CHANGE MANAGEMENT: IMPLEMENTATION AND
BENEFITS OF THE CHANGE CONTROL IN THE
INFORMATION TECHNOLOGY ENVIRONMENT
Paulo Roberto Martins de Andrade1
, Adriano B. Albuquerque2
, WeskleiDourado
Teófilo3
, Fátima Aguiar da Silva3
1
Graduate Studies in Computer Science, University of Regina, Regina, SK, Canada
2
Universidade de Fortaleza, Fortaleza, CE, Brazil
3
FaculdadeEstácio FIC, Fortaleza, CE, Brazil
ABSTRACT
In the competitive environment, companies have given increasing importance to the IT sector and the
resources it delivers as strategic. As a result, IT becomes a living being within the company. This sector is
being subject to continuous changes in this scenario. These changes can occur within the own IT sector or
whether IT to other sectors of the company. For both scenarios, it is important to have a good change
control to avoid unnecessary trouble and expense. This paper aims to show through a case study, the
benefits and results obtained with the implementation of a process of managing and controlling changes in
the information technology environment of a large government company in Brazil.
KEYWORDS
Change control; Information technology, PMBOK, Software engineering.
1. INTRODUCTION
We live in a time when technology advances faster and faster, and with these advances and
changes in technology, corporations have to keep pace to be competitive in the increasingly
computerized and demanding market. Exactly at this point enter the changes made in systems and
network infrastructure.
In the past, the common knowledge said that the IT department of the organization need to be
aligned to the business, but today the IT is already part of the business. Both, the IT and the
Business’ Department, are two areas that should be "integrated". With that in mind, it is necessary
that the IT department is prepared to support and ensure timely, delivery of IT services required
for the company's business and can also add value to the corporation [17].
With some of its foundational texts now decades old, IT change management is one of the most
studied and utilized elements of the systems and infrastructure management discipline. With so
much academic thinking and so many years of practical application behind it, one would think
that the effective management of change would now be commonplace in IT organizations and the
companies they serve. Surprisingly, the opposite it true. Author and IT Service Management
expert, Harris Kern, reports that in a recent survey of 40 corporate IT infrastructure managers a
surprising 60% admitted that their processes to handle change are not effective in communicating
and coordinating changes occurring within their production environment. Among the key findings
of the study: Not all changes are logged 95%; Changes not thoroughly tested 90%; Lack of
International Journal of Advanced Information Technology (IJAIT) Vol. 6, No. 1, February 2016
24
process enforcement; Poor change communication and dissemination; Lack of centralized process
ownership 60%; Lack of change approval policy 50%; Frequent change notification after the fact
40% [9].
More than an overall indictment of poor process implementation, these findings illustrate the
extent to which organizations rely on a change control process to handle IT-related changes.
Changes can be welcomed and usually they happen to have benefits. What is needed is to manage
them the right way to not to be surprised negatively on the results. For every change has an
expectation that must be the closest possible to the final result of the change.
In order to have a management and control appropriate changes, the main aim of this paper is to
define a process to carry out the treatment of changes in the information technology environment,
deploying and generating benefits, because it is an extremely important environment for
companies today. We must select tools to be used, define the stakeholders, ways of
communication and approval roles. Thus we can define a process of change, starting from the
request, its type, its approval, its execution and the lessons learned. With this formalized process,
we can have the benefits expected as a higher rate of success in the changes, greater traceability,
risk mitigation, among several other potential benefits with the use of the process.
This paper delivery information about the sources of change and one some concepts of changes in
the Project Management. Next, the paper shows us the previous scenario overview. After, we
have a case study (with the problems founded, the benefits expected and the difficult in the
implantation. In the next we have the results of the case study. At last, the paper gives us the
conclusion.
2. MORE ABOUT CHANGES
2.1. Sources of Changes
In our lives or in our projects we should always be prepared to deal with and make changes
because they always occur. In the development of software applications, we recommend the use
of good practices related to Software Engineering. For IT Governance there are several
frameworks of best practice, one example would be the COBIT with BAI06 Manage Change
process [10].
The COBIT is an IT governance framework maintained by ISACA (ISACA). It is a reference
model and is not a ready solution. In other words, it needs to adapt it to the business to meet the
needs, and align the information technology sector to the business and can be used only a few
controls that seek to improve the processes that comprise the IT governance of each company
[10].
There are several causes that give rise to the changes, we can highlight the compliance with laws
and regulations such as PCI-DSS (Payment Card Industry - Data Security Standard) [11], SOX
(Sarbanes Oxley Act) [16], needs preventive measures in the IT environment, external events of
which the IT has to comply in determined period, need for improvements in systems and
infrastructure, senior management requests (strategic changes), but the highest incidence of
changes in the IT environment noted in the case study in this article are those that originate from
problems. In this case, the change is the answer to the problem. Another important part of the
change comes from direct demands from any interested party.
International Journal of Advanced Information Technology (IJA
2.2. Concepts in the view of Project Management
The Project Management Institute (PMI) is a non
management professionals around the world integrat
every country through research and education. Its central office is located in Pennsylvania
(United States) [4].
The PMBOK identifies a subset of knowledge in project management, which is generally
recognized as good practice, and as a result, used by the Project Management Institute (PMI),
which defines some concepts down on change management [12]:
“A change request is a formal proposal to modify any document delivery, or baseline”. (PMBOK,
2013, p. 85);
“Perform Integrated Change Control is the process of reviewing all change requests, approving
changes and managing changes being made deliveries, organizational process assets, project
documents and project management plan, and report the disposition of thereof”
p. 94).
The PMBOK describes a process for the integrated change control with a focus on project
management, in which he mentions the main inputs, tools and techniques, and outputs of the
process as shown in Figure 1.
Figure 1. Perform
This process can be adaptable to each company, environment or need, since the focus of the
PMBOK guide is for project management environment.
There is also another project management method cal
through the dissemination of good practice in project management, in which speech and deals
with the importance of using change management [1].
PRINCE2 is a non owner who is emerging worldwide as one of the most accepte
project management and is much used mainly in European countries. It is truly flexible and can
be applied to any project or company, regardless of scale, type, organization, geography or
culture. Addresses project management with four integra
processes and project environment. One of its themes is exactly "change" and has the purpose to
identify, assess and monitor any changes [2].
The fact that the PRINCE2 have a specific area for change management help in th
project, and the changes made. It is evident that the changes will always occur and that
International Journal of Advanced Information Technology (IJAIT) Vol. 6, No. 1, February 201
Concepts in the view of Project Management
The Project Management Institute (PMI) is a non-profit organization that combines project
management professionals around the world integrating more than 2.9 million members in nearly
every country through research and education. Its central office is located in Pennsylvania
The PMBOK identifies a subset of knowledge in project management, which is generally
good practice, and as a result, used by the Project Management Institute (PMI),
which defines some concepts down on change management [12]:
“A change request is a formal proposal to modify any document delivery, or baseline”. (PMBOK,
rm Integrated Change Control is the process of reviewing all change requests, approving
changes and managing changes being made deliveries, organizational process assets, project
documents and project management plan, and report the disposition of thereof”
The PMBOK describes a process for the integrated change control with a focus on project
management, in which he mentions the main inputs, tools and techniques, and outputs of the
process as shown in Figure 1.
Figure 1. Perform Integrated Change Control Process
(source: PMBOK 5ed. P. 94)
This process can be adaptable to each company, environment or need, since the focus of the
PMBOK guide is for project management environment.
There is also another project management method called PRINCE2 is recognized worldwide
through the dissemination of good practice in project management, in which speech and deals
with the importance of using change management [1].
PRINCE2 is a non owner who is emerging worldwide as one of the most accepte
project management and is much used mainly in European countries. It is truly flexible and can
be applied to any project or company, regardless of scale, type, organization, geography or
culture. Addresses project management with four integrated elements: principles, themes,
processes and project environment. One of its themes is exactly "change" and has the purpose to
identify, assess and monitor any changes [2].
The fact that the PRINCE2 have a specific area for change management help in th
project, and the changes made. It is evident that the changes will always occur and that
IT) Vol. 6, No. 1, February 2016
25
profit organization that combines project
ing more than 2.9 million members in nearly
every country through research and education. Its central office is located in Pennsylvania
The PMBOK identifies a subset of knowledge in project management, which is generally
good practice, and as a result, used by the Project Management Institute (PMI),
“A change request is a formal proposal to modify any document delivery, or baseline”. (PMBOK,
rm Integrated Change Control is the process of reviewing all change requests, approving
changes and managing changes being made deliveries, organizational process assets, project
documents and project management plan, and report the disposition of thereof”. (PMBOK, 2013,
The PMBOK describes a process for the integrated change control with a focus on project
management, in which he mentions the main inputs, tools and techniques, and outputs of the
This process can be adaptable to each company, environment or need, since the focus of the
led PRINCE2 is recognized worldwide
through the dissemination of good practice in project management, in which speech and deals
PRINCE2 is a non owner who is emerging worldwide as one of the most accepted methods for
project management and is much used mainly in European countries. It is truly flexible and can
be applied to any project or company, regardless of scale, type, organization, geography or
ted elements: principles, themes,
processes and project environment. One of its themes is exactly "change" and has the purpose to
The fact that the PRINCE2 have a specific area for change management help in the success of the
project, and the changes made. It is evident that the changes will always occur and that
International Journal of Advanced Information Technology (IJAIT) Vol. 6, No. 1, February 2016
26
communication of them is very important for effective implementation, because in this way
reduces the probability of failure, time and cost, and thus fall into important and fundamental
point that is customer satisfaction and success the purpose of the change [1].
The PMI and PRINCE2 (two of the biggest disseminators organs of good practice in project
management, world-renowned) address change management emphatically as an important point
for the success of projects, stating on multiple pages of your guides, good practices that can be
used [13].
The reason to talk specifically about that topic changes in project management is to be the area
where most uses the concepts, and where it is more widespread and used the change management
process. This process can be easily adapted for information technology, using these best practices
in order to achieve better results in the implementation and use of change management [3].
2.3 The importance of the change management
Organizations change to win. And this gain is not always financial. Sometimes the aim is to just
improve interpersonal relationship, hasten the progress of internal processes or stimulate the
involvement of employees in a new project. The possibilities are many and invests up time and
money to achieve the goals. However, in many organizational changes the desired result is far
away. And that does not happen by accident.
When a company is created, its founders have beliefs, values and assumptions related to the way
of how your business should work. If the company prospers, it is natural to hire people who share
the same 'feelings'. These beliefs, values and assumptions are represented by the norms of
behaviour and attitudes accepted by the organization. They are taught as "the correct way it
should be done things around here."
It can not be said, in an isolated manner, if a culture is good or bad. However, it is known that a
culture is good if it is consistent with the company's strategy. For example, companies that
depend on the creativity - such as those of advertisement, for example - may not have hierarchies
and rigid processes; moreover, it does no longer true in chemical and pharmaceutical companies.
Anyway, for us it is extremely important to be always attentive to the evolution of companies, so
we realize that the same culture that led to success may no longer be useful to prosper in the
future. And it's hard for some managers see themselves the need for change.
Many managers fear that their subordinates resist the changes. Therefore, they do not play the
role expected of them in any transformation process. Culture is created by the leaders and
therefore, if we need to change, this change must begin with the leaders. It is they who must
create a sense of need and urgency, to establish the vision and communicate it clearly and
honestly.
A change may require changes in existing structures, new skills needs, work load shifting, etc. All
of these impacts should be managed effectively so that the transformation can occur. The
transition between the current state and the future state should be monitored. Support new
processes, contingency planning and treatment of risks, plans and support change issues must not
be neglected. Training is an extremely important aspect of the process, but often is mishandled
during a transformation. For this reason, it is responsible for the failure of much of the
organizational changes.
As can be seen, the success of organizational change processes is not so simple, requires attention
and support professionals. The fact is that companies with proper professional support are
International Journal of Advanced Information Technology (IJAIT) Vol. 6, No. 1, February 2016
27
evolving and achieved the desired results and this finding has a valuable significance for
businesses, especially for those who are facing the challenge of taking its first steps into the
future.
3. PREVIOUS SCENARIO OVERVIEW
3.1 Problems and benefits expected
The scenario in which we performed the case study of this article it is a large government
company, where we diagnose various problems related to changes in the information technology
environment, such as systems, servers and network infrastructure. Routine problems were:
• Unplanned outages of services. The unavailability of services mostly occurred during
business hours, impacting users and customers of the company, thus affecting the
credibility of the information technology sector.
• Difficulty in tracing changes in the environment for troubleshooting. As the changes were
made without any control we did not know what had changed in the environment, even a
short time ago, making diagnosis difficult to solve problems, often resulting in increased
downtime.
• Risks unmitigated in carrying out the changes. As the risks were not analyzed and treated
in the best way, the impact of changes often were not as expected.
• Rework. A large percentage of the changes generated rework.
• Low success rate in the changes.
• Financial losses not measured, especially on the availability of systems and services.
These are some of the many factors that contributed in the interest of implementing a change
control process in the company. According to the market more and more competitive, and
especially following the controls Framework COBIT and PMBOK, these good practices also
would make other protruding factors to consider the real need to implement a process of
integrated control of changes in management of enterprise information technology, seeking the
benefits when using this process [6].
The main expected benefits that motivated the process of implementation were:
• The better alignment of IT services with business. The changes will be filtered and
prioritized as needed for business.
• Increased visibility into the changes by exercising greater control over the execution of
change, reducing the negative impact of change.
• The risk analysis to prevent the service becomes unavailable due to failures.
• Better assessment of the cost-benefit ratio of the change before it is implemented.
• Reduction of cost, time and rework.
• More stable services and increase of user productivity.
These are some of the expected benefits of the process of implementation. The problems and
benefits were analysed along with IT teams, managers and key stakeholders, thus coming to the
conclusion that it would be quite feasible the implementation of an integrated control changes in
the information technology sector.
International Journal of Advanced Information Technology (IJAIT) Vol. 6, No. 1, February 2016
28
3.2 Difficult of the Change Management Process implementation
During the implementation process were expected difficulties due to the sector's culture and its
employees, being a paradigm shift because there were resistance from some people, especially for
thinking that with this process, increase bureaucracy and this way, possible problems in the
information technology sector, where more and more is expected quick answers to problems and
incidents could take even longer to resolve.
Andrade defines organizational culture as a set of beliefs, traditions, values, written and unwritten
rules that can boost, speed, weaken, delay, facilitate, commit, hinder or prevent changes and
performance of organizations [3].
According Chiavenato, the change is the main characteristic of contemporary times, being an
