e-Jurnal MATRIKS TEKNIK SIPIL Vol. 1 No. 4/Desember 2013/408
ANALISIS NETWORK PLANNING DENGAN CPM (CRITICAL PATH METHOD)
DALAM RANGKA EFISIENSI WAKTU DAN BIAYA PROYEK
Sugiyarto1), Siti Qomariyah2), Faizal Hamzah3)
1),2) Pengajar, Fakultas Teknik, Jurusan Teknik Sipil, Universitas Sebelas Maret
3) Mahasiswa, Fakultas Teknik, Jurusan Teknik Sipil, Universitas Sebelas Maret
Jln Ir. Sutami 36A, Surakarta 57126 Telp: 0271-634524.
Email : xsmile_adefh@yahoo.com
Abstract
CPM (Critical Path Method) is one of network planning methods are oriented at the time that led to the determination of project scheduling and
time estimation are diterministik / definite. Research objectives with this method is to determine the time and cost of the project and to find out
what activities are included in the critical activities. In addition, to control and coordinate the various activities in a project so that the work can be
completed in a timely manner and can also help the company in organizing the planning and control of project time and cost efficient. With the use
of the CPM method produces a critical path with 18 activities and two S curves is to schedule the earliest and at the latest. The calculation of the
CPM method takes 135 days at a cost of Rp. 979.239.000, - while the calculations performed by CV. Catur Tunggal takes 150 days at a cost
of Rp. 1.001.454.000,-. Based on CPM method saves time project completion 15 days (10%) and cost of Rp. 22.215.000,-.
Keywords: Project Management, Network Analysis, CPM, Critical Path, Time and Cost Efficiency Project, Curve S.
Abstrak
CPM (Critical Path Method) adalah salah satu metode network planning yang berorientasi pada waktu yang mengarah pada pe-
nentuan penjadwalan proyek dan estimasi waktunya bersifat diterministik/pasti. Tujuan penelitian dengan metode ini adalah
untuk menentukan waktu dan biaya proyek serta mengetahui kegiatan apa saja yang termasuk dalam kegiatan kritis. Selain itu
juga untuk mengontrol dan mengkoordinasi berbagai kegiatan sehingga proyek dapat diselesaikan dalam jangka waktu yang
tepat dan juga dapat membantu perusahaan dalam mengadakan perencanaan dan pengendalian proyek dengan waktu dan bi-
aya yang lebih efisien. Dengan penggunaan metode CPM ini menghasilkan satu jalur kritis dengan 18 kegiatan dan dua kurva
S yaitu untuk jadwal kegiatan paling awal dan paling lambat. Hasil perhitungan dengan metode CPM membutuhkan waktu
135 hari dengan biaya Rp. 979.239.000,- sedangkan perhitungan yang dilakukan oleh CV. Catur Tunggal membutuhkan wak-
tu 150 hari dengan biaya Rp. 1.001.454.000,-. Berdasarkan metode CPM menghemat waktu penyelesaian proyek 15 hari
(10%) dan biaya sebesar Rp. 22.215.000,-.
Kata Kunci: Manajemen Proyek, Analisa Network, CPM, Jalur Kritis, Efisiensi Waktu dan Biaya Proyek, Kurva S.
PENDAHULUAN
Banyaknya perusahaan kontraktor yang berdiri dan bermunculan mengakibatkan persaingan antar perusahaan un-
tuk mendapatkan proyek semakin terasa sehingga mendorong setiap perusahaan untuk dapat lebih meningkatkan
potensi sumberdaya yang mereka miliki. Salah satu hal dalam persaingan tersebut adalah bersaing dalam segi wak-
tu dan biaya produksi. Dalam hal waktu dan biaya produksi, perusahaan harus bisa seefisien mungkin dalam
penggunaan waktu pada setiap kegiatan atau aktivitas, sehingga biaya dapat diminimalkan dari rencana anggaran
biaya semula. Perencanaan kegiatan proyek merupakan masalah yang sangat penting karena perencanaan kegiatan
merupakan dasar untuk proyek bisa berjalan dan agar proyek yang dilaksanakan dapat selesai dengan waktu yang
optimal dan efisien.
Pada pembangunan sebuah gedung atau yang lainya perlu adanya penanganan manajemen penjadwalan kerja
yang baik, karena itu perlu adanya perhitungan yang cermat dan teliti. Suatu proyek dikatakan baik jika penyele-
saian proyek tersebut efisien dari segi waktu dan biaya serta mempertinggi efisiensi kerja baik sumber daya manu-
sia maupun alat (Badri, 1997:14). Dalam rangka menentukan waktu dan biaya pelaksanaan proyek, maka
diperlukan adanya suatu alternatif pemecahan masalah waktu dan biaya terhadap penjadwalan pelaksanaan
proyek yang dimaksudkan untuk mengoptimalisasikan jangka waktu penyelesaian proyek dan meminimalkan total
biaya proyek. Salah satu alternatifnya yaitu analisis network planning dengan metode CPM (Critical Path Method).
Metode ini dapat dipakai untuk mengontrol dan mengkoordinasi berbagai kegiatan dalam suatu pekerjaan se-
hingga proyek dapat diselesaikan dalam jangka waktu yang tepat dan juga dapat membantu perusahaan dalam
mengadakan perencanaan dan pengendalian proyek dengan waktu dan biaya yang lebih efisien. Dari penelitian
analisis network planning dengan metode CPM ini diharapkan pada perencanaan penjadwalan pelaksanaan
proyek dapat memperoleh waktu dan biaya pelaksanaan proyek yang lebih efisien.
TINJAUAN PUSTAKA
Manajemen merupakan ilmu dan seni mengatur proses pemanfaatan sumber daya manusia dan sumber-sumber
lainnya secara efektif dan efisien untuk mencapai satu tujuan. (Mulayu S.P. Hasibuan, 2000:2).
e-Jurnal MATRIKS TEKNIK SIPIL Vol. 1 No. 4/Desember 2013/409
Proyek adalah setiap pekerjaan yang memiliki kegiatan awal dan memiliki kegiatan akhir, dengan kata lain setiap
pekerjaan yang dimulai pada waktu tertentu dan direncanakan selesai atau berakhir pada waktu yang telah
ditetapkan. (Yamit; 2000:296). Manajemen proyek adalah kegiatan merencanakan, mengorganisasikan,
mengarahkan dan mengendalikan sumber daya organisasi perusahaan untuk mencapai tujuan tertentu dalam
waktu tertentu dengan sumber daya tertentu. (Budi santoso; 2003:3)
Dalam proses untuk mencapai tujuan proyek terdapat batasan yang harus dipenuhi biaya atau anggaran, waktu
atau jadwal, serta kualitas atau mutu. Tiga hal tersebut merupakan parameter penting dalam penyelengaraan suatu
proyek dan sering disebut juga triple constrain. Triple constrain tersebut yaitu:
1. Biaya atau anggaran
Suatu proyek harus diselesaikan dengan biaya yang tidak boleh melebihi anggaran. Proyek berskala besar dan
proses pelaksanaannya bertahun-tahun, biayanya tidak hanya ditentukan dalam total proyek, akan tetapi terba-
gi atas bagian-bagian atau periode tertentu yang jumlahnya disesuaikan dengan keperluan. Dengan demikian
penyelesaian bagian-bagian proyek harus memenuhi sasaran anggaran perperiode.
2. Waktu atau jadwal
Proyek harus dikerjakan sesuai dengan kurun waktu yang telah ditentukan dan penyerahannya tidak boleh me-
lewati batas waktu yang telah ditentukan.
3. Kualitas atau mutu
Hasil kegiatan atau produk harus memenuhi spesifikasi dan kriteria mutu yang telah dipersyaratkan.
Biaya
Waktu Mutu
Gambar 1. Hubungan triple constrain (Iman Soeharto, 1997:3)
Tiga batasan tersebut diatas bersifat saling bersangkutan dan saling tarik-menarik. Jika ingin meningkatkan kinerja
produk yang telah ditentukan, maka secara umumnya harus diikuti dengan meningkatkan mutu. Hal ini selanjut-
nya berakibat pada naiknya biaya sehingga melebihi anggaran. Sebaliknya jika ingin menekan atau memperkecil
biaya, maka biasanya harus memperhatikan jadwal atau waktu dan mutu juga.
Jaringan kerja (Network Planning)
Jaringan kerja merupakan salah satu metode yang menjelaskan hubungan antara kegiatan dan waktu yang secara
grafis mencerminkan urutan rencana kegiatan atau pekerjaan proyek. (Imam Soeharto; 1990:63). Jaringan kerja
pada dasarnya adalah hubungan ketergantungan antara bagian pekerjaan yang digambarkan atau divisualisasikan
dalam diagram network. Dengan demikian dapat diketahui pada area mana pekerjaan yang termasuk kedalam lin-
tasan kritis dan harus diutamakan pelaksanaanya, pekerjaan mana yang menunggu selesainya pekerjaan yang lain,
pekerjaan mana yang tidak perlu tergesa-gesa sehingga alat dan orang digeser ketempat lain demi efisiensi.
CPM (Critical Path Method)
CPM adalah metode yang berorientasi pada waktu yang mengarah pada penentuan jadwal dan estimasi waktunya
bersifat diterministik/pasti. Menurut Srivastava (1995:663).
Jalur Kritis
Jalur kritis itu sendiri merupakan jalur yang memiliki waktu terpanjang dari semua jalur yang dimulai dari peristi-
wa awal hingga peristiwa yang terakhir. .(Yamit; 2000:301). Kegunaan jalur kritis tersebut untuk mengetahui ke-
giatan yang memiliki kepekaan sangat tinggi atas keterlambatan penyelesaian pekerjaan, atau disebut juga kegiatan
kritis. Apabila kegiatan keterlambatan proyek maka akan memperlambat penyelesaian proyek secara keseluruhan
meskipun kegiatan lain tidak mengalami keterlambatan.(Yamit; 2000:301). Dengan demikian waktu yang diperlu-
kan untuk penyelesaian jalur kritis adalah sama dengan waktu untuk menyelesaikan proyek secara keseluruhan.
Waktu longgar merupakan jumlah waktu kegiatan tertentu dapat ditunda, tanpa menunda keseluruhan proyek.
Bila waktu longgar nol maka kegiatan yang berada disepanjang jalur waktu longgar nol tersebut adalah kegiatan
kritis dan jalurnya disebut jalur kritis.
Efisiensi Waktu dan Biaya
Efisiensi adalah tingkat kehematan dalam menggunakan sumber daya yang ada dalam rangka mencapai tujuan
yang diinginkan. Efisiensi terbagi menjadi dua, yaitu efisiensi waktu dan efisiensi biaya. Efisiensi waktu adalah
tingkat kehematan dalam hal waktu saat pelaksanaan hingga kapan proyek itu selesai. Sedangkan efisiensi biaya
e-Jurnal MATRIKS TEKNIK SIPIL Vol. 1 No. 4/Desember 2013/410
adalah tingkat kehematan dan pengorbanan ekonomi yang dilakukan untuk mencapai tujuan yang telah dite-
tapkan. (Muchdoro, 1997:180).
Diagram Network
Variabel kegiatan dalam membuat diagram network adalah kurun waktu, tanggal mulai dan tanggal berakhir. Bila
kegiatan tersebut dijumlahkan kembali akan menjadi lingkup proyek keseluruhan.
a. Peristiwa atau kejadian dan milestone, adalah suatu titik waktu dimana semua kegiatan sebelumnya sudah selesai
dan kegiatan sesudah itu dapat dimulai. Peristiwa dalam proyek adalah titik awal dimulainya proyek dan peris-
tiwa akhir adalah titik dimana proyek selesai. Salah satu peristiwa atau event yang penting dinamakan tonggak
kemajuan atau milestone.
b. Node i dan nide j yang berada diekor anak panah adalah node i, sedngkan yang dikepala adalah node j. Tetapi
node j akan menjadi node i untuk kegiatan berikutnya.
c. Kecuali kegiatan awal maka sebelum suatu kegiatan dapat dimulai, kegiatan terdahulu harus sudah selesai.
d. Dummy merupakan anak panah yang hanya menjelaskan hubungan ketergantungan antara dua kegiatan, tidak
memerlukan sumber daya dan tidak membutuhkan waktu.
e. Penyajian grafis jaringan kerja tidak membutuhkan skala, kecuali untuk keperluan tertentu.
SPAi
SPLi
i
SPAj
SPLj
j
Kegiatan i-j
L
Gambar 2 Hubungan Kegiatan
Keterangan :
I : nomor dari lingkaran kegiatan yang merupakan per-
mulaan dari kegiatan yang ditinjau.
J : nomor dari libgkaran kejadian yang merupakan ujung
akhir dari kegiatan yang ditinjau.
Untuk menyusun network planning digunakan tanda atau simbol sebagai berikut:
1. Anak panah (arrow)
Adalah lambang aktifitas atau kegiatan. Anak panah menggambarkan keterkaitan antar kegiatan proyek atau
urutan kegiatan yang harus diselesaikan. Kegiatan ini memerlukan jangka waktu tertentu dengan mengguna-
