SlideShare a Scribd company logo
1 of 36
Georgetown Pike Walkway
Phase III & Phase IV
Citizen Information Meeting
March 22, 2017, 7PM to 9PM (Great Falls Library)
(Formal Presentation Starts at 7:30)
1
Project Team
Mr. W. Todd Minnix, P.E., Chief, Transportation Design Division
Ms. Brook Khorashadi, P.E., Section Chief, Transportation Design Division
Mr. Bob Ayers, Project Manager, Transportation Design Division
Mr. Doug Miller, Environmental Specialist
Mr. Chris Wells, Bike/Ped Manager
___________________________________________________________
Supervisor John Foust, Dranesville District Supervisor
___________________________________________________________
2
Meeting Schedule
Tonight’s Agenda
• Phase III – Presentation followed by Q&A
• Phase IV – Presentation followed by Q&A
• Return to display boards, one-on-one discussion,
individual questions
• Meeting Ends – 9:00PM
3
Meeting Purpose
Tonight’s Purpose:
• Provide an overview for both Phase III and Phase IV projects
• Provide the public an update on on-going activities related to
both projects, current status, and next steps
• Solicit comments regarding what effect, if any, the proposed
facilities may have on historic resources
Tonight we will answer questions, but please submit all
comments in writing to enable them to be part of the public
record.
4
Overview
Existing conditions:
• No continuous pedestrian facilities
• Phase I (Applewood Lane to Walker Road in Great
Falls Village)
• Phase II (Falls Chase Court to Utterback Store
Road)
5
Overview
Proposed Improvements:
• Phase III will connect existing Phase II Pedestrian Facility to Falls
Bridge Lane
• Phase IV will connect Falls Bridge Lane to Seneca Road
6
Phase III
Phase III - Project from Ex. Pedestrian
Facility to Falls Bridge Lane
7
Phase III: Background
• Federally-funded project utilizing grants that were applied for by
Fairfax County on behalf of the Great Falls Trailblazers.
• Environmental documentation for the project was approved in 2010
for the overall Georgetown Pike Trail project.
• As a federally-funded project, all Fairfax County and VDOT design
standards, including ADA accessibility standards, must be met
• The design for Phase III, started in 2013, and development of final
design plans are pending resolution of project scope.
8
Phase III: Concept Overview
Three conceptual alternatives were considered:
• Alternative #1: Shoulder Section
• Alternative #2: Crosswalk (Avoidance Alternative)
• Alternative #3: Curb & Gutter
9
Phase III: Alt. #1 Shoulder Section
Alternative # 1 – Shoulder Section
• Requires construction of asphalt pedestrian facility in
existing trail easement located on private property.
• Design utilizes a standard buffer and the existing ditch to
separate pedestrians from traffic.
• Tree Loss = Approx. 60-70 trees. Extensive loss of
mature trees nearly eliminating visual screening between
adjacent property and Georgetown Pike.
10
Phase III: Alt. #1 Shoulder Section
Alternative # 1 – Shoulder Section
11
Phase III: Alt. #1 Shoulder Section
Alternative # 1 – Shoulder Section – Approx. Tree Loss
Approx. 60-70 Trees to be Removed – (“X” = Tree Loss)
12
Phase III: Alt. #2 Avoidance
13
Alternative # 2 – Crosswalk (Avoidance)
• Alternative requires construction of asphalt pedestrian
facilities on south side of Georgetown Pike
• Requires two unsignalized pedestrian crossings
(crosswalks) across Georgetown Pike
• It is anticipated that crosswalks would not meet VDOT
requirements for installation
Phase III: Alt. #2 Avoidance
14
Alternative # 2 – Crosswalk (Avoidance Alternative)
Phase III: Alt. #2 Avoidance
Alternative # 2 – Crosswalk (Avoidance Alternative)
• Not feasible/Practical for Pedestrian Facility Users
15
Phase III: Alt. #2 Avoidance
16
Alternative # 2 – Crosswalk (Avoidance Alternative)
If crosswalks were installed, a similar installation could look like this:
Phase III: Alt. #3 Curb/Gutter Section
17
Alternative # 3 – Curb & Gutter Section
• Curb & Gutter Section is least intrusive to property and
trees
• Facility will be 6’ wide asphalt
• Constructed within VDOT R/W
• Tree loss is minimized (approx.10-12 Trees)
 The County is soliciting public comments regarding potential
effects the design may have on historic resources.
Phase III: Alt. #3 Curb/Gutter Section
18
Alternative # 3 – Curb & Gutter Section
Phase III: Alt. #3 Curb/Gutter Section
Alternative # 3 – Curb/Gutter Section – Approx. Tree Loss
Approx. 10-12 Trees to be Removed – (“X” = Tree Loss)
19
Phase III: Historic Resources
Historic Resource Concerns
• Although all alternatives are still under consideration, Fairfax County
DOT supports Alternative #3 (Curb & Gutter Section) for Phase III in
order to avoid impacting private property and to avoid significant tree
loss
• Georgetown Pike (GTP) is listed on the National Register of Historic
Places
• Concerns have been expressed that the installation of curb & gutter will
negatively affect the historic integrity of Georgetown Pike
Phase II
20
Phase III: Context of Project
21
Context of Project
Phase III: Historic Resources
• Due to federal funds on Phase III, an “Effect Determination”
from Virginia Department of Historic Resources (VDHR) is
required
oNo effect – No historic resources present
oNo adverse effect – Project impacts to historic properties do not
rise to the level of an adverse effect
oAdverse effect – An adverse effect is found when an undertaking
may alter, directly or indirectly, any of the characteristics of a
historic property that qualify the property for inclusion in the
National Register in a manner that would diminish "any of the
property's aspects of integrity“
22
Phase III: Historic Resources
•FCDOT believes that alternative #3 is the best
option
BUT…
•Tonight we are seeking your input
•Public involvement is a strong component of the
decision making process
23
Phase III: Historic Resources
Steps involved in assessing impacts
• Are historic properties present?
• What makes GTP historic?
o Very early engineered road – retains much of original design integrity
o Important early transportation corridor – early toll road & farm to
market road linking west to the new Federal City
o Listed on National Register of Historic Places
• Could project potentially affect resource?
24
Phase III: Historic Resources
Completed steps
• Historic properties in vicinity of project have been identified
• Consulting parties have been identified
• Public Information Meeting being held tonight
25
Phase III: Historic Resources
Next Steps
• Tonight – We are soliciting the community’s written feedback on this
issue by April 14, 2017. If desired, please submit a comment for the record
by using the comment sheet provided, email, or online form.
• VDHR is gatekeeper of historic resources in Virginia
• Based in part on public input, VDHR will assess impacts of project on
NRHP listed Georgetown Pike and make an effect determination
• This issue needs to be resolved before final design on Phase III can begin
26
Phase III: Question/Answers
Questions about Phase III?
Reminder:
Please submit all comments in writing by April 14 in order for
them to be considered as part of the public record.
27
Phase IV
Phase IV - Project from Falls Bridge Lane
to Seneca Road
28
Phase IV: Background
• Locally Funded project
• Public pedestrian facility will meet all VDOT &
County standards for maintenance and for ADA
accessibility compliance.
• Facility will be maintained by Fairfax County
29
Phase IV: Concept
30
Concept Features:
• 6’ wide asphalt facility with standard buffer and existing
ditch
• This pedestrian facility will link Phases II and III to Seneca
Square and the existing asphalt trails along Leesburg Pike
• Intent is to minimize right-of-way impacts and tree loss
Phase IV: Concept (1 of 3)
31
Phase IV: Concept (2 of 3)
32
Phase IV: Concept (3 of 3)
33
Phase IV: Question/Answers
34
Questions about Phase IV?
Reminder:
Please submit all comments in writing by April 14 in order for
them to be considered as part of the public record.
Citizen Input
35
Ways to Comment
• Fill out & submit a comment sheet tonight (Comment Box Provided)
• Comment section on project website:
http://www.fairfaxcounty.gov/fcdot/pedestrian/georgetownpiketrail.htm
• Email Douglas Miller: douglas.miller3@fairfaxcounty.gov
• Fill out and mail a comment sheet:
Douglas Miller
Fairfax County Dept. of Transportation
4050 Legato Road, Suite 400
Fairfax, VA 22033
Submit written
comments by
April 14, 2017
Georgetown Pike Walkway
Phase III and Phase IV
Thank you!
36

