Project Planning
BA 339
2
Project Planning and Control
 Definition of Project Management
 Work Breakdown Structure
 Critical Path Scheduling
 Ideal Completion Time
• Time vs. Cost tradeoffs
3
Project Management
 Project
• series of related jobs usually directed toward
some major output and requiring a significant
period of time to perform.
 Project Management
• planning, directing, and controlling resources
(people, equipment, material) to meet the
technical, cost, and time constraints of the
project.
• Project or Program?
4
Project Management
 Personal Life  Work-related
5
Ways to manage project
complexity
 Limit changes once
project begins
 Goal orientation
(completion date
focus)
 Attempt to reduce
uncertainty
 Expediters
 Constantly update
information
6
Work Breakdown Structure
Program
Project 1 Project 2
Task 1.1
Subtask 1.1.1
Work Package 1.1.1.1
Level
1
2
3
4
Task 1.2
Subtask 1.1.2
Work Package 1.1.1.2
7
Work Breakdown Structure
 Allow the elements to be worked on
independently
 Make them manageable in size
 Give authority to carry out the program
 Monitor and measure the program
 Provide the required resources
8
Project Control: Gantt
Chart
New I-5 Bridge Design
Month Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan
Pilot Study development
Pilot Study distribution
Pilot Study analysis
Time & Process analysis
Preliminary Report
Survey design & pretest
Survey translation & copy
Survey distribution
Market Model Report
Collect cost & price data
Simulation development
Simulation analysis
Final Report
9
Critical Path Scheduling
 A project must have:
• well-defined jobs or
tasks whose
completion marks the
end of the project;
• independent jobs or
tasks;
• and tasks that follow a
given sequence.
10
CPM with Single Time Estimate
Consider the following HR consulting project:
Develop a critical path diagram and determine the
duration of the critical path and slack times for all
activities
Activity Designation Immed.Pred. Time(Weeks)
Assess customer's needs A None 2
Write and submit proposal B A 1
Obtain approval C B 1
Develop service vision and goals D C 2
Train employees E C 5
Quality improvement pilot groups F D, E 5
Write assessment report G F 1
11
First draw the network
A, 2 B, 1 C, 1
D, 2
E, 5
F, 5 G, 1
12
Moving forward on the diagram (left to right):
Determine early start and early finish times
ES=0
EF=2
ES=2
EF=3
ES=3
EF=4
ES=4
EF=9
ES=4
EF=6
?
A, 2 B, 1 C, 1
D, 2
E, 5
F, 5 G, 1
13
When F can start depends on when
predecessors (D & E) finish
ES=9
EF=14
ES=14
EF=15
ES=0
EF=2
ES=2
EF=3
ES=3
EF=4
ES=4
EF=9
ES=4
EF=6
A, 2 B, 1 C, 1
D, 2
E, 5
F, 5 G, 1
14
Moving backwards on the diagram (right to left):
Determine late starts and late finish times
ES=9
EF=14
ES=14
EF=15