kan sumber daya.
2. Lingkaran kecil (node)
Menyatakan suatu kegiatan, peristiwa atau event. Kejadian didefinisikan sebagai ujung atau pertemuan dari satu
atau lebih kegiatan.
3. Anak panah sejajar (double arrow)
Merupakan yang menunjunkan kegiatan dilintasan keritis.
4. Anak panah terputus-putus (dummy)
Menunjukan kaitan antara dua kegiatan yang satu harus menunggu selesainya satu kegiatan lain/kegiatan se-
mu. Dummy berfungsi untuk membatasi mulainya kegiatan. Dummy tidak mempunyai durasi karena tidak me-
makai atau menghabiskan sumber daya.
Hubungan Antar Simbol dan Urutan Kegiatan
Dalam proses perhitungan dengan metode CPM dikenal adanya beberapa parameter sebagai berikut:
a. SPA (Saat Paling Awal) : Saat paling cepat atau paling awal peristiwa/node/event mungkin terjadi, yang berar-
ti waktu paling cepat suatu kegiatan yang berasal dari node tersebut dapat dimulai karena menurut aturan da-
sar suatu kegiatan baru dapat dimulai bila kegiatan-kegiatan terdahulu selesai.
b. SPAi : Saat paling cepat peristiwa yang mungkin terjadi, maksunya waktu mulai paling awal suatu kegiatan. Bi-
la waktu kegiatan dinyatakan dalam hari, maka waktu ini merupakan hari pertama kegiatan dimulai.
c. SPAj : Saat paling cepat peristiwa terakhir mungkin terjadi, berarti waktu selesai paling awal suatu kegiatan. Bi-
la hanya ada satu kegiatan terdahulu, maka SPAj kegiatan terdahulunya merupakan SPAi kegiatan berikutnya.
Untuk sebuah kegiatan menuju ke sebuah peristiwa
SPAi
i
SPAj
j
X
L
Rumus :
SPAj=SPAi+L (1)
Keterangan :
X = Kegiatan
j = Peristiwa akhir kegiatan X
i = Peristiwa awal kegiatan X
L = Lama kegiatan X yang diperkirakan
SPAi = Saat paling awal peristiwa awal
e-Jurnal MATRIKS TEKNIK SIPIL Vol. 1 No. 4/Desember 2013/411
SPAj = Saat paling awal peristiwa akhir
Untuk sebuah kegiatan menuju ke sebuah peristiwa
L2
X1
SPAi1
i1
SPAi2
i2
SPAj
j
L1
X2
Rumus :
SPAj = (SPAin + Ln) maksimum (2)
Keterangan :
n = Nomor kegiatan (n = 1,2,3…….z)
Xn = Nma kegiatan ke – n
J = Peristiwa akhir bersama dari semua kegiatan Xn
in = Peristiwa awal kegiatan Xn
SPAin = Saat paling awal peristiwa awal dari kegiatan Xn
Ln = Lama kegistan Xn yang diperkirakan
SPAj =Saat paling awal peristiwa akhir seluruh kegiatan.
SPL (Saat Paling Lambat) : Saat paling lambat suatu peristiwa boleh terjadi, berarti waktu paling lambat yang ma-
sih diperbolehkan bagi suatu peristiwa terjadi.
a. SPLi : Saat paling lambat peristiwa awal boleh terjadi atau waktu paling akhir kegiatan boleh dimulai, yaitu
waktu paling akhir kegiatan boleh dimulai tanpa memperlambat proyek secara keseluruhan.
b. SPLj : Saat paling lambat peristiwa akhir boleh terjadi, berarti waktu paling akhir kegiatan boleh selesai tanpa
memperlambat penyelesaian proyek.
Untuk sebuah kegiatan keluar dari sebuah peristiwa
i j
SPLi SPLj
X
L
Rumus :
SPLi = SPLj – L (3)
Keterangan:
X = Kegiatan
j = Peristiwa akhir kegiatan X
i = Peristiwa awal kegiatan X
L = Lama kegiatan X yang diperkirakan
SPLi = Saat paling lambat peristiwa awal
SPLj = Saat paling lambat peristiwa akhir.
Untuk beberapa kegiatan keluar dari sebuah peristiwa
L2
X1
SPLi
i
SPLj1
j1
SPLj2
j2
L1
X2
Rumus :
SPLi = (SPLjn - Ln) minimum (4)
Keterangan:
n = Nomor kegiatan (n = 1,2,3…….z)
Xn = Nama kegiatan ke – n
i = Peristiwa awal bersama dari semua kegiatan n
jn = Peristiwa akhir masin-masing kegiatan n
SPLjn = Saat paling lambat peristiwa akhir kegiatan Xn
Ln = Lama kegistan Xn yang diperkirakan
SPLi = Saat paling lambat peristiwa awal kegiatan
Jalur Kritis
Peristiwa kritis adalah peristiwa yang tidak mempunyai tenggang waktu SPA-nya sama dengan SPL-nya. Sedang-
kan kegiatan kritis adalah kegiatan yang sangat sensitive terhadap keterlambatan, sehingga bila sebuah kegiatan
kritis terlambat satu hari saja, sedang kegiatan lainnya tidak, maka proyek akan mengalami keterlambatan selama
satu hari. Sifat kritis ini disebabkan karena kegiatan tersebut harus dimulai dan harus selesai pada satu saat. Ke-
simpulannya berarti : SPAi = SPLi SPLj = SPLj
Karena harus dimulai pada suatu saat awal saja dan selesai suatu saat akhir saja dan tidak ada alternative saat lain-
nya, maka : SPAi + L = SPAj SPLi + L = SPLj
Keterangan: L = Lama kegiatan kritis SPAi = SPA peristiwa awal
SPAj = SPA peristiwa akhir SPLi = SPL peristiwa awal
SPLj = SPL peristiwa akhir
Lintasan kritis adalah lintasan yang terdiri dari kegiatan-kegiatan kritis, peristiwa-peristiwa kritis, dan dummy. Tu-
juan mengetahui lintasan kritis adalah untuk mengetahui dengan cepat kegiatan dan peristiwa yang tingkat kepe-
kaannya paling tinggi terhadap keterlambatan pelaksanaan, sehingga setiap saat dapat ditentukan tingkat prioritas
kebijaksanaan proyek, yaitu terhadap kegiatan kritis dan hampir kritis. Dalam mengidentifikasikan jalur keritis
perhitungan waktu pada suatu jaringan kerja dapat dilakukan melalui dua cara, yaitu :
a. Perhitungan maju
Hitungan maju adalah cara perhitungan waktu mulai dari selesai suatu kegiatan dalam rangkaian jaringan kerja
hanya mempergunakan SPAi, SPAj, dan L. Aturan dalam hitungan maju
 Kecuali kegiatan awal, maka suatu kegiatan baru dapat dimulai bila kegiatan yang mendahuluinya telah se-
lesai. Rumus : SPAj = SPAi + L (5)
e-Jurnal MATRIKS TEKNIK SIPIL Vol. 1 No. 4/Desember 2013/412
 Bila suatu kegiatan memiliki dua atau lebih kegiatan menggabung, maka SPCi kegiatan tersebut adalah
SPCj yang terbesar dari kegiatan terdahulu.
b. Perhitungan mundur
Perhitungan mundur dimaksudkan untuk mengetahui waktu paling akhir kegiatan masih dapat dimulai dan
mengakhiri masing-masing kegiatan. Hitungan mundur dimulai dari ujung kanan suatu jaringan kerja atau
waktu akhir penyelesaian proyek. Aturan dalam hitungan mundur
 Bila hanya ada satu kegiatan yang keluar dari peristiwa, maka waktu paling kahir dari kegiatan tersebut sa-
ma dengan waktu selesai paling akhir dikurangi dengan kurun waktu kegiatanya
Rumus : SPLi = SPLj – L (6)
 Bila suatu kegiatan memiliki dua atau lebih yang mengikuti, maka SPLj kegiatan tersebut adalah sama den-
gan SPLi kegiatan berikutnya yang terkecil.
Tenggang Waktu Kegiatan
Tenggang waktu kegiatan adalah jangka waktu yang merupakan ukuran batas toleransi keterlambatan kegiatan.
Dengan ukuran ini dapat diketahui karakteristik pengaruh keterlambatan terhadap penyelenggaraan proyek dan
terhadap pola kebutuhan sumber daya dan biaya.
a. Syarat menghitung tenggang waktu kegiatan adalah:
 Telah ada network diagram yang tepat yaitu terdiri dari kegiatan, peristiwa, dan dummy (bila diperlukan)
yang jumlahnya tepat, hubungan logika antar kegiatan memenuhi persyaratan, dan nomor-nomor peristi-
wanya memeuhi persyaratan.
 Lama kegiatan perkiraan masing-masing telah ditentukan.
 Telah dihitung SPA dan SPL semua peristiwa.
b. Float
Float merupakan sejumlah waku yang tersedia dalam suatu kegiatan, sehingga memungkinkan penundaan atau
perlambatan kegiatan secara sengaja/tidak sengaja, tetapi penundaan tersebut tidak menyebabkan proyek
menjadi terlambat dalam penyelesainnya. Ada tiga macam bentuk tenggang waktu kegiatan yaitu :
 Total Float (TF) : Pada penyusunan dan perencanaan jadwal proyek, arti penting dari total float adalah
menunjukan jumlah waktu yang diperkenankan suatu kegiatan boleh ditunda tanpa mempengaruhi jadwal
proyek secara keseluruhan. Rumus : TF = SPLj - L – SPAi (7)
 Free Float (FF) : adalah jangka waktu antara saat paling awal peristiwa akhir (SPAj) kegiatan yang bersang-
kutan dengan saat selesainya kegiatan yang bersangkutan, bila kegiatan tersebut dimulai pada saat paling
awal (SPAi). Rumus : FF = SPAj - L – SPAi (8)
 Independent Float (IF) : adalah jangka waktu antara saat paling awal peristiwa akhir (SPAj) kegiatan yang
bersangkutan dengan saat selesainya kegiatan tersebut, bila kegiatan tersebut dimulai pada saat paling lam-
bat peristiwa awal (SPLi)nya Rumus : IF = SPAj – L – SPLi (9)
c. Limit jadwal kegiatan
 Keadaan jadwal paling awal
Merupakan keadaan pada saat pelaksanaan kegiatan dimulai dan diselesaikan seawal mungkin. Ini berarti
bahwa kegiatan tersebut tidak mungkin dilaksanakan sebelum saat paling awal kegiatan yang bersangkutan.
Keadaan ini selanjutnya disebut jadwal tipe I dan disebut juga hari mulai satu (HM1), dan hari penyelesaian
kegiatan tersebut adalah hari selesai satu (HS1). Rumus : HM1 = SPA1+1 (10)
HS1= SPA1+L (11)
 Keadaan jadwal paling lambat
Merupakan keadaan pada saat pelaksanaan kegiatan dimulai dan diselesaikan selambat mungkin. Oleh ka-
rena itu kegiatan tersebut tidak boleh berlangsung melebihi saat paling lambatnya, agar proyek tidak men-
galami keterlambatan. Hari mulai jadwal tipe II disebut hari mulai dua (HM2) dan hari penyelesaian dis-
ebut hari penyelesaian dua (HS2). Rumus : HM2 = SPLj+L+1 (12)
HS2 = SPAj (13)
(Tubagus haedar ali, 1997, 111)
Setelah diperoleh durasi waktu tiap-tiap kegiatan, dari hitungan maju maupun mundur, dapat dianalisis tenggang
waktu aktifitas kegiatan tersebut. Dengan menganalisis float dapat diketahui batas toleransi keterlambatan itu
apakah dapat mempengaruhi proyek atau tidak.
METODE
Metode penelitian yang digunakan adalah penelitian deskriptif. Penelitian deskriptif merupakan penelitian yang
dimaksudkan untuk mengumpulkan informasi mengenai status gejala yang ada, yaitu keadaan gejala menurut apa
e-Jurnal MATRIKS TEKNIK SIPIL Vol. 1 No. 4/Desember 2013/413
adanya pada saat penelitian dilakukan. (Arikunto, 2000:309). Penelitian ini dilakukan pada Proyek Pembangunan
Kantor Kelurahan Kerten Kecamatan Laweyan Kota Surakarta dan CV. Catur Tunggal sebagai kontraktor yang
mengerjakan proyek tersebut.. Salah satu metode penelitian yang digunakan dalam efisiensi waktu dan biaya pada
Proyek Pembangunan Kantor Kelurahan Kerten Kecamatan Laweyan Kota Surakarta ini adalah metode CPM
(Critical Path Method).
Untuk mempermudah analisis dalam penelitian ini maka diperlukan data-data yang berkaitan secara langsung
maupun tidak langsung dengan Proyek Pembangunan Kantor Kelurahan Kerten Kecamatan Laweyan Kota Su-
rakarta. Data-data tersebut antara lain : Rencana kerja dalam bentuk kurva S, Rencana Angaran Biaya (RAB), item
pekerjaan dan volume pekerjaan beserta harga satuan pekerjaan, dan data lain yang berhubungan dengan perma-
salahan penelitian.
Langkah-langkah analisis dengan metode CPM adalah sebagai berikut :
1. Pengumpulan data baik di lingkungan proyek maupun dari instansi terkait.
2. Menguraikan jenis kegiatan menjadi kegiatan atau kelompok kegiatan yang merupakan komponen proyek.
3. Menyusun hubungan ketergantungan antara kegiatan-kegiatan yang terlibat dalam pelaksanaan dan menjadi-
kannya mata rantai dengan urutan yang sesuai dengan logika ketergantungan tersebut. Urutan ini dapat ber-
bentuk seri atau paralel.
4. Membuat diagram network untuk tiap kegiatan-kegiatan pada pelaksanaan proyek.
5. Menentukan kurun waktu bagi masing-masing kegiatan yang dihasilakn dari penguraian lingkup proyek.
Umumnya satuan waktu yang digunakan adalah hari. Penentuan kurun waktu kegiatan tergantung dari volume
pekerjaan, sumber daya, ruangan, dan produktifitas jam kerja perhari kerja.