essential aspect of creativity and innovation in organizations today [7].
Barbara mentions that: “Changes happen when people are prepared for the same, however, they
find it difficult to break paradigms, changing behaviour and changing their attitudes, because
changes imply something new and they are still attached to the previous archetype, causing
uncertainty and being affected psychologically, causing fear and consequently generating
resistance.” [5].
The main challenge of the deployment and use of change control process is to provide an
organizational environment propitious to innovation that adds value to the company and to the
information technology sector. In them will be developed and implemented projects and activities
that generate changes, working mostly in dimensions’ people and results.
The process creation, dissemination, definition of approval levels and roles were performed as
expected. The greatest difficulty really was a culture change so that it could follow the process,
especially at the beginning when sometimes tried to put the blame problems unrelated to the
process in the process itself, being something new [15].
4. CASE STUDY
First of all, we need a formal process control changes that would fit as close as possible to the
culture and reality of the IT sector and the company. We defined with all stakeholders in the
process that any changes in the information technology environment should be requested, and
formally managed through the integrated control of process changes.
Through the definition that any changes would use the process, we saw the need to categorize the
changes because there were cases where differential treatment would be needed for certain
changes, aiming to make the process as effective as possible. To this categorization were defined
three types of changes:
Standard Change (Routine): These are pre-approved changes. This means that new requests are
automatically approved and occur in periods intervals previously defined.
Planned changes: Are the changes that run the normal flow within the process.
Emergency changes: Are the changes that may occur outside the standard interval, only
depending on the release of the immediate supervisor for immediate execution, are generally
reactive changes to correct problems that are impacting or may impact the business.
International Journal of Advanced Information Technology (IJA
Any changes in the information technology environment must go through the process, being
necessary to open a change request, which was made available on the company's Intranet a form
to fill the requests. The Figure 2 show this form and in the Figure 3 is possible to see t
of each request in the system. Both figures are in pt
Figure
International Journal of Advanced Information Technology (IJAIT) Vol. 6, No. 1, February 201
e information technology environment must go through the process, being
necessary to open a change request, which was made available on the company's Intranet a form
The Figure 2 show this form and in the Figure 3 is possible to see t
of each request in the system. Both figures are in pt-BR (Portuguese – Brazil).
Figure 2. Form of change request
Figure 3. Tracking screen for the Change Requests
IT) Vol. 6, No. 1, February 2016
29
e information technology environment must go through the process, being
necessary to open a change request, which was made available on the company's Intranet a form
The Figure 2 show this form and in the Figure 3 is possible to see the tracking
International Journal of Advanced Information Technology (IJAIT) Vol. 6, No. 1, February 2016
30
On the form, you are asked to enter the following information:
• What is the purpose of the change?
• Start date and completion of the change.
• What will assets be affected by the change?
• What will items be impacted by the assets affected by the change?
• What is the complexity of change?
• Further details on the change.
• Which the implementation experience of change?
• Tests performed to carry out the change.
• What is the return plan for change?
The roles were defined for analysis and approval of the changes as described below:
• Requester: Any employee of IT sector that want to make the change, and the requester
also mostly responsible for the execution and implementation of the same, then the
execution of the change should be completed by the requester or designed responsible.
• Governance and IT Risk Team: Responsible for evaluate the request, categorize the
change, send the flow of approvals, conduct communication to stakeholders, update the
documentation and record the closure of the change.
• Change Team: Responsible for assessing the feasibility of change, checking the necessary
approval levels for the request.
• Immediate supervisor: They are the persons responsible for the approval of the changes,
usually managers and members of business teams impacted the change.
After requesting submit the form changes, the application will be reviewed. If necessary, will be
asked to charge to carry out possible corrections in your request. Then the change will be
categorized and will cover the flow according to its categorization also being examined its
feasibility, and responsible for approval. After the change is formally approved for execution, the
team communicates to all parties affected by the change. This communication become more
transparent to all the actions taken by TI, increasing their credibility with employees. Shortly after
the execution of change, should be completed a post-implementation form with the questions
shown below:
• Was the purpose of the change reached?
• Did the change occur within the expected interval?
• Was there any incident arising from the change?
• Was it necessary to trigger the return plan (rollback)?
• Will be necessary upgrade documentation?
• Other comments.
After the post-implementation form is submitted, if necessary, documentation will be update, and
thus the closure of the change will be recorded.
5. RESULTS
To be able to measure the results of the integrated control process changes, create a performance
indicator (KPI) to monitor and improve the process, using practices of continuous improvement.
The indicator was set to be four times a year, consisting only the final result of the change, which
may be success or failure. The changes considered successful, briefly, are the ones that occurred
International Journal of Advanced Information Technology (IJA
within the expected time period and had reached their ultimate goal, otherwise the change is
classified as failed.
After the first six months of 2015, we have recorded 200 requests for changes through the form
found on the intranet. They all went through in the process designed and previously mentioned.
Here entered changes relating to update systems, update
systems (to make sure that deployment could affect some other IT assets), emergency changes,
among other types. With AJUSA the process, only 17 changes obtained a failure during its
implementation, it is necessary to
Figure 2. Collected result from the first six months of 2015
With the formalization and implementation, the process has matured gradually until you can be
part of the IT team culture. It was observed the increase of
monitoring reports after the process of implementation. The changes have achieved their goals
almost entirely. The risks are mitigated to be obtained minimal impact to the environment in the
changes.
A major benefit noted by all the company's employees was communication. Earlier the systems
and servers were unavailable without prior knowledge of users, making it stressful
communication with the IT sector. With the process implementation, the system’s stops are
scheduled and even emergencies, are communicated to all interested parties, which made up the
credibility of the IT sector in the company. With the creation of the KPI to monitor the change
control process there was come in quite satisfactory results, as we saw in th
6. CONCLUSIONS
As mentioned throughout this paper, the use of change management is becoming increasingly
essential for the Information Technology sector, and for businesses, helping and supporting the
achievement of strategic planning, target
that we live in today, and growth and alignment of information technology with business, adding
more value to the enterprise processes such as change management, can be a differentiator so that
you can excel in current market scenario. The implementation of the change management process
is not complicated, but you should not expect its implementation from day to night, we need to
adapt the process to the culture and maturity of the company, requiring ded
and effort everyone involved, so that we can break resistance and paradigms related to this
change with the use of the process.
International Journal of Advanced Information Technology (IJAIT) Vol. 6, No. 1, February 201
within the expected time period and had reached their ultimate goal, otherwise the change is
the first six months of 2015, we have recorded 200 requests for changes through the form
found on the intranet. They all went through in the process designed and previously mentioned.
Here entered changes relating to update systems, update hardware, implem
systems (to make sure that deployment could affect some other IT assets), emergency changes,
among other types. With AJUSA the process, only 17 changes obtained a failure during its
implementation, it is necessary to enable the return plan. Figure 4 illustrates this data.
Figure 2. Collected result from the first six months of 2015
With the formalization and implementation, the process has matured gradually until you can be
part of the IT team culture. It was observed the increase of environmental availability through
monitoring reports after the process of implementation. The changes have achieved their goals
almost entirely. The risks are mitigated to be obtained minimal impact to the environment in the
d by all the company's employees was communication. Earlier the systems
and servers were unavailable without prior knowledge of users, making it stressful
communication with the IT sector. With the process implementation, the system’s stops are
nd even emergencies, are communicated to all interested parties, which made up the
credibility of the IT sector in the company. With the creation of the KPI to monitor the change
control process there was come in quite satisfactory results, as we saw in the figure 2.
As mentioned throughout this paper, the use of change management is becoming increasingly
essential for the Information Technology sector, and for businesses, helping and supporting the
achievement of strategic planning, targets, and indicators. With the highly competitive market
that we live in today, and growth and alignment of information technology with business, adding
more value to the enterprise processes such as change management, can be a differentiator so that
excel in current market scenario. The implementation of the change management process
is not complicated, but you should not expect its implementation from day to night, we need to
adapt the process to the culture and maturity of the company, requiring dedication, commitment
and effort everyone involved, so that we can break resistance and paradigms related to this
change with the use of the process.
IT) Vol. 6, No. 1, February 2016
31
within the expected time period and had reached their ultimate goal, otherwise the change is
the first six months of 2015, we have recorded 200 requests for changes through the form
found on the intranet. They all went through in the process designed and previously mentioned.
, implementation of new
systems (to make sure that deployment could affect some other IT assets), emergency changes,
among other types. With AJUSA the process, only 17 changes obtained a failure during its
illustrates this data.
With the formalization and implementation, the process has matured gradually until you can be
environmental availability through
monitoring reports after the process of implementation. The changes have achieved their goals
almost entirely. The risks are mitigated to be obtained minimal impact to the environment in the
d by all the company's employees was communication. Earlier the systems
and servers were unavailable without prior knowledge of users, making it stressful
communication with the IT sector. With the process implementation, the system’s stops are
nd even emergencies, are communicated to all interested parties, which made up the
credibility of the IT sector in the company. With the creation of the KPI to monitor the change
e figure 2.
As mentioned throughout this paper, the use of change management is becoming increasingly
essential for the Information Technology sector, and for businesses, helping and supporting the
s, and indicators. With the highly competitive market
that we live in today, and growth and alignment of information technology with business, adding
more value to the enterprise processes such as change management, can be a differentiator so that
excel in current market scenario. The implementation of the change management process
is not complicated, but you should not expect its implementation from day to night, we need to
ication, commitment
and effort everyone involved, so that we can break resistance and paradigms related to this
International Journal of Advanced Information Technology (IJAIT) Vol. 6, No. 1, February 2016
32
It is observed although the implementation of a change management process brings many benefits
as cited throughout this article. It is a process that does not require much financial investment,
making it highly feasible and recommended for use. For the process, the main barrier to
successful were the people. With time and the use of the process is perceived the change by the
involved culture, making it easier deployment and standardization of other processes in order to
use of best market practices in order to add the most value to the business and making a
difference in today's competitive market.
ACKNOWLEDGEMENTS
The CNPq (Conselho Nacional de Desenvolvimento Científico e Tecnológico - "National
Counsel of Technological and Scientific Development") and the Ceará water and sewage
company support this work.
REFERENCES
[1] ANDRADE, PAULO R. M.; ALBUQUERQUE, A. B.; FROTA, O. F. ; SILVA FILHO, J. F. . PM5:
One approach to the management of IT projects applied in the Brazilian public sector, 2015, Las
Vegas, Nevada, USA. Proceedings of 13th International Conference on Software Engineering
Research and Practice - SERP. San Diego, California, USA: Waset.org, 2015. v. 1.
[2] ANDRADE, P. R. M., ALBUQUERQUE, A. B.. “Escritório de projetos: Características, vantagens e
o planejamento de sua implantação no setor público” RBGP. Revista Brasileira de Gerenciamento de
Projetos, 2014, p. 21-26.
[3] ANDRADE, PAULO R. M.; ALBUQUERQUE, A. B.; ARAUJO, R. G.; CRONEMBERGER
FILHO, J.; PEREIRA, T. R.; MENDONCA, N. C.. Improving business by migrating applications to
the cloud using cloudstep, 2015, Gwangju, Korea. Proceedings for the 29th International Conference
on Advanced Information Networking and Applications Workshops, 2015. p. 77-82.
[4] ATKINSON, R. “Project management: cost, time and quality, two best guesses and a phenomenon,
it’s time to accept other success criteria.” International Journal of Project Management, 1999: 337-
342.
[5] BARBARA, Michele. Gestão de mudança: superando dificuldades na implantação dos sistemas de
informação nas organizações, 2013.
[6] CAVAREC, Y. “Revisiting de Definition of Project Success.” PMI Global Congress Proceedings.
Vancouver, Canada: PMI, 2012.
[7] CHIAVENATO, I. Gestão de Pessoas: o novo papel dos recursos humanos nas organizações. Rio de
Janeiro: Elsevier, 1999.
[8] HALL, M., R. HOLT, e D. PURCHASE. “Project sponsor under new public management: lessons
from the frontline.” International Journal of Project Management, 2003: 495-502.
[9] Harris Kern, http://www.harriskern.com/ (visited on January 20, 2016).
[10] ISACA, http://www.isaca.org/cobit (visited on January 20, 2016).
[11] PCI Compliance Guide, https://www.pcicomplianceguide.org/ (visited on January 20, 2016).
[12] PMI; “A Guide to the Project Management Body of Knowledge: PMBOK(R) Guide.” 5ª. San
Francisco, CA: Syba - PMI Publishing Division, 2013.
[13] REGO, M. L, e H. A. R. IRIGARAY. “Gerenciamento de Projetos: Existe Produção Científica
Brasileira?” Proceedings of XXXV Encontro ANPAD. Rio de Janeiro, RJ: ANPAD, 2011.
[14] SANTOS RODRIGUEZ, A. Evolução do Modelo de Gestão. Proceedings of II CONGRESSO
NACIONAL DE EXCELÊNCIA EM GESTÃO, 4, 2008, Rio de Janeiro
[15] SÖDERLUND, J. “Building theories of project management: past research, questions for the future.”
International Journal of Project Management, 2004: 183-191.
[16] SOX LAW, http://www.soxlaw.com/compliance.htm (visited on January 20, 2016).
[17] SRIVANNABOON, S., e D. Z. MILOSEVIC. “A two-way influence between business strategy and
project management.” International Journal of Project Management, 2006: 493-505.
[18] WISE, L. R. “Public management reform: competing drivers of change.” Public Administration
Review 62, nº 5 (2002)
International Journal of Advanced Information Technology (IJA
AUTHORS
Paulo Roberto Martins deAndrade
andAssociated Professor in the
Management. He has 11 years of experience in IT, with some certifications, like PMP and
Cobit. He has a Master in Applied Informatics
IT Management.
Adriano Bessa Albuquerque has Doctorate in
a Master in Applied. He has experience in computer science with
engineering. Actually he is a professor in the University of Fortaleza and he also
implementer and official evaluator of software maturity models: CMMI and MPS.BR.
WeskleiDouradoTeófilohas a degree in Computer Networks, MBA in IT Governance
and MBA in Project Management.
PMP, COBIT and CompTIA Security +.
of Information Technology, with an emphasis on IT Governance, Project Management
and Information Security.
Fátima Aguiar da Silvahas a degree in
Management. She has certifications likeCAPM, Cobit and
over 6 years in the field of Process Management
Project Management.
International Journal of Advanced Information Technology (IJAIT) Vol. 6, No. 1, February 201
Paulo Roberto Martins deAndrade is a PhD Student in the University of Regina
Professor in the “Estácio FIC”. Actually, his focus is in Project
Management. He has 11 years of experience in IT, with some certifications, like PMP and
Applied Informatics, MBA in Project Management and MBA in
has Doctorate in Systems Engineering and Computing
He has experience in computer science with emphases in softwa
engineering. Actually he is a professor in the University of Fortaleza and he also Acts as
implementer and official evaluator of software maturity models: CMMI and MPS.BR.
has a degree in Computer Networks, MBA in IT Governance
and MBA in Project Management. He has more than 15 certifications, among which are,
and CompTIA Security +. He has been working for over 8 years in the field
of Information Technology, with an emphasis on IT Governance, Project Management
has a degree in Business Administration and MBA in Project
certifications likeCAPM, Cobit and ITIL.Shehas been working for
Process Management, with an emphasis on IT Governance and
IT) Vol. 6, No. 1, February 2016
33
ent in the University of Regina
. Actually, his focus is in Project
Management. He has 11 years of experience in IT, with some certifications, like PMP and
, MBA in Project Management and MBA in
and
in software
Acts as
has a degree in Computer Networks, MBA in IT Governance
ications, among which are,
for over 8 years in the field
of Information Technology, with an emphasis on IT Governance, Project Management
MBA in Project
working for
vernance and

