Giorgio Fantauzzi
Project Leader Tecnimont (Maire Tecnimont Group)
ADVANCING AN INTEGRATED APPROACH IN
PLANNING AND BUILDING INFRASTRUCTURE
PROJECTS SUCH AS METROS AND HIGH SPEED
RAILWAYS
METRORAIL 2010 Asia
New Delhi, 25 - 27 October 2010
ABSTRACT
• A comprehensive planning process to identify and address potential
challenges
• Best practices in underground tunneling for railways and high speed railways
• Technological systems for optimal performance and safety
Mr GIORGIO FANTAUZZI’s CAREER SUMMARY
Project Leader, Tecnimont S.p.A (Maire Tecnimont Group)
Giorgio Fantauzzi is a Project Leader within the Tecnimont
engineering department. He developed his experience by working
intensively on various projects, ranging from highways to high
speed railways and metros (Highway “Variante di Valico”, High
Speed Railway “Bologna-Firenze”, Turin Metro, Rome Metro). He
transferred his knowledge to other projects as well as specialised
universities courses, conferences and training courses. Now he
manages the design phase on different infrastructures project,
using and coordinating several specialist on different matters.
Advancing an integrated approach in planning and building infrastructure
projects such as metros and high-speed railways
2
3
CORPORATE PROFILE
The Group combines high
quality and planning standards
with a focus on multicultural
and environmental issues.
With a workforce of about
5,100 employees, more than
half of whom outside Italy, at
30 June 2010 Maire
Tecnimont reported revenues
of 1112 million Euro and a
backlog of about 6,151
million Euro.
CC Plant - Ibritè, Brazil
Maire Tecnimont is a leading
Engineering and Construction
Group operating worldwide in the
Chemicals and Petrochemicals, Oil
& Gas, Power, Infrastructure and
Civil Engineering sectors.
With a presence in four continents
and 30 countries, the Group
currently owns 50 operating
subsidiaries, with main Italian
offices in Rome, Milan and Turin.
The Group’s success and reputation
have been achieved due to its
strong technology orientation as
well as its advanced skills in
Project Management,
Engineering, Procurement and
Construction services for the
implementation of complex
projects worldwide. It has
developed and demonstrated
significant expertise in managing
large EPC projects on a turnkey
basis in different geographical
locations. Wafa plant for LNG – Mellitah, Libya
Polyolefins Complex - Nanhai,
China
INTERNATIONAL PRESENCE
4* June 2010
Maire Tecnimont presence
MANPOWER*
ITALIA
EUROPA
ASIA
SUD
AMERICA
TOTALE
2.619
353
1.942
167
5.081
5
GROUP’S STRUCTURE
Corporate
Initiatives
Engineering and
Main Contracting
Licensing and IP
group center
Renewable
energy
Process Engineering
Contractor
6
TECNIMONT OVERVIEW
Tecnimont is a global E&C player
 Integrated system of technological
services and installations in Oil, Gas &
Petrochemicals, Power, Infrastructure &
Civil Engineering
 Leader in managing large EPC projects
in different geographical locations.
 Recognized worldwide experience in
engineering and project management
TECNIMONT BUSINESS UNITS
7
Revenues
30.06.10
Backlog
30.06.10
45% 42% 13%
75% 13% 12%
Oil, Gas &
Petrochemicals
Infrastructure &
Civil Engineering
Power
The Group is a global E&C player that operates through its operating company Tecnimont on 4 business
units:
INFRASTRUCTURES
UNDERGROUNDS
RAILWAYS & HIGH
SPEED RAILWAYS
ROADS & HIGHWAYS
8
METRO EXPERIENCE
Tecnimont has been involved in different projects involving design and construction
of Manned and Automatic metro.
Project name Scope of work
Type of
contract
Value State of art
Turin Metro
Collegno - Porta
Nuova
System
Design and construction
FEED +
EPC – Turn key
210 M€ Completed
Rome Metro
B1 Line
Civil Works & System
Design and construction
Design & Build 330 M€ Design: completed
Works: under construction
Milan Metro
Red Line extension
Civil Works
Design and construction
Design & Build 122 M€ Completed
Turin Metro
Collegno - Porta
Nuova
System
Maintenance
Level 1, 2 & 3
Global Service
16 M€ Under execution
Turin Metro Ext.
Porta Nuova-
Lingotto
Civil Works
Design & Construction
General
Contractor
101 M€ Completed
Turin Metro Ext.
Porta Nuova-
Lingotto
System
Design & construction
FEED +
EPC – Turn key
70 M€ Design: completed
Works: under construction
9
Tecnimont integration activity on metros
Automation
Rolling stock
Track
Power Supply
Platform Doors
Operating Control CenterDepot/Workshop
Civil Works
INTEGRATION ACTIVITY
10
ITALIAN HIGH SPEED RAILWAY
11
HS RAILWAY TURIN - MILAN
MAIN PROBLEMS
• Interferencies with public
services
• Irrigation network and hydraulic
• The proximity of highway A4
Turin-Milan
• Relations with local autorities
• Environmental works
• Construction methodology of
main structures (precasting, etc.)
12
13
A
A A
Turin-Novara Section
DESIGN QUANTITIES
. 1200 PROJECTS
. 40.000 DELIVERABLES
Main Quantities
Bridges and viaducts
Commercial speed
Km
Km/h
21
300
Embankments Km 99
Cutting Km 2,5
Artificial tunnels km 2,5
Construction and rehabilitation of
new roads network
km 320
Construction of motorways km 22
Flyovers
Lenght
n.
km
76
22
Motorway Junctions n. 18
Service Areas n. 3
HS RAILWAY TURIN - MILAN
QUANTITIES
HS RAILWAY TURIN - MILAN
ENVIRONMENTAL ASPECTS
In environmental sensitive areas has been
foreseen mitigation measures, including
renaturation interventions in green area near
residential areas and in protected areas.
14
GLASS
STEEL
CONCRETE
WOOD
The design
The environmental simulation
The construction
HS RAILWAY TURIN - MILAN
NOISE REDUCTIONS
15
• Geology and
hydrogeology
• Tunnel design
• Technological
equipment, system
• Safety in tunnel
• Land management
HS RAILWAY BOLOGNA-FLORENCE
MAIN PROBLEMS
16
17
- DESIGN QUANTITIES
. 1250 PROJECTS
. 23.500 DELIVERABLES
Main Quantities
Line Length
+ railway interconnection
Commercial Speed
Bridges and viaducts
Embankments
Km
Km
Km/h
Km
Km
78.540
5.200
300
1,2
4
Cutting Km 0.50
Tunnels
(Traditional System Excavation section 120 m2
11.5m eq. int. Ø; TBM Service Tunnel 6m Ø,
length 600m)
Km 77.5
New road network (ordinary viability) km 110
HS RAILWAY BOLOGNA-FLORENCE
MAIN PROBLEMS
18
INFRASTRUCTURES: RAILWAYS
a – FUNCTIONALITY
- INTERVENTION ON OTHER INFRASTRUCTURES
- INTERACTION WITH LOCAL AUTHORITIES /APPROVAL
- CONCURRENCY BETWEEN RAILWAY AND MOTORWAY DESIGN
ACTIVITIES
b - INTEGRATION WITH OTHER INFRASTRUCTURES
- INTERFERED VIABILITY
- MOTORWAY JUNCTIONS
- RIVERS
- IRRIGATION SYSTEMS
MAIN ASPECTS CONSIDERED DURING THE DESIGN PHASE
c – SAFETY
- ACCESS ROAD FOR CIVIL PROTECTION
- CLIMBING BARRIER (“DUNE”)
- ANTIDAZZLING BARRIER
- TECHNICAL MONITORING
- RAILWAY SIGNALLING SYSTEM
d – ARCHITECTURE AND ENVIRONMENT
- TERRITORIAL INTEGRATION
- ANTROPIC IMPACT MINIMIZATION
- MITIGATION INTEGRATED PROJECTS (P.I.M.)
- RECLAMATION OF POTENTIALLY POLLUTED
SITES
- STRUCTURES ARCHITECTURE AND UNIFORMITY
19
Topography
Geology/Geotechnics
Hydraulic
Railwayalignment
Architecture
Specialstructures
Tunnels
Equipmentandsystem
Environment
HealthandSafety
Costing
Construction
Project Coordination activities 1
Project Coordination activities …n..
Final review of overall project
The basic technological approach traditionally adopted shall be integrated with a
multidisciplinary approach involving architecture and landscaping as essential components
of the project.
MULTIDISCIPLINARY APPROACH
GROWING DEMAND FOR UNDERGROUND TRANSPORT
 A rapid expansion of the cities, growing attention to
environmental issues, to higher comfort of housing
and in general to a better quality of life leads to the
utilization of more sophisticated design and
construction criteria, aimed at minimizing the impact
of existing and new infrastructures on people and
existing facilities.
 Cities are becoming larger and larger. The demand
for public transport is getting higher accordingly. At
the same time available above ground space is
getting smaller, due to limitations to traffic, more
green and pedestrian areas, etc.
 The only way to manage these two conflicting
scenarios is by maximizing the use of underground
mass transport.
20
Best practices in underground tunneling for high speed
lines and metros – Why go underground?
Fundamental characteristics of underground space :
 Underground medium is a space that can provide the setting for activities or infrastructures
that are difficult, impossible, environmentally undesirable or less profitable to install above
ground.
 Underground space offers a natural protection to whatever is placed underground.
 The containment created by undergound structures protects the surface environment from
the risks / disturbances inherents in certain types of activities.
 Underground space is opaque, an underground structure is only visible at the point(s)
where it connects to the surface.
Reasons for going underground :
 Land use and location reasons
 Isolation considerations
 Environmental protection
 Topographic reasons
 Social benefits
21
Best practices in underground tunneling for high speed
lines and metros – Why go underground?
GO UNDERGROUND FOR LAND USE AND LOCATION REASONS
Blaak Station (Rotterdam –ITA)Le Louvre (Paris –ITA)
22
GO UNDERGROUND FOR ISOLATION CONSIDERATIONS
 CLIMATE
 NATURAL DISASTERS AND EARTHQUAKE
 PROTECTION
 CONTAINAMENT
 SECURITY
Underground swimming pool (Finland -ITA)
Damage on building on top, no damages on the underground
shopping mall located below (KOBE -ITA)
Underground storage facilities (USA -ITA)
Best practices in underground tunneling for high speed
lines and metros – Why go underground?
23
GO UNDERGROUND FOR ENVIRONMENTAL PRESERVATION
Situation before and after the construction of the underground car park
A motorway tunnel forming a green bridge, providing a free range for
people, animals, and even vegetation.
Best practices in underground tunneling for high speed
lines and metros – Why go underground?
24
GO UNDERGROUND FOR TOPOGRAPHIC REASONS
BOLOGNA
FLORENCE
High speed railway Bologna-Florence (Italy) – LINE LENGTH: 78.5 km,
of which 73.3 km underground
Best practices in underground tunneling for high speed
lines and metros – Why go underground?
25
Best practices in underground tunneling for high speed
lines and metros – Why go underground?
GO UNDERGROUND FOR SOCIAL BENEFITS
Turin Metro – First driverless subway in Italy
Passante di Torino – Railway tunnels clear trains from surface, traffic
noise and vibrations are reduced and the surface street areas may
partially be used for other purposes.
BEFORE
AFTER
26
Best practices in underground tunneling for high speed
lines and metros – Current practice
CUT AND COVER
Trench excavation, tunnel construction and soil covering of excavated
tunnels are three major integral parts of the tunnelling method. The
method can accommodate changes in tunnel width and non-uniform
shapes and is often adopted in construction of stations.
Bulk excavation is often undertaken under a top slab to minimise
traffic disruption as well as environmental impacts in terms of dust and
noise emissions and visual impact.
This tunnelling method involves the use of explosives. Drilling rigs are
used to bore blast holes on the proposed tunnel surface to a designated
depth for blasting. Explosives and timed detonators are then placed in
the blast holes. Once blasting is carried out, waste rocks and soils are
transported out of the tunnel before further blasting. In soft soil some
mining equipments such as roadheaders and backhoes are commonly
used for the tunnel excavation. Adequate structural support measures
are required when adopting this method for tunnelling.
TRADITIONAL EXCAVATION (NATM, DRILL & BLAST)
Bored tunnelling by using a Tunnel Boring Machine (TBM) is often used
for excavating long tunnels. An effective TMB method requires the
selection of appropriate equipment for different rock mass and
geological conditions. Compared with the cut-and-cover approach,
disturbance to local traffic and associated environmental impacts would
