INTRODUCING WAYS TO EFFECTIVELY SELECT THE RIGHT MATERIAL  NOR ANISAZILA ABDUL RAHIM Ministry Of Works , Kingdom Of Bahrain  24th January 2010
CONTENTS  OVERVIEW MATERIALS FAILURE  : Corrosive Effects Of Effluent  WASTEWATER TREATMENT PLANT MATERIALS COMMONLY USED IN BAHRAIN  SELECTING THE MATERIALS : Performance Spec. Vs  Prescriptive Spec. SELECTING THE MATERIALS : Life Cost Cycle Of Material PROACTIVE APPROACH : Specifications & Standards PREVENTIVE & CORRECTIVE APPROACH : Quality Assurance & Quality Control  RECOMMENDATIONS & CONCLUSION 1 2 3 4 5 6 7 8 9 10
OVERVIEW : corrosive effects of effluent CORROSION is significant at almost any surface within wastewater plant and network. EFFLUENT itself is the  most aggressive corrosive liquids travel through wastewater system component.  ( piping , tank, pump & other related equipment )  “ An estimated $36 Billion in corrosion damage is occur in water & wastewater handling system each year” 12 3 4 5 6 7 8 9 10
OVERVIEW : corrosive effects of effluent CORROSION targets steel piping , tanks , transfer lines and pump         -  compromising not only their integrity but does effect the ability & efficiency of the wastewater plant   Due to the aggressive nature of wastewater , any steel element such as  pipes, joints, pumps or tank surface is vulnerable to corrosion “Selecting the right material is essential”   1 23 4 5 6 7 8 9 10
wastewater Treatment plant  Tubli  Wastewater Treatment Plant  1 2 34 5 6 7 8 9 10
Wastewater plant  Structure  Failure A Bahrain Experience  1 2 3 4 5 6 7 8 9 10
corrosive effects At Treatment Plant Exposed severely corroded steel reinforcement   1 2 3 4 56 7 8 9 10
REHABILITATION & MAINTAINANCE: PREVENTIVE & CORRECTIVE  APPROACH REHABILITATION & MAINTAINANCE IN PROGRESS Improved PUMPING SYSTEM & FIREFIGHTING SYSTEM  Enhanced monitoring with SCADA SYSTEM  REDESIGN & REPLACE old Piping system with NEW MATERIALS & METHODS   Effective Study & Planning for  Kingdom of Bahrain in  NATIONAL MASTERPLAN FOR THE  SANITARY ENGINEERING SERVICES  ( Under Development )  1 2 3 4 56 7 8 9 10
MATERIALS COMMONLY USED Based on Survey: ~90% of foul sewerage  is made of  VCP 1 2 3 4 56 7 8 9 10
MATERIALS COMMONLY USED Based on Survey: ~84% of storm drainage is made of GRP/RTR 1 2 3 4 56 7 8 9 10
NEW MATERIALS USED & RECOMENDED GLASS-REINFORCED PLASTIC (GRP) PIPE GRP has been ACCEPTED and USED as a pipe material for over 30years &its use is well documented.  CORROSION RESISTANCE OF GRPis second to none. It has the ability to work at high or low temperatures in very corrosive environments. PLASTIC is invariably used to resist the corrosive effects 1 2 3 4 56 7 8 9 10
NEW MATERIALS USED & RECOMENDED POLYMER CONCRETE PIPE (PCP)  for Deep Gravity Sewer Pipe Material  POLYMER CONCRETE PIPE (PCP)  ,[object Object]
STRENGTH IN RESPECT OF THE STRESSES from external and internal loads 11 12 13 14 15 16 17 18 19 20
NEW MATERIALS USED & RECOMENDED The future pipes in Bahrain  -  an alternatives materials to extend service life & reduce the cost  POLY-GLASS PIPES is a composite of POLYMER CONCRETE and GRP.A unique design subject to an international patent GRP provides the INNER & POLYMER CONCRETE PIPE provides the OUTER structural wall.  Advantage of the HIGH STRENGTH PROPERTY OF POLYMER CONCRETE &THE PROVEN CORROSION RESISTANCE OF GRP.  111213 14 15 16 17 18 19 20