More Related Content

What's hot

Understanding the use of balanced scorecard in the context of state owned ent...
Understanding the use of balanced scorecard in the context of state owned ent...Understanding the use of balanced scorecard in the context of state owned ent...
Understanding the use of balanced scorecard in the context of state owned ent...Alexander Decker
 
Toward Customer Satisfaction SEC ERP Implementation Project
Toward Customer Satisfaction SEC ERP Implementation ProjectToward Customer Satisfaction SEC ERP Implementation Project
Toward Customer Satisfaction SEC ERP Implementation ProjectBaker Khader Abdallah, PMP
 
EFFECTIVE IT GOVERNANCE presentation
EFFECTIVE IT GOVERNANCE presentationEFFECTIVE IT GOVERNANCE presentation
EFFECTIVE IT GOVERNANCE presentationS L
 
The Three Essential Process Layers - New York Business Process Professionals ...
The Three Essential Process Layers - New York Business Process Professionals ...The Three Essential Process Layers - New York Business Process Professionals ...
The Three Essential Process Layers - New York Business Process Professionals ...Samuel Chin, PMP, CSM
 
Business process monitoring system in supporting information technology gover...
Business process monitoring system in supporting information technology gover...Business process monitoring system in supporting information technology gover...
Business process monitoring system in supporting information technology gover...journalBEEI
 
IT Governance Framework
IT Governance FrameworkIT Governance Framework
IT Governance FrameworkSherri Booher
 
An Investigation of Critical Failure Factors In Information Technology Projects
An Investigation of Critical Failure Factors In Information Technology ProjectsAn Investigation of Critical Failure Factors In Information Technology Projects
An Investigation of Critical Failure Factors In Information Technology ProjectsIOSR Journals
 
Digital Transformation And Solution Architecture
Digital Transformation And Solution ArchitectureDigital Transformation And Solution Architecture
Digital Transformation And Solution ArchitectureAlan McSweeney
 
IT Governance Vs IT Management Presentation V0.1
IT Governance Vs IT Management   Presentation V0.1IT Governance Vs IT Management   Presentation V0.1
IT Governance Vs IT Management Presentation V0.1Richard Willis
 
Project management work
Project management workProject management work
Project management workRichardGorzki1
 
The importance of IT Change Management to the DR and BCP process
The importance of IT Change Management to the DR and BCP processThe importance of IT Change Management to the DR and BCP process
The importance of IT Change Management to the DR and BCP processPaul Monk (CBCI)
 
Erp research agenda(imds)
Erp research agenda(imds)Erp research agenda(imds)
Erp research agenda(imds)012roger
 
It governance 13 may20102
It governance 13 may20102It governance 13 may20102
It governance 13 may20102James Sutter
 
WP1 - Planning and Budgeting Systems
WP1 - Planning and Budgeting SystemsWP1 - Planning and Budgeting Systems
WP1 - Planning and Budgeting SystemsFabien Lennertz
 
Information systems strategy formulation
Information systems strategy formulationInformation systems strategy formulation
Information systems strategy formulationAssignment Studio
 

What's hot (20)

Understanding the use of balanced scorecard in the context of state owned ent...
Understanding the use of balanced scorecard in the context of state owned ent...Understanding the use of balanced scorecard in the context of state owned ent...
Understanding the use of balanced scorecard in the context of state owned ent...
 