ES=0
EF=2
ES=2
EF=3
ES=3
EF=4
ES=4
EF=9
ES=4
EF=6
A, 2 B, 1 C, 1
D, 2
E, 5
F, 5 G, 1
LS=14
LF=15
LS=9
LF=14
LS=4
LF=9
LS=7
LF=9
?
15
Don’t delay the project
ES=9
EF=14
ES=14
EF=15
ES=0
EF=2
ES=2
EF=3
ES=3
EF=4
ES=4
EF=9
ES=4
EF=6
A, 2 B, 1 C, 1
D, 2
E, 5
F, 5 G, 1
LS=14
LF=15
LS=9
LF=14
LS=4
LF=9
LS=7
LF=9
LS=3
LF=4
LS=2
LF=3
LS=0
LF=2
16
Critical Path & Slack
slack = amount of flexibility = LS-ES or LF-EF
Critical path= completion time of the project (project bottleneck). Connect all
points on path which have no slack
ES=9
EF=14
ES=14
EF=15
ES=0
EF=2
ES=2
EF=3
ES=3
EF=4
ES=4
EF=9
ES=4
EF=6
A, 2 B, 1 C, 1
D, 2
E, 5
F, 5 G, 1
LS=14
LF=15
LS=9
LF=14
LS=4
LF=9
LS=7
LF=9
LS=3
LF=4
LS=2
LF=3
LS=0
LF=2
Duration = 15 weeks
Slack=(7-4)=(9-6)= 3 Wks
17
Time-Cost Models
 Basic Assumption: Relationship
between activity completion time and
project cost
 Time Cost Models: Determine the
optimum point in time-cost tradeoffs
• Activity direct costs
• Project indirect costs
• Activity completion times
18
Time-cost Trade-off
“Crashing” a project
 Prepare a CPM-type network diagram
 Determine the cost per unit of time (usually
assume days) to expedite each activity.
NT=normal time CT= crash time
NC=normal cost CC=crash cost
 cost to crash each day = (CC-NC)/(NT-CT)
 Compute critical path
 Shorten the critical path at the least cost
 Determine the minimum cost schedule.
19
A, 2
B, 5
C, 4
D, 3
Activity Cost per day to Expedite Number of possible Days activity may be shortened
A $ 4 1
B $ 3 3
C $ 2 1
D $ 2 2
20
Crashing
Current
Critical Path
Remaining
days activity
may be
shortened
Cost per Day
to Expedite
each Activity
Least cost
activity to
expedite
Total Cost of
all Activities
in network
Project
Completion
time
ABD All $26 10
ABD A-1, B-3,
D-2
A-4, B-3,
D-2
D $28 9
ABD A-1, B-3,
D-1
A-4, B-3,
D-2
D $30 8
ABD A-1, B-3 A-4, B-3 B $33 7
ABCD A-1, B-2,
C-1
A-4, B-3,
C-2
A $37 6
ABCD B-2, C-1 B-3, C-2 B & C $42 5
ABCD B-1 B-3 B $45 5
21
In Class Exercise: Bike Path
Project
22
Bike Path Project:
Activity Description Predecessor Estimated time
A Survey for paths None 2 weeks
B Re-route traffic None 1 weeks
C Move utilities None 4 weeks
D Prepare new path
bed
A,B,C 15 weeks
E Dig and prepare
drainage
D 5 weeks
F Set forms and
reinforcements
D 3 weeks
G Pour concrete E,F 2 weeks
H Build curbs G 3 weeks
I Pave surface G 2 weeks
23
Cost Trade-offs
 The contractor will get a $100,000 bonus for
completing the project within 25 weeks. Some of
the activities can be shortened, but will cost
more:
• Activity D: $10,000 per week for up to 3 weeks
• Activity E: $8,000 per week for up to 1 week
• Activity H: $6,000 per week for up to 1 week
• Activity I: $8,000 per week for up to 1 week
 What should he/she do?