More Related Content

What's hot

What's hot (20)

Shirley Gate Road Extended Corridor Planning Study
Shirley Gate Road Extended Corridor Planning StudyShirley Gate Road Extended Corridor Planning Study
Shirley Gate Road Extended Corridor Planning Study
 
Reston Network Analysis: 2050 2nd Tier Mitigation Results
Reston Network Analysis: 2050 2nd Tier Mitigation ResultsReston Network Analysis: 2050 2nd Tier Mitigation Results
Reston Network Analysis: 2050 2nd Tier Mitigation Results
 
I-66 Multimodal Improvements Inside the Beltway
I-66 Multimodal Improvements Inside the BeltwayI-66 Multimodal Improvements Inside the Beltway
I-66 Multimodal Improvements Inside the Beltway
 
Braddock Road Multimodal Study-Guinea Road to I-495: Community Meeting No. 3:...
Braddock Road Multimodal Study-Guinea Road to I-495: Community Meeting No. 3:...Braddock Road Multimodal Study-Guinea Road to I-495: Community Meeting No. 3:...
Braddock Road Multimodal Study-Guinea Road to I-495: Community Meeting No. 3:...
 
Operational Analysis of Dulles Toll Road Ramps to Tysons
Operational Analysis of Dulles Toll Road Ramps to TysonsOperational Analysis of Dulles Toll Road Ramps to Tysons
Operational Analysis of Dulles Toll Road Ramps to Tysons
 
Continuation of Countywide Dialogue on Transportation
Continuation of Countywide Dialogue on TransportationContinuation of Countywide Dialogue on Transportation
Continuation of Countywide Dialogue on Transportation
 
Silver Line Update: December 1, 2015
Silver Line Update: December 1, 2015Silver Line Update: December 1, 2015
Silver Line Update: December 1, 2015
 
North Kings Highway (VA 241) Intersection Improvements Study
North Kings Highway (VA 241) Intersection Improvements StudyNorth Kings Highway (VA 241) Intersection Improvements Study
North Kings Highway (VA 241) Intersection Improvements Study
 
Route 1 Multimodal Alternative Analysis Status Update
Route 1 Multimodal Alternative Analysis Status UpdateRoute 1 Multimodal Alternative Analysis Status Update
Route 1 Multimodal Alternative Analysis Status Update
 
Southrun Road-2016 VDOT Repaving: Complete Streets-Improving Multimodal Mobility
Southrun Road-2016 VDOT Repaving: Complete Streets-Improving Multimodal MobilitySouthrun Road-2016 VDOT Repaving: Complete Streets-Improving Multimodal Mobility
Southrun Road-2016 VDOT Repaving: Complete Streets-Improving Multimodal Mobility
 
Fairfax County Countywide Transit Network Study: Proposed High Quality Transi...
Fairfax County Countywide Transit Network Study: Proposed High Quality Transi...Fairfax County Countywide Transit Network Study: Proposed High Quality Transi...
Fairfax County Countywide Transit Network Study: Proposed High Quality Transi...
 
