SlideShare a Scribd company logo
1 of 98
In This Session …
                           OVERVIEW



   Purpose




 Production Optimization Versus
 Throughput Optimization — A
 Systematic Approach to Improving
 Production Effectiveness using TOC

    Author


  Pino Villa
  Independent Consultant


                                      1
In This Session …
                                              OVERVIEW

     Discussion Point                                Features

1                       This session explores how the Theory of Constraints business philosophy can be applied
         Explore        to the SAP Production Planning and Detailed Scheduled processes to better understand
                        and optimize organizational throughput (on-time delivery).



                        Understand how production throughput, which focuses on optimizing production
2
                        effectiveness, differs from more cost-focused organizational throughput measures
       Understand       (maximizing production capacity, batch-size).



3                       Learn how to leverage capabilities found in SAP Production Planning to apply the Theory of
          Learn         Constraints to maximize production effectiveness, increase on-time product delivery, and
                        reduce costly inventory levels.


4                       Hear best practices for introducing Theory of Constraints to your organization and learn
      Best Practice     how to avoid common pitfalls you may encounter along the way.



5                       Come away from this session armed with the information you need to assess whether your
         Benefits       organization will benefit from an enhanced focus on organizational throughput.




                                                                                                                     2
What We’ll Cover …
•   Manufacturing throughput
•   Theory of Constraints (TOC) methodology
•   Explanation of Drum, Buffer, Rope (DBR) technique
•   A Theory of Constraint case study
•   Applying the Theory of Constraint technique within SAP
•   Applying the Theory of Constraint technique within SAP PPDS
•   Wrap-up




                                                                  3
Our Key Objective
           Throughput (Sales – Material Costs) is what is provided across the supply chain




OEM      Manufacturer           Distributor                    Dealer                        Retail
                                                                                      OVERVIEW

                                                                  In adopting the Theory of
                                                                  Constraint approach in managing
                                                                  throughput we try to:

                                                                   Maximize Throughput
                                                                   Reduce Inventory
                                                                   Reduce Operating Costs



                                                                  By achieving the above we
                                                                  maximize productivity and
                                                                  profitability
Theory of Constraint (TOC)
                                                                                      OVERVIEW


                                                                           Throughput is based on satisfying
                                                                           customer demand.
                                                                           In order to achieve this, all
                                                                           manufacturing sites have to plan,
                                                                           source raw materials and
                                                                           components, manufacture, and
                                                                           finally deliver.
                                                                           The processes are governed by:
                                                                           • Inputs, raw materials
                                                                           components, money, etc.
                                                                           • Mechanisms (resources such as
                                                                           facilities, people, machines, etc.
                                                                           • Constraints: company policy,
                                                                           equipment constraints (capacity)
                                                                           • Outputs, semi finished, finished
                                                                           product.



                  THEORY OF CONSTRAINTS METHODOLY




By adopting the Theory of Constraint methodology/technique for the above
processes, throughput objectives can be achieved.
Value Chain




                                                  VALUE CHAIN

The value chain is based on system (facilities, human resources, manufacturing resources and IT systems) capability
and key constraints (Company policy, financial resources) to generate throughput.
The fundamental consideration is to maximize throughput with available resources and constraints.
Maximize Throughput Using TOC




                                                TOC METHODOLY

TOC Methodology is used to maximize throughput of the value chain.
TOC is not just only a methodology (not file 13) but also a strategic management approach that the organization will
apply.
Manufacturing Throughput
                                                                                 PURPOSE

                                                                    The key benefit of applying this
                                                                    methodology is that it provides
                                                                    purpose with respect to a
                                                                    fundamental optimization project.
                                                                    The tangible benefits are
                                                                    measurable and impact the
                                                                    profitability of the organization

                                                                    The TOC focus should be part of
                                                                    the tactical layer of the
                                                                    organization while the DBR focus
                                                                    should be part of the operational
                                                                    level.

                                                                    TOC is not once off; it becomes a
                                                                    way of life.
               THEORY OF CONSTRAINTS METHODOLY




The TOC methodology is supported by Drum, Buffer and Rope
(DBR) planning technique as well as buffer management in order to
achieve TOC objectives.
DBR is critical to ensure all is synchronized to the production
capacity of the Constrained Manufacturing resource.
Realizing Real Business Benefits
                  BACKGROUND TO MANUFACTURING SYSTEM IMPLEMENTATION
     Discussion Point                                   Features

1                          There are many situations whereby real business benefits where not achieved because
       BUSINESS            they were focused on IT. Extensive IT investment did not lead to bottom line benefit.
       BENEFITS



                           Some IT departments have underestimated the complexity, resulting a in a poorly built
2
                           solution. This is caused by both customer and partner; partner using low skilled resources.
      COMPLEXITY


                           In many cases project is governed by old habits and old ways of working, which might not
3
                           be ideal. This is a major problem with multi-national organizations where acquisitions
         HABITS
                           played a big role in building up their current organization.



4                         There are ample cases studies documenting project failure, finger pointed at vendor. This
    PROJECT FAILURE       normally is caused not so much by vendor but rather by poor project management by both
                          customer and consulting partner. Sometimes vendor over sells business benefits leading to
                          disappointments.


5                         In business we have many different methodologies for improvements, Business Process
       ACRONYMS           Re-engineering (BPR), Business Process Modeling (BPM), SCOR, etc. But do they actually
                          result in business benefit; is throughput and productivity increased?




                                                                                                                         9
What We’ll Cover …
•   Manufacturing throughput
•   Theory of Constraints (TOC) methodology
•   Explanation of Drum, Buffer, Rope (DBR) technique
•   A Theory of Constraint case study
•   Applying the Theory of Constraint technique within SAP
•   Applying the Theory of Constraint technique within SAP PPDS
•   Wrap-up




                                                                  10
Step 1: Identify the Constraint
                 KEY POINTS WITH RESPECT TO THEORY OF CONSTRAINED OPTIMIZATION TECHNIQUE

Find the one element of the manufacturing system which limits the system's ability to achieve its goal. In most manufacturing,
identify what limits the system performance.
Very important to consider that a process is governed by:
I; Input; components/raw materials
C; Control; policy, methods, shift, set-up requirements; tooling
M; Mechanism; the actual manufacturing machine that has a rated capacity
O: Output; the manufactured item (semi or finished product)
System constraints can be either physical or policy. Physical constraints are relatively easy to identify and relatively
straightforward to break. Policy constraints are usually more difficult to identify and break, but they normally result in a larger
degree of system improvement that the elimination of a physical constraint.




                                                                                              IDENTIFY THE
                                                                                               CONSTRAINT




                                                                                                                                      11
Step 2: Decide How to Exploit the Constraint
               KEY POINTS WITH RESPECT TO THEORY OF CONSTRAINED OPTIMIZATION TECHNIQUE

Understand how to exploit the constraint. That means squeezing the most out of the manufacturing constraint in order to
attain maximum performance. Therefore consider all aspects around the process:
•Policy and procedure
•Tooling, set-up equipment, set-up matrix
•Planning and execution system; ERP, APS, etc.
This must be done without major system changes or capital improvements with the primary objective of eliminating
inefficiency from the constraint



                                                                                    DECIDE HOW TO EXPLOIT
                                                                                       THE CONSTRAINT




                                                                                                                          12
Step 3: Subordinate Everything Else
               KEY POINTS WITH RESPECT TO THEORY OF CONSTRAINED OPTIMIZATION TECHNIQUE

Take the required steps to synchronize and align the performance of all other elements with the "exploited" constraining
element. This may mean slowing down "faster" parts and speeding up "slower" ones. If your constraint is broken at this point,
go back to Step 1 and start looking for the next constraint (next weakest link in the chain). If not, go on to Step 4.
Fundamentally make effective management of the existing constraint the top priority.

                                                                                SUBORDINATE EVERYTHING ELSE
                                                                                  TO THE DECISION IN STEP 2




                                                                                                                                13
Step 4: Elevate the Constraint
               KEY POINTS WITH RESPECT TO THEORY OF CONSTRAINED OPTIMIZATION TECHNIQUE

If the constraining element still remains the reason why the system's performance "tops out"; then “elevate" usually means doing
something to increase the capacity of the constraining element. Obviously, if your constraining element is running at maximum
efficiency (which it should be after Steps 2 & 3), the only way to improve overall system performance is to obtain more of the
constraining element. In a manufacturing environment, this may mean a capital investment in more equipment, or hiring more
people, or increasing working shifts.

                                                                                           ELEVATE THE CONSTRAINT




                                                                                                                                   14
Repeat Steps 1-4: Manage Inertia
               KEY POINTS WITH RESPECT TO THEORY OF CONSTRAINED OPTIMIZATION TECHNIQUE

This is the "repeat Steps 1-4" step. But the warning about "inertia" is important. It's designed to discourage complacency,
thinking that the environment doesn't ever change much over time. Always consider that throughput increase can create other
weaker links that previously were considered secondary.

                                                                        MANAGE INERTIA – GO BACK TO
                                                                            STEP 1 IF REQUIRED




                                                                                                                              15
Theory of Constraints: Summary
                           Typical Process
                                    The TOC methodology allows us to understand
                                    how throughput is generated.
                                    TOC also provides a clear direction on how to
                                    maximize/exploit resources and to
                                    synchronize/subordinate everything around the
                                    critical resources.
                                    TOC provides clear direction on leveraging IT
                                    systems.



                                               TOC PROCESS




IT System to support
above process
                                                                                16
What We’ll Cover …
•   Manufacturing throughput
•   Theory of Constraints (TOC) methodology
•   Explanation of Drum, Buffer, Rope (DBR) technique
•   A Theory of Constraint case study
•   Applying the Theory of Constraint technique within SAP
•   Applying the Theory of Constraint technique within SAP PPDS
•   Wrap-up




                                                                  17
Drum, Buffer, Rope (DBR) Technique
           SUBORDINATING EVERYTHING ELSE TO DECIDING HOW TO EXPLOIT THE CONSTRAINT


 When it comes to subordinating everything to a constraint, its bottlenecks. In a production environment, the
 plants constraint must be the driving factor in how it is managed. In production, the productivity of the
 constraint is the productivity of the entire plant.
 A proven approach to managing production through the constraint is known as "Drum-Buffer-Rope" and
 "Buffer Management."


  • Drum - The constraints, linked to market demand, is the drumbeat for the entire plant.
  • Buffer - Time/inventory that ensures that the constraint is protected from disturbances occurring in the
  system.
  • Rope - Material release is "tied" to the rate of the constraints.



  Drum, buffer, and rope provide the basis for building a production schedule that is highly immune to disruption,
  avoids creating excess inventory, and uses small batches to minimize overall lead time.
  But even with Drum-Buffer-Rope (DBR), occasional disruptions occur that require special attention. Buffer
  Management is used to mitigate and often prevent those disruptions.


 The DBR methodology is Theory of Constraints that will be used to maximize production throughput and
 inventory reduction based on the constraints (weakest link) being the Drum, the Buffer being the inventory
 needed for the constraint and the Rope the timing for releasing the buffer with the main aim of protecting the
 weakest link and thus maximizing overall effectiveness.




                                                                                                                     18
Drum, Buffer, Rope (DBR) Technique (cont.)
                                                  DBR EXPLANATION

          Raw Material                                                                           LEGEND
                                                                                    CCR Capacity Constrained Resource
                       Semi 1             Semi 2           Finished prod.

             WC 1                 WC2                   WC3                WC4
                                                       CCR

                                 Buffer
                                 Semi 2

                                 ROPE

       Drum. The CCR resource (work-centre 3)                         Rope: The release of raw materials scheduled to
 1
       determines the schedule                                  3     start production at work-centre 1 based on the
                                                                      schedule determined by the Drum.
 2     Buffer. Buffer to protect the CCR - Work-centre 3




In TOC, Subordinate everything else to the CCR Work-centre. This means synchronize all planning activities to
production rate (drum) of resource to ensure that the CCR does not stand ideal. The Buffer in front of the CCR will be the
safety margin. Therefore the planning and scheduling system must now satisfy the DBR requirements.




                                                                                                                             19
DBR Buffer Management
              Semi 2       DBR BUFFER MANAGEMENT


                                Finished prod.                               LEGEND
                                                                CCR Capacity Constrained Resource

        WC2                    WC3            WC4
                                                                              Buffer
                               CCR
                Buffer
                                 With DBR, it is critical to protect the CCR with buffer. By
                Semi 2
                                 doing what is supposed to be done in accordance with our
                         CCR     plan we protect the constraint and the system as a whole
 ROPE
                                 This buffer is needed so that CCR is not starved due to
                                 delays in production of input components.
                                 It strives to achieve the following:
                                 • Reliable due date performance
                                 • Effective exploitation of the constraint
                                 • Accurate system data for relevant role players.

                                             Buffer is introduced in front of CCR. This buffer
                                             is divided into 3 zones for expediting purposes.
                                             Red zone penetration was also included in KPI.
                                             The buffer zone helps to simplify exception
                                             management and it helps identify possible
                                             creeping CCR. The buffer zone concept was
                                             included in the monitor of CCR in SAP.
What We’ll Cover …
•   Manufacturing throughput
•   Theory of Constraints (TOC) methodology
•   Explanation of Drum, Buffer, Rope (DBR) technique
•   A Theory of Constraint case study
•   Applying the Theory of Constraint technique within SAP
•   Applying the Theory of Constraint technique within SAP PPDS
•   Wrap-up




                                                                  21
Overview
                                                PROJECT CONTEXT


1    Organization running at maximum capacity           2   Poor on-time delivery, high back-order qty


3    High level of Inventory                            4   Extensive IT expenditure with limited success

                                                                           Company in auto industry component
                                                                           supplier, supplies all makes, from low
                                                                           cost to sports cars.
                                                                           The manufacturing process consists of
                                                                           3 main stages:
                                                                           3.Input Semi finished 1
                                                                           4.Input Semi finished 2
                                                                           5.Finished product
                                                                           Both input semi finished 1 and 2 can be
                                                                           used for multiple finished products
                                                                           (product families)
                                                                           The work centre for finished product
                                                                           takes from 6-8 hours of set-up. Batch
                                                                           runs can run over multiple days.
                                                                           Multiple work-centre (machines) for
                                                                           finished product are available.
                                                                           Possible number of product code
                                                                           20000.
                                                                           Customer orders based on delivery
                                                                           schedule.

                                                                                                                22
TOC Five-Step Analysis
                                      PROJECT CONTEXT


                                                                   The analysis was based on the five
                                                                   TOC steps, primarily Steps 1, 2 and 3.

