SlideShare uma empresa Scribd logo
1 de 55
Civil Engineering Drawing & 
Graphics 
What is formwork? 
When concrete is fresh and in its liquid state it must 
be restrained within a mould in order for it to set in its 
required shape. Formwork is the term used to 
describe this mould. 
For most in-situ pours, the formwork is made of 
wood. A smooth outer surface provides the main 
support for the concrete as it sets. This is normally 
made of plywood. 
Concrete is approximately 2.4 times as dense as 
water, and in its liquid state, it imposes considerable 
forces on the formwork containing it. Consequently it 
is necessary to reinforce the plywood with horizontal 
wooden beams or wailings.
Civil Engineering Drawing & 
Graphics
Civil Engineering Drawing & 
Graphics 
If constructed properly, this mechanism of a 
plywood skin supported by timber wailings 
provides ample support for the setting 
concrete. The mechanism of transferring these 
loads to a solid support can be performed by 
numerous methods which are collectively 
known as falsework.
Civil Engineering Drawing & 
Graphics 
GOOD FORMWORK: 
There are two factors that decide how well the 
concrete will look in the final result.. one is how 
the concrete is placed and compacted, and the 
other is the quality of the formwork. 
Formwork is made from expensive materials, and 
requires great skill and experience in its 
manufactures. Its importance is evident when you 
consider that the cost of fabrication, erecting and 
striking the formwork, often exceeds the cost of 
the concrete it is designed to shape and support.
Civil Engineering Drawing & 
Graphics 
 Formwork usually needs to be used many 
times for it to be cost efficient. This can only be 
done if it is carefully handled, cleaned and 
stored, regardless of what material it is made 
from. 
 For anything other than most smallest of 
concreting jobs e.g. walls over 1m in height, a 
drawing should be provided, showing what 
formwork is required. This need not be an 
intricate design drawing, a simple sketch is 
usually sufficient.
Civil Engineering Drawing & 
Graphics 
The below picture shows part of a concrete 
structure soon after the formwork has been 
struck. Not the poor finish (circled). This is an 
imprint off the painted plywood formwork. 
Some of the paint has run, and this has been 
transposed to the concrete. It is important to 
remember that the face of the concrete is 
effectively a negative of the formwork face. 
Always inspect the formwork prior to pouring.
Civil Engineering Drawing & 
Graphics
Civil Engineering Drawing & 
Graphics 
Good formwork should fulfill the following 
criteria: 
 It is strong enough to support the weight 
of fresh concrete during placing and 
compacting, and any other loads it may be 
required to take. 
 The face of the formwork is of sufficient quality 
for its use. 
 It can be easily erected and struck. 
 It is sufficiently stable in all weathers.
Civil Engineering Drawing & 
Graphics 
 It can be handled safely and easily using the 
equipment available. 
 It provides suitable access for placing and 
compacting the concrete. 
 It conforms with appropriate safety regulations. 
 The joints between members are sound 
enough to prevent grout leakage.
Civil Engineering Drawing & 
Graphics 
Formwork is an ancillary construction, used as 
a mould for a structure. Into this mould, fresh 
concrete is placed only to harden 
subsequently. The construction of formwork 
takes time and involves expenditure up to 20 
to 25% of the cost of the structure or even 
more. Design of these temporary structures 
are made to economic expenditure.
Civil Engineering Drawing & 
Graphics 
The operation of removing the formwork is 
known as stripping. Stripped formwork can be 
reused. Reusable forms are known as panel 
forms and non-usable are called stationary 
forms. 
Timber is the most common material used for 
formwork. The disadvantage with timber 
formwork is that it will warp, swell and shrink. 
Application of water impermeable cost to the 
surface of wood mitigates these defects.
Civil Engineering Drawing & 
Graphics 
A good formwork should satisfy the following 
requirements: 
 It should be strong enough to withstand all types 
of dead and live loads. 
 It should be rigidly constructed and efficiently 
propped and braced both horizontally and 
vertically, so as to retain its shape. 
 The joints in the formwork should be tight against 
leakage of cement grout. 
 Construction of formwork should permit removal 
of various parts in desired sequences without 
damage to the concrete.
Civil Engineering Drawing & 
Graphics 
 The material of the formwork should be cheap, 
easily available and should be suitable for 
reuse. 
 The formwork should be set accurately to the 
desired line and levels should have plane 
surface. 
 It should be as light as possible. 
 The material of the formwork should not warp 
or get distorted when exposed to the elements. 
 It should rest on firm base.
Civil Engineering Drawing & 
Graphics 
Economy in Formwork: 
 The plan of the building should imply minimum 
number of variations in the size of rooms, floor 
area etc. so as to permit reuse of the formwork 
repeatedly. 
 Design should be perfect to use slender sections 
only in a most economical way. 
 Minimum sawing and cutting of wooden pieces 
should be made to enable reuse of the material a 
number of times. The quantity of surface finish 
depends on the quality of the formwork.
Civil Engineering Drawing & 
Graphics 
Formwork can be made out of timber, 
plywood, steel, precast concrete or fiber glass 
used separately or in combination. Steel forms 
are used in situation where large numbers of 
re-use of the same forms are necessary.
Civil Engineering Drawing & 
Graphics 
For small works, timber formwork proves 
useful. Fiber glass made of pre-cast concrete 
and aluminum are used in cast-in-situ 
construction such as slabs or members 
involving curved surfaces.
Civil Engineering Drawing & 
Graphics 
Following are the materials which are used for formwork: 
 Plywood: 
This is by far the most common material used for the 
facing panel. It is easily cut to shape on site, and if 
handled and stored carefully, it can be used many 
times. 
Note the different thickness: A standard plywood 
thickness on site is 18mm. this is usually sufficient for 
most pours. However, if the formwork is curved, a 
thinner plywood is used to facilitate bending. Thicker 
plywood may be used when the weight of concrete 
causes a standard thickness plywood to bow out, 
distorting the concrete face.
Civil Engineering Drawing & 
Graphics 
 Timber: 
This is the most common material used for 
bracing members to the form face. Like 
plywood, it can be easily cut to size on site. 
Formwork made from timber is called 
traditional formwork. The construction methods 
using timber formwork have been used on site 
for years, and all well understood by trained 
operators.
Civil Engineering Drawing & 
Graphics 
Ply wood Timber
Civil Engineering Drawing & 
Graphics 
Steel: 
Steel is also used in pre-fabricated formwork. 
Purpose made steel forms are fabricated when 
dimensional tolerances are critical, or when 
the forms are planned to be re-used. Steel 
forms become cost-efficient after about a 
dozen uses, although they can be used up to 
100 pours if they are carefully cleaned and 
stored.
Civil Engineering Drawing & 
Graphics
Civil Engineering Drawing & 
Graphics 
Aluminum: 
Often used in pre-fabricated formwork, that is 
put together on site. Aluminum is strong and 
light, and consequently fewer supports and 
ties are required. The lighter sections will 
deflect more, but this can be avoided by simply 
following the manufacturers recommendations.
Civil Engineering Drawing & 
Graphics 
Plastics: 
Glass reinforced plastics (GRP) and vacuum 
formed plastics are used when complicated 
concrete shapes are required (e.g. waffle 
floors). Although vacuum formed plastics will 
always need support, GRP can be fabricated 
with integral bearers making it self supporting. 
Like steel, plastic formwork can be re-used 
many times, as long as care is taken not to 
scour the surface whilst vibrating the concrete.
Civil Engineering Drawing & 
Graphics 
Timber Formwork: 
Timber for formwork should satisfy the following 
requirement: 
It should be, 
1. Well seasoned 
2. Light in weight 