Fairfax County Parkway Trail at Dulles Toll Road EB Ramp Improvement Study
Fairfax County Parkway Trail at Dulles Toll Road EB Ramp Improvement StudyFairfax County Parkway Trail at Dulles Toll Road EB Ramp Improvement Study
Fairfax County Parkway Trail at Dulles Toll Road EB Ramp Improvement Study
 
Fairfax Countywide Transit Network Study: Proposed High Quality Transit Network
Fairfax Countywide Transit Network Study: Proposed High Quality Transit NetworkFairfax Countywide Transit Network Study: Proposed High Quality Transit Network
Fairfax Countywide Transit Network Study: Proposed High Quality Transit Network
 
Reston Transportation Funding Plan: July 15, 2016
Reston Transportation Funding Plan: July 15, 2016Reston Transportation Funding Plan: July 15, 2016
Reston Transportation Funding Plan: July 15, 2016
 
VDRPT Route 1 Multimodal Alternatives Analysis: Recommendations for Next Steps
VDRPT Route 1 Multimodal Alternatives Analysis: Recommendations for Next StepsVDRPT Route 1 Multimodal Alternatives Analysis: Recommendations for Next Steps
VDRPT Route 1 Multimodal Alternatives Analysis: Recommendations for Next Steps
 
Reston Network Analysis: 2030 Results and Roadway Classifications
Reston Network Analysis: 2030 Results and Roadway ClassificationsReston Network Analysis: 2030 Results and Roadway Classifications
Reston Network Analysis: 2030 Results and Roadway Classifications
 
Burke Centre VRE Connector Ph. IV: Community Meeting for Bicycle and Pedestri...
Burke Centre VRE Connector Ph. IV: Community Meeting for Bicycle and Pedestri...Burke Centre VRE Connector Ph. IV: Community Meeting for Bicycle and Pedestri...
Burke Centre VRE Connector Ph. IV: Community Meeting for Bicycle and Pedestri...
 
Herndon Metrorail Stations Access Management Study (HMSAMS)
Herndon Metrorail Stations Access Management Study (HMSAMS)Herndon Metrorail Stations Access Management Study (HMSAMS)
Herndon Metrorail Stations Access Management Study (HMSAMS)
 
Transform 66: Inside the Beltway
Transform 66: Inside the BeltwayTransform 66: Inside the Beltway
Transform 66: Inside the Beltway
 
Fairfax County Bicycle Master Plan
Fairfax County Bicycle Master PlanFairfax County Bicycle Master Plan
Fairfax County Bicycle Master Plan
 

Viewers also liked

Viewers also liked (20)

2017 VDOT Repaving and Restriping-Springfield, VA: Bicycle, Pedestrian, and T...
2017 VDOT Repaving and Restriping-Springfield, VA: Bicycle, Pedestrian, and T...2017 VDOT Repaving and Restriping-Springfield, VA: Bicycle, Pedestrian, and T...
2017 VDOT Repaving and Restriping-Springfield, VA: Bicycle, Pedestrian, and T...
 
Citizens Information Meeting: Sleepy Hollow Road Walkway-March 29, 2017
Citizens Information Meeting: Sleepy Hollow Road Walkway-March 29, 2017Citizens Information Meeting: Sleepy Hollow Road Walkway-March 29, 2017
Citizens Information Meeting: Sleepy Hollow Road Walkway-March 29, 2017
 
Mobile Food Vending within VDOT Right-of-Way
Mobile Food Vending within VDOT Right-of-WayMobile Food Vending within VDOT Right-of-Way
Mobile Food Vending within VDOT Right-of-Way
 
Student Free Fare Program
Student Free Fare ProgramStudent Free Fare Program
Student Free Fare Program
 
Reston Network Analysis Unmitigated Results: Jan.15, 2016
Reston Network Analysis Unmitigated Results: Jan.15, 2016Reston Network Analysis Unmitigated Results: Jan.15, 2016
Reston Network Analysis Unmitigated Results: Jan.15, 2016
 
Hunter Mill Road and Sunset Hills Road Study-Community Meeting #4
Hunter Mill Road and Sunset Hills Road Study-Community Meeting #4Hunter Mill Road and Sunset Hills Road Study-Community Meeting #4
Hunter Mill Road and Sunset Hills Road Study-Community Meeting #4
 
Protective Helmets
Protective HelmetsProtective Helmets
Protective Helmets
 
I-66 Inside the Beltway Framework Document
I-66 Inside the Beltway Framework DocumentI-66 Inside the Beltway Framework Document
I-66 Inside the Beltway Framework Document
 
Fairfax County Parkway and Franconia-Springfield Parkway Corridor Study
Fairfax County Parkway and Franconia-Springfield Parkway Corridor StudyFairfax County Parkway and Franconia-Springfield Parkway Corridor Study
Fairfax County Parkway and Franconia-Springfield Parkway Corridor Study
 
Reston Network Analysis: Transportation Advisory Commission: July 19, 2016
Reston Network Analysis: Transportation Advisory Commission: July 19, 2016 Reston Network Analysis: Transportation Advisory Commission: July 19, 2016
Reston Network Analysis: Transportation Advisory Commission: July 19, 2016
 
Status of I-66 Corridor Improvement Projects: US Route 15 to I-495
Status of I-66 Corridor Improvement Projects: US Route 15 to I-495Status of I-66 Corridor Improvement Projects: US Route 15 to I-495
Status of I-66 Corridor Improvement Projects: US Route 15 to I-495
 
I-66 Corridor Improvements Outside the Beltway
I-66 Corridor Improvements Outside the BeltwayI-66 Corridor Improvements Outside the Beltway
I-66 Corridor Improvements Outside the Beltway
 
Braddock District 2016 VDOT Repaving: Complete Streets-Improving Multimodal M...
Braddock District 2016 VDOT Repaving: Complete Streets-Improving Multimodal M...Braddock District 2016 VDOT Repaving: Complete Streets-Improving Multimodal M...
Braddock District 2016 VDOT Repaving: Complete Streets-Improving Multimodal M...
 