6. Menentukan atau mengidentifikasi jalur kritis dan float pada jaringan kerja.
7. Menghitung biaya seluruh kegiatan atau pekerjaan.
8. Analisa waktu yang dilakukan yaitu dengan membuat tolak ukur waktu pada saat paling awal/SPA dan pada
saat paling lambat/SPL.
9. Setelah diperoleh kurva S dengan tolak ukur yang menunjukan SPA dan SPL, maka kita dapat membanding-
kan antara perencanaan atau jadwal dari pihak kontraktor dengan hasil analisis ini.
10.Pengambilan kesimpulan dari hasil analisis yang dilakukan dan merupakan jawaban atas rumusan masalah se-
perti yang tertera pada bab 1.
HASIL DAN PEMBAHASAN
Hasil Analisis
Proyek yang ditinjau dalam penelitian ini adalah Proyek Pembangunan Kantor Kelurahan Kerten Kecamatan
Laweyan Kota Surakarta yang dikerjakan oleh CV. Catur Tunggal dengan nilai kontrak Rp. 1.001.454.000,- dan
waktu pelaksanaan 150 hari kalender.
Penyusunan Jaringan Kerja CPM
A. Mengidentifikasi pekerjaan yang akan dianalisis.
Berdasarkan data time schedule, rencana anggaran biaya dan gambar gedung yang diperoleh dari CV. Catur
Tunggal meliputi berbagai macam pekerjaan. Dari berbagai macam pekerjaan tersebut akan diuraikan menjadi
kegiatan atau kelompok kegiatan dan disusun daftar rencana kegiatan beserta gambar network planning.
B. Menyusun kembali komponen-komponen proyek
 Urutan sesuai logika ketergantungan
Jaringan kerja metode CPM hanya mengenal satu macam hubungan antar kegiatan yaitu finish to start (FS) di-
mana suatu kegiatan dapat dimulai setelah kegiatan yang mendahuluinya selesai dikerjakan. Selain hubungan
FS, kadang juga diperlukan adanya dummy. Dummy merupakan kegiatan fiktif, gunanya untuk menghubungkan
dua peristiwa yang tidak memerlukan kegiatannn tertentu. Logika ketergantungan ini didasarkan pada tahapan
pekerjaan antara kegiatan yang mendahului dengan kegiatan sesudahnya yang saling berkaitan dengan durasi
waktu penyelesaian pekerjaan.
 Diagram jaringan kerja metode CPM
Untuk menjelaskan hubungan antara komponen yang sesuai dengan logika ketergantungan tersebut diperlu-
kan banyak visualisasi yang salah satunya berupa diagram jaringan kerja metode CPM.
C. Memperkirakan durasi waktu masing-masing kegiatan
Memperkirakan durasi waktu digunakan sesuai dengan analisis harga satuan yang digunakan pada proyek yang
ditinjau. Berikut ini beberapa contoh perhitungan durasi waktu :
1. Pekerjaan Tulangan kolom struktur lantai 1
 Volume pekerjaan = 16,40 m3 pembesian 190 kg/m3 (analisis HSP dan RAB dari proyek)
 Volume tulangan = 16,40 x 190 = 3116 kg
 Tenaga kerja = 1 regu ( 1 tbs, 2 pk)
e-Jurnal MATRIKS TEKNIK SIPIL Vol. 1 No. 4/Desember 2013/414
 Upah pekerja = Rp. 33.000,-
 Upah tukang besi = Rp. 40.000,-
 Upah tenaga kerja = Rp. 563,- per kg (analisis HSP dari proyek dan SNI)
 Upah tenaga per regu = (2x33.000)+(1x40.000) = 106.000,-
 Produktifitas tenaga kerja = 106.000/563 = 188,28kg/hari
 Produktifitas per regu = 188,28 kg/hari x 1= 188,28 kg/hari
 Durasi = 3116 / 188,28 = 17 hari
2. Pekerjaan Pasangan batu bata 1:3 Lantai 1
 Volume pekerjaan = 43,08 m2 (analisis HSP dan RAB dari proyek)
 Tenaga kerja = 1 regu ( 1 tbt, 2 pk)
 Upah pekerja = Rp. 33.000,-
 Upah tukang besi = Rp. 40.000,-
 Upah tenaga kerja = Rp. 15.100,- per m2 (analisis HSP dari proyek dan SNI)
 Upah tenaga per regu = (2x33.000)+(1x40.000) = 106.000,-
 Produktifitas tenaga kerja = 106.000/15.100 = 7,01 m2/hari
 Produktifitas per regu = 7,01 m2/hari x 1 = 7,01 m2/hari
 Durasi = 43,08 / 7,01 = 6 hari.
Tahap dan Hasil Perhitungan
A. Tahap Hitungan
1. Hitungan maju
Perhitungan maju dibawah ini menggunakan rumus 5.
Kegiatan B ( Galian Tanah Pondasi)
Kegiatan sebelumnya = kegiatan A ( Pekerjaan Persiapan )
Kegiatan sesudahnya = kegiatan F (Pondasi Batu Kali )
SPA(2-3) = SPA(2-3) + D(2-3) = 3 + 7 = 10
Berarti bahwa waktu selesai paling awal dari kegiatan B jatuh pada hari ke 10 kemudian kegiatan selanjut-
nya yaitu kegiatan F dapat dimulai paling awal pada hari berikutnya yaitu hari ke 11.
2. Hitungan mundur
Perhitungan mundur dibawah ini menggunakan rumus 6.
Kegiatan F (Pondasi Batu Kali)
Kegiatan sebelumnya = kegiatan B (Galian Tanah Pondasi )
Kegiatan sesudahnya = kegiatan H (Pekerjaan Sloof Struktur)
SPL(3-5) = SPL(3-5) – D(3-5) = 20 – 10 = 10
Perhitungan itu menjelaskan bahwa waktu mulai paling lambat kegiatan F adalah waktu selesai paling lam-
bat dari kegiatan.
B. Hasil Hitungan
1. Waktu penyelesaian proyek
Waktu penyelesaian proyek penelitian ini adalah 135 hari dimana waktu penyelesaian itu lebih cepat 15 hari
dari jangka waktu penyelesaian proyek menurut dokumen kontrak. Pada gambar diagram jaringan kerja
CPM, peristiwa akhir adalah peristiwa ke 36 yang memiliki SPA=SPL=135
2. Float
Berikut merupakan contoh hitungan untuk menentukan total float masing-masing kegiatan yang sesuai den-
gan persamaan 7. Float tersebut dihitung berdasarkan diagram jaringan kerja CPM.
Kegiatan T (Pekerjaan Plesteran 1) yang diapit oleh peristiwa awal ke 18 dan peristiwa akhir ke 20.
TF = SPLj20 – D – SPAi18 = 84 – 14 – 70 = 0
Berarti kegiatan T adalah kegiatan kritis.
3. Identifikasi jalur kritis
Jalur kritis merupakan kegiatan-kegiatan yang tidak memiliki tenggang waktu atau TF = 0 dan digambar-
kan sebagai garis tebal pada diagram jaringan kerja CPM. Dari hasil perhitungan diperoleh lintasan kritis
pada kegiatan A – B – F – H – G – K – R – Q – N – P – T – Y – AB – AK – AQ – AO – AN – AS yang
memiliki hasil perhitungan dengan nilai TF = 0.
Tahap Pembuatan Kurva S
Hasil analisis jaringan kerja CPM diaplikasikan pada bagan balok, sehingga diperoleh jadwal pelaksanaan proyek
yang memiliki limit jadwal paling awal dan paling lambat. Oleh karena itu terdapat dua kurva S yang terdapat pa-
e-Jurnal MATRIKS TEKNIK SIPIL Vol. 1 No. 4/Desember 2013/415
da gambar berimpit pada bagan balok tersebut dengan kurun waktu pelaksanaan 135 hari. Prosentase bobot dari
masing-masing kegiatan perhari diperoleh berdasarkan perbandingan antara bobot tiap-tiap kegiatan dengan hasil
pelaksanaan kegiatan. Dengan mendistribusikan sumber daya tenaga kerja pada setiap hari kegiatan yang dilaksa-
nakan, maka didapat distribusi pemakaian sumber daya tenaga kerja pergiatan perhari. Kebutuhan tenaga perhari
tersebut untuk seluruh proyek dapat diketahui dengan cara menjumlahkan pemakaian tenaga kerja oleh kegiatan
yang dilaksanakan pada hari yang sama.
Pembahasan
Dari hasil analisis jaringan kerja CPM dapat digambarkan dua kurva S untuk waktu pelaksanaan proyek 135 hari.
Secara umum dapat dijelaskan bahwa arah kurva yang menanjak berarti terdapat komulatif prosentase bobot pe-
kerjaan yang cukup tinggi. Koridor operasional yang menyempit menunjukkan kecilnya tenggang waktu (float) ke-
giatan. Demikian juga sebaliknya, float yang besar dapat menggambarkan kurva S yang memiliki koridor opera-
sional yang cukup luas. Pada waktu inilah pelaksanaan proyek memiliki kelonggaran dalam pelaksanaan proyek,
yang tentunya dibatasi oleh koridor operasional yang didasarkan pada limit jadwal kegiatan waktu tercepat dan
waktu terlambat.
Penjadwalan Proyek Pembangunan Kantor Kelurahan Kerten Kecamatan Laweyan Kota Surakarta oleh CV. Ca-
tur Tunggal berdasarkan data time schedule bahwa penyelesaian proyek memerlukan waktu 150 hari. Total biaya
proyek tersebut adalah Rp. 1.001.454.000,-. Sedangkan analisis penjadwalan dengan metode CPM, waktu penye-
lesaian proyek tersebut adalah 135 hari. Jika dibandingkan antara hasil perhitungan yang dilakukan oleh CV. Ca-
tur Tunggal dengan perhitungan menggunakan metode CPM, diperoleh hasil yang lebih menguntungkan dengan
metode CPM. Hal ini akan memberikan keuntungan dari segi waktu penyelesaian proyek yaitu akan lebih cepat
15 hari. Dengan data yang diperoleh dari CV. Catur Tunggal bahwa tenaga kerja yang akan diperkerjakan dengan
rata-rata sekitar 40 orang, maka berpengaruh terhadap penghematan biaya tenaga kerja dari biaya pembangunan
secara keseluruhan menjadi Rp. 979.239.000,- sehingga penghematan waktu terhadap biaya pembangunan yang
dapat diperoleh adalah Rp. 22.215.000,-.
SIMPULAN
Dari analisis dan pembahasan yang telah dilakukan maka dapat diambil beberapa kesimpulan sebagai berikut :
1. Hasil perhitungan dengan metode CPM membutuhkan waktu 135 hari dengan biaya Rp. 979.239.000,- se-
dangkan perhitungan yang dilakukan oleh CV. Catur Tunggal membutuhkan waktu 150 hari dengan biaya Rp.
1.001.454.000,- sehingga dapat menghemat waktu 15 hari dan biaya sebesar Rp. 22.215.000,-
2. Lintasan kritis yang diperoleh yaitu terdapat 18 kegiatan atau pekerjaan, di antaranya Pekerjaan Persiapan (A),
Pekerjaan Tanah (B), Pondasi Batu Kali (F), Pekerjaan Sloof Struktur (H), Urugan tanah kembali, mendatang-
kan & dipadatkan (G), Pengecoran Kolom Struktur 1 (K), Bekisting dan Cor Balok Latei & Kolom Praktis 1
(R), Pasangan Dinding 1 (Q), Pengecoran Balok & Plat Lantai 2 (N), Perawatan Beton & Bongkaran Bekist-
ing Balok & Plat Lantai (P), Pekerjaan Plesteran 1(T), Pengecoran Kolom Struktur 2 (Y), Pasangan Dinding 2
(AB), Pekerjaan Penutup Lantai 1 (AK), Pekerjaan Penutup Lantai 2 (AQ), Pekerjaan Doorloop (AO), Insta-
lasi Penangkal Petir (AN), Pekerjaan lain-lain (AS).
UCAPAN TERIMAKASIH
Ucapan terima kasih kepada Ir. Sugiyarto, MT. dan Ir. Siti Qomariyah, M.Sc. yang telah membimbing, memberi
arahan dan masukan dalam penelitian ini.
REFERENSI
Agus, Ahyari. 1986. Manajemen Produksi Perencanaan Sistem Produksi. Yogyakarta, BPFE.
Ali, Tubagus Heidar. 1995. Prinsip-Prinsip Network Planning. Jakarta: P.T. Gramedia Pustaka Utama.
Andri, Nugroho Aryo. 2007. Optimalisasi Penjadwalan Proyek. Pada Pembangunan Gedung Khusus (Laboratorium) Stasiun
Karantina Ikan Kelas 1 Tanjung Mas Semarang. Skripsi, Jurusan Matematika Fakultas Matematika Dan Ilmu
Pengetahuan Alam. UniversitasNegeri Semarang.
Arikunto, Suharsimi. 2000. Manajemen Penelitian. Jakarta : Rineka Cipta.
Hafis, Lep. 2012. Penjadwalan Dengan Mengunakan Jaringan Kerja PDM Dalam Upaya Pengendalian Waktu Pelaksanaan
Proyek. Skripsi, Jurusan Teknik Sipil Fakultas Teknik Universitas Sebelas Maret Surakarta. Surakarta.
Handoko TH,. 2000. Manajemen Personalia dan Sumber Daya Manusia. Edisi 2. Yogyakarta : BPFE.
Hasibuan, Malayu SP. 2002. Manajemen Sumber Daya Manusia. Jakarta : Bumi Aksara.
Ratnasari, Widya. 2005. Penjadwalan Waktu Proyek Dengan Metode CPM (Studi Kasus Proyek Pembangunan Gedung
UKM Universitas Sebelas Maret Surakarta). Surakarta : Universitas Sebelas Maret.
Reksohadiprodjo, Soekanto. 1987. Management Proyek. Yogyakarta : BPFE.
Richard L. Daft. 2002. Era Baru Manajemen. Buku 1 dan 2. Jakarta : Salemba Empat.
e-Jurnal MATRIKS TEKNIK SIPIL Vol. 1 No. 4/Desember 2013/416
Sakdiyah. 2004. Network Planning Dengan CPM Dalam Usaha Meningkatkan Efisiensi Biaya dan Waktu Pada Proyek
Pembangunan Perkantoran di PT. Nilano Malang. Malang : Universitas Muhamadiyah Malang.
Santoso, Budi. 2003. Manajemen Proyek Konsep & Implementasi. Yogyakarta : Graha Ilmu.
Soeharto, Imam. 2001. Manajemen Proyek (Dari Konseptual Sampai Operasional). Jakarta : Erlangga.
Yamit, Zulian. 2001. Manajemen Kualitas Produk & Jasa. Yogyakarta : Ekonisia.

