid gravity dam
Wide valley weak foundation: Buttress dam
Any width of valley, good foundation : Steel Dam
Types of Dams
• Fill Dams
1. Earth fill dams: earth fill
dam, also called Earth Dam, or
Embankment Dam, dam built
up by compacting successive
layers of earth, using the most
impervious materials to form a
core and placing more
permeable substances on the
upstream and downstream
sides.Afacing of crushed
stone prevents erosion by wind
or rain, and an
ample spillway, usually of
concrete.
• Arockfill dam is a type
of embankment
dam which comprises
primarily compacted
rock materials.
Used in mountainous
locations where rock is
available.
Masonry Dams
• Solid Gravity Dam: Massiveand
bulky and depends upon its
weight on stability.
• It requires strong rock foundation
• Bhakra Dam is the highest
Concrete Gravity dam in Asia and
Second Highest in the world.
• Bhakra Dam is across river Sutlej
in Himachal Pradesh
• It is 740 ft. high above the deepest
foundation as straight concrete dam
being more than three times the
height of Qutab Minar.
• Length at top 518.16 m (1700 feet);
Width at base 190.5 m (625 feet),
and at the top is 9.14 m (30 feet)
Butteress Dam
• Is a gravity dam reinforced by structural
supports.
• A buttress dam or hollow dam is a dam
with a solid, water-tight upstream side that
is supported at intervals on the
downstream side by a series of buttresses
or supports. The dam wall may be straight
or curved.
• Most buttress dams are made of
reinforced concrete and are heavy,
pushing the dam into the ground. Water
pushes against the dam, but the
buttresses are inflexible and prevent the
dam from falling over
• Buttress - a support that transmits a force
from a roof or wall to another supporting
structure
• It has a relatively thin structure. Because
of this, these dams often use half as much
concrete as gravity dams can be used for
weaker foundation.
Arch dam
• An arch dam is a solid dam made
of concrete that is curved upstream in
plan. The arch dam is designed sothat
the force of the water against it,
known as hydrostatic pressure,
presses against the arch, compressing
and strengthening the structure as it
pushes into its foundation or
abutments.
• An arch dam is most suitable for
narrow gorges or canyons with steep
walls of stable rock to support the
structure and stresses .Since they are
thinner than any other dam type,they
require much less construction
material, making them economical
and practical in remote areas.
Arch Dam
• Timber Dams
• When wood in plentiful and more durable
material are not accessible timber is used for
low dams 12m.
Spillways
• Aspillway is an integral part of a Dam.
• Aspillway is usually used to remove water from a
reservoir to prevent overflow and to release pressure on
a dam from increasing quantities of water. It is
normally composed of three major
components:
• The approach facility admits flow to the spillway.
• The discharging conduit evacuates the flow from the
approach facility to an outlet structure.
• The outlet structure (tailwater channel) dissipates the
excessive energy of the flow from the discharging
conduits and conveys tranquil flow to the downstream.
Overflow Spillway
• Overflow spillways are also
called ogee-shaped
(S-shaped) spillways.
• This type of spillways
allows the passage of the
flood wave over its crest
(which is S-shaped).
• Can be classified under
controlled or uncontrolled.
• Widely used on Gravity
dams,Arch dams, and
Buttress dams.
Chute spillways
• Chute spillways are common and
basic in design as they transferexcess
water from behind the dam down a
smooth decline into the river below.
• The spillway’s slope and its sides
are lined with concrete.
• In case of having sufficient stiff
foundation conditions at the spillway
location, a chute spillway may be
used instead of overflow spillwaydue
to economic consideration.
Side Channel Spillway
• It is employed when valley is too narrow in
case of solid gravity dams and when non rigid
dams are adopted.
• The side channel spillway is different from
chute spillway in the sense that after crossing
over the spillway crest. Water flows parallel to
the crest length in former, whereas the flow is
normal to the crest in the later.
Side Channel Spillway
Saddle Spillway
• There may be natural depressions or saddle on the peripheryof
the reservoir basin away from the dam. The depressions may
be used as spillway.
• The bottom of the depression should be at full reservoir level.
Siphon Spillway
• Crest is fixed at Full Reservoir Level. When
the water level in the reservoir rises over F.R.L
water starts spilling over the crest.
Conduit
• Aheadrace is a channel which leads water to a turbine anda
tailrace is a channel which conducts water from the wheels.
• Open Conduit: Canals and Flumes
• Close conduits: Tunnels, pipelines and penstock
Penstock
• Closed conduit for supplying water under
pressure to a turbine.
• Thinkness of penstock is given by:
• T = pd/2fn
