Anúncio
Anúncio

Mais conteúdo relacionado

Apresentações para você(20)

Anúncio
Anúncio

Project management for Instructional Designers

  1. PROJECT MANAGEMENT FOR INSTRUCTIONAL DESIGNERS Presented by: Kimberly McKee and Kimberly Klotz University of Central Arkansas Instructional Technologies Graduate Program
  2. Kimberly Klotz (kklotz@uca.edu)  Bachelor of Arts ‘06 (Art, Journalism)  Master of Science ‘13 (Instructional Technology/Distance Education)  7 years of design/marketing experience in higher education  48 hours of Project Management professional development  Employed in the Division of Outreach and Community Engagement, University of Central Arkansas
  3. Kimberly McKee (kmckee@uca.edu)  Bachelor of Arts (English, Writing, Journalism)  Master of Science ‘13 (Instructional Technology/Distance Education Emphasis)  17 years of technical writing experience for a technology company  Grant writing contractor  48 hours of Project Management professional development  Employed in the Division of Outreach and Community Engagement, University of Central Arkansas
  4. Project Management Institute (PMI) http://www.pmi.org PMI is one of the world’s largest not-for-profit membership associations for the Project Management profession, with more than 650,000 members and credential holders in more than 185 countries. PMI Offers Two Certification Levels: Project Management Professional (PMP) Certified Associate in Project Management (CAPM) – Entry Level Certification
  5. Project Management Certification Requirements 1. Bachelor’s degree 2. 3 years of Project Management experience 3. 4500 hours of leading projects 4. 35 hours of Project Management education 5. Pass the test OR 1. High school degree 2. 5 years of Project Management experience 3. 7500 hours of leading projects 4. 35 hours of Project Management education 5. Pass the test 1. High school diploma or equivalent 2. 1500 hours of Project Management experience 3. Pass the test OR 1. High school diploma or equivalent 2. 23 hours of Project Management instruction 3. Pass the test Project Management Professional (PMP) Certified Associate in Project Management (CAPM)
  6. What is Project Management?  The application of knowledge, skills, tools and techniques to project activities to meet the project requirements. (PMI)  To determine project success, we must also include the client. (Meredith & Mantel) Applying Project Management principles increases the success of a project.
  7. What is a project?  Developed to achieve the purposes and goals of an organization, institution or business  Purpose and goals are defined by stakeholders  Initiatives to increase organizational effectiveness or efficiency (such as incorporating new technologies and updating/improving processes)  Major activities outside the normal work of an organization’s department or functional units or major activities that cross functional boundaries
  8. Project Characteristics  Temporary – defined beginning and end  Create a product, service or result that is unique
  9. Who can manage a project?  Outside contractors  Internal group in a Project Management Office (PMO)  Internal team  Instructional Designer
  10. Core Competencies of the Project Manager
  11. Key Skills of the Project Manager  Develops a plan to meet project goals  Monitors plan to ensure project stays on track  Energizes the team around the success of the project  Maintains organization  Establishes priorities  Communicates clear goals and expectations A Project Manager is goal directed and milestone oriented!
  12. Project Management and ADDIE Instructional Design Model
  13. Project Management: Initiate ADDIE: Analyze  Recognizes a project or the next phase of an existing project  Recognizes that resources should be committed to the project Activities: 1. Conduct Needs Analysis 2. Develop Project Charter 3. Identify and Document Stakeholders
  14. Step 1: Needs Analysis  Feasibility study to determine performance gaps at the individual and business levels  Presents alternatives and possible solutions  Prepared by the designer, team, outside agency  Approved by leadership
  15. Conducting a Needs Analysis  Answers Who, What, When, Where, Why, How questions  Locates the root cause of the performance gap  Compares what is expected to what is actually achieved  Understand the learner (job experiences, motivation, aptitude,  Conduct a survey  Walk thru current processes  Talk to customers, if possible and needed  Review previous training efforts  Review sales records and customer feedback forums  Conduct interviews  Facilitate focus groups  Facilitate workshop sessions  Conduct group brainstorming  Observations  Prototype – working model to obtain feedback before proceeding with project WHY? HOW?
