Scaling the Benefits of Kanban
Copyright Lean Kanban Inc.dja@leankanban.com @lki_dja
Enterprise Services Planning
Copyright Lean Kanban Inc.dja@leankanban.com @lki_dja
You are part of a professional services business!
An ecosystem of
professionals
providing
interdependent
services, often with
complex
dependencies.
Professional
Service
organizations
build intangible
goods
Copyright Lean Kanban Inc.dja@leankanban.com @lki_dja
The challenge of professional services businesses
A constantly changing
external environment
has a ripple effect
across your entire
business ecosystem
Priorities change and
required capability & service
levels rise in response to
competition, disruptive
market innovation &
changes in customer tastes
Copyright Lean Kanban Inc.dja@leankanban.com @lki_dja
What should
we start next?
Will it be
delivered when
we need it?
Do we have
capacity to do
everything we
need to do?
Copyright Lean Kanban Inc.dja@leankanban.com @lki_dja
How will
dependencies
affect our ability
to deliver?
How many
activities should
we have running
in parallel?
If we delay starting something,
will the capacity be available
when we need it?
Copyright Lean Kanban Inc.dja@leankanban.com @lki_dja
Demand
Observed
Capability
Demand
Demand
Observed
Capability
Observed
Capability
ESP – Anticipating Demand, Allocating Capacity
Looking downstream, you
want the system to help
you anticipate and
manage dependencies
Copyright Lean Kanban Inc.dja@leankanban.com @lki_dja
ESP – Anticipating Demand, Allocating Capacity
Demand
Observed
Capability
Demand
Demand
Observed
Capability
Observed
Capability
Looking upstream, you want the
system to help you anticipate and
manage demand
Copyright Lean Kanban Inc.dja@leankanban.com @lki_dja
Demand
Observed
Capability
Demand
Demand
Observed
Capability
Observed
Capability
ESP – Anticipating Demand, Allocating Capacity
Combine the two, and
across the organization
you smooth flow end-
to-end and help keep
demand in balance with
overall system capability
Copyright Lean Kanban Inc.dja@leankanban.com @lki_dja
Enterprise Services Planning
*Kanban is a way to organize and manage work. It improves
service delivery speed & predictability through a combination of
limiting work-in-progress & deferred commitment
It uses visual management and Lean techniques such as limiting
the amount of work in progress, and probabilistic forecasting.
Kanban helps to balance demand with capability.
Balancing demand and capability = improved flow.
Improved flow = Improved predictability.
Enterprise Services Planning (ESP) is an enterprise-wide
management solution that leverages Kanban*
to improve each service within your business.
Copyright Lean Kanban Inc.dja@leankanban.com @lki_dja
The goal of Enterprise Services Planning
The goal of
Enterprise Services Planning
is to achieve...
The Right Things
At The Right Time
Done The Right Way
With Appropriate Risk
Exposure
Copyright Lean Kanban Inc.dja@leankanban.com @lki_dja
Enterprise Services Planning
Manufacturing
1947 – Kanban
1964 & 1975 – MRP
Professional Services
2004 – Kanban
2015 – ESP
ESP is “MRP for professional
services”. ESP is for managing
capacity & scheduling intangible
work
Copyright Lean Kanban Inc.dja@leankanban.com @lki_dja
Enterprise Services Planning
Planning involves…
Scheduling
Sequencing
Selecting
Commitment
Anticipating & Managing
Dependencies
Risk Management
Understanding what is
essential based on…
 Business strategy
 Fitness for purpose
Copyright Lean Kanban Inc.dja@leankanban.com @lki_dja
Risk Assessment
(for scheduling, sequencing, & selection)
Copyright Lean Kanban Inc.dja@leankanban.com @lki_dja
Qualitative Taxonomies
2 -> 6 categories
Fact-based
Cheap
Fast
Accurate
Consensus Forming
Managed Risk
Heterogeneous
Expensive
Time Consuming
Fake Precision?
May still be
High Risk
Homogenous
Cheap
Fast
High Risk
A middle-ground in effective Risk Management
Copyright Lean Kanban Inc.dja@leankanban.com @lki_dja
Sketch market utility functionRoomnights
soldperday
Actual rooms sold
Cost of delay
Estimated additional
rooms sold
When we need it When it arrived
Cost of delay for an online Easter holiday marketing promotion
is difference in integral between the two curves
time
Copyright Lean Kanban Inc.dja@leankanban.com @lki_dja
Cost of Delay based on utility function sketches
Cost of delay function for an online Easter holiday marketing
campaign delayed by 1 month from mid-January
(based on diff of 2 integrals on previous slide)
Treat as a Standard Class item
time
impact
Total cost
of delay
Copyright Lean Kanban Inc.dja@leankanban.com @lki_dja
Utility Function Taxonomy
Front-loaded – Most of the value is
realized early in the lifespan of the
product with a long residual tail
Utility Function Shape
Bell curve – Most of the value is
realized in the middle of the lifespan
with slow initial uptake and a
somewhat symmetrical tail off
Back-loaded – Initial take-up is slow
with value realized close to a natural
end-date in the product lifespan
Copyright Lean Kanban Inc.dja@leankanban.com @lki_dja
Visualize Risks to provide Scheduling Information
TS
Market Risk
CR
Spoil
Diff
Lifecycle
Cost of Delay
Tech Risk
Delay Impact
New
Mid
Cow
Expedite
FD
Std
Intangible
ELE
Maj. Cap.
Disc
Unknown Soln
Known but not us
Done it before
Commodity
Risk profile for
a work item or
project
Outside:
Commit Early
Inside:
Commit Late
Items with the same shape carry the
same risks. They cannot be prioritized or
sequenced. From a group of items with
the same risk profile pick whichever
ones you like.
It is also wise to hedge risk by
allocating capacity in the system for
items of different risk profiles.
Copyright Lean Kanban Inc.dja@leankanban.com @lki_dja
Scheduling & Sequencing
TS
Market Risk
CR
Spoil
Diff
Lifecycle
Cost of Delay
Tech Risk
Delay Impact
New
Mid
Cow
Expedite
FD
Std
Intangible
ELE
Maj. Cap.
Disc
Unknown Soln
Known but not us
Done it before
Commodity
Sequence:
1st
Sequence:
3rd
Sequence:
2nd
If only real life was so simple!
Copyright Lean Kanban Inc.dja@leankanban.com @lki_dja
Custom Profile Contains Narrative
Our CEO has
requested we
do the blue
project. Which
one do we
postpone?
The purple
project is
important but
can be delayed
with little
penalty.
Copyright Lean Kanban Inc.dja@leankanban.com @lki_dja
Inherent Risk, Risk of Rework & Sequencing
MarketRisk
Scheduling
High risk
of change
or rework
Low risk
of change
or rework
Can
Commit
Early
Should be
deferred
Differentiators
Spoilers
Table Stakes
Cost Reducers
Regulatory
Defer until later
only incurs
opportunity cost
penalty
Deferring
tables stakes
may mean
foregoing
differentiators
or starting
early and
paying cost of
rework
InherentRisk
RiskofRework
Sequencing
Copyright Lean Kanban Inc.dja@leankanban.com @lki_dja
Revisiting the portfolio options
There is a low
penalty to
deferring the
purple project
compared to
alternatives
The purple
project remains
important. We
may need to
forgo something
else later in
order to insure
it is completed
Copyright Lean Kanban Inc.dja@leankanban.com @lki_dja
Visualizing Inherent Risk
Diff
Market Risk
Spoil
CR
TS
Lifecycle
Cost of Delay
Tech Risk
Delay Impact
Cow
Mid
New
Expedite
FD
Std
Intangible
ELE
Maj. Cap.
Disc
Unknown Soln
Known but not us
Done it before
Commodity
Outside:
High Risk
Inside:
Low Risk
Some axes are reversed when we show
inherent risk in the project or feature
compared to its schedule risk.
If inherent risk is lower than
schedule risk then the project or
feature can be deferred
Where inherent risk is greater than
schedule risk. Deferring only works if
other information gathering is
happening creating an embedded
option
Copyright Lean Kanban Inc.dja@leankanban.com @lki_dja
Demand Shaping Threshold
Dimension 1
Dimension 2
Dimension 3
Dimension 5
Dimension 4
Definitely
Do
This
Demand shaping
threshold
Talk about
this one
Definitely
Don’t
This
Copyright Lean Kanban Inc.dja@leankanban.com @lki_dja
Forecasting
Copyright Lean Kanban Inc.dja@leankanban.com @lki_dja
Lead Time & Weibull Distributions
Lead time histograms
observed to be Weibull
distributions typically
with shape parameter
1.0 < k < 2.0
This example is a Weibull
distribution with a scale parameter
equal to 65 and shape parameter
equal to 1.4
Outliers with known special causes
at 87 & 105 are omitted from
the “best fit” curve
Copyright Lean Kanban Inc.dja@leankanban.com @lki_dja
ChangeRequests
SLA (customer expectation or fitness criteria)
60 days
Use Lead Time Distribution to Evaluate
Service Delivery Effectiveness
22-150 day
spread of variation
85%
on-time
15% late
Due Date
Performance
(DDP)
Predictability
Copyright Lean Kanban Inc.dja@leankanban.com @lki_dja
Forecasting methods
ESP relies on two types of forecasting approaches
 Reference class forecasting
 Monte Carlo simulation
Reference class forecasting requires an assumption
of an equilibrium – the near future will reflect the
continuing conditions of the recent past
 We sample data from a period in the recent past and use it
to forecast future behavior
 The sample period is determined by evaluating the
volatility in kanban system liquidity
Copyright Lean Kanban Inc.dja@leankanban.com @lki_dja
Scheduling
Copyright Lean Kanban Inc.dja@leankanban.com @lki_dja
When should we start something?
impact
When we
need it
85th
percentile
Ideal Start
Here
Commitment point
timeJan
10
Nov
11
If we start too early, we forgo the
option and opportunity to do
something else that may provide
value.
If we start too late we risk
incurring the cost of delay
If we pull the work into our kanban
system on Nov 11 we have a 6 out
of 7 chance of on-time delivery
Copyright Lean Kanban Inc.dja@leankanban.com @lki_dja
What is the latest we could start?
impact
When we
need it
0th percentile
Very late
start
Commitment point
timeJan
10
Dec
19
If we start as late as December 19
we have 0% chance of on-time
delivery
We have about a 10% chance of a
total loss delivering the promotion
beyond the expiry date of the
opportunity
85th percentile
total loss
Copyright Lean Kanban Inc.dja@leankanban.com @lki_dja
To be certain of delivery without incurring any
cost of delay is expensive
impact
When we
need it
98th
percentile
Early Start
Commitment point
timeJan
10
Aug
11
If we are conservative and do not
wish to carry any risk of late
delivery or any risk of incurring an
opportunity cost of delay, then we
must start as early as August 13th.
We must commit to our Spring
Break 2015 promotion during
