PRE-COMMISSIONING &
      COMMISSIONING

             A discussion on
             Pre-commissioning /
             Commissioning &
             Start Up of Projects




1
Contents

       Objective
       Common work at process plant at pipe
        line
       Definition of Mechanical Completion
       Pre-Commissioning Definition and
        Procedure

2
Contents(Continued)

       Activities (Piping & vessels, Mechanical,
        Electrical, Instrumentation, Operations)
       Check Sheets
       Punch Listing
       Completion Activities



3
Objectives


       Start-up and hand-over of the completed

        plant to the Client.

       To support client in operation of plant



                               .
4
COMMISSIONING
                                    & START-UP




MECHANICAL
COMPLETION
                                                    SYSTEM /   OPERATION
Inclusive of                        PLANT
                    COMMISSIONING                   PACKAGE    STAFF
Pre-commissioning                   START-UP
                                                    HANDOVER   TRAINING
Activities




                                                                           5
Commissioning Works
                       At Process Plants
        PIPING / VESSEL                                       ELECT / INSTRUM
•Flushing/Blowing                                      •Preliminary Check
•Chemical Cleaning                                     •Calibration
•Reinstatement                                         •Circuitry Check
•Gross leak with N2                                    •Continuity Check
•Drying                                                •Loop Test
•Inerting                                              • Energization (Power Up)
•Hydrocarbon In                                        •Performance Tests

                                MANAGEMENT
                          •Systems Breakdown
                          •Preparation of Procedures
                          •Loop Folder
                          •Circuit Folder
                          •Test Packs
                                                            CONTROL SYSTEM
    ROTATING EQUIPMENT                                 •SCADA / PCS SAT
•Alignment                                             •Fire & Gas System
•Belt Tensioning                                       •Safety Shutdown Sys.
•Motor Run in Test                                     •Alarm Set-Up & Test
•Vibration Test                                        •Simulation Test

                                                                                   6
Commissioning Works
                  At Pipe Lines
      PRECOMMISSIONING       SPECIALIZED PIPELINE CLEANING
•Cleaning                    •Dewaxing
•Flooding                    •Descaling
•Hydro testing               •De-oiling
•Dewatering & Drying         •Pit cleaning
•Flushing                    •Chemical cleaning
•Nitrogen Inserting          •Combined cleaning methods




     ASSOCIATED SERVICES           PIPELINE INSPECTION
•Temporary pipeline repair   •Geometry inspection
•On-site supervision         •Metal loss inspection
•Cathodic protection         •Crack detection
•Hot tapping & stoppling     •Leak detection and location
•Flow assurance Etc.         •Profile monitoring and mapping

                                                               7
Definition of Mechanical Completion
        & Construction Completion

       Mechanical Completion: A series of
        activities that MUST be completed prior to
        the commencement of Commissioning and
        Start-up of a Utility System or Main Process
        Unit.
       Mechanical Completion ALSO includes
        ALL pre-commissioning activities.

8
Pre-Commissioning Overview

       Process: Confirmation of Loops
        according to P& ID’s
       Vessels: Internal Inspection & Box up
       Piping: Hydro testing, reinstatement &
        verification of main gaskets.
       Stationary Equipment: Tightening and
        Final Box Up.
       Rotary Equipment: Leveling, Rotation,
9       Alignment & lubrications
Pre-Commissioning Activities –
                    Piping & Vessels

        Field checks as per isometrics and P&ID’s

        Verification of hydro testing

        Verification of flushing , blowing & drying

        Internal inspection of equipment as
         required

10
Pre-Commissioning Activities –
           Piping & Vessels(Continued)

        Verification of Internals
        Re-instatement of all flanges, control
         value, orifices, Psv’s and steam traps.
        Verification of blinds / spades installation
         and / or removal
        Box up: Pre-commissioned and closed



11
Pre-Commissioning Activities –
     Mechanical Discipline

        Verification of coupling and belt
         alignment

        Pumps / compressor checks

        Bearing lubrications

        Inspection / checking of filters & strainers

12
Pre-Commissioning Activities –
     Electrical Discipline

      MCC & UPS installation
      Field electrical installation
       – Cable Meggering (Continuity)
       – Termination of wiring; end devices
         to JB’s & MCC
       – Termination & Glanding according
         to area classification.

