Estimation and Scheduling on Activities in
Construction Building using Novel Software
Vikas Kumar Sharmaa,*, Manoj Agrawala , Rajat Yadava
a
Department of Mechanical Engineering, GLA University, Mathura, UP, India
Corresponding author*
-vikash.sharma@gla.ac.in
Abstract
This research paper proposes the analysis of scheduling and financial by using MSP Software is a
process which involves estimation, sequencing the activities, resources allocation and timing. The
construction scheduling is to complete the project in time and match the resources with the allocated
time. Scheduling using MSP Software gives good controlling and clear schedule to a project. EV
analysis may be an standard system for measuring a project’s advancement at whatever provided for
side of the point from completion time, determining its fruition date, final cost furthermore
examination difference in the plan and plan of the undertaking. This project deals with scheduling
using MSP and EV Analysis for a apartment building. Thereby process time and cost overrun are
avoided.
Keywords: MSP Software, EV analysis
1. Introduction
Multi-storey buildings aim to increase the area of the building without increasing the area of the land the
building is built on, hence saving land and, in most cases, money(depending on material used and land
prices in the area, of course). Large scale industrialization and prohibitive land cost in India have resulted
in a vast expansion in the building programme stages has reached when multi-storey construction is
becoming essential and inevitable.[1] Land use economy is achieved by construction of multi-storey
buildings which results in large building more concentrated on relatively small built up area. This makes
available a large proportion of open space for creating natural environments.[2]. Many authors sought to
research the effect of GO and TiO2 nanoparticles on efficiency, of the construction of buildings
structures.[3]
This also ensures better day-lighting and greater airflow as well as well as freedom from street noise.
Living and working in such buildings provide panoramic view of the city. One production scheduling and
control technique which tries to surpass. The CPM difficulties for multi-storey building scheduling are
the Line of Balance (LOB) technique.[4]Materials were characterized for nanostructure and morphology
of the nanocomposites GO, TiO2, GO2-TiO2 to demonstrate the shape of the nanoparticles.[5]
The LOB technique was developed in the early 40’s into the manufacturing environment and adapted by
researchers for using on construction industry in the close as possible to the original scheduled by
reviewing and reprogramming under changed condition in order to adhere to the target time
ofcompletion.[6-7]
European Journal of Molecular & Clinical Medicine
ISSN 2515-8260 Volume 7, Issue 4, 2020
311
A specially built sample package, comprising a glass microfiber filter paper supported on a mild steel wire
frame, was obtained from the samples.[8]
2. Scheduling & Financial Analysis
The schedule of project will be calendar which connects the assignments which need to done through
resources which would do for them. And before creating the schedule of the project, the manager of the
project should possesses the “Work Breakdown Structure (WBS)”, effort predicted aimed at every
assignment, and list of resources with accessibility aimed at every resource.
2.1 Scope
The time of manager of project is finely spend on the team working to form WBS & predicts than
efforting to construct schedule of project without them. And the schedule of project will be core of
project design. It will be utilized through the manager of project for committing the people towards
project & display the administration how the task is executed.
Schedules are utilized for interacting last deadlines & in some instances for evaluating the requirements
of resource. And they are utilized checklist type to assure that each assignment required is executed.
When the assignment will be on schedule then the team will be committed for doing that. In the other
terms, the schedule of the project will be by means of through which the manager of project gets team &
project beneath his control.
A. Purpose of Scheduling
a) Plan is reflected by schedule, yet plan should be first.
b) It will be the definition of ordering of performance and timing in project & assembly to
specified entire time for completion.
c) The scheduling procedure might uncover the plan faults, resulting to plan revisions.
MSProject
Microsoft venture MSP may be an undertaking management programming developed and more
sold by Microsoft which is outlined to support project supervisors to Creating plans, appointing assets
with tasks, following progress, managing financial budgets and dissecting workloads.
The engineer of planning improves the most suitable model and ordering of building operations
aimed at specified project, at the combination with manager of site. They design & oversee the whole
programme of the work & should predict the demands of contracts in words of material, technical
issues, labour and equipment. And also guaranteeing that building will be completed at safety towards
maximum technical benchmark, the engineer for planning also responsible aimed at specifying the
contract duration. This will be important responsibility if penalty clauses aimed at late finishing are on
paper into contracts of project.
Traditional activities of work contain:
• Choosing the suitable methods and ordering of the events aimed at specified project.
• Depicting the work schedules often through “visual aids” as diagrams of process & bar
European Journal of Molecular & Clinical Medicine
ISSN 2515-8260 Volume 7, Issue 4, 2020
312
charts.
• The progress should be observed all over the procedure of construction & comparing this
through projected work schedule.
D. Financial Analysis EVA Analysis
“Earned Value Analysis (EVA)” will be an industry benchmark model of evaluating the
progress of project at any specified time, predicting its finishing cost and date, and evaluating changes
in budget & schedule according to the proceedings of project. When compares the designed quantity of
work through what was really been finished, to evaluate the price, accomplishment of work and
schedule according to design. As the work is finished, it will be deliberated “earned”.
1) Calculating Earning Value
Earned Value Management measures progress against a baseline. It involves calculating three
key values for each activity in the WBS:
a) The Planned Value (PV), (formerly known as the budgeted cost of work scheduled orBCWS)
b) The Actual Cost (AC), (formerly known as the actual cost of work performed orACWP)
c) The Earned Value (EV), (formerly known as the budget cost of work performed orBCWP)
These 3 values are joined for evaluating during time whether the work is accomplished according to
design. The major generally utilized measures are variance of price:
Cost Variance (CV) = EV - AC Schedule Variance (SV) = EV - PV
These 2 values is converted to effective indicators for reflecting cost & scheduling the project
execution. The major generally utilized indicator of “cost-efficiency” will be the “cost performance
index (CPI)”. It will be computed as:
CPI = EV / AC
