2015 -16 Snow Removal Operations
November 18, 2015
2015-16 Snow Removal Operations
Balancing Act
2
Water Quality
Resources
User Desires &
Expectations
Weather
2015-16 Snow Removal Operations
2014-15 Winter Weather
• More events compared to 2013-14
• More small events 19 one-day events compared to
10 one-day events for 2013-14
• 11 events for freezing rain or ice
• Less snow but the western part of the county experienced
14 inches above the average
3
MSMD Winter Weather DOC Activations and/or Responses
Winter
Weather
Season
Total No of
Events
No of
Events <
1 day
No of
Events >
2 days
Total No
of Days
No of
Freezing
Rain and/or
Ice Events
Total
Snowfall
IAD
Historical
Average
Snowfall
IAD
Total
Snow Fall
DCA
Historical
Average
Snowfall
DCA
2014-15 25 19 6 32 11 35.9" 22" 18.3" 15.4"
2013-14 20 10 10 36 0 52.8" 22" 32" 15.4"
2015-16 Snow Removal Operations
Why Was the 2014-15 Winter Different?
• A significant number of “High Impact Storms”
– Smaller storms (more difficult to forecast)
– Little or no accumulation
– Very cold temperatures
• February 2015 coldest month in more than 20 years regionally
– Road temperatures 20 degrees or lower
– Combined with rush hour traffic
4
2015-16 Snow Removal Operations
Our Snow Captains
5
Bobby Kerns Jonathan Murray
Richard Latimer Dave Snyder
2015-16 Snow Removal Operations
Role of Snow Captains
• Open Department of Operations
Center (DOC)
• Manage snow removal operations
– 12- hour shifts - Team A and Team B
– Scalable teams
• Monitoring weather
• Manage equipment
• Ensure employee safety & training
• Communicate directly with County
leadership and liaisons
6
2015-16 Snow Removal Operations
Maintenance and Stormwater Management Division, DPWES
Scope of Operations
• 152 Building Complexes
– Vehicular Travel Ways
– ADA Compliance
– Critical Walkways
– Non-Critical Walkways
• 75 Roadway Segments
– County Roads
– Developer Default Roads
7
2015-16 Snow Removal Operations
Maintenance and Stormwater Management Division, DPWES
Operational Resources
• MSMD
– Staff – Up to 50 per shift
– Equipment - Approximately 18 drivable pieces
– Contract Support – Valley Crest
• Wastewater Collections
– Staff – Up to 20 per shift
– Equipment –
• Eight MSMD Snow Blowers Assigned
• Solid Waste
– Staff - Up to 40 per shift
– Equipment –
• Two MSMD trucks assigned
• Several MSW pickups harnessed for plows
• DVS
– Typically two mechanics
• Community Labor Force
– Up to 35 volunteers and seven sheriff deputies
8
2015-16 Snow Removal Operations
Maintenance and Stormwater Management Division, DPWES
Key Resource Challenges
• Approximately one plow per 12
complexes
• Facilities are spread across a
large geographic area –
– Good weather travel time vs.
BAD weather travel time
• Only three locations for staging
and chemical storage
• Timing of the event
9
• Equipped/staffed for 4” to 8” event – beyond this we’re pretty stretched
2015-16 Snow Removal Operations
Maintenance and Stormwater Management Division, DPWES
Applying Resources Efficiently
• Solid Waste I-66 Transfer Station
handles vehicular & pedestrian areas at:
– Alliance Drive / MPSTOC
– Transfer Station
– Government Center Complex
• MSMD is assigned all other vehicular
areas throughout the County including
Park & Ride / Commuter Lots.
• Solid Waste I-95 handles walkways in
Area “D”
• Wastewater Collections handles
walkways in Area “C”
• Contracting handles walkways in Area
“A” and “B”
10
A
C
D
B
2015-16 Snow Removal Operations
Maintenance and Stormwater Management Division, DPWES
BOS-Approved - Order of Site Priority
• Priority 1 Sites (75)
– Police Stations / Gov’t Centers (17)
– Fire Stations (31)
– Mass Transit Facilities (16)
– Public Safety Center/MPSTOC (10)
– Emergency Services (1)
• Priority 2 Sites (36)
– Health Centers/24-hr Shelters (21)
– Other Essential Facilities (15)
• Priority 3 Sites (41)
– Libraries (21)
– Community Centers / Others (20) (Fire Training
Academy, Police Training Academy, etc.)
• Priority 4 Sites (75)
– Neighborhood Roads (47)
– Developer Default Roads (24)
– Other (4)
11
2015-16 Snow Removal Operations
Maintenance and Stormwater Management Division, DPWES