Summer 2014!!!
Copyright Lean Kanban Inc.dja@leankanban.com @lki_dja
Window of opportunity
impact
When we
need it
Earliest Start
timeJan
10
Aug
11
Latest
viable
start
Dec
19
Optimal Start
Nov
11
On August 11st the item becomes
available for selection at Kanban
system replenishment.
The ideal time to start is November
11th.
After December 19th our option to
deliver this item expires and we
would discard it from our pool.
Copyright Lean Kanban Inc.dja@leankanban.com @lki_dja
Scaling out across the organization
Copyright Lean Kanban Inc.dja@leankanban.com @lki_dja
Treat each service separately
Demand
Observed
Capability
Demand
Demand
Observed
Capability
Observed
Capability
Copyright Lean Kanban Inc.dja@leankanban.com @lki_dja
STATIK
(Systems Thinking Approach to Introducing Kanban)
1. Understand what makes the service “fit for
purpose”
2. Understand sources of dissatisfaction
regarding current delivery
3. Analyze sources of and nature of demand
4. Analyze current delivery capability
5. Model the service delivery workflow
6. Identify & define classes of service
7. Design the kanban system
8. Socialize design & negotiate implementation
This process
tends to be
iterative
Identify Services. For each service…
Copyright Lean Kanban Inc.dja@leankanban.com @lki_dja
The Kanban Method
Scaling Principles
1. Scale out in a service-oriented fashion one service
at a time
2. Design each kanban system from first principles
using STATIK, do not attempt to design a grand
solution at enterprise scale
3. Use the Kanban Cadences as the management
system that enable balance, leading to better
enterprise services delivery
Copyright Lean Kanban Inc.dja@leankanban.com @lki_dja
Anticipating & Managing Dependencies
Copyright Lean Kanban Inc.dja@leankanban.com @lki_dja
Some systems have dependencies on others
Demand
Observed
Capability
Demand
Demand
Observed
Capability
Observed
Capability
Looking
downstream,
you want the
system to help
you anticipate
and manage
dependencies
Copyright Lean Kanban Inc.dja@leankanban.com @lki_dja
Some systems have dependencies on others
Demand
Observed
Capability
Demand
Demand
Observed
Capability
Observed
Capability
Looking
upstream, you
want the system
to help you
anticipate and
manage demand
Copyright Lean Kanban Inc.dja@leankanban.com @lki_dja
Some systems have dependencies on others
Demand
Observed
Capability
Demand
Demand
Observed
Capability
Observed
Capability
Combine the
two, and across
the organization
you smooth
flow end-to-
end and help
keep demand in
balance with
overall system
capability
Copyright Lean Kanban Inc.dja@leankanban.com @lki_dja
Buffer dependencies, agree SLAs
5 4 43 2 2
...Input
Queue
Dev
Ready In Prog DoneDoneIn Prog
DevelopmentAnalysis Build
Ready Test
Release
Ready
Waiting on
External Group
Late against SLA
Dots denote clock
ticking on SLA
∞8
Unbounded
Queue
When the dependent service
becomes reliable &
predictable, we can use
Little’s Law to calculate a
WIP limit for the
dependency buffer
Copyright Lean Kanban Inc.dja@leankanban.com @lki_dja
Feedback Loops
Enable The Network To Evolve
Copyright Lean Kanban Inc.dja@leankanban.com @lki_dja
Strategy
Review
Risk
Review
Monthly
Service
Delivery
Review
Bi-WeeklyQuarterly
Kanban
Meeting
Daily
Operations
Review
Monthly
Replenishment/
Commitment
Meeting
Weekly
Delivery
Planning
Meeting
Per delivery cadence
change change
change
change
change
change
change change
change
info
info
info
info
info
info
info
info
info
change info
Kanban CadencesAre we doing things right?
Are we
doing
the right
thing?
Focus on Service Delivery
Copyright Lean Kanban Inc.dja@leankanban.com @lki_dja
Use feedback loops
to level capability across the network
Copyright Lean Kanban Inc.dja@leankanban.com @lki_dja
Visualizing Dependencies
Copyright Lean Kanban Inc.dja@leankanban.com @lki_dja
5 4 43 2 2
...Input
Queue
Dev
Ready In Prog DoneDoneIn Prog
DevelopmentAnalysis Build
Ready Test
Release
Ready
Waiting on
External Group
Late against SLA
Dots denote clock
ticking on SLA
∞8
Unbounded
Queue
Copyright Lean Kanban Inc.dja@leankanban.com @lki_dja
5 4 2
...Input
Queue In Prog DoneDoneIn Prog
DevAnalysis
System
Test Release
Ready
Dev
4
4
In Prog
Split
Integration
Point
Integration Dependencies
2
Integration
Test
Component1Component2
DoneIn Prog DoneIn Prog
Integration dependencies
should be managed like
small projects for the
components or sub-systems
with the integration point
being scheduled by backing
out integration cycle time
from the desired delivery
date
Integration points should be
treated as localized fixed
delivery dates, hence the
component or sub-system
has a fixed date.
Use project forecasting to
plan the component delivery
Cycle time
Copyright Lean Kanban Inc.dja@leankanban.com @lki_dja
Parent-child dependencies can be
represented with 2-tiered boards
Features
(parents)
Use
Stories
(children)
Copyright Lean Kanban Inc.dja@leankanban.com @lki_dja
Visualizing Dependencies at Posit Science
Dots depict
dependencies
Copyright Lean Kanban Inc.dja@leankanban.com @lki_dja
Visualize dependencies on tickets
Title
Graphic Design
Copy Writing
DBA
Customer Signoff
req
complete
Color of the ticket
May indicate
dependency on
shared services
J
Decorators
(Shape & Color)
(Letter)
SLA or
Target Date
May indicate service,
vendor or customer
dependencies
May be used to
indicate skill level
required
Start dd/mm/yyyy
dd/mm/yyyyDue
End
SIT date
Dates
Age (showing days blocked)
Can be used to
visualize integration
dependencies
Class of service
affected by
dependent request
Copyright Lean Kanban Inc.dja@leankanban.com @lki_dja
Definition of
Enterprise Services Planning
Copyright Lean Kanban Inc.dja@leankanban.com @lki_dja
Enterprise Services Planning
3 Organizational Steps
Foster a culture focused
on continual
fit-for-purpose service
delivery
Seeing Services
“Kanban” each service
Feedback Loop System
Identify interdependent services
in your organization
Use the STATIK method to create a
Kanban system for each service
Implement a set of responsive
feedback loops
Copyright Lean Kanban Inc.dja@leankanban.com @lki_dja
Enterprise Services Planning
Step 1: Seeing Services
Examples:
HR provides services throughout the organization, but they
also need services from IT
Marketing provides services to product development but they
need services from Sales and from IT
IT provides services to Customer Support. There is an
interdependency between Customer Support, QA, and IT
Engineering.
Different feature teams or product teams may have
dependencies on each other
Many groups are dependent upon specialist individuals
Copyright Lean Kanban Inc.dja@leankanban.com @lki_dja
Enterprise Services Planning
Step 2: Kanban the Services
Use STATIK (Systems Thinking Approach to
Implementing Kanban) for each identified service…
1. Understand what makes the service “fit for purpose”
2. Understand sources of dissatisfaction regarding current
delivery
3. Analyze sources of and nature of demand
4. Analyze current delivery capability
5. Model the service delivery workflow
6. Identify & define classes of service
7. Design the kanban system
8. Socialize design & negotiate implementation
Copyright Lean Kanban Inc.dja@leankanban.com @lki_dja
Enterprise Services Planning
Step 3: Responsive Feedback Loops
Strategy
Review
Risk
Review
Monthly
Service
Delivery
Review
Bi-WeeklyQuarterly
Kanban
Meeting
Daily
Operations
Review
Monthly
Replenishment/
Commitment
Meeting
Weekly
Delivery
Planning
Meeting
Per delivery cadence
change change
change
change
change
change
change change
change
info
info
info
info
info
info
info
info
info
change info
Copyright Lean Kanban Inc.dja@leankanban.com @lki_dja
Illustrates 4 Functions of Management in ESP
Strategy
Review
Risk
Review
Monthly
Service
Delivery
Review
Bi-WeeklyQuarterly
Kanban
Meeting
Daily
Operations
Review
Monthly
Replenishment/
Commitment
Meeting
Weekly
Delivery
Planning
Meeting
Per delivery cadence
change change
change
change
change
change
change change
change
info
info
info
info
info
info
info
info
info
change info
Focus on Service Delivery
Driving improvement…
Higher level
management function
Copyright Lean Kanban Inc.dja@leankanban.com @lki_dja
Enterprise Services Planning
Achieve “Fitness for Purpose”
Product component
(capability/brand/non-
functional elements)
Service delivery component
demand /customer expectations/
customer satisfaction)
+
These must be balanced to deliver what your
customers need and expect: to be “fit for purpose”
Copyright Lean Kanban Inc.dja@leankanban.com @lki_dja
Summary
Copyright Lean Kanban Inc.dja@leankanban.com @lki_dja
Enterprise Services Planning Curriculum
Copyright Lean Kanban Inc.dja@leankanban.com @lki_dja
Enterprise Services Planning
Planning involves…
Scheduling
Sequencing
Selecting
Commitment
Anticipating & Managing
Dependencies
Risk Management
Understanding what is
essential based on…
 Business strategy
 Fitness for purpose
Copyright Lean Kanban Inc.dja@leankanban.com @lki_dja
Enterprise Services Planning
The Right Things
At The Right Time
Done The Right Way
With Appropriate Risk
Exposure
Copyright Lean Kanban Inc.dja@leankanban.com @lki_dja
Copyright Lean Kanban Inc.dja@leankanban.com @lki_dja
Thank you!
Copyright Lean Kanban Inc.dja@leankanban.com @lki_dja
About
David Anderson is an innovator in
management of 21st Century
businesses that employ creative
people who “think for a living” . He
leads a training, consulting,
publishing and event planning
business dedicated to developing,
promoting and implementing new
management thinking & methods…
He has 30+ years experience in the high technology industry
starting with computer games in the early 1980’s. He has
led software organizations delivering superior productivity
and quality using innovative methods at large companies such
as Sprint and Motorola.
David defined Enterprise Services Planning and originated
Kanban Method an adaptive approach to improved service
delivery. His latest book, published in June 2012, is, Lessons
in Agile Management – On the Road to Kanban.
David is Chairman & CEO of Lean Kanban Inc., a business
operating globally, dedicated to providing quality training &
events to bring Kanban and Enterprise Services Planning to
businesses who employ those who must “think for a living.”
Copyright Lean Kanban Inc.dja@leankanban.com @lki_dja
Risk profile courtesy of BazaarVoice
Acknowledgements
Copyright Lean Kanban Inc.dja@leankanban.com @lki_dja

