SlideShare uma empresa Scribd logo
1 de 6
Increasing the Probability of Program Success
Program Success starts and end with Process. Along the way, people and tools are needed, but
process is the foundation of program success. These processes start with the Concept of
Operations, describing what Capabilities are needed by the stakeholder to accomplish the
mission of the program. Assessment of progress to plan must be made in units of measure
meaningful to the decision makers. Measures of Effectiveness are defined by the Government.
Measures of Performance and Technical Performance Measures are defined by Industry.
For each step in the processes above, objective evidence in Figure 1 is needed, connected in a
hierarchy of increasing visibility to the description of Done.
❶ Pre-Award Work
 Define desired capabilities
 Assess readiness of technologies.
 Define war fighter’s use System
 Define Measures of Effectiveness
 Create Integrated Master Plan
 Identify uncertainties
 Develop risk-adjusted estimates
❷ Issue Request for Proposal
 Include Government products
 Specify award criteria
 Update IMP and Uncertainties
 Define key framing assumptions
 Submit updated cost and
schedule estimate to 70% JCL
 Submit deterministic IMS
❸ Award Based on Criteria
 Establish these criteria in the
Integrated baseline Review
 Measures performance and
award fee against these criteria
 Use criteria to produce ETC, EAC,
ECD
❹ Awardee create Credible PMB
 Integrated Master Plan
 Technical Plan
 WBS and Dictionary
 Program Management Plan
❺ Install Credible PMB
 Define Measures of
Effectiveness, Measures of
Performance, technical
Performance Measures, or Key
Performance Parameters for
each deliverable
❻ Monitor Progress to Plan
 Ensure technical progress made
accordingto Plan
 Review cost and schedule
progress againstplan
 Update risk register
 Identify which activities requires
closer monitoringin future
Figure 1 ‒ Each processinthe table above requires data to create a credible program performance
management system describedabove in eachstage of the program’s maturity.
In my career, I've worked for a lot of really good managers, and of course, Gene Kranz was one of
the best. One of the things I really admired about Gene ... is that of things didn't work out quite
right in a project or in a ting that you were doing, Gene would often say, "Well, maybe I didn't
explain as clearly as I should have what it was I needed you to do."
‒ Mission Control Center ISS Project Johnson Space Center
Without a clear and concise description of Done in units of measure meaningful to the decision
makers (Effectiveness and Performance), it's hard to know how to reach Done, how much it will
cost to reach Done, and when we will be arriving at Done. This is the purpose of the processes
described in this document - to provide the map with the route, cost, and measures of progress
along the way to Done, while assuring when we arrive at Done, the deliverables implement the
needed Capabilities of the system.
These capabilities provide solutions for each process step. With the Roadmap in Figure 2, a
credible Performance Measurement Baseline developed to inform the decision makers about
progress to plan and corrective action opportunities.
To increase the Probability of Program success, three phases of increasing procurement maturity
must be in place.
Figure 2 – Three Phases neededto construct a credible Performance Measurement Baseline fromthe Concept of Operations.
Concept of Operations (ConOps)
A Concept of Operations (CONOPS) is a document describing the characteristics and intended
usage of a proposed or existing system from the viewpoint of its users. Its purpose is to
communicate the quantitative and qualitative system characteristics to all stakeholders and
serve as a basis for stakeholder discussions about the system. Moreover, the CONOPS can help
reach a “meeting of the minds” before the requirements process begins. Generated effectively,
it may convey a clearer statement of intent than the requirements themselves. 1
Our approach to developing the Concept of Operation starts with a verbal or graphicalstatement
that clearly and concisely expresses what the program intends to accomplish and how it will be
done based on DoDAF V2.02 framework. The Concept of Operation includes:
 Current System or Situation
- Background, mission, objectives, scope, operational policies and constraints
- Operational environment and its characteristics with major system components and
interconnections, Interfaces to external systems and processes
- Capabilities or Functions of the current system
- Performance characteristics needed to fulfill the planned system with their quality attributes
needed to fulfill the planned system
 Concept for new or modified system
- Background, objectives, and scope of new system with Operational policies and constraints
of the new system.
- Technical policies and constraints that impact the new system and operational environment
and its characteristics for the major system components and interconnections
- Capabilities or function for the new or modified system including activities and relationships
WBS/CWBS/WBS Dictionary
The Work Breakdown Structure (WBS) defines the products and the services that produce those
products in a Mutually Exclusive and Exhaustively Complete structured decomposition.
Constructing the WBS starts with the Concept of Operations for the deliverables that implement
that ConOps.The work breakdown structure’s define and organizing the project’s work. A project
budget is allocated to the elements of the work breakdown structure. When the Organizational
Breakdown Structure (OBS) is defined, the staffing budgets are defined based on the each
project's work breakdown structure.
Allocating time and cost estimates to work breakdown elements, the project schedule and
budget can be developed. As the project executes, specific sections of the WBS can be tracked to
identify project cost performance and identify issues and problem areas in the project
organization. The WBS identifies potential technical and programmatic risks. These risks are
tracked and reviewed as the project executes. By integrating the WBS with an OBS, the project
manager identifies communication points and formulate the communication plan across the
project organization.
1 “Developing a Stakeholder-AssistedAgile CONOPS Development Process,” Ali Mostashari, Sara McComb, Deanna Kennedy,
Robert, Cloutier, andPeter Korfiatis, Systems Engineering, Volume 15, Issue 1, 2012, pp. 1-13.
Operational and Technical Requirements
Operational requirements are statements that identify the essential capabilities, associated
requirements, performance measures, and the process or series of actions to be taken in
effecting the results that are desired in order to address mission area deficiencies, evolving
applications or threats, emerging technologies, or system cost improvements. 2
The operational requirements assessment starts with the Concept of Operations (CONOPS) and
goes to a greater level of detail in identifying mission performance assumptions and constraints
and current deficiencies of or enhancements needed for operations and mission success.
Operational requirements are the basis for system requirements.
Elicitation of these requirements starts with users' needs based on an operational needs
assessment. Analysis of the needs identifies capability gaps and defines the operational and top-
level characteristics and requirements of the system. Using CONOPS the operational needs,
desires, visions, expectations, performance requirements, and challenges of the system are
captured from the users, developers, and integrators, to define the system operational