More Related Content

Similar to LectureProjectPlanning.ppt

Engineering design process 3rd edition haik solutions manual
Engineering design process 3rd edition haik solutions manualEngineering design process 3rd edition haik solutions manual
Engineering design process 3rd edition haik solutions manualSummerfieldTBL
 
Network diagram problems
Network diagram problemsNetwork diagram problems
Network diagram problemsSubhra Mishra
 
PMGT 510Principles of Project ManagementGroup Assign.docx
PMGT 510Principles of Project ManagementGroup Assign.docxPMGT 510Principles of Project ManagementGroup Assign.docx
PMGT 510Principles of Project ManagementGroup Assign.docxstilliegeorgiana
 
Program Management 2.0: Monitoring Performance
Program Management 2.0: Monitoring PerformanceProgram Management 2.0: Monitoring Performance
Program Management 2.0: Monitoring PerformanceJohn Carter
 
Deadline 6 PM Friday September 27, 201310 Project Management Que.docx
Deadline 6 PM Friday September 27, 201310 Project Management Que.docxDeadline 6 PM Friday September 27, 201310 Project Management Que.docx
Deadline 6 PM Friday September 27, 201310 Project Management Que.docxedwardmarivel
 
Basics Planning PERT.ppt
Basics Planning PERT.pptBasics Planning PERT.ppt
Basics Planning PERT.pptKAhmedRehman
 
Chapter_3_Project_Planning_Scheduling_an 2.ppt
Chapter_3_Project_Planning_Scheduling_an 2.pptChapter_3_Project_Planning_Scheduling_an 2.ppt
Chapter_3_Project_Planning_Scheduling_an 2.pptJastienAndreanaYaran
 
00 Introduction of project scheduling
00 Introduction of project scheduling00 Introduction of project scheduling
00 Introduction of project schedulingSoe Naing Win
 
Project management
Project managementProject management
Project managementShankaran Rd
 
Lecture - Project, Planning and Control.pdf
Lecture - Project, Planning and Control.pdfLecture - Project, Planning and Control.pdf
Lecture - Project, Planning and Control.pdflucky141651
 
ABCs Of Project Time Management Planning Slides
ABCs Of Project Time Management Planning SlidesABCs Of Project Time Management Planning Slides
ABCs Of Project Time Management Planning SlidesYousef Abugosh, PMP, MA
 
Program Management 2.0: Schedule Prediction Accuracy
Program Management 2.0: Schedule Prediction AccuracyProgram Management 2.0: Schedule Prediction Accuracy
Program Management 2.0: Schedule Prediction AccuracyJohn Carter
 

Similar to LectureProjectPlanning.ppt (20)

Chap03
Chap03Chap03
Chap03
 
Ch 06 - CPM PERT (1).pptx
Ch 06 - CPM  PERT (1).pptxCh 06 - CPM  PERT (1).pptx
Ch 06 - CPM PERT (1).pptx
 
Intro to PM.ppt
Intro to PM.pptIntro to PM.ppt
Intro to PM.ppt
 
Engineering design process 3rd edition haik solutions manual
Engineering design process 3rd edition haik solutions manualEngineering design process 3rd edition haik solutions manual
Engineering design process 3rd edition haik solutions manual
 
Network diagram problems
Network diagram problemsNetwork diagram problems
Network diagram problems
 
PMGT 510Principles of Project ManagementGroup Assign.docx
PMGT 510Principles of Project ManagementGroup Assign.docxPMGT 510Principles of Project ManagementGroup Assign.docx
PMGT 510Principles of Project ManagementGroup Assign.docx
 
Program Management 2.0: Monitoring Performance
Program Management 2.0: Monitoring PerformanceProgram Management 2.0: Monitoring Performance
Program Management 2.0: Monitoring Performance
 
Critical Path Method
Critical Path MethodCritical Path Method
Critical Path Method
 
Deadline 6 PM Friday September 27, 201310 Project Management Que.docx
Deadline 6 PM Friday September 27, 201310 Project Management Que.docxDeadline 6 PM Friday September 27, 201310 Project Management Que.docx
Deadline 6 PM Friday September 27, 201310 Project Management Que.docx
 
Pmp6
Pmp6Pmp6
Pmp6
 
06 pmp time management exam
06 pmp time  management exam06 pmp time  management exam
06 pmp time management exam
 
Basics Planning PERT.ppt
Basics Planning PERT.pptBasics Planning PERT.ppt
Basics Planning PERT.ppt
 
Project Management
Project Management Project Management
Project Management
 
Chapter_3_Project_Planning_Scheduling_an 2.ppt
Chapter_3_Project_Planning_Scheduling_an 2.pptChapter_3_Project_Planning_Scheduling_an 2.ppt
Chapter_3_Project_Planning_Scheduling_an 2.ppt
 