NEW MATERIALS USED & RECOMENDED EFFECTIVE PROTECTIVE COATING   to ensure against corrosion  Corrosion not only threatens water storage tanks, but it can also SHORTEN THE LIFE OF PARTS of the water treatment plant and distribution system Water and wastewater structures should be DESIGNED TO PREVENT CORROSION by making them easy to paint and repaint LONG TERM PROTECTION against attack by a wide range of chemicals 111213 14 15 16 17 18 19 20
PERFORMANCE BASED SPECIFICATION : PRO-ACTIVE APPROACH SPECIFICATION AND STANDARDS  of high technology Set up of Intellectual Base  SPECIFICATION AND STANDARDS MOW SPECIFICATION AND STANDARDS set out the specifications and design procedures. to ensure goods/ materials and services consistently perform in the way they are intended This SPECIFICATION AND STANDARDS make a sustained contribution to generating national wealth, IMPROVING OUR QUALITY OF LIFE, increasing employment, improving safety and health and using our national resources more efficiently. 1112 13 14 15 16 17 18 19 20
PERFORMANCE SPECIFICATIONS VERSUS PRESCRIPTIVE SPECIFICATION WHAT IS A PERFORMANCE SPECIFICATION? ,[object Object]
  The INSTRUCTIONS should be CLEAR, ACHIEVABLE, MEASURABLE AND ENFORCEABLE.
PERFORMANCE SPECIFICATIONS  : clearly specify the TEST METHODS AND THE ACCEPTANCE CRITERIA  that will be used to verify and enforce the requirements.  ,[object Object],performance CHARACTERISTICS OF THE FINAL PRODUCT and links them to construction, materials, and  other items under contractor control 1112 1314 15 16 17 18 19 20
PERFORMANCE SPECIFICATIONS VERSUS PRESCRIPTIVE SPECIFICATION WHAT IS A PRESCRIPTIVE SPECIFICATION? ,[object Object]
   Performance requirements are NOT CLEARLY INDICATED in project specifications and the PRESCRIPTIVE REQUIREMENTS MAY CONFLICT WITH THE INTENDED PERFORMANCE.1112 131415 16 17 18 19 20
IMPACTS OF PRESCRIPTIVESPECIFICATIONS  ,[object Object]
MINIMUM ACCEPTABLE VALUES. THE LOWEST ALLOWABLE VALUE will be accepted.
RESTRAIN DECISION MAKERS AND FORCE FAIR TREATMENT. BOTH PARTIES PROTECTION OVER ARBITRARY decision making. ,[object Object]
DIFFICULT TO CHANGE. GOOD & BAD in difficult to remove.
MINIMUM QUALITY EQUALS MAXIMUM QUALITY. LOW-BID PROCESS
DISTINGUISHING A QUALITY CONTRACTOR.HARMONY WITH LOW-BID 1112 13141516 17 18 19 20
PERFORMANCE SPECIFICATIONS VERSUS PRESCRIPTIVE SPECIFICATION PERFORMANCE SPECIFICATIONS IN SNAPSHOT.  WHEN FUTURE PERFORMANCE OF A PRODUCT  can be estimated using key construction tests and measurements  linked to the original design via modeling and life cycle costs, the  specification structure is commonly described as  PERFORMANCE-RELATED or PERFORMANCE-BASED.  WHEN THE CONDITION OF THE PRODUCT is measured  after some predetermined time, the specification structure  is commonly known as a WARRANTY. WHEN THE FINAL PRODUCT is described in terms of component materials, dimensions, tolerances, weights, and required construction methodology-equipment type, size, speed, etc.-the specifications are commonly known as METHOD or PRESCRIPTIVE SPECIFICATIONS 1112 1314151617 18 19 20
PERFORMANCE SPECIFICATIONS  WARRANTIES WARRANTIESdivided into two areas: MATERIALS AND WORKMANSHIP (M&W) WARRANTIES and PRODUCT PERFORMANCE WARRANTIES.  MATERIALS AND WORKMANSHIP (M&W) WARRANTIES : call for contractors TO CORRECT DEFECTS IN WORK elements within their control.  The PERFORMANCE WARRANTY is a recent concept and requires the contractor TO CORRECT DEFECTS IF THE PRODUCT DOES NOT PERFORM to some desired quality level over a certain time in service.  PRODUCT PERFORMANCE WARRANTIES are somewhat controversial, exponentially so as the length of the warranty period extends beyond three years.  1112 131415161718 1920
PERFORMANCE SPECIFICATIONS  ADVANTAGES   ,[object Object]