Fairfax County Comprehensive Transit Plan and Transit Development Plan
Fairfax County Comprehensive Transit Plan and Transit Development PlanFairfax County Comprehensive Transit Plan and Transit Development Plan
Fairfax County Comprehensive Transit Plan and Transit Development Plan
 
Design Public Hearing Presentation for Wiehle Avenue at W&OD Trail
Design Public Hearing Presentation for Wiehle Avenue at W&OD TrailDesign Public Hearing Presentation for Wiehle Avenue at W&OD Trail
Design Public Hearing Presentation for Wiehle Avenue at W&OD Trail
 
Silver Line Update-Board Transportation Committee: Oct. 13, 2015
Silver Line Update-Board Transportation Committee: Oct. 13, 2015Silver Line Update-Board Transportation Committee: Oct. 13, 2015
Silver Line Update-Board Transportation Committee: Oct. 13, 2015
 
Endorsement of the Recommended Design Concept (Preferred Alternative) for Tra...
Endorsement of the Recommended Design Concept (Preferred Alternative) for Tra...Endorsement of the Recommended Design Concept (Preferred Alternative) for Tra...
Endorsement of the Recommended Design Concept (Preferred Alternative) for Tra...
 
Silver Line Phase 1-Status Report: May 6, 2014
Silver Line Phase 1-Status Report: May 6, 2014Silver Line Phase 1-Status Report: May 6, 2014
Silver Line Phase 1-Status Report: May 6, 2014
 
Transportation Alternatives Program Workshop and Public Comment
Transportation Alternatives Program Workshop and Public CommentTransportation Alternatives Program Workshop and Public Comment
Transportation Alternatives Program Workshop and Public Comment
 
Reston Network Analysis: Stakeholder Kick-off Meeting
Reston Network Analysis: Stakeholder Kick-off Meeting Reston Network Analysis: Stakeholder Kick-off Meeting
Reston Network Analysis: Stakeholder Kick-off Meeting
 

Similar to Georgetown Pike Walkway Phase III & Phase IV

Public Forum 2 - Display Boards
Public Forum 2 - Display BoardsPublic Forum 2 - Display Boards
Public Forum 2 - Display Boards
GardinerEast
 
Fairgrounds Roadway Widening Public Hearing (March 17, 2015)
Fairgrounds Roadway Widening Public Hearing (March 17, 2015)Fairgrounds Roadway Widening Public Hearing (March 17, 2015)
Fairgrounds Roadway Widening Public Hearing (March 17, 2015)
City of Midland
 
Torrey pines road corridor study final
Torrey pines road corridor study finalTorrey pines road corridor study final
Torrey pines road corridor study final
kday1
 

Similar to Georgetown Pike Walkway Phase III & Phase IV (20)

Georgetown Pike Walkway Phase IV
Georgetown Pike Walkway Phase IVGeorgetown Pike Walkway Phase IV
Georgetown Pike Walkway Phase IV
 
East Don Trail - Design Concepts
East Don Trail - Design ConceptsEast Don Trail - Design Concepts
East Don Trail - Design Concepts
 
Imagine Bickett Boulevard: Louisburg, North Carolina
Imagine Bickett Boulevard: Louisburg, North CarolinaImagine Bickett Boulevard: Louisburg, North Carolina
Imagine Bickett Boulevard: Louisburg, North Carolina
 
Public Forum 2 - Display Boards
Public Forum 2 - Display BoardsPublic Forum 2 - Display Boards
Public Forum 2 - Display Boards
 
Fairgrounds Roadway Widening Public Hearing (March 17, 2015)
Fairgrounds Roadway Widening Public Hearing (March 17, 2015)Fairgrounds Roadway Widening Public Hearing (March 17, 2015)
Fairgrounds Roadway Widening Public Hearing (March 17, 2015)
 
Crosstown apwa presentation2016 04-19
Crosstown apwa presentation2016 04-19Crosstown apwa presentation2016 04-19
Crosstown apwa presentation2016 04-19
 
Torrey pines road corridor study final
Torrey pines road corridor study finalTorrey pines road corridor study final
Torrey pines road corridor study final
 
Fairgrounds Roadway Widening Public Meeting (Sept. 23, 2014)
Fairgrounds Roadway Widening Public Meeting (Sept. 23, 2014)Fairgrounds Roadway Widening Public Meeting (Sept. 23, 2014)
Fairgrounds Roadway Widening Public Meeting (Sept. 23, 2014)
 
Lee Highway, U.S. Route 29 Phase III Widening
Lee Highway, U.S. Route 29 Phase III WideningLee Highway, U.S. Route 29 Phase III Widening
Lee Highway, U.S. Route 29 Phase III Widening
 
The Value of Place: Planning for Walkability in the Tigard Triangle
The Value of Place: Planning for Walkability in the Tigard TriangleThe Value of Place: Planning for Walkability in the Tigard Triangle
The Value of Place: Planning for Walkability in the Tigard Triangle
 
Corrine Drive Phase 2 Report
Corrine Drive Phase 2 ReportCorrine Drive Phase 2 Report
Corrine Drive Phase 2 Report
 
