Performance-Based Project Management®

In A Nutshell
Principles, Practices, and Processes that
Increase Your Probability of Project Success
Performance Based Management(sm), Copyright ® Glen B. Alleman, 2012
Why Performance-Based Project Management®?
 All successful projects
must deliver capabilities:
 Not the work efforts,
 Not the cost expenditures,
 Not the documentation,
test results, or the
processes.
Performance-Based Project Management®

Principles, Practices, and Processes for
Increasing the Probability of Project
Success†
† Program Success Probability, John Higbee, Defense Acquisition
University, 9 May 2005

Performance Based Management(sm), Copyright ® Glen B. Alleman, 2012

 All successful projects
must deliver tangible
beneficial outcomes,
measured in units
meaningful to the
decision makers.
2/29
5 Principles of Project Success . . .
1. What Does DONE Look
Like?
2. What is the path to
DONE?
3. Do We Have Enough
Time, Resources, And
Money To Get To DONE?
4. What Impediments Will
We Encounter Along The
Way To DONE?
5. How Do We Know We
Are Making Progress
Toward DONE?
5 Immutable Principles of Project Management, Copyright ©, Glen B. Alleman, 2012

3/29
Identify
Needed
Capabilities

Indentify
Baseline
Requirements

Establish
Performance
Measurement
Baseline

Execute
Performance
Measurement
Baseline

Perform Continuous Risk Management (CRM)
 Define Capabilities
 Define ConOps
 Assess Needs, Cost, and
Risk Impacts
 Define Balanced and
Feasible Alternatives

 Decompose Scope
 Assign Accountability
 Arrange Work
 Develop BCWS
 Assign Performance

Define the Measurable
Capabilities of each
Project Outcome
4

 Fact Finding
 Gather And Classify
 Evaluate And
Rationalize
 Prioritize Requirements
 Integrate And Validate
Assure All Requirements
Provided In Support of
Capabilities

Define Measures of
Performance and
Effectiveness

Performance Based Management(sm), Copyright ® Glen B. Alleman, 2012

 Perform Work
 Accumulate
Performance Measures
 Analyze Performance
 Take Corrective Action

Ensure Cost, Schedule,
and Technical
Performance Compliance
Define the Work Breakdown
Structure(WBS).
 Identify the Organizational
Breakdown Structure (OBS).
 Integrate the WBS and OBS.


Schedule the work.
 Identify the Products and
Milestones.
 Set the time phased budget.



Record direct costs.

Performance Analysis
 Determine variances.
 Sum Data and variances.
 Manage action plans.





Incorporate Changes.

† These 11 processes are a subset of the 32 Criteria of ANSI–748B Earned Value Management. While not all
projects can make use ANSI EVM, these process are the basis of all project management success.
Performance Based Management(sm), Copyright ® Glen B. Alleman, 2012

5/29
6

Kavli Institute at Cornell for Nanoscale Science
Principles and Practices of Performance-Based Project Management ®

5 Practices

5 Principles

Identify
Capabilities

What does
ConOps, SOO,
done look like?
SOW
What is the
path to Done?
What resource
do we need
along the way?

Integrated
Master Plan
(IMP)

What
impediments
will we
encounter along
the way?

4 Levels of
Uncertainty
Assessment

How do we
measure
progress?

Measures of
Effectiveness
(MoE)

Define
Requirements

Performance
Measurement
Baseline (PMB)

Execute the
PMB

Continuous Risk
Management

Technical and
Operational
Based Plan

Incremental
Maturity
Assessment

Physical Percent
Complete

Risk
Identification

Iterative and
Incremental
Delivery

Risk
Analysis

Future
Performance
Forecasting

Risk
Planning

Risk adjusted
Performance
Measurement
Baseline

Risk
Tracking

Earned Value
Management

Risk
Control

Work
Breakdown
Structure
Resource
Management
Plan

Integrated
Master
Schedule (IMS)

Technical and
Risk adjustments
Programmatic
to cost and
Risks assigned
schedule
to all WBS
measures
deliverables

Measures of
Performance
(MoP)

Technical
Performance
Measures
Practices and Processes of Performance-Based Project Management ®

5 Processes
Organize

5 Practices
Identify
Capabilities

Plan, Schedule,
Budget

Project mission, Value stream of
vision, and
increasing
deliverables
maturity

Define
Requirements

Resource
Management
Plan

Analyze
Variances

Top level
budget for
capabilities

Measures of
Effectiveness

Requirements
traced to
capabilities

Performance
Measurement
Baseline

Account for all
costs

Measures of
Performance
Work Packages
with budget

Labor and
material costs

Technical
Performance
Measures

Baseline change
request

Budgeted Cost
Work Package Physical Percent
Technical
for Work
Performance
Complete
change requests
Scheduled

Execute the
PMB
Continuous Risk
Management

Manage
Change

Risk Register

Risk impacts on
cost and
schedule

Risk adjustments
to PMB
Performance-Based Project Management®
Addresses The Critical Project Outcomes†
The
Situation

 By their very nature, project are risky.
 Successful project management is risk management.
 Program management must be about avoiding surprises.

The
Problem

 Traditional program management assumes technical and
program processes drive outcomes.
 Focusing on process alone has failed in the past.

The Need

 Program management is about avoiding surprises.
 Measures of physical percent complete are mandatory.

The
Context

 Organizations execute projects.
 Adapting the organization culture to the project paradigm
increases the probability of success.

The
Solution

 Technical Performance of deliverables is a measure of
increasing probability of success.
 Earned Value Management reveals surprises.

† Project Management Case Study, Pierre Bonnal, CNAM IIM MBA Program, June 2004
Performance Based Management(sm), Copyright ® Glen B. Alleman, 2012

9/29
Practices produce Project Outcomes
 The Outcome does not need to be the end product.
 The Outcome is the result of Work Packages that increase
the measureable maturity of the product or service.
Outcomes incrementally increase a capability’s maturity

 Outcomes are specified and measureable.
 Design complete and verifiable.
 Development complete and testable.
 Testing complete and validated.
 Installation and deployment complete and operational.
Outcomes result from “units of work” – the Work Package
 Work Packages consume time and resources.
 Work Packages are owned by a single accountable person.
 Work Packages produce outcomes.
Project Management Case Study, Pierre Bonnal, CNAM IIM MBA Program, June 2004
Performance Based Management(sm), Copyright ® Glen B. Alleman, 2012

10/29
Five Practices Of Performance-Based Project Management®


What capabilities are needed to fulfill the project goal, mission, or outcome?
Identify
Needed
Capabilities



Establish
Requirements
Baseline



Establish
the Performance
Measurement
Baseline



Execute
the Performance
Measurement
Baseline



Perform
Continuous Risk
Management

Define the set of capabilities needed to achieve the project objectives or the particular end
state for a specific scenario. Using the Concept of Operations (ConOps), define the details of
who, where, and how this capability is to be accomplished, employed, and executed.
What technical & operational requirements are needed to produce the capabilities?
Define the technical and operational requirements for the system capabilities to be fulfilled.
First, define these requirements in terms isolated from any implementation details. Only then
bind the requirements with technology.
What is the schedule to deliver products or services to produce the requirements?
Build a time–phased network of work activities describing the work to be performed, the
budgeted cost for this work, the organizational elements that produce the outcomes, and the
Performance measures showing this work is proceeding according to plan.
What are the periodic measures of physical percent complete?
Execute work activities, while assuring all Performance assessment represent 100%
completion before proceeding. This means – No rework, no forward transfer of activities to the
future. Assure all requirements are traceable to work & all work is traceable to requirements.
What are the impediments to success and how are they being handled?
Apply the processes of Continuous Risk Management for each Performance Based
Management(sm) process area to: Identify, Analyze, Plan, Track, Control, and
Communicate projectmatic and technical risk.

11/29

Identify Needed
Capabilities

Define the capabilities needed to achieve the desired objectives or a particular end state for a
specific scenario. Define the details of who, where, and how these capabilities are to be
accomplished, employed, and executed.
What capabilities are needed to fulfill the Business Case or project Mission?

1.1

Define
Capabilities as
Operational
Concepts

Define
Capabilities
through
Scenarios or Use
Cases

 Partition system capabilities into classes of service within operational scenarios.
 Connect the capabilities to system requirements using some visual modeling notation.
 Define Measures of Effectiveness (MoE) and Measures of Performance (MoP).
 Define the delivery schedule for each measure of Performance and effectiveness.

1.2

 Define scenarios for each system capability.
 Connect these scenarios to a Value Stream Map of the increasing maturity of the project.
 Assess value flow through the map for each needed capability.
 Identify capability mismatches and make corrections to improve overall value flow.

1.3

 Assign costs to each system element using a value flow model.
 Assure risk, probabilistic cost and benefit Performance attributes are defined.
 Use cost, schedule and technical Performance probabilistic models to forecast
potential risks to project performance.

Assess Needs,
Costs, and Risks
of the Capability
Simultaneously

1.4

Define
Explicit,
Balanced, and
Feasible
Alternatives

 Make tradeoffs that connect cost, schedule, and technical Performance in a single
location that compares the tradeoffs and their impacts.
 Use Measures of Effectiveness (MoE) and Measures of Performance (MoP) for these
alternative tradeoffs.

Performance Based Management(sm), Copyright ® Glen B. Alleman, 2012

12/29


What Does A Capability “Sound” Like?
 We need the capability to pre‒process insurance claims at $0.07
per transaction rather than the current $0.11 per transaction.
 We need the capability to remove 1½ hours from the retail
ordering process once the merger is complete.
 We need the capability to change the Wide Field Camera and the
internal nickel hydride batteries, while doing no harm to the
telescope.
 We need the capability to fly 4 astronauts to the International
Space Station, dock, stay 6 months, and return safely.
 We need the capability to control the Hell Fire Missile with a new
touch panel while maintaining existing navigation and guidance
capabilities in the helicopter.
 We need the capability to comply with FAR Part 15 using the
current ERP system and its supporting work processes.
Performance Based Management(sm), Copyright ® Glen B. Alleman, 2012

13/29


Establish
Technical and
Operational
Requirements
Baseline

2.1

Perform Fact
Finding

2.2

Gather
and Classify
Requirements

2.3

Evaluate
and Rationalize
Requirements

2.4

Prioritize
Requirements

2.5

Integrate
and Validate
Requirements

Define the technical and operational requirements that must be present for the system
capabilities to be delivered. Define these requirements in terms isolated from any technology
or implementation. Assure each requirement is connected to a need system capability.
What Technical and Operational Requirements are Needed to Produce the Capabilities?
 Produce an overall statement of the customer need in the operational context.
 Develop the overall operational and technical objectives of the system that meets the need.
 Defined the boundaries and interfaces of the system.
 Gather required system capabilities, functional, nonfunctional and environmental
requirements, and design constraints.
 Build the Top Down capabilities and functional decomposition of the requirements in a
Requirements Management System.
 Answer the question “why do I need this?” in terms of operational capabilities.
 Build a cost / benefit model using probabilistic assessment of all variables, their
dependencies, and impacts.
 For all requirements, perform a risk assessment to cost and schedule.