requirements, ensuring each requirement maps to an operational need in CONOPS.
Integrated Master Plan
Successful Program Management developing and maintaining plans and schedules for all
program processes needed effective Government ‒ Industry interaction. With the contract in
place, schedule, cost, and resources from the contractor established, the program plan accounts
‒ at an appropriate level of detail ‒ the contractor's strategy for the successful delivery of the
programs outcome.
The IMP, with its hierarchy of Significant Accomplishments (SA) and Accomplishment Criteria
(AC), documents that the program is properly structured and executable within schedule and
cost constraints with an acceptable level of risk. During the proposal evaluation and source
selection phases, the IMP and IMS are critical components of the offeror's proposal; identifying
the offeror's ability to decompose a program into tasks and phases to be successfully executed
to deliver the needed capabilities.
After contract award, the IMP and IMS are used by the contractor and the government as the
day-to-day tool for executing the program and tracking program technical and schedule status,
including significant risk mitigation efforts. The IMP is a Systems Engineering activity. describing
the programmatic architecture in the same way the hardware and software are described in the
technical architecture.
A poor, weak, or unstructured Programmatic Architecture reduces the visibility to the Product
Architecture’s cost and schedule performance measures and their connections with the Technical
Performance Measures.
2 Kossiakoff, A., andN. Sweet, 2003, Systems Engineering Principles and Practices, Hoboken, N.J., JohnWiley& Sons.
Integrated Master Schedule
Starting with the Work Breakdown Structure (WBS), the Integrated Master Schedule summarizes
the work and the order of the performance of the work for the Accomplishment Criteria (AC) in
the IMP. 3
A well-constructed IMS contains distinct tasks summarized by WBS identifiers so the program can
track progress and measure schedule performance. Risk mitigation and handling activities are
included in the program IMP and IMS and resourced in the IMS. The IMP and IMS should be
traceable to the program and contractor WBS and Statement of Work.
Starting with the IMP’s top-down planning, the IMS bottom-up execution tool assures visibility
to several critical success factors for the program.
 Measurable Criteria ‒ established by IMP Significant Accomplishments including
accomplishment of critical performance requirements (Key Performance Parameters and
Technical Performance Measures).
 Stakeholder Involvement ‒ including user organizations, financial managers, and sustainment
organizations are involved in the work planning process from alllife-cyclephases to ensure that
technical and support activities are adequately addressed in program plans in the IMP and IMS.
 Communication of Progress to Plan ‒ through the IMS with stakeholders on a regular basis.
For enterprise systems with largenumbers of external interfaces and programs, the IMS is used
as the integration tool to indicate and track milestones relevant to the other programs.
Technical Performance Measures
Technical Performance Measurement (TPM) are used to predict the future value of a key
technical performance parameter of an end product under development based on current
assessments of products lower in the system structure. TPMs define the planned progress of a
selected technical parameter defined as the expected performance at specific points in the
program as shown in the WBS, IMS, IMP.
These connections start with Systems Engineering – where Measures of Effectiveness (MOE),
Measures of Performance (MOP), Technical Performance Measures (TPM), and Risks are
identified.
TPMs are derived from MOPs and characterize the physical or functional attributes relating to
the execution of the mission or function. TPMs may also be derived from Measures of
Effectiveness (MOE) to become system cost and effectiveness metrics.
The TPMs Performance parameters significantly qualify the entire system, with the parameters
derived from analyses, demonstrations, or tests. The measure of value is the result of analyses
or tests and is used to predict future values. Each parameter is periodically measured and
profiled to compare with predicted values and tolerances over the project life cycle.
3 Air Force Pamphlet 63-128, “Integrated LifecycleManagement,” 10 July 2014
Technical and Programmatic Risk Management
Risks are future uncertainties relating to achieving program technical and programmatic
performance goals. 4 Uncertainty comes in two forms – reducible uncertainty (epistemic) and
irreducible uncertainty (aleatory). These uncertainties create risk. Epistemic uncertainty can be
handled with specific work, redundancy, testing, alternative plans. Aleatory uncertainty can only
be handled with margin ‒ cost, schedule, and technical margin. Both handling methods must be
defined in the Integrated Master Schedule ‒ risk buy down tasks and margin.
Starting with a risk adjusted Performance Measurement Baseline (PMB), the information is
needed to inform program performance using both reducible and irreducible risk. Statusing the
reducible risks at the planned reduction date is similar to a Technical Performance Measure,
where the target measure is improved as the program proceeds. Irreducible risks require
schedule margin to protect contract events or end item deliverables.
The connections between the program’s Technical Plan (delivery of technical outcomes
compliance with needed MOE, MOP, and TPM) and the Programmatic Plan (Cost and Schedule)
is the role of the Risk Management Plan. These risk management activities include standard risk
processes with their risk reduction efforts as well as application of Management Reserve and
Schedule Margin to assure acceptable program performance is met.
Management of the Performance Measurement Baseline
Performance measurement is the ongoing monitoring and reporting of program
accomplishments, particularly progress toward pre-established goals. Performance measures
may address the type or level of program activities conducted (process), the direct products and
services delivered by a program (outputs), or the results of those products and services
(outcomes).
The Performance Measurement Baseline (PMB) is a time–phased schedule of all the work to be
performed, the budgeted cost for this work, and the organizational elements that produce the
deliverables from this work. The PMB provides an integrated view of three project constraints:
scope, time, and cost, and establishes a means to measure project’s performance in units of
measure meaningful to the decision makers.
There are three PMB’s:
1. The scope baseline from the WBS, projects specifications, design elements and
deliverables
2. The time baseline in the approved project schedule, showing the planned start and finish
of the work needed to produce the scope
3. The cost baseline for the budget and spend plan used to monitor cost performance
Managing the PMB is part of Program Performance management ‒ a process for making course
corrections to achieve an organization's goals by using performance information to adjust
resources and activities. Focusing on Program Performance Management (PPM) is to focus on
the future.
Program Performance Management techniques track the progress and status of the project and
forecast the likely future performance of the project. Information from the PMB’s performance
provides corrective actions needed to Keep the Program Green.
4 “DOD Risk Management Guide,” V7, December 2014

