S.No. Name of unit Date of Name of Products Annual Capacity Proposed Proposed Remarks
Signing Investment Distt.
(Crores)
1 2 3 4 5 6 7 8
1 Jindal Organization 21/05/2001 1- Rail & Beam Mill 75000 TPA 1900.00 Raigarh
New Delhi 2- C.P.P. 110 MW
3- Steel Products 205000 TPA
4- Coal Washery 2500000 TPA
5- Aluminium Plant 50000 TPA
6- Ferro Chrome Plant 60000 TPA
7- DRI Plant 450000 TPA
8- Mini Blast Furnace (351Cum) 250000 TPA
9- Development of additional
coal mines
2 Monnet Group of 21/05/2001 1- Steel Products 300000 TPA 570.00 Raipur
Companies, Mandir 2- C.P.P. 55 MW
Hasoud, Raipur
3- Sponge Iron 300000 TPA
4- Structural Rolling Mill 300000 TPA
5- Ferro Alloys 50000 TPA
1- Steel Bar & Section making 150000 TPA 590.00 Raigarh
2- Sponge Iron Plant 300000 TPA
3- Steel Ingot Making Facility 150000 TPA
4- Coal Mining & Washery 110000 MT
5- Power Plant 70.5 MW
3 Bhushan Ltd., New 7/11/2001 1- Steel Products 1200000 MT 2285.00 Korba Cancelled
Delhi 2- Power Plant 270 MW
3- Coal Washery 4500000 MT
4 Bharat Aluminium 29/05/2002 1- Expansion of Aluminium 300000 TPA 6000.00 Korba
Company , Korba Smelter Plant
2- Power Plant 600 MW
5 Chmoku Agro & Spices 13/08/2002 1- Various Food Product (Food 50.00 Durg
Ltd., Bangalore Park)
MDsipb2MOUMOU_Progress(Eng)Web Page 1 of 13
2. S.No. Name of unit Date of Name of Products Annual Capacity Proposed Proposed Remarks
Signing Investment Distt.
(Crores)
1 2 3 4 5 6 7 8
6 Agio Industries Pvt. 8/13/2002 1- Sponge Iron Plant 30 TPD 80.00 Bilaspur Cancelled
Ltd., Bilaspur (Shri 2- Waste Heat Power Plant 8 MW (Phase-I)
M.L.Jalan NRI Moscow) 3- Steel Melting Shop 24000 TPA
4- Coal & Iron Ore Mining
1- Power Generation 7.5 MW 35.00 Raigarh
2- SMS & Concost - one furnace
1- Sponge Iron Kiln 300 TPD 65.00 Bilaspur
2- Waste Heat Power Plant 8 MW (Phase-II)
7 Jindal Steel & Power 23/10/2002 1- Private Industrial State 11.00 Raigarh
Ltd., New Delhi Raigarh
8 M.S.P. Steel & Power 3/2/2003 1- Sponge Iron Plant 400000 MT 175.59 Raigarh
Pvt. Ltd., Kolkata 2- M.S. Ingot/Billets Plant 210000 MT
3- Power Plant 20 MW
4- Coal Washery 72000 TPA
5- Captive Coal Mines 600000 TPA
9 Sunil Sponge Iron Ltd. 3/2/2003 1- Sponge Iron Plant 90000 TPA 105.11 Raipur
Kolkata 2- Steel Plant 100000 TPA
3- Power Plant 14 MW
10 VISA Industries Ltd., 5/3/2003 1- Sponge Iron Plant 450000 TPA 1015.00 Raigarh
Kolkata 2- Captive Power Plant 105 MW
3- Steel Plant 200000 TPA
4- Ferro Chrome Plant 75000 TPA
5- Captive Coal Mine & 2000000 TPA
Washery
6- Marchant Coal Washery 5000000 TPA Korba
7- F.B.B. Power Plant 20 MW
11 Ind Agro Synergy Ltd. , 5/3/2003 1- Sponge Iron, Stell Billet 400000 TPA 413.00 Raigarh
Nagpur 2- Power Plant 8 MW
3- Coal Washery 1.26 MTPA
12 Sun Vijay Rolling & 4/21/2003 1- Sponge Iron Plant 320000 MT 465.00 Raigarh Cancelled
Engg. Ltd., Nagpur 2- MS Ingot & Billets 200000 MT
3- Rolling Mill 100000 MT
4- Power Plant 40 MW
5- Coal Washery
6- Coal Mining
7- Iron Ore Mining & Others
MDsipb2MOUMOU_Progress(Eng)Web Page 2 of 13
3. S.No. Name of unit Date of Name of Products Annual Capacity Proposed Proposed Remarks
Signing Investment Distt.
