Basic Concepts of
Earned Value Management
(EVM)
Agenda
7/23/2015
2
 Safety
 EarnedValue Management?
 Why EVM?
 Successful EVM requires…
 Background and Context
 Organizations Practicing EVM
 Approaches to EVM
 Examples ofTerms,Variances, Indices
 Benefits of EVM & KeyTakeAways
 Questions & Support
 PDU opportunities
 The deeper dive…. (for those who wish to participate)
Earned Value Management
7/23/2015
3
Earned value management is a project management
technique for measuring performance and progress. It
combines measurements of the project management
triangle:
 Scope
 Schedule
 Costs
Why Earned Value Management?
7/23/2015
4
 EVM can provide:
 Accurate forecasts of project performance problems
 Significant positive impacts in the areas of planning & controls
 Improvements in scope definition
Successful EVM requires…
7/23/2015
5
 A good project plan
 Values identified for planned work
 Earning metrics – performance indicators
Background & Context
7/23/2015
6
 1900’s EVM practices first used in manufacturing
 1960’s Department of Defense (DoD) adopts EVM; establishes 35 criteria
 1970’s & 1980’s Cost/Schedule Control Systems Criteria (C/SCSC) analysis grows
 1979 EVM introduced toArchitecture and Engineering professions
 1987 PMI Includes EVM into PMBOK Guide
 1990’s EVM emerges as PM methodology for managers and executives
 1998 EVM criteria reduced to 32 and adopted asANSI Standard EIA 748-A
 2002 EVM achieves greater attention due to Sarbanes-OxleyAct of 2002
 2005 EVM becomes part of general federal project risk management
 EVM is now recognized worldwide.
Organizations Practicing EVM…
7/23/2015
7
 Some of the more well known organizations include:
 NASA
 Project Management Institute (PMI)
 Society of Cost Estimating andAnalysis
 DefenseAcquisition University
 Association for theAdvancement of Cost Engineering (AACEi)
 FederalAcquisition Institute
 Acquisition Management (UK)
 Most large engineering, procurement and construction organizations
Approaches to EVM
7/23/2015
8
 Scalable to fit most every project performance need
 Simple – spreadsheet based
 Intermediate – computer programs withWBS, cost & scheduling
 Advanced - complex programs with extensive capabilities
 All approaches require varying degrees of:
 Work Breakdown Structure (WBS) to define the work
 PlanValues (PV) – costs, hours or units of measure
 Schedule to “earn” credit – “value”
 Execute the earned value tracking and measurement plan
Element Description
Estimate at
Completion
(EAC)
The expectedTOTAL cost of the
completed work.
EAC = BAC / CPI
or = AC + ETC
or = AC + ((BAC - EV) / CPI) (typical
case)
or = AC + (BAC - EV) (atypical case)
Estimate to
Complete
(ETC)
The expected cost to FINISH the
remaining work.
ETC = EAC - AC
or = (BAC / CPI) - (EV/CPI)
or = (BAC - EV) / CPI
Cost Forecasting Terms:
7/23/2015
9
BAC - Budget at completion. CPI – Cost Performance Index. AC – Actual Cost. EV – EarnedValue
0
20
40
60
80
100
120
Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec
Jan
Feb
Mar
Project
Cost
$M
PV EV Forecast
Element Description
CostVariances
(CV)
How much under or over budget.
CV = EV-AC
NEGATIVE is over budget, POSITIVE is
under budget.
Schedule
Variances (SV)
How much ahead or behind schedule.
SV = EV-PV
NEGATIVE is behind schedule, POSITIVE
is ahead of schedule.
Variance At
Completion
(VAC)
Variance ofTOTAL cost of the work and
expected cost.
VAC = BAC - EAC
Cost Forecasting Variances:
7/23/2015
10
0
20
40
60
80
100
120
Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec
Jan
Feb
Mar
Project
Cost
($M)
PV EV
Forecast revised EV
revised Forecast
BAC - Budget at completion. EAC – Estimate at Completion. EV – EarnedValue. PV – PlannedValue.AC –Actual Costs.
Element Description
Cost
Performance
Index (CPI)
CPI = EV / AC
Over budget (< 1) or under budget (>
1).
Schedule
Performance
Index (SPI)
SPI = EV / PV
Ahead of schedule (> 1) or behind
schedule (< 1).
Cost Forecasting
Performance Indexes:
7/23/2015
11
0
20
40
60
80
100
120
Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec
Jan
Feb
Mar
Project
Cost
($M)
PV EV
Forecast revised EV
revised Forecast
EV – EarnedValue. PV – PlannedValue.AC –Actual Costs.
Benefits of EVM
7/23/2015
12
 Improves the planning process,
 Fosters a clear definition of the work scope,
 Establishes clear responsibility for work effort,
 Integrates technical, schedule, and cost performance,
 Provides early warning of potential problems,
 Identifies problem areas for immediate and proactive management attention,
 Enables more accurate reporting of cost and schedule impacts of known problems,
 Enhances the ability to assess and integrate technical, schedule, cost, and risk factors,
 Provides consistent and clear communication of progress at all management levels,
 Improves project visibility and accountability.
Key Take Away Items
7/23/2015
13
 Recognize EVM terminology when used.
 Know that EVM is a set of guidelines by which your project
can be more effectively monitored and managed.
 Understand the benefits of utilizing EVM.
Questions?
7/23/2015
14
For PMI-PDU Credit Please send e-mail to:
President@PMI-Metrolina.com
provide their PMI member ID with the notification
What is EVM?
7/23/2015
15