13
Pre-Commissioning Activities –
     Electrical Discipline(Continued)


        Motor installation

         –   Resistance maggering

         –   Rotation confirmation

         –   No load test run

14
Pre-Commissioning Activities -
                Instrumentation

        Instrument installation checks
        PSV calibration
        Calibration of transmitters and switches
        Loop checking of device end to PLC
        Function testing of PLC & ESD systems


15
Pre-Commissioning Check Sheets

        Vessel & Piping Check Sheets

        Mechanical Check Sheets

        Electrical Check Sheets

        Instrumentation Check Sheets


16      Operation / Process Check Sheets
Punch Listing

        Punch Lists are created and sorted as per disciplines
          – Piping and Vessels
          – Mechanical
          – Electrical
          – Instrumentation
          – Operations
        Punch Lists are categorized on a priority basis
          – Category “A”; MUST be completed prior to
             Commissioning
          – Category “B”; MUST be completed prior to Start-up
          – Category “C”; Signifies end of job
        Construction Contractor MUST have a coordinated
         management plan of Punch Listing including categorizing
         of punch list items
17
Completion Activities

        Flushing Blowing Certificates
        Box Up Certificate
        Mechanical Completion Certificate for
         each Utility and Process Unit
        Handover Certificate


18
COMMISSIONING

        Definition

        Utility Description

        Commissioning Activities

        Check Sheets

        Commissioning / Start Up Procedure
19
Systems Description

     Commissioning of The Following Systems
      Air Compression System

        MCC & Plant Lighting System
        UPS, PLC & Plant ESD System
        Fire Water System
        Fire & Gas Detection System


20
Systems Description

        Instrument Air Package
        Inert Gas Package
        Fuel Gas System
        Closed Drain & Waste Water Systems
        Condensate Transfer System
        Process Units; Reactor

21
Commissioning Check Sheets

        Commissioning check sheets are given in
         the Commissioning Protocol.




22
START-UP OF PROCESS UNITS

        Utilities in Service
        Introduction of Raw material (Vacuum Residue
         Feed)
        Introduction of Process Air & Steam
        Production of required grades of products
        Maintaining required proportion of off gases as
         per specs
        Achievement of required steam temperature
        Obtaining steam temperature compatible to
         system steam temperature.

23
Issues for Discussion.


        Less re-work SS304, 304L

        Carbon filter back flow

        Go for the standard packages

        15 KM pipeline

24
THANK YOU



25

Mais conteúdo relacionado

Mais procurados

Piping Hydrostatic Test / Hydrotesting
Piping Hydrostatic Test / HydrotestingPiping Hydrostatic Test / Hydrotesting
Piping Hydrostatic Test / HydrotestingAbhijeet Nagle
 
Piping Installation and Erection Procedure.pdf
Piping Installation and Erection Procedure.pdfPiping Installation and Erection Procedure.pdf
Piping Installation and Erection Procedure.pdfMDAbdullah621330
 
Piping and Vessels Flushing and Cleaning Procedure
Piping and Vessels Flushing and Cleaning ProcedurePiping and Vessels Flushing and Cleaning Procedure
Piping and Vessels Flushing and Cleaning ProcedureGerard B. Hawkins
 
World Class Manufacturing:Plant Start Up and Commissioning Procedure
World  Class Manufacturing:Plant Start Up and Commissioning Procedure World  Class Manufacturing:Plant Start Up and Commissioning Procedure
World Class Manufacturing:Plant Start Up and Commissioning Procedure HIMADRI BANERJI
 
Static equipment in oil and gas industry
Static equipment in oil and gas industryStatic equipment in oil and gas industry
Static equipment in oil and gas industryBaher El-Shaikh, CRE
 