The aggregate of entire unique “EV budgets divided by the sum of all individual AC's is known
as the cumulative CPI”, and will be commonly utilized to predict the complete project worth.
The “schedule performance index (SPI)”, computed thus:
SPI = EV / PV
is generally utilized through “CPI to forecast overall project completion estimates”.
A “negative schedule variance (SV)”computed at specified time as project will be scheduled
behind, whereas “negative cost variance (CV)” means “project is over budget”.
3. Result and Discussion
a. Project Details
1) Project name : RESIDENTIALBUILDING
2) Entire region for Construction :15050sq.ft
3) Entire Saleable region :21,500sq.ft
4) “Grand total cost Construction” : Rs 10, 00, 00,000/
5) Count of floors : 6
6) “Rate/sft” : Rs5000/
European Journal of Molecular & Clinical Medicine
ISSN 2515-8260 Volume 7, Issue 4, 2020
313
b. Project budget
The incurred cost for finishing project will be predicted in the following way:
1) Grand Total:
Table I project budget cost
SI.N
O
Description Total cost
1) Building works Rs 9,36,16,772
2) External
development
works
Rs 25,58,846
3) Architectural
Features
RS 38,24,382
Grand Total Rs 10,00,00,00
0
Total building
area
15,050sq,ft
Rate/sft Rs 1993.35
c. Quantity of the Activity
1) Quantity of the foundation activity
Entire Area of Site =2000m2
Entire Building Area =1400m2
Entire Footing Excavation =438m3
Entire P.C.C Quantity =64m3
Entire Footing Concrete =2454m3
Entire Footing
Reinforcement =23163kg
Entire Pedestal
Reinforcement =2699kg
Entire Concrete Pedestal = 91m3
Entire ground slab =140m3
3)First floor to fifth floor
Entire concrete column =50m3
.
Entire reinforcement of column =4002kg.
Entire concreting of slab =1356m3
.
Entire slab
Reinforcement =14576kg.
Entire shuttering .=20487m2
European Journal of Molecular & Clinical Medicine
ISSN 2515-8260 Volume 7, Issue 4, 2020
314
4)Sixth floor
Entire column concrete =35m3
.
Entire reinforcement column =2654kg.
Entire concreting of slab =1267m3
.
Entire reinforcement of slab =10356kg.
Entire shuttering =13243m2
.
d. Economy in Construction Cost
The construction should be done as economically as possible by organizing labour, materials,
transport, supervision, etc., a well organized work cost less. All design and working drawings should be
prepared in advance, requirement of materials should be worked out and materials should be organized,
collected and stocked close to the site of work well in advance so that work is not held up for want of
materials. The whole construction shall be completed as quickly as possible so that the supervision cost
may be minimum possible Over-head costs should be kept as low as possible
1) Concrete:
Concrete is a homogeneous mix of cement, coarse aggregate, fine aggregate and water. The
concrete members will transfer the load from the building to the soil. Concrete can be prepared by two
means Ready mix concrete (RMS) and Standard mixing concrete (SMC). The SMC is cheaper when
compared with RMC. But the RMC will reduce the time and it will provide a uniform homogenous mix
2)Ground floor
• Entire column concrete =53m3
.
 Entire column
Reinforcement =4553kg.
 Entire slab
Concreting =1540m3
.
 Entire slab
Reinforcement =15750kg.
 Entire shuttering =22487m2
Table Ii Cost for Concrete
Type of material Amount in Rs
concrete RMC 1,65,82,160/
SMC 88,93,980/
European Journal of Molecular & Clinical Medicine
ISSN 2515-8260 Volume 7, Issue 4, 2020
315
20000000
15000000
10000000
50000000
RMC SMC
Fig 1 Cost Comparison for Concrete
e. Scheduling Of the Structural Activities
Table Iii Schedule of The Structural Activity
si.no Tasks Duration Predecessors
1 Mass
Excavation
8 days -
2 Footing
Excavation
8 days 2SS+11 days
3 P.C.C 11 days 3SS+11 days
4 Foundation -
RCC
30 days 4SS+8 days
5 Column/Lift
Wall
Upto G.F
LVL
30 days 5SS+6 days
6 Ground Floor
-
Beam/ Slab
37 days 6SS+5 days
7 Ground
Floo
r
Column/Lift
Wal
23 days 7SS+14 days
8 1st Floor -
Beam/Slab
30 days 8SS+21 days
9 1st Floor -
Column/Lift
Wall
23 days 9SS+6 days
European Journal of Molecular & Clinical Medicine
ISSN 2515-8260 Volume 7, Issue 4, 2020
316
10 2nd Floor -
Beam/Slab
30 days 10SS+14 days
11 2nd Floor -
Column/Lift
Wall
23 days 11SS+7 days
12 3rd Floor -
Beam/Slab
30 days 12SS+14 days
13 3rd Floor -
Column/Lift
Wall
23 days 13SS+7 days
14 4th Floor -
Beam/Slab
30 days 14SS+14 days
15 4th Floor -
Column/Lift
Wall
23 days 15SS+7 days
16 5th Floor -
Beam/Slab
30 days 16SS+14 days
17 5th Floor -
Column/Lift
Wall
23 days 17SS+7 days
18 6th Floor -
Beam/Slab
30 days 18SS+14 days
European Journal of Molecular & Clinical Medicine
ISSN 2515-8260 Volume 7, Issue 4, 2020
317
f. Base Line Cost Report
This report shows the budget, baseline and actual cost of the structural activities, in this chart
two bar present in the cost. The bar represent the budget cost up to the baseline .The second bar shows
remaining period of the budget cost.
Fig 2:Base Line Cost Report
g. Cash Flow Report
Fig 3:Cash Flow Report
The above report shows how much amount spent in quarterly period of year in the project. Two
type of cost represent in the chart.
1. Budget cost
2. Cumulative cost
The sum of the budget cost is known as cumulative cost.
h. Earned Value Analysis of the Structural Activity
Task Actual Earnedval Cost
European Journal of Molecular & Clinical Medicine
ISSN 2515-8260 Volume 7, Issue 4, 2020
318
s no cost AC
in Rs/-
ue EV
in Rs/-
variance
(AC-EV)
in Rs/-
1 33,000.00 30,600.00 2,400.00
2 42,000.00 32,000.00 10,000.00
3 2,20,000.00 2,01,000.00 19,000.00
4 89,31,576.00 88,31,576.0
0
100000.00
5 5,80,900.00 5,60,900.00 20,000.00
6 57,65,678.00 59,90,750.0
0
2,25,072.00
7 24,30,524.00 24,20,216.0
0
10,308.00
8 59,11,850.00 59,09,936.0
0
1,914.00
9 9,21,436.00 9,20,416.00 1,020.00
Table.4. EV Analysis of activity
4. Conclusion
After complete the schedule and financial analysis of the building it has been observed that lot of
differentiates between budget and cost, cost varies is due to increases the materials cost and labor wages,
for construction also delaying more due to natural disturbance occurs
5. References
[1] K.Ananthanarayanan, MPSS: Multiple Project Scheduling Software, journal ofNicmar,PP.19-28.
[2] K.K.Chitkara, Construction Project Management, Tata McGraw-Hill Publishing Company
Limited, New Delhi, pp.180-218.
[3] A Yadav, A Kumar, PK Singh, K Sharma, Glass transition temperature of functionalized graphene
epoxy composites using molecular dynamics simulation, Integrated Ferroelectrics 186 (1), 106-114
[4] K.C.iyer, K.N.jha, Critical Factors Affecting Schedule Performance: Evidence from Indian
Construction projects, Journal of Construction Engineering and Management@ASCE,August,
PP.871-880.
[5] Singh PK, & Sharma K, Molecular Dynamics Simulation of Glass Transition Behaviour of
Polymer based Nanocomposites, Journal of Scientific & Industrial Research, 77 (10) (2018) 592-
595.
[6] M.N.Khaled, Y.H.Mohamed, Developing a complexity measures for project schedule, Journal of
Construction Engineering and Management, June 2006,pp.554-561.
[7] A Kumar, K Sharma, AR Dixit, Carbon nanotube-and graphene-reinforced multiphase polymeric
composites: review on their properties and applications, Journal of Materials Science, 1-43
[8] Mario, Work continuity constraints in project scheduling, Journalof
Construction Engineering and Management, ASCE,January2006,pp4-24.

