1. PRE-COMMISSIONING &
COMMISSIONING
A discussion on
Pre-commissioning /
Commissioning &
Start Up of Projects
1
2. Contents
Objective
Common work at process plant at pipe
line
Definition of Mechanical Completion
Pre-Commissioning Definition and
Procedure
2
4. Objectives
Start-up and hand-over of the completed
plant to the Client.
To support client in operation of plant
.
4
5. COMMISSIONING
& START-UP
MECHANICAL
COMPLETION
SYSTEM / OPERATION
Inclusive of PLANT
COMMISSIONING PACKAGE STAFF
Pre-commissioning START-UP
HANDOVER TRAINING
Activities
5
6. Commissioning Works
At Process Plants
PIPING / VESSEL ELECT / INSTRUM
•Flushing/Blowing •Preliminary Check
•Chemical Cleaning •Calibration
•Reinstatement •Circuitry Check
•Gross leak with N2 •Continuity Check
•Drying •Loop Test
•Inerting • Energization (Power Up)
•Hydrocarbon In •Performance Tests
MANAGEMENT
•Systems Breakdown
•Preparation of Procedures
•Loop Folder
•Circuit Folder
•Test Packs
CONTROL SYSTEM
ROTATING EQUIPMENT •SCADA / PCS SAT
•Alignment •Fire & Gas System
•Belt Tensioning •Safety Shutdown Sys.
•Motor Run in Test •Alarm Set-Up & Test
•Vibration Test •Simulation Test
6
8. Definition of Mechanical Completion
& Construction Completion
Mechanical Completion: A series of
activities that MUST be completed prior to
the commencement of Commissioning and
Start-up of a Utility System or Main Process
Unit.
Mechanical Completion ALSO includes
ALL pre-commissioning activities.
8
9. Pre-Commissioning Overview
Process: Confirmation of Loops
according to P& ID’s
Vessels: Internal Inspection & Box up
Piping: Hydro testing, reinstatement &
verification of main gaskets.
Stationary Equipment: Tightening and
Final Box Up.
Rotary Equipment: Leveling, Rotation,
9 Alignment & lubrications
10. Pre-Commissioning Activities –
Piping & Vessels
Field checks as per isometrics and P&ID’s
Verification of hydro testing
Verification of flushing , blowing & drying
Internal inspection of equipment as
required
10
11. Pre-Commissioning Activities –
Piping & Vessels(Continued)
Verification of Internals
Re-instatement of all flanges, control
value, orifices, Psv’s and steam traps.
Verification of blinds / spades installation
and / or removal
Box up: Pre-commissioned and closed
11
12. Pre-Commissioning Activities –
Mechanical Discipline
Verification of coupling and belt
alignment
Pumps / compressor checks
Bearing lubrications
Inspection / checking of filters & strainers
12
13. Pre-Commissioning Activities –
Electrical Discipline
MCC & UPS installation
Field electrical installation
– Cable Meggering (Continuity)
– Termination of wiring; end devices
to JB’s & MCC
– Termination & Glanding according
to area classification.
13
14. Pre-Commissioning Activities –
Electrical Discipline(Continued)
Motor installation
– Resistance maggering
– Rotation confirmation
– No load test run
14
15. Pre-Commissioning Activities -
Instrumentation
Instrument installation checks
PSV calibration
Calibration of transmitters and switches
Loop checking of device end to PLC
Function testing of PLC & ESD systems
15
17. Punch Listing
Punch Lists are created and sorted as per disciplines
– Piping and Vessels
– Mechanical
– Electrical
– Instrumentation
– Operations
Punch Lists are categorized on a priority basis
– Category “A”; MUST be completed prior to
Commissioning
– Category “B”; MUST be completed prior to Start-up
– Category “C”; Signifies end of job
Construction Contractor MUST have a coordinated
management plan of Punch Listing including categorizing
of punch list items
17
18. Completion Activities
Flushing Blowing Certificates
Box Up Certificate
Mechanical Completion Certificate for
each Utility and Process Unit
Handover Certificate
18
20. Systems Description
Commissioning of The Following Systems
Air Compression System
MCC & Plant Lighting System
UPS, PLC & Plant ESD System
Fire Water System
Fire & Gas Detection System
20
21. Systems Description
Instrument Air Package
Inert Gas Package
Fuel Gas System
Closed Drain & Waste Water Systems
Condensate Transfer System
Process Units; Reactor
21
23. START-UP OF PROCESS UNITS
Utilities in Service
Introduction of Raw material (Vacuum Residue
Feed)
Introduction of Process Air & Steam
Production of required grades of products
Maintaining required proportion of off gases as
per specs
Achievement of required steam temperature
Obtaining steam temperature compatible to
system steam temperature.
23
24. Issues for Discussion.
Less re-work SS304, 304L
Carbon filter back flow
Go for the standard packages
15 KM pipeline