APM QSRA webinar; introduction for risk and planning professionals and decision makers

Association for Project Management
Association for Project Management Association for Project Management
QSRA: Introduction for risk/planning
professionals and decision-makers
Tony McDonald
James Kimmance
Graham Nicol
Welcome and Introduction
• Welcome on behalf of the Risk & PMC SIGs
• Today’s presenters
– Tony McDonald, Costain
– James Kimmance, Jacobs
– Graham Nicol, Turner and Townsend
• Many thanks to Maya and Anna from APM and
members of both SIGs
• Risk SIG Conference 2019 - Using Risk to Influence
the Future (26 Mar 19 in Birmingham)
Why is QSRA best practice and what do decision-
makers need from it?
• QSRA answers 3 key questions concerning overrunning project schedules
– Can overruns be predicted with some degree of accuracy?
– Can causes of risk be identified upfront, helping project to stop them happening
through effective response actions?
– Can risk professionals determine causes of why projects frequently overrun their
initial schedules?
• Overwhelmingly the answer is yes!
• Addresses head-on the fact that don’t know how long activities will take
• Allows investigation of activity ‘uncertainty’ to establish its effects on a project schedule
– How likely is the project to achieve the key dates & milestones in the schedule?
– How much schedule contingency is needed to provide acceptable degree of
certainty?
– Where is the greatest risk in the schedule?
• QSRA outputs provide a strong indication to key decision-makers of the key activities
and risks that will impact the project if not managed correctly project
References: ‘Practical Schedule Risk Analysis’ Hulett, David 2009’
QSRA is based on a good project schedule
• Scheduling is a challenging discipline
• Vital that a project’s risk and scheduling functions work closely together to
conduct QSRA, fully involving project managers/decision-makers from the start
– Build high-level analysis network derived from the project schedule
– Utilise schedulers knowledge of project schedule to ensure that all areas
are explored for potential risk
• QSRA high-level analysis network ‘criteria’
– Left-to-right, logic driven
– ‘Finish-to-Start’ or ‘Start-to-Finish’ predecessors & ‘Finish-to-Start’ or
‘Finish-to-Finish’ successors
– Not a ‘rolled up’ project schedule
– Overall activity durations/dates match project schedule
– Minimal/no use of constraints especially Late-Date constraints
– No dangling logic ‘danglers’
– Minimal/no use of lag/leads(‘negative lag’)
References: ‘Practical Schedule Risk Analysis’ Hulett, David 2009’
Quantitative Schedule Risk
Analysis
Uncertainty and Risk
Content
• Introduction
• A Simplified QSRA Process
• Project Uncertainty and Risk
• Cautionary observations
• The benefits The biggest uncertainty in risk
analysis is whether we started
off analysing the right thing and
in the right way
Introduction- QSRA objectives
• Quantitative Schedule Risk Analysis primarily
used to:
– provide risk based confidence forecasts of key
milestones
– support quantification of a projects schedule (and
cost) contingency requirements
– ......also drives other ‘good’ project behaviours
Introduction (contd)
• A wide variety of tools are available:
• Oracle PRA / Acumen Fuse Risk/ Safran Risk
• A large volume of quality literature and guides
are available
• Hulett, Hillson, GAO (USA), APM etc
• Aim is to provide a:
– ‘Quick Start’ introduction
– Do’s, Maybe’s and Don’ts
A Simplified QSRA Process
• Key simplified stages – appear straightforward
Schedule
Preparation
Assign
Activity
Uncertainty
MapRisk(s)
toActivities
ApplyRisk
Correlations
Incorporate
Probabilistic
Branching
Apply
Weather
Risk
Schedule
Health
Check
Run
Analyses
Review
Analyses
andModel
Interpretive
Report
* Not covered here
Maybe Not That Simple
• Schedule suitable for QSRA may need a ‘logic’
rework:
– Constraints (e.g. expected finish); lags etc
– Size/level ideally 200 – 500 activities, but 2000 possible
• Many things in ‘Risk’ are intuitively understood -
but in practice need clarification. Risk and
Uncertainty are two terms that often lack
clarity, consistency in application, and are often
confused / seen as interchangeable.
Schedule
Preparation
Assign
Activity
Uncertainty
MapRisk(s)
toActivities
Risk & Uncertainty
• A lot has been written in the Project (Risk)
Management space differentiating between
Risk & Uncertainty
• Defining Risk
• Many ‘variations’ – but on a theme with a large consistency
• APM PMBOK.. ‘an uncertain event or condition that, if it occurs,
has a positive or negative effect on the project objective’
• Typically: event based; quantifiable with probabilities of
occurrence; and impact on the project
Risk & Uncertainty (contd.)
• Defining Uncertainty….
• Uncertainty definitions in Project Management are less ubiquitous
and more nebulous
• “Uncertainty is a lack of certainty”; …….”uncertainty is understood
in its most basic form as not knowing for sure, due to lack of
information or ambiguous information”;…………
• Common themes are: absence of information; unknowing;
variability; ambiguity; and lack of clarity; a degree of ‘randomness’
about an average
Risk vs. Uncertainty
• For practical day to day purposes:
– A risk is a discrete event with a probability of
occurrence. The risk effect is only felt if the event
occurs
– Uncertainty is an occurrence that has no
probability, and you know that you don’t know the
actual value
• Effectively a normal activity i.e. – but for which there is
an inherent ‘variability’ caused by a variety of factors
• The variability can be captured as a range based on
‘experience’