Mais conteúdo relacionado

Semelhante a EJMCM_Volume 7_Issue 4_Pages 310-318.pdf

Time Cost Trade Off
Time Cost Trade OffTime Cost Trade Off
Time Cost Trade Offssuserfe1b72
 
Implementation of Line of Balance Method for Scheduling High-rise Building
Implementation of Line of Balance Method for Scheduling High-rise BuildingImplementation of Line of Balance Method for Scheduling High-rise Building
Implementation of Line of Balance Method for Scheduling High-rise BuildingIJERA Editor
 
Construction project management
Construction project managementConstruction project management
Construction project managementsaif hasan
 
IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...
IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...
IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...IRJET Journal
 
project management-cpm and pert methods for managers
project management-cpm and pert methods for managersproject management-cpm and pert methods for managers
project management-cpm and pert methods for managersNaganna Chetty
 
Vocational training report l&t
Vocational training report l&tVocational training report l&t
Vocational training report l&tNishant Pandey
 
IRJET- Application of Time Divisions Scheduling Techniques for Duration and Q...
IRJET- Application of Time Divisions Scheduling Techniques for Duration and Q...IRJET- Application of Time Divisions Scheduling Techniques for Duration and Q...
IRJET- Application of Time Divisions Scheduling Techniques for Duration and Q...IRJET Journal
 
IRJET- Optimization of Time and Cost of Building Construction using Fast ...
IRJET-  	  Optimization of Time and Cost of Building Construction using Fast ...IRJET-  	  Optimization of Time and Cost of Building Construction using Fast ...
IRJET- Optimization of Time and Cost of Building Construction using Fast ...IRJET Journal
 
Project Planning and Scheduling
Project Planning and SchedulingProject Planning and Scheduling
Project Planning and Schedulingijtsrd
 
Cost Overrun Causes Related to the Design Phase in the Egyptian Construction ...
Cost Overrun Causes Related to the Design Phase in the Egyptian Construction ...Cost Overrun Causes Related to the Design Phase in the Egyptian Construction ...
Cost Overrun Causes Related to the Design Phase in the Egyptian Construction ...World-Academic Journal
 
MC0084 – Software Project Management & Quality Assurance - Master of Computer...
MC0084 – Software Project Management & Quality Assurance - Master of Computer...MC0084 – Software Project Management & Quality Assurance - Master of Computer...
MC0084 – Software Project Management & Quality Assurance - Master of Computer...Aravind NC
 
EARNED VALUE ANALYSIS FOR A CONSTRUCTION PROJECT
EARNED VALUE ANALYSIS FOR A CONSTRUCTION PROJECTEARNED VALUE ANALYSIS FOR A CONSTRUCTION PROJECT
EARNED VALUE ANALYSIS FOR A CONSTRUCTION PROJECTIAEME Publication
 
Earned value analysis for a construction project
Earned value analysis for a construction projectEarned value analysis for a construction project
Earned value analysis for a construction projectIAEME Publication
 
Research study on Optimization of Cost and Duration with Line of Balance by U...
Research study on Optimization of Cost and Duration with Line of Balance by U...Research study on Optimization of Cost and Duration with Line of Balance by U...
Research study on Optimization of Cost and Duration with Line of Balance by U...IRJET Journal
 
IRJET- Developing Cost Prediction Model for Building Project
IRJET- Developing Cost Prediction Model for Building ProjectIRJET- Developing Cost Prediction Model for Building Project
IRJET- Developing Cost Prediction Model for Building ProjectIRJET Journal
 
Lec.1 Introduction to Estimation
Lec.1   Introduction to EstimationLec.1   Introduction to Estimation
Lec.1 Introduction to EstimationMuthanna Abbu
 
A CASE STUDY ON TIME AND COST DRIVEN FACTORS OF COMMERCIAL COMPLEX BY USING E...
A CASE STUDY ON TIME AND COST DRIVEN FACTORS OF COMMERCIAL COMPLEX BY USING E...A CASE STUDY ON TIME AND COST DRIVEN FACTORS OF COMMERCIAL COMPLEX BY USING E...
A CASE STUDY ON TIME AND COST DRIVEN FACTORS OF COMMERCIAL COMPLEX BY USING E...IAEME Publication
 