Final DCP
Final DCPFinal DCP
Final DCP
 
November 3, 2021 CTAC Virtual Workshop
November 3, 2021 CTAC Virtual WorkshopNovember 3, 2021 CTAC Virtual Workshop
November 3, 2021 CTAC Virtual Workshop
 
Somerville Broadway Streetscape Project, CAPS comments to MassDOT, March 2011
Somerville Broadway Streetscape Project, CAPS comments to MassDOT, March 2011 Somerville Broadway Streetscape Project, CAPS comments to MassDOT, March 2011
Somerville Broadway Streetscape Project, CAPS comments to MassDOT, March 2011
 
Comp plan kick off meeting notes 1 26 2016
Comp plan kick off meeting notes 1 26 2016Comp plan kick off meeting notes 1 26 2016
Comp plan kick off meeting notes 1 26 2016
 
Downsview Water Service Improvement Study Maps
Downsview Water Service Improvement Study MapsDownsview Water Service Improvement Study Maps
Downsview Water Service Improvement Study Maps
 
Chain Bridge Road Walkway
Chain Bridge Road WalkwayChain Bridge Road Walkway
Chain Bridge Road Walkway
 
State of the Trails 2015
State of the Trails 2015State of the Trails 2015
State of the Trails 2015
 
Kalorama Community Meeting Presentation (October 9, 2014)
Kalorama Community Meeting Presentation (October 9, 2014)Kalorama Community Meeting Presentation (October 9, 2014)
Kalorama Community Meeting Presentation (October 9, 2014)
 
sr 90 sw 8th street at sw 87 avenue pd&e study
sr 90 sw 8th street at sw 87 avenue pd&e studysr 90 sw 8th street at sw 87 avenue pd&e study
sr 90 sw 8th street at sw 87 avenue pd&e study
 

More from Fairfax County

More from Fairfax County (20)

Merrifield Nursery Emergency Gravity Sewer Replacement
Merrifield Nursery Emergency Gravity Sewer ReplacementMerrifield Nursery Emergency Gravity Sewer Replacement
Merrifield Nursery Emergency Gravity Sewer Replacement
 
SULLY BASINS STORMWATER POND RETROFITS
SULLY BASINS STORMWATER POND RETROFITS SULLY BASINS STORMWATER POND RETROFITS
SULLY BASINS STORMWATER POND RETROFITS
 
Clarks Crossing Road Improvements 05-13-22
 Clarks Crossing Road Improvements 05-13-22 Clarks Crossing Road Improvements 05-13-22
Clarks Crossing Road Improvements 05-13-22
 
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptx
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptxTysons West Wastewater Conveyance Systems Modifications Project 05-22.pptx
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptx
 
Lorton Volunteer Fire Station #19
Lorton Volunteer Fire Station  #19 Lorton Volunteer Fire Station  #19
Lorton Volunteer Fire Station #19
 
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream RestorationScotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
 
Sully Community Center Construction Progress
Sully Community Center Construction ProgressSully Community Center Construction Progress
Sully Community Center Construction Progress
 
Riverwood Community Meeting - 04-14-2022- Presentation.pptx
Riverwood Community Meeting - 04-14-2022- Presentation.pptxRiverwood Community Meeting - 04-14-2022- Presentation.pptx
Riverwood Community Meeting - 04-14-2022- Presentation.pptx
 
Burke VRE Connector Phase IV
Burke VRE Connector Phase IVBurke VRE Connector Phase IV
Burke VRE Connector Phase IV
 
Long Branch Public Meeting - FINAL - 04-11-2022
Long Branch Public Meeting - FINAL - 04-11-2022Long Branch Public Meeting - FINAL - 04-11-2022
Long Branch Public Meeting - FINAL - 04-11-2022
 
Workhouse Arts Stakeholder Kick Offpptx
Workhouse Arts Stakeholder Kick OffpptxWorkhouse Arts Stakeholder Kick Offpptx
Workhouse Arts Stakeholder Kick Offpptx
 
Workhouse Arts Affordable Housing Council
Workhouse Arts Affordable Housing CouncilWorkhouse Arts Affordable Housing Council
Workhouse Arts Affordable Housing Council
 
Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
 Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
 
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT
 
Reston Arts Community Center Feasibility - Wrap Up
 Reston Arts Community Center Feasibility - Wrap Up Reston Arts Community Center Feasibility - Wrap Up
Reston Arts Community Center Feasibility - Wrap Up
 
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
 
Reston Arts Center Feasibility Study Focus Group - March 28, 2022
Reston Arts Center Feasibility Study Focus Group - March 28, 2022Reston Arts Center Feasibility Study Focus Group - March 28, 2022
Reston Arts Center Feasibility Study Focus Group - March 28, 2022
 
Oak Marr Pump Station Rehabilitation – Construction Project
Oak Marr Pump Station Rehabilitation – Construction ProjectOak Marr Pump Station Rehabilitation – Construction Project
Oak Marr Pump Station Rehabilitation – Construction Project
 
Tucker Avenue Neighborhood Community Meeting, 03-15-2022
Tucker Avenue Neighborhood Community Meeting, 03-15-2022Tucker Avenue Neighborhood Community Meeting, 03-15-2022
Tucker Avenue Neighborhood Community Meeting, 03-15-2022
 
Reston Arts Center Feasibility - Focus Group Visual Arts
Reston Arts Center Feasibility -  Focus Group Visual ArtsReston Arts Center Feasibility -  Focus Group Visual Arts
Reston Arts Center Feasibility - Focus Group Visual Arts
 

