GUIDELINES FOR PREPARATION OF

                  PERSPECTIVE PLAN

            NATIONAL FOOD FOR WORK

                  PROGRAMME (NFFWP)


        TRAINING OF TRAINERS
        Dr. N. Sai Bhaskar Reddy
  AMR-APARD, RAJENDRANAGAR, HYDERABAD
Objective - comprehensive
    perspective plan of five years
   That would enable develop all the Panchayats of
    the 150 most backward districts during the 5
    years period of 2005-2010 in such a way that
    there is visible impact on the major problems of
    each Panchayat and a sound base is created for
    self sustaining economy to remove poverty
    and bring these Districts at least at par with
    other developed areas of the state and the
    country.
   It will facilitate optimizing all resources available
    under all the developmental programmes operational
    at the panchayat level
   To provide best possible and meaningful option for
    convergence/dovetailing of all such
    programmes to derive maximum benefit in favour
    of the rural poor especially with regard to
    generation of employment opportunities both in
    terms of wage and self employment through creation
    of need based optimum infrastructure at the
    panchayat level in the short term and develop self
    sustaining robust panchayat economy In the
    long run.
Preparing the Perspective
    Plan
   Survey each village and panchayat in the district to
    collect data on

        A. Existing economy infrastructure needs and to

        B. Assess feasibility of projects to be included in
          the plan

   Rough cost estimate for project/works suggested
    must be given based on acceptable parameters and they
    may be indicated in the plan document.
The people involved in perspective
plan preparation
   Consolidation and preparation of final document
    – AMR-APARD
   Training of trainers at District level (~40
    officers) – AMR-APARD
   TOTs – Senior Level Officers / special officers in
    the District
   Training of Mandal level resource persons –
    ToTs
   Perspective plan preparation of each village with
    the participation of primary stakeholders and
    facilitation by Mandal level resource persons.
PERSPECTIVE PLAN OF THE DISTRICT
The perspective plan will be a comprehensive document with
several chapters

CHAPTER-1
The  information for the district as a whole on -
demography - SC/ST, women and children population with
work force divided into employed, semi-employed,
unemployed, occupational distribution,
month wise rainfall distribution,
depth of water table, depletion rate,
gender-wise illiteracy,
main crops, number of crops per year, per hectare
productivity, type of soil, agriculture productivity per
worker,
distribution of average land holding, average size of tilling,
distribution of commercial/Regional Rural Bank, availability
of bank branches per sq. km,
potential occupation, service and industry.
CHAPTER-II
Scheme-wise    availability of resources of the district as
a whole in respect of all employment and development
oriented Programme such as
Swarnajayanti Gram Swarozgar Yojana (SGSY),
Rashtriya Sam Vikas Yojana (RSVY),
Watershed development programmes (such as IWDP,
DPAP, DDP)
PMRY (its share for rural segment),
Rural Employment Generation Programme of KVIC,
Sampoorna Grameena Rozgar Yojana (SGRY)
MPLAD, MLALAD
NFFWP and
all other Centrally and state sponsored programmes
   Block-wise breakup of
    distribution/availability of resources
    under the above programmes along with
    the present status of number of
    persons unemployed/ semi-
    employed may be given.
Location/area specific kinds/types of infrastructure, which are
   expected in the Panchayat.
(i) One panchayat Ghar
(ii) One primary/secondary school building sufficient for the number of
   children studying.
(iii) One low cost storage go down for storing food grains
(iv) Tube/open wells (whichever is relevant in that area) for drinking /
   irrigation purpose.
(v) Internal roads providing connectivity with main roads
(vi) Drainage / nallah to drain out extra water in the water logged/flood
   prone areas
(vii) Dairy/Veterinary development infrastructure.
(viii) Erection of permanent /pucca embankment for flood protection
(IX) Small check dams, water conservation activities like digging of
   ponds/percolation tanks and de-silting of ponds
(x) Strengthening of marketing infrastructure at local Panchayat haats
   / market such as construction of permanent sheds and low cost
   community storage godowns for safe storage of goods etc.
(xi) Individual/community horticulture/social forestry development.
(xii) Any other facility considered essential on the local needs.


* - The above list of infrastructure is only illustrative and not
   exhaustive. It is possible that some of the above infrastructure may
   not be suitable for a particular state / district / panchayat but may
   be relevant in other. As such, the above list may be modified and
   prepared taking into account local needs and aspirations.
CHAPTER-III
   Details on Panchayat –wise (i) list of infrastructure already
    existing and (ii). List of infrastructure that are missing out
    of the list given at Section-B, Chapter –11 (iii)
    requirement of resources for creation of missing
    infrastructure along with Programme-wise inflow/share of
    the Panchayat out of all development programmes listed
    at Section-A of chapter-11 and (iv) estimated employment
    generation in terms of both self and wage employment
    while creating missing infrastructure .

   The above information is to be given year-wise.
   While assessing resource inflow from all sources, 15% for
    maintenance of assets already created /being created be
    shown separately and as such only 85% of the total inflow may
    be taken in to account for showing resource inflow for creation of
    assets.
   The above Panchayat–wise list of missing infrastructure
    have to be prepared in a manner that each missing infrastructure
    will give a clear cut idea under which Programme it is proposed
    with estimated cost and the number of expected beneficiaries to
    be covered under self and wage employment.
   Incase of wage employment, number of man-day’s generation is to
    be divided by 100 to arrive at number of persons to be employed.

   All activities /works shown under the existing Programme have to be
    implemented    in   accordance     with   their   respective   Programme
    guidelines. If any activity which is permissible under more than one
    Programme, it may be shown under that Programme which has
    larger share for that Panchayat.

   It should, however, be ensured that one activity is shown under one
    Programme only with the stipulation that is completed during one
    financial year it self. Spillover to the next year may be indicated in
    exceptional cases where inflow of resources is limited during the
    year.