Mais conteúdo relacionado

Mais procurados

From WBS to Integrated Master Schedule
From WBS to Integrated Master ScheduleFrom WBS to Integrated Master Schedule
From WBS to Integrated Master ScheduleGlen Alleman
 
Earned Value Management Meets Big Data
Earned Value Management Meets Big DataEarned Value Management Meets Big Data
Earned Value Management Meets Big DataGlen Alleman
 
Process Flow and Narrative for Agile+PPM
Process Flow and Narrative for Agile+PPMProcess Flow and Narrative for Agile+PPM
Process Flow and Narrative for Agile+PPMGlen Alleman
 
What Does Done Look Like?
What Does Done Look Like?What Does Done Look Like?
What Does Done Look Like?Glen Alleman
 
A Guide for Capital Project Mamnagers
A Guide for Capital Project MamnagersA Guide for Capital Project Mamnagers
A Guide for Capital Project MamnagersGlen Alleman
 
Agile Project Management Procedures
Agile Project Management ProceduresAgile Project Management Procedures
Agile Project Management ProceduresGlen Alleman
 
Establishing the Performance Measurement Baseline
Establishing the Performance Measurement BaselineEstablishing the Performance Measurement Baseline
Establishing the Performance Measurement BaselineGlen Alleman
 
Risk Management Guidance
Risk Management GuidanceRisk Management Guidance
Risk Management GuidanceGlen Alleman
 
Earning value from risk (v4 full charts)
Earning value from risk (v4 full charts)Earning value from risk (v4 full charts)
Earning value from risk (v4 full charts)Glen Alleman
 
Managing Risk as Opportunity
Managing Risk as OpportunityManaging Risk as Opportunity
Managing Risk as OpportunityGlen Alleman
 
Cure for cost and schedule growth
Cure for cost and schedule growthCure for cost and schedule growth
Cure for cost and schedule growthGlen Alleman
 
Process Flow and Narrative for Agile
Process Flow and Narrative for AgileProcess Flow and Narrative for Agile
Process Flow and Narrative for AgileGlen Alleman
 
Notes on IT programmatic risk in 5 not so easy pieces
Notes on IT programmatic risk in 5 not so easy piecesNotes on IT programmatic risk in 5 not so easy pieces
Notes on IT programmatic risk in 5 not so easy piecesGlen Alleman
 
Continuous Risk Management
Continuous Risk ManagementContinuous Risk Management
Continuous Risk ManagementGlen Alleman
 
Increasing the Probability of Project Success with Five Principles and Practices
Increasing the Probability of Project Success with Five Principles and PracticesIncreasing the Probability of Project Success with Five Principles and Practices
Increasing the Probability of Project Success with Five Principles and PracticesGlen Alleman
 
What Makes a Good Concept of Operations?
What Makes a Good Concept of Operations?What Makes a Good Concept of Operations?
What Makes a Good Concept of Operations?Glen Alleman
 
SOLVING PROJECT ALLOCATION RESOURCE PROBLEMS WITH AEROSPACE ERP
SOLVING PROJECT ALLOCATION RESOURCE PROBLEMS WITH AEROSPACE ERPSOLVING PROJECT ALLOCATION RESOURCE PROBLEMS WITH AEROSPACE ERP
SOLVING PROJECT ALLOCATION RESOURCE PROBLEMS WITH AEROSPACE ERPKevin West
 
Probabilistic Schedule and Cost Analysis
Probabilistic Schedule and Cost AnalysisProbabilistic Schedule and Cost Analysis
Probabilistic Schedule and Cost AnalysisGlen Alleman
 
Cure for Cost and Schedule Growth
Cure for Cost and Schedule GrowthCure for Cost and Schedule Growth
Cure for Cost and Schedule GrowthGlen Alleman
 
IMP / IMS Step by Step
IMP / IMS Step by StepIMP / IMS Step by Step
IMP / IMS Step by StepGlen Alleman
 

Mais procurados (20)

From WBS to Integrated Master Schedule
From WBS to Integrated Master ScheduleFrom WBS to Integrated Master Schedule
From WBS to Integrated Master Schedule
 
Earned Value Management Meets Big Data
Earned Value Management Meets Big DataEarned Value Management Meets Big Data
Earned Value Management Meets Big Data
 
Process Flow and Narrative for Agile+PPM
Process Flow and Narrative for Agile+PPMProcess Flow and Narrative for Agile+PPM
Process Flow and Narrative for Agile+PPM
 
What Does Done Look Like?
What Does Done Look Like?What Does Done Look Like?
What Does Done Look Like?
 
A Guide for Capital Project Mamnagers
A Guide for Capital Project MamnagersA Guide for Capital Project Mamnagers
A Guide for Capital Project Mamnagers
 
Agile Project Management Procedures
Agile Project Management ProceduresAgile Project Management Procedures
Agile Project Management Procedures
 
Establishing the Performance Measurement Baseline
Establishing the Performance Measurement BaselineEstablishing the Performance Measurement Baseline
Establishing the Performance Measurement Baseline
 
Risk Management Guidance
Risk Management GuidanceRisk Management Guidance
Risk Management Guidance
 
Earning value from risk (v4 full charts)
Earning value from risk (v4 full charts)Earning value from risk (v4 full charts)
Earning value from risk (v4 full charts)
 
Managing Risk as Opportunity
Managing Risk as OpportunityManaging Risk as Opportunity
Managing Risk as Opportunity
 
Cure for cost and schedule growth
Cure for cost and schedule growthCure for cost and schedule growth
Cure for cost and schedule growth
 
Process Flow and Narrative for Agile
Process Flow and Narrative for AgileProcess Flow and Narrative for Agile
Process Flow and Narrative for Agile
 
Notes on IT programmatic risk in 5 not so easy pieces
Notes on IT programmatic risk in 5 not so easy piecesNotes on IT programmatic risk in 5 not so easy pieces
Notes on IT programmatic risk in 5 not so easy pieces
 
Continuous Risk Management
Continuous Risk ManagementContinuous Risk Management
Continuous Risk Management
 
Increasing the Probability of Project Success with Five Principles and Practices
Increasing the Probability of Project Success with Five Principles and PracticesIncreasing the Probability of Project Success with Five Principles and Practices
Increasing the Probability of Project Success with Five Principles and Practices
 
What Makes a Good Concept of Operations?
What Makes a Good Concept of Operations?What Makes a Good Concept of Operations?
What Makes a Good Concept of Operations?
 