Semelhante a EJMCM_Volume 7_Issue 4_Pages 310-318.pdf (20)

Time Cost Trade Off
Time Cost Trade OffTime Cost Trade Off
Time Cost Trade Off
 
Chapter 3.pptx
Chapter 3.pptxChapter 3.pptx
Chapter 3.pptx
 
Implementation of Line of Balance Method for Scheduling High-rise Building
Implementation of Line of Balance Method for Scheduling High-rise BuildingImplementation of Line of Balance Method for Scheduling High-rise Building
Implementation of Line of Balance Method for Scheduling High-rise Building
 
Construction project management
Construction project managementConstruction project management
Construction project management
 
IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...
IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...
IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...
 
project management-cpm and pert methods for managers
project management-cpm and pert methods for managersproject management-cpm and pert methods for managers
project management-cpm and pert methods for managers
 
Vocational training report l&t
Vocational training report l&tVocational training report l&t
Vocational training report l&t
 
IRJET- Application of Time Divisions Scheduling Techniques for Duration and Q...
IRJET- Application of Time Divisions Scheduling Techniques for Duration and Q...IRJET- Application of Time Divisions Scheduling Techniques for Duration and Q...
IRJET- Application of Time Divisions Scheduling Techniques for Duration and Q...
 
IRJET- Optimization of Time and Cost of Building Construction using Fast ...
IRJET-  	  Optimization of Time and Cost of Building Construction using Fast ...IRJET-  	  Optimization of Time and Cost of Building Construction using Fast ...
IRJET- Optimization of Time and Cost of Building Construction using Fast ...
 
Project Planning and Scheduling
Project Planning and SchedulingProject Planning and Scheduling
Project Planning and Scheduling
 
Critical Path Method
Critical Path MethodCritical Path Method
Critical Path Method
 
Cost Overrun Causes Related to the Design Phase in the Egyptian Construction ...
Cost Overrun Causes Related to the Design Phase in the Egyptian Construction ...Cost Overrun Causes Related to the Design Phase in the Egyptian Construction ...
Cost Overrun Causes Related to the Design Phase in the Egyptian Construction ...
 
MC0084 – Software Project Management & Quality Assurance - Master of Computer...
MC0084 – Software Project Management & Quality Assurance - Master of Computer...MC0084 – Software Project Management & Quality Assurance - Master of Computer...
MC0084 – Software Project Management & Quality Assurance - Master of Computer...
 
EARNED VALUE ANALYSIS FOR A CONSTRUCTION PROJECT
EARNED VALUE ANALYSIS FOR A CONSTRUCTION PROJECTEARNED VALUE ANALYSIS FOR A CONSTRUCTION PROJECT
EARNED VALUE ANALYSIS FOR A CONSTRUCTION PROJECT
 
Earned value analysis for a construction project
Earned value analysis for a construction projectEarned value analysis for a construction project
Earned value analysis for a construction project
 
Research study on Optimization of Cost and Duration with Line of Balance by U...
Research study on Optimization of Cost and Duration with Line of Balance by U...Research study on Optimization of Cost and Duration with Line of Balance by U...
Research study on Optimization of Cost and Duration with Line of Balance by U...
 
COST CONTROL AND TRACKING OF A BUILDING BY EARNED VALUE METHOD
COST CONTROL AND TRACKING OF A BUILDING BY EARNED VALUE METHODCOST CONTROL AND TRACKING OF A BUILDING BY EARNED VALUE METHOD
COST CONTROL AND TRACKING OF A BUILDING BY EARNED VALUE METHOD
 
IRJET- Developing Cost Prediction Model for Building Project
IRJET- Developing Cost Prediction Model for Building ProjectIRJET- Developing Cost Prediction Model for Building Project
IRJET- Developing Cost Prediction Model for Building Project
 
Lec.1 Introduction to Estimation
Lec.1   Introduction to EstimationLec.1   Introduction to Estimation
Lec.1 Introduction to Estimation
 
A CASE STUDY ON TIME AND COST DRIVEN FACTORS OF COMMERCIAL COMPLEX BY USING E...
A CASE STUDY ON TIME AND COST DRIVEN FACTORS OF COMMERCIAL COMPLEX BY USING E...A CASE STUDY ON TIME AND COST DRIVEN FACTORS OF COMMERCIAL COMPLEX BY USING E...
A CASE STUDY ON TIME AND COST DRIVEN FACTORS OF COMMERCIAL COMPLEX BY USING E...
 

Último

Pride Wonderland Dhanori Pune Brochure.pdf
Pride Wonderland Dhanori Pune Brochure.pdfPride Wonderland Dhanori Pune Brochure.pdf
Pride Wonderland Dhanori Pune Brochure.pdfabbu831446
 
Brigade Neopolis Kokapet, Hyderabad E- Brochure
Brigade Neopolis Kokapet, Hyderabad E- BrochureBrigade Neopolis Kokapet, Hyderabad E- Brochure
Brigade Neopolis Kokapet, Hyderabad E- Brochurefaheemali990101
 
LCAR Unit 22 - Leasing and Property Management - 14th Edition Revised.pptx
LCAR Unit 22 - Leasing and Property Management - 14th Edition Revised.pptxLCAR Unit 22 - Leasing and Property Management - 14th Edition Revised.pptx
LCAR Unit 22 - Leasing and Property Management - 14th Edition Revised.pptxTom Blefko
 
Dynamic Netsoft A leader In Property management Software
Dynamic Netsoft A leader In Property management SoftwareDynamic Netsoft A leader In Property management Software
Dynamic Netsoft A leader In Property management SoftwareDynamic Netsoft
 
What Is Biophilic Design .pdf
What Is Biophilic Design            .pdfWhat Is Biophilic Design            .pdf
What Is Biophilic Design .pdfyamunaNMH
 
Covid 19 and Market Impact during the Pandemic
Covid 19 and Market Impact during the PandemicCovid 19 and Market Impact during the Pandemic
Covid 19 and Market Impact during the PandemicTim Wilmath
 