(Crores)
1 2 3 4 5 6 7 8
13 Anjani Steel (P) Ltd., 17/07/2003 1- Sponge Iron Plant 180000 TPA 185.00 Raigarh
AIlahabad 2- Captive Power Plant 10 MW
3- Steel Plant 150000 TPA
4- Coal Mines
14 Superior Sponge Iron 29/08/2003 1- Sponge Iron Plant 200000 TPA 330.00 Durg
Pvt. Ltd. & Other 2- Power Plant 24 MW
Associate Companies,
3- Pig Iron Plant 150000 TPA
New Delhi
4- Steel Melting Shop 300000 TPA
5- Rolling Mill 225000 TPA
6- Coke Oven Unit 100000 TPA
15 Navbharat Group of 8/9/2003 1- Sponge Iron Project 500000 TPA 1460.00 Raipur And
Companies Raipur 2- Captive Power Plant 16 MW Bastar
3- Steel Plant
4- Coal Mining & Washery 5000000 TPA
5- Power Plant 200 MW
6- Integrated Sugar Plant 2500 TCD
16 Akshay Investment Pvt. 8/9/2003 1- Sponge Iron Plant 90000 TPA 115.00 Rajnadgaon
Ltd., Raipur 2- Captive Power Plant 14 MW
3- Induction Furnance Unit 105000 TPA
4- Captive Coal Mines
5- Captive Iron Ore Mines
17 Vandana Energy & 8/9/2003 1- Coal based Sponge Iron 150000 TPA 145.00 Raipur And
Steels (P) Ltd. Raipur Plant Raigarh
2- Captive Power Plant 16 MW
3- Integrated Steel Plant
4- Captive Coal Mine &
Washery
5- Merchant Coal Washery
18 Shri Bajrang Power & 8/9/2003 1- Sponge Iron Plant 90000 TPA 130.00 Raipur
Ispat Ltd. Raipur 2- Power Plant 25 MW
3- Pig Iron Plant (Mini Blast 60000 MT
Furnace )
19 National Steel and Agro 8/9/2003 1- Sponge Iron Plant 150000 TPA 150.00 Durg
industries Ltd. Mumbai 2- Waste Heat Power Plant 25 MW
3- Steel Melting Shop 150000 TPA
MDsipb2MOUMOU_Progress(Eng)Web Page 3 of 13
4. S.No. Name of unit Date of Name of Products Annual Capacity Proposed Proposed Remarks
Signing Investment Distt.
(Crores)
1 2 3 4 5 6 7 8
20 Aryan Ispat & Power 16/08/2004 1- Sponge Iron Plant 460000 TPA 860.00 Raipur
Pvt. Ltd., Bilaspur 2- Steel Billets 348000 TPA
3- Power Plant 116 MW
4- Coal Washri
21 Godavari Power & Ispat 16/08/2004 1- Sponge Iron Plant 650000 TPA 493.00 Raipur
Ltd., Raipur 2- Steel Billets / Ingots 550000 TPA
3- Power Plant 50 MW
4- Ferro Alloys 33000 TPA
5- HB/GI/Barbed & other Wires 30000 TPA
6- Iron Ore & Coal Mines 3000000 TPA
22 Allaince Integrated 16/08/2004 1- Mini Steel Plant 150000 PT 475.00 Raipur
Metalics Ltd., New Delhi 2- Captive Power Plant 24 MW
3- Sponge Iron 200000 TPA
4- Auto Components 25000 TPA
23 Vandana Global Ltd., 16/08/2004 1- Sponge Iron 351000 MT 426.00 Raipur
Raipur 2- Power Plant 80 MW
3- Furnesh (Ingots/ Billets) 167520 MT
4- Crusher Plant 360000 MT
5- Ferro Alloys (Silico Maganies) 48000 MT
24 S.K.S. Ispat Pvt. Ltd., 16/08/2004 1- Sponge Iron 270000 TPA 295.47 Raipur
Mumbai 2- Power Plant 25 MW
3- Steel Melting Shop 210000 TPA
4- Rolling Mill 210000 TPA
25 Magnum Steel Ltd., 16/08/2004 1- Sponge Iron 300000 TPA 212.00 Raipur
New Delhi 2- Semis & Rolled Products 300000 TPA
3- Power Plant 30 MW
26 GPT Metal Industries 16/08/2004 1- Sponge Iron 105000 MT 139.00 Raipur
Ltd., Kolkata 2- Power Plant 16 MW
3- Iron Ore Mining
4- Industion Furnesh 60000 TPA
27 BEC Projects Ltd., 16/08/2004 1- Sponge Iron 135000 MT 129.00 Durg Cancelled
Bhilai 2- Power Plant 15 MW
MDsipb2MOUMOU_Progress(Eng)Web Page 4 of 13
5. S.No. Name of unit Date of Name of Products Annual Capacity Proposed Proposed Remarks
Signing Investment Distt.
