ELMO quick charging network
How to develop
nationwide charging
network?

Jarmo Tuisk
Head of ELMO program,
KredEx
Topics
•   Background
•   Planning
•   Locations
•   Business model
•   Preparation and Installation
•   Launch and results
BACKGROUND    Started in March 2011
              Fully financed by CO2
               quota sales to the
               Mitsubishi Corporation
              Implemented by the Ministry
               of Economic Affairs and
               Communications

              Implementation agency:
               KredEx
ELMO program

                  Advanced
                   charging
                infrastructure


Competence
                                   EV Grants
  centers



                                  Demo &
  Car sharing                    Awareness
                                   raising
THE PLANNING PHASE
Planning: March – July 2011
• What are the use cases for various needs for
  recharging the EV?
• What are the charging technology choices?
• What is the expectations for the service?
• What kind of IT infrastructure we need?
• Where should we put those chargers?
• How to complete the project in 18 months?
Principal decisions
• It’s going to be a “public safety network” to
  address range anxiety
• We go for single operator/centrally managed
  business structure for the country wide
  network
• We procure the full solution, including the
  service, from single consortium – minimizes
  the risks of technological incompatibilities
Possible charging use cases
                       Public/shared charger


              Routine shared            Emergency
                 charging                charging

                                          Travel
                                         charging
Pre-
                                                    Unplanned
planned
                                                    charging
charging      Daily office
               charging

              Daily home
               charging


                        Dedicated charger
3 main use-cases for the ELMO
                 charging network

 Emergency        • Locations hard to predict
  charging        • Cover the main routes

Shared routine    • Locations easy to predict
   charging       • Follow the daily routines

                  • Locations easier to predict
Travel charging   • Emphasize tourist routes
Use cases and technology options
                    AC Normal   AC Fast   DC superfast
                       6-8h      1-2h      20-30min


    Daily office
                       OK       Maybe       Not OK
     charging

    Daily home
                       OK       Maybe       Not OK
     charging

   Routine shared
                     Maybe      Maybe         OK
      charging

    Emergency
                     Not OK     Maybe         OK
     charging

       Travel
                     Not ok       OK          OK
      charging
It takes time to plan the network
It took roughly one year to be ready for the actual
building works



 Guidelines               Electricity projects

          Tech. Spec.   Locations                Building permits




Q2 2011       Q3 2011   Q4 2011        Q1 2012   Q2 2012       Q3 2012   Q4 2012   Q1 2013
LOCATIONS
LOCATION IS EVERYTHING!
• Well, almost 
• Why the locations are important?
  – Hard to secure them
  – Difficult to change them later
  – Your business is directly dependent on whether
    you hit the right spot in city or road
• Problem: nothing to rely on, because you
  cannot count on the existing traffic data too
  much, battery vehicles are just too different.
We created some simple rules
• No more than 50-60 km between quick chargers
  in main roads
• 1 quick charger for towns with more than 3000
  inhabitants
   – Almost all Estonian towns, because somebody drives
     an EV there someday soon
• Ca 1 quick charger per 10 000 inhabitant in cities
  with more than 10 000 inhabitant
   – Because there is statistical chance that somebody
     buys an EV there
BUSINESS MODEL
Operating model
                               Private operator, selected by KredEx for 5 years
    Services



                  Charger
                                     Business          Customer          Security            Asset
                control and
                                     services           support          services         management
                maintenance


               KredEx selected private operator to run the charging network for 5 years.
Operator will receive a service fee for the operation. No profit from energy sales during initial 5 years.