Creating the model and data
• Key players are the Scheduler, Risk Manager,
Subject Matter Experts, and Project Managers
– Review and amend the schedule with logic in
mind (using schedule health check tool)
– Estimate activity uncertainty
• Individual activities – SME knowledge and experience –
or maybe even data sets from similar activities
• Possibly in groups of similar activities (quick templating)
for example Civils, M&E, ICT, New Technology,
Integration and Commissioning
Creating the model and data (contd.)
– Determine and map schedule impacting risks
• Assumptions analysis – capture necessary risks
• Review existing risk register
• Determine probabilities, and distribution type
– Typically Triangular, or Trigen, Uniform and BetaPert
• Map to activities in the schedule model
• Doing this properly requires significant
resources
• But there are significant benefits – at all stages of the
project
Cautionary Observations
• The schedule and uncertainty data are the key
building blocks upon which the QSRA relies:
• Don’t skimp on creating a suitably sized schedule, with
logic suitable for an analysis
• Look for and capture assumptions
• Prepare, and then challenge activity uncertainty with
SME’s
• Risks
• Don’t just ‘drag and dump’ risks from a general risk
register into the model
Cautionary Observations (contd.)
• With a QSRA model - do not
• Leave the process until last / when you have a ‘finished’
schedule
– It will be rushed / tick box exercise
– You will not get many of the benefits of investing
– May suggest you have a ‘potential’ nightmare (typically just
before you have to submit for finding approval)
• Miss out the SME’s and PM’s because they are ‘busy’
• Try to ‘game’ the result
– Often reflected in some strange outputs and reports
Benefits
• QSRA’s can be resource consuming so
maximising benefits are important.
• Even at an early stage:
– Overruns can be associated with a lack of in depth
analysis / challenge at the planning (or even
bidding) stage. When we can more easily change
things………..
– Unrealistic or overly optimistic plans identified.
– Going through the process can identify what you
don’t know (and need to focus on) as much as
what you think you know.
Benefits (contd.)
• Subsequent stages
• We identify those activities and risks which are having
the biggest impact on our schedule (and costs)
• Prioritise and support the development of mitigation
activities
Interpretation of QSRA Outputs
Interpretation of QSRA Outputs
• The interpretation of QSRA Outputs and how
they are reported is probably the most critical
aspect of the QSRA process
• A lot of work will have gone into producing
the outputs
• However, the QSRA outputs can be extremely
sensitive if presented without context or
without challenge!
Challenges with QSRA Outputs
• Key messages can often be hidden away in
lengthy QSRA reports
• Single Pnumbers i.e P50 confidence – Date ‘X’
don’t actually inform a decision
• Decision makers struggle to grasp what QSRA
outputs are telling them and the value of the
QSRA process is often lost on them
• Often Practitioners can’t explain what’s driving
the analysis or what’s gone into the model
Interpretation of QSRA Outputs- Back
to Basics
• Why do QSRAs in the first place?
– Inform contingency discussions/arrangements
– Provide confidence and assurance regarding
schedule assumptions and integrity
– Identify key risks to delivery and highlight
sensitive areas within the project schedule
– Provides a range of outcomes
– Model various scenarios
Risk Practitioner Questions to Ask…
When questioned by decision makers/senior
management re. QSRA outputs…can I:
– Detail the quality of inputs that went into the model i.e.
management signed off schedules, uncertainty and risk
inputs
– Outline what scenarios have been modelled and any
assumptions and exclusions
– Demonstrate that the QSRA process was iterative and
involved all key stakeholders
– Agree what are the base dates, milestones etc in the
schedule that the QSRA outputs should be compared
against…doesn’t always have to just be the end date!
QSRA Outputs-Distribution Outputs (Pre-Mit)
Pre-mitigated position (assuming no mitigation in place or effective)
1% chance of hitting the base date (Gold arrow)
P50 output (Blue arrow)- 10/04/2024…some 534 days after base date!
QSRA Outputs-Distribution Outputs (Post-Mit)
Post- mitigated position (assuming identified mitigation successful!)
26% chance of hitting the base date (Gold arrow)
P50 output (Blue Arrow)- 25/07/2023…now 274 days after base date an
improvement of 260 days!
QSRA Outputs - Distribution Analyser
Plan Outcomes with
Uncertainty and Pre-Mitigated
RiskPlan Outcomes with
Uncertainty and Post-
Mitigated Risk
Potentially 260 days saving
if the proposed mitigations
are successful at P50!
QSRA Outputs - Tornado Graphs
What’s causing these
top 2 risks to drive the
QSRA model?
Why are delivery to site
activities so sensitive to
uncertainty and risk?
QSRA Outputs – Scatter Graphs
Interpretation of QSRA Outputs
• Be clear on what has gone into the model in terms of
quality inputs
• Present ranges rather than Single Pnumbers…
– P50 date is ‘X’ but considering the P75 output would give an
additional 2 weeks time risk allowance?
• Present the delta of the analysis compared to base data
• Be clear on pre and post-mitigated positions
– Why are certain risks more prominent than others?
– What drives reduction in exposure?
– Are mitigations robust to merit the reduction in exposure?
Q&A
Questions?
Thank You
This presentation was
delivered
at an APM webinar
To find out more about upcoming webinars
please visit our website
www.apm.org.uk/events
1 de 33