Mais conteúdo relacionado

Mais procurados

Software Project Management - Project Management Knowledge
Software Project Management - Project Management KnowledgeSoftware Project Management - Project Management Knowledge
Software Project Management - Project Management KnowledgeDudy Ali
 
Jurnal evaluasi akselerasi pelaksanaan pembangunan proyek berdasarkan time s...
Jurnal evaluasi akselerasi pelaksanaan pembangunan proyek berdasarkan  time s...Jurnal evaluasi akselerasi pelaksanaan pembangunan proyek berdasarkan  time s...
Jurnal evaluasi akselerasi pelaksanaan pembangunan proyek berdasarkan time s...vichytekege
 
Bab 5 perencanaan proyek
Bab 5 perencanaan proyekBab 5 perencanaan proyek
Bab 5 perencanaan proyekRif'at Hm
 
Eksekusi Proyek_Materi Training 'PROJECT MANAGEMENT"
Eksekusi Proyek_Materi Training 'PROJECT MANAGEMENT"Eksekusi Proyek_Materi Training 'PROJECT MANAGEMENT"
Eksekusi Proyek_Materi Training 'PROJECT MANAGEMENT"Kanaidi ken
 
Manajemen Proyek
Manajemen ProyekManajemen Proyek
Manajemen ProyekSari Amelia
 
Bab 4 perencanaan proyek
Bab 4 perencanaan proyekBab 4 perencanaan proyek
Bab 4 perencanaan proyekRif'at Hm
 
PERENCANAAN DAN PENJADWALAN PROYEK
PERENCANAAN DAN PENJADWALAN PROYEKPERENCANAAN DAN PENJADWALAN PROYEK
PERENCANAAN DAN PENJADWALAN PROYEKAsadCungkring97
 
Aminullah assagaf mp1 manajemen proyek
Aminullah assagaf mp1 manajemen proyekAminullah assagaf mp1 manajemen proyek
Aminullah assagaf mp1 manajemen proyekAminullah Assagaf
 
Aminullah assagaf mp1 manajemen proyek
Aminullah assagaf mp1 manajemen proyekAminullah assagaf mp1 manajemen proyek
Aminullah assagaf mp1 manajemen proyekAminullah Assagaf
 
Project management office PMBOK
Project management office PMBOKProject management office PMBOK
Project management office PMBOKTelkom University
 
Materi mempercepat waktu proyek uncp palopo
Materi mempercepat waktu proyek uncp palopoMateri mempercepat waktu proyek uncp palopo
Materi mempercepat waktu proyek uncp palopoHarper's Bazaar Magazine
 
Aminullah assagaf mp1 manajemen proyek
Aminullah assagaf mp1 manajemen proyekAminullah assagaf mp1 manajemen proyek
Aminullah assagaf mp1 manajemen proyekAminullah Assagaf
 
Modul kuliah Manajemen Proyek
Modul kuliah Manajemen ProyekModul kuliah Manajemen Proyek
Modul kuliah Manajemen ProyekAMIK AL MA'SOEM
 
Modul TKP M6KB4 - Penjadwalan Proyek Konstruksi
Modul TKP M6KB4 - Penjadwalan Proyek KonstruksiModul TKP M6KB4 - Penjadwalan Proyek Konstruksi
Modul TKP M6KB4 - Penjadwalan Proyek KonstruksiPPGHybrid1
 

Mais procurados (20)

Software Project Management - Project Management Knowledge
Software Project Management - Project Management KnowledgeSoftware Project Management - Project Management Knowledge
Software Project Management - Project Management Knowledge
 
Jurnal evaluasi akselerasi pelaksanaan pembangunan proyek berdasarkan time s...
Jurnal evaluasi akselerasi pelaksanaan pembangunan proyek berdasarkan  time s...Jurnal evaluasi akselerasi pelaksanaan pembangunan proyek berdasarkan  time s...
Jurnal evaluasi akselerasi pelaksanaan pembangunan proyek berdasarkan time s...
 
Pertemuan7
Pertemuan7Pertemuan7
Pertemuan7
 
Bab 5 perencanaan proyek
Bab 5 perencanaan proyekBab 5 perencanaan proyek
Bab 5 perencanaan proyek
 
Eksekusi Proyek_Materi Training 'PROJECT MANAGEMENT"
Eksekusi Proyek_Materi Training 'PROJECT MANAGEMENT"Eksekusi Proyek_Materi Training 'PROJECT MANAGEMENT"
Eksekusi Proyek_Materi Training 'PROJECT MANAGEMENT"
 
Manajemen Proyek
Manajemen ProyekManajemen Proyek
Manajemen Proyek
 
Kurva s jasa konsultansi
Kurva s jasa konsultansiKurva s jasa konsultansi
Kurva s jasa konsultansi
 
Bab 4 perencanaan proyek
Bab 4 perencanaan proyekBab 4 perencanaan proyek
Bab 4 perencanaan proyek
 
PERENCANAAN DAN PENJADWALAN PROYEK
PERENCANAAN DAN PENJADWALAN PROYEKPERENCANAAN DAN PENJADWALAN PROYEK
PERENCANAAN DAN PENJADWALAN PROYEK
 
Aminullah assagaf mp1 manajemen proyek
Aminullah assagaf mp1 manajemen proyekAminullah assagaf mp1 manajemen proyek
Aminullah assagaf mp1 manajemen proyek
 
Aminullah assagaf mp1 manajemen proyek
Aminullah assagaf mp1 manajemen proyekAminullah assagaf mp1 manajemen proyek
Aminullah assagaf mp1 manajemen proyek
 
Project management office PMBOK
Project management office PMBOKProject management office PMBOK
Project management office PMBOK
 
Materi mempercepat waktu proyek uncp palopo
Materi mempercepat waktu proyek uncp palopoMateri mempercepat waktu proyek uncp palopo
Materi mempercepat waktu proyek uncp palopo
 
Manajemen proyek
Manajemen proyekManajemen proyek
Manajemen proyek
 
Aminullah assagaf mp1 manajemen proyek
Aminullah assagaf mp1 manajemen proyekAminullah assagaf mp1 manajemen proyek
Aminullah assagaf mp1 manajemen proyek
 
1 manajemen proyek
1 manajemen proyek1 manajemen proyek
1 manajemen proyek
 
Modul kuliah Manajemen Proyek
Modul kuliah Manajemen ProyekModul kuliah Manajemen Proyek
Modul kuliah Manajemen Proyek
 
Manajemen proyek
Manajemen proyekManajemen proyek
Manajemen proyek
 
Diktat menpro
Diktat menproDiktat menpro
Diktat menpro
 
Modul TKP M6KB4 - Penjadwalan Proyek Konstruksi
Modul TKP M6KB4 - Penjadwalan Proyek KonstruksiModul TKP M6KB4 - Penjadwalan Proyek Konstruksi
Modul TKP M6KB4 - Penjadwalan Proyek Konstruksi
 

Semelhante a 105 390-1-pb

Aminullah Assagaf_MP1_Manajemen Proyek_8 Maret 2023.pptx
Aminullah Assagaf_MP1_Manajemen Proyek_8 Maret 2023.pptxAminullah Assagaf_MP1_Manajemen Proyek_8 Maret 2023.pptx
Aminullah Assagaf_MP1_Manajemen Proyek_8 Maret 2023.pptxAminullah Assagaf
 
PPT CPM and PERT (2).pdf
PPT CPM and PERT (2).pdfPPT CPM and PERT (2).pdf
PPT CPM and PERT (2).pdfParkHyunji3
 
Aminullah assagaf mp1 manajemen proyek_9 maret 2022
Aminullah assagaf mp1 manajemen proyek_9 maret 2022Aminullah assagaf mp1 manajemen proyek_9 maret 2022
Aminullah assagaf mp1 manajemen proyek_9 maret 2022Aminullah Assagaf
 
16393 39865-1-sm
16393 39865-1-sm16393 39865-1-sm
16393 39865-1-smlanfti015
 
Aminullah Assagaf_MP1_Manajemen Proyek.pptx
Aminullah Assagaf_MP1_Manajemen Proyek.pptxAminullah Assagaf_MP1_Manajemen Proyek.pptx
Aminullah Assagaf_MP1_Manajemen Proyek.pptxAminullah Assagaf
 
Revisi ppt uts 2
Revisi ppt uts 2Revisi ppt uts 2
Revisi ppt uts 2LegendSello
 
Pengendalian Proyek _Materi Training "PROJECT MANAGEMENT"
Pengendalian Proyek _Materi Training "PROJECT MANAGEMENT"Pengendalian Proyek _Materi Training "PROJECT MANAGEMENT"
Pengendalian Proyek _Materi Training "PROJECT MANAGEMENT"Kanaidi ken
 
2463-6747-1-PB.pdf
2463-6747-1-PB.pdf2463-6747-1-PB.pdf
2463-6747-1-PB.pdfSuryoNegoro3
 
Manajemen proyek Diklat Jembatan OK.pptx
Manajemen proyek Diklat Jembatan OK.pptxManajemen proyek Diklat Jembatan OK.pptx
Manajemen proyek Diklat Jembatan OK.pptxBinamarga18
 
Tnd - Pengantar Manajemen Proyek Sistem Informasi - Temu 2
Tnd - Pengantar Manajemen Proyek Sistem Informasi - Temu 2Tnd - Pengantar Manajemen Proyek Sistem Informasi - Temu 2
Tnd - Pengantar Manajemen Proyek Sistem Informasi - Temu 2Tino Dwiantoro
 
Aplikasi matriks dalam teknik sipil
Aplikasi matriks dalam teknik sipilAplikasi matriks dalam teknik sipil
Aplikasi matriks dalam teknik sipilbudiMekka
 
Ppt uts rodi ardiansyah
Ppt uts rodi ardiansyahPpt uts rodi ardiansyah
Ppt uts rodi ardiansyahLegendSello
 
Metode PERT & CPM.pptx
Metode PERT & CPM.pptxMetode PERT & CPM.pptx
Metode PERT & CPM.pptxfalmanfarez
 
Metode PERT & CPM.pptx
Metode PERT & CPM.pptxMetode PERT & CPM.pptx
Metode PERT & CPM.pptxfalmanfarez
 
PENJADWALAN_PROYEK-materi13.pptx
PENJADWALAN_PROYEK-materi13.pptxPENJADWALAN_PROYEK-materi13.pptx
PENJADWALAN_PROYEK-materi13.pptxMargarethaYohanna
 

