SlideShare uma empresa Scribd logo
1 de 18
Baixar para ler offline
Copyright ® 2010, Lewis & Fowler, All Rights Reserved




                                                        Thank you for inviting me to your
                                                        Chapter meeting tonight. I'm speaking
                                                        tomorrow at the Symposium on two
                                                        topics – Establishing the Performance
                                                        Measurement Baseline and the
                                                        Immutable Principles of Project
                                                        Management.
                                                        Both of these topics are critical to
                                                        increasing the probability of success for
                                                        your project.
                                                        Both these topics are founded on a set
                                                        of principles that have emerged over the
                                                        past decade in the aerospace and
                                                        defense business and are now moving
                                                        into commercial project management
                                                        processes.




PMI Fort Worth, Chapter Meeting, 15 July, 2010                                                 1/18
Copyright ® 2010, Lewis & Fowler, All Rights Reserved




                                                        There are four outcomes for this talk.
                                                        1. I’m going to suggest there are gaps
                                                           in the understanding of the elements
                                                           of a project management process.
                                                           Not that our current PMBOK® based
                                                           processes are in error, but the units
                                                           of measure of progress, DONE,
                                                           effectiveness and performance are
                                                           missing.
                                                        1. That connecting the dots between
                                                           cost, schedule, and Technical
                                                           Performance Measures are needed
                                                           to improve the probability of
                                                           success.
                                                        2. Making these connections lives in
                                                           the discipline of Systems
                                                           Engineering.
                                                        3. Once these connections have been
                                                           made, we need to realize that all the
                                                           programmatic elements are random
                                                           variables, and we need to act
                                                           accordingly.




PMI Fort Worth, Chapter Meeting, 15 July, 2010                                                   2/18
Copyright ® 2010, Lewis & Fowler, All Rights Reserved




                                                        We’re all project managers or have
                                                        some relation to project management.
                                                        What’s the core problems we’ve seen in
                                                        the past and will likely see in the future
                                                        around project management.
                                                        Here’s a popular list I’ve encountered
                                                        over the years.
                                                        You’re list many have some of these or
                                                        even better ones.
                                                        No matter what the list is, any project
                                                        management framework must address
                                                        them head on if you’re going to have a
                                                        chance to end successfully.
                                                        I’m going to show you five principles of
                                                        project management that have served us
                                                        well over the years.
                                                        I’m going to suggest these principles are
                                                        immutable. That is they are the same for
                                                        every project management domain and
                                                        context in that domain.
                                                        From mega projects in construction and
                                                        defense to small agile software
                                                        development projects with the customer
                                                        in the same room.
                                                        Immutable = not subject or susceptible
                                                        to change or variation in form or quality
                                                        or nature.




PMI Fort Worth, Chapter Meeting, 15 July, 2010                                                   3/18
Copyright ® 2010, Lewis & Fowler, All Rights Reserved




                                                        So how can we put these principles in
                                                        practice?
                                                        The anchor to the practices that are
                                                        guided by the principles is to focus on
                                                        the Deliverables.
                                                        All other elements of the project are
                                                        secondary or possibly unimportant to
                                                        the deliverables.
                                                        This paradigm may appear different than
                                                        the process groups and knowledge areas
                                                        of PMBOK®.
                                                        These PMBOK® elements are certainly in
                                                        support of this deliverables view, but it
                                                        may not be explicitly stated in a way we
                                                        can “connect the dots.”
                                                        When we leave tonight I’m going to
                                                        suggest you’ll have a different paradigm
                                                        when you look at PMBOK®
                                                        One focused on “what does DONE look
                                                        like.”
                                                        How to measure DONE in units
                                                        meaningful to the buyer.




PMI Fort Worth, Chapter Meeting, 15 July, 2010                                                    4/18
Copyright ® 2010, Lewis & Fowler, All Rights Reserved




                                                        With this notion in mind, we can define
                                                        what DONE looks like.
                                                        It is defined when we answer these five
                                                        (5) questions.
                                                        These questions are core to every
                                                        project. They the are source of processes
                                                        that define the immutable principles.
                                                        They must be answered for success.
                                                        When they are not asked or not
                                                        answered the probability of success is
                                                        lowered, many times lowered to the
                                                        point that the project goes off track and
                                                        possibly fails.
                                                        We’ll see in the coming slides how these
                                                        questions and their answers can be your
                                                        means to increasing the probability of
                                                        success.




PMI Fort Worth, Chapter Meeting, 15 July, 2010                                                5/18
Copyright ® 2010, Lewis & Fowler, All Rights Reserved




                                                        The five irreducible principles of project
                                                        management that answer the previous
                                                        questions are:
                                                        1. Know where you are going by
                                                           defining “done” at some point in the
                                                           future. This point may be far in the
                                                           future – months or years from now.
                                                           Or closer in the future, days or weeks
                                                           from now.
                                                        2. Have some kind of plan to get to
                                                           where you are going. This plan can be
                                                           simple or it can be complex. The
                                                           fidelity of the plan depends on the
                                                           tolerance for risk by the users of the
                                                           plan.
                                                        3. Understand the resources needed to
                                                           execute the plan. How much time
                                                           and money is needed to reach the
                                                           destination. This can be fixed or it can
                                                           be variable.
                                                        4. Identify the impediments to progress
                                                           along the way to the destination.
                                                           Have some means of removing,
                                                           avoiding, or ignoring these
                                                           impediments.
                                                        5. Have some way to measure your
                                                           planned progress, not just your
                                                           progress. Progress to Plan must be
                                                           measured in units of physical percent
                                                           complete.



PMI Fort Worth, Chapter Meeting, 15 July, 2010                                                 6/18
Copyright ® 2010, Lewis & Fowler, All Rights Reserved




                                                        The question “where are we going” must
                                                        be answered in ways meaningful to the
                                                        buyer.
                                                        The answer can be in the form of a
                                                        needed capability.
                                                        This answers the question, “What
                                                        capabilities to we need to posses to call
                                                        the project DONE?”
                                                        Or what are the requirements that need
                                                        to be fulfilled to call the project DONE?
                                                        The answer to this question is a PLAN.
                                                        The PLAN says where we are going. It
                                                        does not say how we’re going to get
                                                        there, just where.
                                                        One critical missing element for many
                                                        troubled projects is the answer to the
                                                        question WHY. WHY are we doing this
                                                        project?
                                                        The PLAN comes after we answer the
                                                        question WHY. This answer comes from
                                                        the business strategy or mission strategy
                                                        of the project and is outside the context
                                                        of the five (5) immutable processes.




PMI Fort Worth, Chapter Meeting, 15 July, 2010                                                 7/18
Copyright ® 2010, Lewis & Fowler, All Rights Reserved




                                                        HOW to get there is described in the
                                                        Schedule.
                                                        Let’s walk through an example.
                                                        Let’s pretend we want to go on a hike. A
                                                        nice hike to the saddle just to the right
                                                        of the peak above this lake. That saddle
                                                        is Pawnee Pass. I
                                                        t’s just west of Boulder Colorado, and a
                                                        bit south of Rocky Mountain National
                                                        Park.
                                                        We’d like to go to Pawnee Pass in a
                                                        single day – there and back. Not get too
                                                        wet if it rains. Not be too hungry. And
                                                        have a good time along the way with our
                                                        hiking group.
                                                        The PLAN is to summit in a day and
                                                        return safely. The SCHEDULE is the steps
                                                        needed to actually reach the summit and
                                                        return.
                                                        This SCHEDULE includes all the work
                                                        effort needed to summit, the order in
                                                        which we’d perform these work
                                                        element, the dependencies between the
                                                        elements, any resources we’ll need for
                                                        success, and both schedule and cost
                                                        margins.