CPM-PERT.ppt
CPM-PERT.pptCPM-PERT.ppt
CPM-PERT.ppt
 
00 Introduction of project scheduling
00 Introduction of project scheduling00 Introduction of project scheduling
00 Introduction of project scheduling
 
Project management
Project managementProject management
Project management
 
Lecture - Project, Planning and Control.pdf
Lecture - Project, Planning and Control.pdfLecture - Project, Planning and Control.pdf
Lecture - Project, Planning and Control.pdf
 
ABCs Of Project Time Management Planning Slides
ABCs Of Project Time Management Planning SlidesABCs Of Project Time Management Planning Slides
ABCs Of Project Time Management Planning Slides
 
Program Management 2.0: Schedule Prediction Accuracy
Program Management 2.0: Schedule Prediction AccuracyProgram Management 2.0: Schedule Prediction Accuracy
Program Management 2.0: Schedule Prediction Accuracy
 

Recently uploaded

Creating Low-Code Loan Applications using the Trisotech Mortgage Feature Set
Creating Low-Code Loan Applications using the Trisotech Mortgage Feature SetCreating Low-Code Loan Applications using the Trisotech Mortgage Feature Set
Creating Low-Code Loan Applications using the Trisotech Mortgage Feature SetDenis Gagné
 
Grateful 7 speech thanking everyone that has helped.pdf
Grateful 7 speech thanking everyone that has helped.pdfGrateful 7 speech thanking everyone that has helped.pdf
Grateful 7 speech thanking everyone that has helped.pdfPaul Menig
 
KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...
KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...
KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...Any kyc Account
 
M.C Lodges -- Guest House in Jhang.
M.C Lodges --  Guest House in Jhang.M.C Lodges --  Guest House in Jhang.
M.C Lodges -- Guest House in Jhang.Aaiza Hassan
 
A DAY IN THE LIFE OF A SALESMAN / WOMAN
A DAY IN THE LIFE OF A  SALESMAN / WOMANA DAY IN THE LIFE OF A  SALESMAN / WOMAN
A DAY IN THE LIFE OF A SALESMAN / WOMANIlamathiKannappan
 
Regression analysis: Simple Linear Regression Multiple Linear Regression
Regression analysis:  Simple Linear Regression Multiple Linear RegressionRegression analysis:  Simple Linear Regression Multiple Linear Regression
Regression analysis: Simple Linear Regression Multiple Linear RegressionRavindra Nath Shukla
 
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...Aggregage
 
Progress Report - Oracle Database Analyst Summit
Progress  Report - Oracle Database Analyst SummitProgress  Report - Oracle Database Analyst Summit
Progress Report - Oracle Database Analyst SummitHolger Mueller
 
Understanding the Pakistan Budgeting Process: Basics and Key Insights
Understanding the Pakistan Budgeting Process: Basics and Key InsightsUnderstanding the Pakistan Budgeting Process: Basics and Key Insights
Understanding the Pakistan Budgeting Process: Basics and Key Insightsseri bangash
 
B.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptx
B.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptxB.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptx
B.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptxpriyanshujha201
 
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best ServicesMysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best ServicesDipal Arora
 
7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...Paul Menig
 
Unlocking the Secrets of Affiliate Marketing.pdf
Unlocking the Secrets of Affiliate Marketing.pdfUnlocking the Secrets of Affiliate Marketing.pdf
Unlocking the Secrets of Affiliate Marketing.pdfOnline Income Engine
 
Cracking the Cultural Competence Code.pptx
Cracking the Cultural Competence Code.pptxCracking the Cultural Competence Code.pptx
Cracking the Cultural Competence Code.pptxWorkforce Group
 
Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...Roland Driesen
 
Call Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine ServiceCall Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine Serviceritikaroy0888
 