More Related Content

What's hot

RESUME FOR QC INSPECTOR
RESUME FOR QC INSPECTORRESUME FOR QC INSPECTOR
RESUME FOR QC INSPECTORMohsin Iqubal
 
Quality Control & Quality Assurance of MS pipeline
Quality Control & Quality Assurance of MS pipelineQuality Control & Quality Assurance of MS pipeline
Quality Control & Quality Assurance of MS pipelineIEI GSC
 
ASME PVP 2016 PCC-1 Appendix A session summary
ASME PVP 2016   PCC-1 Appendix A session summaryASME PVP 2016   PCC-1 Appendix A session summary
ASME PVP 2016 PCC-1 Appendix A session summaryClay D. Rodery
 
Senior HVAC & Plumbing Engineer & QC Inspector
Senior HVAC & Plumbing Engineer & QC Inspector  Senior HVAC & Plumbing Engineer & QC Inspector
Senior HVAC & Plumbing Engineer & QC Inspector SYED MUQTAAR AHAMED
 
Updated-Mohammed Khursheed -CV -Alam, VELOSI LLC
Updated-Mohammed Khursheed -CV -Alam, VELOSI LLCUpdated-Mohammed Khursheed -CV -Alam, VELOSI LLC
Updated-Mohammed Khursheed -CV -Alam, VELOSI LLCkhursheed aiam
 
MADHAN RESUME - UPDATED
MADHAN RESUME - UPDATEDMADHAN RESUME - UPDATED
MADHAN RESUME - UPDATEDMadan Kumar
 
SATHURAGIRI HVAC PROJECT ENGINEER
SATHURAGIRI  HVAC PROJECT ENGINEERSATHURAGIRI  HVAC PROJECT ENGINEER
SATHURAGIRI HVAC PROJECT ENGINEERSathura Giri
 
Suprotim dey LATEST CV
Suprotim dey  LATEST CVSuprotim dey  LATEST CV
Suprotim dey LATEST CVSuprotim Dey
 

What's hot (18)

Jiju new cv
Jiju new cvJiju new cv
Jiju new cv
 
RESUME FOR QC INSPECTOR
RESUME FOR QC INSPECTORRESUME FOR QC INSPECTOR
RESUME FOR QC INSPECTOR
 
Ffs assessment
Ffs assessmentFfs assessment
Ffs assessment
 
RESUME-Sijin
RESUME-SijinRESUME-Sijin
RESUME-Sijin
 
Resume Abdulbari
Resume   AbdulbariResume   Abdulbari
Resume Abdulbari
 
Quality Control & Quality Assurance of MS pipeline
Quality Control & Quality Assurance of MS pipelineQuality Control & Quality Assurance of MS pipeline
Quality Control & Quality Assurance of MS pipeline
 
Qc
QcQc
Qc
 
ASME PVP 2016 PCC-1 Appendix A session summary
ASME PVP 2016   PCC-1 Appendix A session summaryASME PVP 2016   PCC-1 Appendix A session summary
ASME PVP 2016 PCC-1 Appendix A session summary
 
resum Humaun latest1
resum Humaun latest1resum Humaun latest1
resum Humaun latest1
 
Senior HVAC & Plumbing Engineer & QC Inspector
Senior HVAC & Plumbing Engineer & QC Inspector  Senior HVAC & Plumbing Engineer & QC Inspector
Senior HVAC & Plumbing Engineer & QC Inspector
 
Updated-Mohammed Khursheed -CV -Alam, VELOSI LLC
Updated-Mohammed Khursheed -CV -Alam, VELOSI LLCUpdated-Mohammed Khursheed -CV -Alam, VELOSI LLC
Updated-Mohammed Khursheed -CV -Alam, VELOSI LLC
 