Mais conteúdo relacionado

Mais procurados

Creating Resilient, Robust, & Antifragile Organizations
Creating Resilient, Robust, & Antifragile OrganizationsCreating Resilient, Robust, & Antifragile Organizations
Creating Resilient, Robust, & Antifragile OrganizationsDavid Anderson
 
Kanban & ESP - When are they appropriate?
Kanban & ESP - When are they appropriate?Kanban & ESP - When are they appropriate?
Kanban & ESP - When are they appropriate?David Anderson
 
Kanban's 3 Agendas (London Lean Kanban Day)
Kanban's 3 Agendas (London Lean Kanban Day)Kanban's 3 Agendas (London Lean Kanban Day)
Kanban's 3 Agendas (London Lean Kanban Day)David Anderson
 
David Anderson, Enterprise Service Planning – Масштабирование преимуществ Kanban
David Anderson, Enterprise Service Planning – Масштабирование преимуществ KanbanDavid Anderson, Enterprise Service Planning – Масштабирование преимуществ Kanban
David Anderson, Enterprise Service Planning – Масштабирование преимуществ KanbanScrumTrek
 
Getting to pull at enterprise scale
Getting to pull at enterprise scaleGetting to pull at enterprise scale
Getting to pull at enterprise scaleDavid Anderson
 
Social engineering with in for kanban
Social engineering with in for kanbanSocial engineering with in for kanban
Social engineering with in for kanbanDavid Anderson
 
Creating Robust, Resilient & Antifragile Organizations (using Kanban)
Creating Robust, Resilient & Antifragile Organizations (using Kanban)Creating Robust, Resilient & Antifragile Organizations (using Kanban)
Creating Robust, Resilient & Antifragile Organizations (using Kanban)David Anderson
 
Key Note - Lean Kanban North America 2013 - Beyond Kanban
Key Note - Lean Kanban North America 2013 - Beyond KanbanKey Note - Lean Kanban North America 2013 - Beyond Kanban
Key Note - Lean Kanban North America 2013 - Beyond KanbanDavid Anderson
 
Enterprise Services Planning - Scaling the Benefits of Kanban
Enterprise Services Planning - Scaling the Benefits of KanbanEnterprise Services Planning - Scaling the Benefits of Kanban
Enterprise Services Planning - Scaling the Benefits of KanbanDavid Anderson
 
Making Better Decisions - understanding "fitness for purpose", matching strat...
Making Better Decisions - understanding "fitness for purpose", matching strat...Making Better Decisions - understanding "fitness for purpose", matching strat...
Making Better Decisions - understanding "fitness for purpose", matching strat...David Anderson
 
Kanban - follow your own path to agility
Kanban - follow your own path to agilityKanban - follow your own path to agility
Kanban - follow your own path to agilityDavid Anderson
 
Just say #no____ the altenative path to enterprise agility
Just say #no____ the altenative path to enterprise agilityJust say #no____ the altenative path to enterprise agility
Just say #no____ the altenative path to enterprise agilityDavid Anderson
 
Patterns of Kanban Maturity
Patterns of Kanban MaturityPatterns of Kanban Maturity
Patterns of Kanban MaturityDavid Anderson
 
Kanban Cadences & Information Flow
Kanban Cadences & Information FlowKanban Cadences & Information Flow
Kanban Cadences & Information FlowDavid Anderson
 
10 Years of Kanban - What have we learned
10 Years of Kanban - What have we learned10 Years of Kanban - What have we learned
10 Years of Kanban - What have we learnedDavid Anderson
 
Social engineering with in for kanban
Social engineering with in for kanbanSocial engineering with in for kanban
Social engineering with in for kanbanDavid Anderson
 
Kanban - the alternative path to agility
Kanban - the alternative path to agilityKanban - the alternative path to agility
Kanban - the alternative path to agilityDavid Anderson
 
Key Note - Lean Agile Scotland - Individually Smart, Collectively Stupid!
Key Note - Lean Agile Scotland - Individually Smart, Collectively Stupid!Key Note - Lean Agile Scotland - Individually Smart, Collectively Stupid!
Key Note - Lean Agile Scotland - Individually Smart, Collectively Stupid!David Anderson
 
Kanban - an alternative path to agility (Agile Camp Silicon Valley)
Kanban - an alternative path to agility (Agile Camp Silicon Valley)Kanban - an alternative path to agility (Agile Camp Silicon Valley)
Kanban - an alternative path to agility (Agile Camp Silicon Valley)David Anderson
 

Mais procurados (20)

Creating Resilient, Robust, & Antifragile Organizations
Creating Resilient, Robust, & Antifragile OrganizationsCreating Resilient, Robust, & Antifragile Organizations
Creating Resilient, Robust, & Antifragile Organizations
 
Kanban & ESP - When are they appropriate?
Kanban & ESP - When are they appropriate?Kanban & ESP - When are they appropriate?
Kanban & ESP - When are they appropriate?
 