Semelhante a 105 390-1-pb (20)

Aminullah Assagaf_MP1_Manajemen Proyek_8 Maret 2023.pptx
Aminullah Assagaf_MP1_Manajemen Proyek_8 Maret 2023.pptxAminullah Assagaf_MP1_Manajemen Proyek_8 Maret 2023.pptx
Aminullah Assagaf_MP1_Manajemen Proyek_8 Maret 2023.pptx
 
PPT CPM and PERT (2).pdf
PPT CPM and PERT (2).pdfPPT CPM and PERT (2).pdf
PPT CPM and PERT (2).pdf
 
Aminullah assagaf mp1 manajemen proyek_9 maret 2022
Aminullah assagaf mp1 manajemen proyek_9 maret 2022Aminullah assagaf mp1 manajemen proyek_9 maret 2022
Aminullah assagaf mp1 manajemen proyek_9 maret 2022
 
16393 39865-1-sm
16393 39865-1-sm16393 39865-1-sm
16393 39865-1-sm
 
Aminullah Assagaf_MP1_Manajemen Proyek.pptx
Aminullah Assagaf_MP1_Manajemen Proyek.pptxAminullah Assagaf_MP1_Manajemen Proyek.pptx
Aminullah Assagaf_MP1_Manajemen Proyek.pptx
 
Pertemuan 2 Manajemen Proyek.pptx
Pertemuan 2 Manajemen Proyek.pptxPertemuan 2 Manajemen Proyek.pptx
Pertemuan 2 Manajemen Proyek.pptx
 
Revisi ppt uts 2
Revisi ppt uts 2Revisi ppt uts 2
Revisi ppt uts 2
 
Pengendalian Proyek _Materi Training "PROJECT MANAGEMENT"
Pengendalian Proyek _Materi Training "PROJECT MANAGEMENT"Pengendalian Proyek _Materi Training "PROJECT MANAGEMENT"
Pengendalian Proyek _Materi Training "PROJECT MANAGEMENT"
 
2463-6747-1-PB.pdf
2463-6747-1-PB.pdf2463-6747-1-PB.pdf
2463-6747-1-PB.pdf
 
Manajemen proyek Diklat Jembatan OK.pptx
Manajemen proyek Diklat Jembatan OK.pptxManajemen proyek Diklat Jembatan OK.pptx
Manajemen proyek Diklat Jembatan OK.pptx
 
all ABPUT CPM.pdf
all ABPUT CPM.pdfall ABPUT CPM.pdf
all ABPUT CPM.pdf
 
Manajemen proyek
Manajemen proyekManajemen proyek
Manajemen proyek
 
Manajemen Proyek
Manajemen ProyekManajemen Proyek
Manajemen Proyek
 
Tnd - Pengantar Manajemen Proyek Sistem Informasi - Temu 2
Tnd - Pengantar Manajemen Proyek Sistem Informasi - Temu 2Tnd - Pengantar Manajemen Proyek Sistem Informasi - Temu 2
Tnd - Pengantar Manajemen Proyek Sistem Informasi - Temu 2
 
Aplikasi matriks dalam teknik sipil
Aplikasi matriks dalam teknik sipilAplikasi matriks dalam teknik sipil
Aplikasi matriks dalam teknik sipil
 
Revisi ppt uts
Revisi ppt utsRevisi ppt uts
Revisi ppt uts
 
Ppt uts rodi ardiansyah
Ppt uts rodi ardiansyahPpt uts rodi ardiansyah
Ppt uts rodi ardiansyah
 
Metode PERT & CPM.pptx
Metode PERT & CPM.pptxMetode PERT & CPM.pptx
Metode PERT & CPM.pptx
 
Metode PERT & CPM.pptx
Metode PERT & CPM.pptxMetode PERT & CPM.pptx
Metode PERT & CPM.pptx
 
PENJADWALAN_PROYEK-materi13.pptx
PENJADWALAN_PROYEK-materi13.pptxPENJADWALAN_PROYEK-materi13.pptx
PENJADWALAN_PROYEK-materi13.pptx
 

Último

Normalisasi Database dan pengertian database
Normalisasi Database dan pengertian databaseNormalisasi Database dan pengertian database
Normalisasi Database dan pengertian databasethinkplusx1
 
Klasifikasi jenis pompa berdasarkan cara kerjanya
Klasifikasi jenis pompa berdasarkan cara kerjanyaKlasifikasi jenis pompa berdasarkan cara kerjanya
Klasifikasi jenis pompa berdasarkan cara kerjanyafaizalabdillah10
 
Minggu 5 Pepistimlogy berbasis wawasan politik_Ekonomi.pptx
Minggu 5 Pepistimlogy berbasis wawasan politik_Ekonomi.pptxMinggu 5 Pepistimlogy berbasis wawasan politik_Ekonomi.pptx
Minggu 5 Pepistimlogy berbasis wawasan politik_Ekonomi.pptxRahmiAulia20
 
Teori Pembakaran bahan kimia organik .ppt
Teori Pembakaran bahan kimia organik .pptTeori Pembakaran bahan kimia organik .ppt
Teori Pembakaran bahan kimia organik .pptEndarto Yudo
 
PPT Manajemen Konstruksi Unsur Unsur Proyek 1.pptx
PPT Manajemen Konstruksi Unsur Unsur Proyek 1.pptxPPT Manajemen Konstruksi Unsur Unsur Proyek 1.pptx
PPT Manajemen Konstruksi Unsur Unsur Proyek 1.pptxHamidNurMukhlis
 
Thermodynamics analysis of energy, entropy and exergy
Thermodynamics analysis of energy, entropy and exergyThermodynamics analysis of energy, entropy and exergy
Thermodynamics analysis of energy, entropy and exergyEndarto Yudo
 
Analisis Struktur Statis Tak Tentu dengan Force Method.pdf
Analisis Struktur Statis Tak Tentu dengan Force Method.pdfAnalisis Struktur Statis Tak Tentu dengan Force Method.pdf
Analisis Struktur Statis Tak Tentu dengan Force Method.pdfAgusTriyono78
 
PPT PPT Pelaksana lapangan Pekerasan Jalan Beton lvl 6.pptx
PPT PPT Pelaksana lapangan Pekerasan Jalan Beton lvl 6.pptxPPT PPT Pelaksana lapangan Pekerasan Jalan Beton lvl 6.pptx
PPT PPT Pelaksana lapangan Pekerasan Jalan Beton lvl 6.pptxdpcaskonasoki
 
MATERI PRESENTASI KEPALA TEKNIK TAMBANG KEPMEN 555
MATERI PRESENTASI KEPALA TEKNIK TAMBANG KEPMEN 555MATERI PRESENTASI KEPALA TEKNIK TAMBANG KEPMEN 555
MATERI PRESENTASI KEPALA TEKNIK TAMBANG KEPMEN 555zannialzur
 
MEKANIKA TEKNIK TEKNIK PERTAMBANGAN FAK. TEKNIK
MEKANIKA TEKNIK TEKNIK PERTAMBANGAN FAK. TEKNIKMEKANIKA TEKNIK TEKNIK PERTAMBANGAN FAK. TEKNIK
MEKANIKA TEKNIK TEKNIK PERTAMBANGAN FAK. TEKNIKFerdinandus9
 
QCC MANAJEMEN TOOL MAINTENANCE (MAINTENANCE TEAM).pptx
QCC MANAJEMEN TOOL MAINTENANCE (MAINTENANCE TEAM).pptxQCC MANAJEMEN TOOL MAINTENANCE (MAINTENANCE TEAM).pptx
QCC MANAJEMEN TOOL MAINTENANCE (MAINTENANCE TEAM).pptxdjam11
 

Último (11)

Normalisasi Database dan pengertian database
Normalisasi Database dan pengertian databaseNormalisasi Database dan pengertian database
Normalisasi Database dan pengertian database
 
Klasifikasi jenis pompa berdasarkan cara kerjanya
Klasifikasi jenis pompa berdasarkan cara kerjanyaKlasifikasi jenis pompa berdasarkan cara kerjanya
Klasifikasi jenis pompa berdasarkan cara kerjanya
 
Minggu 5 Pepistimlogy berbasis wawasan politik_Ekonomi.pptx
Minggu 5 Pepistimlogy berbasis wawasan politik_Ekonomi.pptxMinggu 5 Pepistimlogy berbasis wawasan politik_Ekonomi.pptx
Minggu 5 Pepistimlogy berbasis wawasan politik_Ekonomi.pptx
 
Teori Pembakaran bahan kimia organik .ppt
Teori Pembakaran bahan kimia organik .pptTeori Pembakaran bahan kimia organik .ppt
Teori Pembakaran bahan kimia organik .ppt
 
PPT Manajemen Konstruksi Unsur Unsur Proyek 1.pptx
PPT Manajemen Konstruksi Unsur Unsur Proyek 1.pptxPPT Manajemen Konstruksi Unsur Unsur Proyek 1.pptx
PPT Manajemen Konstruksi Unsur Unsur Proyek 1.pptx
 
Thermodynamics analysis of energy, entropy and exergy
Thermodynamics analysis of energy, entropy and exergyThermodynamics analysis of energy, entropy and exergy
Thermodynamics analysis of energy, entropy and exergy
 
Analisis Struktur Statis Tak Tentu dengan Force Method.pdf
Analisis Struktur Statis Tak Tentu dengan Force Method.pdfAnalisis Struktur Statis Tak Tentu dengan Force Method.pdf
Analisis Struktur Statis Tak Tentu dengan Force Method.pdf
 
PPT PPT Pelaksana lapangan Pekerasan Jalan Beton lvl 6.pptx
PPT PPT Pelaksana lapangan Pekerasan Jalan Beton lvl 6.pptxPPT PPT Pelaksana lapangan Pekerasan Jalan Beton lvl 6.pptx
PPT PPT Pelaksana lapangan Pekerasan Jalan Beton lvl 6.pptx
 
MATERI PRESENTASI KEPALA TEKNIK TAMBANG KEPMEN 555
MATERI PRESENTASI KEPALA TEKNIK TAMBANG KEPMEN 555MATERI PRESENTASI KEPALA TEKNIK TAMBANG KEPMEN 555
MATERI PRESENTASI KEPALA TEKNIK TAMBANG KEPMEN 555
 
MEKANIKA TEKNIK TEKNIK PERTAMBANGAN FAK. TEKNIK
MEKANIKA TEKNIK TEKNIK PERTAMBANGAN FAK. TEKNIKMEKANIKA TEKNIK TEKNIK PERTAMBANGAN FAK. TEKNIK
MEKANIKA TEKNIK TEKNIK PERTAMBANGAN FAK. TEKNIK
 
QCC MANAJEMEN TOOL MAINTENANCE (MAINTENANCE TEAM).pptx
QCC MANAJEMEN TOOL MAINTENANCE (MAINTENANCE TEAM).pptxQCC MANAJEMEN TOOL MAINTENANCE (MAINTENANCE TEAM).pptx
QCC MANAJEMEN TOOL MAINTENANCE (MAINTENANCE TEAM).pptx
 