 The basic concept of EVM is more than a unique project
management process or technique.
 It is an umbrella term for 32 guidelines that define a set of
requirements that must be met.
 The objectives are to:
 Relate time phased budgets to specific contract tasks and/or
statements of work.
 Provide the basis to capture work progress assessments against the
baseline plan.
 Relate technical, schedule, and cost performance.
 Provide valid, timely, and auditable data/information for proactive
management action.
 Supply managers with a practical level of summarization for effective
decision making.
Terminology
7/23/2015
16
 Earned value management does introduce a few new terms.
 Budget vs.Actual
 Budgeted cost for work scheduled (BCWS), sometimes called the planned value.
 Budgeted cost for work performed (BCWP) or earned value.
 Actual cost of work performed (ACWP).
 Budget at completion (BAC).
 Estimate at completion (EAC) which is comprised of the cumulative to date actual cost
of work performed plus the estimate to complete the remaining work.
 Variance
 Cost variance (CV) which is calculated as BCWP minusACWP. A result greater than
0 is favorable (an underrun), a result less than 0 is unfavorable (an overrun).
 Schedule variance (SV) which is calculated as BCWP minus BCWS. A result greater
than 0 is favorable (ahead of schedule), a result less than 0 is unfavorable (behind
schedule).
 Variance at completion (VAC) which is calculated as BAC minus EAC. A result greater
than 0 is favorable, a result less than 0 is unfavorable.
32 Guidelines
7/23/2015
17
 The 32 guidelines in theANSI-748 Standard for EVMS are
divided into five sections:
 Organization
 Planning, Scheduling and Budgeting
 Accounting Considerations
 Analysis and Management Reports
 Revisions and Data Maintenance
Organization
7/23/2015
18
Element Description
Work Breakdown
Structure (WBS)
Extended down to a level that describes the tasks that will be performed as well as their
relationship to product deliverables.
Organizational
Breakdown Structure
(OBS)
Defines who is responsible for the work effort in theWBS
Control Account Where theWBS (what) and OBS (who) intersect
Responsibility The person responsible for the work effort (scope, schedule, and budget) is the project
manager
Integration of the planning, scheduling, budgeting, work authorization, and processes
Planning, Scheduling and Budgeting
7/23/2015
19
Element Description
Integrated master
schedule
Resource loaded to determine the budget for the work as scheduled.
Forms the basis for the monthly budget, or BCWS, for each task and the project.
Creates the time phased budget for the performance measurement baseline (PMB).
The total budget for each task, control account, or the entire project is defined as the
budget at complete (BAC).
Schedule Uncertainty Managed with Management Reserve (MR) or Net Estimate Uncertainty
EVM Methodology Work classification: discrete, apportioned effort, or level of effort (LOE).
Earned value technique e.g. 50/50, 0/100, rules of credit or percent complete.
Authorization to
complete
Work only begins when there is formal authorization to proceed. This requirement is a
disciplined approach to clearly define work, schedule, and budget before work
commences and actual costs begin to accrue.
Accounting Considerations
7/23/2015
20
Element Description
Actual costs (ACWP) Actual costs must be captured in a manner consistent with the way work is planned and
budgeted
Timeliness Schedule an important project resource, material, and to accrue performance data
correctly
AccrualTiming Common sense practice to accrue the costs for the material in the same month as the
BCWP was taken (earned) to avoid a very misleading cost variance, also known as
“booking lag.”
Element Description
Human Attention To cost and schedule variances, documenting cause, impact, and correction action, and
determining a new estimate at complete (EAC), if warranted.
Variance Calculations Done at the control account level which provides the ability to summarize the data up
through theWBS and/or the OBS. The ability exists to drill down from the control
account level into the detail data to identify the root cause of a variance, determine the
impact of the variance on future work effort, and identify correction actions.
EVM DataAnalysis
Indices
Consider their past performance and their future performance to complete the work
within the approved EAC and estimated completion date (ECD).
Cost & Schedule
Indices
Featured in commercial off the shelf project management toolsets such as MS Project and
Primavera and should be carefully reviewed during each reporting cycle. They serve as a
valuable validity test to the estimate at completion.
Analysis and Management Reports
7/23/2015
21
Element Description
Disciplines and
Timely
Incorporation of customer directed changes, including stop work orders.
Baseline Control Schedule and budget baseline is essential to be able to assess work accomplished for each
reporting period.
Proactive &
Meaningful
The Revision and Data Maintenance section is a must for proactive, meaningful earned
value management when there is a constantly changing baseline.
Revisions and Data Maintenance
7/23/2015
22
1 de 22

