O slideshow foi denunciado.
Seu SlideShare está sendo baixado. ×

Contract monitoring & evaluation

Anúncio
Anúncio
Anúncio
Anúncio
Anúncio
Anúncio
Anúncio
Anúncio
Anúncio
Anúncio
Anúncio
Anúncio
Próximos SlideShares
Chapter 2 [compatibility mode]
Chapter 2 [compatibility mode]
Carregando em…3
×

Confira estes a seguir

1 de 34 Anúncio

Mais Conteúdo rRelacionado

Diapositivos para si (20)

Quem viu também gostou (18)

Anúncio

Semelhante a Contract monitoring & evaluation (20)

Mais recentes (20)

Anúncio

Contract monitoring & evaluation

  1. 1. NAIROBI CBD CAMPUS JOMO KENYATTA UNIVERSITY OF AGRICULTURE AND TECHNOLOGY1
  2. 2. CONTRACT MONITORING AND EVALUATION 1) Tender format 2) Tender Evaluation 3) Procurement Schedule 4) Cost estimate 2 LECTURE 11
  3. 3. I.) TENDER FORMAT The Tender Document may consist of  Tendering Procedures  Requirements  Contract forms 3
  4. 4. PART 1 : Tendering Procedures  Instruction to Tenderers  Tender Data Sheet  Evaluation and Qualification Criteria  Tender Forms  Eligible / potential participants 4
  5. 5. PART 2 : Requirements  Technical requirements/specifications  Scope of statement of works  Definition of terms  Cost estimates  Define deliverables  Delivery schedule  Timelines 5
  6. 6. PART 3: Contract forms  General Conditions of Contract  Particular Conditions of Contract  Contract Forms 6
  7. 7. General Conditions of Contract Under general conditions of contract the following aspects are covered  Definition of terms  Application  Patent rights  Performance security 7
  8. 8. Continued…….  Payment prices/ contract sum  Termination of contract  Resolution of disputes  Governing language  Applicable law  Force majeure  Notices/intent to terminate a tender 8
  9. 9. Particular Conditions of Contract  These are specific to a particular tender/procurement  In general specific conditions are those which are unique to that particular tender and may not be applicable to another tender.  Every tender has its own specific conditions. 9
  10. 10. Contract Forms These are documents which are critical in formation of a contract agreement.  Form of tender  Price schedule form  Contract form  Confidential business questionnaire  Tenders security form  Performance security form 10
  11. 11. Other components are  Completed schedules  Tender security,  At the tenderer’s option, alternative proposals, if permissible,  Written confirmation authorizing the signatory of the tender to commit the tenderer, 11
  12. 12. Continued………  Documentary evidence establishing the eligibility of the goods and services offered by the tenderer,  Documentary evidence establishing the tenderer’s qualifications in accordance with the requirements, evaluation and qualification criteria, using the relevant forms furnished  Documentary evidence establishing the conformity of the technical proposal offered by the tenderer with the tender document, using the relevant forms  Any other document required 12
  13. 13. II) TENDER EVALUATIONS  Assessments that identify the tender that best meets the client’s needs and offers the best value for money is deemed to be more beneficial.  This is sometimes referred to as the ‘most economically advantageous tender’ (MEAT) as opposed to the lowest- price approach. 13
  14. 14. Continued………….. Typically, tender evaluations might consider some of the following  Price.  Relevant experience.  Understanding of the requirements.  Past performance.  Technical skills. 14
  15. 15. Continued…………..  Resource availability.  Management skills and systems.  Proposed methodology (this might include mobilizations plans, design proposals, and non- compliant proposals if these have been allowed).  Compliance with the requirements set out in the invitation to tender 15
  16. 16. III.) PROCUREMENT SCHEDULE  Contracting officers should develop a procurement schedule for the entire procurement cycle in consultation with the client 16
  17. 17. Continued…….. The following, as applicable, must be taken into consideration:  Review and analysis of the client's requirements;  Time for request for information process;  The procurement review committee;  Assessment/approval for the use of a fairness monitor; 17
  18. 18. Continued……..  Approval of the procurement plan or the contract planning and advance approval;  Solicitation documents preparation;  Translation requirements; 18
  19. 19. Continued……..  The time required for the preparation of and the receipt of bids, offers or arrangements, including site visits and bidders conference, if applicable;  Bidding period, and extensions;  Technical evaluation period;  Financial evaluation;  Benchmarking or other pre-award testing; 19
  20. 20. Continued……..  Recommendations from legal and financial reviews;  The evaluation process;  The requirement for negotiation;  The obtaining of security clearances;  The level of approval required;  Approval document preparation;  Any other item that might contribute to the time to complete the procurement. 20
  21. 21. IV.) COST ESTIMATE  A cost estimate is the approximation of the cost of a program, project, or operation.  The cost estimate is the product of the cost estimating process.  The cost estimate has a single total value and may have identifiable component values. 21
  22. 22. Continued…….  An estimator is the professional who prepares cost estimates. There are different types of estimators, such as building estimator, electrical estimator, chief estimator e.tc.  Other professional titles may also prepare estimates or contribute to estimates, such as quantity surveyors, cost engineers, etc. 22
  23. 23. Continued…… Cost estimate types  Various projects and operations have distinct types of cost estimating, which vary in their composition and preparation methods. Some of the major areas include: 23
  24. 24. Continued……  Construction cost  Manufacturing cost  Software development cost  Aerospace mission cost  Resource exploration cost  Facility operation cost  Facility maintenance and repair cost  Facility rehabilitation and renewal cost  Facility retirement cost 24
  25. 25. Continued…… Cost estimate classifications Common cost estimate classifications historically used are  Order of magnitude  Detailed estimate  Preliminary  Definitive 25
  26. 26. Continued…… Life Cycle Costing  Life cycle costing pertains to all four stages of the procurement process, from planning and acquisition to use and disposal. Currently, the Policy on Green Procurement applies to all federal government procurement activities. 26
  27. 27. Continued……  The Policy requires that environmental performance considerations be embedded into the procurement decision-making process in the same manner as price, performance, quality and availability. 27
  28. 28. Continued……  Some cost elements related to environmental factors that could be taken into account in assessing value for money in the evaluation of bids, offers or arrangements include: 28
  29. 29. Continued……  Operation costs, such as energy or water consumed by the product over its life;  Indirect costs (less energy efficient information technology equipment will produce more heat causing the building's air conditioning system to work harder, and increase electricity costs); 29
  30. 30. Continued……  Administrative costs, such as complying to workplace hazardous materials information system (whmis);  Investing up front to save costs later, such as specifying higher levels of insulation where the extra expenditure can be recovered from lower energy costs;  Cost of disposal arrangements; 30
  31. 31. Continued……  The application of total life cycle costing has traditionally meant the sum of the Product, Resource, Operating, and Contingent (PROC) costs relating to procurement. 31
  32. 32. Continued……  Life cycle costing pertains to all four stages of the procurement process, from planning and acquisition to use and disposal. Currently, the Policy on Green Procurement applies to all federal government procurement activities.  The Policy requires that environmental performance considerations be embedded into the procurement decision-making process in the same manner as price, performance, quality and availability. 32
  33. 33. Continued……  The PROC technique is essential for evaluating bids, offers or arrangements. Value for money includes the consideration of many factors such as cost, performance, availability, quality and environmental performance. 33
  34. 34. END 34

×