105 390-1-pb

  • 1. ISSN 2354-8630 e-Jurnal MATRIKS TEKNIK SIPIL Vol. 1 No. 4/Desember 2013/408 ANALISIS NETWORK PLANNING DENGAN CPM (CRITICAL PATH METHOD) DALAM RANGKA EFISIENSI WAKTU DAN BIAYA PROYEK Sugiyarto1), Siti Qomariyah2), Faizal Hamzah3) 1),2) Pengajar, Fakultas Teknik, Jurusan Teknik Sipil, Universitas Sebelas Maret 3) Mahasiswa, Fakultas Teknik, Jurusan Teknik Sipil, Universitas Sebelas Maret Jln Ir. Sutami 36A, Surakarta 57126 Telp: 0271-634524. Email : xsmile_adefh@yahoo.com Abstract CPM (Critical Path Method) is one of network planning methods are oriented at the time that led to the determination of project scheduling and time estimation are diterministik / definite. Research objectives with this method is to determine the time and cost of the project and to find out what activities are included in the critical activities. In addition, to control and coordinate the various activities in a project so that the work can be completed in a timely manner and can also help the company in organizing the planning and control of project time and cost efficient. With the use of the CPM method produces a critical path with 18 activities and two S curves is to schedule the earliest and at the latest. The calculation of the CPM method takes 135 days at a cost of Rp. 979.239.000, - while the calculations performed by CV. Catur Tunggal takes 150 days at a cost of Rp. 1.001.454.000,-. Based on CPM method saves time project completion 15 days (10%) and cost of Rp. 22.215.000,-. Keywords: Project Management, Network Analysis, CPM, Critical Path, Time and Cost Efficiency Project, Curve S. Abstrak CPM (Critical Path Method) adalah salah satu metode network planning yang berorientasi pada waktu yang mengarah pada pe- nentuan penjadwalan proyek dan estimasi waktunya bersifat diterministik/pasti. Tujuan penelitian dengan metode ini adalah untuk menentukan waktu dan biaya proyek serta mengetahui kegiatan apa saja yang termasuk dalam kegiatan kritis. Selain itu juga untuk mengontrol dan mengkoordinasi berbagai kegiatan sehingga proyek dapat diselesaikan dalam jangka waktu yang tepat dan juga dapat membantu perusahaan dalam mengadakan perencanaan dan pengendalian proyek dengan waktu dan bi- aya yang lebih efisien. Dengan penggunaan metode CPM ini menghasilkan satu jalur kritis dengan 18 kegiatan dan dua kurva S yaitu untuk jadwal kegiatan paling awal dan paling lambat. Hasil perhitungan dengan metode CPM membutuhkan waktu 135 hari dengan biaya Rp. 979.239.000,- sedangkan perhitungan yang dilakukan oleh CV. Catur Tunggal membutuhkan wak- tu 150 hari dengan biaya Rp. 1.001.454.000,-. Berdasarkan metode CPM menghemat waktu penyelesaian proyek 15 hari (10%) dan biaya sebesar Rp. 22.215.000,-. Kata Kunci: Manajemen Proyek, Analisa Network, CPM, Jalur Kritis, Efisiensi Waktu dan Biaya Proyek, Kurva S. PENDAHULUAN Banyaknya perusahaan kontraktor yang berdiri dan bermunculan mengakibatkan persaingan antar perusahaan un- tuk mendapatkan proyek semakin terasa sehingga mendorong setiap perusahaan untuk dapat lebih meningkatkan potensi sumberdaya yang mereka miliki. Salah satu hal dalam persaingan tersebut adalah bersaing dalam segi wak- tu dan biaya produksi. Dalam hal waktu dan biaya produksi, perusahaan harus bisa seefisien mungkin dalam penggunaan waktu pada setiap kegiatan atau aktivitas, sehingga biaya dapat diminimalkan dari rencana anggaran biaya semula. Perencanaan kegiatan proyek merupakan masalah yang sangat penting karena perencanaan kegiatan merupakan dasar untuk proyek bisa berjalan dan agar proyek yang dilaksanakan dapat selesai dengan waktu yang optimal dan efisien. Pada pembangunan sebuah gedung atau yang lainya perlu adanya penanganan manajemen penjadwalan kerja yang baik, karena itu perlu adanya perhitungan yang cermat dan teliti. Suatu proyek dikatakan baik jika penyele- saian proyek tersebut efisien dari segi waktu dan biaya serta mempertinggi efisiensi kerja baik sumber daya manu- sia maupun alat (Badri, 1997:14). Dalam rangka menentukan waktu dan biaya pelaksanaan proyek, maka diperlukan adanya suatu alternatif pemecahan masalah waktu dan biaya terhadap penjadwalan pelaksanaan proyek yang dimaksudkan untuk mengoptimalisasikan jangka waktu penyelesaian proyek dan meminimalkan total biaya proyek. Salah satu alternatifnya yaitu analisis network planning dengan metode CPM (Critical Path Method). Metode ini dapat dipakai untuk mengontrol dan mengkoordinasi berbagai kegiatan dalam suatu pekerjaan se- hingga proyek dapat diselesaikan dalam jangka waktu yang tepat dan juga dapat membantu perusahaan dalam mengadakan perencanaan dan pengendalian proyek dengan waktu dan biaya yang lebih efisien. Dari penelitian analisis network planning dengan metode CPM ini diharapkan pada perencanaan penjadwalan pelaksanaan proyek dapat memperoleh waktu dan biaya pelaksanaan proyek yang lebih efisien. TINJAUAN PUSTAKA Manajemen merupakan ilmu dan seni mengatur proses pemanfaatan sumber daya manusia dan sumber-sumber lainnya secara efektif dan efisien untuk mencapai satu tujuan. (Mulayu S.P. Hasibuan, 2000:2).
  • 2. e-Jurnal MATRIKS TEKNIK SIPIL Vol. 1 No. 4/Desember 2013/409 Proyek adalah setiap pekerjaan yang memiliki kegiatan awal dan memiliki kegiatan akhir, dengan kata lain setiap pekerjaan yang dimulai pada waktu tertentu dan direncanakan selesai atau berakhir pada waktu yang telah ditetapkan. (Yamit; 2000:296). Manajemen proyek adalah kegiatan merencanakan, mengorganisasikan, mengarahkan dan mengendalikan sumber daya organisasi perusahaan untuk mencapai tujuan tertentu dalam waktu tertentu dengan sumber daya tertentu. (Budi santoso; 2003:3) Dalam proses untuk mencapai tujuan proyek terdapat batasan yang harus dipenuhi biaya atau anggaran, waktu atau jadwal, serta kualitas atau mutu. Tiga hal tersebut merupakan parameter penting dalam penyelengaraan suatu proyek dan sering disebut juga triple constrain. Triple constrain tersebut yaitu: 1. Biaya atau anggaran Suatu proyek harus diselesaikan dengan biaya yang tidak boleh melebihi anggaran. Proyek berskala besar dan proses pelaksanaannya bertahun-tahun, biayanya tidak hanya ditentukan dalam total proyek, akan tetapi terba- gi atas bagian-bagian atau periode tertentu yang jumlahnya disesuaikan dengan keperluan. Dengan demikian penyelesaian bagian-bagian proyek harus memenuhi sasaran anggaran perperiode. 2. Waktu atau jadwal Proyek harus dikerjakan sesuai dengan kurun waktu yang telah ditentukan dan penyerahannya tidak boleh me- lewati batas waktu yang telah ditentukan. 3. Kualitas atau mutu Hasil kegiatan atau produk harus memenuhi spesifikasi dan kriteria mutu yang telah dipersyaratkan. Biaya Waktu Mutu Gambar 1. Hubungan triple constrain (Iman Soeharto, 1997:3) Tiga batasan tersebut diatas bersifat saling bersangkutan dan saling tarik-menarik. Jika ingin meningkatkan kinerja produk yang telah ditentukan, maka secara umumnya harus diikuti dengan meningkatkan mutu. Hal ini selanjut- nya berakibat pada naiknya biaya sehingga melebihi anggaran. Sebaliknya jika ingin menekan atau memperkecil biaya, maka biasanya harus memperhatikan jadwal atau waktu dan mutu juga. Jaringan kerja (Network Planning) Jaringan kerja merupakan salah satu metode yang menjelaskan hubungan antara kegiatan dan waktu yang secara grafis mencerminkan urutan rencana kegiatan atau pekerjaan proyek. (Imam Soeharto; 1990:63). Jaringan kerja pada dasarnya adalah hubungan ketergantungan antara bagian pekerjaan yang digambarkan atau divisualisasikan dalam diagram network. Dengan demikian dapat diketahui pada area mana pekerjaan yang termasuk kedalam lin- tasan kritis dan harus diutamakan pelaksanaanya, pekerjaan mana yang menunggu selesainya pekerjaan yang lain, pekerjaan mana yang tidak perlu tergesa-gesa sehingga alat dan orang digeser ketempat lain demi efisiensi. CPM (Critical Path Method) CPM adalah metode yang berorientasi pada waktu yang mengarah pada penentuan jadwal dan estimasi waktunya bersifat diterministik/pasti. Menurut Srivastava (1995:663). Jalur Kritis Jalur kritis itu sendiri merupakan jalur yang memiliki waktu terpanjang dari semua jalur yang dimulai dari peristi- wa awal hingga peristiwa yang terakhir. .(Yamit; 2000:301). Kegunaan jalur kritis tersebut untuk mengetahui ke- giatan yang memiliki kepekaan sangat tinggi atas keterlambatan penyelesaian pekerjaan, atau disebut juga kegiatan kritis. Apabila kegiatan keterlambatan proyek maka akan memperlambat penyelesaian proyek secara keseluruhan meskipun kegiatan lain tidak mengalami keterlambatan.(Yamit; 2000:301). Dengan demikian waktu yang diperlu- kan untuk penyelesaian jalur kritis adalah sama dengan waktu untuk menyelesaikan proyek secara keseluruhan. Waktu longgar merupakan jumlah waktu kegiatan tertentu dapat ditunda, tanpa menunda keseluruhan proyek. Bila waktu longgar nol maka kegiatan yang berada disepanjang jalur waktu longgar nol tersebut adalah kegiatan kritis dan jalurnya disebut jalur kritis. Efisiensi Waktu dan Biaya Efisiensi adalah tingkat kehematan dalam menggunakan sumber daya yang ada dalam rangka mencapai tujuan yang diinginkan. Efisiensi terbagi menjadi dua, yaitu efisiensi waktu dan efisiensi biaya. Efisiensi waktu adalah tingkat kehematan dalam hal waktu saat pelaksanaan hingga kapan proyek itu selesai. Sedangkan efisiensi biaya
  • 3. e-Jurnal MATRIKS TEKNIK SIPIL Vol. 1 No. 4/Desember 2013/410 adalah tingkat kehematan dan pengorbanan ekonomi yang dilakukan untuk mencapai tujuan yang telah dite- tapkan. (Muchdoro, 1997:180). Diagram Network Variabel kegiatan dalam membuat diagram network adalah kurun waktu, tanggal mulai dan tanggal berakhir. Bila kegiatan tersebut dijumlahkan kembali akan menjadi lingkup proyek keseluruhan. a. Peristiwa atau kejadian dan milestone, adalah suatu titik waktu dimana semua kegiatan sebelumnya sudah selesai dan kegiatan sesudah itu dapat dimulai. Peristiwa dalam proyek adalah titik awal dimulainya proyek dan peris- tiwa akhir adalah titik dimana proyek selesai. Salah satu peristiwa atau event yang penting dinamakan tonggak kemajuan atau milestone. b. Node i dan nide j yang berada diekor anak panah adalah node i, sedngkan yang dikepala adalah node j. Tetapi node j akan menjadi node i untuk kegiatan berikutnya. c. Kecuali kegiatan awal maka sebelum suatu kegiatan dapat dimulai, kegiatan terdahulu harus sudah selesai. d. Dummy merupakan anak panah yang hanya menjelaskan hubungan ketergantungan antara dua kegiatan, tidak memerlukan sumber daya dan tidak membutuhkan waktu. e. Penyajian grafis jaringan kerja tidak membutuhkan skala, kecuali untuk keperluan tertentu. SPAi SPLi i SPAj SPLj j Kegiatan i-j L Gambar 2 Hubungan Kegiatan Keterangan : I : nomor dari lingkaran kegiatan yang merupakan per- mulaan dari kegiatan yang ditinjau. J : nomor dari libgkaran kejadian yang merupakan ujung akhir dari kegiatan yang ditinjau. Untuk menyusun network planning digunakan tanda atau simbol sebagai berikut: 1. Anak panah (arrow) Adalah lambang aktifitas atau kegiatan. Anak panah menggambarkan keterkaitan antar kegiatan proyek atau urutan kegiatan yang harus diselesaikan. Kegiatan ini memerlukan jangka waktu tertentu dengan mengguna- kan sumber daya. 2. Lingkaran kecil (node) Menyatakan suatu kegiatan, peristiwa atau event. Kejadian didefinisikan sebagai ujung atau pertemuan dari satu atau lebih kegiatan. 