SOLVING PROJECT ALLOCATION RESOURCE PROBLEMS WITH AEROSPACE ERP
SOLVING PROJECT ALLOCATION RESOURCE PROBLEMS WITH AEROSPACE ERPSOLVING PROJECT ALLOCATION RESOURCE PROBLEMS WITH AEROSPACE ERP
SOLVING PROJECT ALLOCATION RESOURCE PROBLEMS WITH AEROSPACE ERP
 
Probabilistic Schedule and Cost Analysis
Probabilistic Schedule and Cost AnalysisProbabilistic Schedule and Cost Analysis
Probabilistic Schedule and Cost Analysis
 
Cure for Cost and Schedule Growth
Cure for Cost and Schedule GrowthCure for Cost and Schedule Growth
Cure for Cost and Schedule Growth
 
IMP / IMS Step by Step
IMP / IMS Step by StepIMP / IMS Step by Step
IMP / IMS Step by Step
 

Semelhante a Increasing the probability of program success

Project management
Project managementProject management
Project managementAhmed Said
 
Building a Credible Performance Measurement Baseline
Building a Credible Performance Measurement BaselineBuilding a Credible Performance Measurement Baseline
Building a Credible Performance Measurement BaselineGlen Alleman
 
SE18_Lec 13_ Project Planning
SE18_Lec 13_ Project PlanningSE18_Lec 13_ Project Planning
SE18_Lec 13_ Project PlanningAmr E. Mohamed
 
How Should We Estimate Agile Software Development Projects and What Data Do W...
How Should We Estimate Agile Software Development Projects and What Data Do W...How Should We Estimate Agile Software Development Projects and What Data Do W...
How Should We Estimate Agile Software Development Projects and What Data Do W...Glen Alleman
 
Running head critical path method1 critical path method7critic
Running head critical path method1 critical path method7criticRunning head critical path method1 critical path method7critic
Running head critical path method1 critical path method7criticDIPESH30
 
SE_Lec 12_ Project Planning
SE_Lec 12_ Project PlanningSE_Lec 12_ Project Planning
SE_Lec 12_ Project PlanningAmr E. Mohamed
 
How should we estimates agile projects (CAST)
How should we estimates agile projects (CAST)How should we estimates agile projects (CAST)
How should we estimates agile projects (CAST)Glen Alleman
 
PM Session 4
PM Session 4PM Session 4
PM Session 4dmdk12
 
Chapter 02 project planning
Chapter 02 project planningChapter 02 project planning
Chapter 02 project planningCharith Sathish
 
Improving DOE Project Performance Using the DOD Integrated Master Plan
Improving DOE Project Performance Using the DOD Integrated Master PlanImproving DOE Project Performance Using the DOD Integrated Master Plan
Improving DOE Project Performance Using the DOD Integrated Master PlanGlen Alleman
 
Scope management term paper
Scope management term paperScope management term paper
Scope management term paperMuhammad Umar
 
Day 1 - 3PM Revision
Day 1 - 3PM RevisionDay 1 - 3PM Revision
Day 1 - 3PM RevisionJeffrey Cheah
 
Earned Value + Agile = Success
Earned Value + Agile = SuccessEarned Value + Agile = Success
Earned Value + Agile = SuccessGlen Alleman
 
Ch23-Software Engineering 9
Ch23-Software Engineering 9Ch23-Software Engineering 9
Ch23-Software Engineering 9Ian Sommerville
 
Building a Credible Performance Measurement Baseline in Two Days
Building a Credible Performance Measurement Baseline in Two DaysBuilding a Credible Performance Measurement Baseline in Two Days
Building a Credible Performance Measurement Baseline in Two DaysGlen Alleman
 

Semelhante a Increasing the probability of program success (20)

Getting it Right
Getting it Right Getting it Right
Getting it Right
 
Project management
Project managementProject management
Project management
 
Building a Credible Performance Measurement Baseline
Building a Credible Performance Measurement BaselineBuilding a Credible Performance Measurement Baseline
Building a Credible Performance Measurement Baseline
 
SE18_Lec 13_ Project Planning
SE18_Lec 13_ Project PlanningSE18_Lec 13_ Project Planning
SE18_Lec 13_ Project Planning
 
How Should We Estimate Agile Software Development Projects and What Data Do W...
How Should We Estimate Agile Software Development Projects and What Data Do W...How Should We Estimate Agile Software Development Projects and What Data Do W...
How Should We Estimate Agile Software Development Projects and What Data Do W...
 
notes_Lecture7.ppt
notes_Lecture7.pptnotes_Lecture7.ppt
notes_Lecture7.ppt
 
Running head critical path method1 critical path method7critic
Running head critical path method1 critical path method7criticRunning head critical path method1 critical path method7critic
Running head critical path method1 critical path method7critic
 
SE-Lecture-5.pptx
SE-Lecture-5.pptxSE-Lecture-5.pptx
SE-Lecture-5.pptx
 
SE_Lec 12_ Project Planning
SE_Lec 12_ Project PlanningSE_Lec 12_ Project Planning
SE_Lec 12_ Project Planning
 
How should we estimates agile projects (CAST)
How should we estimates agile projects (CAST)How should we estimates agile projects (CAST)
How should we estimates agile projects (CAST)
 
PM Session 4
PM Session 4PM Session 4
PM Session 4
 
Chapter 02 project planning
Chapter 02 project planningChapter 02 project planning
Chapter 02 project planning
 
Software
SoftwareSoftware
Software
 
Improving DOE Project Performance Using the DOD Integrated Master Plan
Improving DOE Project Performance Using the DOD Integrated Master PlanImproving DOE Project Performance Using the DOD Integrated Master Plan
Improving DOE Project Performance Using the DOD Integrated Master Plan
 
Scope management term paper
Scope management term paperScope management term paper
Scope management term paper
 
Day 1 - 3PM Revision
Day 1 - 3PM RevisionDay 1 - 3PM Revision
Day 1 - 3PM Revision
 
Earned Value + Agile = Success
Earned Value + Agile = SuccessEarned Value + Agile = Success
Earned Value + Agile = Success
 
Ch23
Ch23Ch23
Ch23
 
Ch23-Software Engineering 9
Ch23-Software Engineering 9Ch23-Software Engineering 9
Ch23-Software Engineering 9
 
Building a Credible Performance Measurement Baseline in Two Days
Building a Credible Performance Measurement Baseline in Two DaysBuilding a Credible Performance Measurement Baseline in Two Days
Building a Credible Performance Measurement Baseline in Two Days
 

Mais de Glen Alleman

Managing risk with deliverables planning
Managing risk with deliverables planningManaging risk with deliverables planning
Managing risk with deliverables planningGlen Alleman
 
A Gentle Introduction to the IMP/IMS
A Gentle Introduction to the IMP/IMSA Gentle Introduction to the IMP/IMS
A Gentle Introduction to the IMP/IMSGlen Alleman
 
Increasing the Probability of Project Success
Increasing the Probability of Project SuccessIncreasing the Probability of Project Success
Increasing the Probability of Project SuccessGlen Alleman
 
Practices of risk management
Practices of risk managementPractices of risk management
Practices of risk managementGlen Alleman
 
Principles of Risk Management
Principles of Risk ManagementPrinciples of Risk Management
Principles of Risk ManagementGlen Alleman
 
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...Glen Alleman
 
From Principles to Strategies for Systems Engineering
From Principles to Strategies for Systems EngineeringFrom Principles to Strategies for Systems Engineering
From Principles to Strategies for Systems EngineeringGlen Alleman
 