Phases for Walkway Efforts
• Phase 1
– Handicap Parking
– Accessible Routes
• Phase 2
– Main on-site walkways
• Phase 3
– Non-critical on-site walks
– Adjacent ROW sidewalks
12
2015-16 Snow Removal Operations
Maintenance and Stormwater Management Division, DPWES
What You Can Expect
• During the Event (snow is falling)
– 75 Priority 1 Sites
– Only plow travel ways
– Handicap parking
– Phase 1 walkways
• After the Event (snow stopped falling)
– Total site cleanup at all 152 sites
– Phase 2 & 3 walkways
– 75 road segments
13
2015-16 Snow Removal Operations
Maintenance and Stormwater Management Division, DPWES
Operational Targets
14
County Facility or Government
Campus Site
0 to 2 inches 2 to 6 inches 6 to 9 inches
Ice and Freezing
Rain
County Government Center
includes Herrity and Pennino Building
Up to 6 hours after the
storm ends
Up to 8 to 12 hours after the
storm ends
Up to 12 to 24 hours
after the storm ends
Up to 6 hours after the
storm ends
Public Safety Center
- MPSTOC
- Courts and Detention Centers
- Pine Ridge EMCC
Police District and Fire Stations
Magisterial District Offices Up to 6 hours after the
storm ends
Up to 12 hours after the
storm ends
Up to 18 to 24 hours after
the storm ends
Up to 6 hours after the
storm ends
Commuter Parking Lots Up to 6 hours after the
storm ends
Up to 12 hours after the
storm ends
Up to 18 to 24 hours after
the storm ends
Up to 8 hours after the
storm ends
Health Centers and
Essential County Facilities
Up to 12 hours after
the storm ends
Up to 18 hours after the
storm ends
Up to 24 hours after the
storm ends
Up to 12 hours after the
storm ends
Libraries, Community Centers
and other Facilities Up to 12 hours after
the storm ends
Up to 12 to 18 hours after the
storm ends
Up to 1 day to 2 days
after the storm ends
Up to 12 to 18 hours after
the storm ends
Road Maintenance and
Improvement and subdivisions in
Developer Default
Up to 1 day after the
storm ends
Up to 1 to 2 days after the
storm ends
Up to 2 to 3 days after
the storm ends
Up to 1 day after the
storm ends
2015-16 Snow Removal Operations
Maintenance and Stormwater Management Division, DPWES
Snow Operations Planning
• Committed Staff Teams
• Snow-worthy Equipment
• Stock Material
• Update Snow Operational Plan
• SOP to Protect Water Quality
• Communication Plan
– Outreach
– Liaisons
15
2015-16 Snow Removal Operations
Maintenance and Stormwater Management Division, DPWES
Role of Agency Liaisons
• Understand what we do
• Communicate with their
facilities
• Help Snow Captains
understand agency priorities
within the Board approved
snow removal priority system
• Liaison partnership
– MSMD Phone Number
703-877-2800
16
Emergency
Operations Center
(EOC)
MSMD
Department
Operations
Center (DOC)
Board of
Supervisors
Liaisons
Agency Liaisons
Agency Heads
DOC Liaisons
Emily Abbott Carolyn Weber
2015-16 Snow Removal Operations
Maintenance and Stormwater Management Division, DPWES
Preparations
• Prepare Equipment & Staff
– Training staff on safety and
equipment
– Self-help barrels
– Parking lot staking
– Brine solution
• Monitor the Weather
17
2015-16 Snow Removal Operations
Maintenance and Stormwater Management Division, DPWES
Wrinkles to the Operational Plan
• Mechanical breakdowns
• Parking lot, personal property, and
equipment damage
• Confusion on the part of citizens
regarding VDOT/County plowing
responsibilities
• Requests to deviate significantly from
the Snow Plan during a storm event
(bypassing liaisons)
18
2015-16 Snow Removal Operations
Maintenance and Stormwater Management Division, DPWES
Cornerstones for Success
• Dedicated Staff (and their families!)
• Early Preparations
– Pre-Season
– Pre-Storm
• Good Communication
– Internal Partnerships
– External Expectations
• A Little Bit of Good Luck
– Weather, Timing & Traffic
19
2015-16 Snow Removal Operations
Maintenance and Stormwater Management Division, DPWES
Questions?
20
Additional Information
For additional information, please contact
www.fairfaxcounty.gov/dpwes
2015-16 Snow Removal Operations
21
Irene Haske, Public Information Officer
703-324-5821, TTY 711
SWPDmail@fairfaxcounty.gov