3. Easily workable with nails without splitting 
4. Free from loose knots 
Timber used for shuttering for exposed concrete 
work should have smooth and even surface on all 
faces which come in contact with concrete.
Civil Engineering Drawing & 
Graphics 
Normal sizes of members for timber 
formwork: 
Sheeting for slabs, beam, column side and 
beam bottom 
25 mm to 40mm thick 
Joints, ledges 
50 x 70 mm to 50 x 150 mm 
Posts 
75 x 100mm to 100 x 100 mm
Civil Engineering Drawing & 
Graphics
Civil Engineering Drawing & 
Graphics 
Plywood Formwork: 
Resin bonded plywood sheets are attached to 
timber frames to make up panels of required 
sizes. The cost of plywood formwork compares 
favorably with that of timber shuttering and it 
may even prove cheaper in certain cases in 
view of the following considerations:
Civil Engineering Drawing & 
Graphics 
 It is possible to have smooth finish in which 
case on cost in surface finishing is there. 
 By use of large size panels it is possible to 
effect saving in the labor cost of fixing and 
dismantling. 
 Number of reuses are more as compared with 
timber shuttering. For estimation purpose, 
number of reuses can be taken as 20 to 25.
Civil Engineering Drawing & 
Graphics 
Steel Formwork: 
This consist of panels fabricated out of thin 
steel plates stiffened along the edges by small 
steel angles. The panel units can be held 
together through the use of suitable clamps or 
bolts and nuts. The panels can be fabricated in 
large number in any desired modular shape or 
size.
Civil Engineering Drawing & 
Graphics 
Steel forms are largely used in large projects 
or in situation where large number reuses of 
the shuttering is possible. This type of 
shuttering is considered most suitable for 
circular or curved structures.
Civil Engineering Drawing & 
Graphics 
Steel forms compared with timber formwork: 
 Steel forms are stronger, durable and have longer 
life than timber formwork and their reuses are 
more in number. 
 Steel forms can be installed and dismantled with 
greater ease and speed. 
 The quality of exposed concrete surface by using 
steel forms is good and such surfaces need no 
further treatment. 
 Steel formwork does not absorb moisture from 
concrete. 
 Steel formwork does not shrink or warp.
Civil Engineering Drawing & 
Graphics 
Construction of formwork: 
This normally involves the following operations: 
1. Propping and centering 
2. Shuttering 
3. Provision of camber 
4. Cleaning and surface treatment
Civil Engineering Drawing & 
Graphics 
Order and method of removing formwork: 
The sequence of orders and method of removal 
of formwork are as follows: 
 Shuttering forming the vertical faces of walls, 
beams and column sides should be removed first 
as they bear no load but only retain the concrete. 
 Shuttering forming soffit of slabs should be 
removed next. 
 Shuttering forming soffit of beams, girders or other 
heavily loaded shuttering should be removed in 
the end.
Civil Engineering Drawing & 
Graphics 
Rapid hardening cement, warm weather and 
light loading conditions allow early removal of 
formwork. The formwork should under no 
circumstances be allowed to be removed until 
all the concrete reaches strength of at least 
twice the stresses to which the concrete may 
be subjected at the time of removal of 
formwork. All formworks should be eased 
gradually and carefully in order to prevent the 
load being suddenly transferred to concrete.
Civil Engineering Drawing & 
Graphics 
Details of timber formwork for 
RCC beam and slab floor Details at section shown in figure
Civil Engineering Drawing & 
Graphics 
Elevation Details of timber formwork for 
circular RCC column
Civil Engineering Drawing & 
Graphics 
3D View 
Details of timber formwork for 
square or rectangular RCC 
column
Civil Engineering Drawing & 
Graphics 
Sectional plan showing details of 
timber formwork for an octagonal 
column 
Details of formwork for stair
Timber formwork for RCC wall
Civil Engineering Drawing & 
Graphics 
Period of removal of formwork: 
Walls, columns and vertical sides of beams 
1 to 2 days 
Slabs (props left under) 
3 days 
Beam soffits (props left under) 
7 days
Civil Engineering Drawing & 
Graphics 
Removal of props to slabs 
(a) For slabs spanning up to 4.5 m 7 days 
(b) For slabs spanning over 4.5 m 14 days 
Removal of props to beams and arches 
(a) Spanning up to 6 m 14 days 
(b) spanning over 6 m 21 days
Civil Engineering Drawing & 
Graphics 
PRE-CONCRETE CHECKS FOR FORMWORK: 
Before the concrete is poured into the 
formwork, it must be checked by someone 
who has been trained to inspect formwork. 
Depending on how big or complicated the pour 
is, the inspection may just take few minutes or 
it could take hours. Only when the formwork 
has been approved, may the pour take place.
Civil Engineering Drawing & 
Graphics 
Formwork pressures are function of height 
(including the height from which concrete is 
dropped into the forms) and are affected by 
concrete workability, rate of stiffening and rate 
of placing. One task of the temporary works 
coordinator is to consider such factors as 
ambient temperatures and concrete 
composition, when calculating maximum 
permissible rate of concrete placing.
Civil Engineering Drawing & 
Graphics 
Exceeding this limit may lead to unacceptable 
formwork deflections, loss of grout / concrete 
at joints, or even collapse. The cost of 
remedial work due to formwork deflection will 
usually exceed the original cost of doing the 
job properly.
Civil Engineering Drawing & 
Graphics
Civil Engineering Drawing & 
Graphics 
Below are the checks that should be verified 
before pouring begins: 
 Is the formwork erected in accordance with the 
approved drawings? 
 Is the formwork restrained against movement in all 
directions? 
 Is it correctly aligned and leveled? 
 Are all the props plum, and at the right spacing? 
 Are bolts and wedges secure against any possible 
loosening? 
 Has the correct number of ties been used? Are they in 
the right places and properly tightened?
Civil Engineering Drawing & 
Graphics 
 Are all inserts and cast-in fixings in the right 
position and secure? 
 Have all stop ends been properly secured? 
 Have all the joints been sealed to stop grout 
loss (especially where the formwork is against 
the kicker)? 
 Can the formwork be struck without damaging 
the concrete?
Civil Engineering Drawing & 
Graphics 
 Are the forms clean and free from rubbish such as 
tie wire cuttings, and odd bits of timber or metal? 
 Has the release agents been applied, and is it the 
correct one? 
 Are all projecting bars straight and correctly 
positioned? 
 Is there proper access for placing the concrete 
and compacting? 
 Have all the toe-boards and guard rails been 
provided?
Civil Engineering Drawing & 
Graphics 
RELEASE AGENTS FOR FORMWORK: 
Formwork needs to be treated with a release 
agent so that it can be removed easily after the 
concrete has set. Failure to use a release 
agent can result in the formwork sticking to the 
concrete, which may lead to damage of the 
concrete surface.
Civil Engineering Drawing & 
Graphics 
A single application of release agent is all that 
is required when forms are then used. Care 
must be taken to cover all the surface that will 
come in contact with the surface of concrete. 
However, if there is an excess of release 
agent, it may cause staining or retardation of 
the concrete.
Civil Engineering Drawing & 
Graphics 
There are different release agents depending 
on what material is used for the formwork. 
The three (03) most common release agents 
for formwork are: 
 Neat oils with surfactants: used mainly on 
steel surfaces, but also suitable for timber and 
plywood.
Civil Engineering Drawing & 
Graphics 
 Mould cream emulsions: good general 
purpose release agents for use on timber and 
plywood. 
 Chemical release agents: recommended for 
high quality work, applied by spray to all types 
of form face.
Civil Engineering Drawing & 
Graphics 
ASSIGNMENT (A REPORT) 
MiNi-Project 
In M.S Word, do make a brief report of at least 
20 pages having in it “Pictures” from original 
sites covering 18 chapters of the referred text 
book (Preferably 01 page for each chapter). 
Try to make report understandable by 
providing sequential pictures of the 
phenomenon and a minimum of 4 to 6 lines in 
each page and relevant topic.
Formwork in civil engineering