MADHAN RESUME - UPDATED
MADHAN RESUME - UPDATEDMADHAN RESUME - UPDATED
MADHAN RESUME - UPDATED
 
SATHURAGIRI HVAC PROJECT ENGINEER
SATHURAGIRI  HVAC PROJECT ENGINEERSATHURAGIRI  HVAC PROJECT ENGINEER
SATHURAGIRI HVAC PROJECT ENGINEER
 
Mithun Banjan CV
Mithun Banjan CVMithun Banjan CV
Mithun Banjan CV
 
hatata cv 2015
hatata cv 2015hatata cv 2015
hatata cv 2015
 
Suprotim dey LATEST CV
Suprotim dey  LATEST CVSuprotim dey  LATEST CV
Suprotim dey LATEST CV
 
Ipea api579
Ipea api579Ipea api579
Ipea api579
 
presentation
presentationpresentation
presentation
 

Similar to Introducing Ways To Effectively Select The Right Material Anisa

validation ppt.pptx
 validation ppt.pptx validation ppt.pptx
validation ppt.pptxPawanDhamala1
 
In-Spec UV Vis Standards and Good Lab Practice
In-Spec UV Vis Standards and Good Lab PracticeIn-Spec UV Vis Standards and Good Lab Practice
In-Spec UV Vis Standards and Good Lab PracticeLiza Tallon
 
2 appendix ii technical conditions, requirements and ma (1)
2 appendix ii   technical conditions, requirements and ma (1)2 appendix ii   technical conditions, requirements and ma (1)
2 appendix ii technical conditions, requirements and ma (1)SERPETBOL.LTDA
 
RESUME - DAVID SILVA (1) (1)
RESUME -  DAVID SILVA (1) (1)RESUME -  DAVID SILVA (1) (1)
RESUME - DAVID SILVA (1) (1)David Silva Polo
 
TESTING AND COMMISSIONING OF VSC HVDC SYSTEMS
TESTING AND COMMISSIONING OF VSC HVDC SYSTEMSTESTING AND COMMISSIONING OF VSC HVDC SYSTEMS
TESTING AND COMMISSIONING OF VSC HVDC SYSTEMSPower System Operation
 
Uni-Bell PVC Pipe Association ENVIRONMENTAL PRODUCT DECLARATION
Uni-Bell PVC Pipe Association ENVIRONMENTAL PRODUCT DECLARATIONUni-Bell PVC Pipe Association ENVIRONMENTAL PRODUCT DECLARATION
Uni-Bell PVC Pipe Association ENVIRONMENTAL PRODUCT DECLARATIONManishPatel169454
 
environmental-product-declaration-2023.pptx
environmental-product-declaration-2023.pptxenvironmental-product-declaration-2023.pptx
environmental-product-declaration-2023.pptxManishPatel169454
 
Natural Gas Storage Sample Memo
Natural Gas Storage Sample MemoNatural Gas Storage Sample Memo
Natural Gas Storage Sample MemoChad Colton
 
environmental-product-declaration-2023.pdf
environmental-product-declaration-2023.pdfenvironmental-product-declaration-2023.pdf
environmental-product-declaration-2023.pdfManishPatel169454
 
Sanitary Pipeline Product Recovery
Sanitary Pipeline Product RecoverySanitary Pipeline Product Recovery
Sanitary Pipeline Product RecoveryManishPatel169454
 
QAQC MEP HVAC INSPECTOR
QAQC MEP HVAC INSPECTORQAQC MEP HVAC INSPECTOR
QAQC MEP HVAC INSPECTORMurugan Pillai
 
495265750-Hydro-Test-Procedure.docx
495265750-Hydro-Test-Procedure.docx495265750-Hydro-Test-Procedure.docx
495265750-Hydro-Test-Procedure.docxSharad Naik
 
Environmental Product Declaration 2023.pptx
Environmental Product Declaration 2023.pptxEnvironmental Product Declaration 2023.pptx
Environmental Product Declaration 2023.pptxManishPatel169454
 