Mais conteúdo relacionado

Semelhante a 2015-2016 Snow Removal Operations

Snow report jan 2014 1.13.14
Snow report jan 2014 1.13.14Snow report jan 2014 1.13.14
Snow report jan 2014 1.13.14cityofevanston
 
2019 VDOT Northern Virginia Snow Briefing
2019 VDOT Northern Virginia Snow Briefing2019 VDOT Northern Virginia Snow Briefing
2019 VDOT Northern Virginia Snow BriefingVDOT Northern Virginia
 
Winter Storm Jonas Response (County Facilities)
Winter Storm Jonas Response (County Facilities)Winter Storm Jonas Response (County Facilities)
Winter Storm Jonas Response (County Facilities)Fairfax County
 
City of Evanston Public Works Snow Removal Report - January 13, 2014
City of Evanston Public Works Snow Removal Report - January 13, 2014City of Evanston Public Works Snow Removal Report - January 13, 2014
City of Evanston Public Works Snow Removal Report - January 13, 2014cityofevanston
 
VDOT - Snowzilla Review and Lessons Learned: Jan 22-29, 2016
VDOT - Snowzilla Review and Lessons Learned: Jan 22-29, 2016VDOT - Snowzilla Review and Lessons Learned: Jan 22-29, 2016
VDOT - Snowzilla Review and Lessons Learned: Jan 22-29, 2016Fairfax County
 
Tas water the other side of the flush
Tas water   the other side of the flushTas water   the other side of the flush
Tas water the other side of the flushprogressive01
 
Harnessing the Power of FME for Near Real-Time Data Transformations
Harnessing the Power of FME for Near Real-Time Data TransformationsHarnessing the Power of FME for Near Real-Time Data Transformations
Harnessing the Power of FME for Near Real-Time Data TransformationsSafe Software
 
Jim Proce - December 2013 Ice Storm Analysis Briefing
Jim Proce - December 2013 Ice Storm Analysis BriefingJim Proce - December 2013 Ice Storm Analysis Briefing
Jim Proce - December 2013 Ice Storm Analysis BriefingJim Proce
 
2015 Multi-Sector General Permit for Stormwater Discharge
2015 Multi-Sector General Permit for Stormwater Discharge2015 Multi-Sector General Permit for Stormwater Discharge
2015 Multi-Sector General Permit for Stormwater DischargeDavid Horowitz
 
Beyond Routine Forecast Services, Gregory Waller
Beyond Routine Forecast Services, Gregory WallerBeyond Routine Forecast Services, Gregory Waller
Beyond Routine Forecast Services, Gregory WallerTWCA
 
New regulatory framework presentation
New regulatory framework presentationNew regulatory framework presentation
New regulatory framework presentationscotra
 
Master class-mobilisation-v2.0
Master class-mobilisation-v2.0Master class-mobilisation-v2.0
Master class-mobilisation-v2.0nirosuganya
 
Solid metrics for the Coal Authority - SITS - 2014
Solid metrics for the Coal Authority - SITS - 2014Solid metrics for the Coal Authority - SITS - 2014
Solid metrics for the Coal Authority - SITS - 2014TOPdesk
 
Pike Branch Tributary at Ridgeview Park - October 2015
Pike Branch Tributary at Ridgeview Park - October 2015Pike Branch Tributary at Ridgeview Park - October 2015
Pike Branch Tributary at Ridgeview Park - October 2015Fairfax County
 

Semelhante a 2015-2016 Snow Removal Operations (20)

Snow report jan 2014 1.13.14
Snow report jan 2014 1.13.14Snow report jan 2014 1.13.14
Snow report jan 2014 1.13.14
 
2019 VDOT Northern Virginia Snow Briefing
2019 VDOT Northern Virginia Snow Briefing2019 VDOT Northern Virginia Snow Briefing
2019 VDOT Northern Virginia Snow Briefing
 
Winter Storm Jonas Response (County Facilities)
Winter Storm Jonas Response (County Facilities)Winter Storm Jonas Response (County Facilities)
Winter Storm Jonas Response (County Facilities)
 
City of Evanston Public Works Snow Removal Report - January 13, 2014
City of Evanston Public Works Snow Removal Report - January 13, 2014City of Evanston Public Works Snow Removal Report - January 13, 2014
City of Evanston Public Works Snow Removal Report - January 13, 2014
 
VDOT - Snowzilla Review and Lessons Learned: Jan 22-29, 2016
VDOT - Snowzilla Review and Lessons Learned: Jan 22-29, 2016VDOT - Snowzilla Review and Lessons Learned: Jan 22-29, 2016
VDOT - Snowzilla Review and Lessons Learned: Jan 22-29, 2016
 
Tas water the other side of the flush
Tas water   the other side of the flushTas water   the other side of the flush
Tas water the other side of the flush
 
Harnessing the Power of FME for Near Real-Time Data Transformations
Harnessing the Power of FME for Near Real-Time Data TransformationsHarnessing the Power of FME for Near Real-Time Data Transformations
Harnessing the Power of FME for Near Real-Time Data Transformations
 