 Determine criticality for the functions of the system.
 Determine trade off relationships for all requirements to be used when option decisions
must be made.
 For all technical items, prioritize their cost and dependency.
 Address the completeness of requirements by removing all “TBD” items.
 Validate that the requirements are traceable to system capabilities, goals, and mission.
 Resolve any requirements inconsistencies and conflicts.

Performance Based Management(sm), Copyright ® Glen B. Alleman, 2012

14/29


What Is a Requirement?
A Requirement is …”A statement identifying a capability, a
physical characteristic, or a quality factor that bounds a
product or process need for which a solution will be
pursued.”
— IEEE Standard 1220–2005
The hardest single part of building a system is deciding
what to build …
... No other part of the work so cripples the resulting
system if done wrong. No other part is more difficult to
rectify later.
– Fred Brooks “No Silver Bullet,” 1987
Performance Based Management(sm), Copyright ® Glen B. Alleman, 2012

15/29


Establish
Performance
Measurement
Baseline

3.1

Decompose
Scope into Work
Packages

Build a time–phased network of activities describing the work to be performed, the budgeted
cost for this work, the organizational elements that produce the outcomes from this work, and
the Performance measures showing this work is proceeding according to plan.
A Baselined Schedule that Produces the Products or Services that Meet The Requirements
Decompose the outcomes into a product based Work Breakdown Structure (WBS), then
further into Work Packages that produce these outcomes all traceable to the requirements,
and to the needed capabilities.

3.2

Assign responsibility to Work Packages (the groupings of outcomes) to a named owner,
accountable for the management of the resource allocations, cost and schedule baseline,
and technical delivery of all element in the Work Breakdown Structure.

3.3

Arrange the Work Packages in a logical network with defined outcomes, milestones,
internal and external dependencies, with credible schedule, cost, and technical
Performance margins.

3.4

Develop the Time–Phased Budgeted Cost for Work Scheduled (BCWS) for the labor and
material costs in each Work Package and the Project as a whole. Assure proper resource
allocations can be met and budget profiles match expectations of the project sponsor

Assign
Responsibility
for outcomes

Arrange
Work Packages
in Logical Order
Develop
BCWS for Work
Packages

3.5

Assign WP
Measures of
Performance

Assign objective Measures of Performance (MoP) and Measures of Effectiveness (MoE) for
each Work Package and summarize these for the Project as a whole.

3.6

Set
Performance
Measurement
Baseline

Establish a Performance Measurement Baseline (PMB) used to forecast the Work
Package and Project ongoing and completion cost and schedule Performance metrics.

Performance Based Management(sm), Copyright ® Glen B. Alleman, 2012

16/29


What Does a Credible Plan and
Schedule Look Like?
 The Plan is the strategy to successfully complete the
project, described through Significant Accomplishments
and their Accomplishment Criteria.
 The Schedule is the sequence of the work activities
measured by the Accomplishment Criteria, that follow
the Plan of the Significant Accomplishments.
 A credible Plan and Schedule means there is a
statistical model of cost, schedule, and technical
Performance of outcomes as the foundation of the
credibility of the project’s probability of success.
Performance Based Management(sm), Copyright ® Glen B. Alleman, 2012

17/29


Execute
the Performance
Measurement
Baseline

Execute the planned work, assuring all work is 100% complete before proceeding to the
next planned work package. No rework, no forward transfer of activities or features.
Assure every requirement is traceable to work and all work is traceable to requirements.
How long are you willing to wait before you find out you’re late?

4.1

 Using the Work Package sequencing, release work to be performed as planned.
 With the responsibility assignments, identify the accountable delivery manager to guide the
development of the products or services for each Work Package.

4.2 Accumulate

 Using Physical Percent Complete or Apportioned Milestones, capture measures of
progress to plan for each Work Package.
 Report this Physical Percent Complete in a centralized database for each Work Package
and the project as a whole.

Perform
the Authorized
Work

and Report Work
Package
Performance

4.3

Analyze
Work Package
Performance

4.4

Take
Corrective
Management
Action

4.5

Maintain
the Performance
Baseline

 Compare the Physical Percent Complete against the Planned Percent Complete for each
period of performance.
 Construct cost and schedule Performance indices from this information and the Physical
Percent complete measures.
 With Cost and Schedule Performance indices, construct a forecast of future
Performance of cost, schedule, and technical Performance compliance.
 Take management actions for any Work Packages not performing as planned.
 Record past Performance based on Work Package completion criteria.
 Record past future forecast Performance estimates in a historical database.
 Forecast next future Performance estimate against the Performance Measurement Baseline.
 Report this next future Performance estimate to the project stakeholders.

Performance Based Management(sm), Copyright ® Glen B. Alleman, 2012

18/29


How Do We Know We Are Achieving
Our Planned Progress?
 The Only measure of progress is the assessment of
physical percent complete.
 This measurement Must be in units meaningful to the
customer.
 These units can be:





Planned capabilities,
Planned capacities,
Planned features and functions,
Planned quantities.

 Done is evidenced by the production of outcomes, on
the planned date, for the planned cost, with the planned
technical performance.
Performance Based Management(sm), Copyright ® Glen B. Alleman, 2012

19/29


Apply
Continuous Risk
Management at
Every Step

5.1

Identify Risks

5.2

Analyze Risks

5.3

Plan Risk
Response

5.4

Track the
Risk
Management
Activities

5.5

Control or
Accept the Risks

Continuous Risk Management starts the underlying principles, concepts, and functions of
risk management and provides guidance on how to implement risk management as a
continuous practice in projects and the organizations that management projects.
What are the impediments to success and what are their mitigations?

 Identify and classify risks in a Risk Register.
 Manage this Risk Register through a Risk Management Board.
 Connect these risks and their handling in the Master Schedule.
 Convert risk data into risk decision‒making information.
 Use this analysis information as the decision basis for the project manager to work on the
“right” risks.

 Turn risk information into decisions and actions (both present and future).
 Develop actions to address individual risks, prioritize risk actions, and create an integrated
risk management plan.

 Monitor the status of risks and actions taken to ameliorate risks.
 Identify and monitor risks to enable the evaluation of the status of risks themselves and
of risk mitigation plans.

 Risk communication lies at the center of the model to emphasize both its pervasiveness and
its criticality.
 Without effective communication, no risk management approach can be viable.

Performance Based Management(sm), Copyright ® Glen B. Alleman, 2012

20/29


Continuous Risk Management†
For Each Risk…
Subproject and partner
data/constraints, hazard
analysis, FMEA, FTA, etc.
Risk data: test data,
expert opinion, hazard
analysis, FMEA, FTA,
lessons learned,
technical analysis
Resources
Replan Mitigation

Identify
Identify Risks, Issues, and
Concerns

Analyze

Risk classification, Likelihood
Consequence, Timeframe
Risk prioritization

Evaluate, classify, and
prioritize risks

Plan
Decide what should be done
about each risk

Program/project data
(metrics information)

Statement of risk

Tr a c k

Research, Watch (tracking
requirements)
Acceptance Rationale,
Mitigation Plans

Risk status reports on:
Risks
Risk Mitigation Plans

Monitor risk metrics and
verify/validate mitigations

Control

Close or Accept Risks
Invoke contingency plans
Continue to track

Make risk decisions
† Continuous Risk Management, Audrey J. Dorofee, Software Engineering Institute, Carnegie Mellon University, 1996

21/29
How is Performance-Based Project
Management® different from traditional
approaches to project management?
 All work activities are traceable to and from the needed
business or mission capabilities†.
 All activities are focused on Outcomes rather than Output.
 Performance is measured as Physical Percent Complete,
not the consumption of resources and the passage of time.
 All planning and measurement is risk adjusted.
 Performance-Based Project Management ® never
confuses effort with results – the customer only bought
results.
† A Metric Framework for Capability Definition, Engineering and Management, Seventeenth Annual International
Symposium of the International Council On Systems Engineering (INCOSE) 24 - 28 July 2007
Performance Based Management(sm), Copyright ® Glen B. Alleman, 2012

22/29
How is Performance-Based Project
Management® the same as traditional
approaches to project management?
 Founding principles based on US DoD program
management processes, PMBOK®, and Agile project
management methods.
 Planning assures incremental progress measured in units
meaningful to the buyer.
 All project participants integrated with each activity
providing full visibility into progress to plan.
 Continuous risk management embedded in each detailed
process step.

Performance Based Management(sm), Copyright ® Glen B. Alleman, 2012

23/29
1. Identify Needed Systems Capabilities – Define the Measures of Effectiveness (MoE) for each Capability
D E F I N E O P E R A T IONA L C O N C E P TS T H R O U GH S C EN ARIOS O R U S E C A S E S
Partition system capabilities into classes of service within operational scenarios
Connect capabilities to system requirements using sysML
Define Measures of Effectiveness (MoE) for these capabilities in units meaningful to the customer
Define in the master schedule the achievement of measure of Technical Performance
D E F I N E C A PA B I L I TIES N E EDED T O I M PL EMENT T H E O PE RATION AL C O N C E PTS
Define scenarios for each system capability
Connect these scenarios to the Value Stream map
Assess value flow through the map for each needed capability
Identify capability mismatches and make corrections to improve overall value flow
A S S E SS N E EDS , C O S T , A N D R I S K S I M U L TANEOUSLY
Assign costs to each system element using a value process model
Assure risk, probabilistic cost and benefit performance attributes are defined
Use cost, schedule, and technical performance probabilistic models to forecast potential risks to project performance
D E F I N E E X P L I C I T , B A L A N CED , A N D F E A S IBLE A L T E RN ATIVES
Make tradeoffs that connect cost, schedule, and technical performance in a single “trade space” model
Measures of Effectiveness and Measures of Performance are the raw materials for these tradeoffs

2. Establish Requirements Baseline – Define Measures Of Performance (MoP) for each requirement delivering a Capability
P E R FORM F A C T F I N D I N G
Produce an overall statement of the problem in the operational context
Develop the overall operational and technical; objectives of the target system through Measures of Performance (MoP) for the requirements
Define the boundaries and interfaces of the target system
G A T H E R A N D C L A S S IFY THE R EQUI REMENTS
Gather required operational capabilities, functional, nonfunctional, and environment requirements and design constraints
Build a Top Down Capabilities and Functional decomposition of the requirements in a flow down tree using a requirements tool
E V A L U A TE A ND R A T I ONALI ZE T H E R E Q UI REMENTS
Answer the question “why do we need this?” in terms of operational benefits
Build a cost / benefit model using probabilistic assessments of all variables and dependencies
For technical requirements, perform a risk assessment to the cost and schedule
P R I O RITIZE T H E R E Q U IREMEN TS
Determine the criticality for the functions for the system’s mission
Determine tradeoff relations for all requirements to be used when option decision are made
For technical items, prioritize the cost and dependencies
I N T E G R ATE A N D V A L I D ATE T H E R E Q U IREMEN TS
Address completeness of requirements by removing all TBD items
Validate the requirements agree and are traceable to capabilities, goals, and the mission
Resolve any requirement inconsistencies and conflicts