Recomendados

Project Management por
Project ManagementProject Management
Project ManagementDavid Edgerton, Jr.
2.1K visualizações33 slides
The 3 actual’s 3Gen por
The 3 actual’s  3GenThe 3 actual’s  3Gen
The 3 actual’s 3Genleansavant
6.2K visualizações4 slides
Giving Presentations to Senior Managers por
Giving Presentations to Senior ManagersGiving Presentations to Senior Managers
Giving Presentations to Senior Managersdeanpbriggs
21.5K visualizações17 slides
Spm unit iii-risk-monitoring & control1 por
Spm unit iii-risk-monitoring & control1Spm unit iii-risk-monitoring & control1
Spm unit iii-risk-monitoring & control1Kanchana Devi
1.5K visualizações25 slides
Cost Management PMBOK por
Cost Management PMBOKCost Management PMBOK
Cost Management PMBOKWasis Witjaksono
377 visualizações28 slides
Visio-Planning FlowChart-3 por
Visio-Planning FlowChart-3Visio-Planning FlowChart-3
Visio-Planning FlowChart-3Allan Leyte
4.7K visualizações3 slides

Mais conteúdo relacionado

Mais procurados

Getting it Done: Project Management Theory por
Getting it Done: Project Management TheoryGetting it Done: Project Management Theory
Getting it Done: Project Management TheoryConverge Consulting
2.2K visualizações68 slides
PMP Training - 11 project risk management por
PMP Training - 11 project risk managementPMP Training - 11 project risk management
PMP Training - 11 project risk managementejlp12
36.1K visualizações32 slides
Focus on the nine I's (v9) por
Focus on the nine I's (v9)Focus on the nine I's (v9)
Focus on the nine I's (v9)Glen Alleman
8.4K visualizações93 slides
Il Ciclo Di Vita Del Progetto por
Il Ciclo Di Vita Del ProgettoIl Ciclo Di Vita Del Progetto
Il Ciclo Di Vita Del ProgettoAliante
5.4K visualizações45 slides
PROJECT SCHEDULING por
PROJECT SCHEDULINGPROJECT SCHEDULING
PROJECT SCHEDULINGShahrukh Vahora
590 visualizações43 slides
PMP Chap4-Project Integration Management Details: Part-2 por
PMP Chap4-Project Integration Management Details: Part-2PMP Chap4-Project Integration Management Details: Part-2
PMP Chap4-Project Integration Management Details: Part-2Anand Bobade
7.1K visualizações100 slides

Mais procurados(20)