Legnetto GI Maintenance Presentation 2014
Legnetto GI Maintenance Presentation 2014Legnetto GI Maintenance Presentation 2014
Legnetto GI Maintenance Presentation 2014
 
2017-2018 VDOT NOVA Snow Briefing
2017-2018 VDOT NOVA Snow Briefing2017-2018 VDOT NOVA Snow Briefing
2017-2018 VDOT NOVA Snow Briefing
 
Fairfax Community Leaders Conference
Fairfax Community Leaders ConferenceFairfax Community Leaders Conference
Fairfax Community Leaders Conference
 
Jim Proce - December 2013 Ice Storm Analysis Briefing
Jim Proce - December 2013 Ice Storm Analysis BriefingJim Proce - December 2013 Ice Storm Analysis Briefing
Jim Proce - December 2013 Ice Storm Analysis Briefing
 
2015 Multi-Sector General Permit for Stormwater Discharge
2015 Multi-Sector General Permit for Stormwater Discharge2015 Multi-Sector General Permit for Stormwater Discharge
2015 Multi-Sector General Permit for Stormwater Discharge
 
NDOR Research Conference: Dr. Tuan
NDOR Research Conference: Dr. TuanNDOR Research Conference: Dr. Tuan
NDOR Research Conference: Dr. Tuan
 
Beyond Routine Forecast Services, Gregory Waller
Beyond Routine Forecast Services, Gregory WallerBeyond Routine Forecast Services, Gregory Waller
Beyond Routine Forecast Services, Gregory Waller
 
New regulatory framework presentation
New regulatory framework presentationNew regulatory framework presentation
New regulatory framework presentation
 
Caltrans District 8 presentation
Caltrans District 8 presentationCaltrans District 8 presentation
Caltrans District 8 presentation
 
Master class-mobilisation-v2.0
Master class-mobilisation-v2.0Master class-mobilisation-v2.0
Master class-mobilisation-v2.0
 
Solid metrics for the Coal Authority - SITS - 2014
Solid metrics for the Coal Authority - SITS - 2014Solid metrics for the Coal Authority - SITS - 2014
Solid metrics for the Coal Authority - SITS - 2014
 
Pike Branch Tributary at Ridgeview Park - October 2015
Pike Branch Tributary at Ridgeview Park - October 2015Pike Branch Tributary at Ridgeview Park - October 2015
Pike Branch Tributary at Ridgeview Park - October 2015
 
2018 NOVA Annual Snow Briefing
2018 NOVA Annual Snow Briefing2018 NOVA Annual Snow Briefing
2018 NOVA Annual Snow Briefing
 

Mais de Fairfax County

Merrifield Nursery Emergency Gravity Sewer Replacement
Merrifield Nursery Emergency Gravity Sewer ReplacementMerrifield Nursery Emergency Gravity Sewer Replacement
Merrifield Nursery Emergency Gravity Sewer ReplacementFairfax County
 
SULLY BASINS STORMWATER POND RETROFITS
SULLY BASINS STORMWATER POND RETROFITS SULLY BASINS STORMWATER POND RETROFITS
SULLY BASINS STORMWATER POND RETROFITS Fairfax County
 
Clarks Crossing Road Improvements 05-13-22
 Clarks Crossing Road Improvements 05-13-22 Clarks Crossing Road Improvements 05-13-22
Clarks Crossing Road Improvements 05-13-22Fairfax County
 
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptx
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptxTysons West Wastewater Conveyance Systems Modifications Project 05-22.pptx
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptxFairfax County
 
Lorton Volunteer Fire Station #19
Lorton Volunteer Fire Station  #19 Lorton Volunteer Fire Station  #19
Lorton Volunteer Fire Station #19 Fairfax County
 
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream RestorationScotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream RestorationFairfax County
 
Sully Community Center Construction Progress
Sully Community Center Construction ProgressSully Community Center Construction Progress
Sully Community Center Construction ProgressFairfax County
 
Riverwood Community Meeting - 04-14-2022- Presentation.pptx
Riverwood Community Meeting - 04-14-2022- Presentation.pptxRiverwood Community Meeting - 04-14-2022- Presentation.pptx
Riverwood Community Meeting - 04-14-2022- Presentation.pptxFairfax County
 
Burke VRE Connector Phase IV
Burke VRE Connector Phase IVBurke VRE Connector Phase IV
Burke VRE Connector Phase IVFairfax County
 
Long Branch Public Meeting - FINAL - 04-11-2022
Long Branch Public Meeting - FINAL - 04-11-2022Long Branch Public Meeting - FINAL - 04-11-2022
Long Branch Public Meeting - FINAL - 04-11-2022Fairfax County
 