be much reduced
MECHANIZED EXCAVATION
27
28
Best practices in underground tunneling for high speed
lines and metros – CUT AND COVER 1/4
1. Applying
Cement/Chemical
injection from ground to
make the stabilized
ground and
impermeable soil layers
before the construction
of diaphragms.
29
Best practices in underground tunneling for high speed
lines and metros – CUT AND COVER 2/4
2. Diaphragm
Constructions using
Grab or Hydromills
30
Best practices in underground tunneling for high speed
lines and metros – CUT AND COVER 3/4
3. Concrete casting of
roof slab
31
Best practices in underground tunneling for high speed
lines and metros – CUT AND COVER 4/4
4. During excavation,
cast in-situ concrete
roof/floor slabs were
used as lateral support
for the diaphragms
walls (downward
construction).
32
CUT AND COVER - Technological systems
33
Best practices in underground tunneling for high speed
lines and metros – TRADITIONAL EXCAVATION
Assess the geological-geotechnical context is fundamental for the project success.
In the case of Bologna-Florence we spent 84 €million (2% of project total cost) for the survey phase.
The Italian practice foresee a four stage process:
I. Survey phase DESIGN
II. Diagnosys phase DESIGN
III. Therapy phase DESIGN
IV. Monitoring phase CONSTRUCTION
34
DIAGNOSIS PHASE
HIGH SPEED RAILWAY SYSTEM
MILAN TO NAPOLI RAILWAY LINE * BOLOGNA TO FLORENCE SECTION
Best practices in underground tunneling for high speed
lines and metros – TRADITIONAL EXCAVATION
Using the acquired data
from survey phase, it’s
possible to predict the
behaviour of the rock in
response to excavation
Category A – 17%
Category B – 57%
Category C – 26%
35
THERAPY PHASE
HIGH SPEED RAILWAY SYSTEM
MILAN TO NAPOLI RAILWAY LINE * BOLOGNA TO FLORENCE SECTION
CONFINEMENT ACTIONPRECONFINEMENT ACTION
Best practices in underground tunneling for high speed
lines and metros – TRADITIONAL EXCAVATION
In the therapy phase we define the excavation
methods and the stabilisation measures to
obtain the stability of the cavity.
36
Best practices in underground tunneling for high speed
lines and metros – TRADITIONAL EXCAVATION
Once the design phase is complete,
during the construction phase using
monitoring it’s possible to check the
correctness of predictions made
during the previous phases; this
monitoring is carried out by
measuring and checking the
response of the medium to
escavation.
MONITORING PHASE
Advance rates were very costant,
thus indicating a excellent match
between design and the actual
reality encountered
Best practices in underground tunneling for high speed
lines and metros – TRADITIONAL EXCAVATION
37
Best practices in underground tunneling for high speed
lines and metros – TRADITIONAL EXCAVATION
38
Best practices in underground tunneling for high speed
lines and metros – TRADITIONAL EXCAVATION
39
40
Best practices in underground tunneling for high speed
lines and metros – TRADITIONAL EXCAVATION
Best practices in underground tunneling for high speed
lines and metros – TRADITIONAL EXCAVATION
41
Best practices in underground tunneling for high speed
lines and metros – TRADITIONAL EXCAVATION
42
43
TRADITIONAL EXCAVATIONS- Technological systems 1/6
Tunnel face extrusion and failure
44
TRADITIONAL EXCAVATIONS- Technological systems 2/6
45
TRADITIONAL EXCAVATIONS- Technological systems 3/6
FOREPOLING
CROWN WEAKNESS
46
TRADITIONAL EXCAVATIONS- Technological systems 4/6
47
TRADITIONAL EXCAVATIONS- Technological systems 5/6
Depending on soil conditions,
we can use different kind of
equipment.
48
TRADITIONAL EXCAVATIONS- Technological systems 6/6
Shotcrete + steel net
Shotcrete + fibers:
Steel fibers
Polyester fibers
Polypropylene fibers
Synthetic fibers (general polymers)
MECHANIZED EXCAVATIONS
49
Rock TBM EPB-S
(Earth Pressure Balanced Shield)
Slurry Shield
50
Mechanized excavation : Basic principles
The Earth Pressure Balanced (EPB) tunnelling method owns it’s name
from the way the front face of the TBM is supported during excavation,
using earth pressure. The principles of the EPB-tunnelling method can
described as follows (Kanayasu, Yamamoto and Kitahara, 1995):
• The soil is excavated by rotating cutter heads;
• The excavated soil is mechanically agitated and fills the face and an
excavation chamber.;
• Using the thrust of the shield machine, by means of hydraulic jacks,
the excavated soil is pressurized to stabilize the excavation front (force
equilibrium);
• Control of the soil pressure in the chamber is done by adjusting the
amount of soil discharged through the screw conveyor or other soil
removal devices and the amount of soil excavated to counterbalance
earth and groundwater pressure (volume equilibrium);
• The excavated soil in the chamber and the screw conveyors work as
a water seal.
The earth pressure support method is generally used in cohesive soils,
enabling it to be used as a supporting medium itself, with the use of
conditioning materials if necessary.
A
MECHANIZED EXCAVATIONS
51
PENETRATION RATE [mm/min]
PRESSURE SENSORS [Bar]
SCREW CONVEYOR RATE [rpm]
Excavation parameters control
The main parameters, to be verified via the sensors and sensing
equipment, are:
 Face-support pressure
 Pressure and volume of the backfill grout of the annular void
 Weight of the extracted material
Pressure sensors
MECHANIZED EXCAVATIONS
Conventional Tunnelling Vs TBM Tunnelling
52
Conventional tunnelling is more cost effective
than mechanized tunnelling for the cases of short
tunnels (< 2.4 km), shafts and tunnels with
changing geometry, and/or substantially changing
geotechnical behaviour. There is an overlapped
area where hand and mechanical mining may be
equally considered and where a dual design is
recommended. With tunnels longer than 3.2 km,
the mechanized tunnelling becomes to be more
economic than conventional tunnelling.
(Sauer, 2004)
Each technique have advantages and
disadvantages; the right choice must be done
according to specific context (soil, cover, etc..)
and on the basis of the boundary conditions
(environmental rules, stakeholder, etc)
Best practices in underground tunneling for high speed
lines and metros – Risk management 1/5
Tunnelling is not a risk-free technology, each tunnel is a specific unique project on its own in a
unique combination of ground / soil. The “right” construction method with the “right” experience
parties involved are crucial for the success. The main most important factor however, the geology, is only
known to a limited extent. Any accident during construction as well as in use provokes a substantial
interruption and often a standstill till the problems are solved.
Risk has two components: probability of occurrence W
and amount of damage D.
The different steps of the process are:
 Identification of the risks (initial one);
 Reduction of the initial risk working on the impact
and/or possibility of occurrence of an event (i.e.
provisional building works, choice of the machinery,
control of the TBM head pression);
 Management of the residual risk (i.e. monitoring).
Residual risks are unavoidable and they should be
shared among the Parties and systematically
controlled by countermeasures.
53
A recommended strategy is to carry out construction risk assessments at each stage of
design and construction in accordance with the information available and the decisions to
be taken or revised at each stage.
Any risk management strategy should include:
 Definition of the risk management responsibilities of the various parties involved
(different departments within the owners organisation, consultants, contractors);
 Short description of the activities to be carried out at different stages of the project in
order to achieve the objectives;
 Scheme to be used for follow-up on results obtained through the risk management
activities by which information about identified hazards (nature and significance) is freely
available;
 Follow-up on initial assumptions regarding the operational phase;
 Monitoring, audit and review procedures.
Best practices in underground tunneling for high speed
lines and metros – Risk management 2/5
54
55
The problem associated with underground construction is that the excavations will alter the
stress fields in the ground around the tunnels and deformations will occur. If these
deformations are not strictly controlled during the construction process, excessive ground
movements will propagate upwards potentially causing significant damage to adjacent buried
infrastructure and surface structures.
Using established methods of analysis of ground movement it’s possible to identify buildings
potentially at risk. For those buildings were planned soil improvements to avoid excessive
movements of its foundations.
Reduction of the initial risk
Project Hypothesis Detailed design Execution
Best practices in underground tunneling for high speed
lines and metros – Risk management 3/5
56
Best practices in underground tunneling for high speed
lines and metros – Risk management 4/5
The residual risk, have to be managed during the constructive phases by means of the
implementation of an integrated monitoring system to:
 Guarantee the correct flow of information to permit designers to analyse and verify the
hypothesis used to develop the basic design;
 Allows to understand the atypical phenomena giving the information necessary to solve
the problem.
The project must define two parameters
which identify the “attention” and
“alarm” levels.
 Attention level activates a specific
control system in order to reach a more
specific following of the event.
Alarm level requires the adoption of
the counter-measures specifically
studied for the event.
Topographical controls on buildings
Example of monitoring during the excavation of part of the work adjacent to the buildings:
Automatic monitoring with electrolevels.
The distortions measured during the
excavation phase were lower than the
trigger limits defined during the design
phase.
Best practices in underground tunneling for high speed
lines and metros – Risk management 5/5
57
58
 The basic technological approach traditionally adopted for infrastructure projects shall be
integrated with a multidisciplinary approach that considers all the processes of the entire
cycle of life and performance of the works. This integrated approach would allow different
disciplines to interact and mutually stimulate the development of a fully comprehensive
infrastructure, as required in the present global scenario.
 Nowadays architecture and landscaping are essential components of the project,
the natural system and infrastructure system have an interplay that can be referred as very
“sensitive”; the disturbance in one of these systems has a way of spreading to the other. To
avoid this problem often the solution is found in underground infrastructures. These
are, in fact, one of the best solutions for sustainable solutions for integrating utilities and
transportation infrastructures within environments with social, technical or other natures
difficult interfaces (such as urban areas, mountains, etc).
 Today, the modern technological systems allow us to build faster tunnel and
underground structures using different solutions in every kind of soil, and the monitoring
systems allow us to control in real time the situation. These technologies can be very
useful to optimize performance and safety.
All these aspects have been studied in detail and put successfully into practice by
Tecnimont during the realization of underground infrastructures in highly urbanized cities as
well in highways and high speed railways.
CONCLUSIONS
59
Rome
Via di Vannina, 88/94
00156 Rome
P +39 06 4122 351
F +39 06 4122 35610
Milan
Viale Monte Grappa, 3
20124 Milan
P +39 02 6313.1
F +39 02 6313.9052
Turin
Corso Ferrucci, 112/a
10138 Turin
P +39 011 0056111
F+39 011 0056444
info@mairetecnimont.it – www.mairetecnimont.it