3. Anak panah sejajar (double arrow) Merupakan yang menunjunkan kegiatan dilintasan keritis. 4. Anak panah terputus-putus (dummy) Menunjukan kaitan antara dua kegiatan yang satu harus menunggu selesainya satu kegiatan lain/kegiatan se- mu. Dummy berfungsi untuk membatasi mulainya kegiatan. Dummy tidak mempunyai durasi karena tidak me- makai atau menghabiskan sumber daya. Hubungan Antar Simbol dan Urutan Kegiatan Dalam proses perhitungan dengan metode CPM dikenal adanya beberapa parameter sebagai berikut: a. SPA (Saat Paling Awal) : Saat paling cepat atau paling awal peristiwa/node/event mungkin terjadi, yang berar- ti waktu paling cepat suatu kegiatan yang berasal dari node tersebut dapat dimulai karena menurut aturan da- sar suatu kegiatan baru dapat dimulai bila kegiatan-kegiatan terdahulu selesai. b. SPAi : Saat paling cepat peristiwa yang mungkin terjadi, maksunya waktu mulai paling awal suatu kegiatan. Bi- la waktu kegiatan dinyatakan dalam hari, maka waktu ini merupakan hari pertama kegiatan dimulai. c. SPAj : Saat paling cepat peristiwa terakhir mungkin terjadi, berarti waktu selesai paling awal suatu kegiatan. Bi- la hanya ada satu kegiatan terdahulu, maka SPAj kegiatan terdahulunya merupakan SPAi kegiatan berikutnya. Untuk sebuah kegiatan menuju ke sebuah peristiwa SPAi i SPAj j X L Rumus : SPAj=SPAi+L (1) Keterangan : X = Kegiatan j = Peristiwa akhir kegiatan X i = Peristiwa awal kegiatan X L = Lama kegiatan X yang diperkirakan SPAi = Saat paling awal peristiwa awal
  • 4. e-Jurnal MATRIKS TEKNIK SIPIL Vol. 1 No. 4/Desember 2013/411 SPAj = Saat paling awal peristiwa akhir Untuk sebuah kegiatan menuju ke sebuah peristiwa L2 X1 SPAi1 i1 SPAi2 i2 SPAj j L1 X2 Rumus : SPAj = (SPAin + Ln) maksimum (2) Keterangan : n = Nomor kegiatan (n = 1,2,3…….z) Xn = Nma kegiatan ke – n J = Peristiwa akhir bersama dari semua kegiatan Xn in = Peristiwa awal kegiatan Xn SPAin = Saat paling awal peristiwa awal dari kegiatan Xn Ln = Lama kegistan Xn yang diperkirakan SPAj =Saat paling awal peristiwa akhir seluruh kegiatan. SPL (Saat Paling Lambat) : Saat paling lambat suatu peristiwa boleh terjadi, berarti waktu paling lambat yang ma- sih diperbolehkan bagi suatu peristiwa terjadi. a. SPLi : Saat paling lambat peristiwa awal boleh terjadi atau waktu paling akhir kegiatan boleh dimulai, yaitu waktu paling akhir kegiatan boleh dimulai tanpa memperlambat proyek secara keseluruhan. b. SPLj : Saat paling lambat peristiwa akhir boleh terjadi, berarti waktu paling akhir kegiatan boleh selesai tanpa memperlambat penyelesaian proyek. Untuk sebuah kegiatan keluar dari sebuah peristiwa i j SPLi SPLj X L Rumus : SPLi = SPLj – L (3) Keterangan: X = Kegiatan j = Peristiwa akhir kegiatan X i = Peristiwa awal kegiatan X L = Lama kegiatan X yang diperkirakan SPLi = Saat paling lambat peristiwa awal SPLj = Saat paling lambat peristiwa akhir. Untuk beberapa kegiatan keluar dari sebuah peristiwa L2 X1 SPLi i SPLj1 j1 SPLj2 j2 L1 X2 Rumus : SPLi = (SPLjn - Ln) minimum (4) Keterangan: n = Nomor kegiatan (n = 1,2,3…….z) Xn = Nama kegiatan ke – n i = Peristiwa awal bersama dari semua kegiatan n jn = Peristiwa akhir masin-masing kegiatan n SPLjn = Saat paling lambat peristiwa akhir kegiatan Xn Ln = Lama kegistan Xn yang diperkirakan SPLi = Saat paling lambat peristiwa awal kegiatan Jalur Kritis Peristiwa kritis adalah peristiwa yang tidak mempunyai tenggang waktu SPA-nya sama dengan SPL-nya. Sedang- kan kegiatan kritis adalah kegiatan yang sangat sensitive terhadap keterlambatan, sehingga bila sebuah kegiatan kritis terlambat satu hari saja, sedang kegiatan lainnya tidak, maka proyek akan mengalami keterlambatan selama satu hari. Sifat kritis ini disebabkan karena kegiatan tersebut harus dimulai dan harus selesai pada satu saat. Ke- simpulannya berarti : SPAi = SPLi SPLj = SPLj Karena harus dimulai pada suatu saat awal saja dan selesai suatu saat akhir saja dan tidak ada alternative saat lain- nya, maka : SPAi + L = SPAj SPLi + L = SPLj Keterangan: L = Lama kegiatan kritis SPAi = SPA peristiwa awal SPAj = SPA peristiwa akhir SPLi = SPL peristiwa awal SPLj = SPL peristiwa akhir Lintasan kritis adalah lintasan yang terdiri dari kegiatan-kegiatan kritis, peristiwa-peristiwa kritis, dan dummy. Tu- juan mengetahui lintasan kritis adalah untuk mengetahui dengan cepat kegiatan dan peristiwa yang tingkat kepe- kaannya paling tinggi terhadap keterlambatan pelaksanaan, sehingga setiap saat dapat ditentukan tingkat prioritas kebijaksanaan proyek, yaitu terhadap kegiatan kritis dan hampir kritis. Dalam mengidentifikasikan jalur keritis perhitungan waktu pada suatu jaringan kerja dapat dilakukan melalui dua cara, yaitu : a. Perhitungan maju Hitungan maju adalah cara perhitungan waktu mulai dari selesai suatu kegiatan dalam rangkaian jaringan kerja hanya mempergunakan SPAi, SPAj, dan L. Aturan dalam hitungan maju  Kecuali kegiatan awal, maka suatu kegiatan baru dapat dimulai bila kegiatan yang mendahuluinya telah se- lesai. Rumus : SPAj = SPAi + L (5)
  • 5. e-Jurnal MATRIKS TEKNIK SIPIL Vol. 1 No. 4/Desember 2013/412  Bila suatu kegiatan memiliki dua atau lebih kegiatan menggabung, maka SPCi kegiatan tersebut adalah SPCj yang terbesar dari kegiatan terdahulu. b. Perhitungan mundur Perhitungan mundur dimaksudkan untuk mengetahui waktu paling akhir kegiatan masih dapat dimulai dan mengakhiri masing-masing kegiatan. Hitungan mundur dimulai dari ujung kanan suatu jaringan kerja atau waktu akhir penyelesaian proyek. Aturan dalam hitungan mundur  Bila hanya ada satu kegiatan yang keluar dari peristiwa, maka waktu paling kahir dari kegiatan tersebut sa- ma dengan waktu selesai paling akhir dikurangi dengan kurun waktu kegiatanya Rumus : SPLi = SPLj – L (6)  Bila suatu kegiatan memiliki dua atau lebih yang mengikuti, maka SPLj kegiatan tersebut adalah sama den- gan SPLi kegiatan berikutnya yang terkecil. Tenggang Waktu Kegiatan Tenggang waktu kegiatan adalah jangka waktu yang merupakan ukuran batas toleransi keterlambatan kegiatan. Dengan ukuran ini dapat diketahui karakteristik pengaruh keterlambatan terhadap penyelenggaraan proyek dan terhadap pola kebutuhan sumber daya dan biaya. a. Syarat menghitung tenggang waktu kegiatan adalah:  Telah ada network diagram yang tepat yaitu terdiri dari kegiatan, peristiwa, dan dummy (bila diperlukan) yang jumlahnya tepat, hubungan logika antar kegiatan memenuhi persyaratan, dan nomor-nomor peristi- wanya memeuhi persyaratan.  Lama kegiatan perkiraan masing-masing telah ditentukan.  Telah dihitung SPA dan SPL semua peristiwa. b. Float Float merupakan sejumlah waku yang tersedia dalam suatu kegiatan, sehingga memungkinkan penundaan atau perlambatan kegiatan secara sengaja/tidak sengaja, tetapi penundaan tersebut tidak menyebabkan proyek menjadi terlambat dalam penyelesainnya. Ada tiga macam bentuk tenggang waktu kegiatan yaitu :  Total Float (TF) : Pada penyusunan dan perencanaan jadwal proyek, arti penting dari total float adalah menunjukan jumlah waktu yang diperkenankan suatu kegiatan boleh ditunda tanpa mempengaruhi jadwal proyek secara keseluruhan. Rumus : TF = SPLj - L – SPAi (7)  Free Float (FF) : adalah jangka waktu antara saat paling awal peristiwa akhir (SPAj) kegiatan yang bersang- kutan dengan saat selesainya kegiatan yang bersangkutan, bila kegiatan tersebut dimulai pada saat paling awal (SPAi). Rumus : FF = SPAj - L – SPAi (8)  Independent Float (IF) : adalah jangka waktu antara saat paling awal peristiwa akhir (SPAj) kegiatan yang bersangkutan dengan saat selesainya kegiatan tersebut, bila kegiatan tersebut dimulai pada saat paling lam- bat peristiwa awal (SPLi)nya Rumus : IF = SPAj – L – SPLi (9) c. Limit jadwal kegiatan  Keadaan jadwal paling awal Merupakan keadaan pada saat pelaksanaan kegiatan dimulai dan diselesaikan seawal mungkin. Ini berarti bahwa kegiatan tersebut tidak mungkin dilaksanakan sebelum saat paling awal kegiatan yang bersangkutan. Keadaan ini selanjutnya disebut jadwal tipe I dan disebut juga hari mulai satu (HM1), dan hari penyelesaian kegiatan tersebut adalah hari selesai satu (HS1). Rumus : HM1 = SPA1+1 (10) HS1= SPA1+L (11)  Keadaan jadwal paling lambat Merupakan keadaan pada saat pelaksanaan kegiatan dimulai dan diselesaikan selambat mungkin. Oleh ka- rena itu kegiatan tersebut tidak boleh berlangsung melebihi saat paling lambatnya, agar proyek tidak men- galami keterlambatan. Hari mulai jadwal tipe II disebut hari mulai dua (HM2) dan hari penyelesaian dis- ebut hari penyelesaian dua (HS2). Rumus : HM2 = SPLj+L+1 (12) HS2 = SPAj (13) (Tubagus haedar ali, 1997, 111) Setelah diperoleh durasi waktu tiap-tiap kegiatan, dari hitungan maju maupun mundur, dapat dianalisis tenggang waktu aktifitas kegiatan tersebut. Dengan menganalisis float dapat diketahui batas toleransi keterlambatan itu apakah dapat mempengaruhi proyek atau tidak. METODE Metode penelitian yang digunakan adalah penelitian deskriptif. Penelitian deskriptif merupakan penelitian yang dimaksudkan untuk mengumpulkan informasi mengenai status gejala yang ada, yaitu keadaan gejala menurut apa
  • 6. e-Jurnal MATRIKS TEKNIK SIPIL Vol. 1 No. 4/Desember 2013/413 adanya pada saat penelitian dilakukan. (Arikunto, 2000:309). Penelitian ini dilakukan pada Proyek Pembangunan Kantor Kelurahan Kerten Kecamatan Laweyan Kota Surakarta dan CV. Catur Tunggal sebagai kontraktor yang mengerjakan proyek tersebut.. Salah satu metode penelitian yang digunakan dalam efisiensi waktu dan biaya pada Proyek Pembangunan Kantor Kelurahan Kerten Kecamatan Laweyan Kota Surakarta ini adalah metode CPM (Critical Path Method). Untuk mempermudah analisis dalam penelitian ini maka diperlukan data-data yang berkaitan secara langsung maupun tidak langsung dengan Proyek Pembangunan Kantor Kelurahan Kerten Kecamatan Laweyan Kota Su- rakarta. Data-data tersebut antara lain : Rencana kerja dalam bentuk kurva S, Rencana Angaran Biaya (RAB), item pekerjaan dan volume pekerjaan beserta harga satuan pekerjaan, dan data lain yang berhubungan dengan perma- salahan penelitian. Langkah-langkah analisis dengan metode CPM adalah sebagai berikut : 1. Pengumpulan data baik di lingkungan proyek maupun dari instansi terkait. 2. Menguraikan jenis kegiatan menjadi kegiatan atau kelompok kegiatan yang merupakan komponen proyek. 3. Menyusun hubungan ketergantungan antara kegiatan-kegiatan yang terlibat dalam pelaksanaan dan menjadi- kannya mata rantai dengan urutan yang sesuai dengan logika ketergantungan tersebut. Urutan ini dapat ber- bentuk seri atau paralel. 4. Membuat diagram network untuk tiap kegiatan-kegiatan pada pelaksanaan proyek. 5. Menentukan kurun waktu bagi masing-masing kegiatan yang dihasilakn dari penguraian lingkup proyek. Umumnya satuan waktu yang digunakan adalah hari. Penentuan kurun waktu kegiatan tergantung dari volume pekerjaan, sumber daya, ruangan, dan produktifitas jam kerja perhari kerja. 