                                                                   The TOC project also provided an
                                                                   opportunity to find out what was going
                                                                   on in production and related areas.




   Project team was made up of manufacturing (Industrial engineers) experts (external) as well as
   SAP functional and technical consultants.
   Project sponsor Financial Manager; critical to avoid hiding problems and internal politics.
   Project based on 3 major steps:
  1. Analysis
  2. Design and build
  3. Implementation

  The deliverables for the analysis phase must be specific in order to allow quick and effective
  implementation. This was critical to avoid a paper exercise.




                                                                                                            23
Brief Summary
                                PLANNING & EXECUTION SYSTEM ANALYSIS
       Analysis                             Identification

1                          Current planning tool did not plan
                           production based on resource capacity
     Current               (finite scheduling).
     planning              In certain situations, scheduling was done
                           in the past.
                           Set-up date not realistic, not updated
                           regularly.
                           Incoming open purchase order did not
2 Raw material             reflect realistic dates, resulting in incorrect
    supplies               planning and poor expediting dates. In
                           certain instances, raw materials were not
                           consumed correctly.
3
                            In certain cases, non-CCR resources were
     Non CCR                overloaded due to poor planning. System
     overload               data did not match reality.
                            Shop floor data updated late (24 hours)
                            resulting in a poor view of downstream semi
                            finished production status.


        Note: During the analysis phase, there was a clear indication of paradigm constraint; locking the
        organization into poor performance due old established habits and lack of willingness to change.




                                                                                                            24
Identification

                            PLANNING & EXECUTION SYSTEM ANALYSIS
          Analysis                    Identification

                       No stability in planning, order changed at
4
                       last minute causing problems in semi-
    Production Order   finished products planning.
    changes & status   Recommendation to introduce frozen
                       period to ensure planning stability.
                       Too many open production orders, status
                       not managed correctly.

                       Due to high set-up (6-8 hours) manufacturing set
5                      large batch run resulting in high inventory.
                       Change this rule based on minimum duration
       Batch size      plus lot coverage. (i.e., average of next 8 weeks
                       of demand) and not on historical data.



                       Demand for semi finished product not planned correctly due to plant responsibility
6                      separate per product group, no common objective. Each department planned their
       Multi-level     machines to maximum capacity without considering global objective.
       planning        Department for semi finished planned to maximum capacity even without demand.
                       This resulted in overstock of semi finished and in certain cases no stock for finished
                       product where customer demand existed.




                                                                                                                25
Shop Floor Data Collection
                      PLANNING & EXECUTION SYSTEM ANALYSIS
         Analysis                   Identification
                       Too many forms, in certain cases forms filled in by operators were illegible. Approved
7
                       standardization of pre-printed forms with barcode with minimum data input. Also
                       agreed to introduce simple entry screens with limited default data.
    Shop Floor Data    Delay in input SFDC into system resulted in inaccurate data specifically around CCR.
      Collection




                                                                                                                26
Summary
                                         SUMMARY OF KEY CONSIDERATION


The analysis for the TOC steps identified a number of issues that covered:
2.     Company procedures
3.     Organization structure, responsibilities, and objectives
4.     Serious Production Planning and execution system weaknesses
5.     Poor shop floor control


This is why a TOC project is not just an IT project.

     Identify the constraint: We identified the key manufacturing constraints, specifically how they where planned,
1
     its set-up effort (tooling etc.), how semi-finished components where planned.


     Exploit the constraint: In order to elevate the constraints, company agreed to change organization structure
2    and responsibilities so that everything is focused around throughput. Departments to synchronize their
     planning based on CCR demand schedule. More effort to reduce set-up time of CCR and ensure accurate
     recording of set-up and tear-down. Set-up became a key KPI.


     Subordinate everything to constraining resource: Agreed to introduced DBR planning technique including
3
     buffer management within the SAP PP DS. Also agreed to introduce supermarket concept to some semi-
     finished products that where common to many subsequent semi-finished items.


     Elevate the constraint: In order to understand current CCR loading versus market demand, introduced SOP
4    (in APO) with simulation facility in order to provide marketing and production a tool to understand how to
     address additional market demand or reduction.


                                                                                                                      27
What We’ll Cover …
•   Manufacturing throughput
•   Theory of Constraints (TOC) methodology
•   Explanation of Drum, Buffer, Rope (DBR) technique
•   A Theory of Constraint case study
•   Applying the Theory of Constraint technique within SAP
•   Applying the Theory of Constraint technique within SAP PPDS
•   Wrap-up




                                                                  28
DBR Planning and Execution Options
                                          SAP PLANNING AND EXECUTION OPTIONS

In order to achieve throughput objectives,
SAP offers a number of planning and
execution solutions.
                                                                                                   The focus will be
All of these technically could be suitable, the
selection depends on the complexity of the
                                                                                                   on Scenario A and
manufacturing processes and related                                                                Scenario D
system relationships.
The following is available:
OPTION A
This is based on planning and execution
using SAP ERP MRP, capacity leveling, and
execution.
OPTION B
Planning in SAP ERP, scheduling in APO
PPDS and execution in ERP.
OPTION C
Planning run 1 and scheduling in APO
PPDS , then in ERP planning (MRP) of other
related aliments (components, bulk,
consumables) and execution in ERP.
OPTION D
Planning and scheduling only in PPDS and
execution in ERP.
OPTION E
This option utilizes CTM (Capable to match) in APO to plan for medium term horizon where planning is executed with
capacity constraints. This plan will create planned orders. These planned orders are then re-planned in short production
horizons including capacity leveling and detailed scheduling. These orders will be firmed production orders. The planned
order (CTM) and firmed production order will then be replicated into ERP which will form dependant demand for other
planning.
DBR Planning and Detailed Scheduling

                DBR PLANNING AND DETAILED SCHEDULING

     Control Point                        Features
                                                                                This section focuses on the
1                        •   Master Production Schedule Finished Product        SAP parts in order to
                         •   Capacity leveling                                  achieve TOC objectives and
    Finished Product     •   Order review and set-up optimization
        Planning                                                                apply the DBR planning
                         •   Multi-level ATP
                                                                                method.
                         •   Order release

                                                                                •Finished product input:
                         • Planning of semi finished 1 on released production   Semi Finished 2
2                          orders of finished product (Drum)
                                                                                •Semi finished 2 input: Semi
    Semi Finished 1:     • Review of results
                         • Semi finished level 3 linkage
                                                                                finished 3
       Level 2
                           (Raw materials ATP)                                  •Semi finished 3 input:
                                                                                Raw materials


3                        • Semi finished 2 planning
    Semi Finished 2:     • Buffer
       Level 3           • Raw materials planning




                                                                                                               30
DBR Planning Process

                    Deletion of
                   firmed order



                    CUSTOMER         MPS for                                                      FIRM PERIOD
                     ORDERS       Finished Items

  MPS Process
                                                      Review of       Planned Orders
                                                   planning results                       Creation of
                                                                                          Production
                                                                                            Orders



    DRUM
                                                                              Production Orders


                                                      This is only relevant for finished products:
                                   Short term
                                    capacity
                                                      Capacity leveling for the CCR work centre
                                    leveling
    Capacity                                          Capacity
                                                                             SCHEDULED ORDER AND DEP.REQUIR
    Leveling                                          Leveling
                                                      Review
                                                                           CYCLE 4: MID-TERM PLAN INCLUDING
                                                                           PLANNED ORDERS

                                                                             Medium term capacity
     JOB OR MANUAL                                                                 leveling
  EXECUTION OF PROGRAM




                                                                                                                31
DBR Planning Process (cont.)
                  MATERIAL MASTER DATA: 1 - 2                         ATTENTION POINTS

1
      Finished product MRP1 View: Transaction MM02
                                                                       The MRP type must be
                                                                       M0, which plans only MPS
                                                                       items.
                                                                       Executing MPS plans only
                                                                       items identified as MPS.




                                                                       The opening period is set
                                                                       to 5 days in order to allow
2                                                                      semi finished 2 lead time
    Verify the scheduling margin key in MRP2 View: Transaction MM02    and buffer. For slow
                                                                       moving items where there
                                                                       is no semi finished 3
                                                                       buffer, select key with 10
                                                                       days.
                                                                       The determination of the
                                                                       opening period is critical
                                                                       for confirming production


    Source: SAP



                                                                                                     32
Buffer Management
                   FINISHED PRODUCT PLANNING: BUFFER MANAGEMENT

   The time buffers are needed to protect the Master Schedule. This buffer is needed for any possible
   unexpected deviation to plan. The schedule of the CCR must be protected in order to maximize
   efficiency.


                                                     Buffer
This is the time buffer
assigned to Finished product.                           MPS
Therefore the end time of                                                      FINISHED GOODS
SEMI-FINISHED 2 must be:                                       MPS            (MPS DRUM-BEAT)
MPS Order start - Buffer
                                                                       MPS




The Semi Finished Input 2
Schedule may have
deviations within the buffer                                                       INPUT
zone without impacting the
MPS plan critical to protecting                        Red zone buffer         SEMI-FINISHED 2
the MPS plan at the CCR
                                                         penetration




                                                                                                        33
Bill of Material
                       BILL OF MATERIAL …                                   ATTENTION POINTS

    Verify the buffer between Finished Product and Input Semi Finished 2:
1
    Transaction CS02                                                        For the finished product, a
                                                                            buffer of 3 days is
                                                                            assigned against the input
                                                                            2 semi finished product.

                                                                            This buffer is used to
                                                                            determine the date Semi
                                                                            finished 2 should be ready
                                                                            by.




Source: SAP




                                                                                                          34
Work Centre Data
                        WORK CENTRE 1-3              ATTENTION POINTS

      Maintain Work-centre data : Transaction CR02
1                                                     Scheduling and Capacity
                                                      formulas are relevant only
                                                      for work centres that
                                                      require capacity loading.
                                                      Work centres of minor
                                                      importance do not require
                                                      this information.



                                                      Critical capacities require
                                                      shift data and relevant
                                                      calendar assigned.
                                                      Efficiency needs to be
                                                      assigned to capacity
                                                      utilization field.
                                                      Only work centres relevant
                                                      to capacity leveling (CCR)
                                                      require the finite
                                                      scheduling flag set.



    Source: SAP



                                                                                    35
Work Centre Data (cont.)
                                 WORK CENTRE 2-3                               ATTENTION POINTS

      Maintain Shift data. This is needed only if shift change occurs during
2     the week.                                                                 Shift detail must be
                                                                                inserted if the work centre
                                                                                has days whereby number
                                                                                of working hours differ,
                                                                                example Saturday and
                                                                                Sunday.




                                                                                Each shift has to have
                                                                                relevant efficiency.




    Source: SAP



                                                                                                              36
Work Centre Data (cont.)
                             WORK CENTRE 3-3                              ATTENTION POINTS

      Maintain grouping rules, this is the number of days we will group
3     orders for set-up optimization and is updated in classification      The value of 5 days means
                                                                           that for this work centre
                                                                           order with same
                                                                           characteristics will be
                                                                           grouped together. If there
                                                                           is no value then no
                                                                           grouping




    Source: SAP



                                                                                                        37
Routing
                  ROUTING CURRENT PROPOSAL 1:2   ATTENTION POINTS
                                                  Only one routing will be
1                                                 created.
       Verify the routing: Transaction CA02

                                                  The routing will be based
                                                  on:
                                                  Group counter number;
                                                  the smallest number is the
                                                  primary
                                                  Usage 1 production
                                                  Status 5 released


                                                  The routing will contain
2                                                 primary work centre
       Verify the operations
                                                  assigned to operation 0010
                                                  and alternate to 001X with
                                                  control key GL07 (alternate
                                                  work centre). Alternate
                                                  work centre will be
                                                  allocated to operation
                                                  001X where X is next
                                                  number, this is critical to
                                                  group alternate to primary

    Source: SAP



                                                                                38
Routing (cont.)
                              ROUTING 2-2                                           ATTENTION POINTS

3
      Verify the manufacturing grouping rules by viewing operation details:          The setup groups category
                                                                                     contains major grouping
                                                                                     category; example MPS 1
                                                                                     to 3.
                                                                                     The setup group key
                                                                                     contains manufacturing
                                                                                     characteristics such as
                                                                                     tooling , material, etc.


4     Verify the relationship of the above to the set-up matrix; transaction OPDA

                                                                                     The setup matrix contains
                                                                                     reduction rules with
                                                                                     respect to setup where
                                                                                     production orders are
                                                                                     grouped according to same
                                                                                     characteristics. The setup
                                                                                     in the set-up matrix
                                                                                     replaces the routing setup
                                                                                     data.



    Source: SAP



                                                                                                                  39
Master Production Scheduling
              MASTER PRODUCTION SCHEDULING …   ATTENTION POINTS
1     Review status of material: MD04
                                                Review current customer
                                                and production orders.

                                                Also review the exception
                                                messages generated by
                                                the system.

                                                Alternate view shows traffic
                                                lights which, in this case,
                                                indicate that orders need to
                                                be brought forward.




    Source: SAP



                                                                               40
Executing MPS
    EXCUTING MASTER PRODUCTION SCHEDULING…                     ATTENTION POINTS
1     Execute Master Production Schedule: Transaction MD40
                                                                Scheduling Parameter = 2
                                                                This means that dates will
                                                                be determined based on
                                                                routing data.
                                                                To plan single material use
                                                                transaction MD42




                                              Select execute


2     MPS generates log of material planned


                                                                MPS has planned only
                                                                Finished Products
                                                                identified as MPS items




    Source: SAP



                                                                                              41
Verifying MPS
VERIFICATION MASTER PRODUCTION SCHEDULING…                       ATTENTION POINTS
1     Verify result of MPS planning for Finished Product: MD04
                                                                  Planned Order for finished
                                                                  products created in the
                                                                  past as per MPS setting.
                                                                  This is critical for
                                                                  determining back-log
                                                                  priority.




                                                                  Planned order created as
                                                                  per lot size rule




    Source: SAP



                                                                                               42
Verifying MPS (cont.)
VERIFICATION MASTER PRODUCTION SCHEDULING…                         ATTENTION POINTS
2     Verify planned order details by selecting individual order
                                                                    Production dates are
                                                                    scheduled as per routing
                                                                    data.
                                                                    The opening date is based
                                                                    on start date minus 5 days
                                                                    as per scheduling margin
                                                                    key (working days).




