The objective of the present study is to optimize the bottoming cycle for a 6 FA gas turbine. The present work focuses on optimization of steam cycle alone by analyzing the sensitivity of steam pressure and steam temperature and configuration of waste heat recovery boiler. A two pressure configuration will have better opportunity for power generation and for applying service steam for feed stack and drying etc. From cycle analysis at 4 kg/cm2 low pressure steam appear to be most
suitable for the thermodynamic cycle.