Recomendados

EVA - Metrics.pptEVA - Metrics.ppt
EVA - Metrics.pptNivethaSampath3
1.2K visualizações28 slides
07.cost management updated07.cost management updated
07.cost management updatedShraddha PMP
199 visualizações5 slides
L06 cost managementL06 cost management
L06 cost managementAsa Chan
238 visualizações48 slides

Mais conteúdo relacionado

Similar a Basic Concepts of Earned Value Management.pdf

2.07 cost management 12.07 cost management 1
2.07 cost management 1reddvise
643 visualizações26 slides
Project Cost ManagementProject Cost Management
Project Cost ManagementSerdar Temiz
3K visualizações31 slides
CostManagementSlides.pdfCostManagementSlides.pdf
CostManagementSlides.pdfAmrishTyagi8
7 visualizações24 slides

Similar a Basic Concepts of Earned Value Management.pdf(20)

2.07 cost management 12.07 cost management 1
2.07 cost management 1
reddvise643 visualizações
Project Cost ManagementProject Cost Management
Project Cost Management
Serdar Temiz3K visualizações
1 day ago Brigitte Moffah RE Week 9 Discussion Top of Form1 day ago Brigitte Moffah RE Week 9 Discussion Top of Form
1 day ago Brigitte Moffah RE Week 9 Discussion Top of Form
MartineMccracken3142 visualizações
CostManagementSlides.pdfCostManagementSlides.pdf
CostManagementSlides.pdf
AmrishTyagi87 visualizações
Earning Value from Earned Value ManagementEarning Value from Earned Value Management
Earning Value from Earned Value Management
Glen Alleman2.4K visualizações
7 cost PMBOK7 cost PMBOK
7 cost PMBOK
Waseem Siddique101 visualizações
Evm intro. slide deck 13 may 2018Evm intro. slide deck 13 may 2018
Evm intro. slide deck 13 may 2018
Roger H. Mandel58 visualizações
Evm power point  january 2017Evm power point  january 2017
Evm power point january 2017
Roger H. Mandel402 visualizações
PROJECT HEALTH MONITORING BY EARNED VALUE ANALYSISPROJECT HEALTH MONITORING BY EARNED VALUE ANALYSIS
PROJECT HEALTH MONITORING BY EARNED VALUE ANALYSIS
G K, BE,MS,ISTQB Certified Expert1K visualizações
Project Cost ManagementProject Cost Management
Project Cost Management
Hayat Denzi6.1K visualizações
Project Management 12Project Management 12
Project Management 12
Tathagat Varma680 visualizações
INFORMATION SYTEMS                                                .docxINFORMATION SYTEMS                                                .docx
INFORMATION SYTEMS .docx
pauline2345672 visualizações
Earned Value ManagementEarned Value Management
Earned Value Management
Russell Taylor BEng CEng FAPM FIET9.8K visualizações
Project performance tracking analysis and reportingProject performance tracking analysis and reporting
Project performance tracking analysis and reporting
Charles Cotter, PhD30K visualizações
Assessing Project Performance Beyond CPI/SPIAssessing Project Performance Beyond CPI/SPI
Assessing Project Performance Beyond CPI/SPI
Glen Alleman190 visualizações
Control Account Manager Short CourseControl Account Manager Short Course
Control Account Manager Short Course
Glen Alleman1.3K visualizações