3     Select Detailed Scheduling folder

                                                                    Scheduling has been
                                                                    executed on work centre
                                                                    Z451 based on work
                                                                    centre scheduling data.
                                                                    Capacity Requirements
                                                                    also generated on work
                                                                    centre


    Source: SAP



                                                                                                 43
Verifying MPS (cont.)
VERIFICATION MASTER PRODUCTION SCHEDULING…                         ATTENTION POINTS

4     Verify planned order details by selecting individual order
                                                                   In transaction MD04, from
                                                                   Environment, select
                                                                   capacity load to view
                                                                   capacity load on work-
                                                                   centre




                                                                   The capacity requirement
                                                                   versus available capacity
                                                                   determines the capacity
                                                                   load percentage. This view
                                                                   contains combined load,
                                                                   therefore all the products
                                                                   that were planned against
                                                                   this primary work centre.


    Source: SAP



                                                                                                44
Dynamic Order Fixing
                                      DYNAMIC ORDER FIXING



            Firm Drum Schedule                                                            NOT FIRMED




                                                                              FIRMED




                                                                  FIRMED



TODAY                                                  +5
                 FIRMING PERIOD

  1 The opening date is date used by planner to firm orders
  2 The opening date must allow for buffer time, semi finished 1 lead time
  3 The opening date logic can be SKU specific to allow for semi-finished 1 lead-time
  4 The planner will firm any planned order where the opening is ≤ today + 5 (flexible)
Order Fixing
                            ORDER FIXING: WIDE STRIP BUFFER
HOW TO MANAGE ORDER FIXING CONSIDERING THE LEAD TIME OF SEMI FINSIHED AND ENSURING
REALISTIC PLANNING DATA FOR FINISHED PRODUCT




                                                                              The Semi Finished 1 lead-time must be
                                                                              included in the opening period for
                                                                              firming. Semi finished 2 is excluded for
                                                                              where there is Kanban.


             Opening period logic is per material or can be assigned to MRP group



 OPENING PERIOD
Converting Planned Orders to Production Orders
    CONVERSION OF PLANNED ORDERS TO PRODUCTION ORDERS…                      ATTENTION POINTS
1     Planned orders are converted to production orders, transaction CO41
                                                                             Critical to select finished
                                                                             products according to
                                                                             opening date criteria.
                                                                             It is critical that Finished
                                                                             Products are firmed up to
                                                                             allow production of Semi
                                                                             Finished 1 and for where
                                                                             there is no Semi Finished 2
                                                                             buffer (Kanban,
                                                                             supermarket)

                                                                             The opening date should
                                                                             be today plus 5 days




                                                                             List of orders that planner
                                                                             should convert to
                                                                             Production order are
                                                                             proposed




    Source: SAP



                                                                                                            47
Converting Planned Orders to Production Orders (cont.)
      CONVERSION OF PLANNED ORDER TO PRODUCTION ORDERS…   ATTENTION POINTS

2     Selection of routing
                                                          User must select relevant
                                                          routing.
                                                          NOTE: this is only relevant
                                                          if alternate routings are
                                                          managed




3     View Production Orders




                                                          Production orders are now
                                                          created for planned orders
                                                          that fall within planning
                                                          horizon of 5-7 days




    Source: SAP



                                                                                        48
Capacity Planning Overview
                                 CAPACITY PLANNING OVERVIEW…


     Control Point                                         Features
                     • The purpose of Capacity Planning is to schedule orders as per defined sequence
1
                       within capacity constraints of a work centre. (Technical name is Dispatching).
        Purpose      • To carry-out set-up optimization for orders that have same characteristics
                     • To update orders once scheduled with relevant start and end date
                     • Allows user to modify production orders; priority, production version


2                    • Consists of:
                          • A work centre view
       Structure          • Scheduled order (dispatched)
                          • Orders to be scheduled


3                    • Capacity planning is controlled by profiles.
        Control      • Each profile determines how capacity should be scheduled, how orders are viewed
       elements        and information provided
                     • Consists of a scheduling strategy that determines how orders are scheduled



4                    • Has links to:
          Links           • Production order header
                          • Production operation
                          • Work centre data
    Source: SAP

                                                                                                         49
Capacity Planning
                EXPLANATION OF CAPACITY PLANNING




                                                   1
                                                   Work centre view and
                                                   scheduled production
                                                          orders



                                                   2
                                                       Material / Production
                                                       orders view showing
                                                         order dispatched




                                                   3
                                                       Production orders to
                                                          be dispatched




Source: SAP



                                                                               50
Viewing Capacity Load
                    VIEW OF CAPACITY LOAD   ATTENTION POINTS
1     View the capacity load



                                             This shows percentage
                                             load. Overload is shown in
                                             red.




    Source: SAP



                                                                          51
Viewing Capacity Load (cont.)
                    VIEW OF CAPACITY LOAD                           ATTENTION POINTS
2     View the details of the loading capacity details for period
                                                                     Selecting the individual row
                                                                     shows the actual
                                                                     production orders.

                                                                     It is possible to show
                                                                     graphic view of load and
                                                                     available capacity.




    Source: SAP



                                                                                                    52
Capacity Leveling
              CAPACITY LEVELING: MPS CYCLE                                ATTENTION POINTS
1     Execute capacity leveling to check back-log and re-schedule where
      required. Transaction CM25, select Profile A_XX.


                                                                           View Change time profile
                                                                           to see dates used




                                                                           Capacity leveling considers
                                                                           orders in the last 30 days.
                                                                           This is critical to show back
                                                                           log.




    Source: SAP



                                                                                                           53
Capacity Leveling (cont.)

               CAPACITY LEVELING: MPS CYCLE                                           ATTENTION POINTS
       First action is to prioritize any backlog production orders, this way system
2                                                                                      Select orders to determine
       will schedule these first and will ignore grouping rules.
                                                                                       if really in backlog (could
       Select row production order.                                                    be delay in updating
                                                                                       system). It is critical that
                                                                                       real back-log orders are re-
                                                                                       scheduled to ensure
                                                                                       correct loading of work-
                                                                                       centre. Orders in back-log
                                                                                       are prioritized by assigning
                                                                                       priority


    Then select                                                                        The table shows key
                                                                                       sequencing data:
                                                                                       Priority
                                                                                       Group category
                                                                                       Group Key
                                                                                       Latest Start date




                                                                    Source: SAP



                                                                                                                      54
Capacity Leveling (cont.)
                  CAPACITY LEVELING MPS CYCLE          ATTENTION POINTS
3     View Planning results with transaction MD04



                                                       Production orders
                                                       rescheduled.
                                                       Orders are not scheduled
                                                       in the past. The std SAP
                                                       message will provide
                                                       relevant messages to user


4     Re-check load on work centre, transaction CM01




                                                       No overload with respect to
                                                       capacity




    Source: SAP



                                                                                     55
Capacity Leveling (cont.)

              CAPACITY LEVELING: MPS CYCLE   ATTENTION POINTS
5     View the GANTT chart details
                                             The GANTT chart at work
                                             centre view provides the
                                             following data:
                                             Production Order number
                                             Material description
                                             Set-up in blue
                                             Execution time in red




                                             The order view shows as
                                             same GANTT as work
                                             centre view, but detailed by
                                             order number




    Source: SAP



                                                                            56
Capacity Leveling (cont.)

              CAPACITY LEVELING: MPS CYCLE           ATTENTION POINTS
6     View the impact of changing production order
                                                      The system automatically
                                                      re-schedules order
                                                      according to set-up time
                                                      and execution time defined
                                                      in routing for alternate
                                                      capacity

                                                      It will automatically change
                                                      the group category and
                                                      group key with what was
                                                      defined in alternate
                                                      routing.

                                                      Note: Just changing the
                                                      work centre does not re-
                                                      determine operation data
                                                      such as set-up, execution,
                                                      and grouping




    Source: SAP



                                                                                     57
Capacity Leveling (cont.)
      CAPACITY LEVELING: SET-UP OPTIMIZATION                                 ATTENTION POINTS
1
      Carry-out set-up optimization. Transaction CM25 select Profile
      A_BUMAN03.




                                                             Select orders




                                                                              Note the set-up group
                                                                              category and set-up key.
                                                                              These two conditions are
                                                                              used for optimization.




    Source: SAP



                                                                                                         58
Capacity Leveling (cont.)
      CAPACITY LEVELING: SET-UP OPTIMIZATION               ATTENTION POINTS
2     Carry-out optimization by selecting from menu

                                                            The system will
                                                            automatically replace set-
                                                            up time as per matrix


                                                    Save



3    Re-enter with same profile to display result




                                                            The set-up optimization
                                                            considers the set-up group
                                                            category and
                                                            Set-up group key




    Source: SAP



                                                                                         59
Capacity Leveling (cont.)
      CAPACITY LEVELING: SET-UP OPTIMIZATION   ATTENTION POINTS
4     View the GANTT chart details



                                                These production orders
                                                have their set-up reduced
                                                as per matrix.




5     View operation details


                                                Operation data
                                                automatically updated.

                                                Production orders modified
                                                automatically




    Source: SAP



                                                                             60
Modifying the Order
                        MODIFICATION TO ORDER                                             ATTENTION POINTS
1     On a regular basis, the planner will have to re-plan order specifically for back-
      log or priorities. Assign priority to backlog orders.
      STEP 1: Verify scheduling Transaction CM25 Profile A_BUMAN04 (Order view)            Planning must be aligned
                                                                                           with current date;
                                                                                           therefore, all orders in
                                                                                           back-log must be re-
                                                                                           scheduled accordingly.
                                                                                           Therefore user must:
                                                                                           Change priority of
                                                                                           backlog order operation to
                                                                                           1 in sequence number field
                                                                                           De-allocate orders

    Select row and click orders
                                                                                           Once we have done this
                                                                                           and we re-schedule, it will
                                                                                           sort in capacity leveling
                                                                                           according to:
                                                                                           1 Sequence Number
    Click on                                                                               2 Group Category
                                                                                           3 Group Key
    Insert value 2 in                                                                      4 Start Date
    priority

    Source: SAP



                                                                                                                         61
Modifying the Order (cont.)
                       MODIFICATION TO ORDER                                      ATTENTION POINTS
2     Carry-out rescheduling of orders.

      STEP 2: Verify scheduling Transaction CM25 Profile A_BUMAN04 (Order view)




                                                                                   The user manually
                                                                                   dispatches the order by
                                                                                   using drag and drop
                                                                                   functionality.

                                                                                   The order will be
                                                                                   dispatched exactly as
                                                                                   requested by planner.




    Source: SAP



                                                                                                             62
Modifying the Order (cont.)
                       MODIFICATION TO ORDER      ATTENTION POINTS
3     Manual Maintenance of Production Order.

      Transaction CO02, change production order
                                                   Changes to order dates
                                                   can be carried-out only if
                                                   order is de-allocated.

                                                   Qty changes require re-
                                                   scheduling as well as
                                                   manual dates changes.

                                                   The re-scheduling will then
                                                   require capacity leveling
    Select menu ‘Functions’


    Change Scheduling to
    forwards and then insert
    new Start date



    Then select re-
    schedule

    Source: SAP



                                                                                 63
The Role of the Drum

The scheduling of the Drum
based on CCR accurately
determines the start and finish
time. The start date minus the      BUFFER
buffer determines the end time in
which preceding semi finished 1
must be finished. The buffer is
like a shock absorber.
                                             START TIME
The CCR determines the Drum.                              END TIME
In this case, the CCR is
responsible for finished product.
The scheduling of the CCR exact
start and finish time, including
set-up, determines the
dependant demand on the semi
finished 1 and related
components. The semi-finished 1
is planned to include a buffer to
protect the CCR.
The Drum also provides release
date (ROPE) for the raw
materials.

                                                                     64
Finished Strip Linkage
                     SEMI FINISHED 2 LINKAGE                         ATTENTION POINTS
1     MPS on Finished product only creates Dependant Requirements.
      Use transaction MD04 to show status on Semi Finished 1
                                                                      MPS on the Finished
                                                                      product has only
                                                                      generated dependant
                                                                      demand and has not
                                                                      executed any planning on
                                                                      semi finished 1.

                                                                      MPR will be generated
                                                                      continuously re-creating
                                                                      planned orders as per
                                                                      requirements.

                                                                      Demand is classified as
                                                                      follows:
                                                                      1 OrdRes is based on FP
                                                                      Production Order
                                                                      2 DepReq is based on FP
                                                                      planned orders




    Source: SAP



                                                                                                 65
Semi-Finished 1 Missing Parts List
              SEMI FINSIHED 1 MISSING PARTS LIST    ATTENTION POINTS
1
      Review Missing Parts List; Transaction CO24    Updated automatically
                                                     when releasing Production
                                                     Order of Semi finished 1.




                                                     The Requirement qty is
                                                     based on the production
                                                     order demand.

                                                     Committed qty is what is
                                                     currently available or
                                                     planned (production
                                                     Orders) to satisfy demand.

                                                     The missing parts info
                                                     system is updated every
                                                     time ATP is executed


    Source: SAP



                                                                                  66
Semi-Finished 1 Missing Parts List (cont.)
              SEMI FINSIHED 1 MISSING PARTS LIST   ATTENTION POINTS
2     Review Production Order
                                                    The production order for
                                                    the Finished Product
                                                    contains the details of the
                                                    Semi finished 1.



                                                   Reservation is assigned to
                                                   Semi finished 1.

                                                   Reservation is only
                                                   relevant for Production
                                                   Orders created for Semi
                                                   finished 1.




                                                    Committed qty is zero. This
                                                    is based on ATP check.




    Source: SAP



                                                                                  67
Semi-Finished 1 Missing Parts List (cont.)
              SEMI FINISHED 1 MISSING PARTS LIST   ATTENTION POINTS
3     ATP Check
                                                    The confirmed qty is
                                                    available to satisfy the
                                                    order.
                                                    The confirmed qty is based
                                                    on production orders
                                                    created for Semi Finished
                                                    1.

                                                    In this example, there is
                                                    nothing confirmed to
                                                    satisfy demand.




                                                    The check rule considers
                                                    only Production Orders.




    Source: SAP



                                                                                 68
Semi-Finished 1 MRP
                        SEMI FINISHED 1 MRP              ATTENTION POINTS
1     Verify Semi Finished 1 Status, Transaction MD04.

                                                          The Semi Finished 1
                                                          should have grouping rules
                                                          .
                                                          Example group 3 days
                                                          demand.




    Source: SAP



                                                                                       69
Semi-Finished 1 MRP (cont.)
                       SEMI FINISHED 1 MRP    ATTENTION POINTS
2     Review Master Data, Transaction MM02.
                                               Lot size rule and minimum
                                               lot qty. Groups 3 days
                                               demand for Finished
                                               products.