Mais conteúdo relacionado

Mais procurados

Building Construction 7. construction site
Building Construction 7. construction siteBuilding Construction 7. construction site
Building Construction 7. construction siteHamdija Velagic
 
Constructionmethodologyandprojectmanagementreport
ConstructionmethodologyandprojectmanagementreportConstructionmethodologyandprojectmanagementreport
ConstructionmethodologyandprojectmanagementreportDivyesh Mungara
 
Lesson3 tunnel design
Lesson3 tunnel designLesson3 tunnel design
Lesson3 tunnel designhaziq42
 
Diploma(civil) sem i boce_unit 3_building construction a
Diploma(civil) sem i boce_unit 3_building construction aDiploma(civil) sem i boce_unit 3_building construction a
Diploma(civil) sem i boce_unit 3_building construction aRai University
 
Tunnel example for road project by Malyar Talash
Tunnel example for road project by Malyar TalashTunnel example for road project by Malyar Talash
Tunnel example for road project by Malyar TalashMalyar Talash
 
Dissertation on skyscrapers the high-rise structures
Dissertation on skyscrapers   the high-rise structuresDissertation on skyscrapers   the high-rise structures
Dissertation on skyscrapers the high-rise structuresSenthilnathan Kalidas
 
Building Construction 1 Project 1 2016
Building Construction 1 Project 1 2016Building Construction 1 Project 1 2016
Building Construction 1 Project 1 2016Mirza Qayyum
 
H igh rise-01-introduction
H igh rise-01-introductionH igh rise-01-introduction
H igh rise-01-introductiontharwat sakr
 
Bcon revised
Bcon revisedBcon revised
Bcon revisedKen Wong
 
Past Bridges Middle East Presentation from Ministry of Public Works and Housi...
Past Bridges Middle East Presentation from Ministry of Public Works and Housi...Past Bridges Middle East Presentation from Ministry of Public Works and Housi...
Past Bridges Middle East Presentation from Ministry of Public Works and Housi...OliviaModisakeng
 
Building Construction: Experiencing Construction
Building Construction: Experiencing ConstructionBuilding Construction: Experiencing Construction
Building Construction: Experiencing ConstructionJoyce Wee
 
150316 high rise design
150316 high rise design150316 high rise design
150316 high rise designTieng Wei
 

Mais procurados (15)

Building Construction 7. construction site
Building Construction 7. construction siteBuilding Construction 7. construction site
Building Construction 7. construction site
 
Constructionmethodologyandprojectmanagementreport
ConstructionmethodologyandprojectmanagementreportConstructionmethodologyandprojectmanagementreport
Constructionmethodologyandprojectmanagementreport
 
Lesson3 tunnel design
Lesson3 tunnel designLesson3 tunnel design
Lesson3 tunnel design
 
Diploma(civil) sem i boce_unit 3_building construction a
Diploma(civil) sem i boce_unit 3_building construction aDiploma(civil) sem i boce_unit 3_building construction a
Diploma(civil) sem i boce_unit 3_building construction a
 
Tunnel example for road project by Malyar Talash
Tunnel example for road project by Malyar TalashTunnel example for road project by Malyar Talash
Tunnel example for road project by Malyar Talash
 
Dissertation on skyscrapers the high-rise structures
Dissertation on skyscrapers   the high-rise structuresDissertation on skyscrapers   the high-rise structures
Dissertation on skyscrapers the high-rise structures
 
Building Construction 1 Project 1 2016
Building Construction 1 Project 1 2016Building Construction 1 Project 1 2016
Building Construction 1 Project 1 2016
 
H igh rise-01-introduction
H igh rise-01-introductionH igh rise-01-introduction
H igh rise-01-introduction
 
Bcon revised
Bcon revisedBcon revised
Bcon revised
 
Ct tutorial 2
Ct tutorial 2Ct tutorial 2
Ct tutorial 2
 
Past Bridges Middle East Presentation from Ministry of Public Works and Housi...
Past Bridges Middle East Presentation from Ministry of Public Works and Housi...Past Bridges Middle East Presentation from Ministry of Public Works and Housi...
Past Bridges Middle East Presentation from Ministry of Public Works and Housi...
 