PMI Fort Worth, Chapter Meeting, 15 July, 2010                                                 8/18
Copyright ® 2010, Lewis & Fowler, All Rights Reserved




                                                        With the destination in mind and
                                                        schedule of all the activities needed to
                                                        reach our destination, do we know if we
                                                        have everything we need to get there?
                                                        This answer includes all the resources,
                                                        technology, processes, and other items
                                                        that will enable success.
                                                        These dependencies must be identified
                                                        in the Master Schedule.
                                                        For example in NASA programs –
                                                        Government Furnished Equipment is
                                                        common.
                                                        Same for external dependencies in
                                                        Enterprise IT projects.
                                                        These dependencies have their own
                                                        schedules and the credibility of those
                                                        schedules must be assessed in the same
                                                        way we are going to do in the next steps.
                                                        This “all in” System of Systems approach
                                                        is needed to collect “all” the elements of
                                                        the project PLAN and SCHEDULE.




PMI Fort Worth, Chapter Meeting, 15 July, 2010                                                 9/18
Copyright ® 2010, Lewis & Fowler, All Rights Reserved



                                                        There are always impediments to
                                                        progress.
                                                        It’s just part of a project. It’s actually
                                                        part of everything we do as project
                                                        managers.
                                                        But do we know them? Can we name
                                                        them and what their impact might be on
                                                        the project?
                                                        Do we have some way of “handling”
                                                        these impediments – the risks to the
                                                        project.
                                                        There are of course the named ways:
                                                        1.Risk avoidance eliminates the sources
                                                          of high risk and replaces them with a
                                                          lower-risk solution.
                                                        2.Risk transfer is the reallocation of risk
                                                          from one part of the system to
                                                          another.
                                                        3.Risk control manages the risk in a
                                                          manner that reduces the probability /
                                                          likelihood of its occurrence and / or
                                                          minimizes the risk's effect on the
                                                          program.
                                                        4.Risk assumption is the
                                                          acknowledgment of the existence of a
                                                          particular risk situation and a
                                                          conscious decision to accept the
                                                          associated level of risk without
                                                          engaging in any special efforts to
                                                          control it.



PMI Fort Worth, Chapter Meeting, 15 July, 2010                                                       10/18
Copyright ® 2010, Lewis & Fowler, All Rights Reserved


                                                        Here’s where many projects start their
                                                        path toward the ditch.
                                                        Progress can only measured in the
                                                        assessment of Physical Percent
                                                        Complete. The percent of the Planned
                                                        progress.
                                                         How far along should we be at this
                                                          point in the project?
                                                         Where are we actually along the path
                                                          to complete?
                                                         What was our planned progress at this
                                                          point in the project?
                                                        The unit of measure for Physical Percent
                                                        Complete starts with tangible
                                                        evidentiary Materials brought to the
                                                        table and shown to project participants.
                                                        The passage of time and consumption of
                                                        resource is never a measure of progress
                                                        to plan.
                                                        This last approach is common in projects
                                                        that have gone off the rails.
                                                        When we are planning and scheduling
                                                        the project we need to define upfront
                                                        what these measures of percent
                                                        complete are. Predefining them.
                                                        Agreeing we measure progress with
                                                        them.
                                                        There can be no retroactive assessment
                                                        of progress to plan. Once defined the
                                                        measures of physical percent complete
                                                        are placed “on baseline,” and represent
                                                        the only assessment of progress.

PMI Fort Worth, Chapter Meeting, 15 July, 2010                                              11/18
Copyright ® 2010, Lewis & Fowler, All Rights Reserved




                                                        If we look back to the beginning of
                                                        tonight's talk to the 4+1 major activities
                                                        of Deliverables Based Planning® and
                                                        connect them with the five (5)
                                                        immutable principles of managing any
                                                        project, we have to look for the evidence
                                                        that we’re following the processes using
                                                        the principles.
                                                        You may have other evidence.
                                                        No matter what you have, there has to
                                                        be artifacts showing that you’ve done
                                                        the work to answer the 4+1 questions
                                                        and satisfied the five (5) immutable
                                                        principles.
                                                        One critical concept in any successful
                                                        project management method is
                                                        “evidence based” assessment of
                                                        progress.
                                                        Personal opinion, verbal discussion,
                                                        management statements are not
                                                        acceptable.
                                                        Only tangible evidence of progress to
                                                        plan is acceptable.




PMI Fort Worth, Chapter Meeting, 15 July, 2010                                                 12/18
Copyright ® 2010, Lewis & Fowler, All Rights Reserved

                                                        Each of these pieces of evidence must
                                                        provide some level of credibility.
                                                        One method of measuring this credibility
                                                        and its tangible value is through a
                                                        systems engineering paradigm.
                                                        This by the way is one of the difficulties
                                                        agile processes run into.
                                                        They mention “value” but don’t have
                                                        units of measure for that value.
                                                        Independent of that, here’s how we do it
                                                        in the systems engineering world.
                                                        MoE’s are defined by the customer.
                                                        They are the measures of the capabilities
                                                        needed to fulfill some mission.
                                                        MoP’s are defined by the supplier.
                                                        They describe the behaviors needed to
                                                        fulfill the mission.
                                                        The KPP’s are the numbers we’ll assign
                                                        to the MoP’s.
                                                        The Technical Performance Measures
                                                        (TPM) are the collection of these
                                                        individual elements.




PMI Fort Worth, Chapter Meeting, 15 July, 2010                                                13/18
Copyright ® 2010, Lewis & Fowler, All Rights Reserved




                                                        All this effort, definitions, processes ,and
                                                        information has only one goal.
                                                        The goal is to describe in a tangibly
                                                        measureable way what DONE looks like.
                                                        This is the only reason for all these
                                                        processes.
                                                        This is the role of the Project Manager
                                                        and the Project Controls staff.
                                                        To define what DONE looks like, manage
                                                        all the resources toward that
                                                        description, handle all the risks and
                                                        impediments to progress.
                                                        All of this starts – and ends – with what
                                                        the customer needs in terms of
                                                        “capabilities.”




PMI Fort Worth, Chapter Meeting, 15 July, 2010                                                  14/18
Copyright ® 2010, Lewis & Fowler, All Rights Reserved




                                                        If we fail to provide credible answers to
                                                        the five (5) immutable project
                                                        management processes, then we’re
                                                        headed in the wrong direction.
                                                         We will not be able to measure our
                                                          progress to plan.
                                                         We will have not defined what
                                                          business or mission capabilities are
                                                          needed for success.
                                                         We won’t know what the
                                                          requirements are to fulfill these
                                                          needed capabilities.
                                                         We'll have failed to identify and
                                                          handle the impediments to our
                                                          progress to plan.
                                                        Our only source of success will be HOPE.
                                                        Hope that we’ll discover these as we go.
                                                        Hope, that the potential impediments to
                                                        progress won’t come true.
                                                        Hope that our customer can articulate
                                                        what DONE looks like for us along the
                                                        way.
                                                        When Hope is are strategy, we’ve
                                                        started on the road to failure.




PMI Fort Worth, Chapter Meeting, 15 July, 2010                                               15/18
Copyright ® 2010, Lewis & Fowler, All Rights Reserved




                                                        In closing here’s the next level down for
                                                        Deliverables Based Planning®.
                                                        Each of the four (4) processes shown
                                                        here – plus the continuous risk
                                                        management has major sub-processes,
                                                        which also have sub-sub-processes .
                                                        There are 74 processes in all.
                                                        I have handouts that cover all these
                                                        processes, you’re welcome to.




PMI Fort Worth, Chapter Meeting, 15 July, 2010                                                 16/18
Copyright ® 2010, Lewis & Fowler, All Rights Reserved




                                                        So with that brief overview of
                                                        Deliverables Based Planning® and its
                                                        application to projects in general, are
                                                        there any questions I can answer in the
                                                        short time we have left?
                                                        My colleague and I will be here for more
                                                        questions and answers.
                                                        Tomorrow the Symposium Work Shops
                                                        will delve into these topics in greater
                                                        detail, I look forward to seeing you
                                                        there.