A Brief History of Intangibles in Ad Valorem Taxation.pdf
A Brief History of Intangibles in Ad Valorem Taxation.pdfA Brief History of Intangibles in Ad Valorem Taxation.pdf
A Brief History of Intangibles in Ad Valorem Taxation.pdfTim Wilmath
 
Sobha Aranya Sector 80 Gurgaon E- Brochure.pdf
Sobha Aranya Sector 80 Gurgaon E- Brochure.pdfSobha Aranya Sector 80 Gurgaon E- Brochure.pdf
Sobha Aranya Sector 80 Gurgaon E- Brochure.pdffaheemali990101
 
Kohinoor Hinjewadi Phase 2 Pune | E-Brochure
Kohinoor Hinjewadi Phase 2 Pune | E-BrochureKohinoor Hinjewadi Phase 2 Pune | E-Brochure
Kohinoor Hinjewadi Phase 2 Pune | E-BrochureOmanaConsulting
 
Prestige Rainbow Waters Raidurgam, Gachibowli Hyderabad E- Brochure.pdf
Prestige Rainbow Waters Raidurgam, Gachibowli Hyderabad E- Brochure.pdfPrestige Rainbow Waters Raidurgam, Gachibowli Hyderabad E- Brochure.pdf
Prestige Rainbow Waters Raidurgam, Gachibowli Hyderabad E- Brochure.pdffaheemali990101
 
Everything you ever Wanted to Know about Florida Property Tax Exemptions.pdf
Everything you ever Wanted to Know about Florida Property Tax Exemptions.pdfEverything you ever Wanted to Know about Florida Property Tax Exemptions.pdf
Everything you ever Wanted to Know about Florida Property Tax Exemptions.pdfTim Wilmath
 
Ajmera Prive at Juhu, Mumbai E-Brochure.pdf
Ajmera Prive at Juhu, Mumbai  E-Brochure.pdfAjmera Prive at Juhu, Mumbai  E-Brochure.pdf
Ajmera Prive at Juhu, Mumbai E-Brochure.pdfManishSaxena95
 
Call Girls In Mayur Vihar-1 Delhi ❤️8860477959 Good Looking Escorts In 24/7 D...
Call Girls In Mayur Vihar-1 Delhi ❤️8860477959 Good Looking Escorts In 24/7 D...Call Girls In Mayur Vihar-1 Delhi ❤️8860477959 Good Looking Escorts In 24/7 D...
Call Girls In Mayur Vihar-1 Delhi ❤️8860477959 Good Looking Escorts In 24/7 D...lizamodels9
 
Affordable and Quality Construction SVTN's Signature Blend of Cost-Efficiency...
Affordable and Quality Construction SVTN's Signature Blend of Cost-Efficiency...Affordable and Quality Construction SVTN's Signature Blend of Cost-Efficiency...
Affordable and Quality Construction SVTN's Signature Blend of Cost-Efficiency...AditiAlishetty
 
DLF Plots Sriperumbudur in Chennai E Brochure Pdf
DLF Plots Sriperumbudur in Chennai E Brochure PdfDLF Plots Sriperumbudur in Chennai E Brochure Pdf
DLF Plots Sriperumbudur in Chennai E Brochure Pdfashiyadav24
 
Mahindra Vista Kandivali East Mumbai Brochure.pdf
Mahindra Vista Kandivali East Mumbai Brochure.pdfMahindra Vista Kandivali East Mumbai Brochure.pdf
Mahindra Vista Kandivali East Mumbai Brochure.pdfPrachiRudram
 
Anandtara Iris Residences Mundhwa Pune Brochure.pdf
Anandtara Iris Residences Mundhwa Pune Brochure.pdfAnandtara Iris Residences Mundhwa Pune Brochure.pdf
Anandtara Iris Residences Mundhwa Pune Brochure.pdfabbu831446
 
8 Key Elements for Comfortable Farmland Living
8 Key Elements for Comfortable Farmland Living 8 Key Elements for Comfortable Farmland Living
8 Key Elements for Comfortable Farmland Living Farmland Bazaar
 
Shapoorji Spectra Sensorium Hinjewadi Pune | E-Brochure
Shapoorji Spectra Sensorium Hinjewadi Pune | E-BrochureShapoorji Spectra Sensorium Hinjewadi Pune | E-Brochure
Shapoorji Spectra Sensorium Hinjewadi Pune | E-BrochureOmanaConsulting
 

Último (20)

Pride Wonderland Dhanori Pune Brochure.pdf
Pride Wonderland Dhanori Pune Brochure.pdfPride Wonderland Dhanori Pune Brochure.pdf
Pride Wonderland Dhanori Pune Brochure.pdf
 
Brigade Neopolis Kokapet, Hyderabad E- Brochure
Brigade Neopolis Kokapet, Hyderabad E- BrochureBrigade Neopolis Kokapet, Hyderabad E- Brochure
Brigade Neopolis Kokapet, Hyderabad E- Brochure
 
LCAR Unit 22 - Leasing and Property Management - 14th Edition Revised.pptx
LCAR Unit 22 - Leasing and Property Management - 14th Edition Revised.pptxLCAR Unit 22 - Leasing and Property Management - 14th Edition Revised.pptx
LCAR Unit 22 - Leasing and Property Management - 14th Edition Revised.pptx
 
Dynamic Netsoft A leader In Property management Software
Dynamic Netsoft A leader In Property management SoftwareDynamic Netsoft A leader In Property management Software
Dynamic Netsoft A leader In Property management Software
 
What Is Biophilic Design .pdf
What Is Biophilic Design            .pdfWhat Is Biophilic Design            .pdf
What Is Biophilic Design .pdf
 
Covid 19 and Market Impact during the Pandemic
Covid 19 and Market Impact during the PandemicCovid 19 and Market Impact during the Pandemic
Covid 19 and Market Impact during the Pandemic
 
A Brief History of Intangibles in Ad Valorem Taxation.pdf
A Brief History of Intangibles in Ad Valorem Taxation.pdfA Brief History of Intangibles in Ad Valorem Taxation.pdf
A Brief History of Intangibles in Ad Valorem Taxation.pdf
 