Building Construction: Experiencing Construction
Building Construction: Experiencing ConstructionBuilding Construction: Experiencing Construction
Building Construction: Experiencing Construction
 
150316 high rise design
150316 high rise design150316 high rise design
150316 high rise design
 
Pipe Jacking
Pipe JackingPipe Jacking
Pipe Jacking
 
presentation ON TALL BUILDING
 presentation ON TALL BUILDING presentation ON TALL BUILDING
presentation ON TALL BUILDING
 

Destaque

Soil arching in granular soil
Soil arching in granular soilSoil arching in granular soil
Soil arching in granular soilJithu G Francis
 
Tunnel Boring Machines (TBM)
Tunnel Boring Machines (TBM)Tunnel Boring Machines (TBM)
Tunnel Boring Machines (TBM)Hamed Zarei
 
Pietilä: Move! Fyysisen toimintakyvyn seurantajärjestelmä
Pietilä: Move! Fyysisen toimintakyvyn seurantajärjestelmäPietilä: Move! Fyysisen toimintakyvyn seurantajärjestelmä
Pietilä: Move! Fyysisen toimintakyvyn seurantajärjestelmäKouluterveyskysely
 
Udział w badaniach w celu walki z miaŝdŝycą
Udział w badaniach w celu walki z miaŝdŝycąUdział w badaniach w celu walki z miaŝdŝycą
Udział w badaniach w celu walki z miaŝdŝycąXplore Health
 
X commerce open stack beijing keynote - 2012-08-10 final
X commerce   open stack beijing keynote - 2012-08-10 finalX commerce   open stack beijing keynote - 2012-08-10 final
X commerce open stack beijing keynote - 2012-08-10 finalOpenCity Community
 
Kivimäki: Kouluterveyskysely
Kivimäki: Kouluterveyskysely Kivimäki: Kouluterveyskysely
Kivimäki: Kouluterveyskysely Kouluterveyskysely
 
Wind Lift Brochure Web
Wind Lift Brochure   WebWind Lift Brochure   Web
Wind Lift Brochure Webgm330
 
MARI KITA SUKSESKAN PROGRAM INDONESIA PINTAR
MARI KITA SUKSESKAN PROGRAM INDONESIA PINTARMARI KITA SUKSESKAN PROGRAM INDONESIA PINTAR
MARI KITA SUKSESKAN PROGRAM INDONESIA PINTARRezha Purbaya
 
1.phan 1.cac buoc thuc hiep hd mua ban qt
1.phan 1.cac buoc thuc hiep hd mua ban qt1.phan 1.cac buoc thuc hiep hd mua ban qt
1.phan 1.cac buoc thuc hiep hd mua ban qtThuy Thanh
 
Basic conversation 4
Basic conversation 4Basic conversation 4
Basic conversation 4Les Davy
 
Sibanda A tale of two peoples the influence of race relations on agricultur...
Sibanda A tale of two peoples   the influence of race relations on agricultur...Sibanda A tale of two peoples   the influence of race relations on agricultur...
Sibanda A tale of two peoples the influence of race relations on agricultur...futureagricultures
 

Destaque (20)

Soil arching in granular soil
Soil arching in granular soilSoil arching in granular soil
Soil arching in granular soil
 
Tunnel Boring Machines
Tunnel Boring Machines  Tunnel Boring Machines
Tunnel Boring Machines
 
Tunnel Boring Machines (TBM)
Tunnel Boring Machines (TBM)Tunnel Boring Machines (TBM)
Tunnel Boring Machines (TBM)
 
Drip fund
Drip fundDrip fund
Drip fund
 
Hello
HelloHello
Hello
 
Pietilä: Move! Fyysisen toimintakyvyn seurantajärjestelmä
Pietilä: Move! Fyysisen toimintakyvyn seurantajärjestelmäPietilä: Move! Fyysisen toimintakyvyn seurantajärjestelmä
Pietilä: Move! Fyysisen toimintakyvyn seurantajärjestelmä
 
Udział w badaniach w celu walki z miaŝdŝycą
Udział w badaniach w celu walki z miaŝdŝycąUdział w badaniach w celu walki z miaŝdŝycą
Udział w badaniach w celu walki z miaŝdŝycą
 
X commerce open stack beijing keynote - 2012-08-10 final
X commerce   open stack beijing keynote - 2012-08-10 finalX commerce   open stack beijing keynote - 2012-08-10 final
X commerce open stack beijing keynote - 2012-08-10 final
 
Kivimäki: Kouluterveyskysely
Kivimäki: Kouluterveyskysely Kivimäki: Kouluterveyskysely
Kivimäki: Kouluterveyskysely
 
Wind Lift Brochure Web
Wind Lift Brochure   WebWind Lift Brochure   Web
Wind Lift Brochure Web
 
IOS
IOSIOS
IOS
 
MARI KITA SUKSESKAN PROGRAM INDONESIA PINTAR
MARI KITA SUKSESKAN PROGRAM INDONESIA PINTARMARI KITA SUKSESKAN PROGRAM INDONESIA PINTAR
MARI KITA SUKSESKAN PROGRAM INDONESIA PINTAR
 
1.phan 1.cac buoc thuc hiep hd mua ban qt
1.phan 1.cac buoc thuc hiep hd mua ban qt1.phan 1.cac buoc thuc hiep hd mua ban qt
1.phan 1.cac buoc thuc hiep hd mua ban qt
 
Basic conversation 4
Basic conversation 4Basic conversation 4
Basic conversation 4
 
Mullen SXSW Themes
Mullen SXSW ThemesMullen SXSW Themes
Mullen SXSW Themes
 
Transport Layer
Transport LayerTransport Layer
Transport Layer
 
Sibanda A tale of two peoples the influence of race relations on agricultur...
Sibanda A tale of two peoples   the influence of race relations on agricultur...Sibanda A tale of two peoples   the influence of race relations on agricultur...
Sibanda A tale of two peoples the influence of race relations on agricultur...
 
Holy cow!!!
Holy cow!!!Holy cow!!!
Holy cow!!!
 
Стратегия развития фонда
Стратегия развития фондаСтратегия развития фонда
Стратегия развития фонда
 
Crowdvibe Mobile App
Crowdvibe Mobile AppCrowdvibe Mobile App
Crowdvibe Mobile App
 

Semelhante a METRO RAIL ASIA 2010

Politecnico of Turin Presentation - 29 May 2014
Politecnico of Turin Presentation - 29 May 2014Politecnico of Turin Presentation - 29 May 2014
Politecnico of Turin Presentation - 29 May 2014Ignazio Dogliani
 
Snr. civil eng. ibrahim hamdan
Snr. civil eng. ibrahim hamdan  Snr. civil eng. ibrahim hamdan
Snr. civil eng. ibrahim hamdan Ibrahim hamdan
 
Communications Based Train Control Conference London March 12 2014
Communications Based Train Control Conference London March 12 2014 Communications Based Train Control Conference London March 12 2014
Communications Based Train Control Conference London March 12 2014 James Nesbitt
 
The Millau Viaduct Project - An Engineering Marvel
The Millau Viaduct Project - An Engineering MarvelThe Millau Viaduct Project - An Engineering Marvel
The Millau Viaduct Project - An Engineering MarvelShivam Sood
 
WaterKE2019 conference - Session 1 - Christophe Leroux: CEA
WaterKE2019 conference - Session 1 - Christophe Leroux: CEAWaterKE2019 conference - Session 1 - Christophe Leroux: CEA
WaterKE2019 conference - Session 1 - Christophe Leroux: CEAWater Europe
 
Event Fuel Cells & Hydrogen | Campus Automobile Spa-Francorchamps - 02 octobr...
Event Fuel Cells & Hydrogen | Campus Automobile Spa-Francorchamps - 02 octobr...Event Fuel Cells & Hydrogen | Campus Automobile Spa-Francorchamps - 02 octobr...
Event Fuel Cells & Hydrogen | Campus Automobile Spa-Francorchamps - 02 octobr...Cluster TWEED
 
Typical challenges in tunnelling
Typical challenges in tunnellingTypical challenges in tunnelling
Typical challenges in tunnellingAntti Nykänen
 
Project Planning and Management of Millau Viaduct Bridge, France
Project Planning and Management of Millau Viaduct Bridge, FranceProject Planning and Management of Millau Viaduct Bridge, France
Project Planning and Management of Millau Viaduct Bridge, FranceRakibul Hasan,MEng,EIT
 
Resume_Rémi_Baneras_Site_Engineer_1207
Resume_Rémi_Baneras_Site_Engineer_1207Resume_Rémi_Baneras_Site_Engineer_1207
Resume_Rémi_Baneras_Site_Engineer_1207Rémi BANERAS
 
Bouygues Travaux Publics_Corporate Presentation
Bouygues Travaux Publics_Corporate PresentationBouygues Travaux Publics_Corporate Presentation
Bouygues Travaux Publics_Corporate PresentationPierre HUBERT
 
Innovation, research and development of road equipments
Innovation, research and development of road equipmentsInnovation, research and development of road equipments
Innovation, research and development of road equipmentsguestecb523
 
About Strukton
About StruktonAbout Strukton
About StruktonStrukton
 

Semelhante a METRO RAIL ASIA 2010 (20)