Mind map the_9_key_elements_video_05_pre-commissioning
Mind map the_9_key_elements_video_05_pre-commissioningMind map the_9_key_elements_video_05_pre-commissioning
Mind map the_9_key_elements_video_05_pre-commissioningsakol kai
 
495265750-Hydro-Test-Procedure.docx
495265750-Hydro-Test-Procedure.docx495265750-Hydro-Test-Procedure.docx
495265750-Hydro-Test-Procedure.docxSharad Naik
 
Process Engineer Training PID.ppt.pdf
Process Engineer Training PID.ppt.pdfProcess Engineer Training PID.ppt.pdf
Process Engineer Training PID.ppt.pdfFaustoMarceloCaibe
 
Process piping design & engineering per asme b 31.3
Process piping design & engineering per asme b 31.3Process piping design & engineering per asme b 31.3
Process piping design & engineering per asme b 31.3Rajiv Kumar
 
what is process piping
what is process pipingwhat is process piping
what is process pipingVarun Patel
 
Hot Tapping Requirement
Hot Tapping RequirementHot Tapping Requirement
Hot Tapping Requirementwael el ariny
 
Process Plant Start Up and Commissioning
Process Plant Start Up and CommissioningProcess Plant Start Up and Commissioning
Process Plant Start Up and CommissioningpetroEDGE
 
Method statement piping works
Method statement piping worksMethod statement piping works
Method statement piping worksSurya Kant
 
Offshore qc welding inspection versi 1
Offshore qc welding inspection versi 1Offshore qc welding inspection versi 1
Offshore qc welding inspection versi 1Ramdani Diningrat
 
Presentation API 570 -510-653.pptx
Presentation API 570 -510-653.pptxPresentation API 570 -510-653.pptx
Presentation API 570 -510-653.pptxhesham ismail
 
Piping and Insruementaion Diagrams
Piping and Insruementaion DiagramsPiping and Insruementaion Diagrams
Piping and Insruementaion DiagramsTejas Deshpande
 

Mais procurados (20)

Piping Hydrostatic Test / Hydrotesting
Piping Hydrostatic Test / HydrotestingPiping Hydrostatic Test / Hydrotesting
Piping Hydrostatic Test / Hydrotesting
 
Piping Installation and Erection Procedure.pdf
Piping Installation and Erection Procedure.pdfPiping Installation and Erection Procedure.pdf
Piping Installation and Erection Procedure.pdf
 
Piping and Vessels Flushing and Cleaning Procedure
Piping and Vessels Flushing and Cleaning ProcedurePiping and Vessels Flushing and Cleaning Procedure
Piping and Vessels Flushing and Cleaning Procedure
 
World Class Manufacturing:Plant Start Up and Commissioning Procedure
World  Class Manufacturing:Plant Start Up and Commissioning Procedure World  Class Manufacturing:Plant Start Up and Commissioning Procedure
World Class Manufacturing:Plant Start Up and Commissioning Procedure
 
Basic engineering_Checklist
Basic engineering_ChecklistBasic engineering_Checklist
Basic engineering_Checklist
 
Static equipment in oil and gas industry
Static equipment in oil and gas industryStatic equipment in oil and gas industry
Static equipment in oil and gas industry
 
Mind map the_9_key_elements_video_05_pre-commissioning
Mind map the_9_key_elements_video_05_pre-commissioningMind map the_9_key_elements_video_05_pre-commissioning
Mind map the_9_key_elements_video_05_pre-commissioning
 
495265750-Hydro-Test-Procedure.docx
495265750-Hydro-Test-Procedure.docx495265750-Hydro-Test-Procedure.docx
495265750-Hydro-Test-Procedure.docx
 
Process Engineer Training PID.ppt.pdf
Process Engineer Training PID.ppt.pdfProcess Engineer Training PID.ppt.pdf
Process Engineer Training PID.ppt.pdf
 
Process piping design & engineering per asme b 31.3
Process piping design & engineering per asme b 31.3Process piping design & engineering per asme b 31.3
Process piping design & engineering per asme b 31.3
 