Getting it Done: Project Management Theory por Converge Consulting
Getting it Done: Project Management TheoryGetting it Done: Project Management Theory
Getting it Done: Project Management Theory
Converge Consulting2.2K visualizações
PMP Training - 11 project risk management por ejlp12
PMP Training - 11 project risk managementPMP Training - 11 project risk management
PMP Training - 11 project risk management
ejlp1236.1K visualizações
Focus on the nine I's (v9) por Glen Alleman
Focus on the nine I's (v9)Focus on the nine I's (v9)
Focus on the nine I's (v9)
Glen Alleman8.4K visualizações
Il Ciclo Di Vita Del Progetto por Aliante
Il Ciclo Di Vita Del ProgettoIl Ciclo Di Vita Del Progetto
Il Ciclo Di Vita Del Progetto
Aliante5.4K visualizações
PROJECT SCHEDULING por Shahrukh Vahora
PROJECT SCHEDULINGPROJECT SCHEDULING
PROJECT SCHEDULING
Shahrukh Vahora590 visualizações
PMP Chap4-Project Integration Management Details: Part-2 por Anand Bobade
PMP Chap4-Project Integration Management Details: Part-2PMP Chap4-Project Integration Management Details: Part-2
PMP Chap4-Project Integration Management Details: Part-2
Anand Bobade7.1K visualizações
Problem solving techniques por Ahsan Saleem
Problem solving techniquesProblem solving techniques
Problem solving techniques
Ahsan Saleem6K visualizações
6.5 The Forward and Backward Pass (Critical Path) por DavidMcLachlan1
6.5 The Forward and Backward Pass (Critical Path)6.5 The Forward and Backward Pass (Critical Path)
6.5 The Forward and Backward Pass (Critical Path)
DavidMcLachlan11.5K visualizações
Project Execution PowerPoint Presentation Slides por SlideTeam
Project Execution PowerPoint Presentation SlidesProject Execution PowerPoint Presentation Slides
Project Execution PowerPoint Presentation Slides
SlideTeam1.9K visualizações
01 pmp introduct to project management exam por Jamil Faraj , PMP
01 pmp introduct to project management exam01 pmp introduct to project management exam
01 pmp introduct to project management exam
Jamil Faraj , PMP5.7K visualizações
6.5 Develop Schedule por DavidMcLachlan1
6.5 Develop Schedule6.5 Develop Schedule
6.5 Develop Schedule
DavidMcLachlan1108 visualizações
12 Terms You Should Know Project Management Fundamentals por Insaf Ali Soomro PMP
12 Terms You Should Know Project Management Fundamentals12 Terms You Should Know Project Management Fundamentals
12 Terms You Should Know Project Management Fundamentals
Insaf Ali Soomro PMP236 visualizações
Project human resources management por Firmansyah Ashari
Project human resources managementProject human resources management
Project human resources management
Firmansyah Ashari12.6K visualizações
Chapt14 por Joe Christensen
Chapt14Chapt14
Chapt14
Joe Christensen458 visualizações
PMBOK GUIDE 7th Summary por Amr Miqdadi
PMBOK GUIDE 7th Summary PMBOK GUIDE 7th Summary
PMBOK GUIDE 7th Summary
Amr Miqdadi3.5K visualizações
Schedule levels-as-presented 02-may11 por PMA Consultants
Schedule levels-as-presented  02-may11Schedule levels-as-presented  02-may11
Schedule levels-as-presented 02-may11
PMA Consultants4.9K visualizações
Project management por meena velmurugan
Project managementProject management
Project management
meena velmurugan282 visualizações
Risk response planning.pptx por SaranSaravanan22
Risk response planning.pptxRisk response planning.pptx
Risk response planning.pptx
SaranSaravanan2266 visualizações

Similar a APM QSRA webinar; introduction for risk and planning professionals and decision makers

Essentials of Entry Level Project Management - Rev A por
Essentials of Entry Level Project Management - Rev AEssentials of Entry Level Project Management - Rev A
Essentials of Entry Level Project Management - Rev ASteve Kiester
127 visualizações29 slides
Project management por
Project managementProject management
Project managementHeather Marie Wells
286 visualizações34 slides
Project Management Principles and Process por
Project Management Principles and ProcessProject Management Principles and Process
Project Management Principles and ProcessCharles Cotter, PhD
12K visualizações64 slides
Projectriskmanagement pmbok5 por
Projectriskmanagement pmbok5Projectriskmanagement pmbok5
Projectriskmanagement pmbok5Dhamo daran
1.6K visualizações115 slides
Ppt.pptx por
Ppt.pptxPpt.pptx
Ppt.pptxnayeembanu1
3 visualizações31 slides
Getting the basics right por
Getting the basics rightGetting the basics right
Getting the basics rightThomas Cream
193 visualizações24 slides

Similar a APM QSRA webinar; introduction for risk and planning professionals and decision makers(20)