Politecnico of Turin Presentation - 29 May 2014
Politecnico of Turin Presentation - 29 May 2014Politecnico of Turin Presentation - 29 May 2014
Politecnico of Turin Presentation - 29 May 2014
 
Snr. civil eng. ibrahim hamdan
Snr. civil eng. ibrahim hamdan  Snr. civil eng. ibrahim hamdan
Snr. civil eng. ibrahim hamdan
 
Communications Based Train Control Conference London March 12 2014
Communications Based Train Control Conference London March 12 2014 Communications Based Train Control Conference London March 12 2014
Communications Based Train Control Conference London March 12 2014
 
The Millau Viaduct Project - An Engineering Marvel
The Millau Viaduct Project - An Engineering MarvelThe Millau Viaduct Project - An Engineering Marvel
The Millau Viaduct Project - An Engineering Marvel
 
Tekla Global BIM Awards 2015
Tekla Global BIM Awards 2015Tekla Global BIM Awards 2015
Tekla Global BIM Awards 2015
 
gerdien
gerdiengerdien
gerdien
 
WaterKE2019 conference - Session 1 - Christophe Leroux: CEA
WaterKE2019 conference - Session 1 - Christophe Leroux: CEAWaterKE2019 conference - Session 1 - Christophe Leroux: CEA
WaterKE2019 conference - Session 1 - Christophe Leroux: CEA
 
Event Fuel Cells & Hydrogen | Campus Automobile Spa-Francorchamps - 02 octobr...
Event Fuel Cells & Hydrogen | Campus Automobile Spa-Francorchamps - 02 octobr...Event Fuel Cells & Hydrogen | Campus Automobile Spa-Francorchamps - 02 octobr...
Event Fuel Cells & Hydrogen | Campus Automobile Spa-Francorchamps - 02 octobr...
 
Typical challenges in tunnelling
Typical challenges in tunnellingTypical challenges in tunnelling
Typical challenges in tunnelling
 
ec_rtd_cl4-destination-4.pdf
ec_rtd_cl4-destination-4.pdfec_rtd_cl4-destination-4.pdf
ec_rtd_cl4-destination-4.pdf
 
Project Planning and Management of Millau Viaduct Bridge, France
Project Planning and Management of Millau Viaduct Bridge, FranceProject Planning and Management of Millau Viaduct Bridge, France
Project Planning and Management of Millau Viaduct Bridge, France
 
Resume_Rémi_Baneras_Site_Engineer_1207
Resume_Rémi_Baneras_Site_Engineer_1207Resume_Rémi_Baneras_Site_Engineer_1207
Resume_Rémi_Baneras_Site_Engineer_1207
 
2019-10-02_presentations_Opportunities for SMEs in Horizon2020_Side_Event
2019-10-02_presentations_Opportunities for SMEs in Horizon2020_Side_Event2019-10-02_presentations_Opportunities for SMEs in Horizon2020_Side_Event
2019-10-02_presentations_Opportunities for SMEs in Horizon2020_Side_Event
 
Bouygues Travaux Publics_Corporate Presentation
Bouygues Travaux Publics_Corporate PresentationBouygues Travaux Publics_Corporate Presentation
Bouygues Travaux Publics_Corporate Presentation
 
Innovation, research and development of road equipments
Innovation, research and development of road equipmentsInnovation, research and development of road equipments
Innovation, research and development of road equipments
 
Materials science, innovation and industry.
Materials science, innovation and industry.Materials science, innovation and industry.
Materials science, innovation and industry.
 
Mohamed HENDI CV
Mohamed HENDI CVMohamed HENDI CV
Mohamed HENDI CV
 
Resume_Fernando_2016
Resume_Fernando_2016Resume_Fernando_2016
Resume_Fernando_2016
 
KWKCV16
KWKCV16KWKCV16
KWKCV16
 
About Strukton
About StruktonAbout Strukton
About Strukton
 

Último

Ethical stalking by Mark Williams. UpliftLive 2024
Ethical stalking by Mark Williams. UpliftLive 2024Ethical stalking by Mark Williams. UpliftLive 2024
Ethical stalking by Mark Williams. UpliftLive 2024Winbusinessin
 
Live-Streaming in the Music Industry Webinar
Live-Streaming in the Music Industry WebinarLive-Streaming in the Music Industry Webinar
Live-Streaming in the Music Industry WebinarNathanielSchmuck
 
Michael Vidyakin: Introduction to PMO (UA)
Michael Vidyakin: Introduction to PMO (UA)Michael Vidyakin: Introduction to PMO (UA)
Michael Vidyakin: Introduction to PMO (UA)Lviv Startup Club
 
Chicago Medical Malpractice Lawyer Chicago Medical Malpractice Lawyer.pdf
Chicago Medical Malpractice Lawyer Chicago Medical Malpractice Lawyer.pdfChicago Medical Malpractice Lawyer Chicago Medical Malpractice Lawyer.pdf
Chicago Medical Malpractice Lawyer Chicago Medical Malpractice Lawyer.pdfSourav Sikder
 
To Create Your Own Wig Online To Create Your Own Wig Online
To Create Your Own Wig Online  To Create Your Own Wig OnlineTo Create Your Own Wig Online  To Create Your Own Wig Online
To Create Your Own Wig Online To Create Your Own Wig Onlinelng ths
 
TalentView Webinar: Empowering the Modern Workforce_ Redefininig Success from...
TalentView Webinar: Empowering the Modern Workforce_ Redefininig Success from...TalentView Webinar: Empowering the Modern Workforce_ Redefininig Success from...
TalentView Webinar: Empowering the Modern Workforce_ Redefininig Success from...TalentView
 
NASA CoCEI Scaling Strategy - November 2023
NASA CoCEI Scaling Strategy - November 2023NASA CoCEI Scaling Strategy - November 2023
NASA CoCEI Scaling Strategy - November 2023Steve Rader
 
Mihir Menda - Member of Supervisory Board at RMZ
Mihir Menda - Member of Supervisory Board at RMZMihir Menda - Member of Supervisory Board at RMZ
Mihir Menda - Member of Supervisory Board at RMZKanakChauhan5
 
Borderless Access - Global B2B Panel book-unlock 2024
Borderless Access - Global B2B Panel book-unlock 2024Borderless Access - Global B2B Panel book-unlock 2024
Borderless Access - Global B2B Panel book-unlock 2024Borderless Access
 
Data skills for Agile Teams- Killing story points
Data skills for Agile Teams- Killing story pointsData skills for Agile Teams- Killing story points
Data skills for Agile Teams- Killing story pointsyasinnathani
 
NewBase 25 March 2024 Energy News issue - 1710 by Khaled Al Awadi_compress...
NewBase  25 March  2024  Energy News issue - 1710 by Khaled Al Awadi_compress...NewBase  25 March  2024  Energy News issue - 1710 by Khaled Al Awadi_compress...
NewBase 25 March 2024 Energy News issue - 1710 by Khaled Al Awadi_compress...Khaled Al Awadi
 
PDT 88 - 4 million seed - Seed - Protecto.pdf
PDT 88 - 4 million seed - Seed - Protecto.pdfPDT 88 - 4 million seed - Seed - Protecto.pdf
PDT 88 - 4 million seed - Seed - Protecto.pdfHajeJanKamps
 
Q2 2024 APCO Geopolitical Radar - The Global Operating Environment for Business
Q2 2024 APCO Geopolitical Radar - The Global Operating Environment for BusinessQ2 2024 APCO Geopolitical Radar - The Global Operating Environment for Business
Q2 2024 APCO Geopolitical Radar - The Global Operating Environment for BusinessAPCO
 
Tata Kelola Bisnis perushaan yang bergerak
Tata Kelola Bisnis perushaan yang bergerakTata Kelola Bisnis perushaan yang bergerak
Tata Kelola Bisnis perushaan yang bergerakEditores1
 
Project Brief & Information Architecture Report
Project Brief & Information Architecture ReportProject Brief & Information Architecture Report
Project Brief & Information Architecture Reportamberjiles31
 
Graham and Doddsville - Issue 1 - Winter 2006 (1).pdf
Graham and Doddsville - Issue 1 - Winter 2006 (1).pdfGraham and Doddsville - Issue 1 - Winter 2006 (1).pdf
Graham and Doddsville - Issue 1 - Winter 2006 (1).pdfAnhNguyen97152
 
Entrepreneurship & organisations: influences and organizations
Entrepreneurship & organisations: influences and organizationsEntrepreneurship & organisations: influences and organizations
Entrepreneurship & organisations: influences and organizationsP&CO
 
Borderless Access - Global Panel book-unlock 2024
Borderless Access - Global Panel book-unlock 2024Borderless Access - Global Panel book-unlock 2024
Borderless Access - Global Panel book-unlock 2024Borderless Access
 
Fabric RFID Wristbands in Ireland for Events and Festivals
Fabric RFID Wristbands in Ireland for Events and FestivalsFabric RFID Wristbands in Ireland for Events and Festivals
Fabric RFID Wristbands in Ireland for Events and FestivalsWristbands Ireland
 

Último (20)