Workhouse Arts Stakeholder Kick Offpptx
Workhouse Arts Stakeholder Kick OffpptxWorkhouse Arts Stakeholder Kick Offpptx
Workhouse Arts Stakeholder Kick OffpptxFairfax County
 
Workhouse Arts Affordable Housing Council
Workhouse Arts Affordable Housing CouncilWorkhouse Arts Affordable Housing Council
Workhouse Arts Affordable Housing CouncilFairfax County
 
Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
 Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptxFairfax County
 
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT Fairfax County
 
Reston Arts Community Center Feasibility - Wrap Up
 Reston Arts Community Center Feasibility - Wrap Up Reston Arts Community Center Feasibility - Wrap Up
Reston Arts Community Center Feasibility - Wrap UpFairfax County
 
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022Fairfax County
 
Reston Arts Center Feasibility Study Focus Group - March 28, 2022
Reston Arts Center Feasibility Study Focus Group - March 28, 2022Reston Arts Center Feasibility Study Focus Group - March 28, 2022
Reston Arts Center Feasibility Study Focus Group - March 28, 2022Fairfax County
 
Oak Marr Pump Station Rehabilitation – Construction Project
Oak Marr Pump Station Rehabilitation – Construction ProjectOak Marr Pump Station Rehabilitation – Construction Project
Oak Marr Pump Station Rehabilitation – Construction ProjectFairfax County
 
Tucker Avenue Neighborhood Community Meeting, 03-15-2022
Tucker Avenue Neighborhood Community Meeting, 03-15-2022Tucker Avenue Neighborhood Community Meeting, 03-15-2022
Tucker Avenue Neighborhood Community Meeting, 03-15-2022Fairfax County
 
Reston Arts Center Feasibility - Focus Group Visual Arts
Reston Arts Center Feasibility -  Focus Group Visual ArtsReston Arts Center Feasibility -  Focus Group Visual Arts
Reston Arts Center Feasibility - Focus Group Visual ArtsFairfax County
 

Mais de Fairfax County (20)

Merrifield Nursery Emergency Gravity Sewer Replacement
Merrifield Nursery Emergency Gravity Sewer ReplacementMerrifield Nursery Emergency Gravity Sewer Replacement
Merrifield Nursery Emergency Gravity Sewer Replacement
 
SULLY BASINS STORMWATER POND RETROFITS
SULLY BASINS STORMWATER POND RETROFITS SULLY BASINS STORMWATER POND RETROFITS
SULLY BASINS STORMWATER POND RETROFITS
 
Clarks Crossing Road Improvements 05-13-22
 Clarks Crossing Road Improvements 05-13-22 Clarks Crossing Road Improvements 05-13-22
Clarks Crossing Road Improvements 05-13-22
 
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptx
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptxTysons West Wastewater Conveyance Systems Modifications Project 05-22.pptx
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptx
 
Lorton Volunteer Fire Station #19
Lorton Volunteer Fire Station  #19 Lorton Volunteer Fire Station  #19
Lorton Volunteer Fire Station #19
 
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream RestorationScotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
 
Sully Community Center Construction Progress
Sully Community Center Construction ProgressSully Community Center Construction Progress
Sully Community Center Construction Progress
 
Riverwood Community Meeting - 04-14-2022- Presentation.pptx
Riverwood Community Meeting - 04-14-2022- Presentation.pptxRiverwood Community Meeting - 04-14-2022- Presentation.pptx
Riverwood Community Meeting - 04-14-2022- Presentation.pptx
 
Burke VRE Connector Phase IV
Burke VRE Connector Phase IVBurke VRE Connector Phase IV
Burke VRE Connector Phase IV
 
Long Branch Public Meeting - FINAL - 04-11-2022
Long Branch Public Meeting - FINAL - 04-11-2022Long Branch Public Meeting - FINAL - 04-11-2022
Long Branch Public Meeting - FINAL - 04-11-2022
 
Workhouse Arts Stakeholder Kick Offpptx
Workhouse Arts Stakeholder Kick OffpptxWorkhouse Arts Stakeholder Kick Offpptx
Workhouse Arts Stakeholder Kick Offpptx
 
Workhouse Arts Affordable Housing Council
Workhouse Arts Affordable Housing CouncilWorkhouse Arts Affordable Housing Council
Workhouse Arts Affordable Housing Council
 
Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
 Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
 
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT
 
Reston Arts Community Center Feasibility - Wrap Up
 Reston Arts Community Center Feasibility - Wrap Up Reston Arts Community Center Feasibility - Wrap Up
Reston Arts Community Center Feasibility - Wrap Up
 