24

Performance-Base Project Management (sm)

Chapter I
3. Establish Performance Measurement Ba seline – Define Technical Performance Measures (TPM)
D E C O M POSE R E Q U IREMENTS I N T O W ORK P A CKA GES A N D P L A N N IN G P A C K A G ES
Decompose the project scope into a product based Work Breakdown Structure (WBS)
Decompose the WBS into Work Packages describing the production of all outcomes and processes traceable to the requirements
A S S I G N A C C O U NTA BILITY F O R T H E O U T C OME F R OM E A C H W O R K P A C K A G E
Assign accountability for Work Packages to a named owner for the management of resource allocation, cost baseline, and technical delivery
ARRANGE WORK PACKAGES IN A LOGICAL ORDER
Arrange Work Packages in a network with defined outcomes, milestones, internal and external dependencies, appropriate schedule and cost margin
D E V E L OP T H E B U D G ETED C O ST F O R W O R K S C H E D ULED (BCWS) F O R E A C H W O R K P A C K A G E A N D P L A N N ING P A C K A GE
Develop a time‒phased Budgeted Cost for Work Scheduled (BCWS) for labor and material costs in each Work Package
Develop a time‒phased Budgeted Cost for Work Scheduled (BCWS) for the project as a whole
Assure proper resource allocations can be met and budget profiles match expectations of the project sponsor
A S S I G N W O R K P A C K A G E M E A S U RES O F P E R F ORMA NCE (M O P), K E Y P E R FORMAN CE P A R A METERS (KPP), A N D T E C H N I CAL P E R F ORMA NCE M E A S U RES (TPM)
Assign an objective Measure of Performance (MoP) for each critical Work Package outcomes
Trace critical outcomes to the Measure of Effectiveness (MoE) defined in the Capabilities baseline
Summarize these Measures of Performance (MoP) and Measures of Effectiveness (MoE) for the project as a whole
Assign measures of Physical Percent Complete for each Work Package
Assign measures of Physical Percent Complete for the program as a whole
S E T T H E P ERFORMA NCE M E A S U REMENT B A S E LINE (PMB)
Establish a Performance Measurement Baseline (PMB) used to forecast Work Package and Project ongoing and completion cost and schedule metrics

4. Execute the Performance Measurement Baseline (PMB) – Maintain Cost, Schedule, and Technical Performance
PER FORM A U T H ORI ZED W O R K I N T H E P L A N N ED S E Q U ENCE
Using the Work Package sequencing, release work to be performed as planned
With the RACI based RAM, the Accountable delivery manager guides the development of the products or service for each Work Package
A C C U M ULATE A N D R E P O RT W ORK P A CKA GE P H Y S I CAL P E R FORMAN CE
Using Physical Percent complete or Apportioned Milestones, capture the measures of “progress to plan” for each Work Package
Report the Physical Percent Complete in a centralized system for each Work Package and he program as a whole
A N A L Y ZE W O R K P A C K A G E P E R FORMAN CE
Compare the Actual Percent Complete against the Planned Percent Complete for each period of performance
Construct cost and schedule performance indices from this information and the Physical Percent Complete measures
T A K E C O R R E CTIV E M A N A G E MEN T A C T I ON FOR A N Y V A R I A NCE I N W O R K P A C K A GE P E R FORMAN CE
With the cost and schedule performance indices, construct a forecast of future performance of cost, schedule, and technical performance compliance
Take management actions for any Work Packages not performing as planned
M A I N T A IN P ERFORMANCE M E ASU REMENT B A S E LINE ’ S I N T E G R ITY
Record past performance based on Work Package completion criteria
Record previous future performance estimates in a historical database
Forecast future performance against the Performance Measurement Baseline
Report the future performance estimate to the program stakeholders

25

Performance-Base Project Management (sm)

Chapter I
5 Principles of Project Success

What does done look like?
How do we get there?
Are there enough resources?
What are progress impediments?
How do we measure progress?
Performance Based Management(sm), Copyright ® Glen B. Alleman, 2012
5 Practices Needed to Implement the
5 Principles
Identify Capabilities in units of
measure meaningful to the customer
Identify Technical & Operational
Requirements to deliver capabilities
Establish risk adjusted Technical, Cost,
and Schedule Baseline.

Execute baseline with measurements of
physical percent complete
Apply Continuous Risk Management
27

Performance Based Management(sm), Copyright ® Glen B. Alleman, 2012
5 Processes Needed the Implement the
5 Practices Guided by the 5 Principles
Organize the deliverables and staff
doing the work
Plan, Budget, and Schedule in the
Performance Measurement baseline
Account for direct and indirect costs
against planned costs

Analyze performance for cost,
schedule, and technical variance
Manage revisions to Performance
Measurement Baseline
28

Performance Based Management(sm), Copyright ® Glen B. Alleman, 2012
Glen B. Alleman, Copyright © 2012

29/29

Mais conteúdo relacionado

Mais procurados

Deliverables based planning handbook
Deliverables based planning handbookDeliverables based planning handbook
Deliverables based planning handbookGlen Alleman
 
Ev+agile=success (final v2)
Ev+agile=success (final v2)Ev+agile=success (final v2)
Ev+agile=success (final v2)Glen Alleman
 
Making the impossible possible
Making the impossible possibleMaking the impossible possible
Making the impossible possibleGlen Alleman
 
Performance-Based Project Management In A Nut Shell
Performance-Based Project Management In A Nut ShellPerformance-Based Project Management In A Nut Shell
Performance-Based Project Management In A Nut ShellGlen Alleman
 
Building the perfect schedule (v6)
Building the perfect schedule (v6)Building the perfect schedule (v6)
Building the perfect schedule (v6)Glen Alleman
 
The 5 Immutable principles of project management
The 5 Immutable principles of project managementThe 5 Immutable principles of project management
The 5 Immutable principles of project managementGlen Alleman
 
Agile project management is systems management
Agile project management is systems managementAgile project management is systems management
Agile project management is systems managementGlen Alleman
 
Measures of Effectiveness, Measures of Performance, Technical Performance Mea...
Measures of Effectiveness, Measures of Performance, Technical Performance Mea...Measures of Effectiveness, Measures of Performance, Technical Performance Mea...
Measures of Effectiveness, Measures of Performance, Technical Performance Mea...Glen Alleman
 
Policy and Procedure Rollout
Policy and Procedure RolloutPolicy and Procedure Rollout
Policy and Procedure RolloutGlen Alleman
 
Product development kaizen (pdk)
Product  development kaizen (pdk)Product  development kaizen (pdk)
Product development kaizen (pdk)Glen Alleman
 
Improving Project Performance in the DOE
Improving Project Performance in the DOEImproving Project Performance in the DOE
Improving Project Performance in the DOEGlen Alleman
 
Earned value, XP and government contracts
Earned value, XP and government contractsEarned value, XP and government contracts
Earned value, XP and government contractsGlen Alleman
 
Increasing the Probability of Project Success with Five Principles and Practices
Increasing the Probability of Project Success with Five Principles and PracticesIncreasing the Probability of Project Success with Five Principles and Practices
Increasing the Probability of Project Success with Five Principles and PracticesGlen Alleman
 
5 immutable principles and 5 processes in 60 seconds
5 immutable principles and 5 processes in 60 seconds5 immutable principles and 5 processes in 60 seconds
5 immutable principles and 5 processes in 60 secondsGlen Alleman
 
Five immutable principles
Five immutable principlesFive immutable principles
Five immutable principlesGlen Alleman
 
Integrated Program Performance Management
Integrated Program Performance ManagementIntegrated Program Performance Management
Integrated Program Performance ManagementGlen Alleman
 
IMP / IMS Step by Step
IMP / IMS Step by StepIMP / IMS Step by Step
IMP / IMS Step by StepGlen Alleman
 
5 Immutable Principles of Capital Project SUccess
5 Immutable Principles of Capital Project SUccess5 Immutable Principles of Capital Project SUccess
5 Immutable Principles of Capital Project SUccessGlen Alleman
 
A Guide for Capital Project Mamnagers
A Guide for Capital Project MamnagersA Guide for Capital Project Mamnagers
A Guide for Capital Project MamnagersGlen Alleman
 

Mais procurados (20)

Deliverables based planning handbook
Deliverables based planning handbookDeliverables based planning handbook
Deliverables based planning handbook
 
Ev+agile=success (final v2)
Ev+agile=success (final v2)Ev+agile=success (final v2)
Ev+agile=success (final v2)
 
Making the impossible possible
Making the impossible possibleMaking the impossible possible
Making the impossible possible
 
Performance-Based Project Management In A Nut Shell
Performance-Based Project Management In A Nut ShellPerformance-Based Project Management In A Nut Shell
Performance-Based Project Management In A Nut Shell
 
Building the perfect schedule (v6)
Building the perfect schedule (v6)Building the perfect schedule (v6)
Building the perfect schedule (v6)
 
The 5 Immutable principles of project management
The 5 Immutable principles of project managementThe 5 Immutable principles of project management
The 5 Immutable principles of project management
 
Agile project management is systems management
Agile project management is systems managementAgile project management is systems management
Agile project management is systems management
 
Lifecycle
LifecycleLifecycle
Lifecycle
 
Measures of Effectiveness, Measures of Performance, Technical Performance Mea...
Measures of Effectiveness, Measures of Performance, Technical Performance Mea...Measures of Effectiveness, Measures of Performance, Technical Performance Mea...
Measures of Effectiveness, Measures of Performance, Technical Performance Mea...
 