  16. Needs Analysis Format Use this format to develop a Needs Analysis Report. 1. Training requested 2. Job, tasks, duties to be performed 3. Expected performance 4. Data collection method 5. Actual performance 6. Cause of performance gap 7. Cost estimate of training 8. Benefit of training 9. Training proposal 10. Management support recommendations (feedback, measurement) 11. Narrative
  17. Step 2: Project Charter  Provides structure to the Project Plan  Justifies the project  Documents the need being addressed  Includes a description of the project  Documents proposed result of the project  Includes input from stakeholders  Leadership responsible for obtaining sign-off by the project sponsor (person financing the project), senior management, stakeholders
  18. Project Charter Format Use this format to develop a Project Charter. 1. Purpose 2. Description of Work 3. Objectives 4. In-scope deliverables (what the project includes) Out-of-scope deliverables (what the project does not include) 5. Roles and responsibilities 6. Milestones 7. Major known risks 8. Assumptions and Constraints 9. Constraints 10. External dependencies 11. Summary of budget 12. Vendors
  19. Stakeholders  Includes practitioners or groups of people with specialized knowledge or skills in a particular area  Interests should be considered throughout the project
  20. Stakeholder Log Format Use this format to develop a Stakeholder Log. 1. Name 2. Role on Project 3. Department 4. Interest 5. Knowledge level 6. Expectation 7. Level of influence on the project
  21. Project Management: Plan ADDIE: Design  40% of time allocated to complete the project should be spent in planning  Size and complexity of project determines the processes to be included Activities: 1. Instructional Design Document 2. Project Management Plan 3. Components of Project Management Plan 4. Project Scope Statement 5. Work Breakdown Structure (WBS)
  22. Step 3: Instructional Design Document  Outlines the framework of the instructional plan  Provides high-level overview of the product content and how it will be treated  Enables stakeholders to validate the program’s objectives, architecture, content and concepts before development  Identifies learning strategies (learning styles and adult learning principles)
  23. Instructional Design Document Format Use this format to develop an Instructional Design Document. Learning Objectives 1. Describe what the learner is expected to achieve when performing the task 2. Task statement 3. Conditions under which the task is performed Key Points – Content and Concept 1. Product information, concepts and criteria to be covered in each module Process and Activity 1. Summary of the types of learning activities that will be completed in the respective modules 2. Describe how presentation and application methods are distributed throughout the learning program
  24. Step 4: Project Management Plan  Overall approach used to plan and manage a project  Consists of subsidiary plans that detail how specific areas of the project will be managed  Documents cost, time, quality, risk, and resources to complete the project Input:  Project charter  Instructional design document  Process outputs that will be used for the project  Environmental factors outside the organization  Specific information about what may influence success, organizational policies, guidelines, procedures, plans, and/or standards for conducting work  Stakeholder input, if skills and knowledge warrant Output:  Project Management Plan
  25. Project Management Plan Components  Project Scope Statement  Cost and Budget  Work Breakdown Structure (WBS)  Schedule Management  Issues Management  Change Management  Quality Management  Human Resource Management  Procurement Management  Risk Management  Communications Plan
  26. Project Scope Statement  Documents initial planning efforts for the project  Used to reach agreement among managers, stakeholders and teams before resources are allocated
  27. Project Scope Statement Format Use this format to develop a Project Scope Statement. 1. Purpose and justification 2. Product description 3. Objectives 4. Project description (Includes: deliverables breakdown. Do not include: completion criteria, external dependencies, assumptions, constraints.) 5. Milestones and target dates 6. Project approach (describes the plans included, scheduled meetings, scheduled status reports, issues management, change management, communications plan, procurement plan, resource management) 7. Approvals 8. Version history
  28. Work Breakdown Structure (WBS)  Comprehensive review of the project scope  Subdivides major project deliverables and project work into smaller, more management components called work packages  The lowest level tasks should have durations between 2 and 22 days and effort should not take more than one person more than one week to complete
  29. Work Breakdown Structure (WBS) Input:  Project scope statement  Organizational policies, guidelines, procedures, plans and or standards for conducting work  Activity Lists (outlines all the scheduled activities to be performed for the project within the scope of work description of each activity and identification code or number)  Activity Attributes (characteristics of the activities)  Milestone Lists (major accomplishments that signal completion of a major deliverable)  Requirements documentation that describe the connection between individual requirements and the business need for the project
  30. Work Breakdown Structure (WBS) Output:  WBS in deliverables  WBS dictionary that includes details for work attached to each component, milestones, person responsible, etc.
