DRILLING ECONOMICS 
JAMES A. CRAIG
TABLE OF CONTENTS 
 
Drilling Cost Prediction 
 
Cost Specification 
 
Authorization for Expenditure (AFE) 
 
Drilling Optimization 
 
Drilling Optimization Techniques 
 
Drilling Cost Equation 
 
Breakeven Calculations 
 
Decision Making
DRILLING COST PREDICTION 
 
Drilling cost predictions are made so that sound economic decision can be made. 
 
Predictions depend primarily on: 
 
Location –governs the cost of preparing wellsite, moving rig to location, and daily operating cost. 
 
Depth –governs the lithologies to be penetrated, thus the time required to complete the well.
 
C = cost, $ 
 
a, b = constants depending on well location 
 
D = depth, ft 
()expCabD= 
Drilling costs tend to increase exponentially with depth.
lnlnCaDbb=−
COST SPECIFICATION 
 
Drilling costs can be broken down into 3 groups: 
 
Fixed 
 
Daily 
 
Unit
Fixed Costs 
 
Fixed costs are determined by the nature of the well, such as: 
 
Wellheads 
 
Site preparation 
 
Casing, cement, tubing and packers
DailyCosts 
 
Dailycostsarerelatedtothetimespentontheoperation. 
 
Offshorerigshavehighexpenseswhichlistedbelow. 
 
Dailycostsinclude: 
 
Paymentstodrillingcontractors(rigtime) 
 
Toolrental 
 
Paymenttospecialistservices 
 
Salaries,wagesetc 
 
Fuel 
 
Lubricatingoil,grease 
 
Drillingconsumables(rope,soapanddope) 
 
Transportofmaterials
UnitCosts 
 
This is the price of a unit of a commodity such as the price per tonne of barite or bentonite. 
 
This can be optimized in the tendering process, which is Drilling Manager responsibility. 
 
Good site supervision can ensure that consumption is not excessive.
AUTHORIZATION FOR EXPENDITURE (AFE) 
 
The operators, should know how much a well is going to cost if it is dry, tested or completed. 
 
Consequently, AFEs should be broken down into sections. 
 
AFE makes it easier to carry out post-well assessment and cost-comparisons between wells.
 
AFEsarebrokendownintothefollowingsections: 
 
Preparation 
 
Drillingandabandonment 
 
Testing 
 
Completion 
AFE Components
Preparation 
 
This part of the AFE covers the costs incurred to the point at which the rig is brought on to location. 
 
For onshore wells this would include site building and well engineering as the main cost. 
 
For offshore wells, the main costs are site surveying and well engineering.
Drilling and Abandonment 
 
This is the ‘dry hole’ drilling component of the well. 
 
It assumes drilling reached the TD, logging carried out and no economicfinding. 
 
The well is, therefore, proposed for abandonment and appropriate cost is allocated to it.
Testing 
 
It is only the testing cost charged by the testing company 
 
It must also include all the ongoing daily costs associated with the rig such as: 
 
rig day rate 
 
fuel oil 
 
site personnel 
 
office personnel 
 
office overheads
Completion 
 
It is not only the cost of completion equipment and services but also the costs of: 
 
rig day rate 
 
fuel oil 
 
extra casing string if run 
 
perforation 
 
site personnel 
 
office personnel 
 
office overheads
 
Costs can be estimated fairly for development wells 
 
Costing for exploratory wells is a much harder task. 
 
The service companies will give the operating companies the main costs: 
 
drilling contractorsmud loggers 
 
electric logging companiesmud companies 
 
cementing companiesbit companies 
 
casing companieswellhead companies 
 
tool rental companiescoring companies
 
The Time Depth Graph created for the Drilling Programme provides an estimate of the days to be spent on the well. 
 
By costing in the charges for these days, the AFE begins to take form. 
 
Some assumptions must be made, e.g.: 
 
It is difficult to fix charges such as coring on an exploration well with the limited knowledge available regarding formations to be drilled. The AFE could either include one 20-m core or several runs.
 
A contingency factor should be applied to the AFE. 
 
This can be in the form of: 
 
A lump sum, or 
 
A percentage of well costs.
DRILLING OPTIMIZATION 
 
Drilling optimization is minimizing the cost of reaching the well’s objective while maintaining safety standards. 
 
This minimum drilling cost is also the optimum drilling cost.
 
The optimization process is a cycle that starts with using the existingdata base of drilling information. 
 
More data are collected during the practical drilling process. 
 
The new data are then analyzed to update the data base for future use.
 
The process of optimizing drillling process is not always straight-forward. 
 
Because of uncertainties involved, there is always need for some trade-offs. 
 
For example, optimization might mean paying more to obtain a better tool, such as choosing a rig with a higher day rate to obtain better equipment.
DRILLING OPTIMIZATION TECHNIQUES 
 
The following optimization techniques are popular in drilling: 
 
Drilling cost equation 
 
Breakeven calculations 
 
Cost-effective decision making
DrillingCostEquation 
 
Also known as the cost per foot equation. 
 