Similar to Introducing Ways To Effectively Select The Right Material Anisa (20)

validation ppt.pptx
 validation ppt.pptx validation ppt.pptx
validation ppt.pptx
 
Company Brochures
Company BrochuresCompany Brochures
Company Brochures
 
In-Spec UV Vis Standards and Good Lab Practice
In-Spec UV Vis Standards and Good Lab PracticeIn-Spec UV Vis Standards and Good Lab Practice
In-Spec UV Vis Standards and Good Lab Practice
 
Rengaraj n c vdone
Rengaraj  n c vdoneRengaraj  n c vdone
Rengaraj n c vdone
 
REY CV
REY CVREY CV
REY CV
 
2 appendix ii technical conditions, requirements and ma (1)
2 appendix ii   technical conditions, requirements and ma (1)2 appendix ii   technical conditions, requirements and ma (1)
2 appendix ii technical conditions, requirements and ma (1)
 
Abraham Sanni CV
Abraham Sanni CVAbraham Sanni CV
Abraham Sanni CV
 
RESUME - DAVID SILVA (1) (1)
RESUME -  DAVID SILVA (1) (1)RESUME -  DAVID SILVA (1) (1)
RESUME - DAVID SILVA (1) (1)
 
Veerasekar api inspectorresume
Veerasekar api inspectorresumeVeerasekar api inspectorresume
Veerasekar api inspectorresume
 
Veerasekar api inspectorresume
Veerasekar api inspectorresumeVeerasekar api inspectorresume
Veerasekar api inspectorresume
 
TESTING AND COMMISSIONING OF VSC HVDC SYSTEMS
TESTING AND COMMISSIONING OF VSC HVDC SYSTEMSTESTING AND COMMISSIONING OF VSC HVDC SYSTEMS
TESTING AND COMMISSIONING OF VSC HVDC SYSTEMS
 
Uni-Bell PVC Pipe Association ENVIRONMENTAL PRODUCT DECLARATION
Uni-Bell PVC Pipe Association ENVIRONMENTAL PRODUCT DECLARATIONUni-Bell PVC Pipe Association ENVIRONMENTAL PRODUCT DECLARATION
Uni-Bell PVC Pipe Association ENVIRONMENTAL PRODUCT DECLARATION
 
environmental-product-declaration-2023.pptx
environmental-product-declaration-2023.pptxenvironmental-product-declaration-2023.pptx
environmental-product-declaration-2023.pptx
 
Natural Gas Storage Sample Memo
Natural Gas Storage Sample MemoNatural Gas Storage Sample Memo
Natural Gas Storage Sample Memo
 
environmental-product-declaration-2023.pdf
environmental-product-declaration-2023.pdfenvironmental-product-declaration-2023.pdf
environmental-product-declaration-2023.pdf
 
Sanitary Pipeline Product Recovery
Sanitary Pipeline Product RecoverySanitary Pipeline Product Recovery
Sanitary Pipeline Product Recovery
 
QAQC MEP HVAC INSPECTOR
QAQC MEP HVAC INSPECTORQAQC MEP HVAC INSPECTOR
QAQC MEP HVAC INSPECTOR
 
495265750-Hydro-Test-Procedure.docx
495265750-Hydro-Test-Procedure.docx495265750-Hydro-Test-Procedure.docx
495265750-Hydro-Test-Procedure.docx
 
Environmental Product Declaration 2023.pptx
Environmental Product Declaration 2023.pptxEnvironmental Product Declaration 2023.pptx
Environmental Product Declaration 2023.pptx
 
CV PL Mukhtar )
CV  PL  Mukhtar )CV  PL  Mukhtar )
CV PL Mukhtar )
 