Mais conteúdo relacionado

Mais procurados

BUILDING CONSTRUCTION Presentation
BUILDING CONSTRUCTION PresentationBUILDING CONSTRUCTION Presentation
BUILDING CONSTRUCTION PresentationDrazzer_Dhruv
 
6. intro to building materials
6. intro to building materials6. intro to building materials
6. intro to building materialsHamdija Velagic
 
Stone Masonry BUILDING CONSTRUCTION
Stone Masonry BUILDING CONSTRUCTIONStone Masonry BUILDING CONSTRUCTION
Stone Masonry BUILDING CONSTRUCTIONRavindra Patnayaka
 
Chapter 4 (d) hollow concrete block masonry
Chapter 4 (d) hollow concrete block masonryChapter 4 (d) hollow concrete block masonry
Chapter 4 (d) hollow concrete block masonryKHUSHBU SHAH
 
Pre cast vs cast-in-situ concrete
Pre cast vs cast-in-situ concretePre cast vs cast-in-situ concrete
Pre cast vs cast-in-situ concreteRajat Nainwal
 
BASICS COMPONENTS OF BUILDING DRAWING FOR CIVIL ENGINEERS
BASICS COMPONENTS OF BUILDING DRAWING FOR CIVIL ENGINEERSBASICS COMPONENTS OF BUILDING DRAWING FOR CIVIL ENGINEERS
BASICS COMPONENTS OF BUILDING DRAWING FOR CIVIL ENGINEERSHafiz JUNAID
 
RCC Elements column, beam.
RCC Elements  column, beam.RCC Elements  column, beam.
RCC Elements column, beam.Puneet Chhonker
 
Timber as building material
Timber as building materialTimber as building material
Timber as building materialPrasadnb55
 
Building Construction 8. formworks and scaffoldings
Building Construction 8. formworks and scaffoldingsBuilding Construction 8. formworks and scaffoldings
Building Construction 8. formworks and scaffoldingsHamdija Velagic
 
rapid walls- modular construction technology
rapid walls- modular construction technologyrapid walls- modular construction technology
rapid walls- modular construction technologyAnjith Augustine
 
Temporary structures
Temporary structuresTemporary structures
Temporary structuresDivya Vishnoi
 