  31. WBS Steps Define Project Deliverables 1. Define scheduled activities to complete project 2. Define tasks for scheduled activities 3. Sequence activities and tasks 4. Identify related dependencies 5. Estimate resources needed/available 6. Estimate duration resources will be required 7. Define milestones and expected target dates 8. Document details for the WBS dictionary
  32. WBS Sequencing Methods Precedence Diagramming Method  Finish-to-start (FS): predecessor activity must finish before successor activity can start  Start-to-finish (SF): predecessor activity must start before the successor activity can finish  Finish-to-finish (FF): predecessor activity must finish before the successor activity finishes  Start-to-finish (SS): predecessor activity must start before the successor activity can start
  33. WBS Sequencing Methods Dependency Determination  Mandatory dependencies: inherent to the nature of the work being done  Discretionary dependencies: established based on best practices within a particular industry or aspect of the project where an unusual sequence is desired Appling Leads and Lags  Lags delay successor activities and require time to be added to start or finish date. Leads speed up successor activity and require time to be taken off either start or finish date of scheduled activity.
  34. Cost and Budget Cost of the resources needed to complete project activities Input:  Scope statement  Work breakdown structure  Defined activities  Sequenced activities  Resource estimates  Schedule  Risks Output:  Cost baseline
  35. Schedule Management  Analyzing activity sequences, duration, resource requirements and schedule constraints to create the project schedule  Approved schedule becomes the baseline for the remainder of the project  Project progress is monitored and tracked against the baseline, which determines if the project is on track
  36. Input:  Project scope statement  Activity list  Activity attributes (characteristics of activity, assumptions, constraints)  Diagram of project activities and dependencies  Activity resource requirements  Resource calendars  Activity duration estimates Output:  Project schedule  Schedule data  Schedule baseline  Project document updates Schedule Management
  37. Schedule Management Scheduling Methods  Schedule Network Analysis Calculate early and late start dates, and early and late finish dates for project activities.  Critical-Path Method Identifies tasks that must be completed on time for the project to be completed by the end date. This data keeps project on track.  Schedule Compression Using mathematical calculations to shorten the schedule without changing the scope. Allows related activities to be accomplished sooner than estimated.  What-if Scenario Analysis Series of what if questions to present activity assumptions to determine project duration.
  38. Schedule Management Scheduling Methods  Resource Leveling Under-allocated resources can be assigned to multiple tasks.  Critical-Chain Method Schedule high risk tasks early in project so problems are identified and addressed as soon as possible.  Applying Leads and Lags Start and finish dates are adjusted.  Automated Scheduling Tools Speeds up scheduling process based on data input.
  39. Schedule Management Plan Format Use this format to develop a Schedule Management Plan. 1. Task 2. Responsible 3. Estimated duration to complete 4. Start date 5. Finish date 6. Delays 7. Reason for delay 8. Action steps
  40. Issues Management  A log to document the issue, the owner, resolution and status Use this format to develop an Issues Management Log. 1. How issues are tracked 2. How issues are assigned 3. How issues are prioritized 4. How issues are resolved 5. How issues are communicated
  41. Change Management Deviations from the project management plan Use this format to develop a Change Management Process Log. 1. How a change request will be managed 2. How a change request will be reviewed 3. How a change request will be tracked 4. How a change request will be resolved 4. What are possible alternatives and cost 5. Sign off
  42. Quality Management  Identifies the quality standards adopted for the project  Describes how the quality will be implemented and managed Input:  Customer definition of quality  Overview of schedule, cost, scope  Quality assurance activities (testing, audits, reviews)  Measurements (within scope, budget, schedule) Output:  Quality Management Plan
  43. Quality Management Plan Format Use this format to develop a Quality Management Plan. 1. Organization’s quality policy 2. How the customer defines quality 3. Deliverables - acceptable criteria and standards 4. Steps to ensure that quality is part of the product 4. Measurements 5. Scheduled audits 6. Sign off
  44. Human Resource Management  Process for organizing and managing the team  Size of team influenced by duration of the project Input:  Factors outside the project that influence project success  Organizational policies, guidelines, procedures, plans and/or standards for conducting work  Activity resource requirements Output:  Human Resource Plan
  45. Human Resource Management Plan Format Use this format to develop a Human Resources Management Plan. 1. Roles 2. Responsibilities 3. Reporting relationships
  46. Procurement Management  Process of documenting project purchasing decisions, specifying the approach and identifying potential sellers.  Identifies project needs that must be met by purchasing products, services or results outside the organization Input:  Factors outside of the project that impact success  Organizational policies, guidelines, plans and/or standards for conducting work  Scope baseline  Requirements documentation  Teaming agreements  Risk information  Activity-resource requirements  Project schedule  Activity cost estimates  Cost baseline Output:  Procurement Management plan