   Estimated cost may be shown increased 5 to 10% every year while
    showing year-wise activities to be taken up.
   Programme      PMRY
   SGRY           REGP
   SGSY           MPLAD
   RSVY           MLALAD
   IWDP
                   Add more
   DPAP            scheme of
   DDP             Central/state if
                    any
Missing Infrastructure with Priority(Shelf of
  Projects)(for example)
   Check dam to store water
   Drainage/ Nallah to drain extra water in water
    logged/flood affected areas
   Digging of pond
   Land Development of Common Wasteland area
   Percolation Wells
   Storage Godown
   and so on.
   Employment Generation
   Under Self Employment Programmes (NO. of
    expected beneficiaries)
   Wage Employment Programmes
   a. Number of expected man days to be generated (in
    numbers)
   b. Number of expected beneficiaries getting employment (
    (a) above/100)
   Area development programme
   a) Number of expected beneficiaries (in Numbers)
    b) (i) Number of expected mandays generated (in
    numbers)
    b) (ii) Number expected mandays converted in to number
    of persons( (b) (i) above/100)
CHAPTER-IV
   Block-wise exercise by consolidating

    panchayat–wise information under respective

    Block (Mandal) may be take-up.

   Summary for each Block separately to indicate

    missing
       Infrastructure wise details giving

       Year wise cost estimates and

       Expected employment generation may be given
Missing Infrastructure
   Drainage (in waterlogged/flood affected areas) (in KM)
   Low cost community food grains storage godowns
   High school Building
    Strengthening/construction of permanent river
    embankment (In KM)
   Check dams
   Digging of ponds/desilting
   Horticulture/Social forestry
        (a)Individual
        (b)Community
   Dairy Development
   (and so on)
CHAPTER-V
   Annual Action plans for the NFFWP for
    the next five years based on the
    perspective plan.
   Segregate Panchayat-wise activities
    /works those indicated against the
    NFFWP quota.
   Panchayat-wise and year-wise
    works/activities to be taken up under
    the NFFWP with clear cut prioritization
    will have to be given.
Name of activities in priority order (for
    example)
   Checkdams
   Digging of ponds/desilting
   Drainage (in waterlogged/flood affected areas)
   Development & Bunding of degraded lands
   Other water harvesting structures (mention
    type of structure)
   (and so on)
CHAPTER-VI

   The success of the program will be
    quantified based on the following type
    of parameters on pre (as on 2005) and
    post (as on 2010) perspective plan
    assessment.
Item (for Example)               Status at the    Estimated      Total
                                 time        of   status after   Increase/Decr
                                 preparation of   the            ease
                                 perspective      completion
                                 plan             of the five
Irrigated areas (In Ha.)                          year   plan
                                                  period
Water table (In Feet)                             (2010)

Agricultural     output     of
differenft crops (In per Ha)

Diversification of   area   to
cash crops (In Ha)

Nutrition level

Rural urban migration (In
persons)
Rural poverty ratio (In %
age)
Village   connectivity      to
Towns (in %age)

More Related Content

What's hot

Physical planning in town planning
Physical planning in town planningPhysical planning in town planning
Physical planning in town planningAbhi Vallabhaneni
 
Draft Proposal of Town Planning Scheme
Draft Proposal of Town Planning SchemeDraft Proposal of Town Planning Scheme
Draft Proposal of Town Planning SchemeYajush Sonar
 
Chapter 3 parth urdpfi (1)
Chapter 3 parth urdpfi (1)Chapter 3 parth urdpfi (1)
Chapter 3 parth urdpfi (1)Parth Desai
 
The concept of Master plan
The concept of Master planThe concept of Master plan
The concept of Master planDania Abdel-aziz
 
Methodology for Preparation of Master Plan
Methodology  for  Preparation of Master PlanMethodology  for  Preparation of Master Plan
Methodology for Preparation of Master PlanJIT KUMAR GUPTA
 
A short hostory of urban planning in bangladesh new
A short hostory of  urban planning in  bangladesh newA short hostory of  urban planning in  bangladesh new
A short hostory of urban planning in bangladesh newAkhter Chaudhury
 
local area plan, Vasna ward, Ahmedabad
local area plan, Vasna ward, Ahmedabadlocal area plan, Vasna ward, Ahmedabad
local area plan, Vasna ward, AhmedabadPratham Pincha
 
National Urban Transport Policy
National Urban Transport PolicyNational Urban Transport Policy
National Urban Transport PolicyAshu Kedia
 
Review of Development Plans/ Master Plans of selected cities of India.
Review of Development Plans/ Master Plans of selected cities of India.Review of Development Plans/ Master Plans of selected cities of India.
Review of Development Plans/ Master Plans of selected cities of India.KARTHICK KRISHNA
 
Methodology for Preparation of Master Plan
 Methodology for Preparation of Master Plan  Methodology for Preparation of Master Plan
Methodology for Preparation of Master Plan JIT KUMAR GUPTA
 
Untold Story of Chandigarh Master Plan
Untold Story of Chandigarh Master PlanUntold Story of Chandigarh Master Plan
Untold Story of Chandigarh Master PlanJIT KUMAR GUPTA
 
Master plan (Town Planning)
Master plan (Town Planning)Master plan (Town Planning)
Master plan (Town Planning)S.m. Atik
 
National Slum Development Program (NSDP)
National Slum Development Program (NSDP) National Slum Development Program (NSDP)
National Slum Development Program (NSDP) Sumit Ranjan
 

What's hot (20)

Perspective plan
Perspective planPerspective plan
Perspective plan
 
Physical planning in town planning
Physical planning in town planningPhysical planning in town planning
Physical planning in town planning
 
Draft Proposal of Town Planning Scheme
Draft Proposal of Town Planning SchemeDraft Proposal of Town Planning Scheme
Draft Proposal of Town Planning Scheme
 