Lecture # 08 (developing business it solution)
Lecture # 08 (developing business it solution)Lecture # 08 (developing business it solution)
Lecture # 08 (developing business it solution)
 
Toward Customer Satisfaction SEC ERP Implementation Project
Toward Customer Satisfaction SEC ERP Implementation ProjectToward Customer Satisfaction SEC ERP Implementation Project
Toward Customer Satisfaction SEC ERP Implementation Project
 
EFFECTIVE IT GOVERNANCE presentation
EFFECTIVE IT GOVERNANCE presentationEFFECTIVE IT GOVERNANCE presentation
EFFECTIVE IT GOVERNANCE presentation
 
The Three Essential Process Layers - New York Business Process Professionals ...
The Three Essential Process Layers - New York Business Process Professionals ...The Three Essential Process Layers - New York Business Process Professionals ...
The Three Essential Process Layers - New York Business Process Professionals ...
 
Baki2005
Baki2005Baki2005
Baki2005
 
Business process monitoring system in supporting information technology gover...
Business process monitoring system in supporting information technology gover...Business process monitoring system in supporting information technology gover...
Business process monitoring system in supporting information technology gover...
 
IT Governance Framework
IT Governance FrameworkIT Governance Framework
IT Governance Framework
 
An Investigation of Critical Failure Factors In Information Technology Projects
An Investigation of Critical Failure Factors In Information Technology ProjectsAn Investigation of Critical Failure Factors In Information Technology Projects
An Investigation of Critical Failure Factors In Information Technology Projects
 
Digital Transformation And Solution Architecture
Digital Transformation And Solution ArchitectureDigital Transformation And Solution Architecture
Digital Transformation And Solution Architecture
 
Tomas bsc eng
Tomas bsc engTomas bsc eng
Tomas bsc eng
 
IT Governance Vs IT Management Presentation V0.1
IT Governance Vs IT Management   Presentation V0.1IT Governance Vs IT Management   Presentation V0.1
IT Governance Vs IT Management Presentation V0.1
 
Project management work
Project management workProject management work
Project management work
 
ECM-article 2015
ECM-article 2015ECM-article 2015
ECM-article 2015
 
The importance of IT Change Management to the DR and BCP process
The importance of IT Change Management to the DR and BCP processThe importance of IT Change Management to the DR and BCP process
The importance of IT Change Management to the DR and BCP process
 
Erp research agenda(imds)
Erp research agenda(imds)Erp research agenda(imds)
Erp research agenda(imds)
 
It governance 13 may20102
It governance 13 may20102It governance 13 may20102
It governance 13 may20102
 
WP1 - Planning and Budgeting Systems
WP1 - Planning and Budgeting SystemsWP1 - Planning and Budgeting Systems
WP1 - Planning and Budgeting Systems
 
ERP
ERPERP
ERP
 
Information systems strategy formulation
Information systems strategy formulationInformation systems strategy formulation
Information systems strategy formulation
 

Similar to CHANGE MANAGEMENT: IMPLEMENTATION AND BENEFITS OF THE CHANGE CONTROL IN THE INFORMATION TECHNOLOGY ENVIRONMENT

Innovative Technologies And Software For Higher Education...
Innovative Technologies And Software For Higher Education...Innovative Technologies And Software For Higher Education...
Innovative Technologies And Software For Higher Education...Robin Anderson
 
ONTOLOGY DRIVEN KNOWLEDGE MAP FOR ENHANCING BUSINESS PROCESS REENGINEERING
ONTOLOGY DRIVEN KNOWLEDGE MAP FOR ENHANCING BUSINESS PROCESS REENGINEERINGONTOLOGY DRIVEN KNOWLEDGE MAP FOR ENHANCING BUSINESS PROCESS REENGINEERING
ONTOLOGY DRIVEN KNOWLEDGE MAP FOR ENHANCING BUSINESS PROCESS REENGINEERINGcseij
 
Project and Change Management Success Factors from Malaysian Government Depar...
Project and Change Management Success Factors from Malaysian Government Depar...Project and Change Management Success Factors from Malaysian Government Depar...
Project and Change Management Success Factors from Malaysian Government Depar...IOSR Journals
 
An Assessment of Project Portfolio Management Techniques on Product and Servi...
An Assessment of Project Portfolio Management Techniques on Product and Servi...An Assessment of Project Portfolio Management Techniques on Product and Servi...
An Assessment of Project Portfolio Management Techniques on Product and Servi...iosrjce
 
A New Framework For Managing IT-Enabled Business Change
A New Framework For Managing IT-Enabled Business ChangeA New Framework For Managing IT-Enabled Business Change
A New Framework For Managing IT-Enabled Business ChangeJulie Davis
 
EXPLORING THE LINK BETWEEN LEADERSHIP AND DEVOPS PRACTICE AND PRINCIPLE ADOPTION
EXPLORING THE LINK BETWEEN LEADERSHIP AND DEVOPS PRACTICE AND PRINCIPLE ADOPTIONEXPLORING THE LINK BETWEEN LEADERSHIP AND DEVOPS PRACTICE AND PRINCIPLE ADOPTION
EXPLORING THE LINK BETWEEN LEADERSHIP AND DEVOPS PRACTICE AND PRINCIPLE ADOPTIONacijjournal
 
EXPLORING THE LINK BETWEEN LEADERSHIP AND DEVOPS PRACTICE AND PRINCIPLE ADOPTION
EXPLORING THE LINK BETWEEN LEADERSHIP AND DEVOPS PRACTICE AND PRINCIPLE ADOPTIONEXPLORING THE LINK BETWEEN LEADERSHIP AND DEVOPS PRACTICE AND PRINCIPLE ADOPTION
EXPLORING THE LINK BETWEEN LEADERSHIP AND DEVOPS PRACTICE AND PRINCIPLE ADOPTIONacijjournal
 
Business Process Reenginering
Business Process ReengineringBusiness Process Reenginering
Business Process ReengineringWsBlemba
 
Health Information Governance Analysis
Health Information Governance AnalysisHealth Information Governance Analysis
Health Information Governance AnalysisKaty Allen
 
Archibald di filippo_comprehensive_plc_model_final
Archibald di filippo_comprehensive_plc_model_finalArchibald di filippo_comprehensive_plc_model_final
Archibald di filippo_comprehensive_plc_model_finalsansharmajs
 
Proper Strategy Implementation And Evaluation Of Dish Network
Proper Strategy Implementation And Evaluation Of Dish NetworkProper Strategy Implementation And Evaluation Of Dish Network
Proper Strategy Implementation And Evaluation Of Dish NetworkTonya Carter
 
project management process groups
project management process groupsproject management process groups
project management process groupserick chuwa
 
A Comparative Analysis Of Various Methodologies Of Agile Project Management V...
A Comparative Analysis Of Various Methodologies Of Agile Project Management V...A Comparative Analysis Of Various Methodologies Of Agile Project Management V...
A Comparative Analysis Of Various Methodologies Of Agile Project Management V...Brittany Allen
 
Management Control in Contemporary Organization: Opportunities, Challenges an...
Management Control in Contemporary Organization: Opportunities, Challenges an...Management Control in Contemporary Organization: Opportunities, Challenges an...
Management Control in Contemporary Organization: Opportunities, Challenges an...Dr. Amarjeet Singh
 
A Methodology For Change Management In Manufacturing
A Methodology For Change Management In ManufacturingA Methodology For Change Management In Manufacturing
A Methodology For Change Management In ManufacturingScott Bou
 
IRJET-Quality Benchmarking in Construction Industry
IRJET-Quality Benchmarking in Construction IndustryIRJET-Quality Benchmarking in Construction Industry
IRJET-Quality Benchmarking in Construction IndustryIRJET Journal
 
Proyek Management E-Book- (3 Constraint)
Proyek Management E-Book- (3 Constraint)Proyek Management E-Book- (3 Constraint)
Proyek Management E-Book- (3 Constraint)PandeGedeAngga
 
MANAGING IT INNOVATION: RECESSIONARY AND POST-RECESSIONARY SERVICE AND STAFFI...
MANAGING IT INNOVATION: RECESSIONARY AND POST-RECESSIONARY SERVICE AND STAFFI...MANAGING IT INNOVATION: RECESSIONARY AND POST-RECESSIONARY SERVICE AND STAFFI...
MANAGING IT INNOVATION: RECESSIONARY AND POST-RECESSIONARY SERVICE AND STAFFI...IJMIT JOURNAL
 

Similar to CHANGE MANAGEMENT: IMPLEMENTATION AND BENEFITS OF THE CHANGE CONTROL IN THE INFORMATION TECHNOLOGY ENVIRONMENT (20)

Innovative Technologies And Software For Higher Education...
Innovative Technologies And Software For Higher Education...Innovative Technologies And Software For Higher Education...
Innovative Technologies And Software For Higher Education...
 
ONTOLOGY DRIVEN KNOWLEDGE MAP FOR ENHANCING BUSINESS PROCESS REENGINEERING
ONTOLOGY DRIVEN KNOWLEDGE MAP FOR ENHANCING BUSINESS PROCESS REENGINEERINGONTOLOGY DRIVEN KNOWLEDGE MAP FOR ENHANCING BUSINESS PROCESS REENGINEERING
ONTOLOGY DRIVEN KNOWLEDGE MAP FOR ENHANCING BUSINESS PROCESS REENGINEERING
 
Project and Change Management Success Factors from Malaysian Government Depar...
Project and Change Management Success Factors from Malaysian Government Depar...Project and Change Management Success Factors from Malaysian Government Depar...
Project and Change Management Success Factors from Malaysian Government Depar...
 
An Assessment of Project Portfolio Management Techniques on Product and Servi...
An Assessment of Project Portfolio Management Techniques on Product and Servi...An Assessment of Project Portfolio Management Techniques on Product and Servi...
An Assessment of Project Portfolio Management Techniques on Product and Servi...
 