p = pressure due to water
d = diameter of the penstock
f = Permissible circumferential stress
n = Joint efficiency
Surge Tanks
• A surge tank is small reservoir or tank in which water
level rises of falls to reduce the pressure swings so that
they are not transmitted in full to closed circuit.
1. They reduce the distance between the free water
surface and turbine thereby reducing water hammer
effect ( the change in in pressure rapidly above or
below normal pressure caused by sudden changes in
the rate of water flow through the pipe according to
the demand of the primemover) on the penstock.
2. To serve as supply tank to the turbine in case of
increased load conditions, and storage tank in case of
low load conditions.
Surge Tank
Prime movers
• Impulse Turbines: Pressure energy of water is
converted to kinetic energy when passing
through nozzle and forms velocity of high
head.
• Reaction Turbines: Water pressure combined
with the velocity works on the runner, power is
developed from the combined action of
pressure and velocity of water, that completely
fill the runner and water passage.
Draft Tubes
• It allows the turbine to be set above tail water
level, without loss of head, to facilitate inspection
and maintenance
• It regains, by diffuser action, the major portion of
the kinetic energy delivered to it from the runner.
1. Conical Type: used on low powered units for all
specific speeds and frequently od large head
units. Side angle 4 to 6 deg.
2. Elbow Type: Mostly used, vertical portion is a
conical section which gradually flattens in the
elbow section and then discharges horizontally.
Draft Tubes
Types of Power Plants
High Head Power Plant
Head: 100m to 2000m
Water is stored in the lake
over the mountain during
high rainy season or when
snow melts.
Water should be available
throughout the year.
Pelton Wheel turbine is
used.
Medium Head Plants
• Head : 30 to 100m
• Uses FrancisTurbine
• Forebay provided at the beginning of penstock at asreservoir.
• Water is carried in open canals from main reservoir to forebay thento
powerhouse through penstock.
Low Head Power Plants
• They consist of dam across the river.
• Asideway stream diverges from the river at the dam, powerhouseis
constructed over the stream, which further joins theriver.
• Vertical shaft Francis or Kaplan turbine
According to Nature of Load
Base Load Plants: they cater to the base load of
the system, they need to supply constant power
when connected to the grid.
Peak Load Plants: some of the plants supply
average load but also some peak load. Other
peak load plants are required to work only during
peak load hours.
According to the quantity of water
1. Run of river plants without pondage:
• No pondage.
• No control on flow of water.
2. Run of river plants with pondage
May work as base load or peak load plants.
Storage for a week
3. Storage Type Plant
The storage is large.
Used as base load and peak load plants
Controlled flow .
4. Pumped Storage plants
• These plants are employed
where quantity of water
required is inadequate.
• Water passing through the
turbine is stored in the tail
race pond. During low load
periods the water is pumped
back to the reservoir, which
can be used during peak
load plants.
• Usually interconnected with
steam or diesel power
plants.
Mini & Microhydel plants
• Mini – 5m to 20 m head
• Micro – below 5 m head
• These plants are scattered in our country and estimated potential is
20,000MW.
• Each plant generate about 100 to 1000kW
per unit.
Hydraulic Turbines
According to the head and quantity of water
• Impulse Turbine: Requires high head and
small flow of water.
• Reaction Turbine: Requires low head and
high rate of flow of water.
According to the name of originator
• Pelton Turbine: It is an impulse type of
turbine used for high head and low discharge.
• Francis Turbine: It is reaction type of turbine,
used for medium high to medium low heads
and medium small to medium large quantities
of water.
• Kaplan Turbine: It is reaction type of turbine,
used for low head and large quantities of flow.
According to action of water on the moving
blades
• Impulse: Pelton
• Reaction: Kaplan, Francis, Propeller.
According to direction of flow of water in runner
• Tangential flow turbine (PeltonTurbine)
• Radial flow turbine ( not used)
• Axial flow turbine (KaplanTurbine)
• Mixed (radial and axial ) flow turbine (Francisturbine)
According to the position of turbine shaft
• Shaft may be horizontal or vertical
• Pelton has horizontal axis
According to specific speed
• The specific speed is defined as the speed of a
geometrically similar turbine that would
develop one brake power horsepower under
the head of one meter.
Impulse Turbine-Pelton Turbine
• Tangential flow impulse
turbine.
• Rotor has equally spaced
hemispherical buckets, Water
is transferred from high head
source through penstock pipes.
• All the available potential
energy is converted to kinetic
energy before the jet strikes the