NAVAIR Integrated Master Schedule Guide guide
NAVAIR Integrated Master Schedule Guide guideNAVAIR Integrated Master Schedule Guide guide
NAVAIR Integrated Master Schedule Guide guideGlen Alleman
 
Integrated master plan methodology (v2)
Integrated master plan methodology (v2)Integrated master plan methodology (v2)
Integrated master plan methodology (v2)Glen Alleman
 
DHS - Using functions points to estimate agile development programs (v2)
DHS - Using functions points to estimate agile development programs (v2)DHS - Using functions points to estimate agile development programs (v2)
DHS - Using functions points to estimate agile development programs (v2)Glen Alleman
 
Making the impossible possible
Making the impossible possibleMaking the impossible possible
Making the impossible possibleGlen Alleman
 
Heliotropic Abundance
Heliotropic AbundanceHeliotropic Abundance
Heliotropic AbundanceGlen Alleman
 
Building the Performance Measurement Baseline
Building the Performance Measurement BaselineBuilding the Performance Measurement Baseline
Building the Performance Measurement BaselineGlen Alleman
 
Program Management Office Lean Software Development and Six Sigma
Program Management Office Lean Software Development and Six SigmaProgram Management Office Lean Software Development and Six Sigma
Program Management Office Lean Software Development and Six SigmaGlen Alleman
 
Policy and Procedure Rollout
Policy and Procedure RolloutPolicy and Procedure Rollout
Policy and Procedure RolloutGlen Alleman
 
Integrated Master Plan Development
Integrated Master Plan DevelopmentIntegrated Master Plan Development
Integrated Master Plan DevelopmentGlen Alleman
 
Project Management Theory
Project Management TheoryProject Management Theory
Project Management TheoryGlen Alleman
 
Seven Habits of a Highly Effective agile project manager
Seven Habits of a Highly Effective agile project managerSeven Habits of a Highly Effective agile project manager
Seven Habits of a Highly Effective agile project managerGlen Alleman
 
Paradigm of agile project management (update)
Paradigm of agile project management (update)Paradigm of agile project management (update)
Paradigm of agile project management (update)Glen Alleman
 
The 5 Immutable principles of project management
The 5 Immutable principles of project managementThe 5 Immutable principles of project management
The 5 Immutable principles of project managementGlen Alleman
 

Mais de Glen Alleman (20)

Managing risk with deliverables planning
Managing risk with deliverables planningManaging risk with deliverables planning
Managing risk with deliverables planning
 
A Gentle Introduction to the IMP/IMS
A Gentle Introduction to the IMP/IMSA Gentle Introduction to the IMP/IMS
A Gentle Introduction to the IMP/IMS
 
Increasing the Probability of Project Success
Increasing the Probability of Project SuccessIncreasing the Probability of Project Success
Increasing the Probability of Project Success
 
Practices of risk management
Practices of risk managementPractices of risk management
Practices of risk management
 
Principles of Risk Management
Principles of Risk ManagementPrinciples of Risk Management
Principles of Risk Management
 
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
 
From Principles to Strategies for Systems Engineering
From Principles to Strategies for Systems EngineeringFrom Principles to Strategies for Systems Engineering
From Principles to Strategies for Systems Engineering
 
NAVAIR Integrated Master Schedule Guide guide
NAVAIR Integrated Master Schedule Guide guideNAVAIR Integrated Master Schedule Guide guide
NAVAIR Integrated Master Schedule Guide guide
 
Integrated master plan methodology (v2)
Integrated master plan methodology (v2)Integrated master plan methodology (v2)
Integrated master plan methodology (v2)
 
DHS - Using functions points to estimate agile development programs (v2)
DHS - Using functions points to estimate agile development programs (v2)DHS - Using functions points to estimate agile development programs (v2)
DHS - Using functions points to estimate agile development programs (v2)
 
Making the impossible possible
Making the impossible possibleMaking the impossible possible
Making the impossible possible
 
Heliotropic Abundance
Heliotropic AbundanceHeliotropic Abundance
Heliotropic Abundance
 
Building the Performance Measurement Baseline
Building the Performance Measurement BaselineBuilding the Performance Measurement Baseline
Building the Performance Measurement Baseline
 
Program Management Office Lean Software Development and Six Sigma
Program Management Office Lean Software Development and Six SigmaProgram Management Office Lean Software Development and Six Sigma
Program Management Office Lean Software Development and Six Sigma
 
Policy and Procedure Rollout
Policy and Procedure RolloutPolicy and Procedure Rollout
Policy and Procedure Rollout
 
Integrated Master Plan Development
Integrated Master Plan DevelopmentIntegrated Master Plan Development
Integrated Master Plan Development
 
Project Management Theory
Project Management TheoryProject Management Theory
Project Management Theory
 
Seven Habits of a Highly Effective agile project manager
Seven Habits of a Highly Effective agile project managerSeven Habits of a Highly Effective agile project manager
Seven Habits of a Highly Effective agile project manager
 
Paradigm of agile project management (update)
Paradigm of agile project management (update)Paradigm of agile project management (update)
Paradigm of agile project management (update)
 
The 5 Immutable principles of project management
The 5 Immutable principles of project managementThe 5 Immutable principles of project management
The 5 Immutable principles of project management
 

Último

Rise of the Machines: Known As Drones...
Rise of the Machines: Known As Drones...Rise of the Machines: Known As Drones...
Rise of the Machines: Known As Drones...Rick Flair
 
"Debugging python applications inside k8s environment", Andrii Soldatenko
"Debugging python applications inside k8s environment", Andrii Soldatenko"Debugging python applications inside k8s environment", Andrii Soldatenko
"Debugging python applications inside k8s environment", Andrii SoldatenkoFwdays
 
How AI, OpenAI, and ChatGPT impact business and software.
How AI, OpenAI, and ChatGPT impact business and software.How AI, OpenAI, and ChatGPT impact business and software.
How AI, OpenAI, and ChatGPT impact business and software.Curtis Poe
 
Use of FIDO in the Payments and Identity Landscape: FIDO Paris Seminar.pptx
Use of FIDO in the Payments and Identity Landscape: FIDO Paris Seminar.pptxUse of FIDO in the Payments and Identity Landscape: FIDO Paris Seminar.pptx
Use of FIDO in the Payments and Identity Landscape: FIDO Paris Seminar.pptxLoriGlavin3
 