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
 
Reston Arts Center Feasibility Study Focus Group - March 28, 2022
Reston Arts Center Feasibility Study Focus Group - March 28, 2022Reston Arts Center Feasibility Study Focus Group - March 28, 2022
Reston Arts Center Feasibility Study Focus Group - March 28, 2022
 
Oak Marr Pump Station Rehabilitation – Construction Project
Oak Marr Pump Station Rehabilitation – Construction ProjectOak Marr Pump Station Rehabilitation – Construction Project
Oak Marr Pump Station Rehabilitation – Construction Project
 
Tucker Avenue Neighborhood Community Meeting, 03-15-2022
Tucker Avenue Neighborhood Community Meeting, 03-15-2022Tucker Avenue Neighborhood Community Meeting, 03-15-2022
Tucker Avenue Neighborhood Community Meeting, 03-15-2022
 
Reston Arts Center Feasibility - Focus Group Visual Arts
Reston Arts Center Feasibility -  Focus Group Visual ArtsReston Arts Center Feasibility -  Focus Group Visual Arts
Reston Arts Center Feasibility - Focus Group Visual Arts
 

Último

Political-Ideologies-and-The-Movements.pptx
Political-Ideologies-and-The-Movements.pptxPolitical-Ideologies-and-The-Movements.pptx
Political-Ideologies-and-The-Movements.pptxSasikiranMarri
 
Geostrategic significance of South Asian countries.ppt
Geostrategic significance of South Asian countries.pptGeostrategic significance of South Asian countries.ppt
Geostrategic significance of South Asian countries.pptUsmanKaran
 
Rohan Jaitley: Central Gov't Standing Counsel for Justice
Rohan Jaitley: Central Gov't Standing Counsel for JusticeRohan Jaitley: Central Gov't Standing Counsel for Justice
Rohan Jaitley: Central Gov't Standing Counsel for JusticeAbdulGhani778830
 
57 Bidens Annihilation Nation Policy.pdf
57 Bidens Annihilation Nation Policy.pdf57 Bidens Annihilation Nation Policy.pdf
57 Bidens Annihilation Nation Policy.pdfGerald Furnkranz
 
Foreign Relation of Pakistan with Neighboring Countries.pptx
Foreign Relation of Pakistan with Neighboring Countries.pptxForeign Relation of Pakistan with Neighboring Countries.pptx
Foreign Relation of Pakistan with Neighboring Countries.pptxunark75
 
15042024_First India Newspaper Jaipur.pdf
15042024_First India Newspaper Jaipur.pdf15042024_First India Newspaper Jaipur.pdf
15042024_First India Newspaper Jaipur.pdfFIRST INDIA
 
IndiaWest: Your Trusted Source for Today's Global News
IndiaWest: Your Trusted Source for Today's Global NewsIndiaWest: Your Trusted Source for Today's Global News
IndiaWest: Your Trusted Source for Today's Global NewsIndiaWest2
 
Global Terrorism and its types and prevention ppt.
Global Terrorism and its types and prevention ppt.Global Terrorism and its types and prevention ppt.
Global Terrorism and its types and prevention ppt.NaveedKhaskheli1
 
16042024_First India Newspaper Jaipur.pdf
16042024_First India Newspaper Jaipur.pdf16042024_First India Newspaper Jaipur.pdf
16042024_First India Newspaper Jaipur.pdfFIRST INDIA
 

Último (9)

Political-Ideologies-and-The-Movements.pptx
Political-Ideologies-and-The-Movements.pptxPolitical-Ideologies-and-The-Movements.pptx
Political-Ideologies-and-The-Movements.pptx
 
Geostrategic significance of South Asian countries.ppt
Geostrategic significance of South Asian countries.pptGeostrategic significance of South Asian countries.ppt
Geostrategic significance of South Asian countries.ppt
 
Rohan Jaitley: Central Gov't Standing Counsel for Justice
Rohan Jaitley: Central Gov't Standing Counsel for JusticeRohan Jaitley: Central Gov't Standing Counsel for Justice
Rohan Jaitley: Central Gov't Standing Counsel for Justice
 
57 Bidens Annihilation Nation Policy.pdf
57 Bidens Annihilation Nation Policy.pdf57 Bidens Annihilation Nation Policy.pdf
57 Bidens Annihilation Nation Policy.pdf
 
Foreign Relation of Pakistan with Neighboring Countries.pptx
Foreign Relation of Pakistan with Neighboring Countries.pptxForeign Relation of Pakistan with Neighboring Countries.pptx
Foreign Relation of Pakistan with Neighboring Countries.pptx
 
15042024_First India Newspaper Jaipur.pdf
15042024_First India Newspaper Jaipur.pdf15042024_First India Newspaper Jaipur.pdf
15042024_First India Newspaper Jaipur.pdf
 
IndiaWest: Your Trusted Source for Today's Global News
IndiaWest: Your Trusted Source for Today's Global NewsIndiaWest: Your Trusted Source for Today's Global News
IndiaWest: Your Trusted Source for Today's Global News
 
Global Terrorism and its types and prevention ppt.
Global Terrorism and its types and prevention ppt.Global Terrorism and its types and prevention ppt.
Global Terrorism and its types and prevention ppt.
 