buckets.
• The pressure all over the wheel
is constant and equal to
atmospheric pressure, energy
transfer occurs due to purely
impulse action.
Reaction Turbine
• The runner utilizes both potential and kinetic
energy.
• As the water flows through the stationary part of
the turbine, whole of its pressure energy is not
transferred to kinetic energy. When the water
flows through the moving parts, there is a change
both in the pressure and in the direction and
velocity of flow of water.
• The water which acts on the runner blades is
under pressure above the atmospheric.
Francis Turbine
• It is an inward mixed flow reaction turbine i.e. water under pressure
, enters the runner form the guide vanes towards the centre in the
radial direction and discharges out of the runner axially.
• It runs under medium heads and requires medium quantity of water.
• Water is brought down to the turbine and directed to a number of
stationary guide vanes.
• The head acting on the turbine is partly transformed into kinetic
energy and rest remains as pressure head.
• The runner is always full of water. The movement of runner is
affected by the change of both the potential and the kinetic energies
of water.
• The water is then discharged to the tail race, through draft tube.
Propeller & Kaplan Turbines
• Propeller turbine is a reaction turbine used for heads between
4m to 80 m and specific speed of 300 to 1000.
• Axial Flow Type
• It consists of axial flow runner
• With 4-6 or max 10 blades of air foil shape
In Propeller Runner blades are fixed and non adjustable as in
Francis Turbine.
In Kaplan Turbine which is a modification of propeller turbine
the runner blades are adjustable and can be rotated aboutpivots
fixed to the base.
KaplanTurbine
Tubular/Bulb Turbine
• It is a modified axial flow
turbine, the turbo generator
set using the bulb/tubular
turbine has the outer casing
of the shape of a bulb.
• The turbine generator set is
called bulb set and turbine
used is called bulb turbine.
The bulb unit is a water
tight assembly of turbine
and generator with
horizontal axis, submerged
in a stream of water.
Turbine Efficiencies
Governing of Hydraulic Turbines
• Governing means the speed regulation. Under
normal conditions the turbine should run at
constant speed irrespective of changes in the
load.
• This is achieved by means of a governor called
oil pressure governor.
Governing of Impulse turbines
• The quantity of water rejected from turbine nozzle and from
striking the buckets may be regulated in following ways:
• Spear regulation: To and fro motion of spear inside the
nozzle alters the cross sectional area of the stream.
• Deflector regulation: the deflector is generally a plate
connected to the oil pressure governor by means of levers.
When it is required to deflect the jet, the plate can be
brought in between the nozzles and buckets, thereby
diverting the water away from the runner and directing into
tailrace.
It is used when supply of water is constant but load fluctuates.
• Combined spear and deflector regulation: the speed is
regulated by spear and pressure is regulated by deflector
Governing of Reaction Turbines
• The guide blades of reaction turbine are pivoted and
connected by levers and links to the regulating ring.
• To the regulating ring are attached two long regulating
rods connected to the regulating lever.
• The regulating ring is keyed to the regulating shaft
which is turned by servomotor piston of oil pressure
governor.
• The penstock which feeds the turbine inlet is has relief
valve know as pressure regulator.
• When guide vanes have to be suddenly closed the
relief valve opens and diverts the water to tailrace.
Hydrology
• It may be defined as the science which deals with the depletion
and replenishment of water resources.
Measurement of run-off
3. Run off tables and curves
• Hydrograph: It is defined as graph showing
discharge(run off) of flowing water with
respect to time for a specified time.
• It indicates the power available from the
stream at different times of day, week or year.
• Unit Hydrograph: It is a hydrograph which
represents unit run off resulted from an intense
rainfall of unit duration and specified areal
distribution.
Flow Duration Curve
• Is a plot of discharge against the percentage of
time the flow was equaled or exceeded.
• It is the curve plotted between the flow
available during a period verses fraction of
time.
• The area under the flow of the duration curve
gives the total quantity of run-off during that
period.
• Aflow duration curve allows the evaluationof
low levels of flow.
• It is highly useful in the planning and design of
water recourses.
• It also finds use in the design of drainage
system and in flood control studies.
Mass Curve
• Mass curve is the graph of cumulative values of water quantity
(run off) against time.Amass curve is integral curve of the
hydrograph which expresses the area under the hydrograph
from one time to another.

