WHAT IS BRIDGE ??
-WHEN THE WATER WAY IS MORE THAN 6 METER THE CROSS-DRAINAGE
STRUCTURE IS PROVIDED TO CROSS STREAMS AND OTHER BODIES OF WATER
IS CALLED BRIDGE.
-A BRIDGE SHOULD BE DESIGNED TO CARRY IRC STANDARD LOADING WITH
REASONABLE AMOUNT OF SAFETY, AND SHOULD FIT INTO THE SURROUNDING
LANDSCAPE.
Highway Engineering
Bridge and Location of a Bridge
Ideal Location For a Bridge Site
 A straight reach of a river, so that the piers of
the bridge can be located parallel to the direction
of flow.
 There should be steady regime of a river and
absence of serious whirls or cross-currents.
 Availability narrow and well defined channel.
 Absence of a sharp curve e in approaches, so that
Scouring(erosion) and Silting(deposition) action
can be prevented.
Ideal Location For a Bridge Site
 Preferring reasonable
proximity(availability) to the direct
alignment of road to be served .
 Rocky or other compact and non-erodable
bed is preferrable.
Factors affecting selection of Bridge
Site
 Width of a River:- The site at which there is least width of
the river is available is suitable for construction of a
bridge.
 A Straight Approach:- Cross-section of a bridge should be
straight as far as possible, because a straight bridge is far
more stable than a curved bridge.
 River Banks:-
 Velocity of the Flow:- The place where the velocity of the
water flow is min. considering the width of the river is
suitable for bridge cons.
Factors affecting selection of Bridge
Site
 Free Board:-
 Absence of Scouring and Silting:- There
should be no erosion and deposition of the
rock and other materials like sand, silt, gravel,
on either side of the river. This can cause a
failure to the piers of the bridge..
 No confluence of large Tributaries:-
Construction of a bridge should be carried out
at such a site where no large tributaries of
rivers meet.
Data to be collected for location of a
Bridge Site
 Type of soil:- Necessary information about the soil type and its
condition should be collected by the geologist/engineer and should
ensure that the soil bed conforms the I.S. for the particular bridge const.
 Avail. of Electricity:-Ample amount of electricity and its sources and
substitutes should be made available in const. of a bridge site.
 Avail. of Skilled&Unskilledlabours:- Construction of different
components of bridge needs different type of labours in considerable
amount .
 Hydrological Data:- Collection of info. about the Rainfall, Run-off,
Infiltration by soil, Evaporisation, Velocity of flow etc .
 Avail. of Const. Material:- More than ample amount of const. material
should be available at all time.
Data to be collected for location of a
Bridge Site
 Possibility of Navigation Facilities:- Navigation of heavy
machinery should be possible at site.
 Possibility of Earthquake:- A site for bridge const. should be
least prone to earthquake, and necessary data of past EQ should
be collected and acc. to it bridge should be designed.
 Present and Future Traffic Volume:- The width of a carriage
way of bridge should fulfill the traffic requirements of the
present and future conditions of the surrounding areas.
FIELD SURVEY.
Before a highway alignment is finalised in highway project,
the engineering surveys are to be carried out. And these
surveys are carried out in four stages. The first three stages
consider all possible alternate alignment i.e. various
requirements of highway alignment and fourth stage is
meant for detailed survey of the selected alignment.
STAGES OF ENGINEERING SURVEYS.
THE FOUR STAGES OF ENGINEERING
SURVEYS:-
1. Mapstudy
2. Reconnaissance
3. Preliminarysurveys
4. Finallocationanddetailedsurveys
MAP STUDY
It is a kind of study of topographic map of an area,
so as to suggest the possible routes of the road.The
main features like river , hills , valley etc are also
shown in this map. By careful study of such maps , it
is possible to have an idea of several alternate
routes of the road.
Details from the map.
 Alignment avoiding valleys , ponds or lakes.
 In hills , possibility of crossing through a
mountain pass.
 Approximate location of bridge site for
crossing rivers.
 Alternate route with permissible gradient.
RECONNAISSANCE
It is a second stage of surveys and used to examine the
general character of the area for deciding the most feasible
routes for detailed studies. A field surveyor may inspect a
fairly broad stretch of land along the proposed alternative
routes of the map in the field.
OBJECTIVES
 To obtain general knowledge of the entire
territory.
 To obtain specific information of salient
features of the area.
 To collect information about the soil type along
the route.
 To collect information about sources of
construction materials.
PRELIMINARY SURVEY