A New Framework For Managing IT-Enabled Business Change
A New Framework For Managing IT-Enabled Business ChangeA New Framework For Managing IT-Enabled Business Change
A New Framework For Managing IT-Enabled Business Change
 
EXPLORING THE LINK BETWEEN LEADERSHIP AND DEVOPS PRACTICE AND PRINCIPLE ADOPTION
EXPLORING THE LINK BETWEEN LEADERSHIP AND DEVOPS PRACTICE AND PRINCIPLE ADOPTIONEXPLORING THE LINK BETWEEN LEADERSHIP AND DEVOPS PRACTICE AND PRINCIPLE ADOPTION
EXPLORING THE LINK BETWEEN LEADERSHIP AND DEVOPS PRACTICE AND PRINCIPLE ADOPTION
 
EXPLORING THE LINK BETWEEN LEADERSHIP AND DEVOPS PRACTICE AND PRINCIPLE ADOPTION
EXPLORING THE LINK BETWEEN LEADERSHIP AND DEVOPS PRACTICE AND PRINCIPLE ADOPTIONEXPLORING THE LINK BETWEEN LEADERSHIP AND DEVOPS PRACTICE AND PRINCIPLE ADOPTION
EXPLORING THE LINK BETWEEN LEADERSHIP AND DEVOPS PRACTICE AND PRINCIPLE ADOPTION
 
Business Process Reenginering
Business Process ReengineringBusiness Process Reenginering
Business Process Reenginering
 
Optimize Change Management
Optimize Change ManagementOptimize Change Management
Optimize Change Management
 
Health Information Governance Analysis
Health Information Governance AnalysisHealth Information Governance Analysis
Health Information Governance Analysis
 
Archibald di filippo_comprehensive_plc_model_final
Archibald di filippo_comprehensive_plc_model_finalArchibald di filippo_comprehensive_plc_model_final
Archibald di filippo_comprehensive_plc_model_final
 
Proper Strategy Implementation And Evaluation Of Dish Network
Proper Strategy Implementation And Evaluation Of Dish NetworkProper Strategy Implementation And Evaluation Of Dish Network
Proper Strategy Implementation And Evaluation Of Dish Network
 
project management process groups
project management process groupsproject management process groups
project management process groups
 
01 itpm6
01 itpm601 itpm6
01 itpm6
 
A Comparative Analysis Of Various Methodologies Of Agile Project Management V...
A Comparative Analysis Of Various Methodologies Of Agile Project Management V...A Comparative Analysis Of Various Methodologies Of Agile Project Management V...
A Comparative Analysis Of Various Methodologies Of Agile Project Management V...
 
Management Control in Contemporary Organization: Opportunities, Challenges an...
Management Control in Contemporary Organization: Opportunities, Challenges an...Management Control in Contemporary Organization: Opportunities, Challenges an...
Management Control in Contemporary Organization: Opportunities, Challenges an...
 
A Methodology For Change Management In Manufacturing
A Methodology For Change Management In ManufacturingA Methodology For Change Management In Manufacturing
A Methodology For Change Management In Manufacturing
 
IRJET-Quality Benchmarking in Construction Industry
IRJET-Quality Benchmarking in Construction IndustryIRJET-Quality Benchmarking in Construction Industry
IRJET-Quality Benchmarking in Construction Industry
 
Proyek Management E-Book- (3 Constraint)
Proyek Management E-Book- (3 Constraint)Proyek Management E-Book- (3 Constraint)
Proyek Management E-Book- (3 Constraint)
 
MANAGING IT INNOVATION: RECESSIONARY AND POST-RECESSIONARY SERVICE AND STAFFI...
MANAGING IT INNOVATION: RECESSIONARY AND POST-RECESSIONARY SERVICE AND STAFFI...MANAGING IT INNOVATION: RECESSIONARY AND POST-RECESSIONARY SERVICE AND STAFFI...
MANAGING IT INNOVATION: RECESSIONARY AND POST-RECESSIONARY SERVICE AND STAFFI...
 

Recently uploaded

Machine Learning Model Validation (Aijun Zhang 2024).pdf
Machine Learning Model Validation (Aijun Zhang 2024).pdfMachine Learning Model Validation (Aijun Zhang 2024).pdf
Machine Learning Model Validation (Aijun Zhang 2024).pdfAijun Zhang
 
UiPath Solutions Management Preview - Northern CA Chapter - March 22.pdf
UiPath Solutions Management Preview - Northern CA Chapter - March 22.pdfUiPath Solutions Management Preview - Northern CA Chapter - March 22.pdf
UiPath Solutions Management Preview - Northern CA Chapter - March 22.pdfDianaGray10
 
How to Effectively Monitor SD-WAN and SASE Environments with ThousandEyes
How to Effectively Monitor SD-WAN and SASE Environments with ThousandEyesHow to Effectively Monitor SD-WAN and SASE Environments with ThousandEyes
How to Effectively Monitor SD-WAN and SASE Environments with ThousandEyesThousandEyes
 
OpenShift Commons Paris - Choose Your Own Observability Adventure
OpenShift Commons Paris - Choose Your Own Observability AdventureOpenShift Commons Paris - Choose Your Own Observability Adventure
OpenShift Commons Paris - Choose Your Own Observability AdventureEric D. Schabell
 
UiPath Platform: The Backend Engine Powering Your Automation - Session 1
UiPath Platform: The Backend Engine Powering Your Automation - Session 1UiPath Platform: The Backend Engine Powering Your Automation - Session 1
UiPath Platform: The Backend Engine Powering Your Automation - Session 1DianaGray10
 
Secure your environment with UiPath and CyberArk technologies - Session 1
Secure your environment with UiPath and CyberArk technologies - Session 1Secure your environment with UiPath and CyberArk technologies - Session 1
Secure your environment with UiPath and CyberArk technologies - Session 1DianaGray10
 
Introduction to Quantum Computing
Introduction to Quantum ComputingIntroduction to Quantum Computing
Introduction to Quantum ComputingGDSC PJATK
 
Computer 10: Lesson 10 - Online Crimes and Hazards
Computer 10: Lesson 10 - Online Crimes and HazardsComputer 10: Lesson 10 - Online Crimes and Hazards
Computer 10: Lesson 10 - Online Crimes and HazardsSeth Reyes
 
UiPath Studio Web workshop series - Day 6
UiPath Studio Web workshop series - Day 6UiPath Studio Web workshop series - Day 6
UiPath Studio Web workshop series - Day 6DianaGray10
 
Designing A Time bound resource download URL
Designing A Time bound resource download URLDesigning A Time bound resource download URL
Designing A Time bound resource download URLRuncy Oommen
 
AI Fame Rush Review – Virtual Influencer Creation In Just Minutes
AI Fame Rush Review – Virtual Influencer Creation In Just MinutesAI Fame Rush Review – Virtual Influencer Creation In Just Minutes
AI Fame Rush Review – Virtual Influencer Creation In Just MinutesMd Hossain Ali
 
UWB Technology for Enhanced Indoor and Outdoor Positioning in Physiological M...
UWB Technology for Enhanced Indoor and Outdoor Positioning in Physiological M...UWB Technology for Enhanced Indoor and Outdoor Positioning in Physiological M...
UWB Technology for Enhanced Indoor and Outdoor Positioning in Physiological M...UbiTrack UK
 
IESVE Software for Florida Code Compliance Using ASHRAE 90.1-2019
IESVE Software for Florida Code Compliance Using ASHRAE 90.1-2019IESVE Software for Florida Code Compliance Using ASHRAE 90.1-2019
IESVE Software for Florida Code Compliance Using ASHRAE 90.1-2019IES VE
 
GenAI and AI GCC State of AI_Object Automation Inc
GenAI and AI GCC State of AI_Object Automation IncGenAI and AI GCC State of AI_Object Automation Inc
GenAI and AI GCC State of AI_Object Automation IncObject Automation
 
Using IESVE for Loads, Sizing and Heat Pump Modeling to Achieve Decarbonization
Using IESVE for Loads, Sizing and Heat Pump Modeling to Achieve DecarbonizationUsing IESVE for Loads, Sizing and Heat Pump Modeling to Achieve Decarbonization
Using IESVE for Loads, Sizing and Heat Pump Modeling to Achieve DecarbonizationIES VE
 
Things you didn't know you can use in your Salesforce
Things you didn't know you can use in your SalesforceThings you didn't know you can use in your Salesforce
Things you didn't know you can use in your SalesforceMartin Humpolec
 
IaC & GitOps in a Nutshell - a FridayInANuthshell Episode.pdf
IaC & GitOps in a Nutshell - a FridayInANuthshell Episode.pdfIaC & GitOps in a Nutshell - a FridayInANuthshell Episode.pdf
IaC & GitOps in a Nutshell - a FridayInANuthshell Episode.pdfDaniel Santiago Silva Capera
 
Empowering Africa's Next Generation: The AI Leadership Blueprint
Empowering Africa's Next Generation: The AI Leadership BlueprintEmpowering Africa's Next Generation: The AI Leadership Blueprint
Empowering Africa's Next Generation: The AI Leadership BlueprintMahmoud Rabie
 
20200723_insight_release_plan_v6.pdf20200723_insight_release_plan_v6.pdf
20200723_insight_release_plan_v6.pdf20200723_insight_release_plan_v6.pdf20200723_insight_release_plan_v6.pdf20200723_insight_release_plan_v6.pdf
20200723_insight_release_plan_v6.pdf20200723_insight_release_plan_v6.pdfJamie (Taka) Wang
 
COMPUTER 10: Lesson 7 - File Storage and Online Collaboration
COMPUTER 10: Lesson 7 - File Storage and Online CollaborationCOMPUTER 10: Lesson 7 - File Storage and Online Collaboration
COMPUTER 10: Lesson 7 - File Storage and Online Collaborationbruanjhuli
 

Recently uploaded (20)

Machine Learning Model Validation (Aijun Zhang 2024).pdf
Machine Learning Model Validation (Aijun Zhang 2024).pdfMachine Learning Model Validation (Aijun Zhang 2024).pdf
Machine Learning Model Validation (Aijun Zhang 2024).pdf
 
UiPath Solutions Management Preview - Northern CA Chapter - March 22.pdf
UiPath Solutions Management Preview - Northern CA Chapter - March 22.pdfUiPath Solutions Management Preview - Northern CA Chapter - March 22.pdf
UiPath Solutions Management Preview - Northern CA Chapter - March 22.pdf
 
How to Effectively Monitor SD-WAN and SASE Environments with ThousandEyes
How to Effectively Monitor SD-WAN and SASE Environments with ThousandEyesHow to Effectively Monitor SD-WAN and SASE Environments with ThousandEyes
How to Effectively Monitor SD-WAN and SASE Environments with ThousandEyes
 
OpenShift Commons Paris - Choose Your Own Observability Adventure
OpenShift Commons Paris - Choose Your Own Observability AdventureOpenShift Commons Paris - Choose Your Own Observability Adventure
OpenShift Commons Paris - Choose Your Own Observability Adventure
 
UiPath Platform: The Backend Engine Powering Your Automation - Session 1
UiPath Platform: The Backend Engine Powering Your Automation - Session 1UiPath Platform: The Backend Engine Powering Your Automation - Session 1
UiPath Platform: The Backend Engine Powering Your Automation - Session 1
 
Secure your environment with UiPath and CyberArk technologies - Session 1
Secure your environment with UiPath and CyberArk technologies - Session 1Secure your environment with UiPath and CyberArk technologies - Session 1
Secure your environment with UiPath and CyberArk technologies - Session 1
 
Introduction to Quantum Computing
Introduction to Quantum ComputingIntroduction to Quantum Computing
Introduction to Quantum Computing
 
Computer 10: Lesson 10 - Online Crimes and Hazards
Computer 10: Lesson 10 - Online Crimes and HazardsComputer 10: Lesson 10 - Online Crimes and Hazards
Computer 10: Lesson 10 - Online Crimes and Hazards
 
UiPath Studio Web workshop series - Day 6
UiPath Studio Web workshop series - Day 6UiPath Studio Web workshop series - Day 6
UiPath Studio Web workshop series - Day 6
 
Designing A Time bound resource download URL
Designing A Time bound resource download URLDesigning A Time bound resource download URL
Designing A Time bound resource download URL
 
AI Fame Rush Review – Virtual Influencer Creation In Just Minutes
AI Fame Rush Review – Virtual Influencer Creation In Just MinutesAI Fame Rush Review – Virtual Influencer Creation In Just Minutes
AI Fame Rush Review – Virtual Influencer Creation In Just Minutes
 
UWB Technology for Enhanced Indoor and Outdoor Positioning in Physiological M...
UWB Technology for Enhanced Indoor and Outdoor Positioning in Physiological M...UWB Technology for Enhanced Indoor and Outdoor Positioning in Physiological M...
UWB Technology for Enhanced Indoor and Outdoor Positioning in Physiological M...
 