Policy and Procedure Rollout
Policy and Procedure RolloutPolicy and Procedure Rollout
Policy and Procedure Rollout
 
Product development kaizen (pdk)
Product  development kaizen (pdk)Product  development kaizen (pdk)
Product development kaizen (pdk)
 
Improving Project Performance in the DOE
Improving Project Performance in the DOEImproving Project Performance in the DOE
Improving Project Performance in the DOE
 
Earned value, XP and government contracts
Earned value, XP and government contractsEarned value, XP and government contracts
Earned value, XP and government contracts
 
Increasing the Probability of Project Success with Five Principles and Practices
Increasing the Probability of Project Success with Five Principles and PracticesIncreasing the Probability of Project Success with Five Principles and Practices
Increasing the Probability of Project Success with Five Principles and Practices
 
5 immutable principles and 5 processes in 60 seconds
5 immutable principles and 5 processes in 60 seconds5 immutable principles and 5 processes in 60 seconds
5 immutable principles and 5 processes in 60 seconds
 
Five immutable principles
Five immutable principlesFive immutable principles
Five immutable principles
 
Integrated Program Performance Management
Integrated Program Performance ManagementIntegrated Program Performance Management
Integrated Program Performance Management
 
IMP / IMS Step by Step
IMP / IMS Step by StepIMP / IMS Step by Step
IMP / IMS Step by Step
 
5 Immutable Principles of Capital Project SUccess
5 Immutable Principles of Capital Project SUccess5 Immutable Principles of Capital Project SUccess
5 Immutable Principles of Capital Project SUccess
 
A Guide for Capital Project Mamnagers
A Guide for Capital Project MamnagersA Guide for Capital Project Mamnagers
A Guide for Capital Project Mamnagers
 

Destaque

Capabilities based planning (v2)
Capabilities based planning (v2)Capabilities based planning (v2)
Capabilities based planning (v2)Glen Alleman
 
Principles of program governance
Principles of program governancePrinciples of program governance
Principles of program governanceGlen Alleman
 
Paradigm of agile project management
Paradigm of agile project managementParadigm of agile project management
Paradigm of agile project managementGlen Alleman
 
Managing in the presence of uncertainty
Managing in the presence of uncertaintyManaging in the presence of uncertainty
Managing in the presence of uncertaintyGlen Alleman
 
Project maturity flow is the incremental delivery of business value
Project maturity flow is the incremental delivery of business valueProject maturity flow is the incremental delivery of business value
Project maturity flow is the incremental delivery of business valueGlen Alleman
 
Vision goal csf kpi
Vision goal csf kpiVision goal csf kpi
Vision goal csf kpiGlen Alleman
 
Agile in the government
Agile in the government Agile in the government
Agile in the government Glen Alleman
 
Agile at scale resources
Agile at scale resourcesAgile at scale resources
Agile at scale resourcesGlen Alleman
 
Risk management using risk+ (v5)
Risk management using risk+ (v5)Risk management using risk+ (v5)
Risk management using risk+ (v5)Glen Alleman
 
Focus on the nine I's (v9)
Focus on the nine I's (v9)Focus on the nine I's (v9)
Focus on the nine I's (v9)Glen Alleman
 
Moe mop tpm connections
Moe mop tpm connectionsMoe mop tpm connections
Moe mop tpm connectionsGlen Alleman
 
Cpm 200 c technical performance measures - alleman (ppm)
Cpm 200 c   technical performance measures - alleman (ppm)Cpm 200 c   technical performance measures - alleman (ppm)
Cpm 200 c technical performance measures - alleman (ppm)Glen Alleman
 
Evm+agile estimating
Evm+agile estimatingEvm+agile estimating
Evm+agile estimatingGlen Alleman
 
The integrated master plan and integrated master schedule
The integrated master plan and integrated master scheduleThe integrated master plan and integrated master schedule
The integrated master plan and integrated master scheduleGlen Alleman
 
Nine Best Practices
Nine Best PracticesNine Best Practices
Nine Best PracticesGlen Alleman
 
Making the impossible possible
Making the impossible possibleMaking the impossible possible
Making the impossible possibleGlen Alleman
 
Notes on balanced scorecard
Notes on balanced scorecardNotes on balanced scorecard
Notes on balanced scorecardGlen Alleman
 
Technical Performance Measures
Technical Performance MeasuresTechnical Performance Measures
Technical Performance MeasuresGlen Alleman
 

Destaque (20)

Capabilities based planning (v2)
Capabilities based planning (v2)Capabilities based planning (v2)
Capabilities based planning (v2)
 
Principles of program governance
Principles of program governancePrinciples of program governance
Principles of program governance
 
Paradigm of agile project management
Paradigm of agile project managementParadigm of agile project management
Paradigm of agile project management
 
Managing in the presence of uncertainty
Managing in the presence of uncertaintyManaging in the presence of uncertainty
Managing in the presence of uncertainty
 
Project maturity flow is the incremental delivery of business value
Project maturity flow is the incremental delivery of business valueProject maturity flow is the incremental delivery of business value
Project maturity flow is the incremental delivery of business value
 
Vision goal csf kpi
Vision goal csf kpiVision goal csf kpi
Vision goal csf kpi
 
Agile in the government
Agile in the government Agile in the government
Agile in the government
 
Agile at scale resources
Agile at scale resourcesAgile at scale resources
Agile at scale resources
 
Governance
GovernanceGovernance
Governance
 
Risk management using risk+ (v5)
Risk management using risk+ (v5)Risk management using risk+ (v5)
Risk management using risk+ (v5)
 
Focus on the nine I's (v9)
Focus on the nine I's (v9)Focus on the nine I's (v9)
Focus on the nine I's (v9)
 
Moe mop tpm connections
Moe mop tpm connectionsMoe mop tpm connections
Moe mop tpm connections
 
Cpm 200 c technical performance measures - alleman (ppm)
Cpm 200 c   technical performance measures - alleman (ppm)Cpm 200 c   technical performance measures - alleman (ppm)
Cpm 200 c technical performance measures - alleman (ppm)
 
Evm+agile estimating
Evm+agile estimatingEvm+agile estimating
Evm+agile estimating
 
The integrated master plan and integrated master schedule
The integrated master plan and integrated master scheduleThe integrated master plan and integrated master schedule
The integrated master plan and integrated master schedule
 
Nine Best Practices
Nine Best PracticesNine Best Practices
Nine Best Practices
 
Del
DelDel
Del
 
Making the impossible possible
Making the impossible possibleMaking the impossible possible
Making the impossible possible
 
Notes on balanced scorecard
Notes on balanced scorecardNotes on balanced scorecard
Notes on balanced scorecard
 
Technical Performance Measures
Technical Performance MeasuresTechnical Performance Measures
Technical Performance Measures
 

Semelhante a Performance based planning in a nut shell (V5)

Heliotropic Abundance
Heliotropic AbundanceHeliotropic Abundance
Heliotropic AbundanceGlen Alleman
 
Chapter 0 of Performance Based Project Management (sm)
Chapter 0 of Performance Based Project Management (sm)Chapter 0 of Performance Based Project Management (sm)
Chapter 0 of Performance Based Project Management (sm)Glen Alleman
 
Five Immutable Principles of Program Success and Their Supporting Processes a...
Five Immutable Principles of Program Success and Their Supporting Processes a...Five Immutable Principles of Program Success and Their Supporting Processes a...
Five Immutable Principles of Program Success and Their Supporting Processes a...Glen Alleman
 
Five Immutable Principles of Project of Digital Transformation Success
Five Immutable Principles of Project of Digital Transformation SuccessFive Immutable Principles of Project of Digital Transformation Success
Five Immutable Principles of Project of Digital Transformation SuccessGlen Alleman
 
Performance based management in a nut shell (v5)
Performance based management in a nut shell (v5)Performance based management in a nut shell (v5)
Performance based management in a nut shell (v5)Glen Alleman
 
Getting to Done (PMI Denver)
Getting to Done (PMI Denver)Getting to Done (PMI Denver)
Getting to Done (PMI Denver)Glen Alleman
 
Getting To Done - A Master Class Workshop
Getting To Done - A Master Class WorkshopGetting To Done - A Master Class Workshop
Getting To Done - A Master Class WorkshopGlen Alleman
 
From Needed Capabilities to Project Deliverables - On Time, On Budget, On Spe...
From Needed Capabilities to Project Deliverables - On Time, On Budget, On Spe...From Needed Capabilities to Project Deliverables - On Time, On Budget, On Spe...
From Needed Capabilities to Project Deliverables - On Time, On Budget, On Spe...Glen Alleman
 
From WBS to Integrated Master Schedule
From WBS to Integrated Master ScheduleFrom WBS to Integrated Master Schedule
From WBS to Integrated Master ScheduleGlen Alleman
 
Increasing the probability of project success using Earned Value Management
Increasing the probability of project success using Earned Value ManagementIncreasing the probability of project success using Earned Value Management
Increasing the probability of project success using Earned Value ManagementGlen Alleman
 
The Five Immutable Principles of Project DSuccess
The Five Immutable Principles of Project DSuccessThe Five Immutable Principles of Project DSuccess
The Five Immutable Principles of Project DSuccessGlen Alleman
 
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...Glen Alleman
 
Connecting PMB® with PMBOK®
Connecting PMB® with PMBOK®Connecting PMB® with PMBOK®
Connecting PMB® with PMBOK®Glen Alleman
 
Deliverables based planning
Deliverables based planning Deliverables based planning
Deliverables based planning Glen Alleman
 
Showing how to Increase the Probability of Project Success by applying the ...
Showing how to Increase the Probability of Project Success by applying the ...Showing how to Increase the Probability of Project Success by applying the ...
Showing how to Increase the Probability of Project Success by applying the ...Glen Alleman
 
PetroSync - Successful Project Cost Estimation & Control
PetroSync - Successful Project Cost Estimation & ControlPetroSync - Successful Project Cost Estimation & Control
PetroSync - Successful Project Cost Estimation & ControlPetroSync
 
Performance Based Management Handbook
Performance Based Management HandbookPerformance Based Management Handbook
Performance Based Management HandbookGlen Alleman
 
Project Success: The Basis of the Five Immutable Principles
Project Success: The Basis of the Five Immutable PrinciplesProject Success: The Basis of the Five Immutable Principles
Project Success: The Basis of the Five Immutable PrinciplesGlen Alleman
 
Earned Value Management and Agile
Earned Value Management and AgileEarned Value Management and Agile
Earned Value Management and AgileGlen Alleman
 

Semelhante a Performance based planning in a nut shell (V5) (20)

Heliotropic Abundance
Heliotropic AbundanceHeliotropic Abundance
Heliotropic Abundance
 
Chapter 0 of Performance Based Project Management (sm)
Chapter 0 of Performance Based Project Management (sm)Chapter 0 of Performance Based Project Management (sm)
Chapter 0 of Performance Based Project Management (sm)
 
Five Immutable Principles of Program Success and Their Supporting Processes a...
Five Immutable Principles of Program Success and Their Supporting Processes a...Five Immutable Principles of Program Success and Their Supporting Processes a...
Five Immutable Principles of Program Success and Their Supporting Processes a...
 
Five Immutable Principles of Project of Digital Transformation Success
Five Immutable Principles of Project of Digital Transformation SuccessFive Immutable Principles of Project of Digital Transformation Success
Five Immutable Principles of Project of Digital Transformation Success
 
Performance based management in a nut shell (v5)
Performance based management in a nut shell (v5)Performance based management in a nut shell (v5)
Performance based management in a nut shell (v5)
 
Getting to Done (PMI Denver)
Getting to Done (PMI Denver)Getting to Done (PMI Denver)
Getting to Done (PMI Denver)
 
Getting To Done - A Master Class Workshop
Getting To Done - A Master Class WorkshopGetting To Done - A Master Class Workshop
Getting To Done - A Master Class Workshop
 
From Needed Capabilities to Project Deliverables - On Time, On Budget, On Spe...
From Needed Capabilities to Project Deliverables - On Time, On Budget, On Spe...From Needed Capabilities to Project Deliverables - On Time, On Budget, On Spe...
From Needed Capabilities to Project Deliverables - On Time, On Budget, On Spe...
 