Chapter 3 parth urdpfi (1)
Chapter 3 parth urdpfi (1)Chapter 3 parth urdpfi (1)
Chapter 3 parth urdpfi (1)
 
The concept of Master plan
The concept of Master planThe concept of Master plan
The concept of Master plan
 
Jnnurm
JnnurmJnnurm
Jnnurm
 
Methodology for Preparation of Master Plan
Methodology  for  Preparation of Master PlanMethodology  for  Preparation of Master Plan
Methodology for Preparation of Master Plan
 
Regional plan
Regional plan Regional plan
Regional plan
 
Master plan
Master planMaster plan
Master plan
 
A short hostory of urban planning in bangladesh new
A short hostory of  urban planning in  bangladesh newA short hostory of  urban planning in  bangladesh new
A short hostory of urban planning in bangladesh new
 
local area plan, Vasna ward, Ahmedabad
local area plan, Vasna ward, Ahmedabadlocal area plan, Vasna ward, Ahmedabad
local area plan, Vasna ward, Ahmedabad
 
National Urban Transport Policy
National Urban Transport PolicyNational Urban Transport Policy
National Urban Transport Policy
 
Review of Development Plans/ Master Plans of selected cities of India.
Review of Development Plans/ Master Plans of selected cities of India.Review of Development Plans/ Master Plans of selected cities of India.
Review of Development Plans/ Master Plans of selected cities of India.
 
Methodology for Preparation of Master Plan
 Methodology for Preparation of Master Plan  Methodology for Preparation of Master Plan
Methodology for Preparation of Master Plan
 
Draft Development Plan 2021 (Review) AUDA - D Thara, IAS
Draft Development Plan 2021 (Review) AUDA - D Thara, IASDraft Development Plan 2021 (Review) AUDA - D Thara, IAS
Draft Development Plan 2021 (Review) AUDA - D Thara, IAS
 
Untold Story of Chandigarh Master Plan
Untold Story of Chandigarh Master PlanUntold Story of Chandigarh Master Plan
Untold Story of Chandigarh Master Plan
 
Master plan (Town Planning)
Master plan (Town Planning)Master plan (Town Planning)
Master plan (Town Planning)
 
National Slum Development Program (NSDP)
National Slum Development Program (NSDP) National Slum Development Program (NSDP)
National Slum Development Program (NSDP)
 
Amrut ppt
Amrut pptAmrut ppt
Amrut ppt
 
Tcpo
TcpoTcpo
Tcpo
 

Viewers also liked

Education mangement powerpoint
Education mangement powerpointEducation mangement powerpoint
Education mangement powerpointEdward Phiri
 
role of voluntary organisation
role of voluntary organisationrole of voluntary organisation
role of voluntary organisationEagathagi Gandiban
 
Iii.1 educational management
Iii.1 educational managementIii.1 educational management
Iii.1 educational managementLyna An Na
 
Approaches to educational planning
Approaches to educational planningApproaches to educational planning
Approaches to educational planningwatsontamil
 
A trivariate causality test among economic growth, government expenditure and...
A trivariate causality test among economic growth, government expenditure and...A trivariate causality test among economic growth, government expenditure and...
A trivariate causality test among economic growth, government expenditure and...Alexander Decker
 
Business, Technology Intelligence
Business, Technology IntelligenceBusiness, Technology Intelligence
Business, Technology IntelligenceAndré Dubreuil
 
Agriculture plan
Agriculture planAgriculture plan
Agriculture planTrung Billy
 
Unit 31 Social Action and Community Media
Unit 31 Social Action and Community MediaUnit 31 Social Action and Community Media
Unit 31 Social Action and Community MediaMissOzzy
 
Rural development planning
Rural development planningRural development planning
Rural development planningM Usama Sehgal
 
Social action and community media - an introduction
Social action and community media - an introductionSocial action and community media - an introduction
Social action and community media - an introductioniain bruce
 
Social Action Theories
Social Action TheoriesSocial Action Theories
Social Action Theoriessmccormac7
 
23. Strategic Planning Outline
23. Strategic Planning Outline23. Strategic Planning Outline
23. Strategic Planning OutlineEarl Stevens
 
Module 6 Perspectives in Strategic Planning
Module 6 Perspectives in Strategic PlanningModule 6 Perspectives in Strategic Planning
Module 6 Perspectives in Strategic PlanningJo Balucanag - Bitonio
 

Viewers also liked (20)

Perspective Planning
Perspective PlanningPerspective Planning
Perspective Planning
 
Educational management planning
Educational management planningEducational management planning
Educational management planning
 
Perspective in Strategic Planning
Perspective in Strategic PlanningPerspective in Strategic Planning
Perspective in Strategic Planning
 
Education mangement powerpoint
Education mangement powerpointEducation mangement powerpoint
Education mangement powerpoint
 
role of voluntary organisation
role of voluntary organisationrole of voluntary organisation
role of voluntary organisation
 
Iii.1 educational management
Iii.1 educational managementIii.1 educational management
Iii.1 educational management
 
Approaches to educational planning
Approaches to educational planningApproaches to educational planning
Approaches to educational planning
 
Planning
PlanningPlanning
Planning
 
A trivariate causality test among economic growth, government expenditure and...
A trivariate causality test among economic growth, government expenditure and...A trivariate causality test among economic growth, government expenditure and...
A trivariate causality test among economic growth, government expenditure and...
 