Cdrill= cost per foot for the interval concerned, $/ft 
 
Cbit= cost of delivered bit at the drill site, $ 
 
Ctools= cost of tools or repair to tools, $ 
 
Cmud= cost of mud to drill the interval, $ 
 
Crig= rental rig rate, $/hour 
 
Csupport= support cost, i.e. third-party contractor rates, $/hour 
()() bittoolsmudrigsupporttoolrentaltripbitlostdrillbitavgCCCCCCTTTCTROP +++++++= ×
 
Ctool rental= rental of tools, $/hour 
 
Ttrip= round trip time, i.e. time to pull and run a bit, hours 
 
Tbit= bit life, i.e. time required to drill the interval, hours 
 
Tlost= non-rotating time, i.e. time chargeable to non- drilling task, hours 
 
ROPavg= average rate of penetration during bit run, ft/hour
 
Eleven variables are listed in the drilling cost equation. 
 
Most of these interact with one or more other variables. 
 
Because the degree of interaction is often impossible to determine intuitively, the drilling cost equation can aid decision making
BreakevenCalculations 
 
Breakeven calculations are economic evaluations that determine the change in a dependent variablethat is required to create a beneficial change in an independent variable.
 
The typical variables are as follows: 
Alteration in Independent Variable 
Required Change in Dependent Variable 
Bit type 
Bit life, ROP 
Drilling tools 
Bit life, ROP, Trip time 
Mud type 
Bit life, ROP, Trip time
 
The procedure is as follows: 
 
Solve the drilling cost equation for present conditions to determine the cost/ft. 
 
Specify the independent variable and the dependent variable to be changed. 
 
Determine the change in any other parameters that will result from the change in the independent variable. 
 
Substitute the cost/ft determined in Step 1, the independent variable specified in Step 2, and all other variables into the drilling cost equation. 
 
Rearrange the equation and solve to find the value of the dependent variable required for breakeven.
 
The breakeven calculations can also be used to evaluate whether additional rig equipment should be obtained for purposes other than to increase the rate of penetration.
DecisionMaking 
 
It is difficult to exactly calculate the consequences of each decision to be made 
 
Some degree of uncertainty concerning the consequences are made. 
 
Decision of this type must be made on a statistical basis: 
 
a decision is made to implement the course of action that on averageresults in the lowest cost.
Expected Values Method 
 
An explicit step-by-step approach to the decision process traditionally used. 
 
The method is used to make decisions by evaluating choices that have both different finanacial returns and different probabilities of occurence.
 
The best decision is that which has the lowest(or least negative) probability cost product. 
 
The fundamental form of the expected value equations is given as follows: 
1122EVCPCP=+ 121PP+=
 
EV = expected value, $ 
 
C1= cost of first event, $ 
 
P1= probability of first event, fraction 
 
C2= cost of second event, $ 
 
P2= probability of second event, fraction
Example1 –Cost per foot calculation 
 
A 17-1/2” bit drills 1,050’ of hole at an average penetration rate of 35 ft/hr. given the following data, what is the cost per foot? 
 
Round trip = 6hrsBit purchase cost = $3,000 
 
Bit life = 30 hrsTool purchase cost = $100 
 
Rig cost = $800/hrInterval mud cost = $5,000 
 
Tool rental = $100/hrSupport cost = $200/hr 
 
Ttrip= 6hrsCbit= $3,000ROPavg= 35 ft/hr 
 
Tbit= 30 hrsCmud= $5,000Crig= $800/hr 
 
Ctools= $100Ctool rental= $100/hrCsupport= $200/hr 

()() bittoolsmudrigsupporttoolrentaltripbitlostdrillbitavgCCCCCCTTTCTROP +++++++= ×()()3,0001005,00080020010063003035drillC+++++++= ×8,10039,6001,050drillC+ = $45.43/ftdrillC=
Example2 –Breakeven calculation 
 
When planning a well. It has been determined that the next section requires a polymer mud that costs $15/bbl. The rig has inefficient shale shakers, which the drilling contractor will not replace without sharing the expense. How much should the operator be prepared to pay for the installation of the new, high- efficiency shale shakers if the rig is to be used for only a single well? 
 
Old shale shaker solid control efficiency = 65% 
 
New shale shaker solid control efficiency = 75% 
 
Anticipated average hole diameter = 13” 
 
Maximum allowable drill solids concentration = 6%
 
We use mud interval cost equation: 
 
Cmud= cost of mud to drill the interval, $ 
 
Lint= length of interval, ft 
 
Cmud/bbl= mud cost, $/bbl 
 
Dh= average hole diameter, in. 
 
Eff = efficiency of solids control system, % 
 
Sactive= drilled solids in active mud, volume % 
()()2hactivemudintmud/bblactiveD1Eff1SCLC1,029S −− =××
 
For the existing shale shakers: 
()()2mud1310.6510.06C6,000151,0290.06 −− =×× mudC6,000150.9006=××mudC$81,051=
 
If new shale shakers were purchased: 
 
Ecost= equipment cost, $ 
()()2mudcost1310.7510.06C6,00015E1,0290.06 −− =×+× mudcostC57,894E=+ ()()2h activemudintmud/bblcostactiveD1Eff1SCLCE1,029S −− =×+×
 
Breakeven occurs when the cost of existing shakers equals the cost of new shakers. 
 