Pid.pdf
Pid.pdfPid.pdf
Pid.pdf
 
what is process piping
what is process pipingwhat is process piping
what is process piping
 
Hot Tapping Requirement
Hot Tapping RequirementHot Tapping Requirement
Hot Tapping Requirement
 
Asme b31,pressure piping code
Asme b31,pressure piping codeAsme b31,pressure piping code
Asme b31,pressure piping code
 
Process Plant Start Up and Commissioning
Process Plant Start Up and CommissioningProcess Plant Start Up and Commissioning
Process Plant Start Up and Commissioning
 
Method statement piping works
Method statement piping worksMethod statement piping works
Method statement piping works
 
Offshore qc welding inspection versi 1
Offshore qc welding inspection versi 1Offshore qc welding inspection versi 1
Offshore qc welding inspection versi 1
 
Presentation API 570 -510-653.pptx
Presentation API 570 -510-653.pptxPresentation API 570 -510-653.pptx
Presentation API 570 -510-653.pptx
 
Piping presentation part ii 2
Piping presentation part ii 2Piping presentation part ii 2
Piping presentation part ii 2
 
Piping and Insruementaion Diagrams
Piping and Insruementaion DiagramsPiping and Insruementaion Diagrams
Piping and Insruementaion Diagrams
 

Destaque

Oil And Gas Processing
Oil And Gas ProcessingOil And Gas Processing
Oil And Gas Processingmubarak2009
 
Petrolium and gas processing
Petrolium and gas processingPetrolium and gas processing
Petrolium and gas processingwaseemakhtar120
 
Hydrocarbon preeti bhatt
Hydrocarbon preeti bhattHydrocarbon preeti bhatt
Hydrocarbon preeti bhattkapde1970
 
Commissioning Plan Robert Thelander, Svenska kraftnät
Commissioning Plan Robert Thelander, Svenska kraftnät Commissioning Plan Robert Thelander, Svenska kraftnät
Commissioning Plan Robert Thelander, Svenska kraftnät Fingrid Oyj
 
Hp 2011 Rph Refining Hydrocarbon Technologies Profiles
Hp 2011 Rph Refining Hydrocarbon Technologies ProfilesHp 2011 Rph Refining Hydrocarbon Technologies Profiles
Hp 2011 Rph Refining Hydrocarbon Technologies Profilesabakshi2011
 
Power Point On Hydrocarbon
Power Point On HydrocarbonPower Point On Hydrocarbon
Power Point On HydrocarbonSamiran Ghosh
 
E nodeb commissioning guide(v100r005c00 04)(pdf)-en
E nodeb commissioning guide(v100r005c00 04)(pdf)-enE nodeb commissioning guide(v100r005c00 04)(pdf)-en
E nodeb commissioning guide(v100r005c00 04)(pdf)-enVugar Ali
 

Destaque (10)

Oil And Gas Processing
Oil And Gas ProcessingOil And Gas Processing
Oil And Gas Processing
 
Petrolium and gas processing
Petrolium and gas processingPetrolium and gas processing
Petrolium and gas processing
 
Hydrocarbon preeti bhatt
Hydrocarbon preeti bhattHydrocarbon preeti bhatt
Hydrocarbon preeti bhatt
 
Commissioning Plan Robert Thelander, Svenska kraftnät
Commissioning Plan Robert Thelander, Svenska kraftnät Commissioning Plan Robert Thelander, Svenska kraftnät
Commissioning Plan Robert Thelander, Svenska kraftnät
 
Hydrocarbons
HydrocarbonsHydrocarbons
Hydrocarbons
 
Hydrocarbons
HydrocarbonsHydrocarbons
Hydrocarbons
 
Hp 2011 Rph Refining Hydrocarbon Technologies Profiles
Hp 2011 Rph Refining Hydrocarbon Technologies ProfilesHp 2011 Rph Refining Hydrocarbon Technologies Profiles
Hp 2011 Rph Refining Hydrocarbon Technologies Profiles
 