Aluminium Formwork Vs Conventional Formwork
Aluminium Formwork Vs  Conventional  FormworkAluminium Formwork Vs  Conventional  Formwork
Aluminium Formwork Vs Conventional Formworkchaitanyakrsk
 
Formwork, by prof. sagar raut
Formwork, by prof. sagar rautFormwork, by prof. sagar raut
Formwork, by prof. sagar rautSAGAR RAUT
 
REINFORCEMENT CONCRETE chapter 1
REINFORCEMENT CONCRETE chapter 1REINFORCEMENT CONCRETE chapter 1
REINFORCEMENT CONCRETE chapter 1Natalie Ulza
 
Chapter 5 formwork
Chapter 5 formworkChapter 5 formwork
Chapter 5 formworkKHUSHBU SHAH
 
STEEL STRUCTURE CONSTRUCTION.
STEEL STRUCTURE CONSTRUCTION.STEEL STRUCTURE CONSTRUCTION.
STEEL STRUCTURE CONSTRUCTION.Mehul Gohil
 

Mais procurados (20)

BUILDING CONSTRUCTION Presentation
BUILDING CONSTRUCTION PresentationBUILDING CONSTRUCTION Presentation
BUILDING CONSTRUCTION Presentation
 
6. intro to building materials
6. intro to building materials6. intro to building materials
6. intro to building materials
 
Formwork
FormworkFormwork
Formwork
 
Stone Masonry BUILDING CONSTRUCTION
Stone Masonry BUILDING CONSTRUCTIONStone Masonry BUILDING CONSTRUCTION
Stone Masonry BUILDING CONSTRUCTION
 
Chapter 4 (d) hollow concrete block masonry
Chapter 4 (d) hollow concrete block masonryChapter 4 (d) hollow concrete block masonry
Chapter 4 (d) hollow concrete block masonry
 
Pre cast vs cast-in-situ concrete
Pre cast vs cast-in-situ concretePre cast vs cast-in-situ concrete
Pre cast vs cast-in-situ concrete
 
Joints in concrete
Joints in concreteJoints in concrete
Joints in concrete
 
BASICS COMPONENTS OF BUILDING DRAWING FOR CIVIL ENGINEERS
BASICS COMPONENTS OF BUILDING DRAWING FOR CIVIL ENGINEERSBASICS COMPONENTS OF BUILDING DRAWING FOR CIVIL ENGINEERS
BASICS COMPONENTS OF BUILDING DRAWING FOR CIVIL ENGINEERS
 
Formwork
FormworkFormwork
Formwork
 
RCC Elements column, beam.
RCC Elements  column, beam.RCC Elements  column, beam.
RCC Elements column, beam.
 
Timber as building material
Timber as building materialTimber as building material
Timber as building material
 
Building Construction 8. formworks and scaffoldings
Building Construction 8. formworks and scaffoldingsBuilding Construction 8. formworks and scaffoldings
Building Construction 8. formworks and scaffoldings
 
rapid walls- modular construction technology
rapid walls- modular construction technologyrapid walls- modular construction technology
rapid walls- modular construction technology
 
Temporary structures
Temporary structuresTemporary structures
Temporary structures
 
Steel structure
Steel structureSteel structure
Steel structure
 
Aluminium Formwork Vs Conventional Formwork
Aluminium Formwork Vs  Conventional  FormworkAluminium Formwork Vs  Conventional  Formwork
Aluminium Formwork Vs Conventional Formwork
 
Formwork, by prof. sagar raut
Formwork, by prof. sagar rautFormwork, by prof. sagar raut
Formwork, by prof. sagar raut
 
REINFORCEMENT CONCRETE chapter 1
REINFORCEMENT CONCRETE chapter 1REINFORCEMENT CONCRETE chapter 1
REINFORCEMENT CONCRETE chapter 1
 
Chapter 5 formwork
Chapter 5 formworkChapter 5 formwork
Chapter 5 formwork
 
STEEL STRUCTURE CONSTRUCTION.
STEEL STRUCTURE CONSTRUCTION.STEEL STRUCTURE CONSTRUCTION.
STEEL STRUCTURE CONSTRUCTION.
 

Semelhante a Formwork in civil engineering

form work - Building construction necessities
form work - Building construction necessities  form work - Building construction necessities
form work - Building construction necessities Pradumn Suryakar
 
Formwork seminar 2
Formwork seminar 2Formwork seminar 2
Formwork seminar 2Gali Suresh
 
Types of Formwork & Materials.pptx
Types of Formwork & Materials.pptxTypes of Formwork & Materials.pptx
Types of Formwork & Materials.pptxMr Amol Ghogare
 
Formwork construction in structures
Formwork construction in structuresFormwork construction in structures
Formwork construction in structuresRithika Ravishankar
 
Formwork-Types and Their Advantages
Formwork-Types and Their AdvantagesFormwork-Types and Their Advantages
Formwork-Types and Their AdvantagesJay1997Singhania
 
formwork Bco (1) final.pdf
formwork Bco (1) final.pdfformwork Bco (1) final.pdf
formwork Bco (1) final.pdfFaizanSolanki
 
Formwork For Structural Member.pptx
Formwork For Structural Member.pptxFormwork For Structural Member.pptx
Formwork For Structural Member.pptxMr Amol Ghogare
 
From work & shuttering
From work & shutteringFrom work & shuttering
From work & shutteringhamidgujjar
 
Formwork & Falsework Practice_2009(July)_to AK.pdf
Formwork & Falsework Practice_2009(July)_to AK.pdfFormwork & Falsework Practice_2009(July)_to AK.pdf
Formwork & Falsework Practice_2009(July)_to AK.pdfLiesaStone
 
Forms and materials for speedy construction
Forms and materials for speedy constructionForms and materials for speedy construction
Forms and materials for speedy constructionMudassir khan
 
Form-work in construction
Form-work in construction Form-work in construction
Form-work in construction purvi golecha
 
Precast compound wall
Precast compound wallPrecast compound wall
Precast compound wallHarsh Bothra
 