This value ($23,157) represents the mostthe operator should pay for the installation of new shakers. 
 
Any amount less that this can be negotiated with the drilling contractor represents a net savings. 
cost81,05157,894E=+ costE$23,157=
Example3 –EVcalculation 
 
When drilling 12-1/4” hole in an area, experience shows that a reverse circulating junk basket (RCJB) is required on 25% of all wells. The average rental period for wells where a RCJB is required is 3 days, and 12 hours rig time is wasted waiting for the equipment. 
 
A rig is contracted for a single well in which the 12- 1/4” section is planned to take 25 days to drill. 
 
Given: Rig rate = $8,000/day 
RCJB rental = $150 first day plus $25/day thereafter 
 
Would it be advantageous to have RCJB on standby at the rigsite:
 
We use the EV method and decision tree. 
RCJB rented 
RCJB not rented 
Required 
Not required
 
RCJB not rented 
 
Not required 
 
Required 
Rig rateInterval time×8,00025=×$200,000= ()[]Rig rateInterval timeWaiting timeRCJB rentalRental time×+++ ()()8,000250.5150252=×+++×$204,200=
 
RCJB on standby 
()()Rig rateInterval timeRCJB rentalInterval time×++ $200,750= ()()8,000251502524=×++×
RCJB rented 
RCJB not rented 
Required 
Not required 
C = $200,000 
P = 75% 
EV = 200,000 x 0.75 
EV = $150,000 
C = $204,200 
P = 25% 
EV = 204,200 x 0.25 
EV = $51,050 
C = $200,750 
P = 100% 
EV = 200,750 x 1.00 
EV = $200,750
RCJB not rented 
Total EV = $150,000 + $51,050 = $201,050 
RCJB on standby 
Total EV = $200,750 
 
RCJB on standby < RCJB not rented 
 
Therefore, the better economic solution is to have the RCJB on standby at the rigsite.

More Related Content

What's hot

Reservoir Primary Recovery Mechanisms
Reservoir Primary Recovery MechanismsReservoir Primary Recovery Mechanisms
Reservoir Primary Recovery Mechanismskusrick29
 
Special core analysis
Special core analysisSpecial core analysis
Special core analysisWajid09
 
Drilling Fluid Circulation Systems
Drilling Fluid Circulation SystemsDrilling Fluid Circulation Systems
Drilling Fluid Circulation SystemsAFATous
 
Fundamentals of Petroleum Engineering Module 3
Fundamentals of Petroleum Engineering Module 3Fundamentals of Petroleum Engineering Module 3
Fundamentals of Petroleum Engineering Module 3Aijaz Ali Mooro
 
Well control equipment
Well control equipmentWell control equipment
Well control equipmentSARWAR SALAM
 
Life Cycle of Oil & Gas Wells
Life Cycle of Oil & Gas WellsLife Cycle of Oil & Gas Wells
Life Cycle of Oil & Gas WellsMohamed Elnagar
 
Drilling economics drilling engineering
Drilling economics drilling engineeringDrilling economics drilling engineering
Drilling economics drilling engineeringSafen D Taha
 
Formation pressure in oil and gas drilling wells
Formation pressure in oil and gas drilling wellsFormation pressure in oil and gas drilling wells
Formation pressure in oil and gas drilling wellsSaeed Fakhr Douzdouzani
 
Tubing Performance Relation (TPR)
Tubing Performance Relation (TPR)Tubing Performance Relation (TPR)
Tubing Performance Relation (TPR)James Craig
 
drilling fluids and its rheology
drilling fluids and its rheology drilling fluids and its rheology
drilling fluids and its rheology SHIKHA THAPA
 
Conventional and Unconventional Reservoirs
Conventional and Unconventional ReservoirsConventional and Unconventional Reservoirs
Conventional and Unconventional ReservoirsRimsha Rais
 
Material balance simulation(1)
Material balance simulation(1)Material balance simulation(1)
Material balance simulation(1)KripalKumarPatel
 
Power System
Power SystemPower System
Power SystemAFATous
 
Presentation1Practical purposes of mud logging
Presentation1Practical purposes of mud loggingPresentation1Practical purposes of mud logging
Presentation1Practical purposes of mud loggingelharith mohamed
 

What's hot (20)

Artificial Lift Methods
Artificial Lift MethodsArtificial Lift Methods
Artificial Lift Methods
 
Reservoir Primary Recovery Mechanisms
Reservoir Primary Recovery MechanismsReservoir Primary Recovery Mechanisms
Reservoir Primary Recovery Mechanisms
 
Special core analysis
Special core analysisSpecial core analysis
Special core analysis
 
Hydraulics
HydraulicsHydraulics
Hydraulics
 
Well test analysis
Well test analysisWell test analysis
Well test analysis
 
Drilling Fluid Circulation Systems
Drilling Fluid Circulation SystemsDrilling Fluid Circulation Systems
Drilling Fluid Circulation Systems
 