                                                Owned by KredEx
    Assets




                                    Network                            High power
                    Quick                           Locations for                        Intellectual
                                   management                             grid
                   chargers                           chargers                            property
                                     system                            connections
Business structure

  Owner and                              KredEx
   manager


Main outsourcing                       ABB Estonia
    partner


                         ABB               G4S             Now!
    Partners         Netherlands
                                      (CRM services)   (IT platform)
                   (quick chargers)
Pricing
                  FLEX           Combi        Volume
Monthly fee       0 EUR           10 EUR        30 EUR

Pay per charge    5 EUR           2,5 EUR        0 EUR

Limits           No limits       No limits     150kWh/
                                                month

                                             1,2EUR per charge
                                                 after that
PREPARATION AND INSTALLATIONS
The real action
• We had two separate companies to do the real
  work
  – Elektritsentrum with multiple teams to prepare the
    locations (groundworks, cables from connection
    points, foundations for QCs)
  – ABB with multiple teams to install and set up the
    chargers
• Amazing speed of deployment
  – We started building the locations in September 2012
  – The network was completed by the end of January
    2013 (with some chargers to be added in spring)
Behind the scenes (last 3 months)
•   Training of the customer support teams
•   Development of business routines
•   Analysing early statistics to model pricing packages
•   Signing the electricity purchase contacts
•   Developing the legal side of the service
•   Setting up the pricing solutions
•   Testing IT background
•   Managing media relations
•   Informing the possible customers of network status
•   Etc etc
LAUNCH AND RESULTS
Launch plan
• Gradual launch – commission the charger ASAP
• Free charging until the end of January
• Introduction of future pricing schemes in late
  November
• Customers were able to sign the contracts since
  December
• Early January we switched to “authentification
  mode”
• Since February charging is not free anymore
• Big party coming in 20th February in Tallinn!
The largest quick charging network in
                                   Europe
Quick facts
Project start: June 2011
Installation start: June 2012

Quick chargers working: 151
Total number: 165

Operated by ABB, G4S and
Now! Innovations
DC fast charging infrastructure
        development in Europe
• Weird island in the
  upper right corner
  of Europe 
• We had no idea,
  that this is how
  Europe will look
  like in 2013.
www.estonia.eu




Questions and answers

THANK YOU!
JARMO.TUISK@KREDEX.EE

Mais conteúdo relacionado

Semelhante a ELMO presentation in CHAdeMO's annual conference in Brussels in 18th February

ELMO case study, e-mobility conference, Budapest 17. March 2015
ELMO case study, e-mobility conference, Budapest 17. March 2015ELMO case study, e-mobility conference, Budapest 17. March 2015
ELMO case study, e-mobility conference, Budapest 17. March 2015Jarmo Tuisk
 
Presentation for the delegation of Finnish tech journalists about Estonian EV...
Presentation for the delegation of Finnish tech journalists about Estonian EV...Presentation for the delegation of Finnish tech journalists about Estonian EV...
Presentation for the delegation of Finnish tech journalists about Estonian EV...Jarmo Tuisk
 
Estonian Electromobility Program overview October 2012
Estonian Electromobility Program overview October 2012Estonian Electromobility Program overview October 2012
Estonian Electromobility Program overview October 2012Jarmo Tuisk
 
Ev employer initiative2-10-30-12
Ev employer initiative2-10-30-12Ev employer initiative2-10-30-12
Ev employer initiative2-10-30-12CALSTART
 
Charge More...For Less with Cyber Switching EV Solutions
Charge More...For Less with Cyber Switching EV SolutionsCharge More...For Less with Cyber Switching EV Solutions
Charge More...For Less with Cyber Switching EV SolutionsGreg Wible
 
Infrastructure Issues for Electric Vehicle Deployment in Ireland - ESB Networks
Infrastructure Issues for Electric Vehicle Deployment in Ireland - ESB NetworksInfrastructure Issues for Electric Vehicle Deployment in Ireland - ESB Networks
Infrastructure Issues for Electric Vehicle Deployment in Ireland - ESB NetworksElectric Vehicle Association of Ireland
 
Telecom Challenges and Electric Vehicles
Telecom Challenges and Electric VehiclesTelecom Challenges and Electric Vehicles
Telecom Challenges and Electric VehiclesWim D'Hondt
 
EVfleetSolutions_ver2211(Eng) (1).pptx
EVfleetSolutions_ver2211(Eng) (1).pptxEVfleetSolutions_ver2211(Eng) (1).pptx
EVfleetSolutions_ver2211(Eng) (1).pptxYuukiKubo1
 