Atecon product catalogue 2017
Atecon product catalogue 2017Atecon product catalogue 2017
Atecon product catalogue 2017Atecon
 

Semelhante a Formwork in civil engineering (20)

form work - Building construction necessities
form work - Building construction necessities  form work - Building construction necessities
form work - Building construction necessities
 
Formwork seminar 2
Formwork seminar 2Formwork seminar 2
Formwork seminar 2
 
Types of Formwork & Materials.pptx
Types of Formwork & Materials.pptxTypes of Formwork & Materials.pptx
Types of Formwork & Materials.pptx
 
Gurme santoshkumar
Gurme santoshkumarGurme santoshkumar
Gurme santoshkumar
 
Formwork construction in structures
Formwork construction in structuresFormwork construction in structures
Formwork construction in structures
 
Unit 16
Unit 16Unit 16
Unit 16
 
Formwork-Types and Their Advantages
Formwork-Types and Their AdvantagesFormwork-Types and Their Advantages
Formwork-Types and Their Advantages
 
Formwork
FormworkFormwork
Formwork
 
formwork Bco (1) final.pdf
formwork Bco (1) final.pdfformwork Bco (1) final.pdf
formwork Bco (1) final.pdf
 
RCC Floor
RCC FloorRCC Floor
RCC Floor
 
Temporary Works (Form Work)
Temporary Works (Form Work)Temporary Works (Form Work)
Temporary Works (Form Work)
 
Formwork For Structural Member.pptx
Formwork For Structural Member.pptxFormwork For Structural Member.pptx
Formwork For Structural Member.pptx
 
From work & shuttering
From work & shutteringFrom work & shuttering
From work & shuttering
 
Design and Manufacturing Homework Help
Design and Manufacturing Homework HelpDesign and Manufacturing Homework Help
Design and Manufacturing Homework Help
 
Formwork & Falsework Practice_2009(July)_to AK.pdf
Formwork & Falsework Practice_2009(July)_to AK.pdfFormwork & Falsework Practice_2009(July)_to AK.pdf
Formwork & Falsework Practice_2009(July)_to AK.pdf
 
Forms and materials for speedy construction
Forms and materials for speedy constructionForms and materials for speedy construction
Forms and materials for speedy construction
 
Form-work in construction
Form-work in construction Form-work in construction
Form-work in construction
 
Formwork
FormworkFormwork
Formwork
 
Precast compound wall
Precast compound wallPrecast compound wall
Precast compound wall
 
Atecon product catalogue 2017
Atecon product catalogue 2017Atecon product catalogue 2017
Atecon product catalogue 2017
 

Mais de Fazal-E- Jalal

Mais de Fazal-E- Jalal (15)

E. soil classification
E. soil classificationE. soil classification
E. soil classification
 
D. atterberg limits
D. atterberg limitsD. atterberg limits
D. atterberg limits
 
C. sieve analysis & hydrometer analysis
C. sieve analysis & hydrometer analysisC. sieve analysis & hydrometer analysis
C. sieve analysis & hydrometer analysis
 
B. water content & sp. gravity
B. water content & sp. gravityB. water content & sp. gravity
B. water content & sp. gravity
 
A. lab report (an introduction)
A. lab report (an introduction)A. lab report (an introduction)
A. lab report (an introduction)
 
Floors and flooring
Floors and flooringFloors and flooring
Floors and flooring
 
Dampness in buildings
Dampness in buildingsDampness in buildings
Dampness in buildings
 
Photogrammetry
PhotogrammetryPhotogrammetry
Photogrammetry
 
Gps
GpsGps
Gps
 
Construction surveys
Construction surveysConstruction surveys
Construction surveys
 
Introduction to Heavy Construction Machinery
Introduction to Heavy Construction MachineryIntroduction to Heavy Construction Machinery
Introduction to Heavy Construction Machinery
 
Concrete equipment
Concrete equipmentConcrete equipment
Concrete equipment
 
2. introduction
2. introduction2. introduction
2. introduction
 
1b. introduction
1b. introduction1b. introduction
1b. introduction
 
1. introduction
1. introduction1. introduction
1. introduction
 

Último

complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...asadnawaz62
 
Correctly Loading Incremental Data at Scale
Correctly Loading Incremental Data at ScaleCorrectly Loading Incremental Data at Scale
Correctly Loading Incremental Data at ScaleAlluxio, Inc.
 
Work Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvWork Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvLewisJB
 
System Simulation and Modelling with types and Event Scheduling
System Simulation and Modelling with types and Event SchedulingSystem Simulation and Modelling with types and Event Scheduling
System Simulation and Modelling with types and Event SchedulingBootNeck1
 
welding defects observed during the welding
welding defects observed during the weldingwelding defects observed during the welding
welding defects observed during the weldingMuhammadUzairLiaqat
 
Virtual memory management in Operating System
Virtual memory management in Operating SystemVirtual memory management in Operating System
Virtual memory management in Operating SystemRashmi Bhat
 
National Level Hackathon Participation Certificate.pdf
National Level Hackathon Participation Certificate.pdfNational Level Hackathon Participation Certificate.pdf
National Level Hackathon Participation Certificate.pdfRajuKanojiya4
 
Vishratwadi & Ghorpadi Bridge Tender documents
Vishratwadi & Ghorpadi Bridge Tender documentsVishratwadi & Ghorpadi Bridge Tender documents
Vishratwadi & Ghorpadi Bridge Tender documentsSachinPawar510423
 
Indian Dairy Industry Present Status and.ppt
Indian Dairy Industry Present Status and.pptIndian Dairy Industry Present Status and.ppt
Indian Dairy Industry Present Status and.pptMadan Karki
 
Industrial Safety Unit-IV workplace health and safety.ppt
Industrial Safety Unit-IV workplace health and safety.pptIndustrial Safety Unit-IV workplace health and safety.ppt
Industrial Safety Unit-IV workplace health and safety.pptNarmatha D
 
