Anúncio
Anúncio

Mais conteúdo relacionado

Anúncio

PRESENTATION- APS GEMPOL EXPANSION PROJECT.pptx

  1. A. INTRODUCTION CONSTRUCTION PLANNING
  2. A.1. PROJECT INFORMATION 1. PROJECT NAME : PT. LYONDELLBASELL 2. PROJECT LOCATION : GEMPOL PASURUAN - JAWA TIMUR 3. OWNER : APS GEMPOL EXPANSION PROJECT 4. SCOPE OF WORK : Civil, Structure & Architecture 6. CONSTRUCTION PERIOD : (5 Calendar Months) CONSTRUCTION PLANNING
  3. B. CONSTRUCTION PLANNING CONSTRUCTION PLANNING
  4. 12/18/2022 CONSTRUCTION PLANNING SITE FACILITY
  5. 12/18/2022 CONSTRUCTION PLANNING SEQUENCE & PLANNING SCHEDULE A F IL L IN G L IN E (W E E K 0 1 - W E E K 2 1 ) B D E B A G G IN G & P R E M IX IN G (W E E K 0 3 -W E E K 2 0 ) C C O M P R E S S O R (W E E K 0 4 - W E E K 1 2 ) D M V & L V (W E E K 0 5 - W E E K 1 5 ) E T R A N S F O R M E R (W E E K 0 6 - W E E K 2 1 ) F C O O L IN G T O W E R (W E E K 0 8 W E E K 1 7 ) G P A N T R Y R O O M (W E E K 0 9 - W E E K 1 8 ) H F U M E (W E E K 1 0 - W E E K 1 7 ) I F U R N A C E (W E E K 1 0 - W E E K 2 2 )
  6. 12/18/2022 CONSTRUCTION PLANNING DEMOLISH EXISTING AREA (EQUIPMENT USED) EXCAVATOR CRAWLER WITH RUBBER TIRE DUMP TRUCK AREA DEMOLISH
  7. CONSTRUCTION PLANNING SEQUENCE OF WORK FOR STEEL STRUCTURE
  8. YES NO YES NO DAILY INSPECTION NOTICE VERIFY,JOINT INSPECTION WITH OWNER FINISH PRODUCT A B C VERIFY INTERNAL INSPECTION GENERAL QUALITY CONTROL FLOWCHART FOR CONSTRUCTION WORKS (2) CONSTRUCTION PLANNING
  9. YES NO YES NO QUALITY CONTROL RECEIVING MATERIAL PLAN QUALITY CONTROL DEPARTMENT 1. INSPECTION & TEST PLAN 2. QC SHEET FORM WAREHOUSE APPROVED MATERIAL START FINISH ENGINEERING DEPARTMENT 1. APPROVAL MATERIAL 2. SAMPLE PROCUREMENT/PURCHASING DEPARTMENT PURCHASING ORDER (PO) SUPPLIER MATERIAL PRODUCTION DEPARTMENT SURAT PERMINTAAN PENGADAAN BARANG (SPP) PROJECT MANAGER 1. FOR CONSTRUCTION DWG 2. TECHNICAL SPECIFICATION 3. GENERAL NOTES VERIFY MATERIAL RECEIVING INSPECTION VERIFY INDEPENDENT LABORATORIU M CONSTRUCTION PLANNING
  10. b. Execution YES NO YES NO OK QUALITY CONTROL INSPECTION FOR CONCRETING GROUND SLAB PLAN (1) QUALITY CONTROL DEPARTMENT VERIFY INTERNAL INSPECTION INSTALL SCAFFOLDING & FORM WORK PRODUCTION DEPARTMENT START ENGINEERING DEPARTMENT 1. DETAIL DWG/SHOP DWG 2. WORK PROCEDURES 3. WORK INSTRUCTIONS PROCUREMENT DEPARTMENT / E N T DEPARTMENT 1. INSPECTION AND TEST PLAN 2. QC SHEET FORM SUPPLY EQUIPMENT, TOOLS AND MATERIAL PREPARATION FOR MAN POWER, EQUIPMENT, MATERIAL AND TIME SCHEDULE PROJECT MANAGER 1. FOR CONSTRUCTION DWG 2. TECHNICAL SPECIFICATION 3. GENERAL NOTES VERIFY, MATERIAL RECEIVING & CALIBRATION INSPECTION A B INSTALL REBAR BEAM, SLAB & STARTER BAR C VERIFY INTERNAL INSPECTION a. Preparing CONSTRUCTION PLANNING
  11. YES NO YES NO YES QUALITY CONTROL INSPECTION FOR CONCRETING GROUND SLAB PLAN (2) DAILY INSPECTION NOTICE FINISH ORDER CONCRETE TO BATCHING PLANT C VERIFY,JOINT INSPECTION WITH OWNER A B REQUEST FOR HANDLING CONCRETE CONCRETE CONCRETE INSPECTION FOR SLUMP VERIFY INTERNAL INSPECTION INSTALL LEVELING TOP CONCRETE & CLEANING CONSTRUCTION PLANNING
  12. b. Execution YES NO OK QUALITY CONTROL INSPECTION FOR CONCRETING COLUMN PLAN (1) QUALITY CONTROL DEPARTMENT SETTING OUT AND MARKING POSITION FOR COLUMN PRODUCTION DEPARTMENT START ENGINEERING DEPARTMENT 1. DETAIL DWG/SHOP DWG 2. WORK PROCEDURES 3. WORK INSTRUCTIONS PROCUREMENT DEPARTMENT / E N T DEPARTMENT 1. INSPECTION AND TEST PLAN 2. QC SHEET FORM SUPPLY EQUIPMENT, TOOLS AND MATERIAL PREPARATION FOR MAN POWER, EQUIPMENT, MATERIAL AND TIME SCHEDULE PROJECT MANAGER 1. FOR CONSTRUCTION DWG 2. TECHNICAL SPECIFICATION 3. GENERAL NOTES VERIFY, MATERIAL RECEIVING & CALIBRATION INSPECTION A B REQUEST FOR HANDLING CONCRETE C VERIFY INTERNAL INSPECTION a. Preparing INSTALL REBAR CLEANING CONSTRUCTION PLANNING
