2. PRESSURE POINTS OF CONTEMPORARY
ELECTRIC UTILITIES:
Peak demand and energy crisis in many
utilities due to ever rising demand
supply gap
Need for optimization of generation
and network utilization
Regulator led energy efficiency
mandates
Strong lobbying from environmental
groups
Resource constraints and customer
demands for cheaper rates
Increased operational flexibility needs
Competition, thanks to reform process
and open access
3. TRADITIONAL UTILITY PLANNING
PROCESS, NEEDS & TOOLS
Load Need to Predict & Provide for:
forecasting
Long Term Planning
More Lead time
Generation Rising Costs
Planning Environmental Impacts
Production Supply side alternatives
Costing Capital Costs
Fuel costs
Other O& M costs
Financial
Analysis
Iterate as Tools: Least Cost Planning
necessary &
Rate
Allocation Demand Side Management
4. LEAST COST PLANNING:
“How much energy efficiency could we achieve if all the
potential end-use energy efficiency were achieved which is
economically competitive with conventional forms of
energy”--- Roger Sant W. -- The Energy Productivity Center
Four basic steps of Least Cost Planning(LCP)are:
Understand how energy is used (end-use energy)
Identify technical potential of high end-use efficiency
Evaluate the benefits and costs from societal perspective
Apply engineering & economic analysis
Introduced to persuade energy planners & policy makers that there
is sizeable potential to improve EUE with following considerations
•Customer & Utility Considerations •Program Implementation
•Financial commitments involved •Monitoring & Evaluation
5. WHAT IS DEMAND SIDE MANAGEMENT ?
“DSM is planning, implementation & monitoring of Utility
activities designed to influence consumer use of electricity in
ways that will produce desired changes in the magnitude
and pattern of load either directly caused or indirectly
stimulated by the utility.”
---Clark W. Gellings, Electric Power Research Institute
Broad purview of DSM
will influence customer use
must achieve selected objectives
should be evaluated against non - DSM alternatives
identify customers response
evaluation process
• Load Management
How to achieve DSM? • End Use efficiency Improvement
• Development & Promoting EET’s.
6. DSM LINKAGES-INDUSTRY SECTOR
Industry sector
Utility Load potential End DSM DSM Implementation
Shape Uses Technology Methods
Objectives Options
Alternative
Peak Clipping pricing like TOU
tariffs
Valley Filling P.F and LF
Improvement Regulatory
Load Shifting measures
Lighting system
Strategic Process utilities Specific menu of Incentives for
Conservation energy efficient EET’s
Process
technologies to
Strategic Load modernization Energy Service
match each end
Growth Drives Companies
use option
promotion
Furnaces
Flexible Load
Devices & controls Designing
Shape
customized DSM
programs
7. DSM FRAME WORK
DSM OBJECTIVES DSM ALTERNATIVES
DEFINED/REDEFINED IDENTIFIED
DSM PROGRAM DSM EVALUATION
MONITORING & SELECTION
DSM PROGRAM
IMPLIMENTED
8. BROAD OPTIONS AND TECHNOLOGIES
FOR INDUSTRIAL DSM
Tariff and revenue related
Static metering, reactive power billing, maximum demand
charges, TOU tariffs, incentives etc.
Low /medium cost technical retrofits in:
Plant/Process utilities, drive side modernization ,furnace controls
and automation.
Illumination system improvement options including:
LEDs, CFLs, low loss ballast's, microprocessor based controls,
high efficiency reflectors etc.
New plant / large capital measures
Process r & m, retrofits, adoption of distributed controls,
automation etc.
Energy Management Techniques
monitoring & targeting, EM staff training & motivation,
mandating and sponsoring energy audits
9. EVALUATION OF DSM OPTIONS
As seen from the above, various identified end use
efficiency,DSM measures, offering energy and demand
saving opportunities qualify to be assessed for supply side
impact, benefits and costs,(as cost of saved capacity and
cost of saved energy).The results relate to local utility
attributes and considerations .
These are then compared with alternative, corresponding,
supply (utility) side costs of capacity addition and long
run marginal cost of generation.
Only those options of DSM are shortlisted, which are
cheaper than supply side costs.
To arrive at cost of saved capacity CSC,and cost of saved
energy, following relations, criteria can be adopted.