Ethical stalking by Mark Williams. UpliftLive 2024
Ethical stalking by Mark Williams. UpliftLive 2024Ethical stalking by Mark Williams. UpliftLive 2024
Ethical stalking by Mark Williams. UpliftLive 2024
 
Live-Streaming in the Music Industry Webinar
Live-Streaming in the Music Industry WebinarLive-Streaming in the Music Industry Webinar
Live-Streaming in the Music Industry Webinar
 
Michael Vidyakin: Introduction to PMO (UA)
Michael Vidyakin: Introduction to PMO (UA)Michael Vidyakin: Introduction to PMO (UA)
Michael Vidyakin: Introduction to PMO (UA)
 
Chicago Medical Malpractice Lawyer Chicago Medical Malpractice Lawyer.pdf
Chicago Medical Malpractice Lawyer Chicago Medical Malpractice Lawyer.pdfChicago Medical Malpractice Lawyer Chicago Medical Malpractice Lawyer.pdf
Chicago Medical Malpractice Lawyer Chicago Medical Malpractice Lawyer.pdf
 
To Create Your Own Wig Online To Create Your Own Wig Online
To Create Your Own Wig Online  To Create Your Own Wig OnlineTo Create Your Own Wig Online  To Create Your Own Wig Online
To Create Your Own Wig Online To Create Your Own Wig Online
 
Investment Opportunity for Thailand's Automotive & EV Industries
Investment Opportunity for Thailand's Automotive & EV IndustriesInvestment Opportunity for Thailand's Automotive & EV Industries
Investment Opportunity for Thailand's Automotive & EV Industries
 
TalentView Webinar: Empowering the Modern Workforce_ Redefininig Success from...
TalentView Webinar: Empowering the Modern Workforce_ Redefininig Success from...TalentView Webinar: Empowering the Modern Workforce_ Redefininig Success from...
TalentView Webinar: Empowering the Modern Workforce_ Redefininig Success from...
 
NASA CoCEI Scaling Strategy - November 2023
NASA CoCEI Scaling Strategy - November 2023NASA CoCEI Scaling Strategy - November 2023
NASA CoCEI Scaling Strategy - November 2023
 
Mihir Menda - Member of Supervisory Board at RMZ
Mihir Menda - Member of Supervisory Board at RMZMihir Menda - Member of Supervisory Board at RMZ
Mihir Menda - Member of Supervisory Board at RMZ
 
Borderless Access - Global B2B Panel book-unlock 2024
Borderless Access - Global B2B Panel book-unlock 2024Borderless Access - Global B2B Panel book-unlock 2024
Borderless Access - Global B2B Panel book-unlock 2024
 
Data skills for Agile Teams- Killing story points
Data skills for Agile Teams- Killing story pointsData skills for Agile Teams- Killing story points
Data skills for Agile Teams- Killing story points
 
NewBase 25 March 2024 Energy News issue - 1710 by Khaled Al Awadi_compress...
NewBase  25 March  2024  Energy News issue - 1710 by Khaled Al Awadi_compress...NewBase  25 March  2024  Energy News issue - 1710 by Khaled Al Awadi_compress...
NewBase 25 March 2024 Energy News issue - 1710 by Khaled Al Awadi_compress...
 
PDT 88 - 4 million seed - Seed - Protecto.pdf
PDT 88 - 4 million seed - Seed - Protecto.pdfPDT 88 - 4 million seed - Seed - Protecto.pdf
PDT 88 - 4 million seed - Seed - Protecto.pdf
 
Q2 2024 APCO Geopolitical Radar - The Global Operating Environment for Business
Q2 2024 APCO Geopolitical Radar - The Global Operating Environment for BusinessQ2 2024 APCO Geopolitical Radar - The Global Operating Environment for Business
Q2 2024 APCO Geopolitical Radar - The Global Operating Environment for Business
 
Tata Kelola Bisnis perushaan yang bergerak
Tata Kelola Bisnis perushaan yang bergerakTata Kelola Bisnis perushaan yang bergerak
Tata Kelola Bisnis perushaan yang bergerak
 
Project Brief & Information Architecture Report
Project Brief & Information Architecture ReportProject Brief & Information Architecture Report
Project Brief & Information Architecture Report
 
Graham and Doddsville - Issue 1 - Winter 2006 (1).pdf
Graham and Doddsville - Issue 1 - Winter 2006 (1).pdfGraham and Doddsville - Issue 1 - Winter 2006 (1).pdf
Graham and Doddsville - Issue 1 - Winter 2006 (1).pdf
 
Entrepreneurship & organisations: influences and organizations
Entrepreneurship & organisations: influences and organizationsEntrepreneurship & organisations: influences and organizations
Entrepreneurship & organisations: influences and organizations
 
Borderless Access - Global Panel book-unlock 2024
Borderless Access - Global Panel book-unlock 2024Borderless Access - Global Panel book-unlock 2024
Borderless Access - Global Panel book-unlock 2024
 
Fabric RFID Wristbands in Ireland for Events and Festivals
Fabric RFID Wristbands in Ireland for Events and FestivalsFabric RFID Wristbands in Ireland for Events and Festivals
Fabric RFID Wristbands in Ireland for Events and Festivals
 