Mine Environment II Lab_MI10448MI__________.pptx
Mine Environment II Lab_MI10448MI__________.pptxMine Environment II Lab_MI10448MI__________.pptx
Mine Environment II Lab_MI10448MI__________.pptxRomil Mishra
 
Introduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxIntroduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxk795866
 
Transport layer issues and challenges - Guide
Transport layer issues and challenges - GuideTransport layer issues and challenges - Guide
Transport layer issues and challenges - GuideGOPINATHS437943
 
Internet of things -Arshdeep Bahga .pptx
Internet of things -Arshdeep Bahga .pptxInternet of things -Arshdeep Bahga .pptx
Internet of things -Arshdeep Bahga .pptxVelmuruganTECE
 
Risk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfRisk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfROCENODodongVILLACER
 
home automation using Arduino by Aditya Prasad
home automation using Arduino by Aditya Prasadhome automation using Arduino by Aditya Prasad
home automation using Arduino by Aditya Prasadaditya806802
 
The SRE Report 2024 - Great Findings for the teams
The SRE Report 2024 - Great Findings for the teamsThe SRE Report 2024 - Great Findings for the teams
The SRE Report 2024 - Great Findings for the teamsDILIPKUMARMONDAL6
 

Último (20)

complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...
 
Correctly Loading Incremental Data at Scale
Correctly Loading Incremental Data at ScaleCorrectly Loading Incremental Data at Scale
Correctly Loading Incremental Data at Scale
 
Work Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvWork Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvv
 
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
 
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Serviceyoung call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
 
System Simulation and Modelling with types and Event Scheduling
System Simulation and Modelling with types and Event SchedulingSystem Simulation and Modelling with types and Event Scheduling
System Simulation and Modelling with types and Event Scheduling
 
POWER SYSTEMS-1 Complete notes examples
POWER SYSTEMS-1 Complete notes  examplesPOWER SYSTEMS-1 Complete notes  examples
POWER SYSTEMS-1 Complete notes examples
 
welding defects observed during the welding
welding defects observed during the weldingwelding defects observed during the welding
welding defects observed during the welding
 
Virtual memory management in Operating System
Virtual memory management in Operating SystemVirtual memory management in Operating System
Virtual memory management in Operating System
 
National Level Hackathon Participation Certificate.pdf
National Level Hackathon Participation Certificate.pdfNational Level Hackathon Participation Certificate.pdf
National Level Hackathon Participation Certificate.pdf
 
Vishratwadi & Ghorpadi Bridge Tender documents
Vishratwadi & Ghorpadi Bridge Tender documentsVishratwadi & Ghorpadi Bridge Tender documents
Vishratwadi & Ghorpadi Bridge Tender documents
 
Indian Dairy Industry Present Status and.ppt
Indian Dairy Industry Present Status and.pptIndian Dairy Industry Present Status and.ppt
Indian Dairy Industry Present Status and.ppt
 
Industrial Safety Unit-IV workplace health and safety.ppt
Industrial Safety Unit-IV workplace health and safety.pptIndustrial Safety Unit-IV workplace health and safety.ppt
Industrial Safety Unit-IV workplace health and safety.ppt
 
Mine Environment II Lab_MI10448MI__________.pptx
Mine Environment II Lab_MI10448MI__________.pptxMine Environment II Lab_MI10448MI__________.pptx
Mine Environment II Lab_MI10448MI__________.pptx
 
Introduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxIntroduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptx
 
Transport layer issues and challenges - Guide
Transport layer issues and challenges - GuideTransport layer issues and challenges - Guide
Transport layer issues and challenges - Guide
 
Internet of things -Arshdeep Bahga .pptx
Internet of things -Arshdeep Bahga .pptxInternet of things -Arshdeep Bahga .pptx
Internet of things -Arshdeep Bahga .pptx
 
Risk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfRisk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdf
 
home automation using Arduino by Aditya Prasad
home automation using Arduino by Aditya Prasadhome automation using Arduino by Aditya Prasad
home automation using Arduino by Aditya Prasad
 
The SRE Report 2024 - Great Findings for the teams
The SRE Report 2024 - Great Findings for the teamsThe SRE Report 2024 - Great Findings for the teams
The SRE Report 2024 - Great Findings for the teams
 