10. RELATIONS AND CRITERIA…..
» Capital recovery factor (CRF)
= d × (1 + d)n / [(1 + d)n - 1]
where d = utility discount rate & n = measure life
» Total DSM measure cost
= initial cost × [ 1 + (1/(1+d/100)m) + (1/(1+d/100)2m+
…...)
where d = utility discount rate & m = device life &
the series includes all terms where exponent is less than
the measure life
» Cost of saved capacity (CSC) Rs/kW or Rs/kVA=
(Total measure cost (Rs))
((Saved capacity kVA or kW × PCF) / (1-TDLF) (CUF))
» Cost of saved energy (CSE) Rs/kWh=
(Total measure cost (Rs) × CRF)
(Annual Energy Savings (kWh))
11. …...RELATIONS AND CRITERIA
T & D loss factor of local HT & EHT segment for measures
relates to HT or EHT segment end use = TDLF (HT)
T & D loss factor of local LT segment for measures relates
to LT segment end use= TDLF (LT)
Capacity utilization factor (CUF)is also PLF of the local
power plants.(A low CUF say in hydro power plants as
against base load thermal plants can influence measure
cost benefits)
Peak Coincidence Factor (PCF), indicates proportion of
the end use equipment actually operational, during system
peak hours.
Utility discount rate, is denoted here as, d.
Each DSM measure cost is assessed for a measure life of 25
years, for parity with considered utility plant life in
account books, and equals the net present value of measure
cost for 25 years of measure life where m is number of
replacements within 25 years, and d is the discount rate.
12. NEXT STEPS IN DSM PROCESS:
Analyze and merit rate each of the choices, where the
cost of saved capacity & cost of saved energy of DSM
measure is less, as compared to cost of capacity
addition and long run marginal cost of
generation(being utility side SSM costs).
Once all the DSM interventions are merit rated, the
logical next step is the development of Detailed
Project Reports and plans for implementation of
short listed DSM interventions, in a programmatic
manner, adopting a standard project management
cycle.
13. ILLUSTRATIVE CASE STUDY OF DSM OPTION EVALUATION…..
(APPLICATION OF LIGHTING VOLTAGE REGULATORS IN
MUNICIPAL WATER PUMP HOUSES)
The Fluorescent tube manufacturers list the rated or nominal
wattage on any given tube as the objective wattage which the tube
should dissipate under prescribed conditions of operation.
The actual wattage, invariably higher, however depends upon
factors such as supply voltage.
A lighting voltage controller operates on the well known principle
that reduction in input power can be achieved by voltage
optimization without significant drop in light output.
A typical device operates by bringing in, an impedance across the
lighting circuit, to control supply voltage and current.
The lighting voltage controllers are modular in configuration and
can be used on lighting circuits and are applicable for Sodium
Vapor and Mercury vapor lamps as well.
Based on end user feedback, Energy Savings of 10% and Demand
Savings of 15% are envisaged through application of the Lighting
Voltage controllers.
14. ….APPLICATION ANALYSIS RESULTS IN A MUNICIPAL
WATER PUMPING STATION……
Lighting System kW Load = 24
PF of Lighting circuit = 0.85
Lighting system kVA Load = 28.2
Hours of annual operation = 8760 (indoor application)
Peak coincidence factor = 1.0
Utility discount rate = 0.09
End User Electricity Cost = Rs.2.46/kWh
Demand Charges = Rs.170/kVA
Capital Recovery factor = 0.102
Transmission and Distribution Loss Factor for HT Industry (TDLF) = 0.3132
Capacity Utilization Factor (CUF) = 0.725
Energy Savings (kWh) scope = 10%
Demand Reduction (kVA) scope = 15%
Investment in Rs/kVA rating = 1800
Measure Life, Years = 25 Years
Device life, hours = 100,000
Total Measure Cost = Rs.71,144 ,being initial investment + discounted costs of
future replacements over measure life period
15. …END USER COST BENEFITS…..
Present annual energy consumption kWh = 181332
Annual electricity savings, kWh@ 10% = 18133
Annual Demand savings @ 15% = 4 kVA * 12 months
Rupee value of annual electricity (kWh) savings = Rs44608
Rupee worth of annual demand (kVA) savings = Rs8160
Total annual savings = Rs52768
Investment for lighting controller (Rs.1800/KVA*Lighting system kVA Load)
= 50800
Simple Payback Period Years =
(Investment/Rupee value of annual electricity cost savings)
= less than 1 year
16. …..SUPPLY SIDE COSTS.