METRO RAIL ASIA 2010

  • 1. Giorgio Fantauzzi Project Leader Tecnimont (Maire Tecnimont Group) ADVANCING AN INTEGRATED APPROACH IN PLANNING AND BUILDING INFRASTRUCTURE PROJECTS SUCH AS METROS AND HIGH SPEED RAILWAYS METRORAIL 2010 Asia New Delhi, 25 - 27 October 2010
  • 2. ABSTRACT • A comprehensive planning process to identify and address potential challenges • Best practices in underground tunneling for railways and high speed railways • Technological systems for optimal performance and safety Mr GIORGIO FANTAUZZI’s CAREER SUMMARY Project Leader, Tecnimont S.p.A (Maire Tecnimont Group) Giorgio Fantauzzi is a Project Leader within the Tecnimont engineering department. He developed his experience by working intensively on various projects, ranging from highways to high speed railways and metros (Highway “Variante di Valico”, High Speed Railway “Bologna-Firenze”, Turin Metro, Rome Metro). He transferred his knowledge to other projects as well as specialised universities courses, conferences and training courses. Now he manages the design phase on different infrastructures project, using and coordinating several specialist on different matters. Advancing an integrated approach in planning and building infrastructure projects such as metros and high-speed railways 2
  • 3. 3 CORPORATE PROFILE The Group combines high quality and planning standards with a focus on multicultural and environmental issues. With a workforce of about 5,100 employees, more than half of whom outside Italy, at 30 June 2010 Maire Tecnimont reported revenues of 1112 million Euro and a backlog of about 6,151 million Euro. CC Plant - Ibritè, Brazil Maire Tecnimont is a leading Engineering and Construction Group operating worldwide in the Chemicals and Petrochemicals, Oil & Gas, Power, Infrastructure and Civil Engineering sectors. With a presence in four continents and 30 countries, the Group currently owns 50 operating subsidiaries, with main Italian offices in Rome, Milan and Turin. The Group’s success and reputation have been achieved due to its strong technology orientation as well as its advanced skills in Project Management, Engineering, Procurement and Construction services for the implementation of complex projects worldwide. It has developed and demonstrated significant expertise in managing large EPC projects on a turnkey basis in different geographical locations. Wafa plant for LNG – Mellitah, Libya Polyolefins Complex - Nanhai, China
  • 4. INTERNATIONAL PRESENCE 4* June 2010 Maire Tecnimont presence MANPOWER* ITALIA EUROPA ASIA SUD AMERICA TOTALE 2.619 353 1.942 167 5.081
  • 5. 5 GROUP’S STRUCTURE Corporate Initiatives Engineering and Main Contracting Licensing and IP group center Renewable energy Process Engineering Contractor
  • 6. 6 TECNIMONT OVERVIEW Tecnimont is a global E&C player  Integrated system of technological services and installations in Oil, Gas & Petrochemicals, Power, Infrastructure & Civil Engineering  Leader in managing large EPC projects in different geographical locations.  Recognized worldwide experience in engineering and project management
  • 7. TECNIMONT BUSINESS UNITS 7 Revenues 30.06.10 Backlog 30.06.10 45% 42% 13% 75% 13% 12% Oil, Gas & Petrochemicals Infrastructure & Civil Engineering Power The Group is a global E&C player that operates through its operating company Tecnimont on 4 business units:
  • 9. METRO EXPERIENCE Tecnimont has been involved in different projects involving design and construction of Manned and Automatic metro. Project name Scope of work Type of contract Value State of art Turin Metro Collegno - Porta Nuova System Design and construction FEED + EPC – Turn key 210 M€ Completed Rome Metro B1 Line Civil Works & System Design and construction Design & Build 330 M€ Design: completed Works: under construction Milan Metro Red Line extension Civil Works Design and construction Design & Build 122 M€ Completed Turin Metro Collegno - Porta Nuova System Maintenance Level 1, 2 & 3 Global Service 16 M€ Under execution Turin Metro Ext. Porta Nuova- Lingotto Civil Works Design & Construction General Contractor 101 M€ Completed Turin Metro Ext. Porta Nuova- Lingotto System Design & construction FEED + EPC – Turn key 70 M€ Design: completed Works: under construction 9
  • 10. Tecnimont integration activity on metros Automation Rolling stock Track Power Supply Platform Doors Operating Control CenterDepot/Workshop Civil Works INTEGRATION ACTIVITY 10
  • 11. ITALIAN HIGH SPEED RAILWAY 11
  • 12. HS RAILWAY TURIN - MILAN MAIN PROBLEMS • Interferencies with public services • Irrigation network and hydraulic • The proximity of highway A4 Turin-Milan • Relations with local autorities • Environmental works • Construction methodology of main structures (precasting, etc.) 12
  • 13. 13 A A A Turin-Novara Section DESIGN QUANTITIES . 1200 PROJECTS . 40.000 DELIVERABLES Main Quantities Bridges and viaducts Commercial speed Km Km/h 21 300 Embankments Km 99 Cutting Km 2,5 Artificial tunnels km 2,5 Construction and rehabilitation of new roads network km 320 Construction of motorways km 22 Flyovers Lenght n. km 76 22 Motorway Junctions n. 18 Service Areas n. 3 HS RAILWAY TURIN - MILAN QUANTITIES
  • 14. HS RAILWAY TURIN - MILAN ENVIRONMENTAL ASPECTS In environmental sensitive areas has been foreseen mitigation measures, including renaturation interventions in green area near residential areas and in protected areas. 14
  • 15. GLASS STEEL CONCRETE WOOD The design The environmental simulation The construction HS RAILWAY TURIN - MILAN NOISE REDUCTIONS 15
  • 16. • Geology and hydrogeology • Tunnel design • Technological equipment, system • Safety in tunnel • Land management HS RAILWAY BOLOGNA-FLORENCE MAIN PROBLEMS 16
  • 17. 17 - DESIGN QUANTITIES . 1250 PROJECTS . 23.500 DELIVERABLES Main Quantities Line Length + railway interconnection Commercial Speed Bridges and viaducts Embankments Km Km Km/h Km Km 78.540 5.200 300 1,2 4 Cutting Km 0.50 Tunnels (Traditional System Excavation section 120 m2 11.5m eq. int. Ø; TBM Service Tunnel 6m Ø, length 600m) Km 77.5 New road network (ordinary viability) km 110 HS RAILWAY BOLOGNA-FLORENCE MAIN PROBLEMS
  • 18. 18 INFRASTRUCTURES: RAILWAYS a – FUNCTIONALITY - INTERVENTION ON OTHER INFRASTRUCTURES - INTERACTION WITH LOCAL AUTHORITIES /APPROVAL - CONCURRENCY BETWEEN RAILWAY AND MOTORWAY DESIGN ACTIVITIES b - INTEGRATION WITH OTHER INFRASTRUCTURES - INTERFERED VIABILITY - MOTORWAY JUNCTIONS - RIVERS - IRRIGATION SYSTEMS MAIN ASPECTS CONSIDERED DURING THE DESIGN PHASE c – SAFETY - ACCESS ROAD FOR CIVIL PROTECTION - CLIMBING BARRIER (“DUNE”) - ANTIDAZZLING BARRIER - TECHNICAL MONITORING - RAILWAY SIGNALLING SYSTEM d – ARCHITECTURE AND ENVIRONMENT - TERRITORIAL INTEGRATION - ANTROPIC IMPACT MINIMIZATION - MITIGATION INTEGRATED PROJECTS (P.I.M.) - RECLAMATION OF POTENTIALLY POLLUTED SITES - STRUCTURES ARCHITECTURE AND UNIFORMITY
  • 19. 19 Topography Geology/Geotechnics Hydraulic Railwayalignment Architecture Specialstructures Tunnels Equipmentandsystem Environment HealthandSafety Costing Construction Project Coordination activities 1 Project Coordination activities …n.. Final review of overall project The basic technological approach traditionally adopted shall be integrated with a multidisciplinary approach involving architecture and landscaping as essential components of the project. MULTIDISCIPLINARY APPROACH
  • 20. GROWING DEMAND FOR UNDERGROUND TRANSPORT  A rapid expansion of the cities, growing attention to environmental issues, to higher comfort of housing and in general to a better quality of life leads to the utilization of more sophisticated design and construction criteria, aimed at minimizing the impact of existing and new infrastructures on people and existing facilities.  Cities are becoming larger and larger. The demand for public transport is getting higher accordingly. At the same time available above ground space is getting smaller, due to limitations to traffic, more green and pedestrian areas, etc.  The only way to manage these two conflicting scenarios is by maximizing the use of underground mass transport. 20
  • 21. Best practices in underground tunneling for high speed lines and metros – Why go underground? Fundamental characteristics of underground space :  Underground medium is a space that can provide the setting for activities or infrastructures that are difficult, impossible, environmentally undesirable or less profitable to install above ground.  Underground space offers a natural protection to whatever is placed underground.  The containment created by undergound structures protects the surface environment from the risks / disturbances inherents in certain types of activities.  Underground space is opaque, an underground structure is only visible at the point(s) where it connects to the surface. Reasons for going underground :  Land use and location reasons  Isolation considerations  Environmental protection  Topographic reasons  Social benefits 21
  • 22. Best practices in underground tunneling for high speed lines and metros – Why go underground? GO UNDERGROUND FOR LAND USE AND LOCATION REASONS Blaak Station (Rotterdam –ITA)Le Louvre (Paris –ITA) 22
  • 23. GO UNDERGROUND FOR ISOLATION CONSIDERATIONS  CLIMATE  NATURAL DISASTERS AND EARTHQUAKE  PROTECTION  CONTAINAMENT  SECURITY Underground swimming pool (Finland -ITA) Damage on building on top, no damages on the underground shopping mall located below (KOBE -ITA) Underground storage facilities (USA -ITA) Best practices in underground tunneling for high speed lines and metros – Why go underground? 23
  • 24. GO UNDERGROUND FOR ENVIRONMENTAL PRESERVATION Situation before and after the construction of the underground car park A motorway tunnel forming a green bridge, providing a free range for people, animals, and even vegetation. Best practices in underground tunneling for high speed lines and metros – Why go underground? 24
  • 25. GO UNDERGROUND FOR TOPOGRAPHIC REASONS BOLOGNA FLORENCE High speed railway Bologna-Florence (Italy) – LINE LENGTH: 78.5 km, of which 73.3 km underground Best practices in underground tunneling for high speed lines and metros – Why go underground? 25
  • 26. Best practices in underground tunneling for high speed lines and metros – Why go underground? GO UNDERGROUND FOR SOCIAL BENEFITS Turin Metro – First driverless subway in Italy Passante di Torino – Railway tunnels clear trains from surface, traffic noise and vibrations are reduced and the surface street areas may partially be used for other purposes. BEFORE AFTER 26
  • 27. Best practices in underground tunneling for high speed lines and metros – Current practice CUT AND COVER Trench excavation, tunnel construction and soil covering of excavated tunnels are three major integral parts of the tunnelling method. The method can accommodate changes in tunnel width and non-uniform shapes and is often adopted in construction of stations. Bulk excavation is often undertaken under a top slab to minimise traffic disruption as well as environmental impacts in terms of dust and noise emissions and visual impact. This tunnelling method involves the use of explosives. Drilling rigs are used to bore blast holes on the proposed tunnel surface to a designated depth for blasting. Explosives and timed detonators are then placed in the blast holes. Once blasting is carried out, waste rocks and soils are transported out of the tunnel before further blasting. In soft soil some mining equipments such as roadheaders and backhoes are commonly used for the tunnel excavation. Adequate structural support measures are required when adopting this method for tunnelling. TRADITIONAL EXCAVATION (NATM, DRILL & BLAST) Bored tunnelling by using a Tunnel Boring Machine (TBM) is often used for excavating long tunnels. An effective TMB method requires the selection of appropriate equipment for different rock mass and geological conditions. Compared with the cut-and-cover approach, disturbance to local traffic and associated environmental impacts would be much reduced MECHANIZED EXCAVATION 27