Mais de Elyes ELEBRI

CHI-DEUX.pdfCHI-DEUX.pdf
CHI-DEUX.pdfElyes ELEBRI
2 visualizações1 slide
msp.pdfmsp.pdf
msp.pdfElyes ELEBRI
33 visualizações89 slides
Chapitre_2.pdfChapitre_2.pdf
Chapitre_2.pdfElyes ELEBRI
17 visualizações42 slides

Mais de Elyes ELEBRI(18)

294059912-Conception-d-Une-Chaine-Logistique.pdf294059912-Conception-d-Une-Chaine-Logistique.pdf
294059912-Conception-d-Une-Chaine-Logistique.pdf
Elyes ELEBRI7 visualizações
CHI-DEUX.pdfCHI-DEUX.pdf
CHI-DEUX.pdf
Elyes ELEBRI2 visualizações
msp.pdfmsp.pdf
msp.pdf
Elyes ELEBRI33 visualizações
Chapitre_2.pdfChapitre_2.pdf
Chapitre_2.pdf
Elyes ELEBRI17 visualizações
Santé sécurité au travail-1.pdfSanté sécurité au travail-1.pdf
Santé sécurité au travail-1.pdf
Elyes ELEBRI90 visualizações
2-pdf-exer-gestion de projet.pdf2-pdf-exer-gestion de projet.pdf
2-pdf-exer-gestion de projet.pdf
Elyes ELEBRI12 visualizações
compressed-air-f-2009.pptcompressed-air-f-2009.ppt
compressed-air-f-2009.ppt
Elyes ELEBRI25 visualizações
18_3_BDModeleRelationnel.ppt18_3_BDModeleRelationnel.ppt
18_3_BDModeleRelationnel.ppt
Elyes ELEBRI3 visualizações
chapter13.pptchapter13.ppt
chapter13.ppt
Elyes ELEBRI2 visualizações
chapter12.pptchapter12.ppt
chapter12.ppt
Elyes ELEBRI1 visão
Time Management .pdfTime Management .pdf
Time Management .pdf
Elyes ELEBRI8 visualizações
EDU_QuickStartGuide_Educators.pdfEDU_QuickStartGuide_Educators.pdf
EDU_QuickStartGuide_Educators.pdf
Elyes ELEBRI8 visualizações
2021-07-09-WEBINAR-BCM-V3.pdf2021-07-09-WEBINAR-BCM-V3.pdf
2021-07-09-WEBINAR-BCM-V3.pdf
Elyes ELEBRI3 visualizações
Maîtrise des flux de productionMaîtrise des flux de production
Maîtrise des flux de production
Elyes ELEBRI1.9K visualizações
Gp03 rapport jalon 6 completGp03 rapport jalon 6 complet
Gp03 rapport jalon 6 complet
Elyes ELEBRI966 visualizações