Baby Smart Grid 11/09
Baby Smart Grid 11/09Baby Smart Grid 11/09
Baby Smart Grid 11/09jessmillar
 
W. Kempton, "The Grid-Integrated Electric Vehicle," in Electric Vehicle Integ...
W. Kempton, "The Grid-Integrated Electric Vehicle," in Electric Vehicle Integ...W. Kempton, "The Grid-Integrated Electric Vehicle," in Electric Vehicle Integ...
W. Kempton, "The Grid-Integrated Electric Vehicle," in Electric Vehicle Integ...Eamon Keane
 
PLS 2017: Residential electric vehicle charging - utilising the common street...
PLS 2017: Residential electric vehicle charging - utilising the common street...PLS 2017: Residential electric vehicle charging - utilising the common street...
PLS 2017: Residential electric vehicle charging - utilising the common street...Institution of Lighting Professionals
 
Electric Vehicle Services for Your Property by Eric Smith
Electric Vehicle Services for Your Property by Eric SmithElectric Vehicle Services for Your Property by Eric Smith
Electric Vehicle Services for Your Property by Eric SmithForth
 
Welcome all to travel green and carbon free road use electric vehicles on road
Welcome all to travel green and carbon free road use electric vehicles on roadWelcome all to travel green and carbon free road use electric vehicles on road
Welcome all to travel green and carbon free road use electric vehicles on roadMahesh Chandra Manav
 
A Case study on encouraging electric car usage
A Case study on encouraging electric car usageA Case study on encouraging electric car usage
A Case study on encouraging electric car usageCGI
 
V2G Cohort: The Future
V2G Cohort: The FutureV2G Cohort: The Future
V2G Cohort: The FutureKTN
 
Electric Vehicles Readiness and Charging at Multi-Unit Dwellings by Eric Huang
Electric Vehicles Readiness and Charging at Multi-Unit Dwellings by Eric HuangElectric Vehicles Readiness and Charging at Multi-Unit Dwellings by Eric Huang
Electric Vehicles Readiness and Charging at Multi-Unit Dwellings by Eric HuangForth
 
Connectivity Challenges for CAVs - Athonet Group
Connectivity Challenges for CAVs - Athonet GroupConnectivity Challenges for CAVs - Athonet Group
Connectivity Challenges for CAVs - Athonet GrouptechUK
 
Get Loose! Microservices and Loosely Coupled Architectures
Get Loose! Microservices and Loosely Coupled ArchitecturesGet Loose! Microservices and Loosely Coupled Architectures
Get Loose! Microservices and Loosely Coupled ArchitecturesDeborah Schalm
 

Semelhante a ELMO presentation in CHAdeMO's annual conference in Brussels in 18th February (20)

ELMO case study, e-mobility conference, Budapest 17. March 2015
ELMO case study, e-mobility conference, Budapest 17. March 2015ELMO case study, e-mobility conference, Budapest 17. March 2015
ELMO case study, e-mobility conference, Budapest 17. March 2015
 
Tuisk
TuiskTuisk
Tuisk
 
Presentation for the delegation of Finnish tech journalists about Estonian EV...
Presentation for the delegation of Finnish tech journalists about Estonian EV...Presentation for the delegation of Finnish tech journalists about Estonian EV...
Presentation for the delegation of Finnish tech journalists about Estonian EV...
 
Estonian Electromobility Program overview October 2012
Estonian Electromobility Program overview October 2012Estonian Electromobility Program overview October 2012
Estonian Electromobility Program overview October 2012
 
Ev employer initiative2-10-30-12
Ev employer initiative2-10-30-12Ev employer initiative2-10-30-12
Ev employer initiative2-10-30-12
 
Charge More...For Less with Cyber Switching EV Solutions
Charge More...For Less with Cyber Switching EV SolutionsCharge More...For Less with Cyber Switching EV Solutions
Charge More...For Less with Cyber Switching EV Solutions
 
Infrastructure Issues for Electric Vehicle Deployment in Ireland - ESB Networks
Infrastructure Issues for Electric Vehicle Deployment in Ireland - ESB NetworksInfrastructure Issues for Electric Vehicle Deployment in Ireland - ESB Networks
Infrastructure Issues for Electric Vehicle Deployment in Ireland - ESB Networks
 