PMI Fort Worth, Chapter Meeting, 15 July, 2010                                              17/18
Copyright ® 2010, Lewis & Fowler, All Rights Reserved




                                                        Here’s my contact information if you’re
                                                        unable to attend tomorrow’s work shop
                                                        or would like more information about
                                                        these processes.




PMI Fort Worth, Chapter Meeting, 15 July, 2010                                             18/18

Mais conteúdo relacionado

Mais procurados

Service Support Quick Reference
Service Support Quick ReferenceService Support Quick Reference
Service Support Quick Referenceguest5f36a4
 
Telecommunications Industry CEO's Discuss Capitalizing on Complexity
Telecommunications Industry CEO's Discuss Capitalizing on ComplexityTelecommunications Industry CEO's Discuss Capitalizing on Complexity
Telecommunications Industry CEO's Discuss Capitalizing on ComplexityIBMTelecom
 
TOP-Change for the fifth technology revolution
TOP-Change for the fifth technology revolutionTOP-Change for the fifth technology revolution
TOP-Change for the fifth technology revolutionLeon Dohmen
 
Ch2 pressman
Ch2   pressmanCh2   pressman
Ch2 pressmansuresh461
 
Accu2010 archrefactoring
Accu2010 archrefactoringAccu2010 archrefactoring
Accu2010 archrefactoringMichael Stal
 
Newcastel International Airport It Strategy
Newcastel International Airport It StrategyNewcastel International Airport It Strategy
Newcastel International Airport It Strategymichaelking
 
One XP Experience: Introducing Agile (XP) Software Development into a Culture...
One XP Experience: Introducing Agile (XP) Software Development into a Culture...One XP Experience: Introducing Agile (XP) Software Development into a Culture...
One XP Experience: Introducing Agile (XP) Software Development into a Culture...David Leip
 
Eggert.joe
Eggert.joeEggert.joe
Eggert.joeNASAPMC
 
Gen sessionthomas.riskofsystemproblemfinal23feb12
Gen sessionthomas.riskofsystemproblemfinal23feb12Gen sessionthomas.riskofsystemproblemfinal23feb12
Gen sessionthomas.riskofsystemproblemfinal23feb12NASAPMC
 
Jim.free
Jim.freeJim.free
Jim.freeNASAPMC
 
Beyond the Scrum - I
Beyond the Scrum - IBeyond the Scrum - I
Beyond the Scrum - IAdam Monago
 
IT GOVERNANCE CONSULTING
IT GOVERNANCE CONSULTINGIT GOVERNANCE CONSULTING
IT GOVERNANCE CONSULTINGArul Nambi
 
Realisor introduction august 2012
Realisor introduction   august 2012Realisor introduction   august 2012
Realisor introduction august 2012Wovex Limited
 
Kirsch.mike
Kirsch.mikeKirsch.mike
Kirsch.mikeNASAPMC
 
10%2 D04%20 Art%20 Bp%20 Maturity%20 Model%20%2 D%20 Fisher%2 Epdf
10%2 D04%20 Art%20 Bp%20 Maturity%20 Model%20%2 D%20 Fisher%2 Epdf10%2 D04%20 Art%20 Bp%20 Maturity%20 Model%20%2 D%20 Fisher%2 Epdf
10%2 D04%20 Art%20 Bp%20 Maturity%20 Model%20%2 D%20 Fisher%2 Epdfshinikju
 
GROM Overview
GROM OverviewGROM Overview
GROM OverviewTADAM
 
Bizier.brenda
Bizier.brendaBizier.brenda
Bizier.brendaNASAPMC
 

Mais procurados (20)

Service Support Quick Reference
Service Support Quick ReferenceService Support Quick Reference
Service Support Quick Reference
 
Telecommunications Industry CEO's Discuss Capitalizing on Complexity
Telecommunications Industry CEO's Discuss Capitalizing on ComplexityTelecommunications Industry CEO's Discuss Capitalizing on Complexity
Telecommunications Industry CEO's Discuss Capitalizing on Complexity
 
TOP-Change for the fifth technology revolution
TOP-Change for the fifth technology revolutionTOP-Change for the fifth technology revolution
TOP-Change for the fifth technology revolution
 
Ch2 pressman
Ch2   pressmanCh2   pressman
Ch2 pressman
 
Accu2010 archrefactoring
Accu2010 archrefactoringAccu2010 archrefactoring
Accu2010 archrefactoring
 
Newcastel International Airport It Strategy
Newcastel International Airport It StrategyNewcastel International Airport It Strategy
Newcastel International Airport It Strategy
 
SEI Overview Dr. Paul Nielsen
SEI Overview Dr. Paul NielsenSEI Overview Dr. Paul Nielsen
SEI Overview Dr. Paul Nielsen
 
One XP Experience: Introducing Agile (XP) Software Development into a Culture...
One XP Experience: Introducing Agile (XP) Software Development into a Culture...One XP Experience: Introducing Agile (XP) Software Development into a Culture...
One XP Experience: Introducing Agile (XP) Software Development into a Culture...
 
Eggert.joe
Eggert.joeEggert.joe
Eggert.joe
 
Gen sessionthomas.riskofsystemproblemfinal23feb12
Gen sessionthomas.riskofsystemproblemfinal23feb12Gen sessionthomas.riskofsystemproblemfinal23feb12
Gen sessionthomas.riskofsystemproblemfinal23feb12
 
Jim.free
Jim.freeJim.free
Jim.free
 
Environmental stress screening
Environmental stress screeningEnvironmental stress screening
Environmental stress screening
 
MCP1
MCP1MCP1
MCP1
 
Beyond the Scrum - I
Beyond the Scrum - IBeyond the Scrum - I
Beyond the Scrum - I
 
IT GOVERNANCE CONSULTING
IT GOVERNANCE CONSULTINGIT GOVERNANCE CONSULTING
IT GOVERNANCE CONSULTING
 
Realisor introduction august 2012
Realisor introduction   august 2012Realisor introduction   august 2012
Realisor introduction august 2012
 
Kirsch.mike
Kirsch.mikeKirsch.mike
Kirsch.mike
 
10%2 D04%20 Art%20 Bp%20 Maturity%20 Model%20%2 D%20 Fisher%2 Epdf
10%2 D04%20 Art%20 Bp%20 Maturity%20 Model%20%2 D%20 Fisher%2 Epdf10%2 D04%20 Art%20 Bp%20 Maturity%20 Model%20%2 D%20 Fisher%2 Epdf
10%2 D04%20 Art%20 Bp%20 Maturity%20 Model%20%2 D%20 Fisher%2 Epdf
 
GROM Overview
GROM OverviewGROM Overview
GROM Overview
 
Bizier.brenda
Bizier.brendaBizier.brenda
Bizier.brenda
 

Destaque

Physical Percent Complete - june 2010 (6)
Physical Percent Complete - june 2010 (6)Physical Percent Complete - june 2010 (6)
Physical Percent Complete - june 2010 (6)Glen Alleman
 
Risk management processes
Risk management processesRisk management processes
Risk management processesGlen Alleman
 
Customer Intelligence & Social Media
Customer Intelligence & Social MediaCustomer Intelligence & Social Media
Customer Intelligence & Social MediaAmplified Analytics
 
Establishing the performance measurement baseline (pmi fort worth)(v4)
Establishing the performance measurement baseline (pmi fort worth)(v4)Establishing the performance measurement baseline (pmi fort worth)(v4)
Establishing the performance measurement baseline (pmi fort worth)(v4)Glen Alleman
 
Inversion of Control
Inversion of ControlInversion of Control
Inversion of ControlGlen Alleman
 
Systems Engineering in One Picture
Systems Engineering in One PictureSystems Engineering in One Picture
Systems Engineering in One PictureGlen Alleman
 
Fix you some bad estimation habits
Fix you some bad estimation habitsFix you some bad estimation habits
Fix you some bad estimation habitsTed M. Young
 
Principles of program governance
Principles of program governancePrinciples of program governance
Principles of program governanceGlen Alleman
 