Fundamentals of Petroleum Engineering Module 3
Fundamentals of Petroleum Engineering Module 3Fundamentals of Petroleum Engineering Module 3
Fundamentals of Petroleum Engineering Module 3
 
Well control equipment
Well control equipmentWell control equipment
Well control equipment
 
Life Cycle of Oil & Gas Wells
Life Cycle of Oil & Gas WellsLife Cycle of Oil & Gas Wells
Life Cycle of Oil & Gas Wells
 
Drilling economics drilling engineering
Drilling economics drilling engineeringDrilling economics drilling engineering
Drilling economics drilling engineering
 
Formation pressure in oil and gas drilling wells
Formation pressure in oil and gas drilling wellsFormation pressure in oil and gas drilling wells
Formation pressure in oil and gas drilling wells
 
Tubing Performance Relation (TPR)
Tubing Performance Relation (TPR)Tubing Performance Relation (TPR)
Tubing Performance Relation (TPR)
 
Reservoir
ReservoirReservoir
Reservoir
 
well control (1)
 well control (1) well control (1)
well control (1)
 
drilling fluids and its rheology
drilling fluids and its rheology drilling fluids and its rheology
drilling fluids and its rheology
 
Conventional and Unconventional Reservoirs
Conventional and Unconventional ReservoirsConventional and Unconventional Reservoirs
Conventional and Unconventional Reservoirs
 
Material balance simulation(1)
Material balance simulation(1)Material balance simulation(1)
Material balance simulation(1)
 
Drilling fluids
Drilling fluidsDrilling fluids
Drilling fluids
 
Power System
Power SystemPower System
Power System
 
Presentation1Practical purposes of mud logging
Presentation1Practical purposes of mud loggingPresentation1Practical purposes of mud logging
Presentation1Practical purposes of mud logging
 

Similar to Drilling Engineering - Drilling Economics

Cost management and performance measurements for petroleum upstream industry ...
Cost management and performance measurements for petroleum upstream industry ...Cost management and performance measurements for petroleum upstream industry ...
Cost management and performance measurements for petroleum upstream industry ...Hamdy Rashed
 
Using a system cost analysis to quantify drilling fluids and
Using a system cost analysis to quantify drilling fluids andUsing a system cost analysis to quantify drilling fluids and
Using a system cost analysis to quantify drilling fluids andamrhaggag
 
Chapter 7 capital cost estimation
Chapter 7 capital cost estimationChapter 7 capital cost estimation
Chapter 7 capital cost estimationjose2424
 
Episode 27 : Project Management Costs
Episode 27 : Project Management Costs Episode 27 : Project Management Costs
Episode 27 : Project Management Costs SAJJAD KHUDHUR ABBAS
 
Economics of turning process
Economics of turning processEconomics of turning process
Economics of turning processAmr El-ashmony
 
Episode 27 : Project Management Costs
Episode 27 : Project Management Costs Episode 27 : Project Management Costs
Episode 27 : Project Management Costs SAJJAD KHUDHUR ABBAS
 
16_ENG_Concept Selection_Nov2012_DOI 10.4236eng.2012.411102
16_ENG_Concept Selection_Nov2012_DOI 10.4236eng.2012.41110216_ENG_Concept Selection_Nov2012_DOI 10.4236eng.2012.411102
16_ENG_Concept Selection_Nov2012_DOI 10.4236eng.2012.411102Efrain Rodriguez Sanchez
 
Construction equipment need and factors-nrc
Construction equipment need and factors-nrcConstruction equipment need and factors-nrc
Construction equipment need and factors-nrcnarayanch1979
 
Economic Excavator Configuration for Earthwork Scheduling
Economic Excavator Configuration for Earthwork SchedulingEconomic Excavator Configuration for Earthwork Scheduling
Economic Excavator Configuration for Earthwork Schedulingcoreconferences
 
Blasting inprovement techniques
Blasting inprovement techniquesBlasting inprovement techniques
Blasting inprovement techniquesKrishna Deo Prasad
 
Impact of Mobility Technologies in Oil and Gas
Impact of Mobility Technologies in Oil and GasImpact of Mobility Technologies in Oil and Gas
Impact of Mobility Technologies in Oil and GasCole Whitney
 
Difference between depreciation and depletion
Difference between depreciation and depletionDifference between depreciation and depletion
Difference between depreciation and depletionAli RazA
 

Similar to Drilling Engineering - Drilling Economics (20)

Drill.pptx
Drill.pptxDrill.pptx
Drill.pptx
 
Presentation 2
Presentation 2Presentation 2
Presentation 2
 
Cost management and performance measurements for petroleum upstream industry ...
Cost management and performance measurements for petroleum upstream industry ...Cost management and performance measurements for petroleum upstream industry ...
Cost management and performance measurements for petroleum upstream industry ...
 