Cost of Capacity saved (CSC) in Rs/kW=
(Total Measure Cost (Rs.)) / ((kW Capacity Saved*PCF)/ (1-TDLF)(CUF))
= (71144) /((2.4 * 1)/ (1-.3132)( 0.725))
= Rs. 14760 / kW
Cost of Energy Saved (CSE) in Rs. /kWh=
(Total Measure Cost(Rs.)*(CRF)/(Annual Electricity Savings in kWh)
= (71144 * 0.102)/(18133)
= Rs. 0.40 / kWh
The end user simple payback period of less than 1.0 Year, alongside attractive utility side
costs of Rs. 14760 per kW saved capacity ,as against utility side cost of Rs 40,000 per kW of
capacity addition; and, Rs0.40/kWh cost of saved energy, as against Rs 2.00/kWh average
utility cost of supply, render the DSM measure a win-win option.
The state Utility / DISCOM could develop a DSM program for all municipal pump houses
in its coverage area and incentivize stakeholders suitably.
It may be appreciated that a well designed DSM program can address energy efficiency
improvement at macro level, considering all local factors.
Analytics in an iterative manner, for sensitivity factors like peak coincidence factor,
TDLF,CUF, discount rate, can be attempted for customized, localized, program design for
various options.
17. GENERIC DSM MEASURES IN LOAD
MANAGEMENT, PROCESS/PLANT
UTILITIES IN INDUSTRY SECTOR…
Power factor improvement
Application of VSD’s, cogeneration
etc, for EE
Conventional ballast's on
FTL’s replaced by low loss
Replacement of old compressors,
ballasts chillers, by energy efficient
compressors, chillers.
Adoption of energy efficient
CFL’s/LEDs ,Magnetic
Distribution system upgrades in
induction lamps, LPSV, HPSV water pumping, compressed air,
lamps… chilled water systems for EE
Adoption of Lighting voltage
Material handling system upgrades
controllers for EE.
Motor Soft starters/Energy
Adoption of distributed control
savers adoption systems, process automation for EE
Replacement of old pumps by
Furnace, heater upgrades for EE.
high efficiency pumps Replacement of old rewound motors
Replacement of old fans by by new high efficiency motors.
high efficiency fans motors………
18. BARRIERS TO DSM…
Limited Information & Awareness
Lack of adequate infrastructure
Perceived risk of implementing new EE technologies
Absence of codes/standards on EE.
Lack of reliable and credible service organizations that
can provide full range of project implementation services
Limited Availability Of Capital for financing EE Projects
High costs for consumers to implement EE projects
Administered energy tariffs which distort economics.
Absence of any regulatory mandate to review all options
on DSM & Supply Side Management to develop a least
cost capacity expansion plan
19. ….BARRIERS TO DSM
Problems with quality of power
Lack of experience in planning, designing &
implementing DSM programs
Absence of load research information, databases
on energy end use segments, reliable data on
peak coincidence factors etc.
Lack of resources specifically allocated for EE
Lack of adequately skilled staff to initiate EE
measures
Inadequate participation and attention from
Govt. and policy makers….
20. ENABLERS FOR DSM MARKETS – A
WISH LIST:
Regulators and utilities start introducing the
concept of LCP,DSM in the power sector planning
frame work
Developing nations initiate programs on EE in
electricity generation, transmission, distribution
and industry sectors
Developing nations initiate design and adoption
of appropriate energy conservation laws and
regulations, efficiency standards & labeling,
rational electricity pricing and incentive schemes
for EE
Regulators and utilities initiate regular load
research and development of customer databases
on energy use and efficiency improvements for
analytics and planning.
Promotion of energy conservation through mass
media - based awareness campaigns
21. CONCLUSIONS
DSM is a viable, win-win cost effective alternative to SSM.
There is a good case for DISCOMs to develop customized
DSM programs for end users like industry clusters,
agricultural pump sector, municipal water pumping, street
lighting, PSU townships, industrial estates, special
economic zones, commercial buildings etc., due to diffused
yet significant bulk nature of these end user entities and
energy efficiency margins.
•DISCOMs may also consider developing customized DSM
programs, involving distribution upgrades, automation,
kVAh billing, static metering, TOD tariffs etc, to bridge
demand supply gaps efficiently, without revenue losses.
Current crunch times at utilities call for load research
and comprehensive re-visit to various end use segments for
structured DSM program design and implementation,
which could be highly cost effective, as against supply side
capacity augmentation initiatives.