UIKit User Interface Catalog (iOS 7)
UIKit User Interface Catalog (iOS 7)UIKit User Interface Catalog (iOS 7)
UIKit User Interface Catalog (iOS 7)Evgeny Belyaev
 
Immutable Principles Of Project Management (V7 Final Cmu)
Immutable Principles Of Project Management (V7 Final Cmu)Immutable Principles Of Project Management (V7 Final Cmu)
Immutable Principles Of Project Management (V7 Final Cmu)Glen Alleman
 
Cure for cost and schedule growth
Cure for cost and schedule growthCure for cost and schedule growth
Cure for cost and schedule growthGlen Alleman
 
Big data meets evm (submitted).pptx
Big data meets evm (submitted).pptxBig data meets evm (submitted).pptx
Big data meets evm (submitted).pptxGlen Alleman
 
The Social Shift Fund - Presentation
The Social Shift Fund - Presentation The Social Shift Fund - Presentation
The Social Shift Fund - Presentation Marine Aubin
 
Avoid software project horror stories - check the reality value of the estima...
Avoid software project horror stories - check the reality value of the estima...Avoid software project horror stories - check the reality value of the estima...
Avoid software project horror stories - check the reality value of the estima...Harold van Heeringen
 
A possible cure 2014 may9
A possible cure 2014 may9A possible cure 2014 may9
A possible cure 2014 may9Glen Alleman
 
Pedir lo mismo de diferentes maneras
Pedir lo mismo de diferentes manerasPedir lo mismo de diferentes maneras
Pedir lo mismo de diferentes manerasAntonio Salvadores
 
Architectured Centered Design
Architectured Centered DesignArchitectured Centered Design
Architectured Centered DesignGlen Alleman
 
UX for Lean Startups Sep 15
UX for Lean Startups Sep 15UX for Lean Startups Sep 15
UX for Lean Startups Sep 15Lane Goldstone
 
PM Chapter on Agile IT Project Management Methods
PM Chapter on Agile IT Project Management MethodsPM Chapter on Agile IT Project Management Methods
PM Chapter on Agile IT Project Management MethodsGlen Alleman
 

Destaque (20)

Physical Percent Complete - june 2010 (6)
Physical Percent Complete - june 2010 (6)Physical Percent Complete - june 2010 (6)
Physical Percent Complete - june 2010 (6)
 
Risk management processes
Risk management processesRisk management processes
Risk management processes
 
Customer Intelligence & Social Media
Customer Intelligence & Social MediaCustomer Intelligence & Social Media
Customer Intelligence & Social Media
 
Establishing the performance measurement baseline (pmi fort worth)(v4)
Establishing the performance measurement baseline (pmi fort worth)(v4)Establishing the performance measurement baseline (pmi fort worth)(v4)
Establishing the performance measurement baseline (pmi fort worth)(v4)
 
Inversion of Control
Inversion of ControlInversion of Control
Inversion of Control
 
Systems Engineering in One Picture
Systems Engineering in One PictureSystems Engineering in One Picture
Systems Engineering in One Picture
 
Fix you some bad estimation habits
Fix you some bad estimation habitsFix you some bad estimation habits
Fix you some bad estimation habits
 
Principles of program governance
Principles of program governancePrinciples of program governance
Principles of program governance
 
UIKit User Interface Catalog (iOS 7)
UIKit User Interface Catalog (iOS 7)UIKit User Interface Catalog (iOS 7)
UIKit User Interface Catalog (iOS 7)
 
Immutable Principles Of Project Management (V7 Final Cmu)
Immutable Principles Of Project Management (V7 Final Cmu)Immutable Principles Of Project Management (V7 Final Cmu)
Immutable Principles Of Project Management (V7 Final Cmu)
 
Universidades
Universidades Universidades
Universidades
 
Cure for cost and schedule growth
Cure for cost and schedule growthCure for cost and schedule growth
Cure for cost and schedule growth
 
Big data meets evm (submitted).pptx
Big data meets evm (submitted).pptxBig data meets evm (submitted).pptx
Big data meets evm (submitted).pptx
 
The Social Shift Fund - Presentation
The Social Shift Fund - Presentation The Social Shift Fund - Presentation
The Social Shift Fund - Presentation
 
Avoid software project horror stories - check the reality value of the estima...
Avoid software project horror stories - check the reality value of the estima...Avoid software project horror stories - check the reality value of the estima...
Avoid software project horror stories - check the reality value of the estima...
 
A possible cure 2014 may9
A possible cure 2014 may9A possible cure 2014 may9
A possible cure 2014 may9
 
Pedir lo mismo de diferentes maneras
Pedir lo mismo de diferentes manerasPedir lo mismo de diferentes maneras
Pedir lo mismo de diferentes maneras
 
Architectured Centered Design
Architectured Centered DesignArchitectured Centered Design
Architectured Centered Design
 
UX for Lean Startups Sep 15
UX for Lean Startups Sep 15UX for Lean Startups Sep 15
UX for Lean Startups Sep 15
 
PM Chapter on Agile IT Project Management Methods
PM Chapter on Agile IT Project Management MethodsPM Chapter on Agile IT Project Management Methods
PM Chapter on Agile IT Project Management Methods
 

Semelhante a PMI chapter meeting (v4)

Immutable principles of project management (fw pmi)(v4)
Immutable principles of project management (fw pmi)(v4)Immutable principles of project management (fw pmi)(v4)
Immutable principles of project management (fw pmi)(v4)Glen Alleman
 
Improving software economics - Top 10 principles of achieving agility at scale
Improving software economics - Top 10 principles of achieving agility at scaleImproving software economics - Top 10 principles of achieving agility at scale
Improving software economics - Top 10 principles of achieving agility at scaleIBM Rational software
 
Rhodes.donna
Rhodes.donnaRhodes.donna
Rhodes.donnaNASAPMC
 
10 tips for Chartering a Project
10 tips for Chartering a Project10 tips for Chartering a Project
10 tips for Chartering a ProjectGlen Alleman
 
Подборка о рисках ИТ-проектов
Подборка о рисках ИТ-проектовПодборка о рисках ИТ-проектов
Подборка о рисках ИТ-проектовAlexey Ivasyuk
 
Ev+agile=success (final v2)
Ev+agile=success (final v2)Ev+agile=success (final v2)
Ev+agile=success (final v2)Glen Alleman
 
Performance based management in a nut shell (austin pmi)(notes)
Performance based management in a nut shell (austin pmi)(notes)Performance based management in a nut shell (austin pmi)(notes)
Performance based management in a nut shell (austin pmi)(notes)Glen Alleman
 
Performance-Based Project Management In A Nut Shell
Performance-Based Project Management In A Nut ShellPerformance-Based Project Management In A Nut Shell
Performance-Based Project Management In A Nut ShellGlen Alleman
 
10 tips for chartering a project (v2)
10 tips for chartering a project (v2)10 tips for chartering a project (v2)
10 tips for chartering a project (v2)Glen Alleman
 
Share Point Governance
Share Point GovernanceShare Point Governance
Share Point GovernanceUGAIA
 
Dec 2012 Evening Talk - Managing Complex Project
Dec 2012 Evening Talk - Managing Complex ProjectDec 2012 Evening Talk - Managing Complex Project
Dec 2012 Evening Talk - Managing Complex ProjectZulkefle Idris
 
Software Risk Management for IT Execs CAST
Software Risk Management for IT Execs CASTSoftware Risk Management for IT Execs CAST
Software Risk Management for IT Execs CASTCAST
 
Agile Adoption Framework
Agile Adoption FrameworkAgile Adoption Framework
Agile Adoption FrameworkVaibhav Sathe
 
Catalyze Webcast - Carey Schwaber From Forrester Research - 10 Tips For Drivi...
Catalyze Webcast - Carey Schwaber From Forrester Research - 10 Tips For Drivi...Catalyze Webcast - Carey Schwaber From Forrester Research - 10 Tips For Drivi...
Catalyze Webcast - Carey Schwaber From Forrester Research - 10 Tips For Drivi...Tom Humbarger
 