Agricultural Performance and Food Security in Nepal: Constraints and Challenges
Agricultural Performance and Food Security in Nepal: Constraints and ChallengesAgricultural Performance and Food Security in Nepal: Constraints and Challenges
Agricultural Performance and Food Security in Nepal: Constraints and Challenges
 
Business, Technology Intelligence
Business, Technology IntelligenceBusiness, Technology Intelligence
Business, Technology Intelligence
 
BRM - Dr. TK - Characteristics of a Good Questionnaire
BRM - Dr. TK - Characteristics of a Good QuestionnaireBRM - Dr. TK - Characteristics of a Good Questionnaire
BRM - Dr. TK - Characteristics of a Good Questionnaire
 
Agriculture plan
Agriculture planAgriculture plan
Agriculture plan
 
Unit 31 Social Action and Community Media
Unit 31 Social Action and Community MediaUnit 31 Social Action and Community Media
Unit 31 Social Action and Community Media
 
Internal Rate of Return
Internal Rate of ReturnInternal Rate of Return
Internal Rate of Return
 
Rural development planning
Rural development planningRural development planning
Rural development planning
 
Social action and community media - an introduction
Social action and community media - an introductionSocial action and community media - an introduction
Social action and community media - an introduction
 
Social Action Theories
Social Action TheoriesSocial Action Theories
Social Action Theories
 
23. Strategic Planning Outline
23. Strategic Planning Outline23. Strategic Planning Outline
23. Strategic Planning Outline
 
Module 6 Perspectives in Strategic Planning
Module 6 Perspectives in Strategic PlanningModule 6 Perspectives in Strategic Planning
Module 6 Perspectives in Strategic Planning
 

Similar to Perspective plan preparation 2

Bu b fy2015 guidelines 0910(1)
Bu b fy2015 guidelines 0910(1)Bu b fy2015 guidelines 0910(1)
Bu b fy2015 guidelines 0910(1)malapatansarangani
 
Bu b fy2015 guidelines 0910
Bu b fy2015 guidelines 0910Bu b fy2015 guidelines 0910
Bu b fy2015 guidelines 0910Aubry Fara-on
 
Agrikulturang pantawid pamilya pilipino tor ppt
Agrikulturang pantawid pamilya pilipino tor pptAgrikulturang pantawid pamilya pilipino tor ppt
Agrikulturang pantawid pamilya pilipino tor pptKaren Mabasa
 
AgWA Definition of a Country Support Tool (CST) - Andy Bullock
AgWA Definition of a Country Support Tool (CST) - Andy Bullock AgWA Definition of a Country Support Tool (CST) - Andy Bullock
AgWA Definition of a Country Support Tool (CST) - Andy Bullock CTA
 
Pc i (social sector)
Pc i (social sector)Pc i (social sector)
Pc i (social sector)hayat alishah
 
Mahatma Gandhi National Rural Employment Guarantee
Mahatma Gandhi National Rural Employment Guarantee Mahatma Gandhi National Rural Employment Guarantee
Mahatma Gandhi National Rural Employment Guarantee CA Narinder Jit Singh
 
Overview of enabling environment and implementation of climate resilient WASH
Overview of enabling environment and implementation of climate resilient WASH Overview of enabling environment and implementation of climate resilient WASH
Overview of enabling environment and implementation of climate resilient WASH IRC
 
DRR mainstreaming through Decentralized Planning with Panchayati Raj Institution
DRR mainstreaming through Decentralized Planning with Panchayati Raj InstitutionDRR mainstreaming through Decentralized Planning with Panchayati Raj Institution
DRR mainstreaming through Decentralized Planning with Panchayati Raj InstitutionMINTU DEBNATH
 
Session 3B Finance - Toro boro burkina faso
Session 3B Finance - Toro boro burkina fasoSession 3B Finance - Toro boro burkina faso
Session 3B Finance - Toro boro burkina fasoIRC
 
City development plan guwahati
City development plan guwahatiCity development plan guwahati
City development plan guwahatiAnupama Krishnan
 
Twelfth five year plan review
Twelfth five year plan reviewTwelfth five year plan review
Twelfth five year plan reviewSushant Karnik
 
Local Planning and Budgeting Linkage
Local Planning and Budgeting LinkageLocal Planning and Budgeting Linkage
Local Planning and Budgeting Linkageyee tandog
 
Session 3B Finance - Getenet community development funds ethiopia (pp tminimi...
Session 3B Finance - Getenet community development funds ethiopia (pp tminimi...Session 3B Finance - Getenet community development funds ethiopia (pp tminimi...
Session 3B Finance - Getenet community development funds ethiopia (pp tminimi...IRC
 
Mukul Asher: Analysing the Bangalore Municipal Budget
Mukul Asher: Analysing the Bangalore Municipal BudgetMukul Asher: Analysing the Bangalore Municipal Budget
Mukul Asher: Analysing the Bangalore Municipal BudgetThe Takshashila Institution
 

Similar to Perspective plan preparation 2 (20)

Bu b fy2015 guidelines 0910(1)
Bu b fy2015 guidelines 0910(1)Bu b fy2015 guidelines 0910(1)
Bu b fy2015 guidelines 0910(1)
 
Bu b fy2015 guidelines 0910
Bu b fy2015 guidelines 0910Bu b fy2015 guidelines 0910
Bu b fy2015 guidelines 0910
 
Agrikulturang pantawid pamilya pilipino tor ppt
Agrikulturang pantawid pamilya pilipino tor pptAgrikulturang pantawid pamilya pilipino tor ppt
Agrikulturang pantawid pamilya pilipino tor ppt
 
2015 bub
2015 bub2015 bub
2015 bub
 
Agriculture Public Expenditure Workshop Module 2
Agriculture Public Expenditure Workshop Module 2Agriculture Public Expenditure Workshop Module 2
Agriculture Public Expenditure Workshop Module 2
 
AgWA Definition of a Country Support Tool (CST) - Andy Bullock
AgWA Definition of a Country Support Tool (CST) - Andy Bullock AgWA Definition of a Country Support Tool (CST) - Andy Bullock
AgWA Definition of a Country Support Tool (CST) - Andy Bullock
 