Kanban's 3 Agendas (London Lean Kanban Day)
Kanban's 3 Agendas (London Lean Kanban Day)Kanban's 3 Agendas (London Lean Kanban Day)
Kanban's 3 Agendas (London Lean Kanban Day)
 
David Anderson, Enterprise Service Planning – Масштабирование преимуществ Kanban
David Anderson, Enterprise Service Planning – Масштабирование преимуществ KanbanDavid Anderson, Enterprise Service Planning – Масштабирование преимуществ Kanban
David Anderson, Enterprise Service Planning – Масштабирование преимуществ Kanban
 
Getting to pull at enterprise scale
Getting to pull at enterprise scaleGetting to pull at enterprise scale
Getting to pull at enterprise scale
 
Social engineering with in for kanban
Social engineering with in for kanbanSocial engineering with in for kanban
Social engineering with in for kanban
 
Creating Robust, Resilient & Antifragile Organizations (using Kanban)
Creating Robust, Resilient & Antifragile Organizations (using Kanban)Creating Robust, Resilient & Antifragile Organizations (using Kanban)
Creating Robust, Resilient & Antifragile Organizations (using Kanban)
 
Key Note - Lean Kanban North America 2013 - Beyond Kanban
Key Note - Lean Kanban North America 2013 - Beyond KanbanKey Note - Lean Kanban North America 2013 - Beyond Kanban
Key Note - Lean Kanban North America 2013 - Beyond Kanban
 
Enterprise Services Planning - Scaling the Benefits of Kanban
Enterprise Services Planning - Scaling the Benefits of KanbanEnterprise Services Planning - Scaling the Benefits of Kanban
Enterprise Services Planning - Scaling the Benefits of Kanban
 
Making Better Decisions - understanding "fitness for purpose", matching strat...
Making Better Decisions - understanding "fitness for purpose", matching strat...Making Better Decisions - understanding "fitness for purpose", matching strat...
Making Better Decisions - understanding "fitness for purpose", matching strat...
 
Fitness For Purpose
Fitness For PurposeFitness For Purpose
Fitness For Purpose
 
Kanban - follow your own path to agility
Kanban - follow your own path to agilityKanban - follow your own path to agility
Kanban - follow your own path to agility
 
Just say #no____ the altenative path to enterprise agility
Just say #no____ the altenative path to enterprise agilityJust say #no____ the altenative path to enterprise agility
Just say #no____ the altenative path to enterprise agility
 
Patterns of Kanban Maturity
Patterns of Kanban MaturityPatterns of Kanban Maturity
Patterns of Kanban Maturity
 
Kanban Cadences & Information Flow
Kanban Cadences & Information FlowKanban Cadences & Information Flow
Kanban Cadences & Information Flow
 
10 Years of Kanban - What have we learned
10 Years of Kanban - What have we learned10 Years of Kanban - What have we learned
10 Years of Kanban - What have we learned
 
Social engineering with in for kanban
Social engineering with in for kanbanSocial engineering with in for kanban
Social engineering with in for kanban
 
Kanban - the alternative path to agility
Kanban - the alternative path to agilityKanban - the alternative path to agility
Kanban - the alternative path to agility
 
Key Note - Lean Agile Scotland - Individually Smart, Collectively Stupid!
Key Note - Lean Agile Scotland - Individually Smart, Collectively Stupid!Key Note - Lean Agile Scotland - Individually Smart, Collectively Stupid!
Key Note - Lean Agile Scotland - Individually Smart, Collectively Stupid!
 
Kanban - an alternative path to agility (Agile Camp Silicon Valley)
Kanban - an alternative path to agility (Agile Camp Silicon Valley)Kanban - an alternative path to agility (Agile Camp Silicon Valley)
Kanban - an alternative path to agility (Agile Camp Silicon Valley)
 

Semelhante a Scaling the Benefits of Kanban with Enterprise Services Planning

Enterprise Services Planning - Scaling the Benefits of Kanban
Enterprise Services Planning - Scaling the Benefits of KanbanEnterprise Services Planning - Scaling the Benefits of Kanban
Enterprise Services Planning - Scaling the Benefits of KanbanDavid Anderson
 
Key Note - Smidig 2013 - Scaling Kanban in the Enterprise - Kanban's 3 Agendas
Key Note - Smidig 2013 - Scaling Kanban in the Enterprise - Kanban's 3 AgendasKey Note - Smidig 2013 - Scaling Kanban in the Enterprise - Kanban's 3 Agendas
Key Note - Smidig 2013 - Scaling Kanban in the Enterprise - Kanban's 3 AgendasDavid Anderson
 
Lean Kanban Netherlands 2012 - Lean Risk Management
Lean Kanban Netherlands 2012 - Lean Risk ManagementLean Kanban Netherlands 2012 - Lean Risk Management
Lean Kanban Netherlands 2012 - Lean Risk ManagementDavid Anderson
 
Kanban Cadences and Information Flow
Kanban Cadences and Information FlowKanban Cadences and Information Flow
Kanban Cadences and Information FlowJanice Linden-Reed
 
Lean Kanban India 2016 | Kanban Coaching for 2017 | Janice Lindeen Reed
Lean Kanban India 2016 | Kanban Coaching for 2017 | Janice Lindeen ReedLean Kanban India 2016 | Kanban Coaching for 2017 | Janice Lindeen Reed
Lean Kanban India 2016 | Kanban Coaching for 2017 | Janice Lindeen ReedLeanKanbanIndia
 
Key Note - DoSE Berlin - Qualitative Risk Management
Key Note - DoSE Berlin -  Qualitative Risk ManagementKey Note - DoSE Berlin -  Qualitative Risk Management
Key Note - DoSE Berlin - Qualitative Risk ManagementDavid Anderson
 
Key Note - Stop Starting, Start Finishing 2013 - Aligning Creative Work with ...
Key Note - Stop Starting, Start Finishing 2013 - Aligning Creative Work with ...Key Note - Stop Starting, Start Finishing 2013 - Aligning Creative Work with ...
Key Note - Stop Starting, Start Finishing 2013 - Aligning Creative Work with ...David Anderson
 
The ROI of Scaling Agile - How to justify the investment in terms your CFO wi...
The ROI of Scaling Agile - How to justify the investment in terms your CFO wi...The ROI of Scaling Agile - How to justify the investment in terms your CFO wi...
The ROI of Scaling Agile - How to justify the investment in terms your CFO wi...Steve Elliott
 
TNG Big Tech Days - Qualitative beats Quantitative Risk Management
TNG Big Tech Days - Qualitative beats Quantitative Risk ManagementTNG Big Tech Days - Qualitative beats Quantitative Risk Management
TNG Big Tech Days - Qualitative beats Quantitative Risk ManagementDavid Anderson
 
Jira Service Desk for Internal Developer Support: It’s Not Just for IT Anymore!
Jira Service Desk for Internal Developer Support: It’s Not Just for IT Anymore!Jira Service Desk for Internal Developer Support: It’s Not Just for IT Anymore!
Jira Service Desk for Internal Developer Support: It’s Not Just for IT Anymore!Atlassian
 
Sap rebates by dilip sadh
Sap rebates by dilip sadhSap rebates by dilip sadh
Sap rebates by dilip sadhdilipsadh
 
Outcome-Driven Product Backlog Management by Mike Dwyer - Agile Maine Day 2016
Outcome-Driven Product Backlog Management by Mike Dwyer - Agile Maine Day 2016Outcome-Driven Product Backlog Management by Mike Dwyer - Agile Maine Day 2016
Outcome-Driven Product Backlog Management by Mike Dwyer - Agile Maine Day 2016agilemaine
 
Tale Of Two Transformations 2015
Tale Of Two Transformations 2015Tale Of Two Transformations 2015
Tale Of Two Transformations 2015Steven Martin
 
Key Note - Path to Agility 2013 - Kanban - the alternative path to agility
Key Note - Path to Agility 2013 - Kanban - the alternative path to agilityKey Note - Path to Agility 2013 - Kanban - the alternative path to agility
Key Note - Path to Agility 2013 - Kanban - the alternative path to agilityDavid Anderson
 