Sobha Aranya Sector 80 Gurgaon E- Brochure.pdf
Sobha Aranya Sector 80 Gurgaon E- Brochure.pdfSobha Aranya Sector 80 Gurgaon E- Brochure.pdf
Sobha Aranya Sector 80 Gurgaon E- Brochure.pdf
 
Kohinoor Hinjewadi Phase 2 Pune | E-Brochure
Kohinoor Hinjewadi Phase 2 Pune | E-BrochureKohinoor Hinjewadi Phase 2 Pune | E-Brochure
Kohinoor Hinjewadi Phase 2 Pune | E-Brochure
 
Prestige Rainbow Waters Raidurgam, Gachibowli Hyderabad E- Brochure.pdf
Prestige Rainbow Waters Raidurgam, Gachibowli Hyderabad E- Brochure.pdfPrestige Rainbow Waters Raidurgam, Gachibowli Hyderabad E- Brochure.pdf
Prestige Rainbow Waters Raidurgam, Gachibowli Hyderabad E- Brochure.pdf
 
Everything you ever Wanted to Know about Florida Property Tax Exemptions.pdf
Everything you ever Wanted to Know about Florida Property Tax Exemptions.pdfEverything you ever Wanted to Know about Florida Property Tax Exemptions.pdf
Everything you ever Wanted to Know about Florida Property Tax Exemptions.pdf
 
Ajmera Prive at Juhu, Mumbai E-Brochure.pdf
Ajmera Prive at Juhu, Mumbai  E-Brochure.pdfAjmera Prive at Juhu, Mumbai  E-Brochure.pdf
Ajmera Prive at Juhu, Mumbai E-Brochure.pdf
 
Call Girls in Mahavir Nagar whatsaap call US +919953056974
Call Girls in Mahavir Nagar  whatsaap call US  +919953056974Call Girls in Mahavir Nagar  whatsaap call US  +919953056974
Call Girls in Mahavir Nagar whatsaap call US +919953056974
 
Call Girls In Mayur Vihar-1 Delhi ❤️8860477959 Good Looking Escorts In 24/7 D...
Call Girls In Mayur Vihar-1 Delhi ❤️8860477959 Good Looking Escorts In 24/7 D...Call Girls In Mayur Vihar-1 Delhi ❤️8860477959 Good Looking Escorts In 24/7 D...
Call Girls In Mayur Vihar-1 Delhi ❤️8860477959 Good Looking Escorts In 24/7 D...
 
Affordable and Quality Construction SVTN's Signature Blend of Cost-Efficiency...
Affordable and Quality Construction SVTN's Signature Blend of Cost-Efficiency...Affordable and Quality Construction SVTN's Signature Blend of Cost-Efficiency...
Affordable and Quality Construction SVTN's Signature Blend of Cost-Efficiency...
 
DLF Plots Sriperumbudur in Chennai E Brochure Pdf
DLF Plots Sriperumbudur in Chennai E Brochure PdfDLF Plots Sriperumbudur in Chennai E Brochure Pdf
DLF Plots Sriperumbudur in Chennai E Brochure Pdf
 
Mahindra Vista Kandivali East Mumbai Brochure.pdf
Mahindra Vista Kandivali East Mumbai Brochure.pdfMahindra Vista Kandivali East Mumbai Brochure.pdf
Mahindra Vista Kandivali East Mumbai Brochure.pdf
 
Anandtara Iris Residences Mundhwa Pune Brochure.pdf
Anandtara Iris Residences Mundhwa Pune Brochure.pdfAnandtara Iris Residences Mundhwa Pune Brochure.pdf
Anandtara Iris Residences Mundhwa Pune Brochure.pdf
 
8 Key Elements for Comfortable Farmland Living
8 Key Elements for Comfortable Farmland Living 8 Key Elements for Comfortable Farmland Living
8 Key Elements for Comfortable Farmland Living
 
Shapoorji Spectra Sensorium Hinjewadi Pune | E-Brochure
Shapoorji Spectra Sensorium Hinjewadi Pune | E-BrochureShapoorji Spectra Sensorium Hinjewadi Pune | E-Brochure
Shapoorji Spectra Sensorium Hinjewadi Pune | E-Brochure
 