  13. YES NO YES NO YES NO YES NO QUALITY CONTROL INSPECTION FOR CONCRETING COLUMN PLAN (2) VERIFY,JOINT INSPECTION WITH OWNER FINISH ORDER CONCRETE TO BATCHING PLANT INSTALL FORMWORK VERIFY,JOINT INSPECTION WITH OWNER A B C CONCRETE CONCRETE INSPECTION FOR SLUMP DAILY INSPECTION NOTICE VERIFY INTERNAL INSPECTION DAILY INSPECTION NOTICE CONSTRUCTION PLANNING
  14. I. Making Safety Plan • Forming a HSE project organization, • List of equipment that need special handling, • Hazard identification and prevention, • HSE site plan, • Hygiene program and brief, clean, neatly, diligent, & treatment. II. Prepare HSE supporting equipment and personal protective equipment • Fire extinguishers, • HSE signs, • Safety instruction, • Supporting tools: temporary toilet, urinoir, & water pump equipment, • Helmet, safety belt, mask , safety shoes, safety belt, & medicine box. III. Cooperation with Hospital, Clinic and insure Labour to Jamsostek (Labour insurance) CONSTRUCTION PLANNING B.6. HSE PROGRAM
  15. Safety, Security & Housekeeping Program Project Start Planning Organizing Controlling Clean, Organize, Healthy & Safe -Project Safety Objective -Risk Assessment and Risk Management -Site Safety Plan -Safety, Security, and Environment budget -Forming safety organization and safety committee -Standard and procedure of safe work practice -Inspection Plan -Audit CONSTRUCTION PLANNING
  16. Corporate Organization CONSTRUCTION PLANNING
  17. Project Organization PROJECT OPERATION GENERAL MANAGER PROJECT MANAGER ENGINEERING MANAGER CONSTRUCTION MANAGER ADMINISTRATION G / A HSE MANAGER HSE COMMITTEE Chairman : Safety Officer Member : PM, Eng.Mng, Const. Mgr Sub Member : Sub Contractor PM SAFETY ENGINEER SAFETY INSPECTOR SUPERVISOR CIVIL / FINISHING SUPERVISOR M / E / P SURVEYOR MECHANIC & OPERATOR CONSTRUCTION PLANNING
  18. EHS MEETING PROGRAM Description Of Meeting Schedule Chairman & Attendants 1. Morning Gathering Daily Chaired by HSE Officer to be attended by safety Supervisors, and field workers. 2. Tool Box Meeting Daily Chaired by construction Supervisors assisted HSE supervisor to be attended by crafts foremen personnel. 3. Security Meeting Daily Chaired by HSE officer, to be attended by security personnel. 4. Supervisors Progress and Safety Meeting Weekly Chaired by HSE Manager/ Officer or construction manager, to be attended by HSE supervisors, construction engineers and supervisors. 5. Progress and Safety Meeting Monthly Chaired by Project Manager and or HSE Manager to be attended by HSE officers, construction Engineers 6. Meeting for specific accident/ incident Decided by HSE Manager or Officer Chaired by HSE Manager or Office to ber attended by concerned individuals.