Project management best practices
Project management best practicesProject management best practices
Project management best practiceswalkerswu
 
The Business of IT - My Kingdom for an Architecture
The Business of IT - My Kingdom for an ArchitectureThe Business of IT - My Kingdom for an Architecture
The Business of IT - My Kingdom for an ArchitecturePaul Wohlleben
 

Semelhante a PMI chapter meeting (v4) (20)

Immutable principles of project management (fw pmi)(v4)
Immutable principles of project management (fw pmi)(v4)Immutable principles of project management (fw pmi)(v4)
Immutable principles of project management (fw pmi)(v4)
 
Improving software economics - Top 10 principles of achieving agility at scale
Improving software economics - Top 10 principles of achieving agility at scaleImproving software economics - Top 10 principles of achieving agility at scale
Improving software economics - Top 10 principles of achieving agility at scale
 
Rhodes.donna
Rhodes.donnaRhodes.donna
Rhodes.donna
 
Life After PPM
Life After PPMLife After PPM
Life After PPM
 
Chap04 project integration management
Chap04 project integration managementChap04 project integration management
Chap04 project integration management
 
Lotti 2011
Lotti 2011Lotti 2011
Lotti 2011
 
10 tips for Chartering a Project
10 tips for Chartering a Project10 tips for Chartering a Project
10 tips for Chartering a Project
 
Подборка о рисках ИТ-проектов
Подборка о рисках ИТ-проектовПодборка о рисках ИТ-проектов
Подборка о рисках ИТ-проектов
 
Ev+agile=success (final v2)
Ev+agile=success (final v2)Ev+agile=success (final v2)
Ev+agile=success (final v2)
 
Performance based management in a nut shell (austin pmi)(notes)
Performance based management in a nut shell (austin pmi)(notes)Performance based management in a nut shell (austin pmi)(notes)
Performance based management in a nut shell (austin pmi)(notes)
 
Performance-Based Project Management In A Nut Shell
Performance-Based Project Management In A Nut ShellPerformance-Based Project Management In A Nut Shell
Performance-Based Project Management In A Nut Shell
 
10 tips for chartering a project (v2)
10 tips for chartering a project (v2)10 tips for chartering a project (v2)
10 tips for chartering a project (v2)
 
Share Point Governance
Share Point GovernanceShare Point Governance
Share Point Governance
 
Dec 2012 Evening Talk - Managing Complex Project
Dec 2012 Evening Talk - Managing Complex ProjectDec 2012 Evening Talk - Managing Complex Project
Dec 2012 Evening Talk - Managing Complex Project
 
Software Risk Management for IT Execs CAST
Software Risk Management for IT Execs CASTSoftware Risk Management for IT Execs CAST
Software Risk Management for IT Execs CAST
 
Lecture 2
Lecture 2 Lecture 2
Lecture 2
 
Agile Adoption Framework
Agile Adoption FrameworkAgile Adoption Framework
Agile Adoption Framework
 
Catalyze Webcast - Carey Schwaber From Forrester Research - 10 Tips For Drivi...
Catalyze Webcast - Carey Schwaber From Forrester Research - 10 Tips For Drivi...Catalyze Webcast - Carey Schwaber From Forrester Research - 10 Tips For Drivi...
Catalyze Webcast - Carey Schwaber From Forrester Research - 10 Tips For Drivi...
 
Project management best practices
Project management best practicesProject management best practices
Project management best practices
 
The Business of IT - My Kingdom for an Architecture
The Business of IT - My Kingdom for an ArchitectureThe Business of IT - My Kingdom for an Architecture
The Business of IT - My Kingdom for an Architecture
 

Mais de Glen Alleman

Managing risk with deliverables planning
Managing risk with deliverables planningManaging risk with deliverables planning
Managing risk with deliverables planningGlen Alleman
 
A Gentle Introduction to the IMP/IMS
A Gentle Introduction to the IMP/IMSA Gentle Introduction to the IMP/IMS
A Gentle Introduction to the IMP/IMSGlen Alleman
 
Increasing the Probability of Project Success
Increasing the Probability of Project SuccessIncreasing the Probability of Project Success
Increasing the Probability of Project SuccessGlen Alleman
 
Process Flow and Narrative for Agile+PPM
Process Flow and Narrative for Agile+PPMProcess Flow and Narrative for Agile+PPM
Process Flow and Narrative for Agile+PPMGlen Alleman
 
Practices of risk management
Practices of risk managementPractices of risk management
Practices of risk managementGlen Alleman
 
Principles of Risk Management
Principles of Risk ManagementPrinciples of Risk Management
Principles of Risk ManagementGlen Alleman
 
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...Glen Alleman
 
From Principles to Strategies for Systems Engineering
From Principles to Strategies for Systems EngineeringFrom Principles to Strategies for Systems Engineering
From Principles to Strategies for Systems EngineeringGlen Alleman
 
NAVAIR Integrated Master Schedule Guide guide
NAVAIR Integrated Master Schedule Guide guideNAVAIR Integrated Master Schedule Guide guide
NAVAIR Integrated Master Schedule Guide guideGlen Alleman
 
Building a Credible Performance Measurement Baseline
Building a Credible Performance Measurement BaselineBuilding a Credible Performance Measurement Baseline
Building a Credible Performance Measurement BaselineGlen Alleman
 
Integrated master plan methodology (v2)
Integrated master plan methodology (v2)Integrated master plan methodology (v2)
Integrated master plan methodology (v2)Glen Alleman
 
IMP / IMS Step by Step
IMP / IMS Step by StepIMP / IMS Step by Step
IMP / IMS Step by StepGlen Alleman
 
DHS - Using functions points to estimate agile development programs (v2)
DHS - Using functions points to estimate agile development programs (v2)DHS - Using functions points to estimate agile development programs (v2)
DHS - Using functions points to estimate agile development programs (v2)Glen Alleman
 
Making the impossible possible
Making the impossible possibleMaking the impossible possible
Making the impossible possibleGlen Alleman
 
Heliotropic Abundance
Heliotropic AbundanceHeliotropic Abundance
Heliotropic AbundanceGlen Alleman
 
Capabilities based planning
Capabilities based planningCapabilities based planning
Capabilities based planningGlen Alleman
 
Process Flow and Narrative for Agile
Process Flow and Narrative for AgileProcess Flow and Narrative for Agile
Process Flow and Narrative for AgileGlen Alleman
 
Building the Performance Measurement Baseline
Building the Performance Measurement BaselineBuilding the Performance Measurement Baseline
Building the Performance Measurement BaselineGlen Alleman
 
Program Management Office Lean Software Development and Six Sigma
Program Management Office Lean Software Development and Six SigmaProgram Management Office Lean Software Development and Six Sigma
Program Management Office Lean Software Development and Six SigmaGlen Alleman
 
Policy and Procedure Rollout
Policy and Procedure RolloutPolicy and Procedure Rollout
Policy and Procedure RolloutGlen Alleman
 

Mais de Glen Alleman (20)

Managing risk with deliverables planning
Managing risk with deliverables planningManaging risk with deliverables planning
Managing risk with deliverables planning
 
A Gentle Introduction to the IMP/IMS
A Gentle Introduction to the IMP/IMSA Gentle Introduction to the IMP/IMS
A Gentle Introduction to the IMP/IMS
 
Increasing the Probability of Project Success
Increasing the Probability of Project SuccessIncreasing the Probability of Project Success
Increasing the Probability of Project Success
 
Process Flow and Narrative for Agile+PPM
Process Flow and Narrative for Agile+PPMProcess Flow and Narrative for Agile+PPM
Process Flow and Narrative for Agile+PPM
 
Practices of risk management
Practices of risk managementPractices of risk management
Practices of risk management
 
Principles of Risk Management
Principles of Risk ManagementPrinciples of Risk Management
Principles of Risk Management
 