Using a system cost analysis to quantify drilling fluids and
Using a system cost analysis to quantify drilling fluids andUsing a system cost analysis to quantify drilling fluids and
Using a system cost analysis to quantify drilling fluids and
 
Warranty
WarrantyWarranty
Warranty
 
3.estimating
3.estimating3.estimating
3.estimating
 
Chapter 7 capital cost estimation
Chapter 7 capital cost estimationChapter 7 capital cost estimation
Chapter 7 capital cost estimation
 
Published
PublishedPublished
Published
 
U1 p2 breakeven analysis
U1 p2 breakeven analysisU1 p2 breakeven analysis
U1 p2 breakeven analysis
 
Episode 27 : Project Management Costs
Episode 27 : Project Management Costs Episode 27 : Project Management Costs
Episode 27 : Project Management Costs
 
Economics of turning process
Economics of turning processEconomics of turning process
Economics of turning process
 
Episode 27 : Project Management Costs
Episode 27 : Project Management Costs Episode 27 : Project Management Costs
Episode 27 : Project Management Costs
 
16_ENG_Concept Selection_Nov2012_DOI 10.4236eng.2012.411102
16_ENG_Concept Selection_Nov2012_DOI 10.4236eng.2012.41110216_ENG_Concept Selection_Nov2012_DOI 10.4236eng.2012.411102
16_ENG_Concept Selection_Nov2012_DOI 10.4236eng.2012.411102
 
Chapter 5
Chapter 5Chapter 5
Chapter 5
 
Construction equipment need and factors-nrc
Construction equipment need and factors-nrcConstruction equipment need and factors-nrc
Construction equipment need and factors-nrc
 
Economic Excavator Configuration for Earthwork Scheduling
Economic Excavator Configuration for Earthwork SchedulingEconomic Excavator Configuration for Earthwork Scheduling
Economic Excavator Configuration for Earthwork Scheduling
 
Blasting inprovement techniques
Blasting inprovement techniquesBlasting inprovement techniques
Blasting inprovement techniques
 
Impact of Mobility Technologies in Oil and Gas
Impact of Mobility Technologies in Oil and GasImpact of Mobility Technologies in Oil and Gas
Impact of Mobility Technologies in Oil and Gas
 
Unit 5 or
Unit 5 orUnit 5 or
Unit 5 or
 
Difference between depreciation and depletion
Difference between depreciation and depletionDifference between depreciation and depletion
Difference between depreciation and depletion
 

More from James Craig

Petroleum Geology - Origin of Petroleum
Petroleum Geology - Origin of PetroleumPetroleum Geology - Origin of Petroleum
Petroleum Geology - Origin of PetroleumJames Craig
 
Drilling Engineering - Primary Cementing
Drilling Engineering - Primary CementingDrilling Engineering - Primary Cementing
Drilling Engineering - Primary CementingJames Craig
 
Drilling Engineering - Casing Design
Drilling Engineering - Casing DesignDrilling Engineering - Casing Design
Drilling Engineering - Casing DesignJames Craig
 
Drilling Engineering - Directional Drilling
Drilling Engineering - Directional DrillingDrilling Engineering - Directional Drilling
Drilling Engineering - Directional DrillingJames Craig
 
Drilling Engineering - Drill Bit
Drilling Engineering - Drill BitDrilling Engineering - Drill Bit
Drilling Engineering - Drill BitJames Craig
 
Reservoir Geomechanics
Reservoir GeomechanicsReservoir Geomechanics
Reservoir GeomechanicsJames Craig
 
Drilling Mud Laboratory
Drilling Mud LaboratoryDrilling Mud Laboratory
Drilling Mud LaboratoryJames Craig
 
Petroleum Production Engineering - Perforation
Petroleum Production Engineering - PerforationPetroleum Production Engineering - Perforation
Petroleum Production Engineering - PerforationJames Craig
 
2. Failure Mechanics
2. Failure Mechanics2. Failure Mechanics
2. Failure MechanicsJames Craig
 
1. Rock Elasticity
1. Rock Elasticity1. Rock Elasticity
1. Rock ElasticityJames Craig
 
4. Borehole Stresses
4. Borehole Stresses4. Borehole Stresses
4. Borehole StressesJames Craig
 

More from James Craig (13)

Petroleum Geology - Origin of Petroleum
Petroleum Geology - Origin of PetroleumPetroleum Geology - Origin of Petroleum
Petroleum Geology - Origin of Petroleum
 
Drilling Engineering - Primary Cementing
Drilling Engineering - Primary CementingDrilling Engineering - Primary Cementing
Drilling Engineering - Primary Cementing
 
Drilling Engineering - Casing Design
Drilling Engineering - Casing DesignDrilling Engineering - Casing Design
Drilling Engineering - Casing Design
 
Drilling Engineering - Directional Drilling
Drilling Engineering - Directional DrillingDrilling Engineering - Directional Drilling
Drilling Engineering - Directional Drilling
 
Drilling Engineering - Drill Bit
Drilling Engineering - Drill BitDrilling Engineering - Drill Bit
Drilling Engineering - Drill Bit
 
Reservoir Geomechanics
Reservoir GeomechanicsReservoir Geomechanics
Reservoir Geomechanics
 