EJMCM_Volume 7_Issue 4_Pages 310-318.pdf

  • 1. European Journal of Molecular & Clinical Medicine ISSN 2515-8260 Volume 7, Issue 4, 2020 310 Estimation and Scheduling on Activities in Construction Building using Novel Software Vikas Kumar Sharmaa,*, Manoj Agrawala , Rajat Yadava a Department of Mechanical Engineering, GLA University, Mathura, UP, India Corresponding author* -vikash.sharma@gla.ac.in Abstract This research paper proposes the analysis of scheduling and financial by using MSP Software is a process which involves estimation, sequencing the activities, resources allocation and timing. The construction scheduling is to complete the project in time and match the resources with the allocated time. Scheduling using MSP Software gives good controlling and clear schedule to a project. EV analysis may be an standard system for measuring a project’s advancement at whatever provided for side of the point from completion time, determining its fruition date, final cost furthermore examination difference in the plan and plan of the undertaking. This project deals with scheduling using MSP and EV Analysis for a apartment building. Thereby process time and cost overrun are avoided. Keywords: MSP Software, EV analysis 1. Introduction Multi-storey buildings aim to increase the area of the building without increasing the area of the land the building is built on, hence saving land and, in most cases, money(depending on material used and land prices in the area, of course). Large scale industrialization and prohibitive land cost in India have resulted in a vast expansion in the building programme stages has reached when multi-storey construction is becoming essential and inevitable.[1] Land use economy is achieved by construction of multi-storey buildings which results in large building more concentrated on relatively small built up area. This makes available a large proportion of open space for creating natural environments.[2]. Many authors sought to research the effect of GO and TiO2 nanoparticles on efficiency, of the construction of buildings structures.[3] This also ensures better day-lighting and greater airflow as well as well as freedom from street noise. Living and working in such buildings provide panoramic view of the city. One production scheduling and control technique which tries to surpass. The CPM difficulties for multi-storey building scheduling are the Line of Balance (LOB) technique.[4]Materials were characterized for nanostructure and morphology of the nanocomposites GO, TiO2, GO2-TiO2 to demonstrate the shape of the nanoparticles.[5] The LOB technique was developed in the early 40’s into the manufacturing environment and adapted by researchers for using on construction industry in the close as possible to the original scheduled by reviewing and reprogramming under changed condition in order to adhere to the target time ofcompletion.[6-7]
  • 2. European Journal of Molecular & Clinical Medicine ISSN 2515-8260 Volume 7, Issue 4, 2020 311 A specially built sample package, comprising a glass microfiber filter paper supported on a mild steel wire frame, was obtained from the samples.[8] 2. Scheduling & Financial Analysis The schedule of project will be calendar which connects the assignments which need to done through resources which would do for them. And before creating the schedule of the project, the manager of the project should possesses the “Work Breakdown Structure (WBS)”, effort predicted aimed at every assignment, and list of resources with accessibility aimed at every resource. 2.1 Scope The time of manager of project is finely spend on the team working to form WBS & predicts than efforting to construct schedule of project without them. And the schedule of project will be core of project design. It will be utilized through the manager of project for committing the people towards project & display the administration how the task is executed. Schedules are utilized for interacting last deadlines & in some instances for evaluating the requirements of resource. And they are utilized checklist type to assure that each assignment required is executed. When the assignment will be on schedule then the team will be committed for doing that. In the other terms, the schedule of the project will be by means of through which the manager of project gets team & project beneath his control. A. Purpose of Scheduling a) Plan is reflected by schedule, yet plan should be first. b) It will be the definition of ordering of performance and timing in project & assembly to specified entire time for completion. c) The scheduling procedure might uncover the plan faults, resulting to plan revisions. MSProject Microsoft venture MSP may be an undertaking management programming developed and more sold by Microsoft which is outlined to support project supervisors to Creating plans, appointing assets with tasks, following progress, managing financial budgets and dissecting workloads. The engineer of planning improves the most suitable model and ordering of building operations aimed at specified project, at the combination with manager of site. They design & oversee the whole programme of the work & should predict the demands of contracts in words of material, technical issues, labour and equipment. And also guaranteeing that building will be completed at safety towards maximum technical benchmark, the engineer for planning also responsible aimed at specifying the contract duration. This will be important responsibility if penalty clauses aimed at late finishing are on paper into contracts of project. Traditional activities of work contain: • Choosing the suitable methods and ordering of the events aimed at specified project. • Depicting the work schedules often through “visual aids” as diagrams of process & bar
  • 3. European Journal of Molecular & Clinical Medicine ISSN 2515-8260 Volume 7, Issue 4, 2020 312 charts. • The progress should be observed all over the procedure of construction & comparing this through projected work schedule. D. Financial Analysis EVA Analysis “Earned Value Analysis (EVA)” will be an industry benchmark model of evaluating the progress of project at any specified time, predicting its finishing cost and date, and evaluating changes in budget & schedule according to the proceedings of project. When compares the designed quantity of work through what was really been finished, to evaluate the price, accomplishment of work and schedule according to design. As the work is finished, it will be deliberated “earned”. 1) Calculating Earning Value Earned Value Management measures progress against a baseline. It involves calculating three key values for each activity in the WBS: a) The Planned Value (PV), (formerly known as the budgeted cost of work scheduled orBCWS) b) The Actual Cost (AC), (formerly known as the actual cost of work performed orACWP) c) The Earned Value (EV), (formerly known as the budget cost of work performed orBCWP) These 3 values are joined for evaluating during time whether the work is accomplished according to design. The major generally utilized measures are variance of price: Cost Variance (CV) = EV - AC Schedule Variance (SV) = EV - PV These 2 values is converted to effective indicators for reflecting cost & scheduling the project execution. The major generally utilized indicator of “cost-efficiency” will be the “cost performance index (CPI)”. It will be computed as: CPI = EV / AC The aggregate of entire unique “EV budgets divided by the sum of all individual AC's is known as the cumulative CPI”, and will be commonly utilized to predict the complete project worth. The “schedule performance index (SPI)”, computed thus: SPI = EV / PV is generally utilized through “CPI to forecast overall project completion estimates”. A “negative schedule variance (SV)”computed at specified time as project will be scheduled behind, whereas “negative cost variance (CV)” means “project is over budget”. 3. Result and Discussion a. Project Details 1) Project name : RESIDENTIALBUILDING 2) Entire region for Construction :15050sq.ft 3) Entire Saleable region :21,500sq.ft 4) “Grand total cost Construction” : Rs 10, 00, 00,000/ 5) Count of floors : 6 6) “Rate/sft” : Rs5000/