(Crores)
1 2 3 4 5 6 7 8
3- Steel Melting Shop
28 Chhattisgarh Iron & 16/08/2004 1- Sponge Iron 105000 MT 115.65 Durg or
Steel Co. Pvt. Ltd., 2- West Hit Power Plant 15 MW Raigarh
Mumbai
3- Steel Melting Shop 100000 MT
29 Mega Power Builders & 16/08/2004 1- Sponge Iron 105000 TPA 115.00 Durg or
Developers Pvt. Ltd., 2- West Hit Power Plant 15 MW Raigarh
Mumbai
3- Steel Melting Shop 100000 TPA
30 Anand Ispat Udyog Pvt. 16/08/2004 1- Sponge Iron 150000 TPA 110.00 Dantewada
Ltd., Bhilai 2- Power Generation 10 MW
3- Industion Furnesh & Concost 130000 TPA
4- Mining & Equipment
31 Feral Enginnering 13/09/2004 1- D.R.I. 200000 MT 100.00 Chhattisgarh
Limited, Londan 2- Power 10 MW
3- Steel Melting Shop 10000 MT
32 Laiteg Asia Limited, 13/09/2004 1- Power Plant 125.00 Chhattisgarh
Londan & Lenco 2- Fly ash - Building Material
Amarkantak Power Pvt.
Ltd., Hyderabad
33 Jindal Steel & Power 1/7/2005 1- Plate Mill 1000000 TPA 2595.00 Raigarh
Ltd., New Delhi 2- Blast Furnance 1225000 TPA
3- Rolling Mill for Re-Bar, TMT 70000 TPA
and Wire Rce
4- Power Plant 99 MW
5- Steel Melting Shop 1225000 TPA
6- Sinter Plant 2500000 TPA
7- Cock Oven Plant 800000 TPA
8- Oxygen Plant 2 x 380 TPD
9- Lime & Dolomite Kiln 3 x 330 TPD
10- Railway Line from Captive -
Coal Mines to Plant Site
34 Chhattisgarh Electricity 1/7/2005 1- Sponge Iron Plant 120000 TPA 2010.00 Raipur
Company Ltd., Raipur 2- Power Plant 250 MW
3- Steel Plant 1000000 TPA
4- Cock Oven 400000 TPA
5- Pelletizing and Sintering 1800000 TPA
MDsipb2MOUMOU_Progress(Eng)Web Page 5 of 13
6. S.No. Name of unit Date of Name of Products Annual Capacity Proposed Proposed Remarks
Signing Investment Distt.
(Crores)
1 2 3 4 5 6 7 8
6- Coal Mining & Coal Washery -
35 Prakash Industries 1/7/2005 1- Cock based Sponge Iron 400000 TPA 1017.00 Janjgir
Limited, New Delhi Plant (DRI Plant) Champa
2- Captive power plant (Co- 25 MW
generation of power)
3- Captive power plant, coal 190 MW
based (fluidized bed boiler &
thermal boiler)
4- Steel Billets/Blooms/Ingots 900000 TPA
making facility (Steel melting
shop-II)
5.a- Development of captive coal 1000000 TPA
mines
5.b- Development of captive coal 1000000 TPA
mines for captive power plant,
together with coal washery
project
6- Development of Iron Ore 1000000 TPA
Mine in the state of
Chhattisgarh with crushing
plant in mines
7- Mini blast furnace for Pig Iron 250000 TPA
8- Sub-merge Arc Furnace 115000 TPA
(SAF) for producing Silico
Management & Ferro Chrome
9- Structural Rolling Mill (2 unit - 300000 TPA
1.5 LTPA each)
10- Wire Rod Mill (2 unit - 1.5 300000 TPA
LTPA each)
36 Bigboss Steel & Alloys 1/7/2005 1- Integrated Steel Plant 700.00 Janjgir
Limited, Kolkata 2- Power Plant Champa
37 Vasundhara Steel & 1/7/2005 1- Integrated Steel Plant with 400000 TPA 465.00 Janjgir
Power Limited, New Captive Power Champa
MDsipb2MOUMOU_Progress(Eng)Web Page 6 of 13
7. S.No. Name of unit Date of Name of Products Annual Capacity Proposed Proposed Remarks
Signing Investment Distt.