Key note - Lean Kanban Central Europe 2012 - Managing a Risky Business - Unde...
Key note - Lean Kanban Central Europe 2012 - Managing a Risky Business - Unde...Key note - Lean Kanban Central Europe 2012 - Managing a Risky Business - Unde...
Key note - Lean Kanban Central Europe 2012 - Managing a Risky Business - Unde...David Anderson
 
Customer Lifetime Value for Insurance Agents
Customer Lifetime Value for Insurance AgentsCustomer Lifetime Value for Insurance Agents
Customer Lifetime Value for Insurance AgentsScott Boren
 
070 170731 bookclub_kaizen - kaizen & suggestion system - kaizen & QCD
070 170731 bookclub_kaizen - kaizen & suggestion system - kaizen & QCD070 170731 bookclub_kaizen - kaizen & suggestion system - kaizen & QCD
070 170731 bookclub_kaizen - kaizen & suggestion system - kaizen & QCDLia s. Associates | Branding & Design
 
Portfolio prioritization with lean canvas
Portfolio prioritization with lean canvasPortfolio prioritization with lean canvas
Portfolio prioritization with lean canvasMike Caspar
 
Portfolio prioritization with lean canvas and value game
Portfolio prioritization with lean canvas and value gamePortfolio prioritization with lean canvas and value game
Portfolio prioritization with lean canvas and value gameBrad Swanson
 
Lean Kanban India 2015 | Integrating Kanban Scalability with High Collaborati...
Lean Kanban India 2015 | Integrating Kanban Scalability with High Collaborati...Lean Kanban India 2015 | Integrating Kanban Scalability with High Collaborati...
Lean Kanban India 2015 | Integrating Kanban Scalability with High Collaborati...LeanKanbanIndia
 

Semelhante a Scaling the Benefits of Kanban with Enterprise Services Planning (20)

Enterprise Services Planning - Scaling the Benefits of Kanban
Enterprise Services Planning - Scaling the Benefits of KanbanEnterprise Services Planning - Scaling the Benefits of Kanban
Enterprise Services Planning - Scaling the Benefits of Kanban
 
Key Note - Smidig 2013 - Scaling Kanban in the Enterprise - Kanban's 3 Agendas
Key Note - Smidig 2013 - Scaling Kanban in the Enterprise - Kanban's 3 AgendasKey Note - Smidig 2013 - Scaling Kanban in the Enterprise - Kanban's 3 Agendas
Key Note - Smidig 2013 - Scaling Kanban in the Enterprise - Kanban's 3 Agendas
 
Lean Kanban Netherlands 2012 - Lean Risk Management
Lean Kanban Netherlands 2012 - Lean Risk ManagementLean Kanban Netherlands 2012 - Lean Risk Management
Lean Kanban Netherlands 2012 - Lean Risk Management
 
Kanban Cadences and Information Flow
Kanban Cadences and Information FlowKanban Cadences and Information Flow
Kanban Cadences and Information Flow
 
Lean Kanban India 2016 | Kanban Coaching for 2017 | Janice Lindeen Reed
Lean Kanban India 2016 | Kanban Coaching for 2017 | Janice Lindeen ReedLean Kanban India 2016 | Kanban Coaching for 2017 | Janice Lindeen Reed
Lean Kanban India 2016 | Kanban Coaching for 2017 | Janice Lindeen Reed
 
Key Note - DoSE Berlin - Qualitative Risk Management
Key Note - DoSE Berlin -  Qualitative Risk ManagementKey Note - DoSE Berlin -  Qualitative Risk Management
Key Note - DoSE Berlin - Qualitative Risk Management
 
Key Note - Stop Starting, Start Finishing 2013 - Aligning Creative Work with ...
Key Note - Stop Starting, Start Finishing 2013 - Aligning Creative Work with ...Key Note - Stop Starting, Start Finishing 2013 - Aligning Creative Work with ...
Key Note - Stop Starting, Start Finishing 2013 - Aligning Creative Work with ...
 
The ROI of Scaling Agile - How to justify the investment in terms your CFO wi...
The ROI of Scaling Agile - How to justify the investment in terms your CFO wi...The ROI of Scaling Agile - How to justify the investment in terms your CFO wi...
The ROI of Scaling Agile - How to justify the investment in terms your CFO wi...
 
TNG Big Tech Days - Qualitative beats Quantitative Risk Management
TNG Big Tech Days - Qualitative beats Quantitative Risk ManagementTNG Big Tech Days - Qualitative beats Quantitative Risk Management
TNG Big Tech Days - Qualitative beats Quantitative Risk Management
 
Jira Service Desk for Internal Developer Support: It’s Not Just for IT Anymore!
Jira Service Desk for Internal Developer Support: It’s Not Just for IT Anymore!Jira Service Desk for Internal Developer Support: It’s Not Just for IT Anymore!
Jira Service Desk for Internal Developer Support: It’s Not Just for IT Anymore!
 
Sap rebates by dilip sadh
Sap rebates by dilip sadhSap rebates by dilip sadh
Sap rebates by dilip sadh
 
Outcome-Driven Product Backlog Management by Mike Dwyer - Agile Maine Day 2016
Outcome-Driven Product Backlog Management by Mike Dwyer - Agile Maine Day 2016Outcome-Driven Product Backlog Management by Mike Dwyer - Agile Maine Day 2016
Outcome-Driven Product Backlog Management by Mike Dwyer - Agile Maine Day 2016
 
Tale Of Two Transformations 2015
Tale Of Two Transformations 2015Tale Of Two Transformations 2015
Tale Of Two Transformations 2015
 
Key Note - Path to Agility 2013 - Kanban - the alternative path to agility
Key Note - Path to Agility 2013 - Kanban - the alternative path to agilityKey Note - Path to Agility 2013 - Kanban - the alternative path to agility
Key Note - Path to Agility 2013 - Kanban - the alternative path to agility
 
Key note - Lean Kanban Central Europe 2012 - Managing a Risky Business - Unde...
Key note - Lean Kanban Central Europe 2012 - Managing a Risky Business - Unde...Key note - Lean Kanban Central Europe 2012 - Managing a Risky Business - Unde...
Key note - Lean Kanban Central Europe 2012 - Managing a Risky Business - Unde...
 
Customer Lifetime Value for Insurance Agents
Customer Lifetime Value for Insurance AgentsCustomer Lifetime Value for Insurance Agents
Customer Lifetime Value for Insurance Agents
 
070 170731 bookclub_kaizen - kaizen & suggestion system - kaizen & QCD
070 170731 bookclub_kaizen - kaizen & suggestion system - kaizen & QCD070 170731 bookclub_kaizen - kaizen & suggestion system - kaizen & QCD
070 170731 bookclub_kaizen - kaizen & suggestion system - kaizen & QCD
 
Portfolio prioritization with lean canvas
Portfolio prioritization with lean canvasPortfolio prioritization with lean canvas
Portfolio prioritization with lean canvas
 
Portfolio prioritization with lean canvas and value game
Portfolio prioritization with lean canvas and value gamePortfolio prioritization with lean canvas and value game
Portfolio prioritization with lean canvas and value game
 
Lean Kanban India 2015 | Integrating Kanban Scalability with High Collaborati...
Lean Kanban India 2015 | Integrating Kanban Scalability with High Collaborati...Lean Kanban India 2015 | Integrating Kanban Scalability with High Collaborati...
Lean Kanban India 2015 | Integrating Kanban Scalability with High Collaborati...
 