Recently uploaded

{Qatar{^🚀^(+971558539980**}})Abortion Pills for Sale in Dubai. .abu dhabi, sh...
{Qatar{^🚀^(+971558539980**}})Abortion Pills for Sale in Dubai. .abu dhabi, sh...{Qatar{^🚀^(+971558539980**}})Abortion Pills for Sale in Dubai. .abu dhabi, sh...
{Qatar{^🚀^(+971558539980**}})Abortion Pills for Sale in Dubai. .abu dhabi, sh...
hyt3577
 
call girls inMahavir Nagar (delhi) call me [🔝9953056974🔝] escort service 24X7
call girls inMahavir Nagar  (delhi) call me [🔝9953056974🔝] escort service 24X7call girls inMahavir Nagar  (delhi) call me [🔝9953056974🔝] escort service 24X7
call girls inMahavir Nagar (delhi) call me [🔝9953056974🔝] escort service 24X7
9953056974 Low Rate Call Girls In Saket, Delhi NCR
 
9953056974 Call Girls In Pratap Nagar, Escorts (Delhi) NCR
9953056974 Call Girls In Pratap Nagar, Escorts (Delhi) NCR9953056974 Call Girls In Pratap Nagar, Escorts (Delhi) NCR
9953056974 Call Girls In Pratap Nagar, Escorts (Delhi) NCR
9953056974 Low Rate Call Girls In Saket, Delhi NCR
 
THE OBSTACLES THAT IMPEDE THE DEVELOPMENT OF BRAZIL IN THE CONTEMPORARY ERA A...
THE OBSTACLES THAT IMPEDE THE DEVELOPMENT OF BRAZIL IN THE CONTEMPORARY ERA A...THE OBSTACLES THAT IMPEDE THE DEVELOPMENT OF BRAZIL IN THE CONTEMPORARY ERA A...
THE OBSTACLES THAT IMPEDE THE DEVELOPMENT OF BRAZIL IN THE CONTEMPORARY ERA A...
Faga1939
 
The political system of the united kingdom
The political system of the united kingdomThe political system of the united kingdom
The political system of the united kingdom
lunadelior
 

Recently uploaded (20)

{Qatar{^🚀^(+971558539980**}})Abortion Pills for Sale in Dubai. .abu dhabi, sh...
{Qatar{^🚀^(+971558539980**}})Abortion Pills for Sale in Dubai. .abu dhabi, sh...{Qatar{^🚀^(+971558539980**}})Abortion Pills for Sale in Dubai. .abu dhabi, sh...
{Qatar{^🚀^(+971558539980**}})Abortion Pills for Sale in Dubai. .abu dhabi, sh...
 
Dubai Call Girls Pinky O525547819 Call Girl's In Dubai
Dubai Call Girls Pinky O525547819 Call Girl's In DubaiDubai Call Girls Pinky O525547819 Call Girl's In Dubai
Dubai Call Girls Pinky O525547819 Call Girl's In Dubai
 
KING VISHNU BHAGWANON KA BHAGWAN PARAMATMONKA PARATOMIC PARAMANU KASARVAMANVA...
KING VISHNU BHAGWANON KA BHAGWAN PARAMATMONKA PARATOMIC PARAMANU KASARVAMANVA...KING VISHNU BHAGWANON KA BHAGWAN PARAMATMONKA PARATOMIC PARAMANU KASARVAMANVA...
KING VISHNU BHAGWANON KA BHAGWAN PARAMATMONKA PARATOMIC PARAMANU KASARVAMANVA...
 
*Navigating Electoral Terrain: TDP's Performance under N Chandrababu Naidu's ...
*Navigating Electoral Terrain: TDP's Performance under N Chandrababu Naidu's ...*Navigating Electoral Terrain: TDP's Performance under N Chandrababu Naidu's ...
*Navigating Electoral Terrain: TDP's Performance under N Chandrababu Naidu's ...
 
call girls inMahavir Nagar (delhi) call me [🔝9953056974🔝] escort service 24X7
call girls inMahavir Nagar  (delhi) call me [🔝9953056974🔝] escort service 24X7call girls inMahavir Nagar  (delhi) call me [🔝9953056974🔝] escort service 24X7
call girls inMahavir Nagar (delhi) call me [🔝9953056974🔝] escort service 24X7
 
05052024_First India Newspaper Jaipur.pdf
05052024_First India Newspaper Jaipur.pdf05052024_First India Newspaper Jaipur.pdf
05052024_First India Newspaper Jaipur.pdf
 
9953056974 Call Girls In Pratap Nagar, Escorts (Delhi) NCR
9953056974 Call Girls In Pratap Nagar, Escorts (Delhi) NCR9953056974 Call Girls In Pratap Nagar, Escorts (Delhi) NCR
9953056974 Call Girls In Pratap Nagar, Escorts (Delhi) NCR
 
04052024_First India Newspaper Jaipur.pdf
04052024_First India Newspaper Jaipur.pdf04052024_First India Newspaper Jaipur.pdf
04052024_First India Newspaper Jaipur.pdf
 
America Is the Target; Israel Is the Front Line _ Andy Blumenthal _ The Blogs...
America Is the Target; Israel Is the Front Line _ Andy Blumenthal _ The Blogs...America Is the Target; Israel Is the Front Line _ Andy Blumenthal _ The Blogs...
America Is the Target; Israel Is the Front Line _ Andy Blumenthal _ The Blogs...
 
declarationleaders_sd_re_greens_theleft_5.pdf
declarationleaders_sd_re_greens_theleft_5.pdfdeclarationleaders_sd_re_greens_theleft_5.pdf
declarationleaders_sd_re_greens_theleft_5.pdf
 
06052024_First India Newspaper Jaipur.pdf
06052024_First India Newspaper Jaipur.pdf06052024_First India Newspaper Jaipur.pdf
06052024_First India Newspaper Jaipur.pdf
 
THE OBSTACLES THAT IMPEDE THE DEVELOPMENT OF BRAZIL IN THE CONTEMPORARY ERA A...
THE OBSTACLES THAT IMPEDE THE DEVELOPMENT OF BRAZIL IN THE CONTEMPORARY ERA A...THE OBSTACLES THAT IMPEDE THE DEVELOPMENT OF BRAZIL IN THE CONTEMPORARY ERA A...
THE OBSTACLES THAT IMPEDE THE DEVELOPMENT OF BRAZIL IN THE CONTEMPORARY ERA A...
 