Telecom Challenges and Electric Vehicles
Telecom Challenges and Electric VehiclesTelecom Challenges and Electric Vehicles
Telecom Challenges and Electric Vehicles
 
Nissan Leaf
Nissan LeafNissan Leaf
Nissan Leaf
 
EVfleetSolutions_ver2211(Eng) (1).pptx
EVfleetSolutions_ver2211(Eng) (1).pptxEVfleetSolutions_ver2211(Eng) (1).pptx
EVfleetSolutions_ver2211(Eng) (1).pptx
 
Baby Smart Grid 11/09
Baby Smart Grid 11/09Baby Smart Grid 11/09
Baby Smart Grid 11/09
 
W. Kempton, "The Grid-Integrated Electric Vehicle," in Electric Vehicle Integ...
W. Kempton, "The Grid-Integrated Electric Vehicle," in Electric Vehicle Integ...W. Kempton, "The Grid-Integrated Electric Vehicle," in Electric Vehicle Integ...
W. Kempton, "The Grid-Integrated Electric Vehicle," in Electric Vehicle Integ...
 
PLS 2017: Residential electric vehicle charging - utilising the common street...
PLS 2017: Residential electric vehicle charging - utilising the common street...PLS 2017: Residential electric vehicle charging - utilising the common street...
PLS 2017: Residential electric vehicle charging - utilising the common street...
 
Electric Vehicle Services for Your Property by Eric Smith
Electric Vehicle Services for Your Property by Eric SmithElectric Vehicle Services for Your Property by Eric Smith
Electric Vehicle Services for Your Property by Eric Smith
 
Welcome all to travel green and carbon free road use electric vehicles on road
Welcome all to travel green and carbon free road use electric vehicles on roadWelcome all to travel green and carbon free road use electric vehicles on road
Welcome all to travel green and carbon free road use electric vehicles on road
 
A Case study on encouraging electric car usage
A Case study on encouraging electric car usageA Case study on encouraging electric car usage
A Case study on encouraging electric car usage
 
V2G Cohort: The Future
V2G Cohort: The FutureV2G Cohort: The Future
V2G Cohort: The Future
 
Electric Vehicles Readiness and Charging at Multi-Unit Dwellings by Eric Huang
Electric Vehicles Readiness and Charging at Multi-Unit Dwellings by Eric HuangElectric Vehicles Readiness and Charging at Multi-Unit Dwellings by Eric Huang
Electric Vehicles Readiness and Charging at Multi-Unit Dwellings by Eric Huang
 
Connectivity Challenges for CAVs - Athonet Group
Connectivity Challenges for CAVs - Athonet GroupConnectivity Challenges for CAVs - Athonet Group
Connectivity Challenges for CAVs - Athonet Group
 
Get Loose! Microservices and Loosely Coupled Architectures
Get Loose! Microservices and Loosely Coupled ArchitecturesGet Loose! Microservices and Loosely Coupled Architectures
Get Loose! Microservices and Loosely Coupled Architectures
 