Último

Choosing the best strategy qspm matrix.pptx
Choosing the best strategy qspm matrix.pptxChoosing the best strategy qspm matrix.pptx
Choosing the best strategy qspm matrix.pptxMadan Karki
 
Mind Mapping: A Visual Approach to Organize Ideas and Thoughts
Mind Mapping: A Visual Approach to Organize Ideas and ThoughtsMind Mapping: A Visual Approach to Organize Ideas and Thoughts
Mind Mapping: A Visual Approach to Organize Ideas and ThoughtsCIToolkit
 
From Red to Green: Enhancing Decision-Making with Traffic Light Assessment
From Red to Green: Enhancing Decision-Making with Traffic Light AssessmentFrom Red to Green: Enhancing Decision-Making with Traffic Light Assessment
From Red to Green: Enhancing Decision-Making with Traffic Light AssessmentCIToolkit
 
Beyond the Five Whys: Exploring the Hierarchical Causes with the Why-Why Diagram
Beyond the Five Whys: Exploring the Hierarchical Causes with the Why-Why DiagramBeyond the Five Whys: Exploring the Hierarchical Causes with the Why-Why Diagram
Beyond the Five Whys: Exploring the Hierarchical Causes with the Why-Why DiagramCIToolkit
 
The Final Activity in Project Management
The Final Activity in Project ManagementThe Final Activity in Project Management
The Final Activity in Project ManagementCIToolkit
 
Shaping Organizational Culture Beyond Wishful Thinking
Shaping Organizational Culture Beyond Wishful ThinkingShaping Organizational Culture Beyond Wishful Thinking
Shaping Organizational Culture Beyond Wishful ThinkingGiuseppe De Simone
 
Effective learning in the Age of Hybrid Work - Agile Saturday Tallinn 2024
Effective learning in the Age of Hybrid Work - Agile Saturday Tallinn 2024Effective learning in the Age of Hybrid Work - Agile Saturday Tallinn 2024
Effective learning in the Age of Hybrid Work - Agile Saturday Tallinn 2024Giuseppe De Simone
 
Unlocking Productivity and Personal Growth through the Importance-Urgency Matrix
Unlocking Productivity and Personal Growth through the Importance-Urgency MatrixUnlocking Productivity and Personal Growth through the Importance-Urgency Matrix
Unlocking Productivity and Personal Growth through the Importance-Urgency MatrixCIToolkit
 
Paired Comparison Analysis: A Practical Tool for Evaluating Options and Prior...
Paired Comparison Analysis: A Practical Tool for Evaluating Options and Prior...Paired Comparison Analysis: A Practical Tool for Evaluating Options and Prior...
Paired Comparison Analysis: A Practical Tool for Evaluating Options and Prior...CIToolkit
 
Simplifying Complexity: How the Four-Field Matrix Reshapes Thinking
Simplifying Complexity: How the Four-Field Matrix Reshapes ThinkingSimplifying Complexity: How the Four-Field Matrix Reshapes Thinking
Simplifying Complexity: How the Four-Field Matrix Reshapes ThinkingCIToolkit
 
How-How Diagram: A Practical Approach to Problem Resolution
How-How Diagram: A Practical Approach to Problem ResolutionHow-How Diagram: A Practical Approach to Problem Resolution
How-How Diagram: A Practical Approach to Problem ResolutionCIToolkit
 
THE LEADERSHIP TO CHANGE THE WOLRD THIS IS YOUR HOUR PURSUES YOUR GIFT, TALEN...
THE LEADERSHIP TO CHANGE THE WOLRD THIS IS YOUR HOUR PURSUES YOUR GIFT, TALEN...THE LEADERSHIP TO CHANGE THE WOLRD THIS IS YOUR HOUR PURSUES YOUR GIFT, TALEN...
THE LEADERSHIP TO CHANGE THE WOLRD THIS IS YOUR HOUR PURSUES YOUR GIFT, TALEN...PROF. PAUL ALLIEU KAMARA
 
Farmer Representative Organization in Lucknow | Rashtriya Kisan Manch
Farmer Representative Organization in Lucknow | Rashtriya Kisan ManchFarmer Representative Organization in Lucknow | Rashtriya Kisan Manch
Farmer Representative Organization in Lucknow | Rashtriya Kisan ManchRashtriya Kisan Manch
 
Chapter 1 Performance Management HRM.ppt
Chapter 1 Performance Management HRM.pptChapter 1 Performance Management HRM.ppt
Chapter 1 Performance Management HRM.ppt2020102713
 
原版1:1复刻密西西比大学毕业证Mississippi毕业证留信学历认证
原版1:1复刻密西西比大学毕业证Mississippi毕业证留信学历认证原版1:1复刻密西西比大学毕业证Mississippi毕业证留信学历认证
原版1:1复刻密西西比大学毕业证Mississippi毕业证留信学历认证jdkhjh
 
Measuring True Process Yield using Robust Yield Metrics
Measuring True Process Yield using Robust Yield MetricsMeasuring True Process Yield using Robust Yield Metrics
Measuring True Process Yield using Robust Yield MetricsCIToolkit
 
Digital PR Summit - Leadership Lessons: Myths, Mistakes, & Toxic Traits
Digital PR Summit - Leadership Lessons: Myths, Mistakes, & Toxic TraitsDigital PR Summit - Leadership Lessons: Myths, Mistakes, & Toxic Traits
Digital PR Summit - Leadership Lessons: Myths, Mistakes, & Toxic TraitsHannah Smith
 
From Goals to Actions: Uncovering the Key Components of Improvement Roadmaps
From Goals to Actions: Uncovering the Key Components of Improvement RoadmapsFrom Goals to Actions: Uncovering the Key Components of Improvement Roadmaps
From Goals to Actions: Uncovering the Key Components of Improvement RoadmapsCIToolkit
 

Último (18)

Choosing the best strategy qspm matrix.pptx
Choosing the best strategy qspm matrix.pptxChoosing the best strategy qspm matrix.pptx
Choosing the best strategy qspm matrix.pptx
 
Mind Mapping: A Visual Approach to Organize Ideas and Thoughts
Mind Mapping: A Visual Approach to Organize Ideas and ThoughtsMind Mapping: A Visual Approach to Organize Ideas and Thoughts
Mind Mapping: A Visual Approach to Organize Ideas and Thoughts
 
From Red to Green: Enhancing Decision-Making with Traffic Light Assessment
From Red to Green: Enhancing Decision-Making with Traffic Light AssessmentFrom Red to Green: Enhancing Decision-Making with Traffic Light Assessment
From Red to Green: Enhancing Decision-Making with Traffic Light Assessment
 
Beyond the Five Whys: Exploring the Hierarchical Causes with the Why-Why Diagram
Beyond the Five Whys: Exploring the Hierarchical Causes with the Why-Why DiagramBeyond the Five Whys: Exploring the Hierarchical Causes with the Why-Why Diagram
Beyond the Five Whys: Exploring the Hierarchical Causes with the Why-Why Diagram
 
The Final Activity in Project Management
The Final Activity in Project ManagementThe Final Activity in Project Management
The Final Activity in Project Management
 
Shaping Organizational Culture Beyond Wishful Thinking
Shaping Organizational Culture Beyond Wishful ThinkingShaping Organizational Culture Beyond Wishful Thinking
Shaping Organizational Culture Beyond Wishful Thinking
 
Effective learning in the Age of Hybrid Work - Agile Saturday Tallinn 2024
Effective learning in the Age of Hybrid Work - Agile Saturday Tallinn 2024Effective learning in the Age of Hybrid Work - Agile Saturday Tallinn 2024
Effective learning in the Age of Hybrid Work - Agile Saturday Tallinn 2024
 
Unlocking Productivity and Personal Growth through the Importance-Urgency Matrix
Unlocking Productivity and Personal Growth through the Importance-Urgency MatrixUnlocking Productivity and Personal Growth through the Importance-Urgency Matrix
Unlocking Productivity and Personal Growth through the Importance-Urgency Matrix
 
Paired Comparison Analysis: A Practical Tool for Evaluating Options and Prior...
Paired Comparison Analysis: A Practical Tool for Evaluating Options and Prior...Paired Comparison Analysis: A Practical Tool for Evaluating Options and Prior...
Paired Comparison Analysis: A Practical Tool for Evaluating Options and Prior...
 
Simplifying Complexity: How the Four-Field Matrix Reshapes Thinking
Simplifying Complexity: How the Four-Field Matrix Reshapes ThinkingSimplifying Complexity: How the Four-Field Matrix Reshapes Thinking
Simplifying Complexity: How the Four-Field Matrix Reshapes Thinking
 
How-How Diagram: A Practical Approach to Problem Resolution
How-How Diagram: A Practical Approach to Problem ResolutionHow-How Diagram: A Practical Approach to Problem Resolution
How-How Diagram: A Practical Approach to Problem Resolution
 
THE LEADERSHIP TO CHANGE THE WOLRD THIS IS YOUR HOUR PURSUES YOUR GIFT, TALEN...
THE LEADERSHIP TO CHANGE THE WOLRD THIS IS YOUR HOUR PURSUES YOUR GIFT, TALEN...THE LEADERSHIP TO CHANGE THE WOLRD THIS IS YOUR HOUR PURSUES YOUR GIFT, TALEN...
THE LEADERSHIP TO CHANGE THE WOLRD THIS IS YOUR HOUR PURSUES YOUR GIFT, TALEN...
 