9599632723 Top Call Girls in Delhi at your Door Step Available 24x7 Delhi
9599632723 Top Call Girls in Delhi at your Door Step Available 24x7 Delhi9599632723 Top Call Girls in Delhi at your Door Step Available 24x7 Delhi
9599632723 Top Call Girls in Delhi at your Door Step Available 24x7 DelhiCall Girls in Delhi
 
VIP Call Girls In Saharaganj ( Lucknow ) 🔝 8923113531 🔝 Cash Payment (COD) 👒
VIP Call Girls In Saharaganj ( Lucknow  ) 🔝 8923113531 🔝  Cash Payment (COD) 👒VIP Call Girls In Saharaganj ( Lucknow  ) 🔝 8923113531 🔝  Cash Payment (COD) 👒
VIP Call Girls In Saharaganj ( Lucknow ) 🔝 8923113531 🔝 Cash Payment (COD) 👒anilsa9823
 
Famous Olympic Siblings from the 21st Century
Famous Olympic Siblings from the 21st CenturyFamous Olympic Siblings from the 21st Century
Famous Olympic Siblings from the 21st Centuryrwgiffor
 

Recently uploaded (20)

Creating Low-Code Loan Applications using the Trisotech Mortgage Feature Set
Creating Low-Code Loan Applications using the Trisotech Mortgage Feature SetCreating Low-Code Loan Applications using the Trisotech Mortgage Feature Set
Creating Low-Code Loan Applications using the Trisotech Mortgage Feature Set
 
Grateful 7 speech thanking everyone that has helped.pdf
Grateful 7 speech thanking everyone that has helped.pdfGrateful 7 speech thanking everyone that has helped.pdf
Grateful 7 speech thanking everyone that has helped.pdf
 
KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...
KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...
KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...
 
M.C Lodges -- Guest House in Jhang.
M.C Lodges --  Guest House in Jhang.M.C Lodges --  Guest House in Jhang.
M.C Lodges -- Guest House in Jhang.
 
A DAY IN THE LIFE OF A SALESMAN / WOMAN
A DAY IN THE LIFE OF A  SALESMAN / WOMANA DAY IN THE LIFE OF A  SALESMAN / WOMAN
A DAY IN THE LIFE OF A SALESMAN / WOMAN
 
Regression analysis: Simple Linear Regression Multiple Linear Regression
Regression analysis:  Simple Linear Regression Multiple Linear RegressionRegression analysis:  Simple Linear Regression Multiple Linear Regression
Regression analysis: Simple Linear Regression Multiple Linear Regression
 
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...
 
Progress Report - Oracle Database Analyst Summit
Progress  Report - Oracle Database Analyst SummitProgress  Report - Oracle Database Analyst Summit
Progress Report - Oracle Database Analyst Summit
 
Understanding the Pakistan Budgeting Process: Basics and Key Insights
Understanding the Pakistan Budgeting Process: Basics and Key InsightsUnderstanding the Pakistan Budgeting Process: Basics and Key Insights
Understanding the Pakistan Budgeting Process: Basics and Key Insights
 
B.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptx
B.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptxB.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptx
B.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptx
 
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best ServicesMysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
 
7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...
 
Forklift Operations: Safety through Cartoons
Forklift Operations: Safety through CartoonsForklift Operations: Safety through Cartoons
Forklift Operations: Safety through Cartoons
 
Unlocking the Secrets of Affiliate Marketing.pdf
Unlocking the Secrets of Affiliate Marketing.pdfUnlocking the Secrets of Affiliate Marketing.pdf
Unlocking the Secrets of Affiliate Marketing.pdf
 
Cracking the Cultural Competence Code.pptx
Cracking the Cultural Competence Code.pptxCracking the Cultural Competence Code.pptx
Cracking the Cultural Competence Code.pptx
 
Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...
 