Pc i (social sector)
Pc i (social sector)Pc i (social sector)
Pc i (social sector)
 
Water shed.ppt
Water shed.pptWater shed.ppt
Water shed.ppt
 
Pc i social sector
Pc i social sectorPc i social sector
Pc i social sector
 
Mahatma Gandhi National Rural Employment Guarantee
Mahatma Gandhi National Rural Employment Guarantee Mahatma Gandhi National Rural Employment Guarantee
Mahatma Gandhi National Rural Employment Guarantee
 
Overview of enabling environment and implementation of climate resilient WASH
Overview of enabling environment and implementation of climate resilient WASH Overview of enabling environment and implementation of climate resilient WASH
Overview of enabling environment and implementation of climate resilient WASH
 
DRR mainstreaming through Decentralized Planning with Panchayati Raj Institution
DRR mainstreaming through Decentralized Planning with Panchayati Raj InstitutionDRR mainstreaming through Decentralized Planning with Panchayati Raj Institution
DRR mainstreaming through Decentralized Planning with Panchayati Raj Institution
 
Session 3B Finance - Toro boro burkina faso
Session 3B Finance - Toro boro burkina fasoSession 3B Finance - Toro boro burkina faso
Session 3B Finance - Toro boro burkina faso
 
City development plan guwahati
City development plan guwahatiCity development plan guwahati
City development plan guwahati
 
Twelfth five year plan review
Twelfth five year plan reviewTwelfth five year plan review
Twelfth five year plan review
 
Local Planning and Budgeting Linkage
Local Planning and Budgeting LinkageLocal Planning and Budgeting Linkage
Local Planning and Budgeting Linkage
 
Agriculture Public Expenditure Workshop Module 1
Agriculture Public Expenditure Workshop Module 1Agriculture Public Expenditure Workshop Module 1
Agriculture Public Expenditure Workshop Module 1
 
Session 3B Finance - Getenet community development funds ethiopia (pp tminimi...
Session 3B Finance - Getenet community development funds ethiopia (pp tminimi...Session 3B Finance - Getenet community development funds ethiopia (pp tminimi...
Session 3B Finance - Getenet community development funds ethiopia (pp tminimi...
 
Note sheet
Note sheetNote sheet
Note sheet
 
Mukul Asher: Analysing the Bangalore Municipal Budget
Mukul Asher: Analysing the Bangalore Municipal BudgetMukul Asher: Analysing the Bangalore Municipal Budget
Mukul Asher: Analysing the Bangalore Municipal Budget
 

More from geosaibhaskar

Our natural heritage local environment 2
Our natural heritage   local environment 2Our natural heritage   local environment 2
Our natural heritage local environment 2geosaibhaskar
 
Rainwater harvesting walamtari june12_1
Rainwater harvesting walamtari june12_1Rainwater harvesting walamtari june12_1
Rainwater harvesting walamtari june12_1geosaibhaskar
 
Understanding Prices
Understanding PricesUnderstanding Prices
Understanding Pricesgeosaibhaskar
 
Biochar global warming
Biochar global warmingBiochar global warming
Biochar global warminggeosaibhaskar
 
Stoves & biochar nabard chittore
Stoves & biochar nabard chittoreStoves & biochar nabard chittore
Stoves & biochar nabard chittoregeosaibhaskar
 
Saibhaskar The Hans India - news2
Saibhaskar The Hans India - news2Saibhaskar The Hans India - news2
Saibhaskar The Hans India - news2geosaibhaskar
 
Saibhaskar The Hans India - news1
Saibhaskar The Hans India - news1Saibhaskar The Hans India - news1
Saibhaskar The Hans India - news1geosaibhaskar
 
Climate Change Rainwater harvesting
Climate Change Rainwater harvestingClimate Change Rainwater harvesting
Climate Change Rainwater harvestinggeosaibhaskar
 
Groundwater project 8
Groundwater project 8Groundwater project 8
Groundwater project 8geosaibhaskar
 

More from geosaibhaskar (20)

Our natural heritage local environment 2
Our natural heritage   local environment 2Our natural heritage   local environment 2
Our natural heritage local environment 2
 
Rainwater harvesting walamtari june12_1
Rainwater harvesting walamtari june12_1Rainwater harvesting walamtari june12_1
Rainwater harvesting walamtari june12_1
 
Understanding Prices
Understanding PricesUnderstanding Prices
Understanding Prices
 
Biochar part 1
Biochar part 1Biochar part 1
Biochar part 1
 
Biochar part 2
Biochar part 2Biochar part 2
Biochar part 2
 
Biochar part 3
Biochar part 3Biochar part 3
Biochar part 3
 
Biochar part 4
Biochar part 4Biochar part 4
Biochar part 4
 
Good stoves part1
Good stoves part1Good stoves part1
Good stoves part1
 
Good stoves part2
Good stoves part2Good stoves part2
Good stoves part2
 
Good stoves part3
Good stoves part3Good stoves part3
Good stoves part3
 
Good stoves part4
Good stoves part4Good stoves part4
Good stoves part4
 
Biochar global warming
Biochar global warmingBiochar global warming
Biochar global warming
 
Green buildings 2
Green buildings 2Green buildings 2
Green buildings 2
 
Indoor Environment
Indoor EnvironmentIndoor Environment
Indoor Environment
 
GEO Spirit
GEO SpiritGEO Spirit
GEO Spirit
 
Stoves & biochar nabard chittore
Stoves & biochar nabard chittoreStoves & biochar nabard chittore
Stoves & biochar nabard chittore
 
Saibhaskar The Hans India - news2
Saibhaskar The Hans India - news2Saibhaskar The Hans India - news2
Saibhaskar The Hans India - news2
 
Saibhaskar The Hans India - news1
Saibhaskar The Hans India - news1Saibhaskar The Hans India - news1
Saibhaskar The Hans India - news1
 