Power Point On Hydrocarbon
Power Point On HydrocarbonPower Point On Hydrocarbon
Power Point On Hydrocarbon
 
The Future of Leadership Development
The Future of Leadership DevelopmentThe Future of Leadership Development
The Future of Leadership Development
 
E nodeb commissioning guide(v100r005c00 04)(pdf)-en
E nodeb commissioning guide(v100r005c00 04)(pdf)-enE nodeb commissioning guide(v100r005c00 04)(pdf)-en
E nodeb commissioning guide(v100r005c00 04)(pdf)-en
 

Semelhante a Commissioning & Interface With Engineering

Qa qc mech enggs or sr.qc inspector welding.piping.pipeline
Qa qc mech enggs or sr.qc inspector welding.piping.pipelineQa qc mech enggs or sr.qc inspector welding.piping.pipeline
Qa qc mech enggs or sr.qc inspector welding.piping.pipelineJOBY Joby.Stephan
 
Episode 34 : Project Execution Part (5)
Episode 34 :  Project Execution Part (5)Episode 34 :  Project Execution Part (5)
Episode 34 : Project Execution Part (5)SAJJAD KHUDHUR ABBAS
 
Ankur Sood-Instrument engineer
Ankur Sood-Instrument engineerAnkur Sood-Instrument engineer
Ankur Sood-Instrument engineerankur sood
 
Ankur Sood-Instrument engineer
Ankur Sood-Instrument engineerAnkur Sood-Instrument engineer
Ankur Sood-Instrument engineerankur sood
 
filip_damian cv poza.docx NEW IUNIE
filip_damian cv poza.docx NEW IUNIEfilip_damian cv poza.docx NEW IUNIE
filip_damian cv poza.docx NEW IUNIEdamian Filip
 
A year with Larsen & Toubro
A year with  Larsen & ToubroA year with  Larsen & Toubro
A year with Larsen & ToubroJAIPRAKASH PATIL
 
110921 commissioning of offshore installations
110921 commissioning of offshore installations110921 commissioning of offshore installations
110921 commissioning of offshore installationslaithu2908
 
SubstationCommissioning.pdf
SubstationCommissioning.pdfSubstationCommissioning.pdf
SubstationCommissioning.pdfAnithaSyam
 
POWER TRANSFORMER UDAIPUR 29022012.ppt
POWER TRANSFORMER UDAIPUR 29022012.pptPOWER TRANSFORMER UDAIPUR 29022012.ppt
POWER TRANSFORMER UDAIPUR 29022012.pptPOOJAOHRI2
 
Validation of water supply system
Validation of water supply systemValidation of water supply system
Validation of water supply systemceutics1315
 

Semelhante a Commissioning & Interface With Engineering (20)

Qa qc mech enggs or sr.qc inspector welding.piping.pipeline
Qa qc mech enggs or sr.qc inspector welding.piping.pipelineQa qc mech enggs or sr.qc inspector welding.piping.pipeline
Qa qc mech enggs or sr.qc inspector welding.piping.pipeline
 
Episode 34 : Project Execution Part (5)
Episode 34 :  Project Execution Part (5)Episode 34 :  Project Execution Part (5)
Episode 34 : Project Execution Part (5)
 
Episode 22 : PROJECT EXECUTION
Episode 22 : PROJECT EXECUTION Episode 22 : PROJECT EXECUTION
Episode 22 : PROJECT EXECUTION
 
Ankur Sood-Instrument engineer
Ankur Sood-Instrument engineerAnkur Sood-Instrument engineer
Ankur Sood-Instrument engineer
 
Ankur Sood-Instrument engineer
Ankur Sood-Instrument engineerAnkur Sood-Instrument engineer
Ankur Sood-Instrument engineer
 