ELMO presentation in CHAdeMO's annual conference in Brussels in 18th February

  • 1. ELMO quick charging network How to develop nationwide charging network? Jarmo Tuisk Head of ELMO program, KredEx
  • 2. Topics • Background • Planning • Locations • Business model • Preparation and Installation • Launch and results
  • 3. BACKGROUND  Started in March 2011  Fully financed by CO2 quota sales to the Mitsubishi Corporation  Implemented by the Ministry of Economic Affairs and Communications  Implementation agency: KredEx
  • 4. ELMO program Advanced charging infrastructure Competence EV Grants centers Demo & Car sharing Awareness raising
  • 6. Planning: March – July 2011 • What are the use cases for various needs for recharging the EV? • What are the charging technology choices? • What is the expectations for the service? • What kind of IT infrastructure we need? • Where should we put those chargers? • How to complete the project in 18 months?
  • 7. Principal decisions • It’s going to be a “public safety network” to address range anxiety • We go for single operator/centrally managed business structure for the country wide network • We procure the full solution, including the service, from single consortium – minimizes the risks of technological incompatibilities
  • 8. Possible charging use cases Public/shared charger Routine shared Emergency charging charging Travel charging Pre- Unplanned planned charging charging Daily office charging Daily home charging Dedicated charger
  • 9. 3 main use-cases for the ELMO charging network Emergency • Locations hard to predict charging • Cover the main routes Shared routine • Locations easy to predict charging • Follow the daily routines • Locations easier to predict Travel charging • Emphasize tourist routes
  • 10. Use cases and technology options AC Normal AC Fast DC superfast 6-8h 1-2h 20-30min Daily office OK Maybe Not OK charging Daily home OK Maybe Not OK charging Routine shared Maybe Maybe OK charging Emergency Not OK Maybe OK charging Travel Not ok OK OK charging
  • 11. It takes time to plan the network It took roughly one year to be ready for the actual building works Guidelines Electricity projects Tech. Spec. Locations Building permits Q2 2011 Q3 2011 Q4 2011 Q1 2012 Q2 2012 Q3 2012 Q4 2012 Q1 2013
  • 13. LOCATION IS EVERYTHING! • Well, almost  • Why the locations are important? – Hard to secure them – Difficult to change them later – Your business is directly dependent on whether you hit the right spot in city or road • Problem: nothing to rely on, because you cannot count on the existing traffic data too much, battery vehicles are just too different.
  • 14. We created some simple rules • No more than 50-60 km between quick chargers in main roads • 1 quick charger for towns with more than 3000 inhabitants – Almost all Estonian towns, because somebody drives an EV there someday soon • Ca 1 quick charger per 10 000 inhabitant in cities with more than 10 000 inhabitant – Because there is statistical chance that somebody buys an EV there
  • 16. Operating model Private operator, selected by KredEx for 5 years Services Charger Business Customer Security Asset control and services support services management maintenance KredEx selected private operator to run the charging network for 5 years. Operator will receive a service fee for the operation. No profit from energy sales during initial 5 years. Owned by KredEx Assets Network High power Quick Locations for Intellectual management grid chargers chargers property system connections
  • 17. Business structure Owner and KredEx manager Main outsourcing ABB Estonia partner ABB G4S Now! Partners Netherlands (CRM services) (IT platform) (quick chargers)
  • 18. Pricing FLEX Combi Volume Monthly fee 0 EUR 10 EUR 30 EUR Pay per charge 5 EUR 2,5 EUR 0 EUR Limits No limits No limits 150kWh/ month 1,2EUR per charge after that
  • 20. The real action • We had two separate companies to do the real work – Elektritsentrum with multiple teams to prepare the locations (groundworks, cables from connection points, foundations for QCs) – ABB with multiple teams to install and set up the chargers • Amazing speed of deployment – We started building the locations in September 2012 – The network was completed by the end of January 2013 (with some chargers to be added in spring)
  • 21. Behind the scenes (last 3 months) • Training of the customer support teams • Development of business routines • Analysing early statistics to model pricing packages • Signing the electricity purchase contacts • Developing the legal side of the service • Setting up the pricing solutions • Testing IT background • Managing media relations • Informing the possible customers of network status • Etc etc
  • 23. Launch plan • Gradual launch – commission the charger ASAP • Free charging until the end of January • Introduction of future pricing schemes in late November • Customers were able to sign the contracts since December • Early January we switched to “authentification mode” • Since February charging is not free anymore • Big party coming in 20th February in Tallinn!
  • 24. The largest quick charging network in Europe Quick facts Project start: June 2011 Installation start: June 2012 Quick chargers working: 151 Total number: 165 Operated by ABB, G4S and Now! Innovations
  • 25. DC fast charging infrastructure development in Europe • Weird island in the upper right corner of Europe  • We had no idea, that this is how Europe will look like in 2013.
  • 26. www.estonia.eu Questions and answers THANK YOU! JARMO.TUISK@KREDEX.EE