DSPy a system for AI to Write Prompts and Do Fine Tuning
DSPy a system for AI to Write Prompts and Do Fine TuningDSPy a system for AI to Write Prompts and Do Fine Tuning
DSPy a system for AI to Write Prompts and Do Fine TuningLars Bell
 
Dev Dives: Streamline document processing with UiPath Studio Web
Dev Dives: Streamline document processing with UiPath Studio WebDev Dives: Streamline document processing with UiPath Studio Web
Dev Dives: Streamline document processing with UiPath Studio WebUiPathCommunity
 
WordPress Websites for Engineers: Elevate Your Brand
WordPress Websites for Engineers: Elevate Your BrandWordPress Websites for Engineers: Elevate Your Brand
WordPress Websites for Engineers: Elevate Your Brandgvaughan
 
"ML in Production",Oleksandr Bagan
"ML in Production",Oleksandr Bagan"ML in Production",Oleksandr Bagan
"ML in Production",Oleksandr BaganFwdays
 
unit 4 immunoblotting technique complete.pptx
unit 4 immunoblotting technique complete.pptxunit 4 immunoblotting technique complete.pptx
unit 4 immunoblotting technique complete.pptxBkGupta21
 
New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024BookNet Canada
 
How to write a Business Continuity Plan
How to write a Business Continuity PlanHow to write a Business Continuity Plan
How to write a Business Continuity PlanDatabarracks
 
Advanced Computer Architecture – An Introduction
Advanced Computer Architecture – An IntroductionAdvanced Computer Architecture – An Introduction
Advanced Computer Architecture – An IntroductionDilum Bandara
 
DevoxxFR 2024 Reproducible Builds with Apache Maven
DevoxxFR 2024 Reproducible Builds with Apache MavenDevoxxFR 2024 Reproducible Builds with Apache Maven
DevoxxFR 2024 Reproducible Builds with Apache MavenHervé Boutemy
 
Tampa BSides - Chef's Tour of Microsoft Security Adoption Framework (SAF)
Tampa BSides - Chef's Tour of Microsoft Security Adoption Framework (SAF)Tampa BSides - Chef's Tour of Microsoft Security Adoption Framework (SAF)
Tampa BSides - Chef's Tour of Microsoft Security Adoption Framework (SAF)Mark Simos
 
New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024
New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024
New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024BookNet Canada
 
DevEX - reference for building teams, processes, and platforms
DevEX - reference for building teams, processes, and platformsDevEX - reference for building teams, processes, and platforms
DevEX - reference for building teams, processes, and platformsSergiu Bodiu
 
From Family Reminiscence to Scholarly Archive .
From Family Reminiscence to Scholarly Archive .From Family Reminiscence to Scholarly Archive .
From Family Reminiscence to Scholarly Archive .Alan Dix
 
Anypoint Exchange: It’s Not Just a Repo!
Anypoint Exchange: It’s Not Just a Repo!Anypoint Exchange: It’s Not Just a Repo!
Anypoint Exchange: It’s Not Just a Repo!Manik S Magar
 
Ensuring Technical Readiness For Copilot in Microsoft 365
Ensuring Technical Readiness For Copilot in Microsoft 365Ensuring Technical Readiness For Copilot in Microsoft 365
Ensuring Technical Readiness For Copilot in Microsoft 3652toLead Limited
 
Unraveling Multimodality with Large Language Models.pdf
Unraveling Multimodality with Large Language Models.pdfUnraveling Multimodality with Large Language Models.pdf
Unraveling Multimodality with Large Language Models.pdfAlex Barbosa Coqueiro
 

Último (20)

Rise of the Machines: Known As Drones...
Rise of the Machines: Known As Drones...Rise of the Machines: Known As Drones...
Rise of the Machines: Known As Drones...
 
"Debugging python applications inside k8s environment", Andrii Soldatenko
"Debugging python applications inside k8s environment", Andrii Soldatenko"Debugging python applications inside k8s environment", Andrii Soldatenko
"Debugging python applications inside k8s environment", Andrii Soldatenko
 
How AI, OpenAI, and ChatGPT impact business and software.
How AI, OpenAI, and ChatGPT impact business and software.How AI, OpenAI, and ChatGPT impact business and software.
How AI, OpenAI, and ChatGPT impact business and software.
 
Use of FIDO in the Payments and Identity Landscape: FIDO Paris Seminar.pptx
Use of FIDO in the Payments and Identity Landscape: FIDO Paris Seminar.pptxUse of FIDO in the Payments and Identity Landscape: FIDO Paris Seminar.pptx
Use of FIDO in the Payments and Identity Landscape: FIDO Paris Seminar.pptx
 
DSPy a system for AI to Write Prompts and Do Fine Tuning
DSPy a system for AI to Write Prompts and Do Fine TuningDSPy a system for AI to Write Prompts and Do Fine Tuning
DSPy a system for AI to Write Prompts and Do Fine Tuning
 
Dev Dives: Streamline document processing with UiPath Studio Web
Dev Dives: Streamline document processing with UiPath Studio WebDev Dives: Streamline document processing with UiPath Studio Web
Dev Dives: Streamline document processing with UiPath Studio Web
 
WordPress Websites for Engineers: Elevate Your Brand
WordPress Websites for Engineers: Elevate Your BrandWordPress Websites for Engineers: Elevate Your Brand
WordPress Websites for Engineers: Elevate Your Brand
 
"ML in Production",Oleksandr Bagan
"ML in Production",Oleksandr Bagan"ML in Production",Oleksandr Bagan
"ML in Production",Oleksandr Bagan
 
unit 4 immunoblotting technique complete.pptx
unit 4 immunoblotting technique complete.pptxunit 4 immunoblotting technique complete.pptx
unit 4 immunoblotting technique complete.pptx
 
New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
 
How to write a Business Continuity Plan
How to write a Business Continuity PlanHow to write a Business Continuity Plan
How to write a Business Continuity Plan
 
Advanced Computer Architecture – An Introduction
Advanced Computer Architecture – An IntroductionAdvanced Computer Architecture – An Introduction
Advanced Computer Architecture – An Introduction
 
DevoxxFR 2024 Reproducible Builds with Apache Maven
DevoxxFR 2024 Reproducible Builds with Apache MavenDevoxxFR 2024 Reproducible Builds with Apache Maven
DevoxxFR 2024 Reproducible Builds with Apache Maven
 
Tampa BSides - Chef's Tour of Microsoft Security Adoption Framework (SAF)
Tampa BSides - Chef's Tour of Microsoft Security Adoption Framework (SAF)Tampa BSides - Chef's Tour of Microsoft Security Adoption Framework (SAF)
Tampa BSides - Chef's Tour of Microsoft Security Adoption Framework (SAF)
 
New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024
New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024
New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024
 
DevEX - reference for building teams, processes, and platforms
DevEX - reference for building teams, processes, and platformsDevEX - reference for building teams, processes, and platforms
DevEX - reference for building teams, processes, and platforms
 
From Family Reminiscence to Scholarly Archive .
From Family Reminiscence to Scholarly Archive .From Family Reminiscence to Scholarly Archive .
From Family Reminiscence to Scholarly Archive .
 