OMV Muzaffar CV
OMV Muzaffar CVOMV Muzaffar CV
OMV Muzaffar CV
 
updated_ashishmalhotra
updated_ashishmalhotraupdated_ashishmalhotra
updated_ashishmalhotra
 
filip_damian cv poza.docx NEW IUNIE
filip_damian cv poza.docx NEW IUNIEfilip_damian cv poza.docx NEW IUNIE
filip_damian cv poza.docx NEW IUNIE
 
A year with Larsen & Toubro
A year with  Larsen & ToubroA year with  Larsen & Toubro
A year with Larsen & Toubro
 
Brij mohan cv
Brij mohan  cvBrij mohan  cv
Brij mohan cv
 
110921 commissioning of offshore installations
110921 commissioning of offshore installations110921 commissioning of offshore installations
110921 commissioning of offshore installations
 
SubstationCommissioning.pdf
SubstationCommissioning.pdfSubstationCommissioning.pdf
SubstationCommissioning.pdf
 
ELECTRICAL TECHNICIAN
ELECTRICAL TECHNICIANELECTRICAL TECHNICIAN
ELECTRICAL TECHNICIAN
 
ELECTRICAL TECHNICIAN
ELECTRICAL TECHNICIANELECTRICAL TECHNICIAN
ELECTRICAL TECHNICIAN
 
POWER TRANSFORMER UDAIPUR 29022012.ppt
POWER TRANSFORMER UDAIPUR 29022012.pptPOWER TRANSFORMER UDAIPUR 29022012.ppt
POWER TRANSFORMER UDAIPUR 29022012.ppt
 
Aamir C.V (1)
Aamir C.V (1)Aamir C.V (1)
Aamir C.V (1)
 
Validation of water supply system
Validation of water supply systemValidation of water supply system
Validation of water supply system
 
Validation of water supply system
Validation of water supply systemValidation of water supply system
Validation of water supply system
 
Water system validation
Water system validationWater system validation
Water system validation
 
Validation of water supply system
Validation of water supply systemValidation of water supply system
Validation of water supply system
 