From WBS to Integrated Master Schedule
From WBS to Integrated Master ScheduleFrom WBS to Integrated Master Schedule
From WBS to Integrated Master Schedule
 
Increasing the probability of project success using Earned Value Management
Increasing the probability of project success using Earned Value ManagementIncreasing the probability of project success using Earned Value Management
Increasing the probability of project success using Earned Value Management
 
The Five Immutable Principles of Project DSuccess
The Five Immutable Principles of Project DSuccessThe Five Immutable Principles of Project DSuccess
The Five Immutable Principles of Project DSuccess
 
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
 
Connecting PMB® with PMBOK®
Connecting PMB® with PMBOK®Connecting PMB® with PMBOK®
Connecting PMB® with PMBOK®
 
Deliverables based planning
Deliverables based planning Deliverables based planning
Deliverables based planning
 
Showing how to Increase the Probability of Project Success by applying the ...
Showing how to Increase the Probability of Project Success by applying the ...Showing how to Increase the Probability of Project Success by applying the ...
Showing how to Increase the Probability of Project Success by applying the ...
 
PetroSync - Successful Project Cost Estimation & Control
PetroSync - Successful Project Cost Estimation & ControlPetroSync - Successful Project Cost Estimation & Control
PetroSync - Successful Project Cost Estimation & Control
 
Psp Tsp Agile 3 1 En
Psp Tsp Agile 3 1 EnPsp Tsp Agile 3 1 En
Psp Tsp Agile 3 1 En
 
Performance Based Management Handbook
Performance Based Management HandbookPerformance Based Management Handbook
Performance Based Management Handbook
 
Project Success: The Basis of the Five Immutable Principles
Project Success: The Basis of the Five Immutable PrinciplesProject Success: The Basis of the Five Immutable Principles
Project Success: The Basis of the Five Immutable Principles
 
Earned Value Management and Agile
Earned Value Management and AgileEarned Value Management and Agile
Earned Value Management and Agile
 

Mais de Glen Alleman

Managing risk with deliverables planning
Managing risk with deliverables planningManaging risk with deliverables planning
Managing risk with deliverables planningGlen Alleman
 
A Gentle Introduction to the IMP/IMS
A Gentle Introduction to the IMP/IMSA Gentle Introduction to the IMP/IMS
A Gentle Introduction to the IMP/IMSGlen Alleman
 
Increasing the Probability of Project Success
Increasing the Probability of Project SuccessIncreasing the Probability of Project Success
Increasing the Probability of Project SuccessGlen Alleman
 
Process Flow and Narrative for Agile+PPM
Process Flow and Narrative for Agile+PPMProcess Flow and Narrative for Agile+PPM
Process Flow and Narrative for Agile+PPMGlen Alleman
 
Practices of risk management
Practices of risk managementPractices of risk management
Practices of risk managementGlen Alleman
 
Principles of Risk Management
Principles of Risk ManagementPrinciples of Risk Management
Principles of Risk ManagementGlen Alleman
 
From Principles to Strategies for Systems Engineering
From Principles to Strategies for Systems EngineeringFrom Principles to Strategies for Systems Engineering
From Principles to Strategies for Systems EngineeringGlen Alleman
 
NAVAIR Integrated Master Schedule Guide guide
NAVAIR Integrated Master Schedule Guide guideNAVAIR Integrated Master Schedule Guide guide
NAVAIR Integrated Master Schedule Guide guideGlen Alleman
 
Building a Credible Performance Measurement Baseline
Building a Credible Performance Measurement BaselineBuilding a Credible Performance Measurement Baseline
Building a Credible Performance Measurement BaselineGlen Alleman
 
Integrated master plan methodology (v2)
Integrated master plan methodology (v2)Integrated master plan methodology (v2)
Integrated master plan methodology (v2)Glen Alleman
 
DHS - Using functions points to estimate agile development programs (v2)
DHS - Using functions points to estimate agile development programs (v2)DHS - Using functions points to estimate agile development programs (v2)
DHS - Using functions points to estimate agile development programs (v2)Glen Alleman
 
Capabilities based planning
Capabilities based planningCapabilities based planning
Capabilities based planningGlen Alleman
 
Process Flow and Narrative for Agile
Process Flow and Narrative for AgileProcess Flow and Narrative for Agile
Process Flow and Narrative for AgileGlen Alleman
 
Building the Performance Measurement Baseline
Building the Performance Measurement BaselineBuilding the Performance Measurement Baseline
Building the Performance Measurement BaselineGlen Alleman
 
Program Management Office Lean Software Development and Six Sigma
Program Management Office Lean Software Development and Six SigmaProgram Management Office Lean Software Development and Six Sigma
Program Management Office Lean Software Development and Six SigmaGlen Alleman
 
Integrated Master Plan Development
Integrated Master Plan DevelopmentIntegrated Master Plan Development
Integrated Master Plan DevelopmentGlen Alleman
 
Project Management Theory
Project Management TheoryProject Management Theory
Project Management TheoryGlen Alleman
 
Seven Habits of a Highly Effective agile project manager
Seven Habits of a Highly Effective agile project managerSeven Habits of a Highly Effective agile project manager
Seven Habits of a Highly Effective agile project managerGlen Alleman
 
Paradigm of agile project management (update)
Paradigm of agile project management (update)Paradigm of agile project management (update)
Paradigm of agile project management (update)Glen Alleman
 
Integrating cost, schedule, and technical performance
Integrating cost, schedule, and technical performanceIntegrating cost, schedule, and technical performance
Integrating cost, schedule, and technical performanceGlen Alleman
 

Mais de Glen Alleman (20)

Managing risk with deliverables planning
Managing risk with deliverables planningManaging risk with deliverables planning
Managing risk with deliverables planning
 
A Gentle Introduction to the IMP/IMS
A Gentle Introduction to the IMP/IMSA Gentle Introduction to the IMP/IMS
A Gentle Introduction to the IMP/IMS
 
Increasing the Probability of Project Success
Increasing the Probability of Project SuccessIncreasing the Probability of Project Success
Increasing the Probability of Project Success
 
Process Flow and Narrative for Agile+PPM
Process Flow and Narrative for Agile+PPMProcess Flow and Narrative for Agile+PPM
Process Flow and Narrative for Agile+PPM
 
Practices of risk management
Practices of risk managementPractices of risk management
Practices of risk management
 
Principles of Risk Management
Principles of Risk ManagementPrinciples of Risk Management
Principles of Risk Management
 
From Principles to Strategies for Systems Engineering
From Principles to Strategies for Systems EngineeringFrom Principles to Strategies for Systems Engineering
From Principles to Strategies for Systems Engineering
 
NAVAIR Integrated Master Schedule Guide guide
NAVAIR Integrated Master Schedule Guide guideNAVAIR Integrated Master Schedule Guide guide
NAVAIR Integrated Master Schedule Guide guide
 
Building a Credible Performance Measurement Baseline
Building a Credible Performance Measurement BaselineBuilding a Credible Performance Measurement Baseline
Building a Credible Performance Measurement Baseline
 
Integrated master plan methodology (v2)
Integrated master plan methodology (v2)Integrated master plan methodology (v2)
Integrated master plan methodology (v2)
 
DHS - Using functions points to estimate agile development programs (v2)
DHS - Using functions points to estimate agile development programs (v2)DHS - Using functions points to estimate agile development programs (v2)
DHS - Using functions points to estimate agile development programs (v2)
 
Capabilities based planning
Capabilities based planningCapabilities based planning
Capabilities based planning
 
Process Flow and Narrative for Agile
Process Flow and Narrative for AgileProcess Flow and Narrative for Agile
Process Flow and Narrative for Agile
 
Building the Performance Measurement Baseline
Building the Performance Measurement BaselineBuilding the Performance Measurement Baseline
Building the Performance Measurement Baseline
 
Program Management Office Lean Software Development and Six Sigma
Program Management Office Lean Software Development and Six SigmaProgram Management Office Lean Software Development and Six Sigma
Program Management Office Lean Software Development and Six Sigma
 
Integrated Master Plan Development
Integrated Master Plan DevelopmentIntegrated Master Plan Development
Integrated Master Plan Development
 
Project Management Theory
Project Management TheoryProject Management Theory
Project Management Theory
 
Seven Habits of a Highly Effective agile project manager
Seven Habits of a Highly Effective agile project managerSeven Habits of a Highly Effective agile project manager
Seven Habits of a Highly Effective agile project manager
 
Paradigm of agile project management (update)
Paradigm of agile project management (update)Paradigm of agile project management (update)
Paradigm of agile project management (update)
 
Integrating cost, schedule, and technical performance
Integrating cost, schedule, and technical performanceIntegrating cost, schedule, and technical performance
Integrating cost, schedule, and technical performance
 

Último

Transcript: New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024Transcript: New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024BookNet Canada
 
What is DBT - The Ultimate Data Build Tool.pdf
What is DBT - The Ultimate Data Build Tool.pdfWhat is DBT - The Ultimate Data Build Tool.pdf
What is DBT - The Ultimate Data Build Tool.pdfMounikaPolabathina
 
A Framework for Development in the AI Age
A Framework for Development in the AI AgeA Framework for Development in the AI Age
A Framework for Development in the AI AgeCprime
 
Decarbonising Buildings: Making a net-zero built environment a reality
Decarbonising Buildings: Making a net-zero built environment a realityDecarbonising Buildings: Making a net-zero built environment a reality
Decarbonising Buildings: Making a net-zero built environment a realityIES VE
 
The Role of FIDO in a Cyber Secure Netherlands: FIDO Paris Seminar.pptx
The Role of FIDO in a Cyber Secure Netherlands: FIDO Paris Seminar.pptxThe Role of FIDO in a Cyber Secure Netherlands: FIDO Paris Seminar.pptx
The Role of FIDO in a Cyber Secure Netherlands: FIDO Paris Seminar.pptxLoriGlavin3
 
UiPath Community: Communication Mining from Zero to Hero
UiPath Community: Communication Mining from Zero to HeroUiPath Community: Communication Mining from Zero to Hero
UiPath Community: Communication Mining from Zero to HeroUiPathCommunity
 
Scale your database traffic with Read & Write split using MySQL Router
Scale your database traffic with Read & Write split using MySQL RouterScale your database traffic with Read & Write split using MySQL Router
Scale your database traffic with Read & Write split using MySQL RouterMydbops
 
Manual 508 Accessibility Compliance Audit
Manual 508 Accessibility Compliance AuditManual 508 Accessibility Compliance Audit
Manual 508 Accessibility Compliance AuditSkynet Technologies
 
TeamStation AI System Report LATAM IT Salaries 2024
TeamStation AI System Report LATAM IT Salaries 2024TeamStation AI System Report LATAM IT Salaries 2024
TeamStation AI System Report LATAM IT Salaries 2024Lonnie McRorey
 
Genislab builds better products and faster go-to-market with Lean project man...
Genislab builds better products and faster go-to-market with Lean project man...Genislab builds better products and faster go-to-market with Lean project man...
Genislab builds better products and faster go-to-market with Lean project man...Farhan Tariq
 
How to write a Business Continuity Plan
How to write a Business Continuity PlanHow to write a Business Continuity Plan
How to write a Business Continuity PlanDatabarracks
 
Unleashing Real-time Insights with ClickHouse_ Navigating the Landscape in 20...
Unleashing Real-time Insights with ClickHouse_ Navigating the Landscape in 20...Unleashing Real-time Insights with ClickHouse_ Navigating the Landscape in 20...
Unleashing Real-time Insights with ClickHouse_ Navigating the Landscape in 20...Alkin Tezuysal
 