Último

Stock Market Brief Deck 1124.pdfStock Market Brief Deck 1124.pdf
Stock Market Brief Deck 1124.pdfMichael Silva
57 visualizações19 slides
DDKT-SAET.pdfDDKT-SAET.pdf
DDKT-SAET.pdfGRAPE
27 visualizações23 slides
DDKT-Praga.pdfDDKT-Praga.pdf
DDKT-Praga.pdfGRAPE
10 visualizações34 slides
Stock Market Brief Deck 1121.pdfStock Market Brief Deck 1121.pdf
Stock Market Brief Deck 1121.pdfMichael Silva
68 visualizações33 slides
Presentation_Yale.pdfPresentation_Yale.pdf
Presentation_Yale.pdfGRAPE
8 visualizações207 slides

Último(20)

Stock Market Brief Deck 1124.pdfStock Market Brief Deck 1124.pdf
Stock Market Brief Deck 1124.pdf
Michael Silva57 visualizações
DDKT-SAET.pdfDDKT-SAET.pdf
DDKT-SAET.pdf
GRAPE27 visualizações
DDKT-Praga.pdfDDKT-Praga.pdf
DDKT-Praga.pdf
GRAPE10 visualizações
Stock Market Brief Deck 1121.pdfStock Market Brief Deck 1121.pdf
Stock Market Brief Deck 1121.pdf
Michael Silva68 visualizações
Presentation_Yale.pdfPresentation_Yale.pdf
Presentation_Yale.pdf
GRAPE8 visualizações
DDKT-SummerWorkshop.pdfDDKT-SummerWorkshop.pdf
DDKT-SummerWorkshop.pdf
GRAPE14 visualizações
DDKT-Munich.pdfDDKT-Munich.pdf
DDKT-Munich.pdf
GRAPE7 visualizações
Jeremy Hunt's letter to Nausicaa DelfasJeremy Hunt's letter to Nausicaa Delfas
Jeremy Hunt's letter to Nausicaa Delfas
Henry Tapper509 visualizações
Slides.pdfSlides.pdf
Slides.pdf
GRAPE12 visualizações
ROLEOFRESERVEBANKININDIANBANKINGSYSTEM.pdfROLEOFRESERVEBANKININDIANBANKINGSYSTEM.pdf
ROLEOFRESERVEBANKININDIANBANKINGSYSTEM.pdf
Mdshamir58 visualizações
Presentation.pdfPresentation.pdf
Presentation.pdf
GRAPE6 visualizações
Presentation.pdfPresentation.pdf
Presentation.pdf
GRAPE12 visualizações
Market Efficiency.pptxMarket Efficiency.pptx
Market Efficiency.pptx
Ravindra Nath Shukla20 visualizações
DDKT-Southern.pdfDDKT-Southern.pdf
DDKT-Southern.pdf
GRAPE15 visualizações
Economic Capsule - November 2023Economic Capsule - November 2023
Economic Capsule - November 2023
Commercial Bank of Ceylon PLC39 visualizações