Commissioning & Interface With Engineering

  • 1. PRE-COMMISSIONING & COMMISSIONING A discussion on Pre-commissioning / Commissioning & Start Up of Projects 1
  • 2. Contents  Objective  Common work at process plant at pipe line  Definition of Mechanical Completion  Pre-Commissioning Definition and Procedure 2
  • 3. Contents(Continued)  Activities (Piping & vessels, Mechanical, Electrical, Instrumentation, Operations)  Check Sheets  Punch Listing  Completion Activities 3
  • 4. Objectives  Start-up and hand-over of the completed plant to the Client.  To support client in operation of plant . 4
  • 5. COMMISSIONING & START-UP MECHANICAL COMPLETION SYSTEM / OPERATION Inclusive of PLANT COMMISSIONING PACKAGE STAFF Pre-commissioning START-UP HANDOVER TRAINING Activities 5
  • 6. Commissioning Works At Process Plants PIPING / VESSEL ELECT / INSTRUM •Flushing/Blowing •Preliminary Check •Chemical Cleaning •Calibration •Reinstatement •Circuitry Check •Gross leak with N2 •Continuity Check •Drying •Loop Test •Inerting • Energization (Power Up) •Hydrocarbon In •Performance Tests MANAGEMENT •Systems Breakdown •Preparation of Procedures •Loop Folder •Circuit Folder •Test Packs CONTROL SYSTEM ROTATING EQUIPMENT •SCADA / PCS SAT •Alignment •Fire & Gas System •Belt Tensioning •Safety Shutdown Sys. •Motor Run in Test •Alarm Set-Up & Test •Vibration Test •Simulation Test 6
  • 7. Commissioning Works At Pipe Lines PRECOMMISSIONING SPECIALIZED PIPELINE CLEANING •Cleaning •Dewaxing •Flooding •Descaling •Hydro testing •De-oiling •Dewatering & Drying •Pit cleaning •Flushing •Chemical cleaning •Nitrogen Inserting •Combined cleaning methods ASSOCIATED SERVICES PIPELINE INSPECTION •Temporary pipeline repair •Geometry inspection •On-site supervision •Metal loss inspection •Cathodic protection •Crack detection •Hot tapping & stoppling •Leak detection and location •Flow assurance Etc. •Profile monitoring and mapping 7
  • 8. Definition of Mechanical Completion & Construction Completion  Mechanical Completion: A series of activities that MUST be completed prior to the commencement of Commissioning and Start-up of a Utility System or Main Process Unit.  Mechanical Completion ALSO includes ALL pre-commissioning activities. 8
  • 9. Pre-Commissioning Overview  Process: Confirmation of Loops according to P& ID’s  Vessels: Internal Inspection & Box up  Piping: Hydro testing, reinstatement & verification of main gaskets.  Stationary Equipment: Tightening and Final Box Up.  Rotary Equipment: Leveling, Rotation, 9 Alignment & lubrications
  • 10. Pre-Commissioning Activities – Piping & Vessels  Field checks as per isometrics and P&ID’s  Verification of hydro testing  Verification of flushing , blowing & drying  Internal inspection of equipment as required 10
  • 11. Pre-Commissioning Activities – Piping & Vessels(Continued)  Verification of Internals  Re-instatement of all flanges, control value, orifices, Psv’s and steam traps.  Verification of blinds / spades installation and / or removal  Box up: Pre-commissioned and closed 11
  • 12. Pre-Commissioning Activities – Mechanical Discipline  Verification of coupling and belt alignment  Pumps / compressor checks  Bearing lubrications  Inspection / checking of filters & strainers 12
  • 13. Pre-Commissioning Activities – Electrical Discipline  MCC & UPS installation  Field electrical installation – Cable Meggering (Continuity) – Termination of wiring; end devices to JB’s & MCC – Termination & Glanding according to area classification. 13
  • 14. Pre-Commissioning Activities – Electrical Discipline(Continued)  Motor installation – Resistance maggering – Rotation confirmation – No load test run 14
  • 15. Pre-Commissioning Activities - Instrumentation  Instrument installation checks  PSV calibration  Calibration of transmitters and switches  Loop checking of device end to PLC  Function testing of PLC & ESD systems 15
  • 16. Pre-Commissioning Check Sheets  Vessel & Piping Check Sheets  Mechanical Check Sheets  Electrical Check Sheets  Instrumentation Check Sheets 16  Operation / Process Check Sheets
  • 17. Punch Listing  Punch Lists are created and sorted as per disciplines – Piping and Vessels – Mechanical – Electrical – Instrumentation – Operations  Punch Lists are categorized on a priority basis – Category “A”; MUST be completed prior to Commissioning – Category “B”; MUST be completed prior to Start-up – Category “C”; Signifies end of job  Construction Contractor MUST have a coordinated management plan of Punch Listing including categorizing of punch list items 17
  • 18. Completion Activities  Flushing Blowing Certificates  Box Up Certificate  Mechanical Completion Certificate for each Utility and Process Unit  Handover Certificate 18
  • 19. COMMISSIONING  Definition  Utility Description  Commissioning Activities  Check Sheets  Commissioning / Start Up Procedure 19
  • 20. Systems Description Commissioning of The Following Systems  Air Compression System  MCC & Plant Lighting System  UPS, PLC & Plant ESD System  Fire Water System  Fire & Gas Detection System 20
  • 21. Systems Description  Instrument Air Package  Inert Gas Package  Fuel Gas System  Closed Drain & Waste Water Systems  Condensate Transfer System  Process Units; Reactor 21
  • 22. Commissioning Check Sheets  Commissioning check sheets are given in the Commissioning Protocol. 22
  • 23. START-UP OF PROCESS UNITS  Utilities in Service  Introduction of Raw material (Vacuum Residue Feed)  Introduction of Process Air & Steam  Production of required grades of products  Maintaining required proportion of off gases as per specs  Achievement of required steam temperature  Obtaining steam temperature compatible to system steam temperature. 23
  • 24. Issues for Discussion.  Less re-work SS304, 304L  Carbon filter back flow  Go for the standard packages  15 KM pipeline 24