Mais conteúdo relacionado

Semelhante a UNIT 4.pptx

Hydro electric power plant lecture
Hydro electric power plant lectureHydro electric power plant lecture
Hydro electric power plant lecturec3b2a1
 
Malay nces ppt
Malay nces pptMalay nces ppt
Malay nces ppt9888437802
 
Spillways, Spillway capacity, flood routing through spillways, different type...
Spillways, Spillway capacity, flood routing through spillways, different type...Spillways, Spillway capacity, flood routing through spillways, different type...
Spillways, Spillway capacity, flood routing through spillways, different type...Denish Jangid
 
Presentation1.pptx
Presentation1.pptxPresentation1.pptx
Presentation1.pptxmagedahmed44
 
2. hydroelectric plant
2. hydroelectric plant2. hydroelectric plant
2. hydroelectric plantAwanKhadka2
 
Hydropower engineering -Hydraulics
Hydropower engineering -HydraulicsHydropower engineering -Hydraulics
Hydropower engineering -HydraulicsCivil Zone
 
HYDROLOGY AND WATER RESOURCE MANAGMENT PPT
HYDROLOGY AND WATER RESOURCE MANAGMENT PPTHYDROLOGY AND WATER RESOURCE MANAGMENT PPT
HYDROLOGY AND WATER RESOURCE MANAGMENT PPTKavin Raval
 
Hydro power plant
Hydro power plantHydro power plant
Hydro power plantprem_jovin
 
Hydal power plant
Hydal power plantHydal power plant
Hydal power plantJUNAID SK
 
Hydro electric power plant
Hydro electric power plantHydro electric power plant
Hydro electric power plantDr. Ramesh B
 

Semelhante a UNIT 4.pptx (20)

Hydro electric power plant lecture
Hydro electric power plant lectureHydro electric power plant lecture
Hydro electric power plant lecture
 
Malay nces ppt
Malay nces pptMalay nces ppt
Malay nces ppt
 
Hydroelectric Power.pptx
Hydroelectric Power.pptxHydroelectric Power.pptx
Hydroelectric Power.pptx
 
Spillways, Spillway capacity, flood routing through spillways, different type...
Spillways, Spillway capacity, flood routing through spillways, different type...Spillways, Spillway capacity, flood routing through spillways, different type...
Spillways, Spillway capacity, flood routing through spillways, different type...
 
Presentation1.pptx
Presentation1.pptxPresentation1.pptx
Presentation1.pptx
 
DAMS AND ITS TYPES
DAMS AND ITS TYPESDAMS AND ITS TYPES
DAMS AND ITS TYPES
 
Hydro power plant
Hydro power plantHydro power plant
Hydro power plant
 
Hydropower plants.pdf
Hydropower plants.pdfHydropower plants.pdf
Hydropower plants.pdf
 
2. hydroelectric plant
2. hydroelectric plant2. hydroelectric plant
2. hydroelectric plant
 
Hydroelctric power u3 pwi
Hydroelctric power  u3 pwiHydroelctric power  u3 pwi
Hydroelctric power u3 pwi
 
Hydel Generation and Types Of Turbines
Hydel Generation and Types Of TurbinesHydel Generation and Types Of Turbines
Hydel Generation and Types Of Turbines
 
Hydropower engineering -Hydraulics
Hydropower engineering -HydraulicsHydropower engineering -Hydraulics
Hydropower engineering -Hydraulics
 
typesofdamsPPT
typesofdamsPPTtypesofdamsPPT
typesofdamsPPT
 
HYDROLOGY AND WATER RESOURCE MANAGMENT PPT
HYDROLOGY AND WATER RESOURCE MANAGMENT PPTHYDROLOGY AND WATER RESOURCE MANAGMENT PPT
HYDROLOGY AND WATER RESOURCE MANAGMENT PPT
 
904787
904787904787
904787
 
Hydro power plant
Hydro power plantHydro power plant
Hydro power plant
 
Hydal power plant
Hydal power plantHydal power plant
Hydal power plant
 
Hydro-Electric Power
Hydro-Electric PowerHydro-Electric Power
Hydro-Electric Power
 
Hydro power plant
Hydro power plantHydro power plant
Hydro power plant
 
Hydro electric power plant
Hydro electric power plantHydro electric power plant
Hydro electric power plant
 

Mais de Mrunmayee Manjari

Mais de Mrunmayee Manjari (20)

UNIt 6.pptxkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkk
UNIt 6.pptxkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkUNIt 6.pptxkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkk
UNIt 6.pptxkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkk
 
nnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnn
nnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnn
nnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnn
 
hjgdhjbqwhjgfehbsdjgk2hbekjhjj,mnkjhaklmdkjq
hjgdhjbqwhjgfehbsdjgk2hbekjhjj,mnkjhaklmdkjqhjgdhjbqwhjgfehbsdjgk2hbekjhjj,mnkjhaklmdkjq
hjgdhjbqwhjgfehbsdjgk2hbekjhjj,mnkjhaklmdkjq
 
noise pollution and sources/ lovely professional university
noise pollution and sources/ lovely professional universitynoise pollution and sources/ lovely professional university
noise pollution and sources/ lovely professional university
 
GIS and Remote sensing CIvil Engg by Mrunmayee
GIS and Remote sensing CIvil Engg by MrunmayeeGIS and Remote sensing CIvil Engg by Mrunmayee
GIS and Remote sensing CIvil Engg by Mrunmayee
 