6. Menentukan atau mengidentifikasi jalur kritis dan float pada jaringan kerja. 7. Menghitung biaya seluruh kegiatan atau pekerjaan. 8. Analisa waktu yang dilakukan yaitu dengan membuat tolak ukur waktu pada saat paling awal/SPA dan pada saat paling lambat/SPL. 9. Setelah diperoleh kurva S dengan tolak ukur yang menunjukan SPA dan SPL, maka kita dapat membanding- kan antara perencanaan atau jadwal dari pihak kontraktor dengan hasil analisis ini. 10.Pengambilan kesimpulan dari hasil analisis yang dilakukan dan merupakan jawaban atas rumusan masalah se- perti yang tertera pada bab 1. HASIL DAN PEMBAHASAN Hasil Analisis Proyek yang ditinjau dalam penelitian ini adalah Proyek Pembangunan Kantor Kelurahan Kerten Kecamatan Laweyan Kota Surakarta yang dikerjakan oleh CV. Catur Tunggal dengan nilai kontrak Rp. 1.001.454.000,- dan waktu pelaksanaan 150 hari kalender. Penyusunan Jaringan Kerja CPM A. Mengidentifikasi pekerjaan yang akan dianalisis. Berdasarkan data time schedule, rencana anggaran biaya dan gambar gedung yang diperoleh dari CV. Catur Tunggal meliputi berbagai macam pekerjaan. Dari berbagai macam pekerjaan tersebut akan diuraikan menjadi kegiatan atau kelompok kegiatan dan disusun daftar rencana kegiatan beserta gambar network planning. B. Menyusun kembali komponen-komponen proyek  Urutan sesuai logika ketergantungan Jaringan kerja metode CPM hanya mengenal satu macam hubungan antar kegiatan yaitu finish to start (FS) di- mana suatu kegiatan dapat dimulai setelah kegiatan yang mendahuluinya selesai dikerjakan. Selain hubungan FS, kadang juga diperlukan adanya dummy. Dummy merupakan kegiatan fiktif, gunanya untuk menghubungkan dua peristiwa yang tidak memerlukan kegiatannn tertentu. Logika ketergantungan ini didasarkan pada tahapan pekerjaan antara kegiatan yang mendahului dengan kegiatan sesudahnya yang saling berkaitan dengan durasi waktu penyelesaian pekerjaan.  Diagram jaringan kerja metode CPM Untuk menjelaskan hubungan antara komponen yang sesuai dengan logika ketergantungan tersebut diperlu- kan banyak visualisasi yang salah satunya berupa diagram jaringan kerja metode CPM. C. Memperkirakan durasi waktu masing-masing kegiatan Memperkirakan durasi waktu digunakan sesuai dengan analisis harga satuan yang digunakan pada proyek yang ditinjau. Berikut ini beberapa contoh perhitungan durasi waktu : 1. Pekerjaan Tulangan kolom struktur lantai 1  Volume pekerjaan = 16,40 m3 pembesian 190 kg/m3 (analisis HSP dan RAB dari proyek)  Volume tulangan = 16,40 x 190 = 3116 kg  Tenaga kerja = 1 regu ( 1 tbs, 2 pk)
  • 7. e-Jurnal MATRIKS TEKNIK SIPIL Vol. 1 No. 4/Desember 2013/414  Upah pekerja = Rp. 33.000,-  Upah tukang besi = Rp. 40.000,-  Upah tenaga kerja = Rp. 563,- per kg (analisis HSP dari proyek dan SNI)  Upah tenaga per regu = (2x33.000)+(1x40.000) = 106.000,-  Produktifitas tenaga kerja = 106.000/563 = 188,28kg/hari  Produktifitas per regu = 188,28 kg/hari x 1= 188,28 kg/hari  Durasi = 3116 / 188,28 = 17 hari 2. Pekerjaan Pasangan batu bata 1:3 Lantai 1  Volume pekerjaan = 43,08 m2 (analisis HSP dan RAB dari proyek)  Tenaga kerja = 1 regu ( 1 tbt, 2 pk)  Upah pekerja = Rp. 33.000,-  Upah tukang besi = Rp. 40.000,-  Upah tenaga kerja = Rp. 15.100,- per m2 (analisis HSP dari proyek dan SNI)  Upah tenaga per regu = (2x33.000)+(1x40.000) = 106.000,-  Produktifitas tenaga kerja = 106.000/15.100 = 7,01 m2/hari  Produktifitas per regu = 7,01 m2/hari x 1 = 7,01 m2/hari  Durasi = 43,08 / 7,01 = 6 hari. Tahap dan Hasil Perhitungan A. Tahap Hitungan 1. Hitungan maju Perhitungan maju dibawah ini menggunakan rumus 5. Kegiatan B ( Galian Tanah Pondasi) Kegiatan sebelumnya = kegiatan A ( Pekerjaan Persiapan ) Kegiatan sesudahnya = kegiatan F (Pondasi Batu Kali ) SPA(2-3) = SPA(2-3) + D(2-3) = 3 + 7 = 10 Berarti bahwa waktu selesai paling awal dari kegiatan B jatuh pada hari ke 10 kemudian kegiatan selanjut- nya yaitu kegiatan F dapat dimulai paling awal pada hari berikutnya yaitu hari ke 11. 2. Hitungan mundur Perhitungan mundur dibawah ini menggunakan rumus 6. Kegiatan F (Pondasi Batu Kali) Kegiatan sebelumnya = kegiatan B (Galian Tanah Pondasi ) Kegiatan sesudahnya = kegiatan H (Pekerjaan Sloof Struktur) SPL(3-5) = SPL(3-5) – D(3-5) = 20 – 10 = 10 Perhitungan itu menjelaskan bahwa waktu mulai paling lambat kegiatan F adalah waktu selesai paling lam- bat dari kegiatan. B. Hasil Hitungan 1. Waktu penyelesaian proyek Waktu penyelesaian proyek penelitian ini adalah 135 hari dimana waktu penyelesaian itu lebih cepat 15 hari dari jangka waktu penyelesaian proyek menurut dokumen kontrak. Pada gambar diagram jaringan kerja CPM, peristiwa akhir adalah peristiwa ke 36 yang memiliki SPA=SPL=135 2. Float Berikut merupakan contoh hitungan untuk menentukan total float masing-masing kegiatan yang sesuai den- gan persamaan 7. Float tersebut dihitung berdasarkan diagram jaringan kerja CPM. Kegiatan T (Pekerjaan Plesteran 1) yang diapit oleh peristiwa awal ke 18 dan peristiwa akhir ke 20. TF = SPLj20 – D – SPAi18 = 84 – 14 – 70 = 0 Berarti kegiatan T adalah kegiatan kritis. 3. Identifikasi jalur kritis Jalur kritis merupakan kegiatan-kegiatan yang tidak memiliki tenggang waktu atau TF = 0 dan digambar- kan sebagai garis tebal pada diagram jaringan kerja CPM. Dari hasil perhitungan diperoleh lintasan kritis pada kegiatan A – B – F – H – G – K – R – Q – N – P – T – Y – AB – AK – AQ – AO – AN – AS yang memiliki hasil perhitungan dengan nilai TF = 0. Tahap Pembuatan Kurva S Hasil analisis jaringan kerja CPM diaplikasikan pada bagan balok, sehingga diperoleh jadwal pelaksanaan proyek yang memiliki limit jadwal paling awal dan paling lambat. Oleh karena itu terdapat dua kurva S yang terdapat pa-
  • 8. e-Jurnal MATRIKS TEKNIK SIPIL Vol. 1 No. 4/Desember 2013/415 da gambar berimpit pada bagan balok tersebut dengan kurun waktu pelaksanaan 135 hari. Prosentase bobot dari masing-masing kegiatan perhari diperoleh berdasarkan perbandingan antara bobot tiap-tiap kegiatan dengan hasil pelaksanaan kegiatan. Dengan mendistribusikan sumber daya tenaga kerja pada setiap hari kegiatan yang dilaksa- nakan, maka didapat distribusi pemakaian sumber daya tenaga kerja pergiatan perhari. Kebutuhan tenaga perhari tersebut untuk seluruh proyek dapat diketahui dengan cara menjumlahkan pemakaian tenaga kerja oleh kegiatan yang dilaksanakan pada hari yang sama. Pembahasan Dari hasil analisis jaringan kerja CPM dapat digambarkan dua kurva S untuk waktu pelaksanaan proyek 135 hari. Secara umum dapat dijelaskan bahwa arah kurva yang menanjak berarti terdapat komulatif prosentase bobot pe- kerjaan yang cukup tinggi. Koridor operasional yang menyempit menunjukkan kecilnya tenggang waktu (float) ke- giatan. Demikian juga sebaliknya, float yang besar dapat menggambarkan kurva S yang memiliki koridor opera- sional yang cukup luas. Pada waktu inilah pelaksanaan proyek memiliki kelonggaran dalam pelaksanaan proyek, yang tentunya dibatasi oleh koridor operasional yang didasarkan pada limit jadwal kegiatan waktu tercepat dan waktu terlambat. Penjadwalan Proyek Pembangunan Kantor Kelurahan Kerten Kecamatan Laweyan Kota Surakarta oleh CV. Ca- tur Tunggal berdasarkan data time schedule bahwa penyelesaian proyek memerlukan waktu 150 hari. Total biaya proyek tersebut adalah Rp. 1.001.454.000,-. Sedangkan analisis penjadwalan dengan metode CPM, waktu penye- lesaian proyek tersebut adalah 135 hari. Jika dibandingkan antara hasil perhitungan yang dilakukan oleh CV. Ca- tur Tunggal dengan perhitungan menggunakan metode CPM, diperoleh hasil yang lebih menguntungkan dengan metode CPM. Hal ini akan memberikan keuntungan dari segi waktu penyelesaian proyek yaitu akan lebih cepat 15 hari. Dengan data yang diperoleh dari CV. Catur Tunggal bahwa tenaga kerja yang akan diperkerjakan dengan rata-rata sekitar 40 orang, maka berpengaruh terhadap penghematan biaya tenaga kerja dari biaya pembangunan secara keseluruhan menjadi Rp. 979.239.000,- sehingga penghematan waktu terhadap biaya pembangunan yang dapat diperoleh adalah Rp. 22.215.000,-. SIMPULAN Dari analisis dan pembahasan yang telah dilakukan maka dapat diambil beberapa kesimpulan sebagai berikut : 1. Hasil perhitungan dengan metode CPM membutuhkan waktu 135 hari dengan biaya Rp. 979.239.000,- se- dangkan perhitungan yang dilakukan oleh CV. Catur Tunggal membutuhkan waktu 150 hari dengan biaya Rp. 1.001.454.000,- sehingga dapat menghemat waktu 15 hari dan biaya sebesar Rp. 22.215.000,- 2. Lintasan kritis yang diperoleh yaitu terdapat 18 kegiatan atau pekerjaan, di antaranya Pekerjaan Persiapan (A), Pekerjaan Tanah (B), Pondasi Batu Kali (F), Pekerjaan Sloof Struktur (H), Urugan tanah kembali, mendatang- kan & dipadatkan (G), Pengecoran Kolom Struktur 1 (K), Bekisting dan Cor Balok Latei & Kolom Praktis 1 (R), Pasangan Dinding 1 (Q), Pengecoran Balok & Plat Lantai 2 (N), Perawatan Beton & Bongkaran Bekist- ing Balok & Plat Lantai (P), Pekerjaan Plesteran 1(T), Pengecoran Kolom Struktur 2 (Y), Pasangan Dinding 2 (AB), Pekerjaan Penutup Lantai 1 (AK), Pekerjaan Penutup Lantai 2 (AQ), Pekerjaan Doorloop (AO), Insta- lasi Penangkal Petir (AN), Pekerjaan lain-lain (AS). UCAPAN TERIMAKASIH Ucapan terima kasih kepada Ir. Sugiyarto, MT. dan Ir. Siti Qomariyah, M.Sc. yang telah membimbing, memberi arahan dan masukan dalam penelitian ini. REFERENSI Agus, Ahyari. 1986. Manajemen Produksi Perencanaan Sistem Produksi. Yogyakarta, BPFE. Ali, Tubagus Heidar. 1995. Prinsip-Prinsip Network Planning. Jakarta: P.T. Gramedia Pustaka Utama. Andri, Nugroho Aryo. 2007. Optimalisasi Penjadwalan Proyek. Pada Pembangunan Gedung Khusus (Laboratorium) Stasiun Karantina Ikan Kelas 1 Tanjung Mas Semarang. Skripsi, Jurusan Matematika Fakultas Matematika Dan Ilmu Pengetahuan Alam. UniversitasNegeri Semarang. Arikunto, Suharsimi. 2000. Manajemen Penelitian. Jakarta : Rineka Cipta. Hafis, Lep. 2012. Penjadwalan Dengan Mengunakan Jaringan Kerja PDM Dalam Upaya Pengendalian Waktu Pelaksanaan Proyek. Skripsi, Jurusan Teknik Sipil Fakultas Teknik Universitas Sebelas Maret Surakarta. Surakarta. Handoko TH,. 2000. Manajemen Personalia dan Sumber Daya Manusia. Edisi 2. Yogyakarta : BPFE. Hasibuan, Malayu SP. 2002. Manajemen Sumber Daya Manusia. Jakarta : Bumi Aksara. Ratnasari, Widya. 2005. Penjadwalan Waktu Proyek Dengan Metode CPM (Studi Kasus Proyek Pembangunan Gedung UKM Universitas Sebelas Maret Surakarta). Surakarta : Universitas Sebelas Maret. Reksohadiprodjo, Soekanto. 1987. Management Proyek. Yogyakarta : BPFE. Richard L. Daft. 2002. Era Baru Manajemen. Buku 1 dan 2. Jakarta : Salemba Empat.
  • 9. e-Jurnal MATRIKS TEKNIK SIPIL Vol. 1 No. 4/Desember 2013/416 Sakdiyah. 2004. Network Planning Dengan CPM Dalam Usaha Meningkatkan Efisiensi Biaya dan Waktu Pada Proyek Pembangunan Perkantoran di PT. Nilano Malang. Malang : Universitas Muhamadiyah Malang. Santoso, Budi. 2003. Manajemen Proyek Konsep & Implementasi. Yogyakarta : Graha Ilmu. Soeharto, Imam. 2001. Manajemen Proyek (Dari Konseptual Sampai Operasional). Jakarta : Erlangga. Yamit, Zulian. 2001. Manajemen Kualitas Produk & Jasa. Yogyakarta : Ekonisia.