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
 
From Principles to Strategies for Systems Engineering
From Principles to Strategies for Systems EngineeringFrom Principles to Strategies for Systems Engineering
From Principles to Strategies for Systems Engineering
 
NAVAIR Integrated Master Schedule Guide guide
NAVAIR Integrated Master Schedule Guide guideNAVAIR Integrated Master Schedule Guide guide
NAVAIR Integrated Master Schedule Guide guide
 
Building a Credible Performance Measurement Baseline
Building a Credible Performance Measurement BaselineBuilding a Credible Performance Measurement Baseline
Building a Credible Performance Measurement Baseline
 
Integrated master plan methodology (v2)
Integrated master plan methodology (v2)Integrated master plan methodology (v2)
Integrated master plan methodology (v2)
 
IMP / IMS Step by Step
IMP / IMS Step by StepIMP / IMS Step by Step
IMP / IMS Step by Step
 
DHS - Using functions points to estimate agile development programs (v2)
DHS - Using functions points to estimate agile development programs (v2)DHS - Using functions points to estimate agile development programs (v2)
DHS - Using functions points to estimate agile development programs (v2)
 
Making the impossible possible
Making the impossible possibleMaking the impossible possible
Making the impossible possible
 
Heliotropic Abundance
Heliotropic AbundanceHeliotropic Abundance
Heliotropic Abundance
 
Capabilities based planning
Capabilities based planningCapabilities based planning
Capabilities based planning
 
Process Flow and Narrative for Agile
Process Flow and Narrative for AgileProcess Flow and Narrative for Agile
Process Flow and Narrative for Agile
 
Building the Performance Measurement Baseline
Building the Performance Measurement BaselineBuilding the Performance Measurement Baseline
Building the Performance Measurement Baseline
 
Program Management Office Lean Software Development and Six Sigma
Program Management Office Lean Software Development and Six SigmaProgram Management Office Lean Software Development and Six Sigma
Program Management Office Lean Software Development and Six Sigma
 
Policy and Procedure Rollout
Policy and Procedure RolloutPolicy and Procedure Rollout
Policy and Procedure Rollout
 

Último

How AI, OpenAI, and ChatGPT impact business and software.
How AI, OpenAI, and ChatGPT impact business and software.How AI, OpenAI, and ChatGPT impact business and software.
How AI, OpenAI, and ChatGPT impact business and software.Curtis Poe
 
Commit 2024 - Secret Management made easy
Commit 2024 - Secret Management made easyCommit 2024 - Secret Management made easy
Commit 2024 - Secret Management made easyAlfredo García Lavilla
 
Ensuring Technical Readiness For Copilot in Microsoft 365
Ensuring Technical Readiness For Copilot in Microsoft 365Ensuring Technical Readiness For Copilot in Microsoft 365
Ensuring Technical Readiness For Copilot in Microsoft 3652toLead Limited
 
Are Multi-Cloud and Serverless Good or Bad?
Are Multi-Cloud and Serverless Good or Bad?Are Multi-Cloud and Serverless Good or Bad?
Are Multi-Cloud and Serverless Good or Bad?Mattias Andersson
 
SAP Build Work Zone - Overview L2-L3.pptx
SAP Build Work Zone - Overview L2-L3.pptxSAP Build Work Zone - Overview L2-L3.pptx
SAP Build Work Zone - Overview L2-L3.pptxNavinnSomaal
 
Connect Wave/ connectwave Pitch Deck Presentation
Connect Wave/ connectwave Pitch Deck PresentationConnect Wave/ connectwave Pitch Deck Presentation
Connect Wave/ connectwave Pitch Deck PresentationSlibray Presentation
 
"LLMs for Python Engineers: Advanced Data Analysis and Semantic Kernel",Oleks...
"LLMs for Python Engineers: Advanced Data Analysis and Semantic Kernel",Oleks..."LLMs for Python Engineers: Advanced Data Analysis and Semantic Kernel",Oleks...
"LLMs for Python Engineers: Advanced Data Analysis and Semantic Kernel",Oleks...Fwdays
 
TrustArc Webinar - How to Build Consumer Trust Through Data Privacy
TrustArc Webinar - How to Build Consumer Trust Through Data PrivacyTrustArc Webinar - How to Build Consumer Trust Through Data Privacy
TrustArc Webinar - How to Build Consumer Trust Through Data PrivacyTrustArc
 
"Subclassing and Composition – A Pythonic Tour of Trade-Offs", Hynek Schlawack
"Subclassing and Composition – A Pythonic Tour of Trade-Offs", Hynek Schlawack"Subclassing and Composition – A Pythonic Tour of Trade-Offs", Hynek Schlawack
"Subclassing and Composition – A Pythonic Tour of Trade-Offs", Hynek SchlawackFwdays
 
Merck Moving Beyond Passwords: FIDO Paris Seminar.pptx
Merck Moving Beyond Passwords: FIDO Paris Seminar.pptxMerck Moving Beyond Passwords: FIDO Paris Seminar.pptx
Merck Moving Beyond Passwords: FIDO Paris Seminar.pptxLoriGlavin3
 
"Debugging python applications inside k8s environment", Andrii Soldatenko
"Debugging python applications inside k8s environment", Andrii Soldatenko"Debugging python applications inside k8s environment", Andrii Soldatenko
"Debugging python applications inside k8s environment", Andrii SoldatenkoFwdays
 
Anypoint Exchange: It’s Not Just a Repo!
Anypoint Exchange: It’s Not Just a Repo!Anypoint Exchange: It’s Not Just a Repo!
Anypoint Exchange: It’s Not Just a Repo!Manik S Magar
 
Human Factors of XR: Using Human Factors to Design XR Systems
Human Factors of XR: Using Human Factors to Design XR SystemsHuman Factors of XR: Using Human Factors to Design XR Systems
Human Factors of XR: Using Human Factors to Design XR SystemsMark Billinghurst
 
New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024BookNet Canada
 
Advanced Test Driven-Development @ php[tek] 2024
Advanced Test Driven-Development @ php[tek] 2024Advanced Test Driven-Development @ php[tek] 2024
Advanced Test Driven-Development @ php[tek] 2024Scott Keck-Warren
 
WordPress Websites for Engineers: Elevate Your Brand
WordPress Websites for Engineers: Elevate Your BrandWordPress Websites for Engineers: Elevate Your Brand
WordPress Websites for Engineers: Elevate Your Brandgvaughan
 
Designing IA for AI - Information Architecture Conference 2024
Designing IA for AI - Information Architecture Conference 2024Designing IA for AI - Information Architecture Conference 2024
Designing IA for AI - Information Architecture Conference 2024Enterprise Knowledge
 
H2O.ai CEO/Founder: Sri Ambati Keynote at Wells Fargo Day
H2O.ai CEO/Founder: Sri Ambati Keynote at Wells Fargo DayH2O.ai CEO/Founder: Sri Ambati Keynote at Wells Fargo Day
H2O.ai CEO/Founder: Sri Ambati Keynote at Wells Fargo DaySri Ambati
 
CloudStudio User manual (basic edition):
CloudStudio User manual (basic edition):CloudStudio User manual (basic edition):
CloudStudio User manual (basic edition):comworks
 

Último (20)

How AI, OpenAI, and ChatGPT impact business and software.
How AI, OpenAI, and ChatGPT impact business and software.How AI, OpenAI, and ChatGPT impact business and software.
How AI, OpenAI, and ChatGPT impact business and software.
 
Commit 2024 - Secret Management made easy
Commit 2024 - Secret Management made easyCommit 2024 - Secret Management made easy
Commit 2024 - Secret Management made easy
 
Ensuring Technical Readiness For Copilot in Microsoft 365
Ensuring Technical Readiness For Copilot in Microsoft 365Ensuring Technical Readiness For Copilot in Microsoft 365
Ensuring Technical Readiness For Copilot in Microsoft 365
 
Are Multi-Cloud and Serverless Good or Bad?
Are Multi-Cloud and Serverless Good or Bad?Are Multi-Cloud and Serverless Good or Bad?
Are Multi-Cloud and Serverless Good or Bad?
 