Unit 3.pptx
Unit 3.pptxUnit 3.pptx
Unit 3.pptx
 
UNIt 2.pptx
UNIt 2.pptxUNIt 2.pptx
UNIt 2.pptx
 
zero.pptx
zero.pptxzero.pptx
zero.pptx
 
CIV340.pptx
CIV340.pptxCIV340.pptx
CIV340.pptx
 
New Microsoft PowerPoint Presentation.pptx
New Microsoft PowerPoint Presentation.pptxNew Microsoft PowerPoint Presentation.pptx
New Microsoft PowerPoint Presentation.pptx
 
reserach methodology.pptx
reserach methodology.pptxreserach methodology.pptx
reserach methodology.pptx
 
CIV208 __ FLUID MECHANICS.pdf
CIV208 __ FLUID MECHANICS.pdfCIV208 __ FLUID MECHANICS.pdf
CIV208 __ FLUID MECHANICS.pdf
 
UNIT 5_2.pptx
UNIT 5_2.pptxUNIT 5_2.pptx
UNIT 5_2.pptx
 
CA2B.pdf
CA2B.pdfCA2B.pdf
CA2B.pdf
 
CA1.pdf
CA1.pdfCA1.pdf
CA1.pdf
 
1673948477_Renewable-Energy-Nov2022.pdf
1673948477_Renewable-Energy-Nov2022.pdf1673948477_Renewable-Energy-Nov2022.pdf
1673948477_Renewable-Energy-Nov2022.pdf
 
UNIT 5.pptx
UNIT 5.pptxUNIT 5.pptx
UNIT 5.pptx
 
UNIT 5.pptx
UNIT 5.pptxUNIT 5.pptx
UNIT 5.pptx
 
1111.pptx
1111.pptx1111.pptx
1111.pptx
 
UNIT 5.pptx
UNIT 5.pptxUNIT 5.pptx
UNIT 5.pptx
 

Último

Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort servicejennyeacort
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionDr.Costas Sachpazis
 
Piping Basic stress analysis by engineering
Piping Basic stress analysis by engineeringPiping Basic stress analysis by engineering
Piping Basic stress analysis by engineeringJuanCarlosMorales19600
 
Work Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvWork Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvLewisJB
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerAnamika Sarkar
 
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catchers
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor CatchersTechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catchers
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catcherssdickerson1
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile servicerehmti665
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...VICTOR MAESTRE RAMIREZ
 
Arduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.pptArduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.pptSAURABHKUMAR892774
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.eptoze12
 
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfg
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfgUnit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfg
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfgsaravananr517913
 
Transport layer issues and challenges - Guide
Transport layer issues and challenges - GuideTransport layer issues and challenges - Guide
Transport layer issues and challenges - GuideGOPINATHS437943
 
Electronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfElectronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfme23b1001
 
Concrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxConcrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxKartikeyaDwivedi3
 
An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...Chandu841456
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AIabhishek36461
 

Último (20)

Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
 
Piping Basic stress analysis by engineering
Piping Basic stress analysis by engineeringPiping Basic stress analysis by engineering
Piping Basic stress analysis by engineering
 
Work Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvWork Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvv
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
 
Design and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdfDesign and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdf
 
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catchers
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor CatchersTechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catchers
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catchers
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile service
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...
 
Arduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.pptArduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.ppt
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.
 
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfg
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfgUnit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfg
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfg
 
Transport layer issues and challenges - Guide
Transport layer issues and challenges - GuideTransport layer issues and challenges - Guide
Transport layer issues and challenges - Guide
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
Electronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfElectronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdf
 
Concrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxConcrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptx
 
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
 
young call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Serviceyoung call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Service
 