                                              Lead-time.

                                              Scheduling Margin Key
                                              has opening period of 2
                                              days.




    Source: SAP



                                                                           70
Semi-Finished 1 MRP (cont.)
                   Semi SEMI FINISHED 1 MRP   ATTENTION POINTS
3     Execute MRP, Transaction MD02.


                                               Orders will be created as
                                               per material master lead
                                               time. No capacity load
                                               generated.




                                               Planned Orders created in
                                               the past.




    Source: SAP



                                                                           71
Semi-Finished 1 MRP (cont.)
                        SEMI FINISHED 1 MRP              ATTENTION POINTS
4     Convert production Order single Order from MD04.



                                                          Start and end as per lead
                                                          time (working days as per
                                                          plant calendar).




                                                          Production Order is not
                                                          allowed to be created in
                                                          the past. This is critical for
                                                          a realistic ATP for the
                                                          Finished Product.




    Source: SAP



                                                                                           72
Creating Production Order for Semi-Finished 1
PRODUCTION ORDER CREATION FOR SEMI FINISHED 1                          ATTENTION POINTS
1     Convert planned Order to Production Orders, Transaction CO41 .




                                                                        Firm up one week’s orders.




                                                                        All planned orders within
                                                                        selected period are
                                                                        converted.




    Source: SAP



                                                                                                     73
Refresh Semi-Finished 1 Product Status
     REFRESH OF SEMI FINISHED 1 PRODUCT STATUS   ATTENTION POINTS
1     Run ATP, transaction COMAC.


                                                  The finished Strip should
                                                  have grouping rules.
                                                  Example group 3 days
                                                  demand.




                                                  Finished product order is
                                                  confirmed with planned
                                                  production orders.




    Source: SAP



                                                                              74
Refresh Semi-Finished 1 Product Status (cont.)
     REFRESH OF SEMI FINISHED 1 PRODUCT STATUS         ATTENTION POINTS
2     Re-check Missing parts list, Transaction CO24.




                                                        Before




                                                        Reservation is gone from
                                                        list indicating that Finished
                                                        Product production order
                                                        can be satisfied with order.




    Source: SAP



                                                                                        75
Refresh Semi-Finished 1 Product Status (cont.)
      REFRESH OF SEMI FINISHED 1 PRODUCT STATUS               ATTENTION POINTS
3     Recheck process chain with transaction CM25.
                                                               This confirms that Finished
                                                               product production order is
                                                               protected in terms of
                                                               Fished Strip planning.

                                                               Zero delay is expected
                                                               Receipt qty exceeds
                                                               demand


    Source: SAP




                     This concludes the planning of the Drum and how the
                     Drum scheduling requirements are transferred to Semi-
                     Finished 1 with the required buffer.


                                                                                             76
What We’ll Cover …
•   Manufacturing throughput
•   Theory of Constraints (TOC) methodology
•   Explanation of Drum, Buffer, Rope (DBR) technique
•   A Theory of Constraint case study
•   Applying the Theory of Constraint technique within SAP
•   Applying the Theory of Constraint technique within SAP PPDS
•   Wrap-up




                                                                  77
Master Data Objects: Product Master
                             MASTER DATA OBJECTS
1   Product master                 The product master is replicated to PPDS using the CIF. PPDS
                                   enables you to assign unique heuristic.
                                   A custom heuristic could be created to replicate the MPS logic,
                                   so that finished products are planned first on CCR and the sub-
                                   components are planned accordingly.




2   Work-centre; Resources




                                                Work centres are replicated to PPDS as
                                                resources. From a production perspective they
                                                will be time-continuous. CCR resource will be
                                                flagged as bottleneck resource.



                                                   Source: SAP
Master Data Objects: Work Center (cont.)
                                             MASTER DATA OBJECTS
2    Work centre; Resources

    The following resource types will be replicated:
    • Single activity resource; therefore only one production order may generate requirements.
    • Multi-mixed resource; multiple production order may generate requirements.
    • Mixed resources; these resources can be used in both PPDS and SNP. Using SNP is critical to get a medium term view
    for production specifically to determine if the CCR capacity is absorbing expected demand; if current shift policy has to
    be changed. SNP also enables you to carry out simulation in different versions and models.

                                                                    Critical considerations regarding scheduling and
                                                                    capacity:
                                                                    • CCR that determines the throughput of the
                                                                    manufacturing plant will be flagged as bottleneck
                                                                    resource.
                                                                    • Secondary critical resource can be flagged as
                                                                    Finite leveling.
                                                                    • The finiteness level is critical to group resources
                                                                    together. This grouping can be run in a separate
                                                                    heuristic step.
                                                                    • The resources that have specific finiteness level
                                                                    can have unique strategy profile. This is critical for
                                                                    DBR when it comes to synchronizing with the
                                                                    CCR resource.
                                                                    Note: resources that are not flagged as finite are
                                                                    planned infinitely. The alert monitor will provide
                                                                    overload for these resources. Critical for Buffer
                                                                    Management.
     Source: SAP
Master Data Objects: Work Center (cont.)
                                 MASTER DATA OBJECTS
2   Work-centre; Resources

                                       Critical consideration for the resource that have finiteness
                                       specific setting
                                       • Scheduling model
                                       • Planning direction
                                       The above is critical to have a streamlined scheduling on
                                       resources.




    Work-centre; CCR Resources         The CCR resource flagged as bottleneck resources are
                                       scheduled using mid-point scheduling. A second step
                                       plans the remaining resources that have their unique
                                       scheduling mode and planning direction.




    Source: SAP
Master Data Objects: Routing
                                           MASTER DATA OBJECTS
3    Routing; PPM /PDS

    Routings are replicated as either PPM or PDS. For a DBR project consider the following:
    • Change management: In PPM there is no change mgt. Changes take effect immediately.
    • Modification in the PPDS system. PDS do not allow changes, therefore all changes have to be managed in routing in
    ECC and replicated.
    From a DBR project perspective, PPM provides the most flexibility.
    Note: PPM/PDS are not needed if planning option is plan with MRP in ERP and scheduling in PPDS




     Source: SAP
Master Data Objects: Setup Matrix
                                            MASTER DATA OBJECTS
4    Setup Matrix

    For CCR where setup plays an important role, the sequence dependant setup and setup costs are fundamental in
    reducing setup time. Reducing setup is fundamental in elevating CCR output. The setup matrix will be used with the
    PPDS optimizer. The purpose of the optimizer is to determine ideal sequence dependant operation taking into
    consideration cost, penalty, delay, etc. Therefore, optimization with reason.




     Source: SAP
Planning Considerations
                                          PLANNING CONSIDERATION
    In order to introduce DBR planning technique in PPDS the following aspects are to be considered:

1    Master data,              Resource types need to be replicated correctly (single, multi, mixed).
      resource,                Resources (CCR) that impact throughput need to be correctly indentified. Related
                               secondary resources that can creep to CCR need also to be identified with assigned
     product and               finiteness level.
        PPM                    PPM (routing) needs to be accurate ; execution times and setup time must be accurate.
                               Setup matrix to be included where set-up plays a big role in CCR.



2                              Important to define relevant heuristics and strategy profile for detail scheduling in order to
                               ensure an accurate and realistic production plan that tries to achieve maximum
 Heuristics and                throughput on the CCR.
strategy profiles

                               Set up an ideal planning cycle that plans the Drum at the CCR by means of finite
3      Planning                planning, include planning steps to synchronize related planning sub-assembly and
                               components to satisfy the Drum schedule. Monitor alerts regarding resource loading on
         Cycle                 non CCR.


                                Set up buffer parameters; this can be set up by product family; use material group; grouping
4      Buffer                   such as components, semi-finished, and finished in grouping. In each group, define buffer
                                parameters.
     management


                                                                                                                                83
Planning Sequence Steps
                                    PLANNING SEQUENCE STEPS
  1 Stage Numbering
                        SAP_PP_020
   Algorithm: To
  determine low level
  code
                                      SAP_MRP_001

                    2 Material Requirement                   Infinite planning; planning object PRODUCT
                    Planning; product
                    Heuristic; finished, sub-
                    assemble and components
                                                        SAP001
                                                                             Function; Optimization of CCR
                                                                             resources in Detailed Scheduling
 Source: SAP                        3 Optimization of CCR                    Planning Board. Defines the Drum for
                                                                             CCR


                                                     4 Propagation & delays of            Re-plan based on
                                                     components; re-schedule              confirmed Drum
                                                     bottom up.



                                                                       5 Review overloads Detailed
In APO PPDS, it is easy to construct the
                                                                       Scheduling Planning Board on
automatic production planning process with                             non CCR, review buffer
 several steps. The individual steps are                               penetration
simply specified in the planning run.
Production Optimization Using TOC
Production Optimization Using TOC
Production Optimization Using TOC
Production Optimization Using TOC
Production Optimization Using TOC
Production Optimization Using TOC
Production Optimization Using TOC
Production Optimization Using TOC
Production Optimization Using TOC
Production Optimization Using TOC
Production Optimization Using TOC
Production Optimization Using TOC
Production Optimization Using TOC
Production Optimization Using TOC

More Related Content

What's hot

Root Cause Failure Analysis Methods for Pump Failures
Root Cause Failure Analysis Methods for Pump FailuresRoot Cause Failure Analysis Methods for Pump Failures
Root Cause Failure Analysis Methods for Pump FailuresAbdulrahman Alkhowaiter
 
Second Genetic algorithm and Job-shop scheduling presentation
Second Genetic algorithm and Job-shop scheduling presentationSecond Genetic algorithm and Job-shop scheduling presentation
Second Genetic algorithm and Job-shop scheduling presentationAccenture
 
Healthcare Kaizen Webinar Mark Graban Gemba Academy Dec 2011
Healthcare Kaizen Webinar Mark Graban Gemba Academy Dec 2011Healthcare Kaizen Webinar Mark Graban Gemba Academy Dec 2011
Healthcare Kaizen Webinar Mark Graban Gemba Academy Dec 2011Mark Graban
 
1.1 Work study and method study -Industrial Engineering Basics
1.1 Work study and method study -Industrial Engineering Basics1.1 Work study and method study -Industrial Engineering Basics
1.1 Work study and method study -Industrial Engineering BasicsDr. Surya Prakash
 
just in time manufacturing
just in time manufacturingjust in time manufacturing
just in time manufacturingravindra sharma
 
Rsb d 45-draw_frames_brochure_2287-v2_fr__32848
Rsb d 45-draw_frames_brochure_2287-v2_fr__32848Rsb d 45-draw_frames_brochure_2287-v2_fr__32848
Rsb d 45-draw_frames_brochure_2287-v2_fr__32848youssefzini
 
BASIC OF TOYOTA PRODUCTION SYSTEM
BASIC OF TOYOTA PRODUCTION SYSTEMBASIC OF TOYOTA PRODUCTION SYSTEM
BASIC OF TOYOTA PRODUCTION SYSTEMPrashant thakur
 
Connecting Kata with Hoshin Kanri and True North
Connecting Kata with Hoshin Kanri and True NorthConnecting Kata with Hoshin Kanri and True North
Connecting Kata with Hoshin Kanri and True NorthW3 Group Canada Inc.
 

What's hot (14)

Root Cause Failure Analysis Methods for Pump Failures
Root Cause Failure Analysis Methods for Pump FailuresRoot Cause Failure Analysis Methods for Pump Failures
Root Cause Failure Analysis Methods for Pump Failures
 
TPM: Focused Improvement (Kobetsu Kaizen)
TPM: Focused Improvement (Kobetsu Kaizen)TPM: Focused Improvement (Kobetsu Kaizen)
TPM: Focused Improvement (Kobetsu Kaizen)
 
Just in time
Just in timeJust in time
Just in time
 
Second Genetic algorithm and Job-shop scheduling presentation
Second Genetic algorithm and Job-shop scheduling presentationSecond Genetic algorithm and Job-shop scheduling presentation
Second Genetic algorithm and Job-shop scheduling presentation
 
Healthcare Kaizen Webinar Mark Graban Gemba Academy Dec 2011
Healthcare Kaizen Webinar Mark Graban Gemba Academy Dec 2011Healthcare Kaizen Webinar Mark Graban Gemba Academy Dec 2011
Healthcare Kaizen Webinar Mark Graban Gemba Academy Dec 2011
 
Kanban Pull System
Kanban Pull SystemKanban Pull System
Kanban Pull System
 
1.1 Work study and method study -Industrial Engineering Basics
1.1 Work study and method study -Industrial Engineering Basics1.1 Work study and method study -Industrial Engineering Basics
1.1 Work study and method study -Industrial Engineering Basics
 
just in time manufacturing
just in time manufacturingjust in time manufacturing
just in time manufacturing
 
Rsb d 45-draw_frames_brochure_2287-v2_fr__32848
Rsb d 45-draw_frames_brochure_2287-v2_fr__32848Rsb d 45-draw_frames_brochure_2287-v2_fr__32848
Rsb d 45-draw_frames_brochure_2287-v2_fr__32848
 
Lean Six Sigma Projects
Lean Six Sigma ProjectsLean Six Sigma Projects
Lean Six Sigma Projects
 
BASIC OF TOYOTA PRODUCTION SYSTEM
BASIC OF TOYOTA PRODUCTION SYSTEMBASIC OF TOYOTA PRODUCTION SYSTEM
BASIC OF TOYOTA PRODUCTION SYSTEM
 
El Pivot Pragmatico
El Pivot PragmaticoEl Pivot Pragmatico
El Pivot Pragmatico
 
Connecting Kata with Hoshin Kanri and True North
Connecting Kata with Hoshin Kanri and True NorthConnecting Kata with Hoshin Kanri and True North
Connecting Kata with Hoshin Kanri and True North
 
Leading using the Oobeya Room
Leading using the Oobeya RoomLeading using the Oobeya Room
Leading using the Oobeya Room
 

Viewers also liked

Theory of Constraints
Theory of ConstraintsTheory of Constraints
Theory of ConstraintsBonnie Aumann
 
TLS - TOC Lean Six Sigma - English 40 slides 2013
TLS - TOC Lean Six Sigma - English 40 slides 2013TLS - TOC Lean Six Sigma - English 40 slides 2013
TLS - TOC Lean Six Sigma - English 40 slides 2013MARRIS Consulting
 
Making the most of your constrained resources optimizing resource allocation ...
Making the most of your constrained resources optimizing resource allocation ...Making the most of your constrained resources optimizing resource allocation ...
Making the most of your constrained resources optimizing resource allocation ...Productivity Intelligence Institute
 
Just in time manufacturing ppt
Just in time manufacturing pptJust in time manufacturing ppt
Just in time manufacturing pptSwati Luthra
 
Basics of SAP for noobs (dummies)
Basics of SAP for noobs (dummies)Basics of SAP for noobs (dummies)
Basics of SAP for noobs (dummies)vins049
 

Viewers also liked (6)

Theory of Constraints
Theory of ConstraintsTheory of Constraints
Theory of Constraints
 
PRODUCT AND SERVICE DESIGN
 PRODUCT AND SERVICE DESIGN  PRODUCT AND SERVICE DESIGN
PRODUCT AND SERVICE DESIGN
 
TLS - TOC Lean Six Sigma - English 40 slides 2013
TLS - TOC Lean Six Sigma - English 40 slides 2013TLS - TOC Lean Six Sigma - English 40 slides 2013
TLS - TOC Lean Six Sigma - English 40 slides 2013
 
Making the most of your constrained resources optimizing resource allocation ...
Making the most of your constrained resources optimizing resource allocation ...Making the most of your constrained resources optimizing resource allocation ...
Making the most of your constrained resources optimizing resource allocation ...
 