Formwork in civil engineering

  • 1.
  • 2. Civil Engineering Drawing & Graphics What is formwork? When concrete is fresh and in its liquid state it must be restrained within a mould in order for it to set in its required shape. Formwork is the term used to describe this mould. For most in-situ pours, the formwork is made of wood. A smooth outer surface provides the main support for the concrete as it sets. This is normally made of plywood. Concrete is approximately 2.4 times as dense as water, and in its liquid state, it imposes considerable forces on the formwork containing it. Consequently it is necessary to reinforce the plywood with horizontal wooden beams or wailings.
  • 4. Civil Engineering Drawing & Graphics If constructed properly, this mechanism of a plywood skin supported by timber wailings provides ample support for the setting concrete. The mechanism of transferring these loads to a solid support can be performed by numerous methods which are collectively known as falsework.
  • 5. Civil Engineering Drawing & Graphics GOOD FORMWORK: There are two factors that decide how well the concrete will look in the final result.. one is how the concrete is placed and compacted, and the other is the quality of the formwork. Formwork is made from expensive materials, and requires great skill and experience in its manufactures. Its importance is evident when you consider that the cost of fabrication, erecting and striking the formwork, often exceeds the cost of the concrete it is designed to shape and support.
  • 6. Civil Engineering Drawing & Graphics  Formwork usually needs to be used many times for it to be cost efficient. This can only be done if it is carefully handled, cleaned and stored, regardless of what material it is made from.  For anything other than most smallest of concreting jobs e.g. walls over 1m in height, a drawing should be provided, showing what formwork is required. This need not be an intricate design drawing, a simple sketch is usually sufficient.
  • 7. Civil Engineering Drawing & Graphics The below picture shows part of a concrete structure soon after the formwork has been struck. Not the poor finish (circled). This is an imprint off the painted plywood formwork. Some of the paint has run, and this has been transposed to the concrete. It is important to remember that the face of the concrete is effectively a negative of the formwork face. Always inspect the formwork prior to pouring.
  • 9. Civil Engineering Drawing & Graphics Good formwork should fulfill the following criteria:  It is strong enough to support the weight of fresh concrete during placing and compacting, and any other loads it may be required to take.  The face of the formwork is of sufficient quality for its use.  It can be easily erected and struck.  It is sufficiently stable in all weathers.
  • 10. Civil Engineering Drawing & Graphics  It can be handled safely and easily using the equipment available.  It provides suitable access for placing and compacting the concrete.  It conforms with appropriate safety regulations.  The joints between members are sound enough to prevent grout leakage.
  • 11. Civil Engineering Drawing & Graphics Formwork is an ancillary construction, used as a mould for a structure. Into this mould, fresh concrete is placed only to harden subsequently. The construction of formwork takes time and involves expenditure up to 20 to 25% of the cost of the structure or even more. Design of these temporary structures are made to economic expenditure.
  • 12. Civil Engineering Drawing & Graphics The operation of removing the formwork is known as stripping. Stripped formwork can be reused. Reusable forms are known as panel forms and non-usable are called stationary forms. Timber is the most common material used for formwork. The disadvantage with timber formwork is that it will warp, swell and shrink. Application of water impermeable cost to the surface of wood mitigates these defects.
  • 13. Civil Engineering Drawing & Graphics A good formwork should satisfy the following requirements:  It should be strong enough to withstand all types of dead and live loads.  It should be rigidly constructed and efficiently propped and braced both horizontally and vertically, so as to retain its shape.  The joints in the formwork should be tight against leakage of cement grout.  Construction of formwork should permit removal of various parts in desired sequences without damage to the concrete.
  • 14. Civil Engineering Drawing & Graphics  The material of the formwork should be cheap, easily available and should be suitable for reuse.  The formwork should be set accurately to the desired line and levels should have plane surface.  It should be as light as possible.  The material of the formwork should not warp or get distorted when exposed to the elements.  It should rest on firm base.
  • 15. Civil Engineering Drawing & Graphics Economy in Formwork:  The plan of the building should imply minimum number of variations in the size of rooms, floor area etc. so as to permit reuse of the formwork repeatedly.  Design should be perfect to use slender sections only in a most economical way.  Minimum sawing and cutting of wooden pieces should be made to enable reuse of the material a number of times. The quantity of surface finish depends on the quality of the formwork.
  • 16. Civil Engineering Drawing & Graphics Formwork can be made out of timber, plywood, steel, precast concrete or fiber glass used separately or in combination. Steel forms are used in situation where large numbers of re-use of the same forms are necessary.
  • 17. Civil Engineering Drawing & Graphics For small works, timber formwork proves useful. Fiber glass made of pre-cast concrete and aluminum are used in cast-in-situ construction such as slabs or members involving curved surfaces.
  • 18. Civil Engineering Drawing & Graphics Following are the materials which are used for formwork:  Plywood: This is by far the most common material used for the facing panel. It is easily cut to shape on site, and if handled and stored carefully, it can be used many times. Note the different thickness: A standard plywood thickness on site is 18mm. this is usually sufficient for most pours. However, if the formwork is curved, a thinner plywood is used to facilitate bending. Thicker plywood may be used when the weight of concrete causes a standard thickness plywood to bow out, distorting the concrete face.
  • 19. Civil Engineering Drawing & Graphics  Timber: This is the most common material used for bracing members to the form face. Like plywood, it can be easily cut to size on site. Formwork made from timber is called traditional formwork. The construction methods using timber formwork have been used on site for years, and all well understood by trained operators.
  • 20. Civil Engineering Drawing & Graphics Ply wood Timber
  • 21. Civil Engineering Drawing & Graphics Steel: Steel is also used in pre-fabricated formwork. Purpose made steel forms are fabricated when dimensional tolerances are critical, or when the forms are planned to be re-used. Steel forms become cost-efficient after about a dozen uses, although they can be used up to 100 pours if they are carefully cleaned and stored.
  • 23. Civil Engineering Drawing & Graphics Aluminum: Often used in pre-fabricated formwork, that is put together on site. Aluminum is strong and light, and consequently fewer supports and ties are required. The lighter sections will deflect more, but this can be avoided by simply following the manufacturers recommendations.
  • 24. Civil Engineering Drawing & Graphics Plastics: Glass reinforced plastics (GRP) and vacuum formed plastics are used when complicated concrete shapes are required (e.g. waffle floors). Although vacuum formed plastics will always need support, GRP can be fabricated with integral bearers making it self supporting. Like steel, plastic formwork can be re-used many times, as long as care is taken not to scour the surface whilst vibrating the concrete.
  • 25. Civil Engineering Drawing & Graphics Timber Formwork: Timber for formwork should satisfy the following requirement: It should be, 1. Well seasoned 2. Light in weight 3. Easily workable with nails without splitting 4. Free from loose knots Timber used for shuttering for exposed concrete work should have smooth and even surface on all faces which come in contact with concrete.