  19. GENERAL INSPECTION PROGRAM HSE Particulars General Inspection Checklist House Keeping And fire Protection Waste disposal, cleaning methods, access ways, material/ tools/ equipment storage, extinguisher, alarm, non smoking areas, response instructions, emergency exits, sign boards. Excavation/ Trenches Shoring, Civil Works Barricades, warning sign in place, access ways, work procedures, work practices, work permits. Personal Protective Gadget Safety helmet, hand gloves, safety footwear, eye protection, hearing protection, respirator, safety belt. Confined Space Entry, Restricted Area, Hazardous Work, Lock out/ Tag out Work permits, Barricades, warning, sign in place, access ways, ventilation, work procedures, work practices, lock out and tag out sign Electrical Works Breakers switches, fuses, grounding, lock out/ tag out, plugs, warning sign, distribution boards, equipment & tools, work procedures, work permit. Mechanical Works, Equipment Installation Machine guards, lighting levels, emergency shutdown, work space, barricades, work permit, work procedures, lock out/ tag out/ work practices. Welding And Other Hot Works Hot work permit, work procedure, work practices, equipment & tools, warning sign, ventilation, hot work protective gadgets. Scaffolding, Cappers, And Fall Protection Warning sign, walkways, ladders, stairs, bracing's, handrails, supports, safety net, work procedures, work permit. Rigging, Cranes, Material Handling Work procedures, work permit, work practices, slings, chains block, barricades, work space, warning sign, storage methods, handling methods, operators. Others (including Environmental and Health) Noise pollution, dust pollution, traffic sign, sanitary facilities, hygiene practices, waste management, hazardous material labeling, first aid facilities, other applicable items not included in above list.
  20. JOB SAFETY ANALYSIS Pre-Task analysis shall be undertaken for jobs with high risk nature. Risks and hazard shall be identified and work procedure shall be developed to minimize if not to totally eliminate such risks and hazards. A. Work Execution Procedure The work procedure is a documented step by step or sequencing of various tasks to guide the employees to perform and complete a particular activity. B. The work permit C. The work Permit provide rules and practices to guide employees safe behavior or action for critical tasks that have high risk potential. D. The following work activities shall or might require work procedure and work permits: • Hot works • Excavation, trenching and shoring work • Works on confined spaces or restricted areas • Utility Tie-ins or disconnection's • Works that involve hazardous materials/Compound • Scaffolding erection works • Heavy lighting and rigging works • Start-up and commissioning works For projects which requires Job Safety Analysis, HIRARC (Hazard Identification, Risk Assessment and Risk Control) will be changed into JSA format
  21. P S NO SMOKING FIRE PROHIBITED PASS PROHIBITED PASS PROHIBITED FIRIE EXTINGUISHIER EQUIPMENT NO PARKING NO STOP DO NOT OPEN THE PANEL OBLIGED TO WEAR SAFETY GLASS OBLIGED TO WEAR HELMET OBLIGED TO WEAR GAUNTLET OBLIGET TO WEAR SAFETY BELT OBLIGED TO WEAR SAFETY SHOES OBLIGED TO WEAR MASKER OBLIGED TO WEAR EARMUFF OBLIGED TO WEAR WLDING HELMET DANGER PATH DANGER PATH OF TOWER CRANE FLAMMABLE HIGH VOLTAGE MEDICATION CLINIC [FIRE/BURNING] DIRECTION MUST ER AREA SAFE AREA FOR EMERGENCY CONDITION BE CAREFULLY HSE SIGNED CONSTRUCTION PLANNING
  22. HSE APPLICATION ON SITE CONSTRUCTION PLANNING
  23. SITE INSPECTION SAFETY & HEALTH WEEKLY MEETING SAFETY MORNING MEETING HSE APPLICATION ON SITE CONSTRUCTION PLANNING
  24. FIRE FIGHTING TRAINING HSE APPLICATION ON SITE CONSTRUCTION PLANNING
  25. HSE APPLICATION ON SITE CONSTRUCTION PLANNING
  26. HSE SIGNS CONSTRUCTION PLANNING
  27. RAILING FOR PERIMETER AREA SAFETY NET SAFETY NET RAILING FOR STAIR HSE APPLICATION ON SITE CONSTRUCTION PLANNING

Notas do Editor

  1. 1
  2. 2
  3. 3
Anúncio