IESVE Software for Florida Code Compliance Using ASHRAE 90.1-2019
IESVE Software for Florida Code Compliance Using ASHRAE 90.1-2019IESVE Software for Florida Code Compliance Using ASHRAE 90.1-2019
IESVE Software for Florida Code Compliance Using ASHRAE 90.1-2019
 
GenAI and AI GCC State of AI_Object Automation Inc
GenAI and AI GCC State of AI_Object Automation IncGenAI and AI GCC State of AI_Object Automation Inc
GenAI and AI GCC State of AI_Object Automation Inc
 
Using IESVE for Loads, Sizing and Heat Pump Modeling to Achieve Decarbonization
Using IESVE for Loads, Sizing and Heat Pump Modeling to Achieve DecarbonizationUsing IESVE for Loads, Sizing and Heat Pump Modeling to Achieve Decarbonization
Using IESVE for Loads, Sizing and Heat Pump Modeling to Achieve Decarbonization
 
Things you didn't know you can use in your Salesforce
Things you didn't know you can use in your SalesforceThings you didn't know you can use in your Salesforce
Things you didn't know you can use in your Salesforce
 
IaC & GitOps in a Nutshell - a FridayInANuthshell Episode.pdf
IaC & GitOps in a Nutshell - a FridayInANuthshell Episode.pdfIaC & GitOps in a Nutshell - a FridayInANuthshell Episode.pdf
IaC & GitOps in a Nutshell - a FridayInANuthshell Episode.pdf
 
Empowering Africa's Next Generation: The AI Leadership Blueprint
Empowering Africa's Next Generation: The AI Leadership BlueprintEmpowering Africa's Next Generation: The AI Leadership Blueprint
Empowering Africa's Next Generation: The AI Leadership Blueprint
 
20200723_insight_release_plan_v6.pdf20200723_insight_release_plan_v6.pdf
20200723_insight_release_plan_v6.pdf20200723_insight_release_plan_v6.pdf20200723_insight_release_plan_v6.pdf20200723_insight_release_plan_v6.pdf
20200723_insight_release_plan_v6.pdf20200723_insight_release_plan_v6.pdf
 
COMPUTER 10: Lesson 7 - File Storage and Online Collaboration
COMPUTER 10: Lesson 7 - File Storage and Online CollaborationCOMPUTER 10: Lesson 7 - File Storage and Online Collaboration
COMPUTER 10: Lesson 7 - File Storage and Online Collaboration
 