Introducing Ways To Effectively Select The Right Material Anisa

  • 1. INTRODUCING WAYS TO EFFECTIVELY SELECT THE RIGHT MATERIAL NOR ANISAZILA ABDUL RAHIM Ministry Of Works , Kingdom Of Bahrain 24th January 2010
  • 2. CONTENTS OVERVIEW MATERIALS FAILURE : Corrosive Effects Of Effluent WASTEWATER TREATMENT PLANT MATERIALS COMMONLY USED IN BAHRAIN SELECTING THE MATERIALS : Performance Spec. Vs Prescriptive Spec. SELECTING THE MATERIALS : Life Cost Cycle Of Material PROACTIVE APPROACH : Specifications & Standards PREVENTIVE & CORRECTIVE APPROACH : Quality Assurance & Quality Control RECOMMENDATIONS & CONCLUSION 1 2 3 4 5 6 7 8 9 10
  • 3. OVERVIEW : corrosive effects of effluent CORROSION is significant at almost any surface within wastewater plant and network. EFFLUENT itself is the most aggressive corrosive liquids travel through wastewater system component. ( piping , tank, pump & other related equipment ) “ An estimated $36 Billion in corrosion damage is occur in water & wastewater handling system each year” 12 3 4 5 6 7 8 9 10
  • 4. OVERVIEW : corrosive effects of effluent CORROSION targets steel piping , tanks , transfer lines and pump - compromising not only their integrity but does effect the ability & efficiency of the wastewater plant Due to the aggressive nature of wastewater , any steel element such as pipes, joints, pumps or tank surface is vulnerable to corrosion “Selecting the right material is essential” 1 23 4 5 6 7 8 9 10
  • 5. wastewater Treatment plant Tubli Wastewater Treatment Plant 1 2 34 5 6 7 8 9 10
  • 6. Wastewater plant Structure Failure A Bahrain Experience 1 2 3 4 5 6 7 8 9 10
  • 7. corrosive effects At Treatment Plant Exposed severely corroded steel reinforcement 1 2 3 4 56 7 8 9 10
  • 8. REHABILITATION & MAINTAINANCE: PREVENTIVE & CORRECTIVE APPROACH REHABILITATION & MAINTAINANCE IN PROGRESS Improved PUMPING SYSTEM & FIREFIGHTING SYSTEM Enhanced monitoring with SCADA SYSTEM REDESIGN & REPLACE old Piping system with NEW MATERIALS & METHODS Effective Study & Planning for Kingdom of Bahrain in NATIONAL MASTERPLAN FOR THE SANITARY ENGINEERING SERVICES ( Under Development ) 1 2 3 4 56 7 8 9 10
  • 9. MATERIALS COMMONLY USED Based on Survey: ~90% of foul sewerage is made of VCP 1 2 3 4 56 7 8 9 10
  • 10. MATERIALS COMMONLY USED Based on Survey: ~84% of storm drainage is made of GRP/RTR 1 2 3 4 56 7 8 9 10
  • 11. NEW MATERIALS USED & RECOMENDED GLASS-REINFORCED PLASTIC (GRP) PIPE GRP has been ACCEPTED and USED as a pipe material for over 30years &its use is well documented. CORROSION RESISTANCE OF GRPis second to none. It has the ability to work at high or low temperatures in very corrosive environments. PLASTIC is invariably used to resist the corrosive effects 1 2 3 4 56 7 8 9 10
  • 12.
  • 13. STRENGTH IN RESPECT OF THE STRESSES from external and internal loads 11 12 13 14 15 16 17 18 19 20
  • 14. NEW MATERIALS USED & RECOMENDED The future pipes in Bahrain - an alternatives materials to extend service life & reduce the cost POLY-GLASS PIPES is a composite of POLYMER CONCRETE and GRP.A unique design subject to an international patent GRP provides the INNER & POLYMER CONCRETE PIPE provides the OUTER structural wall. Advantage of the HIGH STRENGTH PROPERTY OF POLYMER CONCRETE &THE PROVEN CORROSION RESISTANCE OF GRP. 111213 14 15 16 17 18 19 20
  • 15. NEW MATERIALS USED & RECOMENDED EFFECTIVE PROTECTIVE COATING to ensure against corrosion Corrosion not only threatens water storage tanks, but it can also SHORTEN THE LIFE OF PARTS of the water treatment plant and distribution system Water and wastewater structures should be DESIGNED TO PREVENT CORROSION by making them easy to paint and repaint LONG TERM PROTECTION against attack by a wide range of chemicals 111213 14 15 16 17 18 19 20