An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AI
 

UNIT 4.pptx

  • 1. Hydro power and other water borne Renewable energy technologies UNIT 4
  • 2. Introduction Hydroelectric power (often called hydropower) is considered a renewable energy source. A renewable energy source is one that is not depleted (used up) in the production of energy. Through hydropower, the energy in falling water is converted into electricity without “using up” the water. Hydroelectric power (hydropower) systems convert the kinetic energy in flowing water into electric energy.
  • 3. 1. Source of power. 2.Interconnected with steam power plants, base load is supplied by the hydro power plants while the peak load is supplied by steam power plant, when stream flow is less than maximum flow demand. 3.When stream flow is more than the maximum flow demand, base load is supplied by the steam power plants while the peak load is supplied by hydro power plant. Applications
  • 4. Advantages 1. No fuel charges. 2. Any hydro electric plant is highly reliable 3. Maintenance and operation charges are very low. 4. Running cost of plant is low. 5. It has no standby losses. 6. The plant efficiency doesn’t change with age. 7. It take a few minutes to run and synchronize the plant. 8. Less supervising staff is required. 9. No fuel transportation problem. 10. No ashproblem. 11. In addition to power generation these plants are also used for flood control and irrigation purposes. 12. The have long life (100-125yrs, 20-45yrs of thermalplant)
  • 5. Disadvantages • The initial cost is very high. • It takes considerable time for the erection of such plants. • Such plants are usually located in hilly areas far away from the load centre and as such they require long transmission lines to deliver power, hence the cost of transmission linear and losses in them will be more. • Power generation by the hydro-electric plants depend upon quantity of water hence rain.
  • 6. Selection of Site • Availability of water • Water storage • Water head • Accessibility of the site • Distance from the load centre • Type of the land of site
  • 7. 1. CatchmentArea 2. Reservoir 3. Dam 4. Spillways 5. Conduits 6. Surge tanks 7. Prime movers 8. Draft Tubes 9. Powerhouse and Equipment Essential Features & Elements of Hydro electric Power Plant
  • 8. 1. Catchment area: The whole area behind the dam draining into the stream. 2. Reservoir: Used to store water. A. Natural (lake) B. Artificial (dam, called pondage)
  • 9. Dam: barrier to raise water for storage or diversion to create a hydraulic head. Types of dams: A. Fill Dams : Earth dams, Rock Fill Dams B. Masonary Dams: Solid gravity dams, Butteress dams,Arch dams. C. Timber Dams Selection of type of Dam 1. Nature of foundation Sound rock formation in foundation: any type of dam Poor rock and earth foundation: earth dam 2. Nature of valley Narrow valley : arch dam Rocky bed: Solid gravity dam Wide valley weak foundation: Buttress dam Any width of valley, good foundation : Steel Dam
  • 10. Types of Dams • Fill Dams 1. Earth fill dams: earth fill dam, also called Earth Dam, or Embankment Dam, dam built up by compacting successive layers of earth, using the most impervious materials to form a core and placing more permeable substances on the upstream and downstream sides.Afacing of crushed stone prevents erosion by wind or rain, and an ample spillway, usually of concrete.
  • 11. • Arockfill dam is a type of embankment dam which comprises primarily compacted rock materials. Used in mountainous locations where rock is available.
  • 12. Masonry Dams • Solid Gravity Dam: Massiveand bulky and depends upon its weight on stability. • It requires strong rock foundation • Bhakra Dam is the highest Concrete Gravity dam in Asia and Second Highest in the world. • Bhakra Dam is across river Sutlej in Himachal Pradesh • It is 740 ft. high above the deepest foundation as straight concrete dam being more than three times the height of Qutab Minar. • Length at top 518.16 m (1700 feet); Width at base 190.5 m (625 feet), and at the top is 9.14 m (30 feet)
  • 13.
  • 14. Butteress Dam • Is a gravity dam reinforced by structural supports. • A buttress dam or hollow dam is a dam with a solid, water-tight upstream side that is supported at intervals on the downstream side by a series of buttresses or supports. The dam wall may be straight or curved. • Most buttress dams are made of reinforced concrete and are heavy, pushing the dam into the ground. Water pushes against the dam, but the buttresses are inflexible and prevent the dam from falling over • Buttress - a support that transmits a force from a roof or wall to another supporting structure • It has a relatively thin structure. Because of this, these dams often use half as much concrete as gravity dams can be used for weaker foundation.
  • 15. Arch dam • An arch dam is a solid dam made of concrete that is curved upstream in plan. The arch dam is designed sothat the force of the water against it, known as hydrostatic pressure, presses against the arch, compressing and strengthening the structure as it pushes into its foundation or abutments. • An arch dam is most suitable for narrow gorges or canyons with steep walls of stable rock to support the structure and stresses .Since they are thinner than any other dam type,they require much less construction material, making them economical and practical in remote areas.
  • 17. • Timber Dams • When wood in plentiful and more durable material are not accessible timber is used for low dams 12m.
  • 18. Spillways • Aspillway is an integral part of a Dam. • Aspillway is usually used to remove water from a reservoir to prevent overflow and to release pressure on a dam from increasing quantities of water. It is normally composed of three major components: • The approach facility admits flow to the spillway. • The discharging conduit evacuates the flow from the approach facility to an outlet structure. • The outlet structure (tailwater channel) dissipates the excessive energy of the flow from the discharging conduits and conveys tranquil flow to the downstream.