OBJECTIVES
1. To conduct the survey for alternate alignments propose
after reconnaissance.
2. To compare the different proposals in view of the
requirement of a good alignment.
3. To collect necessary physical information and details of
topography, drainage and soil.
4. To estimate quality of earth work materials.
Procedure of preliminary survey
1. Primary traverse.
The first step in the preliminary survey is to establish the primary
traverse following the line recommended in the reconnaissance.
2. Topographical features.
All geographical and other man made features along the transverse
and for a certain width are surveyed and plotted.
3. Levelling work.
Levelling work is also carried out side by side to give the center line
profiles and typical cross section.
4. Drainage studies and Hydrological data.
Drainage investigations and hydrological data are collected so as to
estimate the type, number and approximate size of cross drainage
structures.
5. SOIL SURVEY
It is an essential part of preliminary survey and by help of this
survey final location is being decided.
6. MATERIAL SURVEY
This survey is done for naturally occurring materials like
stone aggregates and identification of suitable quarries.
7. TRAFFIC SURVEY
This survey is conducted in the region for deciding the
number of traffic lanes and roadway width, pavement
design and economic analysis of highway project.
8. DETERMINATION OF FINAL CENTER LINE
After completing the preliminary survey and conducting the
comparative studies of alternate alignments the final
center line of the road is to be decided before the final
location survey.
FINAL LOCATION AND DETAILED SURVEY
The alignment finalised after the preliminary survey then detailed
survey is carried out for the preparation of plans and construction
details.
The location survey is carried out in two stages;
1. On paper location
2. Field location
1. On paper location.
The final route is put on the drawings and details such as gradient
, radius of curves etc are marked clearly.
2. Field location
On paper location is transferred to the field within help of transit
theodolite and precise level.
DETAILED SURVEY
 Temporary bench marks are fixed at the at the interval
of 250m.
 Vertical alignment , earth work and drainage details
are worked out from level notes.
 A detailed soil survey is carried out and soil profile is
established.
 Work on all rivers and valley are surveyed in detail up
to considerable distance on either sides.
DRAWING REQUIRED FOR HIGHWAY
PROJECT
 IN A HIGHWAY PROJECT,THE FOLLING
DRAWING ARE REQUIRED:-
 KEY PLAN
 INDEX MAP
 PRELIMINARY SURVEY PLANS
 DETAILED PALNS
 LONGITUDINAL SECTION
 CROSS SECTION
 LAND ACQUISITION PLANS
 DEAWING OF ROAD INTERSECTION
KEY MAP
 It shows how actually the project has to be
done
 Map showing proposed and existing roads
 Importatant places to be connected
 Size of the map should not exceed
240x330mm(A4 size)
 Scale should be chosen depending upon the
area
INDEX MAP
 It shows how actully the highway project
looks like
 It shows the general topography of the area
 Details are symbolically represented
 Size of the map should not exceed
240x330mm(A4 size)
 The usual scale is 1cm=0.5km
PRELIMINARY SURVEY PLANS
 It shows the details of various alternative
alignments
 It shows all the information collected during
preliminaery survey
 Its size from 240x330mm(A4 size) to
880x1230mm(A0).
 Scale 10cm=1km
DETAILED PALNS
 It shows the ground plan with alignment and
boundaries,countour at interval 1 to 2 m in
plain country and 3 to 6 m in hilly areas.
 Size of the drawing may b 625x880 mm
 It should also the existing structures ,rivers
,physical features ,etc.
LONGITUDINAL SECTION
 The Longitudinal section(L-section) should be
drawn to a horizontal scale of 1:2000 and a
vertical scale of 1:2000
 The levels should be taken at 50m intervals for
plain and rolling terrain and at 25m interval for
hilly terrain.
 The L-section should have information like
chainages ,horizontal and vertical alignment
,datum level ,ground level ,formation level
,depth of cutting ,height of filling ,posiotion of
cross-roads etc
CROSS-SECTION
 It should be drawn at to nstural scale of 1cm=2-
2.5 m
 It should be drawn in every 100m or where
abrupt changes in level
 It should include cross-section number,the
reduced distances and the area of cutting and
filling.
 In hill roads cross section should be drawn at
closer intervals.
LAND ACQUISITION PLANS
 It shows the land acquisition details.
 Generl details like building, wells, nature of
gradients and others details required for
assessing the values.
 The scale adpoted may b 1cm=40m or less.
 Drawing of road intersections should be
prepared showing all details of pavement ,
islands etc.