Essentials of Entry Level Project Management - Rev A por Steve Kiester
Essentials of Entry Level Project Management - Rev AEssentials of Entry Level Project Management - Rev A
Essentials of Entry Level Project Management - Rev A
Steve Kiester127 visualizações
Project Management Principles and Process por Charles Cotter, PhD
Project Management Principles and ProcessProject Management Principles and Process
Project Management Principles and Process
Charles Cotter, PhD12K visualizações
Projectriskmanagement pmbok5 por Dhamo daran
Projectriskmanagement pmbok5Projectriskmanagement pmbok5
Projectriskmanagement pmbok5
Dhamo daran1.6K visualizações
Ppt.pptx por nayeembanu1
Ppt.pptxPpt.pptx
Ppt.pptx
nayeembanu13 visualizações
Getting the basics right por Thomas Cream
Getting the basics rightGetting the basics right
Getting the basics right
Thomas Cream193 visualizações
Project Management - principles, practice and process por Charles Cotter, PhD
Project Management - principles, practice and process Project Management - principles, practice and process
Project Management - principles, practice and process
Charles Cotter, PhD3.3K visualizações
Project management by Dr. Huda Hassan por Dr Ghaiath Hussein
Project management by Dr. Huda HassanProject management by Dr. Huda Hassan
Project management by Dr. Huda Hassan
Dr Ghaiath Hussein86 visualizações
Mitigating cost and schedule risk with oracle primavera risk analysis - Oracl... por p6academy
Mitigating cost and schedule risk with oracle primavera risk analysis - Oracl...Mitigating cost and schedule risk with oracle primavera risk analysis - Oracl...
Mitigating cost and schedule risk with oracle primavera risk analysis - Oracl...
p6academy1.8K visualizações
2. PAE AcFn621 Ch-2 Principle ppt.pptx por ProfDrAnbalaganChinn
2. PAE AcFn621 Ch-2 Principle ppt.pptx2. PAE AcFn621 Ch-2 Principle ppt.pptx
2. PAE AcFn621 Ch-2 Principle ppt.pptx
ProfDrAnbalaganChinn7 visualizações
PROJECT CHARTER TEMPLATE GENERAL PROJECT INFORMATIONProject Na.docx por wkyra78
PROJECT CHARTER TEMPLATE GENERAL PROJECT INFORMATIONProject Na.docxPROJECT CHARTER TEMPLATE GENERAL PROJECT INFORMATIONProject Na.docx
PROJECT CHARTER TEMPLATE GENERAL PROJECT INFORMATIONProject Na.docx
wkyra788 visualizações
Integrating risk with earned value por Glen Alleman
Integrating risk with earned valueIntegrating risk with earned value
Integrating risk with earned value
Glen Alleman685 visualizações
Peoject Risk Management(quantative&qualitive) por Evgeni Tsonev
Peoject Risk Management(quantative&qualitive)Peoject Risk Management(quantative&qualitive)
Peoject Risk Management(quantative&qualitive)
Evgeni Tsonev814 visualizações
Risk management - A short course por Malcolm Peart
Risk management  - A short courseRisk management  - A short course
Risk management - A short course
Malcolm Peart620 visualizações
Risk Event Modeling and Event Chains por Intaver Insititute
Risk Event Modeling and Event ChainsRisk Event Modeling and Event Chains
Risk Event Modeling and Event Chains
Intaver Insititute69 visualizações
Quantitative Project Risk Analysis por Intaver Insititute
Quantitative Project Risk AnalysisQuantitative Project Risk Analysis
Quantitative Project Risk Analysis
Intaver Insititute2.7K visualizações
3. PAE AcFn621 Ch-3 Project Planning.ppt por ProfDrAnbalaganChinn
3. PAE AcFn621 Ch-3 Project Planning.ppt3. PAE AcFn621 Ch-3 Project Planning.ppt
3. PAE AcFn621 Ch-3 Project Planning.ppt
ProfDrAnbalaganChinn7 visualizações
Quantitative Project Risk Analysis por Intaver Insititute
Quantitative Project Risk AnalysisQuantitative Project Risk Analysis
Quantitative Project Risk Analysis
Intaver Insititute103 visualizações
Price.rick por NASAPMC
Price.rickPrice.rick
Price.rick
NASAPMC13.6K visualizações

Mais de Association for Project Management

Mindfulness.pdf por
Mindfulness.pdfMindfulness.pdf
Mindfulness.pdfAssociation for Project Management
21 visualizações12 slides
Integrated Cost and Schedule Risk Analysis (ICSRA), Demystified webinar, 14 N... por
Integrated Cost and Schedule Risk Analysis (ICSRA), Demystified webinar, 14 N...Integrated Cost and Schedule Risk Analysis (ICSRA), Demystified webinar, 14 N...
Integrated Cost and Schedule Risk Analysis (ICSRA), Demystified webinar, 14 N...Association for Project Management
346 visualizações53 slides
Presenting with Impact (APM) Oct 2023.pdf por
Presenting with Impact (APM) Oct 2023.pdfPresenting with Impact (APM) Oct 2023.pdf
Presenting with Impact (APM) Oct 2023.pdfAssociation for Project Management
195 visualizações9 slides
Benefits and Value and Governance SIG Conference, Building for Legacy - The L... por
Benefits and Value and Governance SIG Conference, Building for Legacy - The L...Benefits and Value and Governance SIG Conference, Building for Legacy - The L...
Benefits and Value and Governance SIG Conference, Building for Legacy - The L...Association for Project Management
334 visualizações38 slides
Benefits and Value and Governance SIG Conference, Prioritizing sustainability... por
Benefits and Value and Governance SIG Conference, Prioritizing sustainability...Benefits and Value and Governance SIG Conference, Prioritizing sustainability...
Benefits and Value and Governance SIG Conference, Prioritizing sustainability...Association for Project Management
328 visualizações12 slides
Benefits and Value and Governance SIG Conference, The Governance of Sustainab... por
Benefits and Value and Governance SIG Conference, The Governance of Sustainab...Benefits and Value and Governance SIG Conference, The Governance of Sustainab...
Benefits and Value and Governance SIG Conference, The Governance of Sustainab...Association for Project Management
334 visualizações14 slides

Mais de Association for Project Management (20)