16042024_First India Newspaper Jaipur.pdf
16042024_First India Newspaper Jaipur.pdf16042024_First India Newspaper Jaipur.pdf
16042024_First India Newspaper Jaipur.pdf
 

2015-2016 Snow Removal Operations

  • 1. A Fairfax County, VA, publication Department of Public Works and Environmental Services Working for You! 2015 -16 Snow Removal Operations November 18, 2015
  • 2. 2015-16 Snow Removal Operations Balancing Act 2 Water Quality Resources User Desires & Expectations Weather
  • 3. 2015-16 Snow Removal Operations 2014-15 Winter Weather • More events compared to 2013-14 • More small events 19 one-day events compared to 10 one-day events for 2013-14 • 11 events for freezing rain or ice • Less snow but the western part of the county experienced 14 inches above the average 3 MSMD Winter Weather DOC Activations and/or Responses Winter Weather Season Total No of Events No of Events < 1 day No of Events > 2 days Total No of Days No of Freezing Rain and/or Ice Events Total Snowfall IAD Historical Average Snowfall IAD Total Snow Fall DCA Historical Average Snowfall DCA 2014-15 25 19 6 32 11 35.9" 22" 18.3" 15.4" 2013-14 20 10 10 36 0 52.8" 22" 32" 15.4"
  • 4. 2015-16 Snow Removal Operations Why Was the 2014-15 Winter Different? • A significant number of “High Impact Storms” – Smaller storms (more difficult to forecast) – Little or no accumulation – Very cold temperatures • February 2015 coldest month in more than 20 years regionally – Road temperatures 20 degrees or lower – Combined with rush hour traffic 4
  • 5. 2015-16 Snow Removal Operations Our Snow Captains 5 Bobby Kerns Jonathan Murray Richard Latimer Dave Snyder
  • 6. 2015-16 Snow Removal Operations Role of Snow Captains • Open Department of Operations Center (DOC) • Manage snow removal operations – 12- hour shifts - Team A and Team B – Scalable teams • Monitoring weather • Manage equipment • Ensure employee safety & training • Communicate directly with County leadership and liaisons 6
  • 7. 2015-16 Snow Removal Operations Maintenance and Stormwater Management Division, DPWES Scope of Operations • 152 Building Complexes – Vehicular Travel Ways – ADA Compliance – Critical Walkways – Non-Critical Walkways • 75 Roadway Segments – County Roads – Developer Default Roads 7
  • 8. 2015-16 Snow Removal Operations Maintenance and Stormwater Management Division, DPWES Operational Resources • MSMD – Staff – Up to 50 per shift – Equipment - Approximately 18 drivable pieces – Contract Support – Valley Crest • Wastewater Collections – Staff – Up to 20 per shift – Equipment – • Eight MSMD Snow Blowers Assigned • Solid Waste – Staff - Up to 40 per shift – Equipment – • Two MSMD trucks assigned • Several MSW pickups harnessed for plows • DVS – Typically two mechanics • Community Labor Force – Up to 35 volunteers and seven sheriff deputies 8
  • 9. 2015-16 Snow Removal Operations Maintenance and Stormwater Management Division, DPWES Key Resource Challenges • Approximately one plow per 12 complexes • Facilities are spread across a large geographic area – – Good weather travel time vs. BAD weather travel time • Only three locations for staging and chemical storage • Timing of the event 9 • Equipped/staffed for 4” to 8” event – beyond this we’re pretty stretched
  • 10. 2015-16 Snow Removal Operations Maintenance and Stormwater Management Division, DPWES Applying Resources Efficiently • Solid Waste I-66 Transfer Station handles vehicular & pedestrian areas at: – Alliance Drive / MPSTOC – Transfer Station – Government Center Complex • MSMD is assigned all other vehicular areas throughout the County including Park & Ride / Commuter Lots. • Solid Waste I-95 handles walkways in Area “D” • Wastewater Collections handles walkways in Area “C” • Contracting handles walkways in Area “A” and “B” 10 A C D B
  • 11. 2015-16 Snow Removal Operations Maintenance and Stormwater Management Division, DPWES BOS-Approved - Order of Site Priority • Priority 1 Sites (75) – Police Stations / Gov’t Centers (17) – Fire Stations (31) – Mass Transit Facilities (16) – Public Safety Center/MPSTOC (10) – Emergency Services (1) • Priority 2 Sites (36) – Health Centers/24-hr Shelters (21) – Other Essential Facilities (15) • Priority 3 Sites (41) – Libraries (21) – Community Centers / Others (20) (Fire Training Academy, Police Training Academy, etc.) • Priority 4 Sites (75) – Neighborhood Roads (47) – Developer Default Roads (24) – Other (4) 11