  • 16. PERFORMANCE BASED SPECIFICATION : PRO-ACTIVE APPROACH SPECIFICATION AND STANDARDS of high technology Set up of Intellectual Base SPECIFICATION AND STANDARDS MOW SPECIFICATION AND STANDARDS set out the specifications and design procedures. to ensure goods/ materials and services consistently perform in the way they are intended This SPECIFICATION AND STANDARDS make a sustained contribution to generating national wealth, IMPROVING OUR QUALITY OF LIFE, increasing employment, improving safety and health and using our national resources more efficiently. 1112 13 14 15 16 17 18 19 20
  • 17.
  • 18. The INSTRUCTIONS should be CLEAR, ACHIEVABLE, MEASURABLE AND ENFORCEABLE.
  • 19.
  • 20.
  • 21. Performance requirements are NOT CLEARLY INDICATED in project specifications and the PRESCRIPTIVE REQUIREMENTS MAY CONFLICT WITH THE INTENDED PERFORMANCE.1112 131415 16 17 18 19 20
  • 22.
  • 23. MINIMUM ACCEPTABLE VALUES. THE LOWEST ALLOWABLE VALUE will be accepted.
  • 24.
  • 25. DIFFICULT TO CHANGE. GOOD & BAD in difficult to remove.
  • 26. MINIMUM QUALITY EQUALS MAXIMUM QUALITY. LOW-BID PROCESS
  • 27. DISTINGUISHING A QUALITY CONTRACTOR.HARMONY WITH LOW-BID 1112 13141516 17 18 19 20
  • 28. PERFORMANCE SPECIFICATIONS VERSUS PRESCRIPTIVE SPECIFICATION PERFORMANCE SPECIFICATIONS IN SNAPSHOT. WHEN FUTURE PERFORMANCE OF A PRODUCT can be estimated using key construction tests and measurements linked to the original design via modeling and life cycle costs, the specification structure is commonly described as PERFORMANCE-RELATED or PERFORMANCE-BASED. WHEN THE CONDITION OF THE PRODUCT is measured after some predetermined time, the specification structure is commonly known as a WARRANTY. WHEN THE FINAL PRODUCT is described in terms of component materials, dimensions, tolerances, weights, and required construction methodology-equipment type, size, speed, etc.-the specifications are commonly known as METHOD or PRESCRIPTIVE SPECIFICATIONS 1112 1314151617 18 19 20
  • 29. PERFORMANCE SPECIFICATIONS WARRANTIES WARRANTIESdivided into two areas: MATERIALS AND WORKMANSHIP (M&W) WARRANTIES and PRODUCT PERFORMANCE WARRANTIES. MATERIALS AND WORKMANSHIP (M&W) WARRANTIES : call for contractors TO CORRECT DEFECTS IN WORK elements within their control. The PERFORMANCE WARRANTY is a recent concept and requires the contractor TO CORRECT DEFECTS IF THE PRODUCT DOES NOT PERFORM to some desired quality level over a certain time in service. PRODUCT PERFORMANCE WARRANTIES are somewhat controversial, exponentially so as the length of the warranty period extends beyond three years. 1112 131415161718 1920
  • 30.
  • 33. CLEARER DISTINCTION IN ROLES AND RESPONSIBILITIES.
  • 37. MORE INNOVATIVE ENVIRONMENT. 1112 131415161718 1920
  • 38. LIFE CYCLE COST ANALYSES A LIFE CYCLE ANALYSES consists of evaluating a broad spectrum of ENVIRONMENTAL ATTRIBUTES of the product, manufacturing process, and manufacturer. Selecting the most relevant attributes is dependent upon the commodity or service being purchased, LOCAL ENVIRONMENTAL PRIORITIES, & AVAILABILITY OF RELIABLE INFORMATION in addition to the traditional CAP (Cost, Availability, Performance) factors. A 'LIFE CYCLE ANALYSIS also known as 'Life Cycle Assessment ', 'Eco-balance', and 'Cradle-to-grave Analysis') is the INVESTIGATION AND EVALUATION OF THE ENVIRONMENTAL IMPACTS OF A GIVEN PRODUCT OR SERVICEcaused or necessitated by its existence 21 22 23 24 25 26 27 28 29 30
  • 39.