CHANGE MANAGEMENT: IMPLEMENTATION AND BENEFITS OF THE CHANGE CONTROL IN THE INFORMATION TECHNOLOGY ENVIRONMENT

  • 1. International Journal of Advanced Information Technology (IJAIT) Vol. 6, No. 1, February 2016 DOI :10.5121/ijait.2016.6102 23 CHANGE MANAGEMENT: IMPLEMENTATION AND BENEFITS OF THE CHANGE CONTROL IN THE INFORMATION TECHNOLOGY ENVIRONMENT Paulo Roberto Martins de Andrade1 , Adriano B. Albuquerque2 , WeskleiDourado Teófilo3 , Fátima Aguiar da Silva3 1 Graduate Studies in Computer Science, University of Regina, Regina, SK, Canada 2 Universidade de Fortaleza, Fortaleza, CE, Brazil 3 FaculdadeEstácio FIC, Fortaleza, CE, Brazil ABSTRACT In the competitive environment, companies have given increasing importance to the IT sector and the resources it delivers as strategic. As a result, IT becomes a living being within the company. This sector is being subject to continuous changes in this scenario. These changes can occur within the own IT sector or whether IT to other sectors of the company. For both scenarios, it is important to have a good change control to avoid unnecessary trouble and expense. This paper aims to show through a case study, the benefits and results obtained with the implementation of a process of managing and controlling changes in the information technology environment of a large government company in Brazil. KEYWORDS Change control; Information technology, PMBOK, Software engineering. 1. INTRODUCTION We live in a time when technology advances faster and faster, and with these advances and changes in technology, corporations have to keep pace to be competitive in the increasingly computerized and demanding market. Exactly at this point enter the changes made in systems and network infrastructure. In the past, the common knowledge said that the IT department of the organization need to be aligned to the business, but today the IT is already part of the business. Both, the IT and the Business’ Department, are two areas that should be "integrated". With that in mind, it is necessary that the IT department is prepared to support and ensure timely, delivery of IT services required for the company's business and can also add value to the corporation [17]. With some of its foundational texts now decades old, IT change management is one of the most studied and utilized elements of the systems and infrastructure management discipline. With so much academic thinking and so many years of practical application behind it, one would think that the effective management of change would now be commonplace in IT organizations and the companies they serve. Surprisingly, the opposite it true. Author and IT Service Management expert, Harris Kern, reports that in a recent survey of 40 corporate IT infrastructure managers a surprising 60% admitted that their processes to handle change are not effective in communicating and coordinating changes occurring within their production environment. Among the key findings of the study: Not all changes are logged 95%; Changes not thoroughly tested 90%; Lack of
  • 2. International Journal of Advanced Information Technology (IJAIT) Vol. 6, No. 1, February 2016 24 process enforcement; Poor change communication and dissemination; Lack of centralized process ownership 60%; Lack of change approval policy 50%; Frequent change notification after the fact 40% [9]. More than an overall indictment of poor process implementation, these findings illustrate the extent to which organizations rely on a change control process to handle IT-related changes. Changes can be welcomed and usually they happen to have benefits. What is needed is to manage them the right way to not to be surprised negatively on the results. For every change has an expectation that must be the closest possible to the final result of the change. In order to have a management and control appropriate changes, the main aim of this paper is to define a process to carry out the treatment of changes in the information technology environment, deploying and generating benefits, because it is an extremely important environment for companies today. We must select tools to be used, define the stakeholders, ways of communication and approval roles. Thus we can define a process of change, starting from the request, its type, its approval, its execution and the lessons learned. With this formalized process, we can have the benefits expected as a higher rate of success in the changes, greater traceability, risk mitigation, among several other potential benefits with the use of the process. This paper delivery information about the sources of change and one some concepts of changes in the Project Management. Next, the paper shows us the previous scenario overview. After, we have a case study (with the problems founded, the benefits expected and the difficult in the implantation. In the next we have the results of the case study. At last, the paper gives us the conclusion. 2. MORE ABOUT CHANGES 2.1. Sources of Changes In our lives or in our projects we should always be prepared to deal with and make changes because they always occur. In the development of software applications, we recommend the use of good practices related to Software Engineering. For IT Governance there are several frameworks of best practice, one example would be the COBIT with BAI06 Manage Change process [10]. The COBIT is an IT governance framework maintained by ISACA (ISACA). It is a reference model and is not a ready solution. In other words, it needs to adapt it to the business to meet the needs, and align the information technology sector to the business and can be used only a few controls that seek to improve the processes that comprise the IT governance of each company [10]. There are several causes that give rise to the changes, we can highlight the compliance with laws and regulations such as PCI-DSS (Payment Card Industry - Data Security Standard) [11], SOX (Sarbanes Oxley Act) [16], needs preventive measures in the IT environment, external events of which the IT has to comply in determined period, need for improvements in systems and infrastructure, senior management requests (strategic changes), but the highest incidence of changes in the IT environment noted in the case study in this article are those that originate from problems. In this case, the change is the answer to the problem. Another important part of the change comes from direct demands from any interested party.
  • 3. International Journal of Advanced Information Technology (IJA 2.2. Concepts in the view of Project Management The Project Management Institute (PMI) is a non management professionals around the world integrat every country through research and education. Its central office is located in Pennsylvania (United States) [4]. The PMBOK identifies a subset of knowledge in project management, which is generally recognized as good practice, and as a result, used by the Project Management Institute (PMI), which defines some concepts down on change management [12]: “A change request is a formal proposal to modify any document delivery, or baseline”. (PMBOK, 2013, p. 85); “Perform Integrated Change Control is the process of reviewing all change requests, approving changes and managing changes being made deliveries, organizational process assets, project documents and project management plan, and report the disposition of thereof” p. 94). The PMBOK describes a process for the integrated change control with a focus on project management, in which he mentions the main inputs, tools and techniques, and outputs of the process as shown in Figure 1. Figure 1. Perform This process can be adaptable to each company, environment or need, since the focus of the PMBOK guide is for project management environment. There is also another project management method cal through the dissemination of good practice in project management, in which speech and deals with the importance of using change management [1]. PRINCE2 is a non owner who is emerging worldwide as one of the most accepte project management and is much used mainly in European countries. It is truly flexible and can be applied to any project or company, regardless of scale, type, organization, geography or culture. Addresses project management with four integra processes and project environment. One of its themes is exactly "change" and has the purpose to identify, assess and monitor any changes [2]. The fact that the PRINCE2 have a specific area for change management help in th project, and the changes made. It is evident that the changes will always occur and that International Journal of Advanced Information Technology (IJAIT) Vol. 6, No. 1, February 201 Concepts in the view of Project Management The Project Management Institute (PMI) is a non-profit organization that combines project management professionals around the world integrating more than 2.9 million members in nearly every country through research and education. Its central office is located in Pennsylvania The PMBOK identifies a subset of knowledge in project management, which is generally good practice, and as a result, used by the Project Management Institute (PMI), which defines some concepts down on change management [12]: “A change request is a formal proposal to modify any document delivery, or baseline”. (PMBOK, rm Integrated Change Control is the process of reviewing all change requests, approving changes and managing changes being made deliveries, organizational process assets, project documents and project management plan, and report the disposition of thereof” The PMBOK describes a process for the integrated change control with a focus on project management, in which he mentions the main inputs, tools and techniques, and outputs of the process as shown in Figure 1. Figure 1. Perform Integrated Change Control Process (source: PMBOK 5ed. P. 94) This process can be adaptable to each company, environment or need, since the focus of the PMBOK guide is for project management environment. There is also another project management method called PRINCE2 is recognized worldwide through the dissemination of good practice in project management, in which speech and deals with the importance of using change management [1]. PRINCE2 is a non owner who is emerging worldwide as one of the most accepte project management and is much used mainly in European countries. It is truly flexible and can be applied to any project or company, regardless of scale, type, organization, geography or culture. Addresses project management with four integrated elements: principles, themes, processes and project environment. One of its themes is exactly "change" and has the purpose to identify, assess and monitor any changes [2]. The fact that the PRINCE2 have a specific area for change management help in th project, and the changes made. It is evident that the changes will always occur and that IT) Vol. 6, No. 1, February 2016 25 profit organization that combines project ing more than 2.9 million members in nearly every country through research and education. Its central office is located in Pennsylvania The PMBOK identifies a subset of knowledge in project management, which is generally good practice, and as a result, used by the Project Management Institute (PMI), “A change request is a formal proposal to modify any document delivery, or baseline”. (PMBOK, rm Integrated Change Control is the process of reviewing all change requests, approving changes and managing changes being made deliveries, organizational process assets, project documents and project management plan, and report the disposition of thereof”. (PMBOK, 2013, The PMBOK describes a process for the integrated change control with a focus on project management, in which he mentions the main inputs, tools and techniques, and outputs of the This process can be adaptable to each company, environment or need, since the focus of the led PRINCE2 is recognized worldwide through the dissemination of good practice in project management, in which speech and deals PRINCE2 is a non owner who is emerging worldwide as one of the most accepted methods for project management and is much used mainly in European countries. It is truly flexible and can be applied to any project or company, regardless of scale, type, organization, geography or ted elements: principles, themes, processes and project environment. One of its themes is exactly "change" and has the purpose to The fact that the PRINCE2 have a specific area for change management help in the success of the project, and the changes made. It is evident that the changes will always occur and that
  • 4. International Journal of Advanced Information Technology (IJAIT) Vol. 6, No. 1, February 2016 26 communication of them is very important for effective implementation, because in this way reduces the probability of failure, time and cost, and thus fall into important and fundamental point that is customer satisfaction and success the purpose of the change [1]. The PMI and PRINCE2 (two of the biggest disseminators organs of good practice in project management, world-renowned) address change management emphatically as an important point for the success of projects, stating on multiple pages of your guides, good practices that can be used [13]. The reason to talk specifically about that topic changes in project management is to be the area where most uses the concepts, and where it is more widespread and used the change management process. This process can be easily adapted for information technology, using these best practices in order to achieve better results in the implementation and use of change management [3]. 2.3 The importance of the change management Organizations change to win. And this gain is not always financial. Sometimes the aim is to just improve interpersonal relationship, hasten the progress of internal processes or stimulate the involvement of employees in a new project. The possibilities are many and invests up time and money to achieve the goals. However, in many organizational changes the desired result is far away. And that does not happen by accident. When a company is created, its founders have beliefs, values and assumptions related to the way of how your business should work. If the company prospers, it is natural to hire people who share the same 'feelings'. These beliefs, values and assumptions are represented by the norms of behaviour and attitudes accepted by the organization. They are taught as "the correct way it should be done things around here." It can not be said, in an isolated manner, if a culture is good or bad. However, it is known that a culture is good if it is consistent with the company's strategy. For example, companies that depend on the creativity - such as those of advertisement, for example - may not have hierarchies and rigid processes; moreover, it does no longer true in chemical and pharmaceutical companies. Anyway, for us it is extremely important to be always attentive to the evolution of companies, so we realize that the same culture that led to success may no longer be useful to prosper in the future. And it's hard for some managers see themselves the need for change. Many managers fear that their subordinates resist the changes. Therefore, they do not play the role expected of them in any transformation process. Culture is created by the leaders and therefore, if we need to change, this change must begin with the leaders. It is they who must create a sense of need and urgency, to establish the vision and communicate it clearly and honestly. A change may require changes in existing structures, new skills needs, work load shifting, etc. All of these impacts should be managed effectively so that the transformation can occur. The transition between the current state and the future state should be monitored. Support new processes, contingency planning and treatment of risks, plans and support change issues must not be neglected. Training is an extremely important aspect of the process, but often is mishandled during a transformation. For this reason, it is responsible for the failure of much of the organizational changes. As can be seen, the success of organizational change processes is not so simple, requires attention and support professionals. The fact is that companies with proper professional support are
  • 5. International Journal of Advanced Information Technology (IJAIT) Vol. 6, No. 1, February 2016 27 evolving and achieved the desired results and this finding has a valuable significance for businesses, especially for those who are facing the challenge of taking its first steps into the future. 3. PREVIOUS SCENARIO OVERVIEW 3.1 Problems and benefits expected The scenario in which we performed the case study of this article it is a large government company, where we diagnose various problems related to changes in the information technology environment, such as systems, servers and network infrastructure. Routine problems were: • Unplanned outages of services. The unavailability of services mostly occurred during business hours, impacting users and customers of the company, thus affecting the credibility of the information technology sector. • Difficulty in tracing changes in the environment for troubleshooting. As the changes were made without any control we did not know what had changed in the environment, even a short time ago, making diagnosis difficult to solve problems, often resulting in increased downtime. • Risks unmitigated in carrying out the changes. As the risks were not analyzed and treated in the best way, the impact of changes often were not as expected. • Rework. A large percentage of the changes generated rework. • Low success rate in the changes. • Financial losses not measured, especially on the availability of systems and services. These are some of the many factors that contributed in the interest of implementing a change control process in the company. According to the market more and more competitive, and especially following the controls Framework COBIT and PMBOK, these good practices also would make other protruding factors to consider the real need to implement a process of integrated control of changes in management of enterprise information technology, seeking the benefits when using this process [6]. The main expected benefits that motivated the process of implementation were: • The better alignment of IT services with business. The changes will be filtered and prioritized as needed for business. • Increased visibility into the changes by exercising greater control over the execution of change, reducing the negative impact of change. • The risk analysis to prevent the service becomes unavailable due to failures. • Better assessment of the cost-benefit ratio of the change before it is implemented. • Reduction of cost, time and rework. • More stable services and increase of user productivity. These are some of the expected benefits of the process of implementation. The problems and benefits were analysed along with IT teams, managers and key stakeholders, thus coming to the conclusion that it would be quite feasible the implementation of an integrated control changes in the information technology sector.