More Related Content

What's hot

Bridge engineering
Bridge engineeringBridge engineering
Bridge engineering
Halcrow
 

What's hot (20)

Pavements PPT
 Pavements PPT  Pavements PPT
Pavements PPT
 
Introduction to highway engineering
Introduction to highway engineeringIntroduction to highway engineering
Introduction to highway engineering
 
L4 engineering surveys for highways 1.3
L4 engineering surveys for highways 1.3 L4 engineering surveys for highways 1.3
L4 engineering surveys for highways 1.3
 
Traffic Engineering
Traffic Engineering Traffic Engineering
Traffic Engineering
 
Railway station and YARD
Railway station and YARD Railway station and YARD
Railway station and YARD
 
Highway Drainage System
Highway Drainage SystemHighway Drainage System
Highway Drainage System
 
Transition curve and Superelevation
Transition curve and SuperelevationTransition curve and Superelevation
Transition curve and Superelevation
 
highway maintenance and evaluation
highway maintenance and evaluation highway maintenance and evaluation
highway maintenance and evaluation
 
GEOMETRIC DESIGN OF HIGHWAY
GEOMETRIC DESIGN OF HIGHWAYGEOMETRIC DESIGN OF HIGHWAY
GEOMETRIC DESIGN OF HIGHWAY
 
Tunneling in soft ground and hard rock
Tunneling in soft ground and hard rockTunneling in soft ground and hard rock
Tunneling in soft ground and hard rock
 
Unit 2
Unit 2Unit 2
Unit 2
 
Permanent Way of Railway & Components ?(part -1,2,3,4,5)
Permanent Way of Railway & Components ?(part -1,2,3,4,5)Permanent Way of Railway & Components ?(part -1,2,3,4,5)
Permanent Way of Railway & Components ?(part -1,2,3,4,5)
 
2.5 HIGHWAY TRANSPORTATION : PAVEMENT MAINTENANCE (TRE) 3150611 GTU
2.5 HIGHWAY TRANSPORTATION : PAVEMENT MAINTENANCE (TRE) 3150611 GTU2.5 HIGHWAY TRANSPORTATION : PAVEMENT MAINTENANCE (TRE) 3150611 GTU
2.5 HIGHWAY TRANSPORTATION : PAVEMENT MAINTENANCE (TRE) 3150611 GTU
 
Elements of road x-section
Elements of road x-section Elements of road x-section
Elements of road x-section
 
Highway engineering PPT
Highway engineering PPTHighway engineering PPT
Highway engineering PPT
 
Design of expressways
Design of expresswaysDesign of expressways
Design of expressways
 
construction of flexible pavement
construction of flexible pavementconstruction of flexible pavement
construction of flexible pavement
 
Bridge engineering
Bridge engineeringBridge engineering
Bridge engineering
 
Classification of bridges
Classification of bridgesClassification of bridges
Classification of bridges
 
railway failure and its type
railway failure and its typerailway failure and its type
railway failure and its type
 

Similar to Highway presentation

Important of soil survey and selection of suitable dam site-topography/geolog...
Important of soil survey and selection of suitable dam site-topography/geolog...Important of soil survey and selection of suitable dam site-topography/geolog...
Important of soil survey and selection of suitable dam site-topography/geolog...
GauravGautam344043
 

Similar to Highway presentation (20)

Geological investigations for highways
Geological investigations for highwaysGeological investigations for highways
Geological investigations for highways
 
Lecture 7
Lecture 7Lecture 7
Lecture 7
 
Hill roads
Hill roadsHill roads
Hill roads
 
hillroads-200131051526.pptx
hillroads-200131051526.pptxhillroads-200131051526.pptx
hillroads-200131051526.pptx
 
Location survey for the Rural and urban areas
Location survey for the Rural and urban areasLocation survey for the Rural and urban areas
Location survey for the Rural and urban areas
 