Anypoint Exchange: It’s Not Just a Repo!
Anypoint Exchange: It’s Not Just a Repo!Anypoint Exchange: It’s Not Just a Repo!
Anypoint Exchange: It’s Not Just a Repo!
 
Ensuring Technical Readiness For Copilot in Microsoft 365
Ensuring Technical Readiness For Copilot in Microsoft 365Ensuring Technical Readiness For Copilot in Microsoft 365
Ensuring Technical Readiness For Copilot in Microsoft 365
 
Unraveling Multimodality with Large Language Models.pdf
Unraveling Multimodality with Large Language Models.pdfUnraveling Multimodality with Large Language Models.pdf
Unraveling Multimodality with Large Language Models.pdf
 

Increasing the probability of program success

  • 1. Increasing the Probability of Program Success Program Success starts and end with Process. Along the way, people and tools are needed, but process is the foundation of program success. These processes start with the Concept of Operations, describing what Capabilities are needed by the stakeholder to accomplish the mission of the program. Assessment of progress to plan must be made in units of measure meaningful to the decision makers. Measures of Effectiveness are defined by the Government. Measures of Performance and Technical Performance Measures are defined by Industry. For each step in the processes above, objective evidence in Figure 1 is needed, connected in a hierarchy of increasing visibility to the description of Done. ❶ Pre-Award Work  Define desired capabilities  Assess readiness of technologies.  Define war fighter’s use System  Define Measures of Effectiveness  Create Integrated Master Plan  Identify uncertainties  Develop risk-adjusted estimates ❷ Issue Request for Proposal  Include Government products  Specify award criteria  Update IMP and Uncertainties  Define key framing assumptions  Submit updated cost and schedule estimate to 70% JCL  Submit deterministic IMS ❸ Award Based on Criteria  Establish these criteria in the Integrated baseline Review  Measures performance and award fee against these criteria  Use criteria to produce ETC, EAC, ECD ❹ Awardee create Credible PMB  Integrated Master Plan  Technical Plan  WBS and Dictionary  Program Management Plan ❺ Install Credible PMB  Define Measures of Effectiveness, Measures of Performance, technical Performance Measures, or Key Performance Parameters for each deliverable ❻ Monitor Progress to Plan  Ensure technical progress made accordingto Plan  Review cost and schedule progress againstplan  Update risk register  Identify which activities requires closer monitoringin future Figure 1 ‒ Each processinthe table above requires data to create a credible program performance management system describedabove in eachstage of the program’s maturity.
  • 2. In my career, I've worked for a lot of really good managers, and of course, Gene Kranz was one of the best. One of the things I really admired about Gene ... is that of things didn't work out quite right in a project or in a ting that you were doing, Gene would often say, "Well, maybe I didn't explain as clearly as I should have what it was I needed you to do." ‒ Mission Control Center ISS Project Johnson Space Center Without a clear and concise description of Done in units of measure meaningful to the decision makers (Effectiveness and Performance), it's hard to know how to reach Done, how much it will cost to reach Done, and when we will be arriving at Done. This is the purpose of the processes described in this document - to provide the map with the route, cost, and measures of progress along the way to Done, while assuring when we arrive at Done, the deliverables implement the needed Capabilities of the system. These capabilities provide solutions for each process step. With the Roadmap in Figure 2, a credible Performance Measurement Baseline developed to inform the decision makers about progress to plan and corrective action opportunities. To increase the Probability of Program success, three phases of increasing procurement maturity must be in place. Figure 2 – Three Phases neededto construct a credible Performance Measurement Baseline fromthe Concept of Operations.
  • 3. Concept of Operations (ConOps) A Concept of Operations (CONOPS) is a document describing the characteristics and intended usage of a proposed or existing system from the viewpoint of its users. Its purpose is to communicate the quantitative and qualitative system characteristics to all stakeholders and serve as a basis for stakeholder discussions about the system. Moreover, the CONOPS can help reach a “meeting of the minds” before the requirements process begins. Generated effectively, it may convey a clearer statement of intent than the requirements themselves. 1 Our approach to developing the Concept of Operation starts with a verbal or graphicalstatement that clearly and concisely expresses what the program intends to accomplish and how it will be done based on DoDAF V2.02 framework. The Concept of Operation includes:  Current System or Situation - Background, mission, objectives, scope, operational policies and constraints - Operational environment and its characteristics with major system components and interconnections, Interfaces to external systems and processes - Capabilities or Functions of the current system - Performance characteristics needed to fulfill the planned system with their quality attributes needed to fulfill the planned system  Concept for new or modified system - Background, objectives, and scope of new system with Operational policies and constraints of the new system. - Technical policies and constraints that impact the new system and operational environment and its characteristics for the major system components and interconnections - Capabilities or function for the new or modified system including activities and relationships WBS/CWBS/WBS Dictionary The Work Breakdown Structure (WBS) defines the products and the services that produce those products in a Mutually Exclusive and Exhaustively Complete structured decomposition. Constructing the WBS starts with the Concept of Operations for the deliverables that implement that ConOps.The work breakdown structure’s define and organizing the project’s work. A project budget is allocated to the elements of the work breakdown structure. When the Organizational Breakdown Structure (OBS) is defined, the staffing budgets are defined based on the each project's work breakdown structure. Allocating time and cost estimates to work breakdown elements, the project schedule and budget can be developed. As the project executes, specific sections of the WBS can be tracked to identify project cost performance and identify issues and problem areas in the project organization. The WBS identifies potential technical and programmatic risks. These risks are tracked and reviewed as the project executes. By integrating the WBS with an OBS, the project manager identifies communication points and formulate the communication plan across the project organization. 1 “Developing a Stakeholder-AssistedAgile CONOPS Development Process,” Ali Mostashari, Sara McComb, Deanna Kennedy, Robert, Cloutier, andPeter Korfiatis, Systems Engineering, Volume 15, Issue 1, 2012, pp. 1-13.