  • 19. Overflow Spillway • Overflow spillways are also called ogee-shaped (S-shaped) spillways. • This type of spillways allows the passage of the flood wave over its crest (which is S-shaped). • Can be classified under controlled or uncontrolled. • Widely used on Gravity dams,Arch dams, and Buttress dams.
  • 20. Chute spillways • Chute spillways are common and basic in design as they transferexcess water from behind the dam down a smooth decline into the river below. • The spillway’s slope and its sides are lined with concrete. • In case of having sufficient stiff foundation conditions at the spillway location, a chute spillway may be used instead of overflow spillwaydue to economic consideration.
  • 21. Side Channel Spillway • It is employed when valley is too narrow in case of solid gravity dams and when non rigid dams are adopted. • The side channel spillway is different from chute spillway in the sense that after crossing over the spillway crest. Water flows parallel to the crest length in former, whereas the flow is normal to the crest in the later.
  • 23. Saddle Spillway • There may be natural depressions or saddle on the peripheryof the reservoir basin away from the dam. The depressions may be used as spillway. • The bottom of the depression should be at full reservoir level.
  • 24. Siphon Spillway • Crest is fixed at Full Reservoir Level. When the water level in the reservoir rises over F.R.L water starts spilling over the crest.
  • 25. Conduit • Aheadrace is a channel which leads water to a turbine anda tailrace is a channel which conducts water from the wheels. • Open Conduit: Canals and Flumes • Close conduits: Tunnels, pipelines and penstock
  • 26. Penstock • Closed conduit for supplying water under pressure to a turbine. • Thinkness of penstock is given by: • T = pd/2fn p = pressure due to water d = diameter of the penstock f = Permissible circumferential stress n = Joint efficiency
  • 27. Surge Tanks • A surge tank is small reservoir or tank in which water level rises of falls to reduce the pressure swings so that they are not transmitted in full to closed circuit. 1. They reduce the distance between the free water surface and turbine thereby reducing water hammer effect ( the change in in pressure rapidly above or below normal pressure caused by sudden changes in the rate of water flow through the pipe according to the demand of the primemover) on the penstock. 2. To serve as supply tank to the turbine in case of increased load conditions, and storage tank in case of low load conditions.
  • 29. Prime movers • Impulse Turbines: Pressure energy of water is converted to kinetic energy when passing through nozzle and forms velocity of high head. • Reaction Turbines: Water pressure combined with the velocity works on the runner, power is developed from the combined action of pressure and velocity of water, that completely fill the runner and water passage.
  • 30. Draft Tubes • It allows the turbine to be set above tail water level, without loss of head, to facilitate inspection and maintenance • It regains, by diffuser action, the major portion of the kinetic energy delivered to it from the runner. 1. Conical Type: used on low powered units for all specific speeds and frequently od large head units. Side angle 4 to 6 deg. 2. Elbow Type: Mostly used, vertical portion is a conical section which gradually flattens in the elbow section and then discharges horizontally.
  • 32. Types of Power Plants
  • 33. High Head Power Plant Head: 100m to 2000m Water is stored in the lake over the mountain during high rainy season or when snow melts. Water should be available throughout the year. Pelton Wheel turbine is used.
  • 34. Medium Head Plants • Head : 30 to 100m • Uses FrancisTurbine • Forebay provided at the beginning of penstock at asreservoir. • Water is carried in open canals from main reservoir to forebay thento powerhouse through penstock.
  • 35. Low Head Power Plants • They consist of dam across the river. • Asideway stream diverges from the river at the dam, powerhouseis constructed over the stream, which further joins theriver. • Vertical shaft Francis or Kaplan turbine
  • 36. According to Nature of Load Base Load Plants: they cater to the base load of the system, they need to supply constant power when connected to the grid. Peak Load Plants: some of the plants supply average load but also some peak load. Other peak load plants are required to work only during peak load hours.
  • 37. According to the quantity of water 1. Run of river plants without pondage: • No pondage. • No control on flow of water. 2. Run of river plants with pondage May work as base load or peak load plants. Storage for a week 3. Storage Type Plant The storage is large. Used as base load and peak load plants Controlled flow .
  • 38. 4. Pumped Storage plants • These plants are employed where quantity of water required is inadequate. • Water passing through the turbine is stored in the tail race pond. During low load periods the water is pumped back to the reservoir, which can be used during peak load plants. • Usually interconnected with steam or diesel power plants.
  • 39. Mini & Microhydel plants • Mini – 5m to 20 m head • Micro – below 5 m head • These plants are scattered in our country and estimated potential is 20,000MW. • Each plant generate about 100 to 1000kW per unit.
  • 41. According to the head and quantity of water • Impulse Turbine: Requires high head and small flow of water. • Reaction Turbine: Requires low head and high rate of flow of water.
  • 42. According to the name of originator • Pelton Turbine: It is an impulse type of turbine used for high head and low discharge. • Francis Turbine: It is reaction type of turbine, used for medium high to medium low heads and medium small to medium large quantities of water. • Kaplan Turbine: It is reaction type of turbine, used for low head and large quantities of flow.