Skin Effects
Skin EffectsSkin Effects
Skin Effects
 
Drilling Mud Laboratory
Drilling Mud LaboratoryDrilling Mud Laboratory
Drilling Mud Laboratory
 
Petroleum Production Engineering - Perforation
Petroleum Production Engineering - PerforationPetroleum Production Engineering - Perforation
Petroleum Production Engineering - Perforation
 
1. World Energy
1. World Energy1. World Energy
1. World Energy
 
2. Failure Mechanics
2. Failure Mechanics2. Failure Mechanics
2. Failure Mechanics
 
1. Rock Elasticity
1. Rock Elasticity1. Rock Elasticity
1. Rock Elasticity
 
4. Borehole Stresses
4. Borehole Stresses4. Borehole Stresses
4. Borehole Stresses
 

Recently uploaded

University management System project report..pdf
University management System project report..pdfUniversity management System project report..pdf
University management System project report..pdfKamal Acharya
 
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...SUHANI PANDEY
 
Thermal Engineering Unit - I & II . ppt
Thermal Engineering  Unit - I & II . pptThermal Engineering  Unit - I & II . ppt
Thermal Engineering Unit - I & II . pptDineshKumar4165
 
Call for Papers - International Journal of Intelligent Systems and Applicatio...
Call for Papers - International Journal of Intelligent Systems and Applicatio...Call for Papers - International Journal of Intelligent Systems and Applicatio...
Call for Papers - International Journal of Intelligent Systems and Applicatio...Christo Ananth
 
Unleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapUnleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapRishantSharmaFr
 
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptxBSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptxfenichawla
 
Bhosari ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For ...
Bhosari ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For ...Bhosari ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For ...
Bhosari ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For ...tanu pandey
 
Double Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torqueDouble Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torqueBhangaleSonal
 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...roncy bisnoi
 
AKTU Computer Networks notes --- Unit 3.pdf
AKTU Computer Networks notes ---  Unit 3.pdfAKTU Computer Networks notes ---  Unit 3.pdf
AKTU Computer Networks notes --- Unit 3.pdfankushspencer015
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlysanyuktamishra911
 
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756dollysharma2066
 
Generative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPTGenerative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPTbhaskargani46
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performancesivaprakash250
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Call Girls in Nagpur High Profile
 

Recently uploaded (20)

University management System project report..pdf
University management System project report..pdfUniversity management System project report..pdf
University management System project report..pdf
 
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
 
NFPA 5000 2024 standard .
NFPA 5000 2024 standard                                  .NFPA 5000 2024 standard                                  .
NFPA 5000 2024 standard .
 
Thermal Engineering Unit - I & II . ppt
Thermal Engineering  Unit - I & II . pptThermal Engineering  Unit - I & II . ppt
Thermal Engineering Unit - I & II . ppt
 
Call for Papers - International Journal of Intelligent Systems and Applicatio...
Call for Papers - International Journal of Intelligent Systems and Applicatio...Call for Papers - International Journal of Intelligent Systems and Applicatio...
Call for Papers - International Journal of Intelligent Systems and Applicatio...
 
Unleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapUnleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leap
 
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptxBSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
 
Roadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and RoutesRoadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and Routes
 
Bhosari ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For ...
Bhosari ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For ...Bhosari ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For ...
Bhosari ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For ...
 
Double Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torqueDouble Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torque
 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
 
AKTU Computer Networks notes --- Unit 3.pdf
AKTU Computer Networks notes ---  Unit 3.pdfAKTU Computer Networks notes ---  Unit 3.pdf
AKTU Computer Networks notes --- Unit 3.pdf
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghly
 
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
 
Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024
 
Generative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPTGenerative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPT
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performance
 