Why device, WIFI, and ISP insights are crucial to supporting remote Microsoft...
Why device, WIFI, and ISP insights are crucial to supporting remote Microsoft...Why device, WIFI, and ISP insights are crucial to supporting remote Microsoft...
Why device, WIFI, and ISP insights are crucial to supporting remote Microsoft...panagenda
 
Digital Identity is Under Attack: FIDO Paris Seminar.pptx
Digital Identity is Under Attack: FIDO Paris Seminar.pptxDigital Identity is Under Attack: FIDO Paris Seminar.pptx
Digital Identity is Under Attack: FIDO Paris Seminar.pptxLoriGlavin3
 
Use of FIDO in the Payments and Identity Landscape: FIDO Paris Seminar.pptx
Use of FIDO in the Payments and Identity Landscape: FIDO Paris Seminar.pptxUse of FIDO in the Payments and Identity Landscape: FIDO Paris Seminar.pptx
Use of FIDO in the Payments and Identity Landscape: FIDO Paris Seminar.pptxLoriGlavin3
 
Moving Beyond Passwords: FIDO Paris Seminar.pdf
Moving Beyond Passwords: FIDO Paris Seminar.pdfMoving Beyond Passwords: FIDO Paris Seminar.pdf
Moving Beyond Passwords: FIDO Paris Seminar.pdfLoriGlavin3
 
Merck Moving Beyond Passwords: FIDO Paris Seminar.pptx
Merck Moving Beyond Passwords: FIDO Paris Seminar.pptxMerck Moving Beyond Passwords: FIDO Paris Seminar.pptx
Merck Moving Beyond Passwords: FIDO Paris Seminar.pptxLoriGlavin3
 
A Deep Dive on Passkeys: FIDO Paris Seminar.pptx
A Deep Dive on Passkeys: FIDO Paris Seminar.pptxA Deep Dive on Passkeys: FIDO Paris Seminar.pptx
A Deep Dive on Passkeys: FIDO Paris Seminar.pptxLoriGlavin3
 
The State of Passkeys with FIDO Alliance.pptx
The State of Passkeys with FIDO Alliance.pptxThe State of Passkeys with FIDO Alliance.pptx
The State of Passkeys with FIDO Alliance.pptxLoriGlavin3
 
Potential of AI (Generative AI) in Business: Learnings and Insights
Potential of AI (Generative AI) in Business: Learnings and InsightsPotential of AI (Generative AI) in Business: Learnings and Insights
Potential of AI (Generative AI) in Business: Learnings and InsightsRavi Sanghani
 

Último (20)

Transcript: New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024Transcript: New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024
 
What is DBT - The Ultimate Data Build Tool.pdf
What is DBT - The Ultimate Data Build Tool.pdfWhat is DBT - The Ultimate Data Build Tool.pdf
What is DBT - The Ultimate Data Build Tool.pdf
 
A Framework for Development in the AI Age
A Framework for Development in the AI AgeA Framework for Development in the AI Age
A Framework for Development in the AI Age
 
Decarbonising Buildings: Making a net-zero built environment a reality
Decarbonising Buildings: Making a net-zero built environment a realityDecarbonising Buildings: Making a net-zero built environment a reality
Decarbonising Buildings: Making a net-zero built environment a reality
 
The Role of FIDO in a Cyber Secure Netherlands: FIDO Paris Seminar.pptx
The Role of FIDO in a Cyber Secure Netherlands: FIDO Paris Seminar.pptxThe Role of FIDO in a Cyber Secure Netherlands: FIDO Paris Seminar.pptx
The Role of FIDO in a Cyber Secure Netherlands: FIDO Paris Seminar.pptx
 
UiPath Community: Communication Mining from Zero to Hero
UiPath Community: Communication Mining from Zero to HeroUiPath Community: Communication Mining from Zero to Hero
UiPath Community: Communication Mining from Zero to Hero
 
Scale your database traffic with Read & Write split using MySQL Router
Scale your database traffic with Read & Write split using MySQL RouterScale your database traffic with Read & Write split using MySQL Router
Scale your database traffic with Read & Write split using MySQL Router
 
Manual 508 Accessibility Compliance Audit
Manual 508 Accessibility Compliance AuditManual 508 Accessibility Compliance Audit
Manual 508 Accessibility Compliance Audit
 
TeamStation AI System Report LATAM IT Salaries 2024
TeamStation AI System Report LATAM IT Salaries 2024TeamStation AI System Report LATAM IT Salaries 2024
TeamStation AI System Report LATAM IT Salaries 2024
 
Genislab builds better products and faster go-to-market with Lean project man...
Genislab builds better products and faster go-to-market with Lean project man...Genislab builds better products and faster go-to-market with Lean project man...
Genislab builds better products and faster go-to-market with Lean project man...
 
How to write a Business Continuity Plan
How to write a Business Continuity PlanHow to write a Business Continuity Plan
How to write a Business Continuity Plan
 
Unleashing Real-time Insights with ClickHouse_ Navigating the Landscape in 20...
Unleashing Real-time Insights with ClickHouse_ Navigating the Landscape in 20...Unleashing Real-time Insights with ClickHouse_ Navigating the Landscape in 20...
Unleashing Real-time Insights with ClickHouse_ Navigating the Landscape in 20...
 
Why device, WIFI, and ISP insights are crucial to supporting remote Microsoft...
Why device, WIFI, and ISP insights are crucial to supporting remote Microsoft...Why device, WIFI, and ISP insights are crucial to supporting remote Microsoft...
Why device, WIFI, and ISP insights are crucial to supporting remote Microsoft...
 
Digital Identity is Under Attack: FIDO Paris Seminar.pptx
Digital Identity is Under Attack: FIDO Paris Seminar.pptxDigital Identity is Under Attack: FIDO Paris Seminar.pptx
Digital Identity is Under Attack: FIDO Paris Seminar.pptx
 
Use of FIDO in the Payments and Identity Landscape: FIDO Paris Seminar.pptx
Use of FIDO in the Payments and Identity Landscape: FIDO Paris Seminar.pptxUse of FIDO in the Payments and Identity Landscape: FIDO Paris Seminar.pptx
Use of FIDO in the Payments and Identity Landscape: FIDO Paris Seminar.pptx
 
Moving Beyond Passwords: FIDO Paris Seminar.pdf
Moving Beyond Passwords: FIDO Paris Seminar.pdfMoving Beyond Passwords: FIDO Paris Seminar.pdf
Moving Beyond Passwords: FIDO Paris Seminar.pdf
 
Merck Moving Beyond Passwords: FIDO Paris Seminar.pptx
Merck Moving Beyond Passwords: FIDO Paris Seminar.pptxMerck Moving Beyond Passwords: FIDO Paris Seminar.pptx
Merck Moving Beyond Passwords: FIDO Paris Seminar.pptx
 
A Deep Dive on Passkeys: FIDO Paris Seminar.pptx
A Deep Dive on Passkeys: FIDO Paris Seminar.pptxA Deep Dive on Passkeys: FIDO Paris Seminar.pptx
A Deep Dive on Passkeys: FIDO Paris Seminar.pptx
 
The State of Passkeys with FIDO Alliance.pptx
The State of Passkeys with FIDO Alliance.pptxThe State of Passkeys with FIDO Alliance.pptx
The State of Passkeys with FIDO Alliance.pptx
 
Potential of AI (Generative AI) in Business: Learnings and Insights
Potential of AI (Generative AI) in Business: Learnings and InsightsPotential of AI (Generative AI) in Business: Learnings and Insights
Potential of AI (Generative AI) in Business: Learnings and Insights
 

Performance based planning in a nut shell (V5)