Último

Rangell Auto Detailing por
Rangell Auto Detailing Rangell Auto Detailing
Rangell Auto Detailing rangellautodetailing
18 visualizações8 slides
Integrating Talent Management Practices por
Integrating Talent Management PracticesIntegrating Talent Management Practices
Integrating Talent Management PracticesSeta Wicaksana
150 visualizações29 slides
Quandoo - Passion - Matthias M.pptx por
Quandoo - Passion - Matthias M.pptxQuandoo - Passion - Matthias M.pptx
Quandoo - Passion - Matthias M.pptxMatthias Maximilian
23 visualizações5 slides
Basic of Air Ticketing & IATA Geography por
Basic of Air Ticketing & IATA GeographyBasic of Air Ticketing & IATA Geography
Basic of Air Ticketing & IATA GeographyMd Shaifullar Rabbi
69 visualizações27 slides
Root Cause Analysis (RCA) por
Root Cause Analysis (RCA)Root Cause Analysis (RCA)
Root Cause Analysis (RCA)Operational Excellence Consulting (Singapore)
53 visualizações28 slides
Netflix Inc. por
Netflix Inc.Netflix Inc.
Netflix Inc.125071027
11 visualizações11 slides

Último(20)

Integrating Talent Management Practices por Seta Wicaksana
Integrating Talent Management PracticesIntegrating Talent Management Practices
Integrating Talent Management Practices
Seta Wicaksana150 visualizações
Quandoo - Passion - Matthias M.pptx por Matthias Maximilian
Quandoo - Passion - Matthias M.pptxQuandoo - Passion - Matthias M.pptx
Quandoo - Passion - Matthias M.pptx
Matthias Maximilian23 visualizações
Basic of Air Ticketing & IATA Geography por Md Shaifullar Rabbi
Basic of Air Ticketing & IATA GeographyBasic of Air Ticketing & IATA Geography
Basic of Air Ticketing & IATA Geography
Md Shaifullar Rabbi 69 visualizações
Netflix Inc. por 125071027
Netflix Inc.Netflix Inc.
Netflix Inc.
12507102711 visualizações
Navigating EUDR Compliance within the Coffee Industry por Peter Horsten
Navigating EUDR Compliance within the Coffee IndustryNavigating EUDR Compliance within the Coffee Industry
Navigating EUDR Compliance within the Coffee Industry
Peter Horsten46 visualizações
Bloomerang Thank Yous Dec 2023.pdf por Bloomerang
Bloomerang Thank Yous Dec 2023.pdfBloomerang Thank Yous Dec 2023.pdf
Bloomerang Thank Yous Dec 2023.pdf
Bloomerang140 visualizações
Why are KPIs(key performance indicators) important? por Epixel MLM Software
Why are KPIs(key performance indicators) important? Why are KPIs(key performance indicators) important?
Why are KPIs(key performance indicators) important?
Epixel MLM Software20 visualizações
Amazing Opportunities: PCD Pharma Franchise in Kerala.pptx por SaphnixMedicure1
Amazing Opportunities: PCD Pharma Franchise in Kerala.pptxAmazing Opportunities: PCD Pharma Franchise in Kerala.pptx
Amazing Opportunities: PCD Pharma Franchise in Kerala.pptx
SaphnixMedicure123 visualizações
davood_keshavarz_david_keshavarz_criminal_conviction_prison_sentence_judgemen... por morshedislam3
davood_keshavarz_david_keshavarz_criminal_conviction_prison_sentence_judgemen...davood_keshavarz_david_keshavarz_criminal_conviction_prison_sentence_judgemen...
davood_keshavarz_david_keshavarz_criminal_conviction_prison_sentence_judgemen...
morshedislam318 visualizações
The Talent Management Navigator Performance Management por Seta Wicaksana
The Talent Management Navigator Performance ManagementThe Talent Management Navigator Performance Management
The Talent Management Navigator Performance Management
Seta Wicaksana35 visualizações
Engaging Senior Leaders to Accelerate Your Continuous Improvement Program por KaiNexus
Engaging Senior Leaders to Accelerate Your Continuous Improvement ProgramEngaging Senior Leaders to Accelerate Your Continuous Improvement Program
Engaging Senior Leaders to Accelerate Your Continuous Improvement Program
KaiNexus12 visualizações
Accounts Class 12 project cash flow statement and ratio analysis por JinendraPamecha
Accounts Class 12 project cash flow statement and ratio analysisAccounts Class 12 project cash flow statement and ratio analysis
Accounts Class 12 project cash flow statement and ratio analysis
JinendraPamecha50 visualizações
Accel_Series_2023Autumn_En.pptx por NTTDATA INTRAMART
Accel_Series_2023Autumn_En.pptxAccel_Series_2023Autumn_En.pptx
Accel_Series_2023Autumn_En.pptx
NTTDATA INTRAMART209 visualizações
The Truth About Customer Journey Mapping por Aggregage
The Truth About Customer Journey MappingThe Truth About Customer Journey Mapping
The Truth About Customer Journey Mapping
Aggregage117 visualizações

APM QSRA webinar; introduction for risk and planning professionals and decision makers