Basic Concepts of Earned Value Management.pdf

  • 1. Basic Concepts of Earned Value Management (EVM)
  • 2. Agenda 7/23/2015 2  Safety  EarnedValue Management?  Why EVM?  Successful EVM requires…  Background and Context  Organizations Practicing EVM  Approaches to EVM  Examples ofTerms,Variances, Indices  Benefits of EVM & KeyTakeAways  Questions & Support  PDU opportunities  The deeper dive…. (for those who wish to participate)
  • 3. Earned Value Management 7/23/2015 3 Earned value management is a project management technique for measuring performance and progress. It combines measurements of the project management triangle:  Scope  Schedule  Costs
  • 4. Why Earned Value Management? 7/23/2015 4  EVM can provide:  Accurate forecasts of project performance problems  Significant positive impacts in the areas of planning & controls  Improvements in scope definition
  • 5. Successful EVM requires… 7/23/2015 5  A good project plan  Values identified for planned work  Earning metrics – performance indicators
  • 6. Background & Context 7/23/2015 6  1900’s EVM practices first used in manufacturing  1960’s Department of Defense (DoD) adopts EVM; establishes 35 criteria  1970’s & 1980’s Cost/Schedule Control Systems Criteria (C/SCSC) analysis grows  1979 EVM introduced toArchitecture and Engineering professions  1987 PMI Includes EVM into PMBOK Guide  1990’s EVM emerges as PM methodology for managers and executives  1998 EVM criteria reduced to 32 and adopted asANSI Standard EIA 748-A  2002 EVM achieves greater attention due to Sarbanes-OxleyAct of 2002  2005 EVM becomes part of general federal project risk management  EVM is now recognized worldwide.
  • 7. Organizations Practicing EVM… 7/23/2015 7  Some of the more well known organizations include:  NASA  Project Management Institute (PMI)  Society of Cost Estimating andAnalysis  DefenseAcquisition University  Association for theAdvancement of Cost Engineering (AACEi)  FederalAcquisition Institute  Acquisition Management (UK)  Most large engineering, procurement and construction organizations
  • 8. Approaches to EVM 7/23/2015 8  Scalable to fit most every project performance need  Simple – spreadsheet based  Intermediate – computer programs withWBS, cost & scheduling  Advanced - complex programs with extensive capabilities  All approaches require varying degrees of:  Work Breakdown Structure (WBS) to define the work  PlanValues (PV) – costs, hours or units of measure  Schedule to “earn” credit – “value”  Execute the earned value tracking and measurement plan
  • 9. Element Description Estimate at Completion (EAC) The expectedTOTAL cost of the completed work. EAC = BAC / CPI or = AC + ETC or = AC + ((BAC - EV) / CPI) (typical case) or = AC + (BAC - EV) (atypical case) Estimate to Complete (ETC) The expected cost to FINISH the remaining work. ETC = EAC - AC or = (BAC / CPI) - (EV/CPI) or = (BAC - EV) / CPI Cost Forecasting Terms: 7/23/2015 9 BAC - Budget at completion. CPI – Cost Performance Index. AC – Actual Cost. EV – EarnedValue 0 20 40 60 80 100 120 Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Project Cost $M PV EV Forecast
  • 10. Element Description CostVariances (CV) How much under or over budget. CV = EV-AC NEGATIVE is over budget, POSITIVE is under budget. Schedule Variances (SV) How much ahead or behind schedule. SV = EV-PV NEGATIVE is behind schedule, POSITIVE is ahead of schedule. Variance At Completion (VAC) Variance ofTOTAL cost of the work and expected cost. VAC = BAC - EAC Cost Forecasting Variances: 7/23/2015 10 0 20 40 60 80 100 120 Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Project Cost ($M) PV EV Forecast revised EV revised Forecast BAC - Budget at completion. EAC – Estimate at Completion. EV – EarnedValue. PV – PlannedValue.AC –Actual Costs.
  • 11. Element Description Cost Performance Index (CPI) CPI = EV / AC Over budget (< 1) or under budget (> 1). Schedule Performance Index (SPI) SPI = EV / PV Ahead of schedule (> 1) or behind schedule (< 1). Cost Forecasting Performance Indexes: 7/23/2015 11 0 20 40 60 80 100 120 Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Project Cost ($M) PV EV Forecast revised EV revised Forecast EV – EarnedValue. PV – PlannedValue.AC –Actual Costs.
  • 12. Benefits of EVM 7/23/2015 12  Improves the planning process,  Fosters a clear definition of the work scope,  Establishes clear responsibility for work effort,  Integrates technical, schedule, and cost performance,  Provides early warning of potential problems,  Identifies problem areas for immediate and proactive management attention,  Enables more accurate reporting of cost and schedule impacts of known problems,  Enhances the ability to assess and integrate technical, schedule, cost, and risk factors,  Provides consistent and clear communication of progress at all management levels,  Improves project visibility and accountability.
  • 13. Key Take Away Items 7/23/2015 13  Recognize EVM terminology when used.  Know that EVM is a set of guidelines by which your project can be more effectively monitored and managed.  Understand the benefits of utilizing EVM.
  • 14. Questions? 7/23/2015 14 For PMI-PDU Credit Please send e-mail to: President@PMI-Metrolina.com provide their PMI member ID with the notification