Unit 1:- HIGHWAY DEVELOPMENT AND PLANNING
Unit 1:- HIGHWAY DEVELOPMENT AND PLANNINGUnit 1:- HIGHWAY DEVELOPMENT AND PLANNING
Unit 1:- HIGHWAY DEVELOPMENT AND PLANNING
 
Module 1 Highway Engg (1).pdf
Module 1 Highway Engg (1).pdfModule 1 Highway Engg (1).pdf
Module 1 Highway Engg (1).pdf
 
2 - Route Surveys and Location.pptx
2 - Route Surveys and Location.pptx2 - Route Surveys and Location.pptx
2 - Route Surveys and Location.pptx
 
Minor project bridge report( aka survey camp)
Minor project bridge report( aka survey camp)Minor project bridge report( aka survey camp)
Minor project bridge report( aka survey camp)
 
Terrain Evaluation with Landuse Planning
Terrain Evaluation with Landuse PlanningTerrain Evaluation with Landuse Planning
Terrain Evaluation with Landuse Planning
 
Design Methodology for Feasible Railway Alignment
Design Methodology for Feasible Railway AlignmentDesign Methodology for Feasible Railway Alignment
Design Methodology for Feasible Railway Alignment
 
Unit 5
Unit 5Unit 5
Unit 5
 
Important of soil survey and selection of suitable dam site-topography/geolog...
Important of soil survey and selection of suitable dam site-topography/geolog...Important of soil survey and selection of suitable dam site-topography/geolog...
Important of soil survey and selection of suitable dam site-topography/geolog...
 
Aen 203
Aen 203Aen 203
Aen 203
 
Canal Surveying.pdf
Canal Surveying.pdfCanal Surveying.pdf
Canal Surveying.pdf
 
Chapter 2 highway route surveys and locationaa
Chapter 2 highway route surveys and locationaaChapter 2 highway route surveys and locationaa
Chapter 2 highway route surveys and locationaa
 
Dam engineering i 3
Dam engineering i 3Dam engineering i 3
Dam engineering i 3
 
Introduction to surveying
Introduction to surveyingIntroduction to surveying
Introduction to surveying
 
Geological factor for canal alignment
Geological factor for canal alignmentGeological factor for canal alignment
Geological factor for canal alignment
 
PPT Estimate.pptx
PPT Estimate.pptxPPT Estimate.pptx
PPT Estimate.pptx
 

Recently uploaded

Recently uploaded (20)

Towards a code of practice for AI in AT.pptx
Towards a code of practice for AI in AT.pptxTowards a code of practice for AI in AT.pptx
Towards a code of practice for AI in AT.pptx
 
Food safety_Challenges food safety laboratories_.pdf
Food safety_Challenges food safety laboratories_.pdfFood safety_Challenges food safety laboratories_.pdf
Food safety_Challenges food safety laboratories_.pdf
 
Fostering Friendships - Enhancing Social Bonds in the Classroom
Fostering Friendships - Enhancing Social Bonds  in the ClassroomFostering Friendships - Enhancing Social Bonds  in the Classroom
Fostering Friendships - Enhancing Social Bonds in the Classroom
 
80 ĐỀ THI THỬ TUYỂN SINH TIẾNG ANH VÀO 10 SỞ GD – ĐT THÀNH PHỐ HỒ CHÍ MINH NĂ...
80 ĐỀ THI THỬ TUYỂN SINH TIẾNG ANH VÀO 10 SỞ GD – ĐT THÀNH PHỐ HỒ CHÍ MINH NĂ...80 ĐỀ THI THỬ TUYỂN SINH TIẾNG ANH VÀO 10 SỞ GD – ĐT THÀNH PHỐ HỒ CHÍ MINH NĂ...
80 ĐỀ THI THỬ TUYỂN SINH TIẾNG ANH VÀO 10 SỞ GD – ĐT THÀNH PHỐ HỒ CHÍ MINH NĂ...
 