Climate Change Rainwater harvesting
Climate Change Rainwater harvestingClimate Change Rainwater harvesting
Climate Change Rainwater harvesting
 
Groundwater project 8
Groundwater project 8Groundwater project 8
Groundwater project 8
 

Recently uploaded

DBX First Quarter 2024 Investor Presentation
DBX First Quarter 2024 Investor PresentationDBX First Quarter 2024 Investor Presentation
DBX First Quarter 2024 Investor PresentationDropbox
 
Architecting Cloud Native Applications
Architecting Cloud Native ApplicationsArchitecting Cloud Native Applications
Architecting Cloud Native ApplicationsWSO2
 
Manulife - Insurer Transformation Award 2024
Manulife - Insurer Transformation Award 2024Manulife - Insurer Transformation Award 2024
Manulife - Insurer Transformation Award 2024The Digital Insurer
 
How to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected WorkerHow to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected WorkerThousandEyes
 
Repurposing LNG terminals for Hydrogen Ammonia: Feasibility and Cost Saving
Repurposing LNG terminals for Hydrogen Ammonia: Feasibility and Cost SavingRepurposing LNG terminals for Hydrogen Ammonia: Feasibility and Cost Saving
Repurposing LNG terminals for Hydrogen Ammonia: Feasibility and Cost SavingEdi Saputra
 
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...apidays
 
Powerful Google developer tools for immediate impact! (2023-24 C)
Powerful Google developer tools for immediate impact! (2023-24 C)Powerful Google developer tools for immediate impact! (2023-24 C)
Powerful Google developer tools for immediate impact! (2023-24 C)wesley chun
 
A Year of the Servo Reboot: Where Are We Now?
A Year of the Servo Reboot: Where Are We Now?A Year of the Servo Reboot: Where Are We Now?
A Year of the Servo Reboot: Where Are We Now?Igalia
 
presentation ICT roal in 21st century education
presentation ICT roal in 21st century educationpresentation ICT roal in 21st century education
presentation ICT roal in 21st century educationjfdjdjcjdnsjd
 
Automating Google Workspace (GWS) & more with Apps Script
Automating Google Workspace (GWS) & more with Apps ScriptAutomating Google Workspace (GWS) & more with Apps Script
Automating Google Workspace (GWS) & more with Apps Scriptwesley chun
 
AWS Community Day CPH - Three problems of Terraform
AWS Community Day CPH - Three problems of TerraformAWS Community Day CPH - Three problems of Terraform
AWS Community Day CPH - Three problems of TerraformAndrey Devyatkin
 
MS Copilot expands with MS Graph connectors
MS Copilot expands with MS Graph connectorsMS Copilot expands with MS Graph connectors
MS Copilot expands with MS Graph connectorsNanddeep Nachan
 
Real Time Object Detection Using Open CV
Real Time Object Detection Using Open CVReal Time Object Detection Using Open CV
Real Time Object Detection Using Open CVKhem
 
2024: Domino Containers - The Next Step. News from the Domino Container commu...
2024: Domino Containers - The Next Step. News from the Domino Container commu...2024: Domino Containers - The Next Step. News from the Domino Container commu...
2024: Domino Containers - The Next Step. News from the Domino Container commu...Martijn de Jong
 
Strategies for Landing an Oracle DBA Job as a Fresher
Strategies for Landing an Oracle DBA Job as a FresherStrategies for Landing an Oracle DBA Job as a Fresher
Strategies for Landing an Oracle DBA Job as a FresherRemote DBA Services
 
A Beginners Guide to Building a RAG App Using Open Source Milvus
A Beginners Guide to Building a RAG App Using Open Source MilvusA Beginners Guide to Building a RAG App Using Open Source Milvus
A Beginners Guide to Building a RAG App Using Open Source MilvusZilliz
 
AXA XL - Insurer Innovation Award Americas 2024
AXA XL - Insurer Innovation Award Americas 2024AXA XL - Insurer Innovation Award Americas 2024
AXA XL - Insurer Innovation Award Americas 2024The Digital Insurer
 
Exploring the Future Potential of AI-Enabled Smartphone Processors
Exploring the Future Potential of AI-Enabled Smartphone ProcessorsExploring the Future Potential of AI-Enabled Smartphone Processors
Exploring the Future Potential of AI-Enabled Smartphone Processorsdebabhi2
 
ICT role in 21st century education and its challenges
ICT role in 21st century education and its challengesICT role in 21st century education and its challenges
ICT role in 21st century education and its challengesrafiqahmad00786416
 
Apidays New York 2024 - Scaling API-first by Ian Reasor and Radu Cotescu, Adobe
Apidays New York 2024 - Scaling API-first by Ian Reasor and Radu Cotescu, AdobeApidays New York 2024 - Scaling API-first by Ian Reasor and Radu Cotescu, Adobe
Apidays New York 2024 - Scaling API-first by Ian Reasor and Radu Cotescu, Adobeapidays
 

Recently uploaded (20)

DBX First Quarter 2024 Investor Presentation
DBX First Quarter 2024 Investor PresentationDBX First Quarter 2024 Investor Presentation
DBX First Quarter 2024 Investor Presentation
 
Architecting Cloud Native Applications
Architecting Cloud Native ApplicationsArchitecting Cloud Native Applications
Architecting Cloud Native Applications
 
Manulife - Insurer Transformation Award 2024
Manulife - Insurer Transformation Award 2024Manulife - Insurer Transformation Award 2024
Manulife - Insurer Transformation Award 2024
 
How to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected WorkerHow to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected Worker
 
Repurposing LNG terminals for Hydrogen Ammonia: Feasibility and Cost Saving
Repurposing LNG terminals for Hydrogen Ammonia: Feasibility and Cost SavingRepurposing LNG terminals for Hydrogen Ammonia: Feasibility and Cost Saving
Repurposing LNG terminals for Hydrogen Ammonia: Feasibility and Cost Saving
 