SAP Build Work Zone - Overview L2-L3.pptx
SAP Build Work Zone - Overview L2-L3.pptxSAP Build Work Zone - Overview L2-L3.pptx
SAP Build Work Zone - Overview L2-L3.pptx
 
Connect Wave/ connectwave Pitch Deck Presentation
Connect Wave/ connectwave Pitch Deck PresentationConnect Wave/ connectwave Pitch Deck Presentation
Connect Wave/ connectwave Pitch Deck Presentation
 
"LLMs for Python Engineers: Advanced Data Analysis and Semantic Kernel",Oleks...
"LLMs for Python Engineers: Advanced Data Analysis and Semantic Kernel",Oleks..."LLMs for Python Engineers: Advanced Data Analysis and Semantic Kernel",Oleks...
"LLMs for Python Engineers: Advanced Data Analysis and Semantic Kernel",Oleks...
 
E-Vehicle_Hacking_by_Parul Sharma_null_owasp.pptx
E-Vehicle_Hacking_by_Parul Sharma_null_owasp.pptxE-Vehicle_Hacking_by_Parul Sharma_null_owasp.pptx
E-Vehicle_Hacking_by_Parul Sharma_null_owasp.pptx
 
TrustArc Webinar - How to Build Consumer Trust Through Data Privacy
TrustArc Webinar - How to Build Consumer Trust Through Data PrivacyTrustArc Webinar - How to Build Consumer Trust Through Data Privacy
TrustArc Webinar - How to Build Consumer Trust Through Data Privacy
 
"Subclassing and Composition – A Pythonic Tour of Trade-Offs", Hynek Schlawack
"Subclassing and Composition – A Pythonic Tour of Trade-Offs", Hynek Schlawack"Subclassing and Composition – A Pythonic Tour of Trade-Offs", Hynek Schlawack
"Subclassing and Composition – A Pythonic Tour of Trade-Offs", Hynek Schlawack
 
Merck Moving Beyond Passwords: FIDO Paris Seminar.pptx
Merck Moving Beyond Passwords: FIDO Paris Seminar.pptxMerck Moving Beyond Passwords: FIDO Paris Seminar.pptx
Merck Moving Beyond Passwords: FIDO Paris Seminar.pptx
 
"Debugging python applications inside k8s environment", Andrii Soldatenko
"Debugging python applications inside k8s environment", Andrii Soldatenko"Debugging python applications inside k8s environment", Andrii Soldatenko
"Debugging python applications inside k8s environment", Andrii Soldatenko
 
Anypoint Exchange: It’s Not Just a Repo!
Anypoint Exchange: It’s Not Just a Repo!Anypoint Exchange: It’s Not Just a Repo!
Anypoint Exchange: It’s Not Just a Repo!
 
Human Factors of XR: Using Human Factors to Design XR Systems
Human Factors of XR: Using Human Factors to Design XR SystemsHuman Factors of XR: Using Human Factors to Design XR Systems
Human Factors of XR: Using Human Factors to Design XR Systems
 
New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
 
Advanced Test Driven-Development @ php[tek] 2024
Advanced Test Driven-Development @ php[tek] 2024Advanced Test Driven-Development @ php[tek] 2024
Advanced Test Driven-Development @ php[tek] 2024
 
WordPress Websites for Engineers: Elevate Your Brand
WordPress Websites for Engineers: Elevate Your BrandWordPress Websites for Engineers: Elevate Your Brand
WordPress Websites for Engineers: Elevate Your Brand
 
Designing IA for AI - Information Architecture Conference 2024
Designing IA for AI - Information Architecture Conference 2024Designing IA for AI - Information Architecture Conference 2024
Designing IA for AI - Information Architecture Conference 2024
 
H2O.ai CEO/Founder: Sri Ambati Keynote at Wells Fargo Day
H2O.ai CEO/Founder: Sri Ambati Keynote at Wells Fargo DayH2O.ai CEO/Founder: Sri Ambati Keynote at Wells Fargo Day
H2O.ai CEO/Founder: Sri Ambati Keynote at Wells Fargo Day
 
CloudStudio User manual (basic edition):
CloudStudio User manual (basic edition):CloudStudio User manual (basic edition):
CloudStudio User manual (basic edition):
 

PMI chapter meeting (v4)