Farmer Representative Organization in Lucknow | Rashtriya Kisan Manch
Farmer Representative Organization in Lucknow | Rashtriya Kisan ManchFarmer Representative Organization in Lucknow | Rashtriya Kisan Manch
Farmer Representative Organization in Lucknow | Rashtriya Kisan Manch
 
Chapter 1 Performance Management HRM.ppt
Chapter 1 Performance Management HRM.pptChapter 1 Performance Management HRM.ppt
Chapter 1 Performance Management HRM.ppt
 
原版1:1复刻密西西比大学毕业证Mississippi毕业证留信学历认证
原版1:1复刻密西西比大学毕业证Mississippi毕业证留信学历认证原版1:1复刻密西西比大学毕业证Mississippi毕业证留信学历认证
原版1:1复刻密西西比大学毕业证Mississippi毕业证留信学历认证
 
Measuring True Process Yield using Robust Yield Metrics
Measuring True Process Yield using Robust Yield MetricsMeasuring True Process Yield using Robust Yield Metrics
Measuring True Process Yield using Robust Yield Metrics
 
Digital PR Summit - Leadership Lessons: Myths, Mistakes, & Toxic Traits
Digital PR Summit - Leadership Lessons: Myths, Mistakes, & Toxic TraitsDigital PR Summit - Leadership Lessons: Myths, Mistakes, & Toxic Traits
Digital PR Summit - Leadership Lessons: Myths, Mistakes, & Toxic Traits
 
From Goals to Actions: Uncovering the Key Components of Improvement Roadmaps
From Goals to Actions: Uncovering the Key Components of Improvement RoadmapsFrom Goals to Actions: Uncovering the Key Components of Improvement Roadmaps
From Goals to Actions: Uncovering the Key Components of Improvement Roadmaps
 