  • 40. LCC provides a systematic process for EVALUATING AND QUANTIFYING THE COST IMPACTS of alternate courses of action. support TRADE-OFF ANALYSIS between several product design configurations, or MEASURE OF SENSITIVITY of a specific product design to changes in selected performance parameters (such as reliability, maintainability, and testability). Product quality can AFFECT OPERATION AND REPAIR COSTS. Higher quality products can MINIMIZE associated scrap and rework costs. 2122 23 24 25 26 27 28 29 30
  • 41. PERFORMANCE BASED SPECIFICATION : PRO-ACTIVE APPROACH MOW Specification and Standards - ENSURE PRODUCTS AND SYSTEMS ARE SAFE AND RELIABLE. SPECIFICATION DEVELOP based on a collection of references including literature or data collected from industry, association, survey or data obtained through research and technology development & usually UNIQUE TO LOCAL CONDITIONS such as in Kingdom of Bahrain 2122 23 24 25 26 27 28 29 30
  • 42.
  • 43. Workmanship (inexperienced contractor, lack of supervision by consultant)
  • 44. Overlooked design considerations (traffic-induced stresses, ground saturation, construction activities in pipeline’s vicinity)To assure the Quality of Sanitary Pipeline Projects A QA Framework to be implemented involving the resources of MED and Project Manager/team members 212223 24 25 26 27 28 29 30
  • 45. QUALITY ASSURANCE FRAMEWORK MED has formulated framework which covers provision of guidelines on requirements pertaining to QUALITY AND MATERIALS SPECIFICATIONS FOR TENDER OF PROJECT CONTRACTS & ESTABLISHMENT OF A ROBUST MONITORING SYSTEM comprising of the review of contractual quality documents as well as AUDIT, INSPECTION AND TESTING. 212223 2425 26 27 28 29 30
  • 46.
  • 47. ELIMINATE REPEAT WORKS and MINIMIZE MAINTENANCE COSTS
  • 48. Return on investment for the stakeholders QA FRAMEWORK MAIN ACTIVITIES: REVIEW contractor/consultant’sPQP and materials specification/ selection. AUDIT: Scheduled monthly (or 2 or 3 monthly), looks at contractor’s/consultant‘s processes and examines documents/ records. TESTING: Independent testing of samples obtained from site at MED or MED-appointed accredited lab. INSPECTION: Observation of construction processes at site based on developed checklists. 212223 242526 27 28 29 30
  • 49. ACCHIEVING QUALITY ASSURANCE MATERIALS ENGINEERING DIRECTORATE providing quality control services on government contracts, and acting as a facility for investigation and research that deal with the SELECTION AND USE OF CONSTRUCTION MATERIALSin the Kingdom of Bahrain, roles which still continue until present. In line with MoW’s strategy and Bahrain Vision 2030 a mandate has been given to assure that quality in government projects ATTAIN A HIGH LEVEL OF PERFORMANCE and COST-EFFECTIVENESS, with the DESIRED RESULT OF ACHIEVING THE GREATEST POSSIBLE LONGEVITY OF THE END PRODUCT. 212223 242526 27 28 29 30
  • 50. RECOMMENDATIONS & CONCLUSION EFFECTIVELY SELECT THE RIGHT MATERIAL Addition of comparing to “ If a tank manufacturer promises a low cost for tank and corrosion-resistant coating, make sure you review cost for the total life cycle of the tank, not just initial cost. A HIGHER QUALITY COATING MAY HAVE A HIGHER UPFRONT COST BUT OFFER LOWER LIFETIME MAINTENANCE AND RECOATING REQUIREMENTS, AS CORROSION SHORTENS THE LIFE OF A TANK.” 212223 24252627 28 29 30
  • 51. Thank You ….. Let’s Save Our Planet And Preserve A Clean Environment … Towards A Sustainable Water With An Effective Wastewater Infrastructure…. 212223 24252627 282930

Editor's Notes

  1. From GTZ Consultant Data for National Master Plan for Sanitary Engineering Services ..
  2. From GTZ Consultant Data for National Master Plan for Sanitary Engineering Services ..