Just in time manufacturing ppt
Just in time manufacturing pptJust in time manufacturing ppt
Just in time manufacturing ppt
 
Basics of SAP for noobs (dummies)
Basics of SAP for noobs (dummies)Basics of SAP for noobs (dummies)
Basics of SAP for noobs (dummies)
 

Similar to Production Optimization Using TOC

Improving business performance through the recession: Are your HR systems fit...
Improving business performance through the recession: Are your HR systems fit...Improving business performance through the recession: Are your HR systems fit...
Improving business performance through the recession: Are your HR systems fit...Softworld
 
Toc vs abc
Toc vs abcToc vs abc
Toc vs abcwphethi
 
Continuous improvement methods summary by the sig rev052914
Continuous improvement methods summary by the sig rev052914Continuous improvement methods summary by the sig rev052914
Continuous improvement methods summary by the sig rev052914Richard Platt
 
Insorce Presentation
Insorce PresentationInsorce Presentation
Insorce PresentationShammik Gupta
 
Flevy.com - Cost Drivers Analysis
Flevy.com - Cost Drivers AnalysisFlevy.com - Cost Drivers Analysis
Flevy.com - Cost Drivers AnalysisDavid Tracy
 
Theory of Constraints – A Review
Theory of Constraints – A ReviewTheory of Constraints – A Review
Theory of Constraints – A ReviewIJMERJOURNAL
 
Measuring the Results of your Agile Adoption
Measuring the Results of your Agile AdoptionMeasuring the Results of your Agile Adoption
Measuring the Results of your Agile AdoptionSoftware Guru
 
Value Chain Transformation
Value Chain TransformationValue Chain Transformation
Value Chain TransformationSteven Bonacorsi
 
Continuous Auditing D.French
Continuous Auditing D.FrenchContinuous Auditing D.French
Continuous Auditing D.FrenchDan French
 
Sourcing lecture 1 ITSM class
Sourcing lecture 1 ITSM classSourcing lecture 1 ITSM class
Sourcing lecture 1 ITSM classFrank Willems
 
1 day workshop managing manufacturing organizations - the toc way
1 day workshop   managing manufacturing organizations - the toc way1 day workshop   managing manufacturing organizations - the toc way
1 day workshop managing manufacturing organizations - the toc wayShridhar Lolla
 
Mark johnson business model transformation
Mark johnson   business model transformationMark johnson   business model transformation
Mark johnson business model transformationifmaworld
 
Radically increase your process and project throughput with the theory of con...
Radically increase your process and project throughput with the theory of con...Radically increase your process and project throughput with the theory of con...
Radically increase your process and project throughput with the theory of con...Jonathan Sapir
 
10%2 D04%20 Art%20 Bp%20 Maturity%20 Model%20%2 D%20 Fisher%2 Epdf
10%2 D04%20 Art%20 Bp%20 Maturity%20 Model%20%2 D%20 Fisher%2 Epdf10%2 D04%20 Art%20 Bp%20 Maturity%20 Model%20%2 D%20 Fisher%2 Epdf
10%2 D04%20 Art%20 Bp%20 Maturity%20 Model%20%2 D%20 Fisher%2 Epdfshinikju
 
Ensuring maximum return on HR technology investment
Ensuring maximum return on HR technology investmentEnsuring maximum return on HR technology investment
Ensuring maximum return on HR technology investmentSoftworld
 

Similar to Production Optimization Using TOC (20)

Improving business performance through the recession: Are your HR systems fit...
Improving business performance through the recession: Are your HR systems fit...Improving business performance through the recession: Are your HR systems fit...
Improving business performance through the recession: Are your HR systems fit...
 
Unit viii
Unit viiiUnit viii
Unit viii
 
Unit viii
Unit viiiUnit viii
Unit viii
 
Toc vs abc
Toc vs abcToc vs abc
Toc vs abc
 
Continuous improvement methods summary by the sig rev052914
Continuous improvement methods summary by the sig rev052914Continuous improvement methods summary by the sig rev052914
Continuous improvement methods summary by the sig rev052914
 
Insorce Presentation
Insorce PresentationInsorce Presentation
Insorce Presentation
 
Toc Sample
Toc SampleToc Sample
Toc Sample
 
Flevy.com - Cost Drivers Analysis
Flevy.com - Cost Drivers AnalysisFlevy.com - Cost Drivers Analysis
Flevy.com - Cost Drivers Analysis
 
Theory of Constraints – A Review
Theory of Constraints – A ReviewTheory of Constraints – A Review
Theory of Constraints – A Review
 
Measuring the Results of your Agile Adoption
Measuring the Results of your Agile AdoptionMeasuring the Results of your Agile Adoption
Measuring the Results of your Agile Adoption
 
Value Chain Transformation
Value Chain TransformationValue Chain Transformation
Value Chain Transformation
 
Continuous Auditing D.French
Continuous Auditing D.FrenchContinuous Auditing D.French
Continuous Auditing D.French
 
Child Wear Ea Blueprint V0.7
Child Wear Ea Blueprint V0.7Child Wear Ea Blueprint V0.7
Child Wear Ea Blueprint V0.7
 
Sourcing lecture 1 ITSM class
Sourcing lecture 1 ITSM classSourcing lecture 1 ITSM class
Sourcing lecture 1 ITSM class
 
1 day workshop managing manufacturing organizations - the toc way
1 day workshop   managing manufacturing organizations - the toc way1 day workshop   managing manufacturing organizations - the toc way
1 day workshop managing manufacturing organizations - the toc way
 
Mark johnson business model transformation
Mark johnson   business model transformationMark johnson   business model transformation
Mark johnson business model transformation
 
Savi chapter10
Savi chapter10Savi chapter10
Savi chapter10
 
Radically increase your process and project throughput with the theory of con...
Radically increase your process and project throughput with the theory of con...Radically increase your process and project throughput with the theory of con...
Radically increase your process and project throughput with the theory of con...
 
10%2 D04%20 Art%20 Bp%20 Maturity%20 Model%20%2 D%20 Fisher%2 Epdf
10%2 D04%20 Art%20 Bp%20 Maturity%20 Model%20%2 D%20 Fisher%2 Epdf10%2 D04%20 Art%20 Bp%20 Maturity%20 Model%20%2 D%20 Fisher%2 Epdf
10%2 D04%20 Art%20 Bp%20 Maturity%20 Model%20%2 D%20 Fisher%2 Epdf
 
Ensuring maximum return on HR technology investment
Ensuring maximum return on HR technology investmentEnsuring maximum return on HR technology investment
Ensuring maximum return on HR technology investment
 

Recently uploaded

Install Stable Diffusion in windows machine
Install Stable Diffusion in windows machineInstall Stable Diffusion in windows machine
Install Stable Diffusion in windows machinePadma Pradeep
 
The 7 Things I Know About Cyber Security After 25 Years | April 2024
The 7 Things I Know About Cyber Security After 25 Years | April 2024The 7 Things I Know About Cyber Security After 25 Years | April 2024
The 7 Things I Know About Cyber Security After 25 Years | April 2024Rafal Los
 
Scaling API-first – The story of a global engineering organization
Scaling API-first – The story of a global engineering organizationScaling API-first – The story of a global engineering organization
Scaling API-first – The story of a global engineering organizationRadu Cotescu
 
Factors to Consider When Choosing Accounts Payable Services Providers.pptx
Factors to Consider When Choosing Accounts Payable Services Providers.pptxFactors to Consider When Choosing Accounts Payable Services Providers.pptx
Factors to Consider When Choosing Accounts Payable Services Providers.pptxKatpro Technologies
 
Presentation on how to chat with PDF using ChatGPT code interpreter
Presentation on how to chat with PDF using ChatGPT code interpreterPresentation on how to chat with PDF using ChatGPT code interpreter
Presentation on how to chat with PDF using ChatGPT code interpreternaman860154
 
How to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected WorkerHow to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected WorkerThousandEyes
 
Swan(sea) Song – personal research during my six years at Swansea ... and bey...
Swan(sea) Song – personal research during my six years at Swansea ... and bey...Swan(sea) Song – personal research during my six years at Swansea ... and bey...
Swan(sea) Song – personal research during my six years at Swansea ... and bey...Alan Dix
 
08448380779 Call Girls In Civil Lines Women Seeking Men
08448380779 Call Girls In Civil Lines Women Seeking Men08448380779 Call Girls In Civil Lines Women Seeking Men
08448380779 Call Girls In Civil Lines Women Seeking MenDelhi Call girls
 
Beyond Boundaries: Leveraging No-Code Solutions for Industry Innovation
Beyond Boundaries: Leveraging No-Code Solutions for Industry InnovationBeyond Boundaries: Leveraging No-Code Solutions for Industry Innovation
Beyond Boundaries: Leveraging No-Code Solutions for Industry InnovationSafe Software
 
SIEMENS: RAPUNZEL – A Tale About Knowledge Graph
SIEMENS: RAPUNZEL – A Tale About Knowledge GraphSIEMENS: RAPUNZEL – A Tale About Knowledge Graph
SIEMENS: RAPUNZEL – A Tale About Knowledge GraphNeo4j
 
The Codex of Business Writing Software for Real-World Solutions 2.pptx
The Codex of Business Writing Software for Real-World Solutions 2.pptxThe Codex of Business Writing Software for Real-World Solutions 2.pptx
The Codex of Business Writing Software for Real-World Solutions 2.pptxMalak Abu Hammad
 
Pigging Solutions Piggable Sweeping Elbows
Pigging Solutions Piggable Sweeping ElbowsPigging Solutions Piggable Sweeping Elbows
Pigging Solutions Piggable Sweeping ElbowsPigging Solutions
 
Injustice - Developers Among Us (SciFiDevCon 2024)
Injustice - Developers Among Us (SciFiDevCon 2024)Injustice - Developers Among Us (SciFiDevCon 2024)
Injustice - Developers Among Us (SciFiDevCon 2024)Allon Mureinik
 
IAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI SolutionsIAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI SolutionsEnterprise Knowledge
 
WhatsApp 9892124323 ✓Call Girls In Kalyan ( Mumbai ) secure service
WhatsApp 9892124323 ✓Call Girls In Kalyan ( Mumbai ) secure serviceWhatsApp 9892124323 ✓Call Girls In Kalyan ( Mumbai ) secure service
WhatsApp 9892124323 ✓Call Girls In Kalyan ( Mumbai ) secure servicePooja Nehwal
 
Salesforce Community Group Quito, Salesforce 101
Salesforce Community Group Quito, Salesforce 101Salesforce Community Group Quito, Salesforce 101
Salesforce Community Group Quito, Salesforce 101Paola De la Torre
 
Understanding the Laravel MVC Architecture
Understanding the Laravel MVC ArchitectureUnderstanding the Laravel MVC Architecture
Understanding the Laravel MVC ArchitecturePixlogix Infotech
 
Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 365
Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 365Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 365
Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 3652toLead Limited
 
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmatics
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmaticsKotlin Multiplatform & Compose Multiplatform - Starter kit for pragmatics
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmaticscarlostorres15106
 
Handwritten Text Recognition for manuscripts and early printed texts
Handwritten Text Recognition for manuscripts and early printed textsHandwritten Text Recognition for manuscripts and early printed texts
Handwritten Text Recognition for manuscripts and early printed textsMaria Levchenko
 

Recently uploaded (20)

Install Stable Diffusion in windows machine
Install Stable Diffusion in windows machineInstall Stable Diffusion in windows machine
Install Stable Diffusion in windows machine
 
The 7 Things I Know About Cyber Security After 25 Years | April 2024
The 7 Things I Know About Cyber Security After 25 Years | April 2024The 7 Things I Know About Cyber Security After 25 Years | April 2024
The 7 Things I Know About Cyber Security After 25 Years | April 2024
 
Scaling API-first – The story of a global engineering organization
Scaling API-first – The story of a global engineering organizationScaling API-first – The story of a global engineering organization
Scaling API-first – The story of a global engineering organization
 
Factors to Consider When Choosing Accounts Payable Services Providers.pptx
Factors to Consider When Choosing Accounts Payable Services Providers.pptxFactors to Consider When Choosing Accounts Payable Services Providers.pptx
Factors to Consider When Choosing Accounts Payable Services Providers.pptx
 
Presentation on how to chat with PDF using ChatGPT code interpreter
Presentation on how to chat with PDF using ChatGPT code interpreterPresentation on how to chat with PDF using ChatGPT code interpreter
Presentation on how to chat with PDF using ChatGPT code interpreter
 
How to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected WorkerHow to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected Worker
 
Swan(sea) Song – personal research during my six years at Swansea ... and bey...
Swan(sea) Song – personal research during my six years at Swansea ... and bey...Swan(sea) Song – personal research during my six years at Swansea ... and bey...
Swan(sea) Song – personal research during my six years at Swansea ... and bey...
 