Call Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine ServiceCall Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine Service
 
9599632723 Top Call Girls in Delhi at your Door Step Available 24x7 Delhi
9599632723 Top Call Girls in Delhi at your Door Step Available 24x7 Delhi9599632723 Top Call Girls in Delhi at your Door Step Available 24x7 Delhi
9599632723 Top Call Girls in Delhi at your Door Step Available 24x7 Delhi
 
VIP Call Girls In Saharaganj ( Lucknow ) 🔝 8923113531 🔝 Cash Payment (COD) 👒
VIP Call Girls In Saharaganj ( Lucknow  ) 🔝 8923113531 🔝  Cash Payment (COD) 👒VIP Call Girls In Saharaganj ( Lucknow  ) 🔝 8923113531 🔝  Cash Payment (COD) 👒
VIP Call Girls In Saharaganj ( Lucknow ) 🔝 8923113531 🔝 Cash Payment (COD) 👒
 
Famous Olympic Siblings from the 21st Century
Famous Olympic Siblings from the 21st CenturyFamous Olympic Siblings from the 21st Century
Famous Olympic Siblings from the 21st Century
 

LectureProjectPlanning.ppt

  • 2. 2 Project Planning and Control  Definition of Project Management  Work Breakdown Structure  Critical Path Scheduling  Ideal Completion Time • Time vs. Cost tradeoffs
  • 3. 3 Project Management  Project • series of related jobs usually directed toward some major output and requiring a significant period of time to perform.  Project Management • planning, directing, and controlling resources (people, equipment, material) to meet the technical, cost, and time constraints of the project. • Project or Program?
  • 4. 4 Project Management  Personal Life  Work-related
  • 5. 5 Ways to manage project complexity  Limit changes once project begins  Goal orientation (completion date focus)  Attempt to reduce uncertainty  Expediters  Constantly update information
  • 6. 6 Work Breakdown Structure Program Project 1 Project 2 Task 1.1 Subtask 1.1.1 Work Package 1.1.1.1 Level 1 2 3 4 Task 1.2 Subtask 1.1.2 Work Package 1.1.1.2
  • 7. 7 Work Breakdown Structure  Allow the elements to be worked on independently  Make them manageable in size  Give authority to carry out the program  Monitor and measure the program  Provide the required resources
  • 8. 8 Project Control: Gantt Chart New I-5 Bridge Design Month Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Pilot Study development Pilot Study distribution Pilot Study analysis Time & Process analysis Preliminary Report Survey design & pretest Survey translation & copy Survey distribution Market Model Report Collect cost & price data Simulation development Simulation analysis Final Report
  • 9. 9 Critical Path Scheduling  A project must have: • well-defined jobs or tasks whose completion marks the end of the project; • independent jobs or tasks; • and tasks that follow a given sequence.
  • 10. 10 CPM with Single Time Estimate Consider the following HR consulting project: Develop a critical path diagram and determine the duration of the critical path and slack times for all activities Activity Designation Immed.Pred. Time(Weeks) Assess customer's needs A None 2 Write and submit proposal B A 1 Obtain approval C B 1 Develop service vision and goals D C 2 Train employees E C 5 Quality improvement pilot groups F D, E 5 Write assessment report G F 1
  • 11. 11 First draw the network A, 2 B, 1 C, 1 D, 2 E, 5 F, 5 G, 1