  • 28. 28 Best practices in underground tunneling for high speed lines and metros – CUT AND COVER 1/4 1. Applying Cement/Chemical injection from ground to make the stabilized ground and impermeable soil layers before the construction of diaphragms.
  • 29. 29 Best practices in underground tunneling for high speed lines and metros – CUT AND COVER 2/4 2. Diaphragm Constructions using Grab or Hydromills
  • 30. 30 Best practices in underground tunneling for high speed lines and metros – CUT AND COVER 3/4 3. Concrete casting of roof slab
  • 31. 31 Best practices in underground tunneling for high speed lines and metros – CUT AND COVER 4/4 4. During excavation, cast in-situ concrete roof/floor slabs were used as lateral support for the diaphragms walls (downward construction).
  • 32. 32 CUT AND COVER - Technological systems
  • 33. 33 Best practices in underground tunneling for high speed lines and metros – TRADITIONAL EXCAVATION Assess the geological-geotechnical context is fundamental for the project success. In the case of Bologna-Florence we spent 84 €million (2% of project total cost) for the survey phase. The Italian practice foresee a four stage process: I. Survey phase DESIGN II. Diagnosys phase DESIGN III. Therapy phase DESIGN IV. Monitoring phase CONSTRUCTION
  • 34. 34 DIAGNOSIS PHASE HIGH SPEED RAILWAY SYSTEM MILAN TO NAPOLI RAILWAY LINE * BOLOGNA TO FLORENCE SECTION Best practices in underground tunneling for high speed lines and metros – TRADITIONAL EXCAVATION Using the acquired data from survey phase, it’s possible to predict the behaviour of the rock in response to excavation Category A – 17% Category B – 57% Category C – 26%
  • 35. 35 THERAPY PHASE HIGH SPEED RAILWAY SYSTEM MILAN TO NAPOLI RAILWAY LINE * BOLOGNA TO FLORENCE SECTION CONFINEMENT ACTIONPRECONFINEMENT ACTION Best practices in underground tunneling for high speed lines and metros – TRADITIONAL EXCAVATION In the therapy phase we define the excavation methods and the stabilisation measures to obtain the stability of the cavity.
  • 36. 36 Best practices in underground tunneling for high speed lines and metros – TRADITIONAL EXCAVATION Once the design phase is complete, during the construction phase using monitoring it’s possible to check the correctness of predictions made during the previous phases; this monitoring is carried out by measuring and checking the response of the medium to escavation. MONITORING PHASE Advance rates were very costant, thus indicating a excellent match between design and the actual reality encountered
  • 37. Best practices in underground tunneling for high speed lines and metros – TRADITIONAL EXCAVATION 37
  • 38. Best practices in underground tunneling for high speed lines and metros – TRADITIONAL EXCAVATION 38
  • 39. Best practices in underground tunneling for high speed lines and metros – TRADITIONAL EXCAVATION 39
  • 40. 40 Best practices in underground tunneling for high speed lines and metros – TRADITIONAL EXCAVATION
  • 41. Best practices in underground tunneling for high speed lines and metros – TRADITIONAL EXCAVATION 41
  • 42. Best practices in underground tunneling for high speed lines and metros – TRADITIONAL EXCAVATION 42
  • 43. 43 TRADITIONAL EXCAVATIONS- Technological systems 1/6 Tunnel face extrusion and failure
  • 45. 45 TRADITIONAL EXCAVATIONS- Technological systems 3/6 FOREPOLING CROWN WEAKNESS
  • 47. 47 TRADITIONAL EXCAVATIONS- Technological systems 5/6 Depending on soil conditions, we can use different kind of equipment.
  • 48. 48 TRADITIONAL EXCAVATIONS- Technological systems 6/6 Shotcrete + steel net Shotcrete + fibers: Steel fibers Polyester fibers Polypropylene fibers Synthetic fibers (general polymers)
  • 49. MECHANIZED EXCAVATIONS 49 Rock TBM EPB-S (Earth Pressure Balanced Shield) Slurry Shield
  • 50. 50 Mechanized excavation : Basic principles The Earth Pressure Balanced (EPB) tunnelling method owns it’s name from the way the front face of the TBM is supported during excavation, using earth pressure. The principles of the EPB-tunnelling method can described as follows (Kanayasu, Yamamoto and Kitahara, 1995): • The soil is excavated by rotating cutter heads; • The excavated soil is mechanically agitated and fills the face and an excavation chamber.; • Using the thrust of the shield machine, by means of hydraulic jacks, the excavated soil is pressurized to stabilize the excavation front (force equilibrium); • Control of the soil pressure in the chamber is done by adjusting the amount of soil discharged through the screw conveyor or other soil removal devices and the amount of soil excavated to counterbalance earth and groundwater pressure (volume equilibrium); • The excavated soil in the chamber and the screw conveyors work as a water seal. The earth pressure support method is generally used in cohesive soils, enabling it to be used as a supporting medium itself, with the use of conditioning materials if necessary. A MECHANIZED EXCAVATIONS
  • 51. 51 PENETRATION RATE [mm/min] PRESSURE SENSORS [Bar] SCREW CONVEYOR RATE [rpm] Excavation parameters control The main parameters, to be verified via the sensors and sensing equipment, are:  Face-support pressure  Pressure and volume of the backfill grout of the annular void  Weight of the extracted material Pressure sensors MECHANIZED EXCAVATIONS
  • 52. Conventional Tunnelling Vs TBM Tunnelling 52 Conventional tunnelling is more cost effective than mechanized tunnelling for the cases of short tunnels (< 2.4 km), shafts and tunnels with changing geometry, and/or substantially changing geotechnical behaviour. There is an overlapped area where hand and mechanical mining may be equally considered and where a dual design is recommended. With tunnels longer than 3.2 km, the mechanized tunnelling becomes to be more economic than conventional tunnelling. (Sauer, 2004) Each technique have advantages and disadvantages; the right choice must be done according to specific context (soil, cover, etc..) and on the basis of the boundary conditions (environmental rules, stakeholder, etc)
  • 53. Best practices in underground tunneling for high speed lines and metros – Risk management 1/5 Tunnelling is not a risk-free technology, each tunnel is a specific unique project on its own in a unique combination of ground / soil. The “right” construction method with the “right” experience parties involved are crucial for the success. The main most important factor however, the geology, is only known to a limited extent. Any accident during construction as well as in use provokes a substantial interruption and often a standstill till the problems are solved. Risk has two components: probability of occurrence W and amount of damage D. The different steps of the process are:  Identification of the risks (initial one);  Reduction of the initial risk working on the impact and/or possibility of occurrence of an event (i.e. provisional building works, choice of the machinery, control of the TBM head pression);  Management of the residual risk (i.e. monitoring). Residual risks are unavoidable and they should be shared among the Parties and systematically controlled by countermeasures. 53
  • 54. A recommended strategy is to carry out construction risk assessments at each stage of design and construction in accordance with the information available and the decisions to be taken or revised at each stage. Any risk management strategy should include:  Definition of the risk management responsibilities of the various parties involved (different departments within the owners organisation, consultants, contractors);  Short description of the activities to be carried out at different stages of the project in order to achieve the objectives;  Scheme to be used for follow-up on results obtained through the risk management activities by which information about identified hazards (nature and significance) is freely available;  Follow-up on initial assumptions regarding the operational phase;  Monitoring, audit and review procedures. Best practices in underground tunneling for high speed lines and metros – Risk management 2/5 54
  • 55. 55 The problem associated with underground construction is that the excavations will alter the stress fields in the ground around the tunnels and deformations will occur. If these deformations are not strictly controlled during the construction process, excessive ground movements will propagate upwards potentially causing significant damage to adjacent buried infrastructure and surface structures. Using established methods of analysis of ground movement it’s possible to identify buildings potentially at risk. For those buildings were planned soil improvements to avoid excessive movements of its foundations. Reduction of the initial risk Project Hypothesis Detailed design Execution Best practices in underground tunneling for high speed lines and metros – Risk management 3/5
  • 56. 56 Best practices in underground tunneling for high speed lines and metros – Risk management 4/5 The residual risk, have to be managed during the constructive phases by means of the implementation of an integrated monitoring system to:  Guarantee the correct flow of information to permit designers to analyse and verify the hypothesis used to develop the basic design;  Allows to understand the atypical phenomena giving the information necessary to solve the problem. The project must define two parameters which identify the “attention” and “alarm” levels.  Attention level activates a specific control system in order to reach a more specific following of the event. Alarm level requires the adoption of the counter-measures specifically studied for the event. Topographical controls on buildings
  • 57. Example of monitoring during the excavation of part of the work adjacent to the buildings: Automatic monitoring with electrolevels. The distortions measured during the excavation phase were lower than the trigger limits defined during the design phase. Best practices in underground tunneling for high speed lines and metros – Risk management 5/5 57
  • 58. 58  The basic technological approach traditionally adopted for infrastructure projects shall be integrated with a multidisciplinary approach that considers all the processes of the entire cycle of life and performance of the works. This integrated approach would allow different disciplines to interact and mutually stimulate the development of a fully comprehensive infrastructure, as required in the present global scenario.  Nowadays architecture and landscaping are essential components of the project, the natural system and infrastructure system have an interplay that can be referred as very “sensitive”; the disturbance in one of these systems has a way of spreading to the other. To avoid this problem often the solution is found in underground infrastructures. These are, in fact, one of the best solutions for sustainable solutions for integrating utilities and transportation infrastructures within environments with social, technical or other natures difficult interfaces (such as urban areas, mountains, etc).  Today, the modern technological systems allow us to build faster tunnel and underground structures using different solutions in every kind of soil, and the monitoring systems allow us to control in real time the situation. These technologies can be very useful to optimize performance and safety. All these aspects have been studied in detail and put successfully into practice by Tecnimont during the realization of underground infrastructures in highly urbanized cities as well in highways and high speed railways. CONCLUSIONS
  • 59. 59
  • 60. Rome Via di Vannina, 88/94 00156 Rome P +39 06 4122 351 F +39 06 4122 35610 Milan Viale Monte Grappa, 3 20124 Milan P +39 02 6313.1 F +39 02 6313.9052 Turin Corso Ferrucci, 112/a 10138 Turin P +39 011 0056111 F+39 011 0056444 info@mairetecnimont.it – www.mairetecnimont.it