422524114-Patriarchy-Kamla-Bhasin gg.pdf
422524114-Patriarchy-Kamla-Bhasin gg.pdf422524114-Patriarchy-Kamla-Bhasin gg.pdf
422524114-Patriarchy-Kamla-Bhasin gg.pdf
 
Politician uddhav thackeray biography- Full Details
Politician uddhav thackeray biography- Full DetailsPolitician uddhav thackeray biography- Full Details
Politician uddhav thackeray biography- Full Details
 
Job-Oriеntеd Courses That Will Boost Your Career in 2024
Job-Oriеntеd Courses That Will Boost Your Career in 2024Job-Oriеntеd Courses That Will Boost Your Career in 2024
Job-Oriеntеd Courses That Will Boost Your Career in 2024
 
Unveiling the Characteristics of Political Institutions_ A Comprehensive Anal...
Unveiling the Characteristics of Political Institutions_ A Comprehensive Anal...Unveiling the Characteristics of Political Institutions_ A Comprehensive Anal...
Unveiling the Characteristics of Political Institutions_ A Comprehensive Anal...
 
10052024_First India Newspaper Jaipur.pdf
10052024_First India Newspaper Jaipur.pdf10052024_First India Newspaper Jaipur.pdf
10052024_First India Newspaper Jaipur.pdf
 
China's soft power in 21st century .pptx
China's soft power in 21st century   .pptxChina's soft power in 21st century   .pptx
China's soft power in 21st century .pptx
 
Transformative Leadership: N Chandrababu Naidu and TDP's Vision for Innovatio...
Transformative Leadership: N Chandrababu Naidu and TDP's Vision for Innovatio...Transformative Leadership: N Chandrababu Naidu and TDP's Vision for Innovatio...
Transformative Leadership: N Chandrababu Naidu and TDP's Vision for Innovatio...
 
The political system of the united kingdom
The political system of the united kingdomThe political system of the united kingdom
The political system of the united kingdom
 