08448380779 Call Girls In Civil Lines Women Seeking Men
08448380779 Call Girls In Civil Lines Women Seeking Men08448380779 Call Girls In Civil Lines Women Seeking Men
08448380779 Call Girls In Civil Lines Women Seeking Men
 
Beyond Boundaries: Leveraging No-Code Solutions for Industry Innovation
Beyond Boundaries: Leveraging No-Code Solutions for Industry InnovationBeyond Boundaries: Leveraging No-Code Solutions for Industry Innovation
Beyond Boundaries: Leveraging No-Code Solutions for Industry Innovation
 
SIEMENS: RAPUNZEL – A Tale About Knowledge Graph
SIEMENS: RAPUNZEL – A Tale About Knowledge GraphSIEMENS: RAPUNZEL – A Tale About Knowledge Graph
SIEMENS: RAPUNZEL – A Tale About Knowledge Graph
 
The Codex of Business Writing Software for Real-World Solutions 2.pptx
The Codex of Business Writing Software for Real-World Solutions 2.pptxThe Codex of Business Writing Software for Real-World Solutions 2.pptx
The Codex of Business Writing Software for Real-World Solutions 2.pptx
 
Pigging Solutions Piggable Sweeping Elbows
Pigging Solutions Piggable Sweeping ElbowsPigging Solutions Piggable Sweeping Elbows
Pigging Solutions Piggable Sweeping Elbows
 
Injustice - Developers Among Us (SciFiDevCon 2024)
Injustice - Developers Among Us (SciFiDevCon 2024)Injustice - Developers Among Us (SciFiDevCon 2024)
Injustice - Developers Among Us (SciFiDevCon 2024)
 
IAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI SolutionsIAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI Solutions
 
WhatsApp 9892124323 ✓Call Girls In Kalyan ( Mumbai ) secure service
WhatsApp 9892124323 ✓Call Girls In Kalyan ( Mumbai ) secure serviceWhatsApp 9892124323 ✓Call Girls In Kalyan ( Mumbai ) secure service
WhatsApp 9892124323 ✓Call Girls In Kalyan ( Mumbai ) secure service
 
Salesforce Community Group Quito, Salesforce 101
Salesforce Community Group Quito, Salesforce 101Salesforce Community Group Quito, Salesforce 101
Salesforce Community Group Quito, Salesforce 101
 
Understanding the Laravel MVC Architecture
Understanding the Laravel MVC ArchitectureUnderstanding the Laravel MVC Architecture
Understanding the Laravel MVC Architecture
 
Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 365
Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 365Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 365
Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 365
 
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmatics
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmaticsKotlin Multiplatform & Compose Multiplatform - Starter kit for pragmatics
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmatics
 
Handwritten Text Recognition for manuscripts and early printed texts
Handwritten Text Recognition for manuscripts and early printed textsHandwritten Text Recognition for manuscripts and early printed texts
Handwritten Text Recognition for manuscripts and early printed texts
 