  • 4. Operational and Technical Requirements Operational requirements are statements that identify the essential capabilities, associated requirements, performance measures, and the process or series of actions to be taken in effecting the results that are desired in order to address mission area deficiencies, evolving applications or threats, emerging technologies, or system cost improvements. 2 The operational requirements assessment starts with the Concept of Operations (CONOPS) and goes to a greater level of detail in identifying mission performance assumptions and constraints and current deficiencies of or enhancements needed for operations and mission success. Operational requirements are the basis for system requirements. Elicitation of these requirements starts with users' needs based on an operational needs assessment. Analysis of the needs identifies capability gaps and defines the operational and top- level characteristics and requirements of the system. Using CONOPS the operational needs, desires, visions, expectations, performance requirements, and challenges of the system are captured from the users, developers, and integrators, to define the system operational requirements, ensuring each requirement maps to an operational need in CONOPS. Integrated Master Plan Successful Program Management developing and maintaining plans and schedules for all program processes needed effective Government ‒ Industry interaction. With the contract in place, schedule, cost, and resources from the contractor established, the program plan accounts ‒ at an appropriate level of detail ‒ the contractor's strategy for the successful delivery of the programs outcome. The IMP, with its hierarchy of Significant Accomplishments (SA) and Accomplishment Criteria (AC), documents that the program is properly structured and executable within schedule and cost constraints with an acceptable level of risk. During the proposal evaluation and source selection phases, the IMP and IMS are critical components of the offeror's proposal; identifying the offeror's ability to decompose a program into tasks and phases to be successfully executed to deliver the needed capabilities. After contract award, the IMP and IMS are used by the contractor and the government as the day-to-day tool for executing the program and tracking program technical and schedule status, including significant risk mitigation efforts. The IMP is a Systems Engineering activity. describing the programmatic architecture in the same way the hardware and software are described in the technical architecture. A poor, weak, or unstructured Programmatic Architecture reduces the visibility to the Product Architecture’s cost and schedule performance measures and their connections with the Technical Performance Measures. 2 Kossiakoff, A., andN. Sweet, 2003, Systems Engineering Principles and Practices, Hoboken, N.J., JohnWiley& Sons.
  • 5. Integrated Master Schedule Starting with the Work Breakdown Structure (WBS), the Integrated Master Schedule summarizes the work and the order of the performance of the work for the Accomplishment Criteria (AC) in the IMP. 3 A well-constructed IMS contains distinct tasks summarized by WBS identifiers so the program can track progress and measure schedule performance. Risk mitigation and handling activities are included in the program IMP and IMS and resourced in the IMS. The IMP and IMS should be traceable to the program and contractor WBS and Statement of Work. Starting with the IMP’s top-down planning, the IMS bottom-up execution tool assures visibility to several critical success factors for the program.  Measurable Criteria ‒ established by IMP Significant Accomplishments including accomplishment of critical performance requirements (Key Performance Parameters and Technical Performance Measures).  Stakeholder Involvement ‒ including user organizations, financial managers, and sustainment organizations are involved in the work planning process from alllife-cyclephases to ensure that technical and support activities are adequately addressed in program plans in the IMP and IMS.  Communication of Progress to Plan ‒ through the IMS with stakeholders on a regular basis. For enterprise systems with largenumbers of external interfaces and programs, the IMS is used as the integration tool to indicate and track milestones relevant to the other programs. Technical Performance Measures Technical Performance Measurement (TPM) are used to predict the future value of a key technical performance parameter of an end product under development based on current assessments of products lower in the system structure. TPMs define the planned progress of a selected technical parameter defined as the expected performance at specific points in the program as shown in the WBS, IMS, IMP. These connections start with Systems Engineering – where Measures of Effectiveness (MOE), Measures of Performance (MOP), Technical Performance Measures (TPM), and Risks are identified. TPMs are derived from MOPs and characterize the physical or functional attributes relating to the execution of the mission or function. TPMs may also be derived from Measures of Effectiveness (MOE) to become system cost and effectiveness metrics. The TPMs Performance parameters significantly qualify the entire system, with the parameters derived from analyses, demonstrations, or tests. The measure of value is the result of analyses or tests and is used to predict future values. Each parameter is periodically measured and profiled to compare with predicted values and tolerances over the project life cycle. 3 Air Force Pamphlet 63-128, “Integrated LifecycleManagement,” 10 July 2014
  • 6. Technical and Programmatic Risk Management Risks are future uncertainties relating to achieving program technical and programmatic performance goals. 4 Uncertainty comes in two forms – reducible uncertainty (epistemic) and irreducible uncertainty (aleatory). These uncertainties create risk. Epistemic uncertainty can be handled with specific work, redundancy, testing, alternative plans. Aleatory uncertainty can only be handled with margin ‒ cost, schedule, and technical margin. Both handling methods must be defined in the Integrated Master Schedule ‒ risk buy down tasks and margin. Starting with a risk adjusted Performance Measurement Baseline (PMB), the information is needed to inform program performance using both reducible and irreducible risk. Statusing the reducible risks at the planned reduction date is similar to a Technical Performance Measure, where the target measure is improved as the program proceeds. Irreducible risks require schedule margin to protect contract events or end item deliverables. The connections between the program’s Technical Plan (delivery of technical outcomes compliance with needed MOE, MOP, and TPM) and the Programmatic Plan (Cost and Schedule) is the role of the Risk Management Plan. These risk management activities include standard risk processes with their risk reduction efforts as well as application of Management Reserve and Schedule Margin to assure acceptable program performance is met. Management of the Performance Measurement Baseline Performance measurement is the ongoing monitoring and reporting of program accomplishments, particularly progress toward pre-established goals. Performance measures may address the type or level of program activities conducted (process), the direct products and services delivered by a program (outputs), or the results of those products and services (outcomes). The Performance Measurement Baseline (PMB) is a time–phased schedule of all the work to be performed, the budgeted cost for this work, and the organizational elements that produce the deliverables from this work. The PMB provides an integrated view of three project constraints: scope, time, and cost, and establishes a means to measure project’s performance in units of measure meaningful to the decision makers. There are three PMB’s: 1. The scope baseline from the WBS, projects specifications, design elements and deliverables 2. The time baseline in the approved project schedule, showing the planned start and finish of the work needed to produce the scope 3. The cost baseline for the budget and spend plan used to monitor cost performance Managing the PMB is part of Program Performance management ‒ a process for making course corrections to achieve an organization's goals by using performance information to adjust resources and activities. Focusing on Program Performance Management (PPM) is to focus on the future. Program Performance Management techniques track the progress and status of the project and forecast the likely future performance of the project. Information from the PMB’s performance provides corrective actions needed to Keep the Program Green. 4 “DOD Risk Management Guide,” V7, December 2014