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
 
Powerful Google developer tools for immediate impact! (2023-24 C)
Powerful Google developer tools for immediate impact! (2023-24 C)Powerful Google developer tools for immediate impact! (2023-24 C)
Powerful Google developer tools for immediate impact! (2023-24 C)
 
A Year of the Servo Reboot: Where Are We Now?
A Year of the Servo Reboot: Where Are We Now?A Year of the Servo Reboot: Where Are We Now?
A Year of the Servo Reboot: Where Are We Now?
 
presentation ICT roal in 21st century education
presentation ICT roal in 21st century educationpresentation ICT roal in 21st century education
presentation ICT roal in 21st century education
 
Automating Google Workspace (GWS) & more with Apps Script
Automating Google Workspace (GWS) & more with Apps ScriptAutomating Google Workspace (GWS) & more with Apps Script
Automating Google Workspace (GWS) & more with Apps Script
 
AWS Community Day CPH - Three problems of Terraform
AWS Community Day CPH - Three problems of TerraformAWS Community Day CPH - Three problems of Terraform
AWS Community Day CPH - Three problems of Terraform
 
MS Copilot expands with MS Graph connectors
MS Copilot expands with MS Graph connectorsMS Copilot expands with MS Graph connectors
MS Copilot expands with MS Graph connectors
 
Real Time Object Detection Using Open CV
Real Time Object Detection Using Open CVReal Time Object Detection Using Open CV
Real Time Object Detection Using Open CV
 
2024: Domino Containers - The Next Step. News from the Domino Container commu...
2024: Domino Containers - The Next Step. News from the Domino Container commu...2024: Domino Containers - The Next Step. News from the Domino Container commu...
2024: Domino Containers - The Next Step. News from the Domino Container commu...
 
Strategies for Landing an Oracle DBA Job as a Fresher
Strategies for Landing an Oracle DBA Job as a FresherStrategies for Landing an Oracle DBA Job as a Fresher
Strategies for Landing an Oracle DBA Job as a Fresher
 
A Beginners Guide to Building a RAG App Using Open Source Milvus
A Beginners Guide to Building a RAG App Using Open Source MilvusA Beginners Guide to Building a RAG App Using Open Source Milvus
A Beginners Guide to Building a RAG App Using Open Source Milvus
 
AXA XL - Insurer Innovation Award Americas 2024
AXA XL - Insurer Innovation Award Americas 2024AXA XL - Insurer Innovation Award Americas 2024
AXA XL - Insurer Innovation Award Americas 2024
 
Exploring the Future Potential of AI-Enabled Smartphone Processors
Exploring the Future Potential of AI-Enabled Smartphone ProcessorsExploring the Future Potential of AI-Enabled Smartphone Processors
Exploring the Future Potential of AI-Enabled Smartphone Processors
 
ICT role in 21st century education and its challenges
ICT role in 21st century education and its challengesICT role in 21st century education and its challenges
ICT role in 21st century education and its challenges
 
Apidays New York 2024 - Scaling API-first by Ian Reasor and Radu Cotescu, Adobe
Apidays New York 2024 - Scaling API-first by Ian Reasor and Radu Cotescu, AdobeApidays New York 2024 - Scaling API-first by Ian Reasor and Radu Cotescu, Adobe
Apidays New York 2024 - Scaling API-first by Ian Reasor and Radu Cotescu, Adobe
 