  • 12. 2015-16 Snow Removal Operations Maintenance and Stormwater Management Division, DPWES Phases for Walkway Efforts • Phase 1 – Handicap Parking – Accessible Routes • Phase 2 – Main on-site walkways • Phase 3 – Non-critical on-site walks – Adjacent ROW sidewalks 12
  • 13. 2015-16 Snow Removal Operations Maintenance and Stormwater Management Division, DPWES What You Can Expect • During the Event (snow is falling) – 75 Priority 1 Sites – Only plow travel ways – Handicap parking – Phase 1 walkways • After the Event (snow stopped falling) – Total site cleanup at all 152 sites – Phase 2 & 3 walkways – 75 road segments 13
  • 14. 2015-16 Snow Removal Operations Maintenance and Stormwater Management Division, DPWES Operational Targets 14 County Facility or Government Campus Site 0 to 2 inches 2 to 6 inches 6 to 9 inches Ice and Freezing Rain County Government Center includes Herrity and Pennino Building Up to 6 hours after the storm ends Up to 8 to 12 hours after the storm ends Up to 12 to 24 hours after the storm ends Up to 6 hours after the storm ends Public Safety Center - MPSTOC - Courts and Detention Centers - Pine Ridge EMCC Police District and Fire Stations Magisterial District Offices Up to 6 hours after the storm ends Up to 12 hours after the storm ends Up to 18 to 24 hours after the storm ends Up to 6 hours after the storm ends Commuter Parking Lots Up to 6 hours after the storm ends Up to 12 hours after the storm ends Up to 18 to 24 hours after the storm ends Up to 8 hours after the storm ends Health Centers and Essential County Facilities Up to 12 hours after the storm ends Up to 18 hours after the storm ends Up to 24 hours after the storm ends Up to 12 hours after the storm ends Libraries, Community Centers and other Facilities Up to 12 hours after the storm ends Up to 12 to 18 hours after the storm ends Up to 1 day to 2 days after the storm ends Up to 12 to 18 hours after the storm ends Road Maintenance and Improvement and subdivisions in Developer Default Up to 1 day after the storm ends Up to 1 to 2 days after the storm ends Up to 2 to 3 days after the storm ends Up to 1 day after the storm ends
  • 15. 2015-16 Snow Removal Operations Maintenance and Stormwater Management Division, DPWES Snow Operations Planning • Committed Staff Teams • Snow-worthy Equipment • Stock Material • Update Snow Operational Plan • SOP to Protect Water Quality • Communication Plan – Outreach – Liaisons 15
  • 16. 2015-16 Snow Removal Operations Maintenance and Stormwater Management Division, DPWES Role of Agency Liaisons • Understand what we do • Communicate with their facilities • Help Snow Captains understand agency priorities within the Board approved snow removal priority system • Liaison partnership – MSMD Phone Number 703-877-2800 16 Emergency Operations Center (EOC) MSMD Department Operations Center (DOC) Board of Supervisors Liaisons Agency Liaisons Agency Heads DOC Liaisons Emily Abbott Carolyn Weber
  • 17. 2015-16 Snow Removal Operations Maintenance and Stormwater Management Division, DPWES Preparations • Prepare Equipment & Staff – Training staff on safety and equipment – Self-help barrels – Parking lot staking – Brine solution • Monitor the Weather 17
  • 18. 2015-16 Snow Removal Operations Maintenance and Stormwater Management Division, DPWES Wrinkles to the Operational Plan • Mechanical breakdowns • Parking lot, personal property, and equipment damage • Confusion on the part of citizens regarding VDOT/County plowing responsibilities • Requests to deviate significantly from the Snow Plan during a storm event (bypassing liaisons) 18
  • 19. 2015-16 Snow Removal Operations Maintenance and Stormwater Management Division, DPWES Cornerstones for Success • Dedicated Staff (and their families!) • Early Preparations – Pre-Season – Pre-Storm • Good Communication – Internal Partnerships – External Expectations • A Little Bit of Good Luck – Weather, Timing & Traffic 19
  • 20. 2015-16 Snow Removal Operations Maintenance and Stormwater Management Division, DPWES Questions? 20
  • 21. Additional Information For additional information, please contact www.fairfaxcounty.gov/dpwes 2015-16 Snow Removal Operations 21 Irene Haske, Public Information Officer 703-324-5821, TTY 711 SWPDmail@fairfaxcounty.gov