Production Optimization Using TOC

  • 1. In This Session … OVERVIEW Purpose Production Optimization Versus Throughput Optimization — A Systematic Approach to Improving Production Effectiveness using TOC Author Pino Villa Independent Consultant 1
  • 2. In This Session … OVERVIEW Discussion Point Features 1 This session explores how the Theory of Constraints business philosophy can be applied Explore to the SAP Production Planning and Detailed Scheduled processes to better understand and optimize organizational throughput (on-time delivery). Understand how production throughput, which focuses on optimizing production 2 effectiveness, differs from more cost-focused organizational throughput measures Understand (maximizing production capacity, batch-size). 3 Learn how to leverage capabilities found in SAP Production Planning to apply the Theory of Learn Constraints to maximize production effectiveness, increase on-time product delivery, and reduce costly inventory levels. 4 Hear best practices for introducing Theory of Constraints to your organization and learn Best Practice how to avoid common pitfalls you may encounter along the way. 5 Come away from this session armed with the information you need to assess whether your Benefits organization will benefit from an enhanced focus on organizational throughput. 2
  • 3. What We’ll Cover … • Manufacturing throughput • Theory of Constraints (TOC) methodology • Explanation of Drum, Buffer, Rope (DBR) technique • A Theory of Constraint case study • Applying the Theory of Constraint technique within SAP • Applying the Theory of Constraint technique within SAP PPDS • Wrap-up 3
  • 4. Our Key Objective Throughput (Sales – Material Costs) is what is provided across the supply chain OEM Manufacturer Distributor Dealer Retail OVERVIEW In adopting the Theory of Constraint approach in managing throughput we try to:  Maximize Throughput  Reduce Inventory  Reduce Operating Costs By achieving the above we maximize productivity and profitability
  • 5. Theory of Constraint (TOC) OVERVIEW Throughput is based on satisfying customer demand. In order to achieve this, all manufacturing sites have to plan, source raw materials and components, manufacture, and finally deliver. The processes are governed by: • Inputs, raw materials components, money, etc. • Mechanisms (resources such as facilities, people, machines, etc. • Constraints: company policy, equipment constraints (capacity) • Outputs, semi finished, finished product. THEORY OF CONSTRAINTS METHODOLY By adopting the Theory of Constraint methodology/technique for the above processes, throughput objectives can be achieved.
  • 6. Value Chain VALUE CHAIN The value chain is based on system (facilities, human resources, manufacturing resources and IT systems) capability and key constraints (Company policy, financial resources) to generate throughput. The fundamental consideration is to maximize throughput with available resources and constraints.
  • 7. Maximize Throughput Using TOC TOC METHODOLY TOC Methodology is used to maximize throughput of the value chain. TOC is not just only a methodology (not file 13) but also a strategic management approach that the organization will apply.
  • 8. Manufacturing Throughput PURPOSE The key benefit of applying this methodology is that it provides purpose with respect to a fundamental optimization project. The tangible benefits are measurable and impact the profitability of the organization The TOC focus should be part of the tactical layer of the organization while the DBR focus should be part of the operational level. TOC is not once off; it becomes a way of life. THEORY OF CONSTRAINTS METHODOLY The TOC methodology is supported by Drum, Buffer and Rope (DBR) planning technique as well as buffer management in order to achieve TOC objectives. DBR is critical to ensure all is synchronized to the production capacity of the Constrained Manufacturing resource.
  • 9. Realizing Real Business Benefits BACKGROUND TO MANUFACTURING SYSTEM IMPLEMENTATION Discussion Point Features 1 There are many situations whereby real business benefits where not achieved because BUSINESS they were focused on IT. Extensive IT investment did not lead to bottom line benefit. BENEFITS Some IT departments have underestimated the complexity, resulting a in a poorly built 2 solution. This is caused by both customer and partner; partner using low skilled resources. COMPLEXITY In many cases project is governed by old habits and old ways of working, which might not 3 be ideal. This is a major problem with multi-national organizations where acquisitions HABITS played a big role in building up their current organization. 4 There are ample cases studies documenting project failure, finger pointed at vendor. This PROJECT FAILURE normally is caused not so much by vendor but rather by poor project management by both customer and consulting partner. Sometimes vendor over sells business benefits leading to disappointments. 5 In business we have many different methodologies for improvements, Business Process ACRONYMS Re-engineering (BPR), Business Process Modeling (BPM), SCOR, etc. But do they actually result in business benefit; is throughput and productivity increased? 9
  • 10. What We’ll Cover … • Manufacturing throughput • Theory of Constraints (TOC) methodology • Explanation of Drum, Buffer, Rope (DBR) technique • A Theory of Constraint case study • Applying the Theory of Constraint technique within SAP • Applying the Theory of Constraint technique within SAP PPDS • Wrap-up 10
  • 11. Step 1: Identify the Constraint KEY POINTS WITH RESPECT TO THEORY OF CONSTRAINED OPTIMIZATION TECHNIQUE Find the one element of the manufacturing system which limits the system's ability to achieve its goal. In most manufacturing, identify what limits the system performance. Very important to consider that a process is governed by: I; Input; components/raw materials C; Control; policy, methods, shift, set-up requirements; tooling M; Mechanism; the actual manufacturing machine that has a rated capacity O: Output; the manufactured item (semi or finished product) System constraints can be either physical or policy. Physical constraints are relatively easy to identify and relatively straightforward to break. Policy constraints are usually more difficult to identify and break, but they normally result in a larger degree of system improvement that the elimination of a physical constraint. IDENTIFY THE CONSTRAINT 11
  • 12. Step 2: Decide How to Exploit the Constraint KEY POINTS WITH RESPECT TO THEORY OF CONSTRAINED OPTIMIZATION TECHNIQUE Understand how to exploit the constraint. That means squeezing the most out of the manufacturing constraint in order to attain maximum performance. Therefore consider all aspects around the process: •Policy and procedure •Tooling, set-up equipment, set-up matrix •Planning and execution system; ERP, APS, etc. This must be done without major system changes or capital improvements with the primary objective of eliminating inefficiency from the constraint DECIDE HOW TO EXPLOIT THE CONSTRAINT 12
  • 13. Step 3: Subordinate Everything Else KEY POINTS WITH RESPECT TO THEORY OF CONSTRAINED OPTIMIZATION TECHNIQUE Take the required steps to synchronize and align the performance of all other elements with the "exploited" constraining element. This may mean slowing down "faster" parts and speeding up "slower" ones. If your constraint is broken at this point, go back to Step 1 and start looking for the next constraint (next weakest link in the chain). If not, go on to Step 4. Fundamentally make effective management of the existing constraint the top priority. SUBORDINATE EVERYTHING ELSE TO THE DECISION IN STEP 2 13
  • 14. Step 4: Elevate the Constraint KEY POINTS WITH RESPECT TO THEORY OF CONSTRAINED OPTIMIZATION TECHNIQUE If the constraining element still remains the reason why the system's performance "tops out"; then “elevate" usually means doing something to increase the capacity of the constraining element. Obviously, if your constraining element is running at maximum efficiency (which it should be after Steps 2 & 3), the only way to improve overall system performance is to obtain more of the constraining element. In a manufacturing environment, this may mean a capital investment in more equipment, or hiring more people, or increasing working shifts. ELEVATE THE CONSTRAINT 14
  • 15. Repeat Steps 1-4: Manage Inertia KEY POINTS WITH RESPECT TO THEORY OF CONSTRAINED OPTIMIZATION TECHNIQUE This is the "repeat Steps 1-4" step. But the warning about "inertia" is important. It's designed to discourage complacency, thinking that the environment doesn't ever change much over time. Always consider that throughput increase can create other weaker links that previously were considered secondary. MANAGE INERTIA – GO BACK TO STEP 1 IF REQUIRED 15
  • 16. Theory of Constraints: Summary Typical Process The TOC methodology allows us to understand how throughput is generated. TOC also provides a clear direction on how to maximize/exploit resources and to synchronize/subordinate everything around the critical resources. TOC provides clear direction on leveraging IT systems. TOC PROCESS IT System to support above process 16
  • 17. What We’ll Cover … • Manufacturing throughput • Theory of Constraints (TOC) methodology • Explanation of Drum, Buffer, Rope (DBR) technique • A Theory of Constraint case study • Applying the Theory of Constraint technique within SAP • Applying the Theory of Constraint technique within SAP PPDS • Wrap-up 17
  • 18. Drum, Buffer, Rope (DBR) Technique SUBORDINATING EVERYTHING ELSE TO DECIDING HOW TO EXPLOIT THE CONSTRAINT When it comes to subordinating everything to a constraint, its bottlenecks. In a production environment, the plants constraint must be the driving factor in how it is managed. In production, the productivity of the constraint is the productivity of the entire plant. A proven approach to managing production through the constraint is known as "Drum-Buffer-Rope" and "Buffer Management." • Drum - The constraints, linked to market demand, is the drumbeat for the entire plant. • Buffer - Time/inventory that ensures that the constraint is protected from disturbances occurring in the system. • Rope - Material release is "tied" to the rate of the constraints. Drum, buffer, and rope provide the basis for building a production schedule that is highly immune to disruption, avoids creating excess inventory, and uses small batches to minimize overall lead time. But even with Drum-Buffer-Rope (DBR), occasional disruptions occur that require special attention. Buffer Management is used to mitigate and often prevent those disruptions. The DBR methodology is Theory of Constraints that will be used to maximize production throughput and inventory reduction based on the constraints (weakest link) being the Drum, the Buffer being the inventory needed for the constraint and the Rope the timing for releasing the buffer with the main aim of protecting the weakest link and thus maximizing overall effectiveness. 18
  • 19. Drum, Buffer, Rope (DBR) Technique (cont.) DBR EXPLANATION Raw Material LEGEND CCR Capacity Constrained Resource Semi 1 Semi 2 Finished prod. WC 1 WC2 WC3 WC4 CCR Buffer Semi 2 ROPE Drum. The CCR resource (work-centre 3) Rope: The release of raw materials scheduled to 1 determines the schedule 3 start production at work-centre 1 based on the schedule determined by the Drum. 2 Buffer. Buffer to protect the CCR - Work-centre 3 In TOC, Subordinate everything else to the CCR Work-centre. This means synchronize all planning activities to production rate (drum) of resource to ensure that the CCR does not stand ideal. The Buffer in front of the CCR will be the safety margin. Therefore the planning and scheduling system must now satisfy the DBR requirements. 19
  • 20. DBR Buffer Management Semi 2 DBR BUFFER MANAGEMENT Finished prod. LEGEND CCR Capacity Constrained Resource WC2 WC3 WC4 Buffer CCR Buffer With DBR, it is critical to protect the CCR with buffer. By Semi 2 doing what is supposed to be done in accordance with our CCR plan we protect the constraint and the system as a whole ROPE This buffer is needed so that CCR is not starved due to delays in production of input components. It strives to achieve the following: • Reliable due date performance • Effective exploitation of the constraint • Accurate system data for relevant role players. Buffer is introduced in front of CCR. This buffer is divided into 3 zones for expediting purposes. Red zone penetration was also included in KPI. The buffer zone helps to simplify exception management and it helps identify possible creeping CCR. The buffer zone concept was included in the monitor of CCR in SAP.
  • 21. What We’ll Cover … • Manufacturing throughput • Theory of Constraints (TOC) methodology • Explanation of Drum, Buffer, Rope (DBR) technique • A Theory of Constraint case study • Applying the Theory of Constraint technique within SAP • Applying the Theory of Constraint technique within SAP PPDS • Wrap-up 21
  • 22. Overview PROJECT CONTEXT 1 Organization running at maximum capacity 2 Poor on-time delivery, high back-order qty 3 High level of Inventory 4 Extensive IT expenditure with limited success Company in auto industry component supplier, supplies all makes, from low cost to sports cars. The manufacturing process consists of 3 main stages: 3.Input Semi finished 1 4.Input Semi finished 2 5.Finished product Both input semi finished 1 and 2 can be used for multiple finished products (product families) The work centre for finished product takes from 6-8 hours of set-up. Batch runs can run over multiple days. Multiple work-centre (machines) for finished product are available. Possible number of product code 20000. Customer orders based on delivery schedule. 22
  • 23. TOC Five-Step Analysis PROJECT CONTEXT The analysis was based on the five TOC steps, primarily Steps 1, 2 and 3. The TOC project also provided an opportunity to find out what was going on in production and related areas. Project team was made up of manufacturing (Industrial engineers) experts (external) as well as SAP functional and technical consultants. Project sponsor Financial Manager; critical to avoid hiding problems and internal politics. Project based on 3 major steps: 1. Analysis 2. Design and build 3. Implementation The deliverables for the analysis phase must be specific in order to allow quick and effective implementation. This was critical to avoid a paper exercise. 23
  • 24. Brief Summary PLANNING & EXECUTION SYSTEM ANALYSIS Analysis Identification 1 Current planning tool did not plan production based on resource capacity Current (finite scheduling). planning In certain situations, scheduling was done in the past. Set-up date not realistic, not updated regularly. Incoming open purchase order did not 2 Raw material reflect realistic dates, resulting in incorrect supplies planning and poor expediting dates. In certain instances, raw materials were not consumed correctly. 3 In certain cases, non-CCR resources were Non CCR overloaded due to poor planning. System overload data did not match reality. Shop floor data updated late (24 hours) resulting in a poor view of downstream semi finished production status. Note: During the analysis phase, there was a clear indication of paradigm constraint; locking the organization into poor performance due old established habits and lack of willingness to change. 24
  • 25. Identification PLANNING & EXECUTION SYSTEM ANALYSIS Analysis Identification No stability in planning, order changed at 4 last minute causing problems in semi- Production Order finished products planning. changes & status Recommendation to introduce frozen period to ensure planning stability. Too many open production orders, status not managed correctly. Due to high set-up (6-8 hours) manufacturing set 5 large batch run resulting in high inventory. Change this rule based on minimum duration Batch size plus lot coverage. (i.e., average of next 8 weeks of demand) and not on historical data. Demand for semi finished product not planned correctly due to plant responsibility 6 separate per product group, no common objective. Each department planned their Multi-level machines to maximum capacity without considering global objective. planning Department for semi finished planned to maximum capacity even without demand. This resulted in overstock of semi finished and in certain cases no stock for finished product where customer demand existed. 25
  • 26. Shop Floor Data Collection PLANNING & EXECUTION SYSTEM ANALYSIS Analysis Identification Too many forms, in certain cases forms filled in by operators were illegible. Approved 7 standardization of pre-printed forms with barcode with minimum data input. Also agreed to introduce simple entry screens with limited default data. Shop Floor Data Delay in input SFDC into system resulted in inaccurate data specifically around CCR. Collection 26
  • 27. Summary SUMMARY OF KEY CONSIDERATION The analysis for the TOC steps identified a number of issues that covered: 2. Company procedures 3. Organization structure, responsibilities, and objectives 4. Serious Production Planning and execution system weaknesses 5. Poor shop floor control This is why a TOC project is not just an IT project. Identify the constraint: We identified the key manufacturing constraints, specifically how they where planned, 1 its set-up effort (tooling etc.), how semi-finished components where planned. Exploit the constraint: In order to elevate the constraints, company agreed to change organization structure 2 and responsibilities so that everything is focused around throughput. Departments to synchronize their planning based on CCR demand schedule. More effort to reduce set-up time of CCR and ensure accurate recording of set-up and tear-down. Set-up became a key KPI. Subordinate everything to constraining resource: Agreed to introduced DBR planning technique including 3 buffer management within the SAP PP DS. Also agreed to introduce supermarket concept to some semi- finished products that where common to many subsequent semi-finished items. Elevate the constraint: In order to understand current CCR loading versus market demand, introduced SOP 4 (in APO) with simulation facility in order to provide marketing and production a tool to understand how to address additional market demand or reduction. 27
  • 28. What We’ll Cover … • Manufacturing throughput • Theory of Constraints (TOC) methodology • Explanation of Drum, Buffer, Rope (DBR) technique • A Theory of Constraint case study • Applying the Theory of Constraint technique within SAP • Applying the Theory of Constraint technique within SAP PPDS • Wrap-up 28
  • 29. DBR Planning and Execution Options SAP PLANNING AND EXECUTION OPTIONS In order to achieve throughput objectives, SAP offers a number of planning and execution solutions. The focus will be All of these technically could be suitable, the selection depends on the complexity of the on Scenario A and manufacturing processes and related Scenario D system relationships. The following is available: OPTION A This is based on planning and execution using SAP ERP MRP, capacity leveling, and execution. OPTION B Planning in SAP ERP, scheduling in APO PPDS and execution in ERP. OPTION C Planning run 1 and scheduling in APO PPDS , then in ERP planning (MRP) of other related aliments (components, bulk, consumables) and execution in ERP. OPTION D Planning and scheduling only in PPDS and execution in ERP. OPTION E This option utilizes CTM (Capable to match) in APO to plan for medium term horizon where planning is executed with capacity constraints. This plan will create planned orders. These planned orders are then re-planned in short production horizons including capacity leveling and detailed scheduling. These orders will be firmed production orders. The planned order (CTM) and firmed production order will then be replicated into ERP which will form dependant demand for other planning.
  • 30. DBR Planning and Detailed Scheduling DBR PLANNING AND DETAILED SCHEDULING Control Point Features This section focuses on the 1 • Master Production Schedule Finished Product SAP parts in order to • Capacity leveling achieve TOC objectives and Finished Product • Order review and set-up optimization Planning apply the DBR planning • Multi-level ATP method. • Order release •Finished product input: • Planning of semi finished 1 on released production Semi Finished 2 2 orders of finished product (Drum) •Semi finished 2 input: Semi Semi Finished 1: • Review of results • Semi finished level 3 linkage finished 3 Level 2 (Raw materials ATP) •Semi finished 3 input: Raw materials 3 • Semi finished 2 planning Semi Finished 2: • Buffer Level 3 • Raw materials planning 30
  • 31. DBR Planning Process Deletion of firmed order CUSTOMER MPS for FIRM PERIOD ORDERS Finished Items MPS Process Review of Planned Orders planning results Creation of Production Orders DRUM Production Orders This is only relevant for finished products: Short term capacity Capacity leveling for the CCR work centre leveling Capacity Capacity SCHEDULED ORDER AND DEP.REQUIR Leveling Leveling Review CYCLE 4: MID-TERM PLAN INCLUDING PLANNED ORDERS Medium term capacity JOB OR MANUAL leveling EXECUTION OF PROGRAM 31
  • 32. DBR Planning Process (cont.) MATERIAL MASTER DATA: 1 - 2 ATTENTION POINTS 1 Finished product MRP1 View: Transaction MM02 The MRP type must be M0, which plans only MPS items. Executing MPS plans only items identified as MPS. The opening period is set to 5 days in order to allow 2 semi finished 2 lead time Verify the scheduling margin key in MRP2 View: Transaction MM02 and buffer. For slow moving items where there is no semi finished 3 buffer, select key with 10 days. The determination of the opening period is critical for confirming production Source: SAP 32
  • 33. Buffer Management FINISHED PRODUCT PLANNING: BUFFER MANAGEMENT The time buffers are needed to protect the Master Schedule. This buffer is needed for any possible unexpected deviation to plan. The schedule of the CCR must be protected in order to maximize efficiency. Buffer This is the time buffer assigned to Finished product. MPS Therefore the end time of FINISHED GOODS SEMI-FINISHED 2 must be: MPS (MPS DRUM-BEAT) MPS Order start - Buffer MPS The Semi Finished Input 2 Schedule may have deviations within the buffer INPUT zone without impacting the MPS plan critical to protecting Red zone buffer SEMI-FINISHED 2 the MPS plan at the CCR penetration 33
  • 34. Bill of Material BILL OF MATERIAL … ATTENTION POINTS Verify the buffer between Finished Product and Input Semi Finished 2: 1 Transaction CS02 For the finished product, a buffer of 3 days is assigned against the input 2 semi finished product. This buffer is used to determine the date Semi finished 2 should be ready by. Source: SAP 34