  • 6. International Journal of Advanced Information Technology (IJAIT) Vol. 6, No. 1, February 2016 28 3.2 Difficult of the Change Management Process implementation During the implementation process were expected difficulties due to the sector's culture and its employees, being a paradigm shift because there were resistance from some people, especially for thinking that with this process, increase bureaucracy and this way, possible problems in the information technology sector, where more and more is expected quick answers to problems and incidents could take even longer to resolve. Andrade defines organizational culture as a set of beliefs, traditions, values, written and unwritten rules that can boost, speed, weaken, delay, facilitate, commit, hinder or prevent changes and performance of organizations [3]. According Chiavenato, the change is the main characteristic of contemporary times, being an essential aspect of creativity and innovation in organizations today [7]. Barbara mentions that: “Changes happen when people are prepared for the same, however, they find it difficult to break paradigms, changing behaviour and changing their attitudes, because changes imply something new and they are still attached to the previous archetype, causing uncertainty and being affected psychologically, causing fear and consequently generating resistance.” [5]. The main challenge of the deployment and use of change control process is to provide an organizational environment propitious to innovation that adds value to the company and to the information technology sector. In them will be developed and implemented projects and activities that generate changes, working mostly in dimensions’ people and results. The process creation, dissemination, definition of approval levels and roles were performed as expected. The greatest difficulty really was a culture change so that it could follow the process, especially at the beginning when sometimes tried to put the blame problems unrelated to the process in the process itself, being something new [15]. 4. CASE STUDY First of all, we need a formal process control changes that would fit as close as possible to the culture and reality of the IT sector and the company. We defined with all stakeholders in the process that any changes in the information technology environment should be requested, and formally managed through the integrated control of process changes. Through the definition that any changes would use the process, we saw the need to categorize the changes because there were cases where differential treatment would be needed for certain changes, aiming to make the process as effective as possible. To this categorization were defined three types of changes: Standard Change (Routine): These are pre-approved changes. This means that new requests are automatically approved and occur in periods intervals previously defined. Planned changes: Are the changes that run the normal flow within the process. Emergency changes: Are the changes that may occur outside the standard interval, only depending on the release of the immediate supervisor for immediate execution, are generally reactive changes to correct problems that are impacting or may impact the business.
  • 7. International Journal of Advanced Information Technology (IJA Any changes in the information technology environment must go through the process, being necessary to open a change request, which was made available on the company's Intranet a form to fill the requests. The Figure 2 show this form and in the Figure 3 is possible to see t of each request in the system. Both figures are in pt Figure International Journal of Advanced Information Technology (IJAIT) Vol. 6, No. 1, February 201 e information technology environment must go through the process, being necessary to open a change request, which was made available on the company's Intranet a form The Figure 2 show this form and in the Figure 3 is possible to see t of each request in the system. Both figures are in pt-BR (Portuguese – Brazil). Figure 2. Form of change request Figure 3. Tracking screen for the Change Requests IT) Vol. 6, No. 1, February 2016 29 e information technology environment must go through the process, being necessary to open a change request, which was made available on the company's Intranet a form The Figure 2 show this form and in the Figure 3 is possible to see the tracking
  • 8. International Journal of Advanced Information Technology (IJAIT) Vol. 6, No. 1, February 2016 30 On the form, you are asked to enter the following information: • What is the purpose of the change? • Start date and completion of the change. • What will assets be affected by the change? • What will items be impacted by the assets affected by the change? • What is the complexity of change? • Further details on the change. • Which the implementation experience of change? • Tests performed to carry out the change. • What is the return plan for change? The roles were defined for analysis and approval of the changes as described below: • Requester: Any employee of IT sector that want to make the change, and the requester also mostly responsible for the execution and implementation of the same, then the execution of the change should be completed by the requester or designed responsible. • Governance and IT Risk Team: Responsible for evaluate the request, categorize the change, send the flow of approvals, conduct communication to stakeholders, update the documentation and record the closure of the change. • Change Team: Responsible for assessing the feasibility of change, checking the necessary approval levels for the request. • Immediate supervisor: They are the persons responsible for the approval of the changes, usually managers and members of business teams impacted the change. After requesting submit the form changes, the application will be reviewed. If necessary, will be asked to charge to carry out possible corrections in your request. Then the change will be categorized and will cover the flow according to its categorization also being examined its feasibility, and responsible for approval. After the change is formally approved for execution, the team communicates to all parties affected by the change. This communication become more transparent to all the actions taken by TI, increasing their credibility with employees. Shortly after the execution of change, should be completed a post-implementation form with the questions shown below: • Was the purpose of the change reached? • Did the change occur within the expected interval? • Was there any incident arising from the change? • Was it necessary to trigger the return plan (rollback)? • Will be necessary upgrade documentation? • Other comments. After the post-implementation form is submitted, if necessary, documentation will be update, and thus the closure of the change will be recorded. 5. RESULTS To be able to measure the results of the integrated control process changes, create a performance indicator (KPI) to monitor and improve the process, using practices of continuous improvement. The indicator was set to be four times a year, consisting only the final result of the change, which may be success or failure. The changes considered successful, briefly, are the ones that occurred
  • 9. International Journal of Advanced Information Technology (IJA within the expected time period and had reached their ultimate goal, otherwise the change is classified as failed. After the first six months of 2015, we have recorded 200 requests for changes through the form found on the intranet. They all went through in the process designed and previously mentioned. Here entered changes relating to update systems, update systems (to make sure that deployment could affect some other IT assets), emergency changes, among other types. With AJUSA the process, only 17 changes obtained a failure during its implementation, it is necessary to Figure 2. Collected result from the first six months of 2015 With the formalization and implementation, the process has matured gradually until you can be part of the IT team culture. It was observed the increase of monitoring reports after the process of implementation. The changes have achieved their goals almost entirely. The risks are mitigated to be obtained minimal impact to the environment in the changes. A major benefit noted by all the company's employees was communication. Earlier the systems and servers were unavailable without prior knowledge of users, making it stressful communication with the IT sector. With the process implementation, the system’s stops are scheduled and even emergencies, are communicated to all interested parties, which made up the credibility of the IT sector in the company. With the creation of the KPI to monitor the change control process there was come in quite satisfactory results, as we saw in th 6. CONCLUSIONS As mentioned throughout this paper, the use of change management is becoming increasingly essential for the Information Technology sector, and for businesses, helping and supporting the achievement of strategic planning, target that we live in today, and growth and alignment of information technology with business, adding more value to the enterprise processes such as change management, can be a differentiator so that you can excel in current market scenario. The implementation of the change management process is not complicated, but you should not expect its implementation from day to night, we need to adapt the process to the culture and maturity of the company, requiring ded and effort everyone involved, so that we can break resistance and paradigms related to this change with the use of the process. International Journal of Advanced Information Technology (IJAIT) Vol. 6, No. 1, February 201 within the expected time period and had reached their ultimate goal, otherwise the change is the first six months of 2015, we have recorded 200 requests for changes through the form found on the intranet. They all went through in the process designed and previously mentioned. Here entered changes relating to update systems, update hardware, implem systems (to make sure that deployment could affect some other IT assets), emergency changes, among other types. With AJUSA the process, only 17 changes obtained a failure during its implementation, it is necessary to enable the return plan. Figure 4 illustrates this data. Figure 2. Collected result from the first six months of 2015 With the formalization and implementation, the process has matured gradually until you can be part of the IT team culture. It was observed the increase of environmental availability through monitoring reports after the process of implementation. The changes have achieved their goals almost entirely. The risks are mitigated to be obtained minimal impact to the environment in the d by all the company's employees was communication. Earlier the systems and servers were unavailable without prior knowledge of users, making it stressful communication with the IT sector. With the process implementation, the system’s stops are nd even emergencies, are communicated to all interested parties, which made up the credibility of the IT sector in the company. With the creation of the KPI to monitor the change control process there was come in quite satisfactory results, as we saw in the figure 2. As mentioned throughout this paper, the use of change management is becoming increasingly essential for the Information Technology sector, and for businesses, helping and supporting the achievement of strategic planning, targets, and indicators. With the highly competitive market that we live in today, and growth and alignment of information technology with business, adding more value to the enterprise processes such as change management, can be a differentiator so that excel in current market scenario. The implementation of the change management process is not complicated, but you should not expect its implementation from day to night, we need to adapt the process to the culture and maturity of the company, requiring dedication, commitment and effort everyone involved, so that we can break resistance and paradigms related to this change with the use of the process. IT) Vol. 6, No. 1, February 2016 31 within the expected time period and had reached their ultimate goal, otherwise the change is the first six months of 2015, we have recorded 200 requests for changes through the form found on the intranet. They all went through in the process designed and previously mentioned. , implementation of new systems (to make sure that deployment could affect some other IT assets), emergency changes, among other types. With AJUSA the process, only 17 changes obtained a failure during its illustrates this data. With the formalization and implementation, the process has matured gradually until you can be environmental availability through monitoring reports after the process of implementation. The changes have achieved their goals almost entirely. The risks are mitigated to be obtained minimal impact to the environment in the d by all the company's employees was communication. Earlier the systems and servers were unavailable without prior knowledge of users, making it stressful communication with the IT sector. With the process implementation, the system’s stops are nd even emergencies, are communicated to all interested parties, which made up the credibility of the IT sector in the company. With the creation of the KPI to monitor the change e figure 2. As mentioned throughout this paper, the use of change management is becoming increasingly essential for the Information Technology sector, and for businesses, helping and supporting the s, and indicators. With the highly competitive market that we live in today, and growth and alignment of information technology with business, adding more value to the enterprise processes such as change management, can be a differentiator so that excel in current market scenario. The implementation of the change management process is not complicated, but you should not expect its implementation from day to night, we need to ication, commitment and effort everyone involved, so that we can break resistance and paradigms related to this
  • 10. International Journal of Advanced Information Technology (IJAIT) Vol. 6, No. 1, February 2016 32 It is observed although the implementation of a change management process brings many benefits as cited throughout this article. It is a process that does not require much financial investment, making it highly feasible and recommended for use. For the process, the main barrier to successful were the people. With time and the use of the process is perceived the change by the involved culture, making it easier deployment and standardization of other processes in order to use of best market practices in order to add the most value to the business and making a difference in today's competitive market. ACKNOWLEDGEMENTS The CNPq (Conselho Nacional de Desenvolvimento Científico e Tecnológico - "National Counsel of Technological and Scientific Development") and the Ceará water and sewage company support this work. REFERENCES [1] ANDRADE, PAULO R. M.; ALBUQUERQUE, A. B.; FROTA, O. F. ; SILVA FILHO, J. F. . PM5: One approach to the management of IT projects applied in the Brazilian public sector, 2015, Las Vegas, Nevada, USA. Proceedings of 13th International Conference on Software Engineering Research and Practice - SERP. San Diego, California, USA: Waset.org, 2015. v. 1. [2] ANDRADE, P. R. M., ALBUQUERQUE, A. B.. “Escritório de projetos: Características, vantagens e o planejamento de sua implantação no setor público” RBGP. Revista Brasileira de Gerenciamento de Projetos, 2014, p. 21-26. [3] ANDRADE, PAULO R. M.; ALBUQUERQUE, A. B.; ARAUJO, R. G.; CRONEMBERGER FILHO, J.; PEREIRA, T. R.; MENDONCA, N. C.. Improving business by migrating applications to the cloud using cloudstep, 2015, Gwangju, Korea. Proceedings for the 29th International Conference on Advanced Information Networking and Applications Workshops, 2015. p. 77-82. [4] ATKINSON, R. “Project management: cost, time and quality, two best guesses and a phenomenon, it’s time to accept other success criteria.” International Journal of Project Management, 1999: 337- 342. [5] BARBARA, Michele. Gestão de mudança: superando dificuldades na implantação dos sistemas de informação nas organizações, 2013. [6] CAVAREC, Y. “Revisiting de Definition of Project Success.” PMI Global Congress Proceedings. Vancouver, Canada: PMI, 2012. [7] CHIAVENATO, I. Gestão de Pessoas: o novo papel dos recursos humanos nas organizações. Rio de Janeiro: Elsevier, 1999. [8] HALL, M., R. HOLT, e D. PURCHASE. “Project sponsor under new public management: lessons from the frontline.” International Journal of Project Management, 2003: 495-502. [9] Harris Kern, http://www.harriskern.com/ (visited on January 20, 2016). [10] ISACA, http://www.isaca.org/cobit (visited on January 20, 2016). [11] PCI Compliance Guide, https://www.pcicomplianceguide.org/ (visited on January 20, 2016). [12] PMI; “A Guide to the Project Management Body of Knowledge: PMBOK(R) Guide.” 5ª. San Francisco, CA: Syba - PMI Publishing Division, 2013. [13] REGO, M. L, e H. A. R. IRIGARAY. “Gerenciamento de Projetos: Existe Produção Científica Brasileira?” Proceedings of XXXV Encontro ANPAD. Rio de Janeiro, RJ: ANPAD, 2011. [14] SANTOS RODRIGUEZ, A. Evolução do Modelo de Gestão. Proceedings of II CONGRESSO NACIONAL DE EXCELÊNCIA EM GESTÃO, 4, 2008, Rio de Janeiro [15] SÖDERLUND, J. “Building theories of project management: past research, questions for the future.” International Journal of Project Management, 2004: 183-191. [16] SOX LAW, http://www.soxlaw.com/compliance.htm (visited on January 20, 2016). [17] SRIVANNABOON, S., e D. Z. MILOSEVIC. “A two-way influence between business strategy and project management.” International Journal of Project Management, 2006: 493-505. [18] WISE, L. R. “Public management reform: competing drivers of change.” Public Administration Review 62, nº 5 (2002)
  • 11. International Journal of Advanced Information Technology (IJA AUTHORS Paulo Roberto Martins deAndrade andAssociated Professor in the Management. He has 11 years of experience in IT, with some certifications, like PMP and Cobit. He has a Master in Applied Informatics IT Management. Adriano Bessa Albuquerque has Doctorate in a Master in Applied. He has experience in computer science with engineering. Actually he is a professor in the University of Fortaleza and he also implementer and official evaluator of software maturity models: CMMI and MPS.BR. WeskleiDouradoTeófilohas a degree in Computer Networks, MBA in IT Governance and MBA in Project Management. PMP, COBIT and CompTIA Security +. of Information Technology, with an emphasis on IT Governance, Project Management and Information Security. Fátima Aguiar da Silvahas a degree in Management. She has certifications likeCAPM, Cobit and over 6 years in the field of Process Management Project Management. International Journal of Advanced Information Technology (IJAIT) Vol. 6, No. 1, February 201 Paulo Roberto Martins deAndrade is a PhD Student in the University of Regina Professor in the “Estácio FIC”. Actually, his focus is in Project Management. He has 11 years of experience in IT, with some certifications, like PMP and Applied Informatics, MBA in Project Management and MBA in has Doctorate in Systems Engineering and Computing He has experience in computer science with emphases in softwa engineering. Actually he is a professor in the University of Fortaleza and he also Acts as implementer and official evaluator of software maturity models: CMMI and MPS.BR. has a degree in Computer Networks, MBA in IT Governance and MBA in Project Management. He has more than 15 certifications, among which are, and CompTIA Security +. He has been working for over 8 years in the field of Information Technology, with an emphasis on IT Governance, Project Management has a degree in Business Administration and MBA in Project certifications likeCAPM, Cobit and ITIL.Shehas been working for Process Management, with an emphasis on IT Governance and IT) Vol. 6, No. 1, February 2016 33 ent in the University of Regina . Actually, his focus is in Project Management. He has 11 years of experience in IT, with some certifications, like PMP and , MBA in Project Management and MBA in and in software Acts as has a degree in Computer Networks, MBA in IT Governance ications, among which are, for over 8 years in the field of Information Technology, with an emphasis on IT Governance, Project Management MBA in Project working for vernance and