  • 1. Copyright ® 2010, Lewis & Fowler, All Rights Reserved Thank you for inviting me to your Chapter meeting tonight. I'm speaking tomorrow at the Symposium on two topics – Establishing the Performance Measurement Baseline and the Immutable Principles of Project Management. Both of these topics are critical to increasing the probability of success for your project. Both these topics are founded on a set of principles that have emerged over the past decade in the aerospace and defense business and are now moving into commercial project management processes. PMI Fort Worth, Chapter Meeting, 15 July, 2010 1/18
  • 2. Copyright ® 2010, Lewis & Fowler, All Rights Reserved There are four outcomes for this talk. 1. I’m going to suggest there are gaps in the understanding of the elements of a project management process. Not that our current PMBOK® based processes are in error, but the units of measure of progress, DONE, effectiveness and performance are missing. 1. That connecting the dots between cost, schedule, and Technical Performance Measures are needed to improve the probability of success. 2. Making these connections lives in the discipline of Systems Engineering. 3. Once these connections have been made, we need to realize that all the programmatic elements are random variables, and we need to act accordingly. PMI Fort Worth, Chapter Meeting, 15 July, 2010 2/18
  • 3. Copyright ® 2010, Lewis & Fowler, All Rights Reserved We’re all project managers or have some relation to project management. What’s the core problems we’ve seen in the past and will likely see in the future around project management. Here’s a popular list I’ve encountered over the years. You’re list many have some of these or even better ones. No matter what the list is, any project management framework must address them head on if you’re going to have a chance to end successfully. I’m going to show you five principles of project management that have served us well over the years. I’m going to suggest these principles are immutable. That is they are the same for every project management domain and context in that domain. From mega projects in construction and defense to small agile software development projects with the customer in the same room. Immutable = not subject or susceptible to change or variation in form or quality or nature. PMI Fort Worth, Chapter Meeting, 15 July, 2010 3/18
  • 4. Copyright ® 2010, Lewis & Fowler, All Rights Reserved So how can we put these principles in practice? The anchor to the practices that are guided by the principles is to focus on the Deliverables. All other elements of the project are secondary or possibly unimportant to the deliverables. This paradigm may appear different than the process groups and knowledge areas of PMBOK®. These PMBOK® elements are certainly in support of this deliverables view, but it may not be explicitly stated in a way we can “connect the dots.” When we leave tonight I’m going to suggest you’ll have a different paradigm when you look at PMBOK® One focused on “what does DONE look like.” How to measure DONE in units meaningful to the buyer. PMI Fort Worth, Chapter Meeting, 15 July, 2010 4/18
  • 5. Copyright ® 2010, Lewis & Fowler, All Rights Reserved With this notion in mind, we can define what DONE looks like. It is defined when we answer these five (5) questions. These questions are core to every project. They the are source of processes that define the immutable principles. They must be answered for success. When they are not asked or not answered the probability of success is lowered, many times lowered to the point that the project goes off track and possibly fails. We’ll see in the coming slides how these questions and their answers can be your means to increasing the probability of success. PMI Fort Worth, Chapter Meeting, 15 July, 2010 5/18
  • 6. Copyright ® 2010, Lewis & Fowler, All Rights Reserved The five irreducible principles of project management that answer the previous questions are: 1. Know where you are going by defining “done” at some point in the future. This point may be far in the future – months or years from now. Or closer in the future, days or weeks from now. 2. Have some kind of plan to get to where you are going. This plan can be simple or it can be complex. The fidelity of the plan depends on the tolerance for risk by the users of the plan. 3. Understand the resources needed to execute the plan. How much time and money is needed to reach the destination. This can be fixed or it can be variable. 4. Identify the impediments to progress along the way to the destination. Have some means of removing, avoiding, or ignoring these impediments. 5. Have some way to measure your planned progress, not just your progress. Progress to Plan must be measured in units of physical percent complete. PMI Fort Worth, Chapter Meeting, 15 July, 2010 6/18
  • 7. Copyright ® 2010, Lewis & Fowler, All Rights Reserved The question “where are we going” must be answered in ways meaningful to the buyer. The answer can be in the form of a needed capability. This answers the question, “What capabilities to we need to posses to call the project DONE?” Or what are the requirements that need to be fulfilled to call the project DONE? The answer to this question is a PLAN. The PLAN says where we are going. It does not say how we’re going to get there, just where. One critical missing element for many troubled projects is the answer to the question WHY. WHY are we doing this project? The PLAN comes after we answer the question WHY. This answer comes from the business strategy or mission strategy of the project and is outside the context of the five (5) immutable processes. PMI Fort Worth, Chapter Meeting, 15 July, 2010 7/18
  • 8. Copyright ® 2010, Lewis & Fowler, All Rights Reserved HOW to get there is described in the Schedule. Let’s walk through an example. Let’s pretend we want to go on a hike. A nice hike to the saddle just to the right of the peak above this lake. That saddle is Pawnee Pass. I t’s just west of Boulder Colorado, and a bit south of Rocky Mountain National Park. We’d like to go to Pawnee Pass in a single day – there and back. Not get too wet if it rains. Not be too hungry. And have a good time along the way with our hiking group. The PLAN is to summit in a day and return safely. The SCHEDULE is the steps needed to actually reach the summit and return. This SCHEDULE includes all the work effort needed to summit, the order in which we’d perform these work element, the dependencies between the elements, any resources we’ll need for success, and both schedule and cost margins. PMI Fort Worth, Chapter Meeting, 15 July, 2010 8/18
  • 9. Copyright ® 2010, Lewis & Fowler, All Rights Reserved With the destination in mind and schedule of all the activities needed to reach our destination, do we know if we have everything we need to get there? This answer includes all the resources, technology, processes, and other items that will enable success. These dependencies must be identified in the Master Schedule. For example in NASA programs – Government Furnished Equipment is common. Same for external dependencies in Enterprise IT projects. These dependencies have their own schedules and the credibility of those schedules must be assessed in the same way we are going to do in the next steps. This “all in” System of Systems approach is needed to collect “all” the elements of the project PLAN and SCHEDULE. PMI Fort Worth, Chapter Meeting, 15 July, 2010 9/18
  • 10. Copyright ® 2010, Lewis & Fowler, All Rights Reserved There are always impediments to progress. It’s just part of a project. It’s actually part of everything we do as project managers. But do we know them? Can we name them and what their impact might be on the project? Do we have some way of “handling” these impediments – the risks to the project. There are of course the named ways: 1.Risk avoidance eliminates the sources of high risk and replaces them with a lower-risk solution. 2.Risk transfer is the reallocation of risk from one part of the system to another. 3.Risk control manages the risk in a manner that reduces the probability / likelihood of its occurrence and / or minimizes the risk's effect on the program. 4.Risk assumption is the acknowledgment of the existence of a particular risk situation and a conscious decision to accept the associated level of risk without engaging in any special efforts to control it. PMI Fort Worth, Chapter Meeting, 15 July, 2010 10/18
  • 11. Copyright ® 2010, Lewis & Fowler, All Rights Reserved Here’s where many projects start their path toward the ditch. Progress can only measured in the assessment of Physical Percent Complete. The percent of the Planned progress.  How far along should we be at this point in the project?  Where are we actually along the path to complete?  What was our planned progress at this point in the project? The unit of measure for Physical Percent Complete starts with tangible evidentiary Materials brought to the table and shown to project participants. The passage of time and consumption of resource is never a measure of progress to plan. This last approach is common in projects that have gone off the rails. When we are planning and scheduling the project we need to define upfront what these measures of percent complete are. Predefining them. Agreeing we measure progress with them. There can be no retroactive assessment of progress to plan. Once defined the measures of physical percent complete are placed “on baseline,” and represent the only assessment of progress. PMI Fort Worth, Chapter Meeting, 15 July, 2010 11/18
  • 12. Copyright ® 2010, Lewis & Fowler, All Rights Reserved If we look back to the beginning of tonight's talk to the 4+1 major activities of Deliverables Based Planning® and connect them with the five (5) immutable principles of managing any project, we have to look for the evidence that we’re following the processes using the principles. You may have other evidence. No matter what you have, there has to be artifacts showing that you’ve done the work to answer the 4+1 questions and satisfied the five (5) immutable principles. One critical concept in any successful project management method is “evidence based” assessment of progress. Personal opinion, verbal discussion, management statements are not acceptable. Only tangible evidence of progress to plan is acceptable. PMI Fort Worth, Chapter Meeting, 15 July, 2010 12/18
  • 13. Copyright ® 2010, Lewis & Fowler, All Rights Reserved Each of these pieces of evidence must provide some level of credibility. One method of measuring this credibility and its tangible value is through a systems engineering paradigm. This by the way is one of the difficulties agile processes run into. They mention “value” but don’t have units of measure for that value. Independent of that, here’s how we do it in the systems engineering world. MoE’s are defined by the customer. They are the measures of the capabilities needed to fulfill some mission. MoP’s are defined by the supplier. They describe the behaviors needed to fulfill the mission. The KPP’s are the numbers we’ll assign to the MoP’s. The Technical Performance Measures (TPM) are the collection of these individual elements. PMI Fort Worth, Chapter Meeting, 15 July, 2010 13/18
  • 14. Copyright ® 2010, Lewis & Fowler, All Rights Reserved All this effort, definitions, processes ,and information has only one goal. The goal is to describe in a tangibly measureable way what DONE looks like. This is the only reason for all these processes. This is the role of the Project Manager and the Project Controls staff. To define what DONE looks like, manage all the resources toward that description, handle all the risks and impediments to progress. All of this starts – and ends – with what the customer needs in terms of “capabilities.” PMI Fort Worth, Chapter Meeting, 15 July, 2010 14/18
  • 15. Copyright ® 2010, Lewis & Fowler, All Rights Reserved If we fail to provide credible answers to the five (5) immutable project management processes, then we’re headed in the wrong direction.  We will not be able to measure our progress to plan.  We will have not defined what business or mission capabilities are needed for success.  We won’t know what the requirements are to fulfill these needed capabilities.  We'll have failed to identify and handle the impediments to our progress to plan. Our only source of success will be HOPE. Hope that we’ll discover these as we go. Hope, that the potential impediments to progress won’t come true. Hope that our customer can articulate what DONE looks like for us along the way. When Hope is are strategy, we’ve started on the road to failure. PMI Fort Worth, Chapter Meeting, 15 July, 2010 15/18
  • 16. Copyright ® 2010, Lewis & Fowler, All Rights Reserved In closing here’s the next level down for Deliverables Based Planning®. Each of the four (4) processes shown here – plus the continuous risk management has major sub-processes, which also have sub-sub-processes . There are 74 processes in all. I have handouts that cover all these processes, you’re welcome to. PMI Fort Worth, Chapter Meeting, 15 July, 2010 16/18
  • 17. Copyright ® 2010, Lewis & Fowler, All Rights Reserved So with that brief overview of Deliverables Based Planning® and its application to projects in general, are there any questions I can answer in the short time we have left? My colleague and I will be here for more questions and answers. Tomorrow the Symposium Work Shops will delve into these topics in greater detail, I look forward to seeing you there. PMI Fort Worth, Chapter Meeting, 15 July, 2010 17/18
  • 18. Copyright ® 2010, Lewis & Fowler, All Rights Reserved Here’s my contact information if you’re unable to attend tomorrow’s work shop or would like more information about these processes. PMI Fort Worth, Chapter Meeting, 15 July, 2010 18/18