HMCS Max Bernays Pre-Deployment Brief (May 2024).pptx
HMCS Max Bernays Pre-Deployment Brief (May 2024).pptxHMCS Max Bernays Pre-Deployment Brief (May 2024).pptx
HMCS Max Bernays Pre-Deployment Brief (May 2024).pptx
 
REMIFENTANIL: An Ultra short acting opioid.pptx
REMIFENTANIL: An Ultra short acting opioid.pptxREMIFENTANIL: An Ultra short acting opioid.pptx
REMIFENTANIL: An Ultra short acting opioid.pptx
 
Mehran University Newsletter Vol-X, Issue-I, 2024
Mehran University Newsletter Vol-X, Issue-I, 2024Mehran University Newsletter Vol-X, Issue-I, 2024
Mehran University Newsletter Vol-X, Issue-I, 2024
 
Application orientated numerical on hev.ppt
Application orientated numerical on hev.pptApplication orientated numerical on hev.ppt
Application orientated numerical on hev.ppt
 
How to Add New Custom Addons Path in Odoo 17
How to Add New Custom Addons Path in Odoo 17How to Add New Custom Addons Path in Odoo 17
How to Add New Custom Addons Path in Odoo 17
 
Google Gemini An AI Revolution in Education.pptx
Google Gemini An AI Revolution in Education.pptxGoogle Gemini An AI Revolution in Education.pptx
Google Gemini An AI Revolution in Education.pptx
 
Sociology 101 Demonstration of Learning Exhibit
Sociology 101 Demonstration of Learning ExhibitSociology 101 Demonstration of Learning Exhibit
Sociology 101 Demonstration of Learning Exhibit
 
Graduate Outcomes Presentation Slides - English
Graduate Outcomes Presentation Slides - EnglishGraduate Outcomes Presentation Slides - English
Graduate Outcomes Presentation Slides - English
 
Python Notes for mca i year students osmania university.docx
Python Notes for mca i year students osmania university.docxPython Notes for mca i year students osmania university.docx
Python Notes for mca i year students osmania university.docx
 
On_Translating_a_Tamil_Poem_by_A_K_Ramanujan.pptx
On_Translating_a_Tamil_Poem_by_A_K_Ramanujan.pptxOn_Translating_a_Tamil_Poem_by_A_K_Ramanujan.pptx
On_Translating_a_Tamil_Poem_by_A_K_Ramanujan.pptx
 
FSB Advising Checklist - Orientation 2024
FSB Advising Checklist - Orientation 2024FSB Advising Checklist - Orientation 2024
FSB Advising Checklist - Orientation 2024
 
NO1 Top Black Magic Specialist In Lahore Black magic In Pakistan Kala Ilam Ex...
NO1 Top Black Magic Specialist In Lahore Black magic In Pakistan Kala Ilam Ex...NO1 Top Black Magic Specialist In Lahore Black magic In Pakistan Kala Ilam Ex...
NO1 Top Black Magic Specialist In Lahore Black magic In Pakistan Kala Ilam Ex...
 
Plant propagation: Sexual and Asexual propapagation.pptx
Plant propagation: Sexual and Asexual propapagation.pptxPlant propagation: Sexual and Asexual propapagation.pptx
Plant propagation: Sexual and Asexual propapagation.pptx
 
Sensory_Experience_and_Emotional_Resonance_in_Gabriel_Okaras_The_Piano_and_Th...
Sensory_Experience_and_Emotional_Resonance_in_Gabriel_Okaras_The_Piano_and_Th...Sensory_Experience_and_Emotional_Resonance_in_Gabriel_Okaras_The_Piano_and_Th...
Sensory_Experience_and_Emotional_Resonance_in_Gabriel_Okaras_The_Piano_and_Th...
 
HMCS Vancouver Pre-Deployment Brief - May 2024 (Web Version).pptx
HMCS Vancouver Pre-Deployment Brief - May 2024 (Web Version).pptxHMCS Vancouver Pre-Deployment Brief - May 2024 (Web Version).pptx
HMCS Vancouver Pre-Deployment Brief - May 2024 (Web Version).pptx
 
Micro-Scholarship, What it is, How can it help me.pdf
Micro-Scholarship, What it is, How can it help me.pdfMicro-Scholarship, What it is, How can it help me.pdf
Micro-Scholarship, What it is, How can it help me.pdf
 