  • 35. Work Centre Data WORK CENTRE 1-3 ATTENTION POINTS Maintain Work-centre data : Transaction CR02 1 Scheduling and Capacity formulas are relevant only for work centres that require capacity loading. Work centres of minor importance do not require this information. Critical capacities require shift data and relevant calendar assigned. Efficiency needs to be assigned to capacity utilization field. Only work centres relevant to capacity leveling (CCR) require the finite scheduling flag set. Source: SAP 35
  • 36. Work Centre Data (cont.) WORK CENTRE 2-3 ATTENTION POINTS Maintain Shift data. This is needed only if shift change occurs during 2 the week. Shift detail must be inserted if the work centre has days whereby number of working hours differ, example Saturday and Sunday. Each shift has to have relevant efficiency. Source: SAP 36
  • 37. Work Centre Data (cont.) WORK CENTRE 3-3 ATTENTION POINTS Maintain grouping rules, this is the number of days we will group 3 orders for set-up optimization and is updated in classification The value of 5 days means that for this work centre order with same characteristics will be grouped together. If there is no value then no grouping Source: SAP 37
  • 38. Routing ROUTING CURRENT PROPOSAL 1:2 ATTENTION POINTS Only one routing will be 1 created. Verify the routing: Transaction CA02 The routing will be based on: Group counter number; the smallest number is the primary Usage 1 production Status 5 released The routing will contain 2 primary work centre Verify the operations assigned to operation 0010 and alternate to 001X with control key GL07 (alternate work centre). Alternate work centre will be allocated to operation 001X where X is next number, this is critical to group alternate to primary Source: SAP 38
  • 39. Routing (cont.) ROUTING 2-2 ATTENTION POINTS 3 Verify the manufacturing grouping rules by viewing operation details: The setup groups category contains major grouping category; example MPS 1 to 3. The setup group key contains manufacturing characteristics such as tooling , material, etc. 4 Verify the relationship of the above to the set-up matrix; transaction OPDA The setup matrix contains reduction rules with respect to setup where production orders are grouped according to same characteristics. The setup in the set-up matrix replaces the routing setup data. Source: SAP 39
  • 40. Master Production Scheduling MASTER PRODUCTION SCHEDULING … ATTENTION POINTS 1 Review status of material: MD04 Review current customer and production orders. Also review the exception messages generated by the system. Alternate view shows traffic lights which, in this case, indicate that orders need to be brought forward. Source: SAP 40
  • 41. Executing MPS EXCUTING MASTER PRODUCTION SCHEDULING… ATTENTION POINTS 1 Execute Master Production Schedule: Transaction MD40 Scheduling Parameter = 2 This means that dates will be determined based on routing data. To plan single material use transaction MD42 Select execute 2 MPS generates log of material planned MPS has planned only Finished Products identified as MPS items Source: SAP 41
  • 42. Verifying MPS VERIFICATION MASTER PRODUCTION SCHEDULING… ATTENTION POINTS 1 Verify result of MPS planning for Finished Product: MD04 Planned Order for finished products created in the past as per MPS setting. This is critical for determining back-log priority. Planned order created as per lot size rule Source: SAP 42
  • 43. Verifying MPS (cont.) VERIFICATION MASTER PRODUCTION SCHEDULING… ATTENTION POINTS 2 Verify planned order details by selecting individual order Production dates are scheduled as per routing data. The opening date is based on start date minus 5 days as per scheduling margin key (working days). 3 Select Detailed Scheduling folder Scheduling has been executed on work centre Z451 based on work centre scheduling data. Capacity Requirements also generated on work centre Source: SAP 43
  • 44. Verifying MPS (cont.) VERIFICATION MASTER PRODUCTION SCHEDULING… ATTENTION POINTS 4 Verify planned order details by selecting individual order In transaction MD04, from Environment, select capacity load to view capacity load on work- centre The capacity requirement versus available capacity determines the capacity load percentage. This view contains combined load, therefore all the products that were planned against this primary work centre. Source: SAP 44
  • 45. Dynamic Order Fixing DYNAMIC ORDER FIXING Firm Drum Schedule NOT FIRMED FIRMED FIRMED TODAY +5 FIRMING PERIOD 1 The opening date is date used by planner to firm orders 2 The opening date must allow for buffer time, semi finished 1 lead time 3 The opening date logic can be SKU specific to allow for semi-finished 1 lead-time 4 The planner will firm any planned order where the opening is ≤ today + 5 (flexible)
  • 46. Order Fixing ORDER FIXING: WIDE STRIP BUFFER HOW TO MANAGE ORDER FIXING CONSIDERING THE LEAD TIME OF SEMI FINSIHED AND ENSURING REALISTIC PLANNING DATA FOR FINISHED PRODUCT The Semi Finished 1 lead-time must be included in the opening period for firming. Semi finished 2 is excluded for where there is Kanban. Opening period logic is per material or can be assigned to MRP group OPENING PERIOD
  • 47. Converting Planned Orders to Production Orders CONVERSION OF PLANNED ORDERS TO PRODUCTION ORDERS… ATTENTION POINTS 1 Planned orders are converted to production orders, transaction CO41 Critical to select finished products according to opening date criteria. It is critical that Finished Products are firmed up to allow production of Semi Finished 1 and for where there is no Semi Finished 2 buffer (Kanban, supermarket) The opening date should be today plus 5 days List of orders that planner should convert to Production order are proposed Source: SAP 47
  • 48. Converting Planned Orders to Production Orders (cont.) CONVERSION OF PLANNED ORDER TO PRODUCTION ORDERS… ATTENTION POINTS 2 Selection of routing User must select relevant routing. NOTE: this is only relevant if alternate routings are managed 3 View Production Orders Production orders are now created for planned orders that fall within planning horizon of 5-7 days Source: SAP 48
  • 49. Capacity Planning Overview CAPACITY PLANNING OVERVIEW… Control Point Features • The purpose of Capacity Planning is to schedule orders as per defined sequence 1 within capacity constraints of a work centre. (Technical name is Dispatching). Purpose • To carry-out set-up optimization for orders that have same characteristics • To update orders once scheduled with relevant start and end date • Allows user to modify production orders; priority, production version 2 • Consists of: • A work centre view Structure • Scheduled order (dispatched) • Orders to be scheduled 3 • Capacity planning is controlled by profiles. Control • Each profile determines how capacity should be scheduled, how orders are viewed elements and information provided • Consists of a scheduling strategy that determines how orders are scheduled 4 • Has links to: Links • Production order header • Production operation • Work centre data Source: SAP 49
  • 50. Capacity Planning EXPLANATION OF CAPACITY PLANNING 1 Work centre view and scheduled production orders 2 Material / Production orders view showing order dispatched 3 Production orders to be dispatched Source: SAP 50
  • 51. Viewing Capacity Load VIEW OF CAPACITY LOAD ATTENTION POINTS 1 View the capacity load This shows percentage load. Overload is shown in red. Source: SAP 51
  • 52. Viewing Capacity Load (cont.) VIEW OF CAPACITY LOAD ATTENTION POINTS 2 View the details of the loading capacity details for period Selecting the individual row shows the actual production orders. It is possible to show graphic view of load and available capacity. Source: SAP 52
  • 53. Capacity Leveling CAPACITY LEVELING: MPS CYCLE ATTENTION POINTS 1 Execute capacity leveling to check back-log and re-schedule where required. Transaction CM25, select Profile A_XX. View Change time profile to see dates used Capacity leveling considers orders in the last 30 days. This is critical to show back log. Source: SAP 53
  • 54. Capacity Leveling (cont.) CAPACITY LEVELING: MPS CYCLE ATTENTION POINTS First action is to prioritize any backlog production orders, this way system 2 Select orders to determine will schedule these first and will ignore grouping rules. if really in backlog (could Select row production order. be delay in updating system). It is critical that real back-log orders are re- scheduled to ensure correct loading of work- centre. Orders in back-log are prioritized by assigning priority Then select The table shows key sequencing data: Priority Group category Group Key Latest Start date Source: SAP 54
  • 55. Capacity Leveling (cont.) CAPACITY LEVELING MPS CYCLE ATTENTION POINTS 3 View Planning results with transaction MD04 Production orders rescheduled. Orders are not scheduled in the past. The std SAP message will provide relevant messages to user 4 Re-check load on work centre, transaction CM01 No overload with respect to capacity Source: SAP 55
  • 56. Capacity Leveling (cont.) CAPACITY LEVELING: MPS CYCLE ATTENTION POINTS 5 View the GANTT chart details The GANTT chart at work centre view provides the following data: Production Order number Material description Set-up in blue Execution time in red The order view shows as same GANTT as work centre view, but detailed by order number Source: SAP 56
  • 57. Capacity Leveling (cont.) CAPACITY LEVELING: MPS CYCLE ATTENTION POINTS 6 View the impact of changing production order The system automatically re-schedules order according to set-up time and execution time defined in routing for alternate capacity It will automatically change the group category and group key with what was defined in alternate routing. Note: Just changing the work centre does not re- determine operation data such as set-up, execution, and grouping Source: SAP 57
  • 58. Capacity Leveling (cont.) CAPACITY LEVELING: SET-UP OPTIMIZATION ATTENTION POINTS 1 Carry-out set-up optimization. Transaction CM25 select Profile A_BUMAN03. Select orders Note the set-up group category and set-up key. These two conditions are used for optimization. Source: SAP 58
  • 59. Capacity Leveling (cont.) CAPACITY LEVELING: SET-UP OPTIMIZATION ATTENTION POINTS 2 Carry-out optimization by selecting from menu The system will automatically replace set- up time as per matrix Save 3 Re-enter with same profile to display result The set-up optimization considers the set-up group category and Set-up group key Source: SAP 59
  • 60. Capacity Leveling (cont.) CAPACITY LEVELING: SET-UP OPTIMIZATION ATTENTION POINTS 4 View the GANTT chart details These production orders have their set-up reduced as per matrix. 5 View operation details Operation data automatically updated. Production orders modified automatically Source: SAP 60
  • 61. Modifying the Order MODIFICATION TO ORDER ATTENTION POINTS 1 On a regular basis, the planner will have to re-plan order specifically for back- log or priorities. Assign priority to backlog orders. STEP 1: Verify scheduling Transaction CM25 Profile A_BUMAN04 (Order view) Planning must be aligned with current date; therefore, all orders in back-log must be re- scheduled accordingly. Therefore user must: Change priority of backlog order operation to 1 in sequence number field De-allocate orders Select row and click orders Once we have done this and we re-schedule, it will sort in capacity leveling according to: 1 Sequence Number Click on 2 Group Category 3 Group Key Insert value 2 in 4 Start Date priority Source: SAP 61
  • 62. Modifying the Order (cont.) MODIFICATION TO ORDER ATTENTION POINTS 2 Carry-out rescheduling of orders. STEP 2: Verify scheduling Transaction CM25 Profile A_BUMAN04 (Order view) The user manually dispatches the order by using drag and drop functionality. The order will be dispatched exactly as requested by planner. Source: SAP 62
  • 63. Modifying the Order (cont.) MODIFICATION TO ORDER ATTENTION POINTS 3 Manual Maintenance of Production Order. Transaction CO02, change production order Changes to order dates can be carried-out only if order is de-allocated. Qty changes require re- scheduling as well as manual dates changes. The re-scheduling will then require capacity leveling Select menu ‘Functions’ Change Scheduling to forwards and then insert new Start date Then select re- schedule Source: SAP 63
  • 64. The Role of the Drum The scheduling of the Drum based on CCR accurately determines the start and finish time. The start date minus the BUFFER buffer determines the end time in which preceding semi finished 1 must be finished. The buffer is like a shock absorber. START TIME The CCR determines the Drum. END TIME In this case, the CCR is responsible for finished product. The scheduling of the CCR exact start and finish time, including set-up, determines the dependant demand on the semi finished 1 and related components. The semi-finished 1 is planned to include a buffer to protect the CCR. The Drum also provides release date (ROPE) for the raw materials. 64
  • 65. Finished Strip Linkage SEMI FINISHED 2 LINKAGE ATTENTION POINTS 1 MPS on Finished product only creates Dependant Requirements. Use transaction MD04 to show status on Semi Finished 1 MPS on the Finished product has only generated dependant demand and has not executed any planning on semi finished 1. MPR will be generated continuously re-creating planned orders as per requirements. Demand is classified as follows: 1 OrdRes is based on FP Production Order 2 DepReq is based on FP planned orders Source: SAP 65
  • 66. Semi-Finished 1 Missing Parts List SEMI FINSIHED 1 MISSING PARTS LIST ATTENTION POINTS 1 Review Missing Parts List; Transaction CO24 Updated automatically when releasing Production Order of Semi finished 1. The Requirement qty is based on the production order demand. Committed qty is what is currently available or planned (production Orders) to satisfy demand. The missing parts info system is updated every time ATP is executed Source: SAP 66
  • 67. Semi-Finished 1 Missing Parts List (cont.) SEMI FINSIHED 1 MISSING PARTS LIST ATTENTION POINTS 2 Review Production Order The production order for the Finished Product contains the details of the Semi finished 1. Reservation is assigned to Semi finished 1. Reservation is only relevant for Production Orders created for Semi finished 1. Committed qty is zero. This is based on ATP check. Source: SAP 67
  • 68. Semi-Finished 1 Missing Parts List (cont.) SEMI FINISHED 1 MISSING PARTS LIST ATTENTION POINTS 3 ATP Check The confirmed qty is available to satisfy the order. The confirmed qty is based on production orders created for Semi Finished 1. In this example, there is nothing confirmed to satisfy demand. The check rule considers only Production Orders. Source: SAP 68
  • 69. Semi-Finished 1 MRP SEMI FINISHED 1 MRP ATTENTION POINTS 1 Verify Semi Finished 1 Status, Transaction MD04. The Semi Finished 1 should have grouping rules . Example group 3 days demand. Source: SAP 69
  • 70. Semi-Finished 1 MRP (cont.) SEMI FINISHED 1 MRP ATTENTION POINTS 2 Review Master Data, Transaction MM02. Lot size rule and minimum lot qty. Groups 3 days demand for Finished products. Lead-time. Scheduling Margin Key has opening period of 2 days. Source: SAP 70
  • 71. Semi-Finished 1 MRP (cont.) Semi SEMI FINISHED 1 MRP ATTENTION POINTS 3 Execute MRP, Transaction MD02. Orders will be created as per material master lead time. No capacity load generated. Planned Orders created in the past. Source: SAP 71
  • 72. Semi-Finished 1 MRP (cont.) SEMI FINISHED 1 MRP ATTENTION POINTS 4 Convert production Order single Order from MD04. Start and end as per lead time (working days as per plant calendar). Production Order is not allowed to be created in the past. This is critical for a realistic ATP for the Finished Product. Source: SAP 72
  • 73. Creating Production Order for Semi-Finished 1 PRODUCTION ORDER CREATION FOR SEMI FINISHED 1 ATTENTION POINTS 1 Convert planned Order to Production Orders, Transaction CO41 . Firm up one week’s orders. All planned orders within selected period are converted. Source: SAP 73
  • 74. Refresh Semi-Finished 1 Product Status REFRESH OF SEMI FINISHED 1 PRODUCT STATUS ATTENTION POINTS 1 Run ATP, transaction COMAC. The finished Strip should have grouping rules. Example group 3 days demand. Finished product order is confirmed with planned production orders. Source: SAP 74
  • 75. Refresh Semi-Finished 1 Product Status (cont.) REFRESH OF SEMI FINISHED 1 PRODUCT STATUS ATTENTION POINTS 2 Re-check Missing parts list, Transaction CO24. Before Reservation is gone from list indicating that Finished Product production order can be satisfied with order. Source: SAP 75
  • 76. Refresh Semi-Finished 1 Product Status (cont.) REFRESH OF SEMI FINISHED 1 PRODUCT STATUS ATTENTION POINTS 3 Recheck process chain with transaction CM25. This confirms that Finished product production order is protected in terms of Fished Strip planning. Zero delay is expected Receipt qty exceeds demand Source: SAP This concludes the planning of the Drum and how the Drum scheduling requirements are transferred to Semi- Finished 1 with the required buffer. 76
  • 77. What We’ll Cover … • Manufacturing throughput • Theory of Constraints (TOC) methodology • Explanation of Drum, Buffer, Rope (DBR) technique • A Theory of Constraint case study • Applying the Theory of Constraint technique within SAP • Applying the Theory of Constraint technique within SAP PPDS • Wrap-up 77
  • 78. Master Data Objects: Product Master MASTER DATA OBJECTS 1 Product master The product master is replicated to PPDS using the CIF. PPDS enables you to assign unique heuristic. A custom heuristic could be created to replicate the MPS logic, so that finished products are planned first on CCR and the sub- components are planned accordingly. 2 Work-centre; Resources Work centres are replicated to PPDS as resources. From a production perspective they will be time-continuous. CCR resource will be flagged as bottleneck resource. Source: SAP
  • 79. Master Data Objects: Work Center (cont.) MASTER DATA OBJECTS 2 Work centre; Resources The following resource types will be replicated: • Single activity resource; therefore only one production order may generate requirements. • Multi-mixed resource; multiple production order may generate requirements. • Mixed resources; these resources can be used in both PPDS and SNP. Using SNP is critical to get a medium term view for production specifically to determine if the CCR capacity is absorbing expected demand; if current shift policy has to be changed. SNP also enables you to carry out simulation in different versions and models. Critical considerations regarding scheduling and capacity: • CCR that determines the throughput of the manufacturing plant will be flagged as bottleneck resource. • Secondary critical resource can be flagged as Finite leveling. • The finiteness level is critical to group resources together. This grouping can be run in a separate heuristic step. • The resources that have specific finiteness level can have unique strategy profile. This is critical for DBR when it comes to synchronizing with the CCR resource. Note: resources that are not flagged as finite are planned infinitely. The alert monitor will provide overload for these resources. Critical for Buffer Management. Source: SAP
  • 80. Master Data Objects: Work Center (cont.) MASTER DATA OBJECTS 2 Work-centre; Resources Critical consideration for the resource that have finiteness specific setting • Scheduling model • Planning direction The above is critical to have a streamlined scheduling on resources. Work-centre; CCR Resources The CCR resource flagged as bottleneck resources are scheduled using mid-point scheduling. A second step plans the remaining resources that have their unique scheduling mode and planning direction. Source: SAP
  • 81. Master Data Objects: Routing MASTER DATA OBJECTS 3 Routing; PPM /PDS Routings are replicated as either PPM or PDS. For a DBR project consider the following: • Change management: In PPM there is no change mgt. Changes take effect immediately. • Modification in the PPDS system. PDS do not allow changes, therefore all changes have to be managed in routing in ECC and replicated. From a DBR project perspective, PPM provides the most flexibility. Note: PPM/PDS are not needed if planning option is plan with MRP in ERP and scheduling in PPDS Source: SAP
  • 82. Master Data Objects: Setup Matrix MASTER DATA OBJECTS 4 Setup Matrix For CCR where setup plays an important role, the sequence dependant setup and setup costs are fundamental in reducing setup time. Reducing setup is fundamental in elevating CCR output. The setup matrix will be used with the PPDS optimizer. The purpose of the optimizer is to determine ideal sequence dependant operation taking into consideration cost, penalty, delay, etc. Therefore, optimization with reason. Source: SAP
  • 83. Planning Considerations PLANNING CONSIDERATION In order to introduce DBR planning technique in PPDS the following aspects are to be considered: 1 Master data, Resource types need to be replicated correctly (single, multi, mixed). resource, Resources (CCR) that impact throughput need to be correctly indentified. Related secondary resources that can creep to CCR need also to be identified with assigned product and finiteness level. PPM PPM (routing) needs to be accurate ; execution times and setup time must be accurate. Setup matrix to be included where set-up plays a big role in CCR. 2 Important to define relevant heuristics and strategy profile for detail scheduling in order to ensure an accurate and realistic production plan that tries to achieve maximum Heuristics and throughput on the CCR. strategy profiles Set up an ideal planning cycle that plans the Drum at the CCR by means of finite 3 Planning planning, include planning steps to synchronize related planning sub-assembly and components to satisfy the Drum schedule. Monitor alerts regarding resource loading on Cycle non CCR. Set up buffer parameters; this can be set up by product family; use material group; grouping 4 Buffer such as components, semi-finished, and finished in grouping. In each group, define buffer parameters. management 83
  • 84. Planning Sequence Steps PLANNING SEQUENCE STEPS 1 Stage Numbering SAP_PP_020 Algorithm: To determine low level code SAP_MRP_001 2 Material Requirement Infinite planning; planning object PRODUCT Planning; product Heuristic; finished, sub- assemble and components SAP001 Function; Optimization of CCR resources in Detailed Scheduling Source: SAP 3 Optimization of CCR Planning Board. Defines the Drum for CCR 4 Propagation & delays of Re-plan based on components; re-schedule confirmed Drum bottom up. 5 Review overloads Detailed In APO PPDS, it is easy to construct the Scheduling Planning Board on automatic production planning process with non CCR, review buffer several steps. The individual steps are penetration simply specified in the planning run.