(Crores)
1 2 3 4 5 6 7 8
Delhi 2- Coal based captive power 82 MW
plant with WHRB and AFBC
38 Rexon Strips Ltd., 1/7/2005 1- Integrated Steel Plant with 400000 TPA 465.00 Bilaspur
Rourkela, Orissa Captive Power
2- Coal based captive power 82 MW
plant with WHRB and AFBC
39 Chhattisgarh Steel & 1/7/2005 1- Power Generation (3 x 30 112.5 MW 464.88 Janjgir
Power Ltd., Raipur MW Coal + 3 x 7.5 MW WHR Champa
based)
2- Sponge Iron (3 x 350 TPD) 380000 TPA
40 Pushp Steel & Mining 1/7/2005 1- Sponge Iron Plant (350 TPD 315000 TPA 380.00 Durg
Pvt. Ltd., Delhi x 3)
2- Captive Power Plant (8 x 3) 24 MW
3- Low Pollution (Euro-IV & V)
compliant automotive parts
made out of captive materials
41 Salasalar Sponge & 1/7/2005 1- Sponge Iron Plant 120000 TPA 287.51 Raigarh
Power Limited, Raipur 2- Coal Washery 576000 TPA
3- Power Plant 30 MW
4- Steel Plant 100000 TPA
5- Ferro Alloys 20000 TPA
42 Shree Radhe Industries 1/7/2005 1- Sponge Iron Plant 260000 TPA 232.50 Bilaspur
Ltd., Bilaspur 2- Captive Power Plant 34 MW
3- Steel Melting Shop 50000 TPA
43 Satyarth Steel & Power 1/7/2005 1- Coal based Sponge Iron 219999 TPA 175.00 Raipur
Pvt. Ltd., Raipur Plant
2- Captive Power Plant 131400 MW
3- Steel Plant (Induction 182500 Tonne
Furnace)
4- Re-Rolled Products 31400 TPA
44 API Ispat & Powertech 1/7/2005 1- Sponge Iron Plant (350 TPD 315000 TPA 158.00 Raipur
(P) Ltd., New Delhi x 3)
2- Power Plant 16 MW
3- Steel Ingots (12 MT x 2) 86400 TPA
45 Topworth Steels Pvt. 1/7/2005 1- Sponge Iron Plant 120000 TPA 129.00 Durg
Ltd M b i
MDsipb2MOUMOU_Progress(Eng)Web Page 7 of 13
8. S.No. Name of unit Date of Name of Products Annual Capacity Proposed Proposed Remarks
Signing Investment Distt.