  • 26. Civil Engineering Drawing & Graphics Normal sizes of members for timber formwork: Sheeting for slabs, beam, column side and beam bottom 25 mm to 40mm thick Joints, ledges 50 x 70 mm to 50 x 150 mm Posts 75 x 100mm to 100 x 100 mm
  • 28. Civil Engineering Drawing & Graphics Plywood Formwork: Resin bonded plywood sheets are attached to timber frames to make up panels of required sizes. The cost of plywood formwork compares favorably with that of timber shuttering and it may even prove cheaper in certain cases in view of the following considerations:
  • 29. Civil Engineering Drawing & Graphics  It is possible to have smooth finish in which case on cost in surface finishing is there.  By use of large size panels it is possible to effect saving in the labor cost of fixing and dismantling.  Number of reuses are more as compared with timber shuttering. For estimation purpose, number of reuses can be taken as 20 to 25.
  • 30. Civil Engineering Drawing & Graphics Steel Formwork: This consist of panels fabricated out of thin steel plates stiffened along the edges by small steel angles. The panel units can be held together through the use of suitable clamps or bolts and nuts. The panels can be fabricated in large number in any desired modular shape or size.
  • 31. Civil Engineering Drawing & Graphics Steel forms are largely used in large projects or in situation where large number reuses of the shuttering is possible. This type of shuttering is considered most suitable for circular or curved structures.
  • 32. Civil Engineering Drawing & Graphics Steel forms compared with timber formwork:  Steel forms are stronger, durable and have longer life than timber formwork and their reuses are more in number.  Steel forms can be installed and dismantled with greater ease and speed.  The quality of exposed concrete surface by using steel forms is good and such surfaces need no further treatment.  Steel formwork does not absorb moisture from concrete.  Steel formwork does not shrink or warp.
  • 33. Civil Engineering Drawing & Graphics Construction of formwork: This normally involves the following operations: 1. Propping and centering 2. Shuttering 3. Provision of camber 4. Cleaning and surface treatment
  • 34. Civil Engineering Drawing & Graphics Order and method of removing formwork: The sequence of orders and method of removal of formwork are as follows:  Shuttering forming the vertical faces of walls, beams and column sides should be removed first as they bear no load but only retain the concrete.  Shuttering forming soffit of slabs should be removed next.  Shuttering forming soffit of beams, girders or other heavily loaded shuttering should be removed in the end.
  • 35. Civil Engineering Drawing & Graphics Rapid hardening cement, warm weather and light loading conditions allow early removal of formwork. The formwork should under no circumstances be allowed to be removed until all the concrete reaches strength of at least twice the stresses to which the concrete may be subjected at the time of removal of formwork. All formworks should be eased gradually and carefully in order to prevent the load being suddenly transferred to concrete.
  • 36. Civil Engineering Drawing & Graphics Details of timber formwork for RCC beam and slab floor Details at section shown in figure
  • 37. Civil Engineering Drawing & Graphics Elevation Details of timber formwork for circular RCC column
  • 38. Civil Engineering Drawing & Graphics 3D View Details of timber formwork for square or rectangular RCC column
  • 39. Civil Engineering Drawing & Graphics Sectional plan showing details of timber formwork for an octagonal column Details of formwork for stair
  • 41. Civil Engineering Drawing & Graphics Period of removal of formwork: Walls, columns and vertical sides of beams 1 to 2 days Slabs (props left under) 3 days Beam soffits (props left under) 7 days
  • 42. Civil Engineering Drawing & Graphics Removal of props to slabs (a) For slabs spanning up to 4.5 m 7 days (b) For slabs spanning over 4.5 m 14 days Removal of props to beams and arches (a) Spanning up to 6 m 14 days (b) spanning over 6 m 21 days
  • 43. Civil Engineering Drawing & Graphics PRE-CONCRETE CHECKS FOR FORMWORK: Before the concrete is poured into the formwork, it must be checked by someone who has been trained to inspect formwork. Depending on how big or complicated the pour is, the inspection may just take few minutes or it could take hours. Only when the formwork has been approved, may the pour take place.
  • 44. Civil Engineering Drawing & Graphics Formwork pressures are function of height (including the height from which concrete is dropped into the forms) and are affected by concrete workability, rate of stiffening and rate of placing. One task of the temporary works coordinator is to consider such factors as ambient temperatures and concrete composition, when calculating maximum permissible rate of concrete placing.
  • 45. Civil Engineering Drawing & Graphics Exceeding this limit may lead to unacceptable formwork deflections, loss of grout / concrete at joints, or even collapse. The cost of remedial work due to formwork deflection will usually exceed the original cost of doing the job properly.
  • 47. Civil Engineering Drawing & Graphics Below are the checks that should be verified before pouring begins:  Is the formwork erected in accordance with the approved drawings?  Is the formwork restrained against movement in all directions?  Is it correctly aligned and leveled?  Are all the props plum, and at the right spacing?  Are bolts and wedges secure against any possible loosening?  Has the correct number of ties been used? Are they in the right places and properly tightened?
  • 48. Civil Engineering Drawing & Graphics  Are all inserts and cast-in fixings in the right position and secure?  Have all stop ends been properly secured?  Have all the joints been sealed to stop grout loss (especially where the formwork is against the kicker)?  Can the formwork be struck without damaging the concrete?
  • 49. Civil Engineering Drawing & Graphics  Are the forms clean and free from rubbish such as tie wire cuttings, and odd bits of timber or metal?  Has the release agents been applied, and is it the correct one?  Are all projecting bars straight and correctly positioned?  Is there proper access for placing the concrete and compacting?  Have all the toe-boards and guard rails been provided?
  • 50. Civil Engineering Drawing & Graphics RELEASE AGENTS FOR FORMWORK: Formwork needs to be treated with a release agent so that it can be removed easily after the concrete has set. Failure to use a release agent can result in the formwork sticking to the concrete, which may lead to damage of the concrete surface.
  • 51. Civil Engineering Drawing & Graphics A single application of release agent is all that is required when forms are then used. Care must be taken to cover all the surface that will come in contact with the surface of concrete. However, if there is an excess of release agent, it may cause staining or retardation of the concrete.
  • 52. Civil Engineering Drawing & Graphics There are different release agents depending on what material is used for the formwork. The three (03) most common release agents for formwork are:  Neat oils with surfactants: used mainly on steel surfaces, but also suitable for timber and plywood.
  • 53. Civil Engineering Drawing & Graphics  Mould cream emulsions: good general purpose release agents for use on timber and plywood.  Chemical release agents: recommended for high quality work, applied by spray to all types of form face.
  • 54. Civil Engineering Drawing & Graphics ASSIGNMENT (A REPORT) MiNi-Project In M.S Word, do make a brief report of at least 20 pages having in it “Pictures” from original sites covering 18 chapters of the referred text book (Preferably 01 page for each chapter). Try to make report understandable by providing sequential pictures of the phenomenon and a minimum of 4 to 6 lines in each page and relevant topic.