  • 1. V5.0 Performance-Based Project Management® In A Nutshell Principles, Practices, and Processes that Increase Your Probability of Project Success Performance Based Management(sm), Copyright ® Glen B. Alleman, 2012
  • 2. Why Performance-Based Project Management®?  All successful projects must deliver capabilities:  Not the work efforts,  Not the cost expenditures,  Not the documentation, test results, or the processes. Performance-Based Project Management® Principles, Practices, and Processes for Increasing the Probability of Project Success† † Program Success Probability, John Higbee, Defense Acquisition University, 9 May 2005 Performance Based Management(sm), Copyright ® Glen B. Alleman, 2012  All successful projects must deliver tangible beneficial outcomes, measured in units meaningful to the decision makers. 2/29
  • 3. 5 Principles of Project Success . . . 1. What Does DONE Look Like? 2. What is the path to DONE? 3. Do We Have Enough Time, Resources, And Money To Get To DONE? 4. What Impediments Will We Encounter Along The Way To DONE? 5. How Do We Know We Are Making Progress Toward DONE? 5 Immutable Principles of Project Management, Copyright ©, Glen B. Alleman, 2012 3/29
  • 4. Identify Needed Capabilities Indentify Baseline Requirements Establish Performance Measurement Baseline Execute Performance Measurement Baseline Perform Continuous Risk Management (CRM)  Define Capabilities  Define ConOps  Assess Needs, Cost, and Risk Impacts  Define Balanced and Feasible Alternatives  Decompose Scope  Assign Accountability  Arrange Work  Develop BCWS  Assign Performance Define the Measurable Capabilities of each Project Outcome 4  Fact Finding  Gather And Classify  Evaluate And Rationalize  Prioritize Requirements  Integrate And Validate Assure All Requirements Provided In Support of Capabilities Define Measures of Performance and Effectiveness Performance Based Management(sm), Copyright ® Glen B. Alleman, 2012  Perform Work  Accumulate Performance Measures  Analyze Performance  Take Corrective Action Ensure Cost, Schedule, and Technical Performance Compliance
  • 5. Define the Work Breakdown Structure(WBS).  Identify the Organizational Breakdown Structure (OBS).  Integrate the WBS and OBS.  Schedule the work.  Identify the Products and Milestones.  Set the time phased budget.  Record direct costs. Performance Analysis  Determine variances.  Sum Data and variances.  Manage action plans.   Incorporate Changes. † These 11 processes are a subset of the 32 Criteria of ANSI–748B Earned Value Management. While not all projects can make use ANSI EVM, these process are the basis of all project management success. Performance Based Management(sm), Copyright ® Glen B. Alleman, 2012 5/29
  • 6. 6 Kavli Institute at Cornell for Nanoscale Science
  • 7. Principles and Practices of Performance-Based Project Management ® 5 Practices 5 Principles Identify Capabilities What does ConOps, SOO, done look like? SOW What is the path to Done? What resource do we need along the way? Integrated Master Plan (IMP) What impediments will we encounter along the way? 4 Levels of Uncertainty Assessment How do we measure progress? Measures of Effectiveness (MoE) Define Requirements Performance Measurement Baseline (PMB) Execute the PMB Continuous Risk Management Technical and Operational Based Plan Incremental Maturity Assessment Physical Percent Complete Risk Identification Iterative and Incremental Delivery Risk Analysis Future Performance Forecasting Risk Planning Risk adjusted Performance Measurement Baseline Risk Tracking Earned Value Management Risk Control Work Breakdown Structure Resource Management Plan Integrated Master Schedule (IMS) Technical and Risk adjustments Programmatic to cost and Risks assigned schedule to all WBS measures deliverables Measures of Performance (MoP) Technical Performance Measures
  • 8. Practices and Processes of Performance-Based Project Management ® 5 Processes Organize 5 Practices Identify Capabilities Plan, Schedule, Budget Project mission, Value stream of vision, and increasing deliverables maturity Define Requirements Resource Management Plan Analyze Variances Top level budget for capabilities Measures of Effectiveness Requirements traced to capabilities Performance Measurement Baseline Account for all costs Measures of Performance Work Packages with budget Labor and material costs Technical Performance Measures Baseline change request Budgeted Cost Work Package Physical Percent Technical for Work Performance Complete change requests Scheduled Execute the PMB Continuous Risk Management Manage Change Risk Register Risk impacts on cost and schedule Risk adjustments to PMB
  • 9. Performance-Based Project Management® Addresses The Critical Project Outcomes† The Situation  By their very nature, project are risky.  Successful project management is risk management.  Program management must be about avoiding surprises. The Problem  Traditional program management assumes technical and program processes drive outcomes.  Focusing on process alone has failed in the past. The Need  Program management is about avoiding surprises.  Measures of physical percent complete are mandatory. The Context  Organizations execute projects.  Adapting the organization culture to the project paradigm increases the probability of success. The Solution  Technical Performance of deliverables is a measure of increasing probability of success.  Earned Value Management reveals surprises. † Project Management Case Study, Pierre Bonnal, CNAM IIM MBA Program, June 2004 Performance Based Management(sm), Copyright ® Glen B. Alleman, 2012 9/29
  • 10. Practices produce Project Outcomes  The Outcome does not need to be the end product.  The Outcome is the result of Work Packages that increase the measureable maturity of the product or service. Outcomes incrementally increase a capability’s maturity  Outcomes are specified and measureable.  Design complete and verifiable.  Development complete and testable.  Testing complete and validated.  Installation and deployment complete and operational. Outcomes result from “units of work” – the Work Package  Work Packages consume time and resources.  Work Packages are owned by a single accountable person.  Work Packages produce outcomes. Project Management Case Study, Pierre Bonnal, CNAM IIM MBA Program, June 2004 Performance Based Management(sm), Copyright ® Glen B. Alleman, 2012 10/29
  • 11. Five Practices Of Performance-Based Project Management®  What capabilities are needed to fulfill the project goal, mission, or outcome? Identify Needed Capabilities  Establish Requirements Baseline  Establish the Performance Measurement Baseline  Execute the Performance Measurement Baseline  Perform Continuous Risk Management Define the set of capabilities needed to achieve the project objectives or the particular end state for a specific scenario. Using the Concept of Operations (ConOps), define the details of who, where, and how this capability is to be accomplished, employed, and executed. What technical & operational requirements are needed to produce the capabilities? Define the technical and operational requirements for the system capabilities to be fulfilled. First, define these requirements in terms isolated from any implementation details. Only then bind the requirements with technology. What is the schedule to deliver products or services to produce the requirements? Build a time–phased network of work activities describing the work to be performed, the budgeted cost for this work, the organizational elements that produce the outcomes, and the Performance measures showing this work is proceeding according to plan. What are the periodic measures of physical percent complete? Execute work activities, while assuring all Performance assessment represent 100% completion before proceeding. This means – No rework, no forward transfer of activities to the future. Assure all requirements are traceable to work & all work is traceable to requirements. What are the impediments to success and how are they being handled? Apply the processes of Continuous Risk Management for each Performance Based Management(sm) process area to: Identify, Analyze, Plan, Track, Control, and Communicate projectmatic and technical risk. 11/29
  • 12.  Identify Needed Capabilities Define the capabilities needed to achieve the desired objectives or a particular end state for a specific scenario. Define the details of who, where, and how these capabilities are to be accomplished, employed, and executed. What capabilities are needed to fulfill the Business Case or project Mission? 1.1 Define Capabilities as Operational Concepts Define Capabilities through Scenarios or Use Cases  Partition system capabilities into classes of service within operational scenarios.  Connect the capabilities to system requirements using some visual modeling notation.  Define Measures of Effectiveness (MoE) and Measures of Performance (MoP).  Define the delivery schedule for each measure of Performance and effectiveness. 1.2  Define scenarios for each system capability.  Connect these scenarios to a Value Stream Map of the increasing maturity of the project.  Assess value flow through the map for each needed capability.  Identify capability mismatches and make corrections to improve overall value flow. 1.3  Assign costs to each system element using a value flow model.  Assure risk, probabilistic cost and benefit Performance attributes are defined.  Use cost, schedule and technical Performance probabilistic models to forecast potential risks to project performance. Assess Needs, Costs, and Risks of the Capability Simultaneously 1.4 Define Explicit, Balanced, and Feasible Alternatives  Make tradeoffs that connect cost, schedule, and technical Performance in a single location that compares the tradeoffs and their impacts.  Use Measures of Effectiveness (MoE) and Measures of Performance (MoP) for these alternative tradeoffs. Performance Based Management(sm), Copyright ® Glen B. Alleman, 2012 12/29
  • 13.  What Does A Capability “Sound” Like?  We need the capability to pre‒process insurance claims at $0.07 per transaction rather than the current $0.11 per transaction.  We need the capability to remove 1½ hours from the retail ordering process once the merger is complete.  We need the capability to change the Wide Field Camera and the internal nickel hydride batteries, while doing no harm to the telescope.  We need the capability to fly 4 astronauts to the International Space Station, dock, stay 6 months, and return safely.  We need the capability to control the Hell Fire Missile with a new touch panel while maintaining existing navigation and guidance capabilities in the helicopter.  We need the capability to comply with FAR Part 15 using the current ERP system and its supporting work processes. Performance Based Management(sm), Copyright ® Glen B. Alleman, 2012 13/29
  • 14.  Establish Technical and Operational Requirements Baseline 2.1 Perform Fact Finding 2.2 Gather and Classify Requirements 2.3 Evaluate and Rationalize Requirements 2.4 Prioritize Requirements 2.5 Integrate and Validate Requirements Define the technical and operational requirements that must be present for the system capabilities to be delivered. Define these requirements in terms isolated from any technology or implementation. Assure each requirement is connected to a need system capability. What Technical and Operational Requirements are Needed to Produce the Capabilities?  Produce an overall statement of the customer need in the operational context.  Develop the overall operational and technical objectives of the system that meets the need.  Defined the boundaries and interfaces of the system.  Gather required system capabilities, functional, nonfunctional and environmental requirements, and design constraints.  Build the Top Down capabilities and functional decomposition of the requirements in a Requirements Management System.  Answer the question “why do I need this?” in terms of operational capabilities.  Build a cost / benefit model using probabilistic assessment of all variables, their dependencies, and impacts.  For all requirements, perform a risk assessment to cost and schedule.  Determine criticality for the functions of the system.  Determine trade off relationships for all requirements to be used when option decisions must be made.  For all technical items, prioritize their cost and dependency.  Address the completeness of requirements by removing all “TBD” items.  Validate that the requirements are traceable to system capabilities, goals, and mission.  Resolve any requirements inconsistencies and conflicts. Performance Based Management(sm), Copyright ® Glen B. Alleman, 2012 14/29
  • 15.  What Is a Requirement? A Requirement is …”A statement identifying a capability, a physical characteristic, or a quality factor that bounds a product or process need for which a solution will be pursued.” — IEEE Standard 1220–2005 The hardest single part of building a system is deciding what to build … ... No other part of the work so cripples the resulting system if done wrong. No other part is more difficult to rectify later. – Fred Brooks “No Silver Bullet,” 1987 Performance Based Management(sm), Copyright ® Glen B. Alleman, 2012 15/29
  • 16.  Establish Performance Measurement Baseline 3.1 Decompose Scope into Work Packages Build a time–phased network of activities describing the work to be performed, the budgeted cost for this work, the organizational elements that produce the outcomes from this work, and the Performance measures showing this work is proceeding according to plan. A Baselined Schedule that Produces the Products or Services that Meet The Requirements Decompose the outcomes into a product based Work Breakdown Structure (WBS), then further into Work Packages that produce these outcomes all traceable to the requirements, and to the needed capabilities. 3.2 Assign responsibility to Work Packages (the groupings of outcomes) to a named owner, accountable for the management of the resource allocations, cost and schedule baseline, and technical delivery of all element in the Work Breakdown Structure. 3.3 Arrange the Work Packages in a logical network with defined outcomes, milestones, internal and external dependencies, with credible schedule, cost, and technical Performance margins. 3.4 Develop the Time–Phased Budgeted Cost for Work Scheduled (BCWS) for the labor and material costs in each Work Package and the Project as a whole. Assure proper resource allocations can be met and budget profiles match expectations of the project sponsor Assign Responsibility for outcomes Arrange Work Packages in Logical Order Develop BCWS for Work Packages 3.5 Assign WP Measures of Performance Assign objective Measures of Performance (MoP) and Measures of Effectiveness (MoE) for each Work Package and summarize these for the Project as a whole. 3.6 Set Performance Measurement Baseline Establish a Performance Measurement Baseline (PMB) used to forecast the Work Package and Project ongoing and completion cost and schedule Performance metrics. Performance Based Management(sm), Copyright ® Glen B. Alleman, 2012 16/29