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
 
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
 

Drilling Engineering - Drilling Economics

  • 2. TABLE OF CONTENTS  Drilling Cost Prediction  Cost Specification  Authorization for Expenditure (AFE)  Drilling Optimization  Drilling Optimization Techniques  Drilling Cost Equation  Breakeven Calculations  Decision Making
  • 3. DRILLING COST PREDICTION  Drilling cost predictions are made so that sound economic decision can be made.  Predictions depend primarily on:  Location –governs the cost of preparing wellsite, moving rig to location, and daily operating cost.  Depth –governs the lithologies to be penetrated, thus the time required to complete the well.
  • 4.  C = cost, $  a, b = constants depending on well location  D = depth, ft ()expCabD= Drilling costs tend to increase exponentially with depth.
  • 6. COST SPECIFICATION  Drilling costs can be broken down into 3 groups:  Fixed  Daily  Unit
  • 7. Fixed Costs  Fixed costs are determined by the nature of the well, such as:  Wellheads  Site preparation  Casing, cement, tubing and packers
  • 8. DailyCosts  Dailycostsarerelatedtothetimespentontheoperation.  Offshorerigshavehighexpenseswhichlistedbelow.  Dailycostsinclude:  Paymentstodrillingcontractors(rigtime)  Toolrental  Paymenttospecialistservices  Salaries,wagesetc  Fuel  Lubricatingoil,grease  Drillingconsumables(rope,soapanddope)  Transportofmaterials
  • 9. UnitCosts  This is the price of a unit of a commodity such as the price per tonne of barite or bentonite.  This can be optimized in the tendering process, which is Drilling Manager responsibility.  Good site supervision can ensure that consumption is not excessive.
  • 10. AUTHORIZATION FOR EXPENDITURE (AFE)  The operators, should know how much a well is going to cost if it is dry, tested or completed.  Consequently, AFEs should be broken down into sections.  AFE makes it easier to carry out post-well assessment and cost-comparisons between wells.
  • 11.  AFEsarebrokendownintothefollowingsections:  Preparation  Drillingandabandonment  Testing  Completion AFE Components
  • 12. Preparation  This part of the AFE covers the costs incurred to the point at which the rig is brought on to location.  For onshore wells this would include site building and well engineering as the main cost.  For offshore wells, the main costs are site surveying and well engineering.
  • 13. Drilling and Abandonment  This is the ‘dry hole’ drilling component of the well.  It assumes drilling reached the TD, logging carried out and no economicfinding.  The well is, therefore, proposed for abandonment and appropriate cost is allocated to it.
  • 14. Testing  It is only the testing cost charged by the testing company  It must also include all the ongoing daily costs associated with the rig such as:  rig day rate  fuel oil  site personnel  office personnel  office overheads
  • 15. Completion  It is not only the cost of completion equipment and services but also the costs of:  rig day rate  fuel oil  extra casing string if run  perforation  site personnel  office personnel  office overheads
  • 16.  Costs can be estimated fairly for development wells  Costing for exploratory wells is a much harder task.  The service companies will give the operating companies the main costs:  drilling contractorsmud loggers  electric logging companiesmud companies  cementing companiesbit companies  casing companieswellhead companies  tool rental companiescoring companies
  • 17.  The Time Depth Graph created for the Drilling Programme provides an estimate of the days to be spent on the well.  By costing in the charges for these days, the AFE begins to take form.  Some assumptions must be made, e.g.:  It is difficult to fix charges such as coring on an exploration well with the limited knowledge available regarding formations to be drilled. The AFE could either include one 20-m core or several runs.
  • 18.  A contingency factor should be applied to the AFE.  This can be in the form of:  A lump sum, or  A percentage of well costs.
  • 19. DRILLING OPTIMIZATION  Drilling optimization is minimizing the cost of reaching the well’s objective while maintaining safety standards.  This minimum drilling cost is also the optimum drilling cost.
  • 20.  The optimization process is a cycle that starts with using the existingdata base of drilling information.  More data are collected during the practical drilling process.  The new data are then analyzed to update the data base for future use.
  • 21.
  • 22.  The process of optimizing drillling process is not always straight-forward.  Because of uncertainties involved, there is always need for some trade-offs.  For example, optimization might mean paying more to obtain a better tool, such as choosing a rig with a higher day rate to obtain better equipment.
  • 23. DRILLING OPTIMIZATION TECHNIQUES  The following optimization techniques are popular in drilling:  Drilling cost equation  Breakeven calculations  Cost-effective decision making
  • 24. DrillingCostEquation  Also known as the cost per foot equation.  Cdrill= cost per foot for the interval concerned, $/ft  Cbit= cost of delivered bit at the drill site, $  Ctools= cost of tools or repair to tools, $  Cmud= cost of mud to drill the interval, $  Crig= rental rig rate, $/hour  Csupport= support cost, i.e. third-party contractor rates, $/hour ()() bittoolsmudrigsupporttoolrentaltripbitlostdrillbitavgCCCCCCTTTCTROP +++++++= ×
  • 25.  Ctool rental= rental of tools, $/hour  Ttrip= round trip time, i.e. time to pull and run a bit, hours  Tbit= bit life, i.e. time required to drill the interval, hours  Tlost= non-rotating time, i.e. time chargeable to non- drilling task, hours  ROPavg= average rate of penetration during bit run, ft/hour