  • 1. QSRA: Introduction for risk/planning professionals and decision-makers Tony McDonald James Kimmance Graham Nicol
  • 2. Welcome and Introduction • Welcome on behalf of the Risk & PMC SIGs • Today’s presenters – Tony McDonald, Costain – James Kimmance, Jacobs – Graham Nicol, Turner and Townsend • Many thanks to Maya and Anna from APM and members of both SIGs • Risk SIG Conference 2019 - Using Risk to Influence the Future (26 Mar 19 in Birmingham)
  • 3. Why is QSRA best practice and what do decision- makers need from it? • QSRA answers 3 key questions concerning overrunning project schedules – Can overruns be predicted with some degree of accuracy? – Can causes of risk be identified upfront, helping project to stop them happening through effective response actions? – Can risk professionals determine causes of why projects frequently overrun their initial schedules? • Overwhelmingly the answer is yes! • Addresses head-on the fact that don’t know how long activities will take • Allows investigation of activity ‘uncertainty’ to establish its effects on a project schedule – How likely is the project to achieve the key dates & milestones in the schedule? – How much schedule contingency is needed to provide acceptable degree of certainty? – Where is the greatest risk in the schedule? • QSRA outputs provide a strong indication to key decision-makers of the key activities and risks that will impact the project if not managed correctly project References: ‘Practical Schedule Risk Analysis’ Hulett, David 2009’
  • 4. QSRA is based on a good project schedule • Scheduling is a challenging discipline • Vital that a project’s risk and scheduling functions work closely together to conduct QSRA, fully involving project managers/decision-makers from the start – Build high-level analysis network derived from the project schedule – Utilise schedulers knowledge of project schedule to ensure that all areas are explored for potential risk • QSRA high-level analysis network ‘criteria’ – Left-to-right, logic driven – ‘Finish-to-Start’ or ‘Start-to-Finish’ predecessors & ‘Finish-to-Start’ or ‘Finish-to-Finish’ successors – Not a ‘rolled up’ project schedule – Overall activity durations/dates match project schedule – Minimal/no use of constraints especially Late-Date constraints – No dangling logic ‘danglers’ – Minimal/no use of lag/leads(‘negative lag’) References: ‘Practical Schedule Risk Analysis’ Hulett, David 2009’
  • 6. Content • Introduction • A Simplified QSRA Process • Project Uncertainty and Risk • Cautionary observations • The benefits The biggest uncertainty in risk analysis is whether we started off analysing the right thing and in the right way
  • 7. Introduction- QSRA objectives • Quantitative Schedule Risk Analysis primarily used to: – provide risk based confidence forecasts of key milestones – support quantification of a projects schedule (and cost) contingency requirements – ......also drives other ‘good’ project behaviours
  • 8. Introduction (contd) • A wide variety of tools are available: • Oracle PRA / Acumen Fuse Risk/ Safran Risk • A large volume of quality literature and guides are available • Hulett, Hillson, GAO (USA), APM etc • Aim is to provide a: – ‘Quick Start’ introduction – Do’s, Maybe’s and Don’ts
  • 9. A Simplified QSRA Process • Key simplified stages – appear straightforward Schedule Preparation Assign Activity Uncertainty MapRisk(s) toActivities ApplyRisk Correlations Incorporate Probabilistic Branching Apply Weather Risk Schedule Health Check Run Analyses Review Analyses andModel Interpretive Report * Not covered here
  • 10. Maybe Not That Simple • Schedule suitable for QSRA may need a ‘logic’ rework: – Constraints (e.g. expected finish); lags etc – Size/level ideally 200 – 500 activities, but 2000 possible • Many things in ‘Risk’ are intuitively understood - but in practice need clarification. Risk and Uncertainty are two terms that often lack clarity, consistency in application, and are often confused / seen as interchangeable. Schedule Preparation Assign Activity Uncertainty MapRisk(s) toActivities
  • 11. Risk & Uncertainty • A lot has been written in the Project (Risk) Management space differentiating between Risk & Uncertainty • Defining Risk • Many ‘variations’ – but on a theme with a large consistency • APM PMBOK.. ‘an uncertain event or condition that, if it occurs, has a positive or negative effect on the project objective’ • Typically: event based; quantifiable with probabilities of occurrence; and impact on the project
  • 12. Risk & Uncertainty (contd.) • Defining Uncertainty…. • Uncertainty definitions in Project Management are less ubiquitous and more nebulous • “Uncertainty is a lack of certainty”; …….”uncertainty is understood in its most basic form as not knowing for sure, due to lack of information or ambiguous information”;………… • Common themes are: absence of information; unknowing; variability; ambiguity; and lack of clarity; a degree of ‘randomness’ about an average
  • 13. Risk vs. Uncertainty • For practical day to day purposes: – A risk is a discrete event with a probability of occurrence. The risk effect is only felt if the event occurs – Uncertainty is an occurrence that has no probability, and you know that you don’t know the actual value • Effectively a normal activity i.e. – but for which there is an inherent ‘variability’ caused by a variety of factors • The variability can be captured as a range based on ‘experience’