  • 17.  What Does a Credible Plan and Schedule Look Like?  The Plan is the strategy to successfully complete the project, described through Significant Accomplishments and their Accomplishment Criteria.  The Schedule is the sequence of the work activities measured by the Accomplishment Criteria, that follow the Plan of the Significant Accomplishments.  A credible Plan and Schedule means there is a statistical model of cost, schedule, and technical Performance of outcomes as the foundation of the credibility of the project’s probability of success. Performance Based Management(sm), Copyright ® Glen B. Alleman, 2012 17/29
  • 18.  Execute the Performance Measurement Baseline Execute the planned work, assuring all work is 100% complete before proceeding to the next planned work package. No rework, no forward transfer of activities or features. Assure every requirement is traceable to work and all work is traceable to requirements. How long are you willing to wait before you find out you’re late? 4.1  Using the Work Package sequencing, release work to be performed as planned.  With the responsibility assignments, identify the accountable delivery manager to guide the development of the products or services for each Work Package. 4.2 Accumulate  Using Physical Percent Complete or Apportioned Milestones, capture measures of progress to plan for each Work Package.  Report this Physical Percent Complete in a centralized database for each Work Package and the project as a whole. Perform the Authorized Work and Report Work Package Performance 4.3 Analyze Work Package Performance 4.4 Take Corrective Management Action 4.5 Maintain the Performance Baseline  Compare the Physical Percent Complete against the Planned Percent Complete for each period of performance.  Construct cost and schedule Performance indices from this information and the Physical Percent complete measures.  With Cost and Schedule Performance indices, construct a forecast of future Performance of cost, schedule, and technical Performance compliance.  Take management actions for any Work Packages not performing as planned.  Record past Performance based on Work Package completion criteria.  Record past future forecast Performance estimates in a historical database.  Forecast next future Performance estimate against the Performance Measurement Baseline.  Report this next future Performance estimate to the project stakeholders. Performance Based Management(sm), Copyright ® Glen B. Alleman, 2012 18/29
  • 19.  How Do We Know We Are Achieving Our Planned Progress?  The Only measure of progress is the assessment of physical percent complete.  This measurement Must be in units meaningful to the customer.  These units can be:     Planned capabilities, Planned capacities, Planned features and functions, Planned quantities.  Done is evidenced by the production of outcomes, on the planned date, for the planned cost, with the planned technical performance. Performance Based Management(sm), Copyright ® Glen B. Alleman, 2012 19/29
  • 20.  Apply Continuous Risk Management at Every Step 5.1 Identify Risks 5.2 Analyze Risks 5.3 Plan Risk Response 5.4 Track the Risk Management Activities 5.5 Control or Accept the Risks Continuous Risk Management starts the underlying principles, concepts, and functions of risk management and provides guidance on how to implement risk management as a continuous practice in projects and the organizations that management projects. What are the impediments to success and what are their mitigations?  Identify and classify risks in a Risk Register.  Manage this Risk Register through a Risk Management Board.  Connect these risks and their handling in the Master Schedule.  Convert risk data into risk decision‒making information.  Use this analysis information as the decision basis for the project manager to work on the “right” risks.  Turn risk information into decisions and actions (both present and future).  Develop actions to address individual risks, prioritize risk actions, and create an integrated risk management plan.  Monitor the status of risks and actions taken to ameliorate risks.  Identify and monitor risks to enable the evaluation of the status of risks themselves and of risk mitigation plans.  Risk communication lies at the center of the model to emphasize both its pervasiveness and its criticality.  Without effective communication, no risk management approach can be viable. Performance Based Management(sm), Copyright ® Glen B. Alleman, 2012 20/29
  • 21.  Continuous Risk Management† For Each Risk… Subproject and partner data/constraints, hazard analysis, FMEA, FTA, etc. Risk data: test data, expert opinion, hazard analysis, FMEA, FTA, lessons learned, technical analysis Resources Replan Mitigation Identify Identify Risks, Issues, and Concerns Analyze Risk classification, Likelihood Consequence, Timeframe Risk prioritization Evaluate, classify, and prioritize risks Plan Decide what should be done about each risk Program/project data (metrics information) Statement of risk Tr a c k Research, Watch (tracking requirements) Acceptance Rationale, Mitigation Plans Risk status reports on: Risks Risk Mitigation Plans Monitor risk metrics and verify/validate mitigations Control Close or Accept Risks Invoke contingency plans Continue to track Make risk decisions † Continuous Risk Management, Audrey J. Dorofee, Software Engineering Institute, Carnegie Mellon University, 1996 21/29
  • 22. How is Performance-Based Project Management® different from traditional approaches to project management?  All work activities are traceable to and from the needed business or mission capabilities†.  All activities are focused on Outcomes rather than Output.  Performance is measured as Physical Percent Complete, not the consumption of resources and the passage of time.  All planning and measurement is risk adjusted.  Performance-Based Project Management ® never confuses effort with results – the customer only bought results. † A Metric Framework for Capability Definition, Engineering and Management, Seventeenth Annual International Symposium of the International Council On Systems Engineering (INCOSE) 24 - 28 July 2007 Performance Based Management(sm), Copyright ® Glen B. Alleman, 2012 22/29
  • 23. How is Performance-Based Project Management® the same as traditional approaches to project management?  Founding principles based on US DoD program management processes, PMBOK®, and Agile project management methods.  Planning assures incremental progress measured in units meaningful to the buyer.  All project participants integrated with each activity providing full visibility into progress to plan.  Continuous risk management embedded in each detailed process step. Performance Based Management(sm), Copyright ® Glen B. Alleman, 2012 23/29
  • 24. 1. Identify Needed Systems Capabilities – Define the Measures of Effectiveness (MoE) for each Capability D E F I N E O P E R A T IONA L C O N C E P TS T H R O U GH S C EN ARIOS O R U S E C A S E S Partition system capabilities into classes of service within operational scenarios Connect capabilities to system requirements using sysML Define Measures of Effectiveness (MoE) for these capabilities in units meaningful to the customer Define in the master schedule the achievement of measure of Technical Performance D E F I N E C A PA B I L I TIES N E EDED T O I M PL EMENT T H E O PE RATION AL C O N C E PTS Define scenarios for each system capability Connect these scenarios to the Value Stream map Assess value flow through the map for each needed capability Identify capability mismatches and make corrections to improve overall value flow A S S E SS N E EDS , C O S T , A N D R I S K S I M U L TANEOUSLY Assign costs to each system element using a value process model Assure risk, probabilistic cost and benefit performance attributes are defined Use cost, schedule, and technical performance probabilistic models to forecast potential risks to project performance D E F I N E E X P L I C I T , B A L A N CED , A N D F E A S IBLE A L T E RN ATIVES Make tradeoffs that connect cost, schedule, and technical performance in a single “trade space” model Measures of Effectiveness and Measures of Performance are the raw materials for these tradeoffs 2. Establish Requirements Baseline – Define Measures Of Performance (MoP) for each requirement delivering a Capability P E R FORM F A C T F I N D I N G Produce an overall statement of the problem in the operational context Develop the overall operational and technical; objectives of the target system through Measures of Performance (MoP) for the requirements Define the boundaries and interfaces of the target system G A T H E R A N D C L A S S IFY THE R EQUI REMENTS Gather required operational capabilities, functional, nonfunctional, and environment requirements and design constraints Build a Top Down Capabilities and Functional decomposition of the requirements in a flow down tree using a requirements tool E V A L U A TE A ND R A T I ONALI ZE T H E R E Q UI REMENTS Answer the question “why do we need this?” in terms of operational benefits Build a cost / benefit model using probabilistic assessments of all variables and dependencies For technical requirements, perform a risk assessment to the cost and schedule P R I O RITIZE T H E R E Q U IREMEN TS Determine the criticality for the functions for the system’s mission Determine tradeoff relations for all requirements to be used when option decision are made For technical items, prioritize the cost and dependencies I N T E G R ATE A N D V A L I D ATE T H E R E Q U IREMEN TS Address completeness of requirements by removing all TBD items Validate the requirements agree and are traceable to capabilities, goals, and the mission Resolve any requirement inconsistencies and conflicts 24 Performance-Base Project Management (sm) Chapter I
  • 25. 3. Establish Performance Measurement Ba seline – Define Technical Performance Measures (TPM) D E C O M POSE R E Q U IREMENTS I N T O W ORK P A CKA GES A N D P L A N N IN G P A C K A G ES Decompose the project scope into a product based Work Breakdown Structure (WBS) Decompose the WBS into Work Packages describing the production of all outcomes and processes traceable to the requirements A S S I G N A C C O U NTA BILITY F O R T H E O U T C OME F R OM E A C H W O R K P A C K A G E Assign accountability for Work Packages to a named owner for the management of resource allocation, cost baseline, and technical delivery ARRANGE WORK PACKAGES IN A LOGICAL ORDER Arrange Work Packages in a network with defined outcomes, milestones, internal and external dependencies, appropriate schedule and cost margin D E V E L OP T H E B U D G ETED C O ST F O R W O R K S C H E D ULED (BCWS) F O R E A C H W O R K P A C K A G E A N D P L A N N ING P A C K A GE Develop a time‒phased Budgeted Cost for Work Scheduled (BCWS) for labor and material costs in each Work Package Develop a time‒phased Budgeted Cost for Work Scheduled (BCWS) for the project as a whole Assure proper resource allocations can be met and budget profiles match expectations of the project sponsor A S S I G N W O R K P A C K A G E M E A S U RES O F P E R F ORMA NCE (M O P), K E Y P E R FORMAN CE P A R A METERS (KPP), A N D T E C H N I CAL P E R F ORMA NCE M E A S U RES (TPM) Assign an objective Measure of Performance (MoP) for each critical Work Package outcomes Trace critical outcomes to the Measure of Effectiveness (MoE) defined in the Capabilities baseline Summarize these Measures of Performance (MoP) and Measures of Effectiveness (MoE) for the project as a whole Assign measures of Physical Percent Complete for each Work Package Assign measures of Physical Percent Complete for the program as a whole S E T T H E P ERFORMA NCE M E A S U REMENT B A S E LINE (PMB) Establish a Performance Measurement Baseline (PMB) used to forecast Work Package and Project ongoing and completion cost and schedule metrics 4. Execute the Performance Measurement Baseline (PMB) – Maintain Cost, Schedule, and Technical Performance PER FORM A U T H ORI ZED W O R K I N T H E P L A N N ED S E Q U ENCE Using the Work Package sequencing, release work to be performed as planned With the RACI based RAM, the Accountable delivery manager guides the development of the products or service for each Work Package A C C U M ULATE A N D R E P O RT W ORK P A CKA GE P H Y S I CAL P E R FORMAN CE Using Physical Percent complete or Apportioned Milestones, capture the measures of “progress to plan” for each Work Package Report the Physical Percent Complete in a centralized system for each Work Package and he program as a whole A N A L Y ZE W O R K P A C K A G E P E R FORMAN CE Compare the Actual Percent Complete against the Planned Percent Complete for each period of performance Construct cost and schedule performance indices from this information and the Physical Percent Complete measures T A K E C O R R E CTIV E M A N A G E MEN T A C T I ON FOR A N Y V A R I A NCE I N W O R K P A C K A GE P E R FORMAN CE With the cost and schedule performance indices, construct a forecast of future performance of cost, schedule, and technical performance compliance Take management actions for any Work Packages not performing as planned M A I N T A IN P ERFORMANCE M E ASU REMENT B A S E LINE ’ S I N T E G R ITY Record past performance based on Work Package completion criteria Record previous future performance estimates in a historical database Forecast future performance against the Performance Measurement Baseline Report the future performance estimate to the program stakeholders 25 Performance-Base Project Management (sm) Chapter I
  • 26. 5 Principles of Project Success What does done look like? How do we get there? Are there enough resources? What are progress impediments? How do we measure progress? Performance Based Management(sm), Copyright ® Glen B. Alleman, 2012
  • 27. 5 Practices Needed to Implement the 5 Principles Identify Capabilities in units of measure meaningful to the customer Identify Technical & Operational Requirements to deliver capabilities Establish risk adjusted Technical, Cost, and Schedule Baseline. Execute baseline with measurements of physical percent complete Apply Continuous Risk Management 27 Performance Based Management(sm), Copyright ® Glen B. Alleman, 2012
  • 28. 5 Processes Needed the Implement the 5 Practices Guided by the 5 Principles Organize the deliverables and staff doing the work Plan, Budget, and Schedule in the Performance Measurement baseline Account for direct and indirect costs against planned costs Analyze performance for cost, schedule, and technical variance Manage revisions to Performance Measurement Baseline 28 Performance Based Management(sm), Copyright ® Glen B. Alleman, 2012
  • 29. Glen B. Alleman, Copyright © 2012 29/29