  • 4. European Journal of Molecular & Clinical Medicine ISSN 2515-8260 Volume 7, Issue 4, 2020 313 b. Project budget The incurred cost for finishing project will be predicted in the following way: 1) Grand Total: Table I project budget cost SI.N O Description Total cost 1) Building works Rs 9,36,16,772 2) External development works Rs 25,58,846 3) Architectural Features RS 38,24,382 Grand Total Rs 10,00,00,00 0 Total building area 15,050sq,ft Rate/sft Rs 1993.35 c. Quantity of the Activity 1) Quantity of the foundation activity Entire Area of Site =2000m2 Entire Building Area =1400m2 Entire Footing Excavation =438m3 Entire P.C.C Quantity =64m3 Entire Footing Concrete =2454m3 Entire Footing Reinforcement =23163kg Entire Pedestal Reinforcement =2699kg Entire Concrete Pedestal = 91m3 Entire ground slab =140m3 3)First floor to fifth floor Entire concrete column =50m3 . Entire reinforcement of column =4002kg. Entire concreting of slab =1356m3 . Entire slab Reinforcement =14576kg. Entire shuttering .=20487m2
  • 5. European Journal of Molecular & Clinical Medicine ISSN 2515-8260 Volume 7, Issue 4, 2020 314 4)Sixth floor Entire column concrete =35m3 . Entire reinforcement column =2654kg. Entire concreting of slab =1267m3 . Entire reinforcement of slab =10356kg. Entire shuttering =13243m2 . d. Economy in Construction Cost The construction should be done as economically as possible by organizing labour, materials, transport, supervision, etc., a well organized work cost less. All design and working drawings should be prepared in advance, requirement of materials should be worked out and materials should be organized, collected and stocked close to the site of work well in advance so that work is not held up for want of materials. The whole construction shall be completed as quickly as possible so that the supervision cost may be minimum possible Over-head costs should be kept as low as possible 1) Concrete: Concrete is a homogeneous mix of cement, coarse aggregate, fine aggregate and water. The concrete members will transfer the load from the building to the soil. Concrete can be prepared by two means Ready mix concrete (RMS) and Standard mixing concrete (SMC). The SMC is cheaper when compared with RMC. But the RMC will reduce the time and it will provide a uniform homogenous mix 2)Ground floor • Entire column concrete =53m3 .  Entire column Reinforcement =4553kg.  Entire slab Concreting =1540m3 .  Entire slab Reinforcement =15750kg.  Entire shuttering =22487m2 Table Ii Cost for Concrete Type of material Amount in Rs concrete RMC 1,65,82,160/ SMC 88,93,980/
  • 6. European Journal of Molecular & Clinical Medicine ISSN 2515-8260 Volume 7, Issue 4, 2020 315 20000000 15000000 10000000 50000000 RMC SMC Fig 1 Cost Comparison for Concrete e. Scheduling Of the Structural Activities Table Iii Schedule of The Structural Activity si.no Tasks Duration Predecessors 1 Mass Excavation 8 days - 2 Footing Excavation 8 days 2SS+11 days 3 P.C.C 11 days 3SS+11 days 4 Foundation - RCC 30 days 4SS+8 days 5 Column/Lift Wall Upto G.F LVL 30 days 5SS+6 days 6 Ground Floor - Beam/ Slab 37 days 6SS+5 days 7 Ground Floo r Column/Lift Wal 23 days 7SS+14 days 8 1st Floor - Beam/Slab 30 days 8SS+21 days 9 1st Floor - Column/Lift Wall 23 days 9SS+6 days
  • 7. European Journal of Molecular & Clinical Medicine ISSN 2515-8260 Volume 7, Issue 4, 2020 316 10 2nd Floor - Beam/Slab 30 days 10SS+14 days 11 2nd Floor - Column/Lift Wall 23 days 11SS+7 days 12 3rd Floor - Beam/Slab 30 days 12SS+14 days 13 3rd Floor - Column/Lift Wall 23 days 13SS+7 days 14 4th Floor - Beam/Slab 30 days 14SS+14 days 15 4th Floor - Column/Lift Wall 23 days 15SS+7 days 16 5th Floor - Beam/Slab 30 days 16SS+14 days 17 5th Floor - Column/Lift Wall 23 days 17SS+7 days 18 6th Floor - Beam/Slab 30 days 18SS+14 days
  • 8. European Journal of Molecular & Clinical Medicine ISSN 2515-8260 Volume 7, Issue 4, 2020 317 f. Base Line Cost Report This report shows the budget, baseline and actual cost of the structural activities, in this chart two bar present in the cost. The bar represent the budget cost up to the baseline .The second bar shows remaining period of the budget cost. Fig 2:Base Line Cost Report g. Cash Flow Report Fig 3:Cash Flow Report The above report shows how much amount spent in quarterly period of year in the project. Two type of cost represent in the chart. 1. Budget cost 2. Cumulative cost The sum of the budget cost is known as cumulative cost. h. Earned Value Analysis of the Structural Activity Task Actual Earnedval Cost
  • 9. European Journal of Molecular & Clinical Medicine ISSN 2515-8260 Volume 7, Issue 4, 2020 318 s no cost AC in Rs/- ue EV in Rs/- variance (AC-EV) in Rs/- 1 33,000.00 30,600.00 2,400.00 2 42,000.00 32,000.00 10,000.00 3 2,20,000.00 2,01,000.00 19,000.00 4 89,31,576.00 88,31,576.0 0 100000.00 5 5,80,900.00 5,60,900.00 20,000.00 6 57,65,678.00 59,90,750.0 0 2,25,072.00 7 24,30,524.00 24,20,216.0 0 10,308.00 8 59,11,850.00 59,09,936.0 0 1,914.00 9 9,21,436.00 9,20,416.00 1,020.00 Table.4. EV Analysis of activity 4. Conclusion After complete the schedule and financial analysis of the building it has been observed that lot of differentiates between budget and cost, cost varies is due to increases the materials cost and labor wages, for construction also delaying more due to natural disturbance occurs 5. References [1] K.Ananthanarayanan, MPSS: Multiple Project Scheduling Software, journal ofNicmar,PP.19-28. [2] K.K.Chitkara, Construction Project Management, Tata McGraw-Hill Publishing Company Limited, New Delhi, pp.180-218. [3] A Yadav, A Kumar, PK Singh, K Sharma, Glass transition temperature of functionalized graphene epoxy composites using molecular dynamics simulation, Integrated Ferroelectrics 186 (1), 106-114 [4] K.C.iyer, K.N.jha, Critical Factors Affecting Schedule Performance: Evidence from Indian Construction projects, Journal of Construction Engineering and Management@ASCE,August, PP.871-880. [5] Singh PK, & Sharma K, Molecular Dynamics Simulation of Glass Transition Behaviour of Polymer based Nanocomposites, Journal of Scientific & Industrial Research, 77 (10) (2018) 592- 595. [6] M.N.Khaled, Y.H.Mohamed, Developing a complexity measures for project schedule, Journal of Construction Engineering and Management, June 2006,pp.554-561. [7] A Kumar, K Sharma, AR Dixit, Carbon nanotube-and graphene-reinforced multiphase polymeric composites: review on their properties and applications, Journal of Materials Science, 1-43 [8] Mario, Work continuity constraints in project scheduling, Journalof Construction Engineering and Management, ASCE,January2006,pp4-24.