(Crores)
1 2 3 4 5 6 7 8
Ltd., Mumbai 2- Power Plant 15 MW
3- Steel Melting Shop, Concast 100000 TPA
rolling mill
46 Shree Shyam Global 1/7/2005 1- Sponge Iron Plant 165000 TPA 124.00 Raipur
Pvt. Ltd., Janjgir- 2- Power Plant 8 MW
Champa
3- Induction Furnace 72000 TPA
4- Re-rolling Mill (Structural) 60000 TPA
47 Crest Steel & Power (P) 1/7/2005 1- Sponge Iron Plant 210000 TPA 116.50 Durg
Ltd., Bhilai 2- Thermal Power Plant 16 MW
3- Ferro Alloys 18 MVA
48 Balaji Vidyut & Sponge 1/7/2005 1- Sponge Iron Plant 60000 TPA 105.01 Raipur Cancelled
Pvt. Ltd., Raipur 2- Captive Power Plant 15 MW
3- Ferro Alloys (6 MVA) 15000 TPA
49 Texas Powergen, USA 22/05/2005 1- Thermal Power Plant 1000 MW 5550.00 Chhattisgarh
2- Sponge Iron 720000 TPA
3- Induction Furnace 216000 TPA
4- Rolling Mill 216000 TPA
5- Captive Power Plant 100 MW
6- Coal Washery 720000 TPA
7- Structural Mill 100000 TPA
50 Tata Steels Ltd., 4/6/2005 1- Integreated Steel Plant 5000000 TPA 10000.00 Bastar
Mumbai
51 Essar Steel 5/7/2005 1- Integreated Steel Plant 3200000 TPA 7000.00 Dantewada
Chhattisgarh Ltd.,
Hazira
52 Shri Bajrang Power & 10/6/2006 1- Coke Oven Battery 2.00 mTPA 1400.00 Raipur Expansion
Ispat Ltd. Raipur 2- Sinter Plant 2.27 LTPA
3- Blast Furnace with Pig 2.31 LTPA
Casting Machine
4- Steel Melting and Continuous 2.70 LTPA
Casting Shop
5- Sponge Iron (DRI) Plant 6.00 LTPA
6- Captive Power Plant 100 MW
7- Re Bar Mill 1.00 LTPA
8- Section Mill 1.00 LTPA
9- Oxygen Plant 0.60 mCMPA
10- Bauxite Calcinations Plant 3.00 LTPA
MDsipb2MOUMOU_Progress(Eng)Web Page 8 of 13
9. S.No. Name of unit Date of Name of Products Annual Capacity Proposed Proposed Remarks
Signing Investment Distt.
(Crores)
1 2 3 4 5 6 7 8
11- Coal Washery 5.00 mTPA
12- Pelletization Plant 1.00 mTPA
13- Ferro Alloys 36000 TPA
53 Ind Synergy Ltd. , 10/6/2006 1- Sponge Iron 4.00 LTPA 960.00 Raigarh Expansion
Nagpur 2- Captive Power Plant 132 MW
3- Coke Oven & Washery 210 MT/hr
4- Blast Furnace 450.00 Cu.Mtr
54 S.K.S. Ispat Pvt. Ltd., 10/6/2006 1- Sponge Iron 3.30 LTPA 1175.00 Raipur Expansion
Mumbai 2- Captive Power Plant 130 MW
3- SMS / Concast 2.37 LTPA
4- Rolling Mill 1.60 LTPA
5- Ferro Alloys 2 x 9 MVA
6- Coal Washery 1.00 mTPA
7- Mini Blast Furnace 5.00 LTPA
8- Coke Oven / Sinter Plant 11.00 LTPA
9- Arc Furnace 8.00 LTPA
10- Oxygen Plant 10.00 TPD
11- Rolling Mill Special Steel 6.00 LTPA
55 Raipur Alloys & Steel 10/6/2006 1- Sponge Iron 5.00 LTPA 720.00 Raipur Expansion
Limited, Raipur 2- Steel 2.40 LTPA
3- Captive Power Plant 40 MW
4- Structural Rolling Mill 2.00 LTPA
5- Coal Washery 4.00 LTPA
56 Lafarge India Private 10/6/2006 1- Clinker 1.50 mTPA 515.00 Raipur Expansion
Limited, Mumbai 2- Blended Cement 0.10 mTPA
57 Ambuja Cement 12/7/2006 1- Blended Cement 0.60 mTPA 850.00 Raipur Expansion
Eastern Limited, Raipur 2- Clinker 2.72 mTPA
3- Captive Power Plant 48 MW
58 Shri Bajrang Metalics & 12/21/2006 1- Ribd Bar Mill 1.25 LTPA 109.41 Raipur Expansion
Power Ltd., Raipur 2- Captive Power Plant 12 MW
3- Pig Iron 0.60 MW
59 Rajesh Strips Ltd., 1/16/2007 1- Steel Melting Shop 3.00 LTPA 120.00 Raipur Expansion
R i
MDsipb2MOUMOU_Progress(Eng)Web Page 9 of 13
13. S.No. Name of unit Date of Name of Products Annual Capacity Proposed Proposed Remarks
Signing Investment Distt.
(Crores)
1 2 3 4 5 6 7 8
Note :
5 MoUs mentioned in sl. no. 3, 6, 12, 27 & 48 are cancelled. Total No. of efective MoUs 75 &
proposed investment Rs. 85,934 Crore.
MDsipb2MOUMOU_Progress(Eng)Web Page 13 of 13