  • 26.  Eleven variables are listed in the drilling cost equation.  Most of these interact with one or more other variables.  Because the degree of interaction is often impossible to determine intuitively, the drilling cost equation can aid decision making
  • 27. BreakevenCalculations  Breakeven calculations are economic evaluations that determine the change in a dependent variablethat is required to create a beneficial change in an independent variable.
  • 28.  The typical variables are as follows: Alteration in Independent Variable Required Change in Dependent Variable Bit type Bit life, ROP Drilling tools Bit life, ROP, Trip time Mud type Bit life, ROP, Trip time
  • 29.  The procedure is as follows:  Solve the drilling cost equation for present conditions to determine the cost/ft.  Specify the independent variable and the dependent variable to be changed.  Determine the change in any other parameters that will result from the change in the independent variable.  Substitute the cost/ft determined in Step 1, the independent variable specified in Step 2, and all other variables into the drilling cost equation.  Rearrange the equation and solve to find the value of the dependent variable required for breakeven.
  • 30.  The breakeven calculations can also be used to evaluate whether additional rig equipment should be obtained for purposes other than to increase the rate of penetration.
  • 31. DecisionMaking  It is difficult to exactly calculate the consequences of each decision to be made  Some degree of uncertainty concerning the consequences are made.  Decision of this type must be made on a statistical basis:  a decision is made to implement the course of action that on averageresults in the lowest cost.
  • 32. Expected Values Method  An explicit step-by-step approach to the decision process traditionally used.  The method is used to make decisions by evaluating choices that have both different finanacial returns and different probabilities of occurence.
  • 33.  The best decision is that which has the lowest(or least negative) probability cost product.  The fundamental form of the expected value equations is given as follows: 1122EVCPCP=+ 121PP+=
  • 34.  EV = expected value, $  C1= cost of first event, $  P1= probability of first event, fraction  C2= cost of second event, $  P2= probability of second event, fraction
  • 35. Example1 –Cost per foot calculation  A 17-1/2” bit drills 1,050’ of hole at an average penetration rate of 35 ft/hr. given the following data, what is the cost per foot?  Round trip = 6hrsBit purchase cost = $3,000  Bit life = 30 hrsTool purchase cost = $100  Rig cost = $800/hrInterval mud cost = $5,000  Tool rental = $100/hrSupport cost = $200/hr  Ttrip= 6hrsCbit= $3,000ROPavg= 35 ft/hr  Tbit= 30 hrsCmud= $5,000Crig= $800/hr  Ctools= $100Ctool rental= $100/hrCsupport= $200/hr 
  • 36. ()() bittoolsmudrigsupporttoolrentaltripbitlostdrillbitavgCCCCCCTTTCTROP +++++++= ×()()3,0001005,00080020010063003035drillC+++++++= ×8,10039,6001,050drillC+ = $45.43/ftdrillC=
  • 37. Example2 –Breakeven calculation  When planning a well. It has been determined that the next section requires a polymer mud that costs $15/bbl. The rig has inefficient shale shakers, which the drilling contractor will not replace without sharing the expense. How much should the operator be prepared to pay for the installation of the new, high- efficiency shale shakers if the rig is to be used for only a single well?  Old shale shaker solid control efficiency = 65%  New shale shaker solid control efficiency = 75%  Anticipated average hole diameter = 13”  Maximum allowable drill solids concentration = 6%
  • 38.  We use mud interval cost equation:  Cmud= cost of mud to drill the interval, $  Lint= length of interval, ft  Cmud/bbl= mud cost, $/bbl  Dh= average hole diameter, in.  Eff = efficiency of solids control system, %  Sactive= drilled solids in active mud, volume % ()()2hactivemudintmud/bblactiveD1Eff1SCLC1,029S −− =××
  • 39.  For the existing shale shakers: ()()2mud1310.6510.06C6,000151,0290.06 −− =×× mudC6,000150.9006=××mudC$81,051=
  • 40.  If new shale shakers were purchased:  Ecost= equipment cost, $ ()()2mudcost1310.7510.06C6,00015E1,0290.06 −− =×+× mudcostC57,894E=+ ()()2h activemudintmud/bblcostactiveD1Eff1SCLCE1,029S −− =×+×
  • 41.  Breakeven occurs when the cost of existing shakers equals the cost of new shakers.  This value ($23,157) represents the mostthe operator should pay for the installation of new shakers.  Any amount less that this can be negotiated with the drilling contractor represents a net savings. cost81,05157,894E=+ costE$23,157=
  • 42. Example3 –EVcalculation  When drilling 12-1/4” hole in an area, experience shows that a reverse circulating junk basket (RCJB) is required on 25% of all wells. The average rental period for wells where a RCJB is required is 3 days, and 12 hours rig time is wasted waiting for the equipment.  A rig is contracted for a single well in which the 12- 1/4” section is planned to take 25 days to drill.  Given: Rig rate = $8,000/day RCJB rental = $150 first day plus $25/day thereafter  Would it be advantageous to have RCJB on standby at the rigsite:
  • 43.  We use the EV method and decision tree. RCJB rented RCJB not rented Required Not required
  • 44.  RCJB not rented  Not required  Required Rig rateInterval time×8,00025=×$200,000= ()[]Rig rateInterval timeWaiting timeRCJB rentalRental time×+++ ()()8,000250.5150252=×+++×$204,200=
  • 45.  RCJB on standby ()()Rig rateInterval timeRCJB rentalInterval time×++ $200,750= ()()8,000251502524=×++×
  • 46. RCJB rented RCJB not rented Required Not required C = $200,000 P = 75% EV = 200,000 x 0.75 EV = $150,000 C = $204,200 P = 25% EV = 204,200 x 0.25 EV = $51,050 C = $200,750 P = 100% EV = 200,750 x 1.00 EV = $200,750
  • 47. RCJB not rented Total EV = $150,000 + $51,050 = $201,050 RCJB on standby Total EV = $200,750  RCJB on standby < RCJB not rented  Therefore, the better economic solution is to have the RCJB on standby at the rigsite.