  • 43. According to action of water on the moving blades • Impulse: Pelton • Reaction: Kaplan, Francis, Propeller.
  • 44. According to direction of flow of water in runner • Tangential flow turbine (PeltonTurbine) • Radial flow turbine ( not used) • Axial flow turbine (KaplanTurbine) • Mixed (radial and axial ) flow turbine (Francisturbine)
  • 45. According to the position of turbine shaft • Shaft may be horizontal or vertical • Pelton has horizontal axis
  • 46. According to specific speed • The specific speed is defined as the speed of a geometrically similar turbine that would develop one brake power horsepower under the head of one meter.
  • 47.
  • 48. Impulse Turbine-Pelton Turbine • Tangential flow impulse turbine. • Rotor has equally spaced hemispherical buckets, Water is transferred from high head source through penstock pipes. • All the available potential energy is converted to kinetic energy before the jet strikes the buckets. • The pressure all over the wheel is constant and equal to atmospheric pressure, energy transfer occurs due to purely impulse action.
  • 49. Reaction Turbine • The runner utilizes both potential and kinetic energy. • As the water flows through the stationary part of the turbine, whole of its pressure energy is not transferred to kinetic energy. When the water flows through the moving parts, there is a change both in the pressure and in the direction and velocity of flow of water. • The water which acts on the runner blades is under pressure above the atmospheric.
  • 50. Francis Turbine • It is an inward mixed flow reaction turbine i.e. water under pressure , enters the runner form the guide vanes towards the centre in the radial direction and discharges out of the runner axially. • It runs under medium heads and requires medium quantity of water. • Water is brought down to the turbine and directed to a number of stationary guide vanes. • The head acting on the turbine is partly transformed into kinetic energy and rest remains as pressure head. • The runner is always full of water. The movement of runner is affected by the change of both the potential and the kinetic energies of water. • The water is then discharged to the tail race, through draft tube.
  • 51.
  • 52. Propeller & Kaplan Turbines • Propeller turbine is a reaction turbine used for heads between 4m to 80 m and specific speed of 300 to 1000. • Axial Flow Type • It consists of axial flow runner • With 4-6 or max 10 blades of air foil shape In Propeller Runner blades are fixed and non adjustable as in Francis Turbine. In Kaplan Turbine which is a modification of propeller turbine the runner blades are adjustable and can be rotated aboutpivots fixed to the base.
  • 54. Tubular/Bulb Turbine • It is a modified axial flow turbine, the turbo generator set using the bulb/tubular turbine has the outer casing of the shape of a bulb. • The turbine generator set is called bulb set and turbine used is called bulb turbine. The bulb unit is a water tight assembly of turbine and generator with horizontal axis, submerged in a stream of water.
  • 56. Governing of Hydraulic Turbines • Governing means the speed regulation. Under normal conditions the turbine should run at constant speed irrespective of changes in the load. • This is achieved by means of a governor called oil pressure governor.
  • 57. Governing of Impulse turbines • The quantity of water rejected from turbine nozzle and from striking the buckets may be regulated in following ways: • Spear regulation: To and fro motion of spear inside the nozzle alters the cross sectional area of the stream. • Deflector regulation: the deflector is generally a plate connected to the oil pressure governor by means of levers. When it is required to deflect the jet, the plate can be brought in between the nozzles and buckets, thereby diverting the water away from the runner and directing into tailrace. It is used when supply of water is constant but load fluctuates. • Combined spear and deflector regulation: the speed is regulated by spear and pressure is regulated by deflector
  • 58.
  • 59. Governing of Reaction Turbines • The guide blades of reaction turbine are pivoted and connected by levers and links to the regulating ring. • To the regulating ring are attached two long regulating rods connected to the regulating lever. • The regulating ring is keyed to the regulating shaft which is turned by servomotor piston of oil pressure governor. • The penstock which feeds the turbine inlet is has relief valve know as pressure regulator. • When guide vanes have to be suddenly closed the relief valve opens and diverts the water to tailrace.
  • 60.
  • 61. Hydrology • It may be defined as the science which deals with the depletion and replenishment of water resources.
  • 62.
  • 64. 3. Run off tables and curves • Hydrograph: It is defined as graph showing discharge(run off) of flowing water with respect to time for a specified time. • It indicates the power available from the stream at different times of day, week or year. • Unit Hydrograph: It is a hydrograph which represents unit run off resulted from an intense rainfall of unit duration and specified areal distribution.
  • 65.
  • 66. Flow Duration Curve • Is a plot of discharge against the percentage of time the flow was equaled or exceeded. • It is the curve plotted between the flow available during a period verses fraction of time. • The area under the flow of the duration curve gives the total quantity of run-off during that period.
  • 67.
  • 68.
  • 69.
  • 70.
  • 71.
  • 72.
  • 73. • Aflow duration curve allows the evaluationof low levels of flow. • It is highly useful in the planning and design of water recourses. • It also finds use in the design of drainage system and in flood control studies.
  • 74. Mass Curve • Mass curve is the graph of cumulative values of water quantity (run off) against time.Amass curve is integral curve of the hydrograph which expresses the area under the hydrograph from one time to another.