  • 12. 12 Moving forward on the diagram (left to right): Determine early start and early finish times ES=0 EF=2 ES=2 EF=3 ES=3 EF=4 ES=4 EF=9 ES=4 EF=6 ? A, 2 B, 1 C, 1 D, 2 E, 5 F, 5 G, 1
  • 13. 13 When F can start depends on when predecessors (D & E) finish ES=9 EF=14 ES=14 EF=15 ES=0 EF=2 ES=2 EF=3 ES=3 EF=4 ES=4 EF=9 ES=4 EF=6 A, 2 B, 1 C, 1 D, 2 E, 5 F, 5 G, 1
  • 14. 14 Moving backwards on the diagram (right to left): Determine late starts and late finish times ES=9 EF=14 ES=14 EF=15 ES=0 EF=2 ES=2 EF=3 ES=3 EF=4 ES=4 EF=9 ES=4 EF=6 A, 2 B, 1 C, 1 D, 2 E, 5 F, 5 G, 1 LS=14 LF=15 LS=9 LF=14 LS=4 LF=9 LS=7 LF=9 ?
  • 15. 15 Don’t delay the project ES=9 EF=14 ES=14 EF=15 ES=0 EF=2 ES=2 EF=3 ES=3 EF=4 ES=4 EF=9 ES=4 EF=6 A, 2 B, 1 C, 1 D, 2 E, 5 F, 5 G, 1 LS=14 LF=15 LS=9 LF=14 LS=4 LF=9 LS=7 LF=9 LS=3 LF=4 LS=2 LF=3 LS=0 LF=2
  • 16. 16 Critical Path & Slack slack = amount of flexibility = LS-ES or LF-EF Critical path= completion time of the project (project bottleneck). Connect all points on path which have no slack ES=9 EF=14 ES=14 EF=15 ES=0 EF=2 ES=2 EF=3 ES=3 EF=4 ES=4 EF=9 ES=4 EF=6 A, 2 B, 1 C, 1 D, 2 E, 5 F, 5 G, 1 LS=14 LF=15 LS=9 LF=14 LS=4 LF=9 LS=7 LF=9 LS=3 LF=4 LS=2 LF=3 LS=0 LF=2 Duration = 15 weeks Slack=(7-4)=(9-6)= 3 Wks
  • 17. 17 Time-Cost Models  Basic Assumption: Relationship between activity completion time and project cost  Time Cost Models: Determine the optimum point in time-cost tradeoffs • Activity direct costs • Project indirect costs • Activity completion times
  • 18. 18 Time-cost Trade-off “Crashing” a project  Prepare a CPM-type network diagram  Determine the cost per unit of time (usually assume days) to expedite each activity. NT=normal time CT= crash time NC=normal cost CC=crash cost  cost to crash each day = (CC-NC)/(NT-CT)  Compute critical path  Shorten the critical path at the least cost  Determine the minimum cost schedule.
  • 19. 19 A, 2 B, 5 C, 4 D, 3 Activity Cost per day to Expedite Number of possible Days activity may be shortened A $ 4 1 B $ 3 3 C $ 2 1 D $ 2 2
  • 20. 20 Crashing Current Critical Path Remaining days activity may be shortened Cost per Day to Expedite each Activity Least cost activity to expedite Total Cost of all Activities in network Project Completion time ABD All $26 10 ABD A-1, B-3, D-2 A-4, B-3, D-2 D $28 9 ABD A-1, B-3, D-1 A-4, B-3, D-2 D $30 8 ABD A-1, B-3 A-4, B-3 B $33 7 ABCD A-1, B-2, C-1 A-4, B-3, C-2 A $37 6 ABCD B-2, C-1 B-3, C-2 B & C $42 5 ABCD B-1 B-3 B $45 5
  • 21. 21 In Class Exercise: Bike Path Project
  • 22. 22 Bike Path Project: Activity Description Predecessor Estimated time A Survey for paths None 2 weeks B Re-route traffic None 1 weeks C Move utilities None 4 weeks D Prepare new path bed A,B,C 15 weeks E Dig and prepare drainage D 5 weeks F Set forms and reinforcements D 3 weeks G Pour concrete E,F 2 weeks H Build curbs G 3 weeks I Pave surface G 2 weeks
  • 23. 23 Cost Trade-offs  The contractor will get a $100,000 bonus for completing the project within 25 weeks. Some of the activities can be shortened, but will cost more: • Activity D: $10,000 per week for up to 3 weeks • Activity E: $8,000 per week for up to 1 week • Activity H: $6,000 per week for up to 1 week • Activity I: $8,000 per week for up to 1 week  What should he/she do?