Perspective plan preparation 2

  • 1. GUIDELINES FOR PREPARATION OF PERSPECTIVE PLAN NATIONAL FOOD FOR WORK PROGRAMME (NFFWP) TRAINING OF TRAINERS Dr. N. Sai Bhaskar Reddy AMR-APARD, RAJENDRANAGAR, HYDERABAD
  • 2. Objective - comprehensive perspective plan of five years  That would enable develop all the Panchayats of the 150 most backward districts during the 5 years period of 2005-2010 in such a way that there is visible impact on the major problems of each Panchayat and a sound base is created for self sustaining economy to remove poverty and bring these Districts at least at par with other developed areas of the state and the country.
  • 3. It will facilitate optimizing all resources available under all the developmental programmes operational at the panchayat level  To provide best possible and meaningful option for convergence/dovetailing of all such programmes to derive maximum benefit in favour of the rural poor especially with regard to generation of employment opportunities both in terms of wage and self employment through creation of need based optimum infrastructure at the panchayat level in the short term and develop self sustaining robust panchayat economy In the long run.
  • 4. Preparing the Perspective Plan  Survey each village and panchayat in the district to collect data on A. Existing economy infrastructure needs and to B. Assess feasibility of projects to be included in the plan  Rough cost estimate for project/works suggested must be given based on acceptable parameters and they may be indicated in the plan document.
  • 5. The people involved in perspective plan preparation  Consolidation and preparation of final document – AMR-APARD  Training of trainers at District level (~40 officers) – AMR-APARD  TOTs – Senior Level Officers / special officers in the District  Training of Mandal level resource persons – ToTs  Perspective plan preparation of each village with the participation of primary stakeholders and facilitation by Mandal level resource persons.
  • 6. PERSPECTIVE PLAN OF THE DISTRICT The perspective plan will be a comprehensive document with several chapters CHAPTER-1 The information for the district as a whole on - demography - SC/ST, women and children population with work force divided into employed, semi-employed, unemployed, occupational distribution, month wise rainfall distribution, depth of water table, depletion rate, gender-wise illiteracy, main crops, number of crops per year, per hectare productivity, type of soil, agriculture productivity per worker, distribution of average land holding, average size of tilling, distribution of commercial/Regional Rural Bank, availability of bank branches per sq. km, potential occupation, service and industry.
  • 7. CHAPTER-II Scheme-wise availability of resources of the district as a whole in respect of all employment and development oriented Programme such as Swarnajayanti Gram Swarozgar Yojana (SGSY), Rashtriya Sam Vikas Yojana (RSVY), Watershed development programmes (such as IWDP, DPAP, DDP) PMRY (its share for rural segment), Rural Employment Generation Programme of KVIC, Sampoorna Grameena Rozgar Yojana (SGRY) MPLAD, MLALAD NFFWP and all other Centrally and state sponsored programmes
  • 8. Block-wise breakup of distribution/availability of resources under the above programmes along with the present status of number of persons unemployed/ semi- employed may be given.
  • 9. Location/area specific kinds/types of infrastructure, which are expected in the Panchayat. (i) One panchayat Ghar (ii) One primary/secondary school building sufficient for the number of children studying. (iii) One low cost storage go down for storing food grains (iv) Tube/open wells (whichever is relevant in that area) for drinking / irrigation purpose. (v) Internal roads providing connectivity with main roads (vi) Drainage / nallah to drain out extra water in the water logged/flood prone areas (vii) Dairy/Veterinary development infrastructure. (viii) Erection of permanent /pucca embankment for flood protection
  • 10. (IX) Small check dams, water conservation activities like digging of ponds/percolation tanks and de-silting of ponds (x) Strengthening of marketing infrastructure at local Panchayat haats / market such as construction of permanent sheds and low cost community storage godowns for safe storage of goods etc. (xi) Individual/community horticulture/social forestry development. (xii) Any other facility considered essential on the local needs. * - The above list of infrastructure is only illustrative and not exhaustive. It is possible that some of the above infrastructure may not be suitable for a particular state / district / panchayat but may be relevant in other. As such, the above list may be modified and prepared taking into account local needs and aspirations.
  • 11. CHAPTER-III  Details on Panchayat –wise (i) list of infrastructure already existing and (ii). List of infrastructure that are missing out of the list given at Section-B, Chapter –11 (iii) requirement of resources for creation of missing infrastructure along with Programme-wise inflow/share of the Panchayat out of all development programmes listed at Section-A of chapter-11 and (iv) estimated employment generation in terms of both self and wage employment while creating missing infrastructure .  The above information is to be given year-wise.
  • 12. While assessing resource inflow from all sources, 15% for maintenance of assets already created /being created be shown separately and as such only 85% of the total inflow may be taken in to account for showing resource inflow for creation of assets.  The above Panchayat–wise list of missing infrastructure have to be prepared in a manner that each missing infrastructure will give a clear cut idea under which Programme it is proposed with estimated cost and the number of expected beneficiaries to be covered under self and wage employment.
  • 13. Incase of wage employment, number of man-day’s generation is to be divided by 100 to arrive at number of persons to be employed.  All activities /works shown under the existing Programme have to be implemented in accordance with their respective Programme guidelines. If any activity which is permissible under more than one Programme, it may be shown under that Programme which has larger share for that Panchayat.  It should, however, be ensured that one activity is shown under one Programme only with the stipulation that is completed during one financial year it self. Spillover to the next year may be indicated in exceptional cases where inflow of resources is limited during the year.  Estimated cost may be shown increased 5 to 10% every year while showing year-wise activities to be taken up.
  • 14. Programme  PMRY  SGRY  REGP  SGSY  MPLAD  RSVY  MLALAD  IWDP  Add more  DPAP scheme of  DDP Central/state if any
  • 15. Missing Infrastructure with Priority(Shelf of Projects)(for example)  Check dam to store water  Drainage/ Nallah to drain extra water in water logged/flood affected areas  Digging of pond  Land Development of Common Wasteland area  Percolation Wells  Storage Godown  and so on.
  • 16. Employment Generation  Under Self Employment Programmes (NO. of expected beneficiaries)  Wage Employment Programmes  a. Number of expected man days to be generated (in numbers)  b. Number of expected beneficiaries getting employment ( (a) above/100)  Area development programme  a) Number of expected beneficiaries (in Numbers)  b) (i) Number of expected mandays generated (in numbers)  b) (ii) Number expected mandays converted in to number of persons( (b) (i) above/100)
  • 17. CHAPTER-IV  Block-wise exercise by consolidating panchayat–wise information under respective Block (Mandal) may be take-up.  Summary for each Block separately to indicate missing  Infrastructure wise details giving  Year wise cost estimates and  Expected employment generation may be given
  • 18. Missing Infrastructure  Drainage (in waterlogged/flood affected areas) (in KM)  Low cost community food grains storage godowns  High school Building  Strengthening/construction of permanent river embankment (In KM)  Check dams  Digging of ponds/desilting  Horticulture/Social forestry (a)Individual (b)Community  Dairy Development  (and so on)
  • 19. CHAPTER-V  Annual Action plans for the NFFWP for the next five years based on the perspective plan.  Segregate Panchayat-wise activities /works those indicated against the NFFWP quota.  Panchayat-wise and year-wise works/activities to be taken up under the NFFWP with clear cut prioritization will have to be given.
  • 20. Name of activities in priority order (for example)  Checkdams  Digging of ponds/desilting  Drainage (in waterlogged/flood affected areas)  Development & Bunding of degraded lands  Other water harvesting structures (mention type of structure)  (and so on)
  • 21. CHAPTER-VI  The success of the program will be quantified based on the following type of parameters on pre (as on 2005) and post (as on 2010) perspective plan assessment.
  • 22. Item (for Example) Status at the Estimated Total time of status after Increase/Decr preparation of the ease perspective completion plan of the five Irrigated areas (In Ha.) year plan period Water table (In Feet) (2010) Agricultural output of differenft crops (In per Ha) Diversification of area to cash crops (In Ha) Nutrition level Rural urban migration (In persons) Rural poverty ratio (In % age) Village connectivity to Towns (in %age)