  47. Procurement Management Plan Format Use this format to develop a Procurement Management Plan. 1. Procurement statement (products or services being considered) 2. Estimated cost 3. Vendor selection (RFI/RFP/etc.) 4. Procurement definition (what items will be procured and under what conditions) 5. Selection process criteria 6. Procurement team with contact information and defined roles 7. Contract type and actions required to initiate 8. Standards for each contract 9. Vendor management (steps to ensure everything is received) 9.. Sign off
  48. Risk Management Plan  Processes necessary to increase the probability and impact of positive events and decrease probability and impact of negative events Input:  Factors outside of the project that influence success  Organizational policies, guidelines, procedures, plans and/or standards for conducting work  Scope statement  Cost Management plan  Schedule Management plan  Communications Management plan Output:  Risk Management plan
  49. Risk Management Plan Format Use this format to develop a Risk Management Plan. 1. Risk identification (based on discussions with key stakeholders) 2. Risk categorization 3. Risk probability and impact assessment 4. Risk prioritization 5. Risk response planning 6. Risk management strategy 7. Risk monitoring (build reviews into project schedule) 8. Risk control 9. Assumptions with significant impact on project risk 10. Roles and responsibilities unique to the risk function
  50. Risk Management Plan Format Risk Management Plan - Continued 11. Risk management milestones 12. Risk rating score technique 13. Risk thresholds (high, medium, low – based on impact and probability) 14. Risk communication 15. Risk tracking process 16. Sign off
  51. Communication Plan  Processes required to ensure timely and appropriate collection, retrieval and dissemination of project information  Ensures that stakeholder needs are met Input:  Factors outside the project with significant influence  Organizational policies, guidelines, procedures, plans and standards for conducting work  Project Charter  Procurement documents Output:  Communication Plan
  52. Communication Plan Format Use this format to develop a Communication Plan. 1. Purpose 2. Need 3. Communication Principles (ensure consistency and tone in messages and communication efforts) 4. Communication objectives 5. Target audience 6. Key messages (who, what, when, where, why, how) 7. Change implications (impact of the organizational changes as a result of the project) 8. Challenges and opportunities (Factors that help or hinder such as past situations, rumors, trust, etc.) 9. Sign off
  53. ADDIE: Develop and Implement Project Management: Execute  Design document is moved to development  Communication is key to the success of the project Activities: 1. Preview instructional product 2. Validate instructional product 3. Deliver instructional product
  54. Communication Barriers  Perceptions (How individuals make sense of information)  Beliefs (True/false or probable/improbable)  Attitudes (Positive/negative responses)  Values (Good/bad or preferred/rejected)  Noise (Internal/external disruption to the communication process)
  55. Communication Elements  Create a positive environment  Know your audience  Project credibility  Listen  Awareness of verbal and nonverbal  Response to feedback
  56. Communication Resources The communication methods chosen should be driven by the needs of the project.  Email  Text Message  Video conferencing and chat services, like Skype  Blogs and wikis (WordPress)  Calendar sharing (Google Docs)  Postal and shipping services  Desktop software tools  Microsoft Office or Open Office Suite  Visual design and mockup software  Project management software (Microsoft Project or OpenProject)  Online project management software (Wrike, TeamBox, ManyMoons)
  57. Validating Product Content  Was learning content relevant to the tasks to be performed? Process  Did the presentation method help you learn the content? Materials  Were the manuals, job aids, etc., adequate, useful and applicable?
  58. ADDIE: Evaluate Project Management: Close  Ensure that your customer is content with the project deliverables  Obtain sign off by customer that project is complete  Hold a “lessons learned” meeting with project team and appropriate stakeholders  Celebrate success
  59. Final Project Report Format Use this format to develop a Final Project Report. 1. Compare project outputs to project objectives 1. Identify what went right or wrong 2. Document weaknesses and strengths 3. Include original project plan 4. Include meeting minutes 5. Include project journals 6. Obtain customer feedback 7. All project documents for archives 8. Accounting documentation 9. Sign off
  60. References Cox, D. (2009). Project management for instructional. designers: a practical guide. Bloomington, Indiana: iUniverse Wiley, D. Project management for instructional designers. Brigham Young University: Creative Commons license. Retrieved from http://pm4id.org/(2013). A guide to the project management body of knowledge. (4th ed.). project management institute. Swaim, T. (2013). Project management fundamentals. Ed To Go, Retrieved from http://www.ed2go.com/CourseDetails.aspx?tab=detail&course=pmf Swaim, T. (2013). Pmp certification prep 1. Ed To Go, Retrieved from http://www.ed2go.com/CourseDetails.aspx?tab=detail&course=ppf
Anúncio