Highway presentation

  • 1. WHAT IS BRIDGE ?? -WHEN THE WATER WAY IS MORE THAN 6 METER THE CROSS-DRAINAGE STRUCTURE IS PROVIDED TO CROSS STREAMS AND OTHER BODIES OF WATER IS CALLED BRIDGE. -A BRIDGE SHOULD BE DESIGNED TO CARRY IRC STANDARD LOADING WITH REASONABLE AMOUNT OF SAFETY, AND SHOULD FIT INTO THE SURROUNDING LANDSCAPE. Highway Engineering Bridge and Location of a Bridge
  • 2. Ideal Location For a Bridge Site  A straight reach of a river, so that the piers of the bridge can be located parallel to the direction of flow.  There should be steady regime of a river and absence of serious whirls or cross-currents.  Availability narrow and well defined channel.  Absence of a sharp curve e in approaches, so that Scouring(erosion) and Silting(deposition) action can be prevented.
  • 3. Ideal Location For a Bridge Site  Preferring reasonable proximity(availability) to the direct alignment of road to be served .  Rocky or other compact and non-erodable bed is preferrable.
  • 4. Factors affecting selection of Bridge Site  Width of a River:- The site at which there is least width of the river is available is suitable for construction of a bridge.  A Straight Approach:- Cross-section of a bridge should be straight as far as possible, because a straight bridge is far more stable than a curved bridge.  River Banks:-  Velocity of the Flow:- The place where the velocity of the water flow is min. considering the width of the river is suitable for bridge cons.
  • 5. Factors affecting selection of Bridge Site  Free Board:-  Absence of Scouring and Silting:- There should be no erosion and deposition of the rock and other materials like sand, silt, gravel, on either side of the river. This can cause a failure to the piers of the bridge..  No confluence of large Tributaries:- Construction of a bridge should be carried out at such a site where no large tributaries of rivers meet.
  • 6. Data to be collected for location of a Bridge Site  Type of soil:- Necessary information about the soil type and its condition should be collected by the geologist/engineer and should ensure that the soil bed conforms the I.S. for the particular bridge const.  Avail. of Electricity:-Ample amount of electricity and its sources and substitutes should be made available in const. of a bridge site.  Avail. of Skilled&Unskilledlabours:- Construction of different components of bridge needs different type of labours in considerable amount .  Hydrological Data:- Collection of info. about the Rainfall, Run-off, Infiltration by soil, Evaporisation, Velocity of flow etc .  Avail. of Const. Material:- More than ample amount of const. material should be available at all time.
  • 7. Data to be collected for location of a Bridge Site  Possibility of Navigation Facilities:- Navigation of heavy machinery should be possible at site.  Possibility of Earthquake:- A site for bridge const. should be least prone to earthquake, and necessary data of past EQ should be collected and acc. to it bridge should be designed.  Present and Future Traffic Volume:- The width of a carriage way of bridge should fulfill the traffic requirements of the present and future conditions of the surrounding areas.
  • 8.
  • 9. FIELD SURVEY. Before a highway alignment is finalised in highway project, the engineering surveys are to be carried out. And these surveys are carried out in four stages. The first three stages consider all possible alternate alignment i.e. various requirements of highway alignment and fourth stage is meant for detailed survey of the selected alignment.
  • 10. STAGES OF ENGINEERING SURVEYS. THE FOUR STAGES OF ENGINEERING SURVEYS:- 1. Mapstudy 2. Reconnaissance 3. Preliminarysurveys 4. Finallocationanddetailedsurveys
  • 11. MAP STUDY It is a kind of study of topographic map of an area, so as to suggest the possible routes of the road.The main features like river , hills , valley etc are also shown in this map. By careful study of such maps , it is possible to have an idea of several alternate routes of the road.
  • 12. Details from the map.  Alignment avoiding valleys , ponds or lakes.  In hills , possibility of crossing through a mountain pass.  Approximate location of bridge site for crossing rivers.  Alternate route with permissible gradient.
  • 13. RECONNAISSANCE It is a second stage of surveys and used to examine the general character of the area for deciding the most feasible routes for detailed studies. A field surveyor may inspect a fairly broad stretch of land along the proposed alternative routes of the map in the field.
  • 14. OBJECTIVES  To obtain general knowledge of the entire territory.  To obtain specific information of salient features of the area.  To collect information about the soil type along the route.  To collect information about sources of construction materials.