  • 14. Creating the model and data • Key players are the Scheduler, Risk Manager, Subject Matter Experts, and Project Managers – Review and amend the schedule with logic in mind (using schedule health check tool) – Estimate activity uncertainty • Individual activities – SME knowledge and experience – or maybe even data sets from similar activities • Possibly in groups of similar activities (quick templating) for example Civils, M&E, ICT, New Technology, Integration and Commissioning
  • 15. Creating the model and data (contd.) – Determine and map schedule impacting risks • Assumptions analysis – capture necessary risks • Review existing risk register • Determine probabilities, and distribution type – Typically Triangular, or Trigen, Uniform and BetaPert • Map to activities in the schedule model • Doing this properly requires significant resources • But there are significant benefits – at all stages of the project
  • 16. Cautionary Observations • The schedule and uncertainty data are the key building blocks upon which the QSRA relies: • Don’t skimp on creating a suitably sized schedule, with logic suitable for an analysis • Look for and capture assumptions • Prepare, and then challenge activity uncertainty with SME’s • Risks • Don’t just ‘drag and dump’ risks from a general risk register into the model
  • 17. Cautionary Observations (contd.) • With a QSRA model - do not • Leave the process until last / when you have a ‘finished’ schedule – It will be rushed / tick box exercise – You will not get many of the benefits of investing – May suggest you have a ‘potential’ nightmare (typically just before you have to submit for finding approval) • Miss out the SME’s and PM’s because they are ‘busy’ • Try to ‘game’ the result – Often reflected in some strange outputs and reports
  • 18. Benefits • QSRA’s can be resource consuming so maximising benefits are important. • Even at an early stage: – Overruns can be associated with a lack of in depth analysis / challenge at the planning (or even bidding) stage. When we can more easily change things……….. – Unrealistic or overly optimistic plans identified. – Going through the process can identify what you don’t know (and need to focus on) as much as what you think you know.
  • 19. Benefits (contd.) • Subsequent stages • We identify those activities and risks which are having the biggest impact on our schedule (and costs) • Prioritise and support the development of mitigation activities
  • 21. Interpretation of QSRA Outputs • The interpretation of QSRA Outputs and how they are reported is probably the most critical aspect of the QSRA process • A lot of work will have gone into producing the outputs • However, the QSRA outputs can be extremely sensitive if presented without context or without challenge!
  • 22. Challenges with QSRA Outputs • Key messages can often be hidden away in lengthy QSRA reports • Single Pnumbers i.e P50 confidence – Date ‘X’ don’t actually inform a decision • Decision makers struggle to grasp what QSRA outputs are telling them and the value of the QSRA process is often lost on them • Often Practitioners can’t explain what’s driving the analysis or what’s gone into the model
  • 23. Interpretation of QSRA Outputs- Back to Basics • Why do QSRAs in the first place? – Inform contingency discussions/arrangements – Provide confidence and assurance regarding schedule assumptions and integrity – Identify key risks to delivery and highlight sensitive areas within the project schedule – Provides a range of outcomes – Model various scenarios
  • 24. Risk Practitioner Questions to Ask… When questioned by decision makers/senior management re. QSRA outputs…can I: – Detail the quality of inputs that went into the model i.e. management signed off schedules, uncertainty and risk inputs – Outline what scenarios have been modelled and any assumptions and exclusions – Demonstrate that the QSRA process was iterative and involved all key stakeholders – Agree what are the base dates, milestones etc in the schedule that the QSRA outputs should be compared against…doesn’t always have to just be the end date!
  • 25. QSRA Outputs-Distribution Outputs (Pre-Mit) Pre-mitigated position (assuming no mitigation in place or effective) 1% chance of hitting the base date (Gold arrow) P50 output (Blue arrow)- 10/04/2024…some 534 days after base date!
  • 26. QSRA Outputs-Distribution Outputs (Post-Mit) Post- mitigated position (assuming identified mitigation successful!) 26% chance of hitting the base date (Gold arrow) P50 output (Blue Arrow)- 25/07/2023…now 274 days after base date an improvement of 260 days!
  • 27. QSRA Outputs - Distribution Analyser Plan Outcomes with Uncertainty and Pre-Mitigated RiskPlan Outcomes with Uncertainty and Post- Mitigated Risk Potentially 260 days saving if the proposed mitigations are successful at P50!
  • 28. QSRA Outputs - Tornado Graphs What’s causing these top 2 risks to drive the QSRA model? Why are delivery to site activities so sensitive to uncertainty and risk?
  • 29. QSRA Outputs – Scatter Graphs
  • 30. Interpretation of QSRA Outputs • Be clear on what has gone into the model in terms of quality inputs • Present ranges rather than Single Pnumbers… – P50 date is ‘X’ but considering the P75 output would give an additional 2 weeks time risk allowance? • Present the delta of the analysis compared to base data • Be clear on pre and post-mitigated positions – Why are certain risks more prominent than others? – What drives reduction in exposure? – Are mitigations robust to merit the reduction in exposure?
  • 33. This presentation was delivered at an APM webinar To find out more about upcoming webinars please visit our website www.apm.org.uk/events