Georgetown Pike Walkway Phase III & Phase IV

  • 1. Georgetown Pike Walkway Phase III & Phase IV Citizen Information Meeting March 22, 2017, 7PM to 9PM (Great Falls Library) (Formal Presentation Starts at 7:30) 1
  • 2. Project Team Mr. W. Todd Minnix, P.E., Chief, Transportation Design Division Ms. Brook Khorashadi, P.E., Section Chief, Transportation Design Division Mr. Bob Ayers, Project Manager, Transportation Design Division Mr. Doug Miller, Environmental Specialist Mr. Chris Wells, Bike/Ped Manager ___________________________________________________________ Supervisor John Foust, Dranesville District Supervisor ___________________________________________________________ 2
  • 3. Meeting Schedule Tonight’s Agenda • Phase III – Presentation followed by Q&A • Phase IV – Presentation followed by Q&A • Return to display boards, one-on-one discussion, individual questions • Meeting Ends – 9:00PM 3
  • 4. Meeting Purpose Tonight’s Purpose: • Provide an overview for both Phase III and Phase IV projects • Provide the public an update on on-going activities related to both projects, current status, and next steps • Solicit comments regarding what effect, if any, the proposed facilities may have on historic resources Tonight we will answer questions, but please submit all comments in writing to enable them to be part of the public record. 4
  • 5. Overview Existing conditions: • No continuous pedestrian facilities • Phase I (Applewood Lane to Walker Road in Great Falls Village) • Phase II (Falls Chase Court to Utterback Store Road) 5
  • 6. Overview Proposed Improvements: • Phase III will connect existing Phase II Pedestrian Facility to Falls Bridge Lane • Phase IV will connect Falls Bridge Lane to Seneca Road 6
  • 7. Phase III Phase III - Project from Ex. Pedestrian Facility to Falls Bridge Lane 7
  • 8. Phase III: Background • Federally-funded project utilizing grants that were applied for by Fairfax County on behalf of the Great Falls Trailblazers. • Environmental documentation for the project was approved in 2010 for the overall Georgetown Pike Trail project. • As a federally-funded project, all Fairfax County and VDOT design standards, including ADA accessibility standards, must be met • The design for Phase III, started in 2013, and development of final design plans are pending resolution of project scope. 8
  • 9. Phase III: Concept Overview Three conceptual alternatives were considered: • Alternative #1: Shoulder Section • Alternative #2: Crosswalk (Avoidance Alternative) • Alternative #3: Curb & Gutter 9
  • 10. Phase III: Alt. #1 Shoulder Section Alternative # 1 – Shoulder Section • Requires construction of asphalt pedestrian facility in existing trail easement located on private property. • Design utilizes a standard buffer and the existing ditch to separate pedestrians from traffic. • Tree Loss = Approx. 60-70 trees. Extensive loss of mature trees nearly eliminating visual screening between adjacent property and Georgetown Pike. 10
  • 11. Phase III: Alt. #1 Shoulder Section Alternative # 1 – Shoulder Section 11
  • 12. Phase III: Alt. #1 Shoulder Section Alternative # 1 – Shoulder Section – Approx. Tree Loss Approx. 60-70 Trees to be Removed – (“X” = Tree Loss) 12
  • 13. Phase III: Alt. #2 Avoidance 13 Alternative # 2 – Crosswalk (Avoidance) • Alternative requires construction of asphalt pedestrian facilities on south side of Georgetown Pike • Requires two unsignalized pedestrian crossings (crosswalks) across Georgetown Pike • It is anticipated that crosswalks would not meet VDOT requirements for installation
  • 14. Phase III: Alt. #2 Avoidance 14 Alternative # 2 – Crosswalk (Avoidance Alternative)
  • 15. Phase III: Alt. #2 Avoidance Alternative # 2 – Crosswalk (Avoidance Alternative) • Not feasible/Practical for Pedestrian Facility Users 15
  • 16. Phase III: Alt. #2 Avoidance 16 Alternative # 2 – Crosswalk (Avoidance Alternative) If crosswalks were installed, a similar installation could look like this:
  • 17. Phase III: Alt. #3 Curb/Gutter Section 17 Alternative # 3 – Curb & Gutter Section • Curb & Gutter Section is least intrusive to property and trees • Facility will be 6’ wide asphalt • Constructed within VDOT R/W • Tree loss is minimized (approx.10-12 Trees)  The County is soliciting public comments regarding potential effects the design may have on historic resources.
  • 18. Phase III: Alt. #3 Curb/Gutter Section 18 Alternative # 3 – Curb & Gutter Section
  • 19. Phase III: Alt. #3 Curb/Gutter Section Alternative # 3 – Curb/Gutter Section – Approx. Tree Loss Approx. 10-12 Trees to be Removed – (“X” = Tree Loss) 19
  • 20. Phase III: Historic Resources Historic Resource Concerns • Although all alternatives are still under consideration, Fairfax County DOT supports Alternative #3 (Curb & Gutter Section) for Phase III in order to avoid impacting private property and to avoid significant tree loss • Georgetown Pike (GTP) is listed on the National Register of Historic Places • Concerns have been expressed that the installation of curb & gutter will negatively affect the historic integrity of Georgetown Pike Phase II 20
  • 21. Phase III: Context of Project 21 Context of Project
  • 22. Phase III: Historic Resources • Due to federal funds on Phase III, an “Effect Determination” from Virginia Department of Historic Resources (VDHR) is required oNo effect – No historic resources present oNo adverse effect – Project impacts to historic properties do not rise to the level of an adverse effect oAdverse effect – An adverse effect is found when an undertaking may alter, directly or indirectly, any of the characteristics of a historic property that qualify the property for inclusion in the National Register in a manner that would diminish "any of the property's aspects of integrity“ 22
  • 23. Phase III: Historic Resources •FCDOT believes that alternative #3 is the best option BUT… •Tonight we are seeking your input •Public involvement is a strong component of the decision making process 23
  • 24. Phase III: Historic Resources Steps involved in assessing impacts • Are historic properties present? • What makes GTP historic? o Very early engineered road – retains much of original design integrity o Important early transportation corridor – early toll road & farm to market road linking west to the new Federal City o Listed on National Register of Historic Places • Could project potentially affect resource? 24
  • 25. Phase III: Historic Resources Completed steps • Historic properties in vicinity of project have been identified • Consulting parties have been identified • Public Information Meeting being held tonight 25
  • 26. Phase III: Historic Resources Next Steps • Tonight – We are soliciting the community’s written feedback on this issue by April 14, 2017. If desired, please submit a comment for the record by using the comment sheet provided, email, or online form. • VDHR is gatekeeper of historic resources in Virginia • Based in part on public input, VDHR will assess impacts of project on NRHP listed Georgetown Pike and make an effect determination • This issue needs to be resolved before final design on Phase III can begin 26
  • 27. Phase III: Question/Answers Questions about Phase III? Reminder: Please submit all comments in writing by April 14 in order for them to be considered as part of the public record. 27
  • 28. Phase IV Phase IV - Project from Falls Bridge Lane to Seneca Road 28
  • 29. Phase IV: Background • Locally Funded project • Public pedestrian facility will meet all VDOT & County standards for maintenance and for ADA accessibility compliance. • Facility will be maintained by Fairfax County 29
  • 30. Phase IV: Concept 30 Concept Features: • 6’ wide asphalt facility with standard buffer and existing ditch • This pedestrian facility will link Phases II and III to Seneca Square and the existing asphalt trails along Leesburg Pike • Intent is to minimize right-of-way impacts and tree loss
  • 31. Phase IV: Concept (1 of 3) 31
  • 32. Phase IV: Concept (2 of 3) 32
  • 33. Phase IV: Concept (3 of 3) 33
  • 34. Phase IV: Question/Answers 34 Questions about Phase IV? Reminder: Please submit all comments in writing by April 14 in order for them to be considered as part of the public record.
  • 35. Citizen Input 35 Ways to Comment • Fill out & submit a comment sheet tonight (Comment Box Provided) • Comment section on project website: http://www.fairfaxcounty.gov/fcdot/pedestrian/georgetownpiketrail.htm • Email Douglas Miller: douglas.miller3@fairfaxcounty.gov • Fill out and mail a comment sheet: Douglas Miller Fairfax County Dept. of Transportation 4050 Legato Road, Suite 400 Fairfax, VA 22033 Submit written comments by April 14, 2017
  • 36. Georgetown Pike Walkway Phase III and Phase IV Thank you! 36

Editor's Notes

  1. GTP is NRHP listed. While all of GTP remains historically significant, some portions of GTP have had the original integrity, setting, and feeling diminished/compromised by modern development.
  2. Showing trail details from west to east. This is adjacent to shopping center at Seneca Rd.
  3. “Middle section”
  4. Western section, to connect to proposed Phase III