  • 15. PRELIMINARY SURVEY OBJECTIVES 1. To conduct the survey for alternate alignments propose after reconnaissance. 2. To compare the different proposals in view of the requirement of a good alignment. 3. To collect necessary physical information and details of topography, drainage and soil. 4. To estimate quality of earth work materials.
  • 16. Procedure of preliminary survey 1. Primary traverse. The first step in the preliminary survey is to establish the primary traverse following the line recommended in the reconnaissance. 2. Topographical features. All geographical and other man made features along the transverse and for a certain width are surveyed and plotted. 3. Levelling work. Levelling work is also carried out side by side to give the center line profiles and typical cross section. 4. Drainage studies and Hydrological data. Drainage investigations and hydrological data are collected so as to estimate the type, number and approximate size of cross drainage structures.
  • 17. 5. SOIL SURVEY It is an essential part of preliminary survey and by help of this survey final location is being decided. 6. MATERIAL SURVEY This survey is done for naturally occurring materials like stone aggregates and identification of suitable quarries. 7. TRAFFIC SURVEY This survey is conducted in the region for deciding the number of traffic lanes and roadway width, pavement design and economic analysis of highway project. 8. DETERMINATION OF FINAL CENTER LINE After completing the preliminary survey and conducting the comparative studies of alternate alignments the final center line of the road is to be decided before the final location survey.
  • 18. FINAL LOCATION AND DETAILED SURVEY The alignment finalised after the preliminary survey then detailed survey is carried out for the preparation of plans and construction details. The location survey is carried out in two stages; 1. On paper location 2. Field location 1. On paper location. The final route is put on the drawings and details such as gradient , radius of curves etc are marked clearly. 2. Field location On paper location is transferred to the field within help of transit theodolite and precise level.
  • 19. DETAILED SURVEY  Temporary bench marks are fixed at the at the interval of 250m.  Vertical alignment , earth work and drainage details are worked out from level notes.  A detailed soil survey is carried out and soil profile is established.  Work on all rivers and valley are surveyed in detail up to considerable distance on either sides.
  • 20. DRAWING REQUIRED FOR HIGHWAY PROJECT  IN A HIGHWAY PROJECT,THE FOLLING DRAWING ARE REQUIRED:-  KEY PLAN  INDEX MAP  PRELIMINARY SURVEY PLANS  DETAILED PALNS  LONGITUDINAL SECTION  CROSS SECTION  LAND ACQUISITION PLANS  DEAWING OF ROAD INTERSECTION
  • 21. KEY MAP  It shows how actually the project has to be done  Map showing proposed and existing roads  Importatant places to be connected  Size of the map should not exceed 240x330mm(A4 size)  Scale should be chosen depending upon the area
  • 22. INDEX MAP  It shows how actully the highway project looks like  It shows the general topography of the area  Details are symbolically represented  Size of the map should not exceed 240x330mm(A4 size)  The usual scale is 1cm=0.5km
  • 23. PRELIMINARY SURVEY PLANS  It shows the details of various alternative alignments  It shows all the information collected during preliminaery survey  Its size from 240x330mm(A4 size) to 880x1230mm(A0).  Scale 10cm=1km
  • 24. DETAILED PALNS  It shows the ground plan with alignment and boundaries,countour at interval 1 to 2 m in plain country and 3 to 6 m in hilly areas.  Size of the drawing may b 625x880 mm  It should also the existing structures ,rivers ,physical features ,etc.
  • 25. LONGITUDINAL SECTION  The Longitudinal section(L-section) should be drawn to a horizontal scale of 1:2000 and a vertical scale of 1:2000  The levels should be taken at 50m intervals for plain and rolling terrain and at 25m interval for hilly terrain.  The L-section should have information like chainages ,horizontal and vertical alignment ,datum level ,ground level ,formation level ,depth of cutting ,height of filling ,posiotion of cross-roads etc
  • 26. CROSS-SECTION  It should be drawn at to nstural scale of 1cm=2- 2.5 m  It should be drawn in every 100m or where abrupt changes in level  It should include cross-section number,the reduced distances and the area of cutting and filling.  In hill roads cross section should be drawn at closer intervals.
  • 27. LAND ACQUISITION PLANS  It shows the land acquisition details.  Generl details like building, wells, nature of gradients and others details required for assessing the values.  The scale adpoted may b 1cm=40m or less.  Drawing of road intersections should be prepared showing all details of pavement , islands etc.