  • 15. What is EVM? 7/23/2015 15  The basic concept of EVM is more than a unique project management process or technique.  It is an umbrella term for 32 guidelines that define a set of requirements that must be met.  The objectives are to:  Relate time phased budgets to specific contract tasks and/or statements of work.  Provide the basis to capture work progress assessments against the baseline plan.  Relate technical, schedule, and cost performance.  Provide valid, timely, and auditable data/information for proactive management action.  Supply managers with a practical level of summarization for effective decision making.
  • 16. Terminology 7/23/2015 16  Earned value management does introduce a few new terms.  Budget vs.Actual  Budgeted cost for work scheduled (BCWS), sometimes called the planned value.  Budgeted cost for work performed (BCWP) or earned value.  Actual cost of work performed (ACWP).  Budget at completion (BAC).  Estimate at completion (EAC) which is comprised of the cumulative to date actual cost of work performed plus the estimate to complete the remaining work.  Variance  Cost variance (CV) which is calculated as BCWP minusACWP. A result greater than 0 is favorable (an underrun), a result less than 0 is unfavorable (an overrun).  Schedule variance (SV) which is calculated as BCWP minus BCWS. A result greater than 0 is favorable (ahead of schedule), a result less than 0 is unfavorable (behind schedule).  Variance at completion (VAC) which is calculated as BAC minus EAC. A result greater than 0 is favorable, a result less than 0 is unfavorable.
  • 17. 32 Guidelines 7/23/2015 17  The 32 guidelines in theANSI-748 Standard for EVMS are divided into five sections:  Organization  Planning, Scheduling and Budgeting  Accounting Considerations  Analysis and Management Reports  Revisions and Data Maintenance
  • 18. Organization 7/23/2015 18 Element Description Work Breakdown Structure (WBS) Extended down to a level that describes the tasks that will be performed as well as their relationship to product deliverables. Organizational Breakdown Structure (OBS) Defines who is responsible for the work effort in theWBS Control Account Where theWBS (what) and OBS (who) intersect Responsibility The person responsible for the work effort (scope, schedule, and budget) is the project manager Integration of the planning, scheduling, budgeting, work authorization, and processes
  • 19. Planning, Scheduling and Budgeting 7/23/2015 19 Element Description Integrated master schedule Resource loaded to determine the budget for the work as scheduled. Forms the basis for the monthly budget, or BCWS, for each task and the project. Creates the time phased budget for the performance measurement baseline (PMB). The total budget for each task, control account, or the entire project is defined as the budget at complete (BAC). Schedule Uncertainty Managed with Management Reserve (MR) or Net Estimate Uncertainty EVM Methodology Work classification: discrete, apportioned effort, or level of effort (LOE). Earned value technique e.g. 50/50, 0/100, rules of credit or percent complete. Authorization to complete Work only begins when there is formal authorization to proceed. This requirement is a disciplined approach to clearly define work, schedule, and budget before work commences and actual costs begin to accrue.
  • 20. Accounting Considerations 7/23/2015 20 Element Description Actual costs (ACWP) Actual costs must be captured in a manner consistent with the way work is planned and budgeted Timeliness Schedule an important project resource, material, and to accrue performance data correctly AccrualTiming Common sense practice to accrue the costs for the material in the same month as the BCWP was taken (earned) to avoid a very misleading cost variance, also known as “booking lag.”
  • 21. Element Description Human Attention To cost and schedule variances, documenting cause, impact, and correction action, and determining a new estimate at complete (EAC), if warranted. Variance Calculations Done at the control account level which provides the ability to summarize the data up through theWBS and/or the OBS. The ability exists to drill down from the control account level into the detail data to identify the root cause of a variance, determine the impact of the variance on future work effort, and identify correction actions. EVM DataAnalysis Indices Consider their past performance and their future performance to complete the work within the approved EAC and estimated completion date (ECD). Cost & Schedule Indices Featured in commercial off the shelf project management toolsets such as MS Project and Primavera and should be carefully reviewed during each reporting cycle. They serve as a valuable validity test to the estimate at completion. Analysis and Management Reports 7/23/2015 21
  • 22. Element Description Disciplines and Timely Incorporation of customer directed changes, including stop work orders. Baseline Control Schedule and budget baseline is essential to be able to assess work accomplished for each reporting period. Proactive & Meaningful The Revision and Data Maintenance section is a must for proactive, meaningful earned value management when there is a constantly changing baseline. Revisions and Data Maintenance 7/23/2015 22