Scaling the Benefits of Kanban with Enterprise Services Planning

  • 1. Copyright Lean Kanban Inc.dja@leankanban.com @lki_dja Training & Consulting Presenter David J. Anderson Oredev Malmo November 2015 Scaling the Benefits of Kanban
  • 2. Copyright Lean Kanban Inc.dja@leankanban.com @lki_dja Enterprise Services Planning
  • 3. Copyright Lean Kanban Inc.dja@leankanban.com @lki_dja You are part of a professional services business! An ecosystem of professionals providing interdependent services, often with complex dependencies. Professional Service organizations build intangible goods
  • 4. Copyright Lean Kanban Inc.dja@leankanban.com @lki_dja The challenge of professional services businesses A constantly changing external environment has a ripple effect across your entire business ecosystem Priorities change and required capability & service levels rise in response to competition, disruptive market innovation & changes in customer tastes
  • 5. Copyright Lean Kanban Inc.dja@leankanban.com @lki_dja What should we start next? Will it be delivered when we need it? Do we have capacity to do everything we need to do?
  • 6. Copyright Lean Kanban Inc.dja@leankanban.com @lki_dja How will dependencies affect our ability to deliver? How many activities should we have running in parallel? If we delay starting something, will the capacity be available when we need it?
  • 7. Copyright Lean Kanban Inc.dja@leankanban.com @lki_dja Demand Observed Capability Demand Demand Observed Capability Observed Capability ESP – Anticipating Demand, Allocating Capacity Looking downstream, you want the system to help you anticipate and manage dependencies
  • 8. Copyright Lean Kanban Inc.dja@leankanban.com @lki_dja ESP – Anticipating Demand, Allocating Capacity Demand Observed Capability Demand Demand Observed Capability Observed Capability Looking upstream, you want the system to help you anticipate and manage demand
  • 9. Copyright Lean Kanban Inc.dja@leankanban.com @lki_dja Demand Observed Capability Demand Demand Observed Capability Observed Capability ESP – Anticipating Demand, Allocating Capacity Combine the two, and across the organization you smooth flow end- to-end and help keep demand in balance with overall system capability
  • 10. Copyright Lean Kanban Inc.dja@leankanban.com @lki_dja Enterprise Services Planning *Kanban is a way to organize and manage work. It improves service delivery speed & predictability through a combination of limiting work-in-progress & deferred commitment It uses visual management and Lean techniques such as limiting the amount of work in progress, and probabilistic forecasting. Kanban helps to balance demand with capability. Balancing demand and capability = improved flow. Improved flow = Improved predictability. Enterprise Services Planning (ESP) is an enterprise-wide management solution that leverages Kanban* to improve each service within your business.
  • 11. Copyright Lean Kanban Inc.dja@leankanban.com @lki_dja The goal of Enterprise Services Planning The goal of Enterprise Services Planning is to achieve... The Right Things At The Right Time Done The Right Way With Appropriate Risk Exposure
  • 12. Copyright Lean Kanban Inc.dja@leankanban.com @lki_dja Enterprise Services Planning Manufacturing 1947 – Kanban 1964 & 1975 – MRP Professional Services 2004 – Kanban 2015 – ESP ESP is “MRP for professional services”. ESP is for managing capacity & scheduling intangible work
  • 13. Copyright Lean Kanban Inc.dja@leankanban.com @lki_dja Enterprise Services Planning Planning involves… Scheduling Sequencing Selecting Commitment Anticipating & Managing Dependencies Risk Management Understanding what is essential based on…  Business strategy  Fitness for purpose
  • 14. Copyright Lean Kanban Inc.dja@leankanban.com @lki_dja Risk Assessment (for scheduling, sequencing, & selection)
  • 15. Copyright Lean Kanban Inc.dja@leankanban.com @lki_dja Qualitative Taxonomies 2 -> 6 categories Fact-based Cheap Fast Accurate Consensus Forming Managed Risk Heterogeneous Expensive Time Consuming Fake Precision? May still be High Risk Homogenous Cheap Fast High Risk A middle-ground in effective Risk Management
  • 16. Copyright Lean Kanban Inc.dja@leankanban.com @lki_dja Sketch market utility functionRoomnights soldperday Actual rooms sold Cost of delay Estimated additional rooms sold When we need it When it arrived Cost of delay for an online Easter holiday marketing promotion is difference in integral between the two curves time
  • 17. Copyright Lean Kanban Inc.dja@leankanban.com @lki_dja Cost of Delay based on utility function sketches Cost of delay function for an online Easter holiday marketing campaign delayed by 1 month from mid-January (based on diff of 2 integrals on previous slide) Treat as a Standard Class item time impact Total cost of delay
  • 18. Copyright Lean Kanban Inc.dja@leankanban.com @lki_dja Utility Function Taxonomy Front-loaded – Most of the value is realized early in the lifespan of the product with a long residual tail Utility Function Shape Bell curve – Most of the value is realized in the middle of the lifespan with slow initial uptake and a somewhat symmetrical tail off Back-loaded – Initial take-up is slow with value realized close to a natural end-date in the product lifespan
  • 19. Copyright Lean Kanban Inc.dja@leankanban.com @lki_dja Visualize Risks to provide Scheduling Information TS Market Risk CR Spoil Diff Lifecycle Cost of Delay Tech Risk Delay Impact New Mid Cow Expedite FD Std Intangible ELE Maj. Cap. Disc Unknown Soln Known but not us Done it before Commodity Risk profile for a work item or project Outside: Commit Early Inside: Commit Late Items with the same shape carry the same risks. They cannot be prioritized or sequenced. From a group of items with the same risk profile pick whichever ones you like. It is also wise to hedge risk by allocating capacity in the system for items of different risk profiles.
  • 20. Copyright Lean Kanban Inc.dja@leankanban.com @lki_dja Scheduling & Sequencing TS Market Risk CR Spoil Diff Lifecycle Cost of Delay Tech Risk Delay Impact New Mid Cow Expedite FD Std Intangible ELE Maj. Cap. Disc Unknown Soln Known but not us Done it before Commodity Sequence: 1st Sequence: 3rd Sequence: 2nd If only real life was so simple!
  • 21. Copyright Lean Kanban Inc.dja@leankanban.com @lki_dja Custom Profile Contains Narrative Our CEO has requested we do the blue project. Which one do we postpone? The purple project is important but can be delayed with little penalty.
  • 22. Copyright Lean Kanban Inc.dja@leankanban.com @lki_dja Inherent Risk, Risk of Rework & Sequencing MarketRisk Scheduling High risk of change or rework Low risk of change or rework Can Commit Early Should be deferred Differentiators Spoilers Table Stakes Cost Reducers Regulatory Defer until later only incurs opportunity cost penalty Deferring tables stakes may mean foregoing differentiators or starting early and paying cost of rework InherentRisk RiskofRework Sequencing
  • 23. Copyright Lean Kanban Inc.dja@leankanban.com @lki_dja Revisiting the portfolio options There is a low penalty to deferring the purple project compared to alternatives The purple project remains important. We may need to forgo something else later in order to insure it is completed
  • 24. Copyright Lean Kanban Inc.dja@leankanban.com @lki_dja Visualizing Inherent Risk Diff Market Risk Spoil CR TS Lifecycle Cost of Delay Tech Risk Delay Impact Cow Mid New Expedite FD Std Intangible ELE Maj. Cap. Disc Unknown Soln Known but not us Done it before Commodity Outside: High Risk Inside: Low Risk Some axes are reversed when we show inherent risk in the project or feature compared to its schedule risk. If inherent risk is lower than schedule risk then the project or feature can be deferred Where inherent risk is greater than schedule risk. Deferring only works if other information gathering is happening creating an embedded option
  • 25. Copyright Lean Kanban Inc.dja@leankanban.com @lki_dja Demand Shaping Threshold Dimension 1 Dimension 2 Dimension 3 Dimension 5 Dimension 4 Definitely Do This Demand shaping threshold Talk about this one Definitely Don’t This
  • 26. Copyright Lean Kanban Inc.dja@leankanban.com @lki_dja Forecasting
  • 27. Copyright Lean Kanban Inc.dja@leankanban.com @lki_dja Lead Time & Weibull Distributions Lead time histograms observed to be Weibull distributions typically with shape parameter 1.0 < k < 2.0 This example is a Weibull distribution with a scale parameter equal to 65 and shape parameter equal to 1.4 Outliers with known special causes at 87 & 105 are omitted from the “best fit” curve
  • 28. Copyright Lean Kanban Inc.dja@leankanban.com @lki_dja ChangeRequests SLA (customer expectation or fitness criteria) 60 days Use Lead Time Distribution to Evaluate Service Delivery Effectiveness 22-150 day spread of variation 85% on-time 15% late Due Date Performance (DDP) Predictability
  • 29. Copyright Lean Kanban Inc.dja@leankanban.com @lki_dja Forecasting methods ESP relies on two types of forecasting approaches  Reference class forecasting  Monte Carlo simulation Reference class forecasting requires an assumption of an equilibrium – the near future will reflect the continuing conditions of the recent past  We sample data from a period in the recent past and use it to forecast future behavior  The sample period is determined by evaluating the volatility in kanban system liquidity
  • 30. Copyright Lean Kanban Inc.dja@leankanban.com @lki_dja Scheduling
  • 31. Copyright Lean Kanban Inc.dja@leankanban.com @lki_dja When should we start something? impact When we need it 85th percentile Ideal Start Here Commitment point timeJan 10 Nov 11 If we start too early, we forgo the option and opportunity to do something else that may provide value. If we start too late we risk incurring the cost of delay If we pull the work into our kanban system on Nov 11 we have a 6 out of 7 chance of on-time delivery
  • 32. Copyright Lean Kanban Inc.dja@leankanban.com @lki_dja What is the latest we could start? impact When we need it 0th percentile Very late start Commitment point timeJan 10 Dec 19 If we start as late as December 19 we have 0% chance of on-time delivery We have about a 10% chance of a total loss delivering the promotion beyond the expiry date of the opportunity 85th percentile total loss
  • 33. Copyright Lean Kanban Inc.dja@leankanban.com @lki_dja To be certain of delivery without incurring any cost of delay is expensive impact When we need it 98th percentile Early Start Commitment point timeJan 10 Aug 11 If we are conservative and do not wish to carry any risk of late delivery or any risk of incurring an opportunity cost of delay, then we must start as early as August 13th. We must commit to our Spring Break 2015 promotion during Summer 2014!!!
  • 34. Copyright Lean Kanban Inc.dja@leankanban.com @lki_dja Window of opportunity impact When we need it Earliest Start timeJan 10 Aug 11 Latest viable start Dec 19 Optimal Start Nov 11 On August 11st the item becomes available for selection at Kanban system replenishment. The ideal time to start is November 11th. After December 19th our option to deliver this item expires and we would discard it from our pool.
  • 35. Copyright Lean Kanban Inc.dja@leankanban.com @lki_dja Scaling out across the organization
  • 36. Copyright Lean Kanban Inc.dja@leankanban.com @lki_dja Treat each service separately Demand Observed Capability Demand Demand Observed Capability Observed Capability
  • 37. Copyright Lean Kanban Inc.dja@leankanban.com @lki_dja STATIK (Systems Thinking Approach to Introducing Kanban) 1. Understand what makes the service “fit for purpose” 2. Understand sources of dissatisfaction regarding current delivery 3. Analyze sources of and nature of demand 4. Analyze current delivery capability 5. Model the service delivery workflow 6. Identify & define classes of service 7. Design the kanban system 8. Socialize design & negotiate implementation This process tends to be iterative Identify Services. For each service…
  • 38. Copyright Lean Kanban Inc.dja@leankanban.com @lki_dja The Kanban Method Scaling Principles 1. Scale out in a service-oriented fashion one service at a time 2. Design each kanban system from first principles using STATIK, do not attempt to design a grand solution at enterprise scale 3. Use the Kanban Cadences as the management system that enable balance, leading to better enterprise services delivery
  • 39. Copyright Lean Kanban Inc.dja@leankanban.com @lki_dja Anticipating & Managing Dependencies
  • 40. Copyright Lean Kanban Inc.dja@leankanban.com @lki_dja Some systems have dependencies on others Demand Observed Capability Demand Demand Observed Capability Observed Capability Looking downstream, you want the system to help you anticipate and manage dependencies
  • 41. Copyright Lean Kanban Inc.dja@leankanban.com @lki_dja Some systems have dependencies on others Demand Observed Capability Demand Demand Observed Capability Observed Capability Looking upstream, you want the system to help you anticipate and manage demand
  • 42. Copyright Lean Kanban Inc.dja@leankanban.com @lki_dja Some systems have dependencies on others Demand Observed Capability Demand Demand Observed Capability Observed Capability Combine the two, and across the organization you smooth flow end-to- end and help keep demand in balance with overall system capability
  • 43. Copyright Lean Kanban Inc.dja@leankanban.com @lki_dja Buffer dependencies, agree SLAs 5 4 43 2 2 ...Input Queue Dev Ready In Prog DoneDoneIn Prog DevelopmentAnalysis Build Ready Test Release Ready Waiting on External Group Late against SLA Dots denote clock ticking on SLA ∞8 Unbounded Queue When the dependent service becomes reliable & predictable, we can use Little’s Law to calculate a WIP limit for the dependency buffer
  • 44. Copyright Lean Kanban Inc.dja@leankanban.com @lki_dja Feedback Loops Enable The Network To Evolve
  • 45. Copyright Lean Kanban Inc.dja@leankanban.com @lki_dja Strategy Review Risk Review Monthly Service Delivery Review Bi-WeeklyQuarterly Kanban Meeting Daily Operations Review Monthly Replenishment/ Commitment Meeting Weekly Delivery Planning Meeting Per delivery cadence change change change change change change change change change info info info info info info info info info change info Kanban CadencesAre we doing things right? Are we doing the right thing? Focus on Service Delivery
  • 46. Copyright Lean Kanban Inc.dja@leankanban.com @lki_dja Use feedback loops to level capability across the network
  • 47. Copyright Lean Kanban Inc.dja@leankanban.com @lki_dja Visualizing Dependencies
  • 48. Copyright Lean Kanban Inc.dja@leankanban.com @lki_dja 5 4 43 2 2 ...Input Queue Dev Ready In Prog DoneDoneIn Prog DevelopmentAnalysis Build Ready Test Release Ready Waiting on External Group Late against SLA Dots denote clock ticking on SLA ∞8 Unbounded Queue
  • 49. Copyright Lean Kanban Inc.dja@leankanban.com @lki_dja 5 4 2 ...Input Queue In Prog DoneDoneIn Prog DevAnalysis System Test Release Ready Dev 4 4 In Prog Split Integration Point Integration Dependencies 2 Integration Test Component1Component2 DoneIn Prog DoneIn Prog Integration dependencies should be managed like small projects for the components or sub-systems with the integration point being scheduled by backing out integration cycle time from the desired delivery date Integration points should be treated as localized fixed delivery dates, hence the component or sub-system has a fixed date. Use project forecasting to plan the component delivery Cycle time
  • 50. Copyright Lean Kanban Inc.dja@leankanban.com @lki_dja Parent-child dependencies can be represented with 2-tiered boards Features (parents) Use Stories (children)
  • 51. Copyright Lean Kanban Inc.dja@leankanban.com @lki_dja Visualizing Dependencies at Posit Science Dots depict dependencies
  • 52. Copyright Lean Kanban Inc.dja@leankanban.com @lki_dja Visualize dependencies on tickets Title Graphic Design Copy Writing DBA Customer Signoff req complete Color of the ticket May indicate dependency on shared services J Decorators (Shape & Color) (Letter) SLA or Target Date May indicate service, vendor or customer dependencies May be used to indicate skill level required Start dd/mm/yyyy dd/mm/yyyyDue End SIT date Dates Age (showing days blocked) Can be used to visualize integration dependencies Class of service affected by dependent request
  • 53. Copyright Lean Kanban Inc.dja@leankanban.com @lki_dja Definition of Enterprise Services Planning
  • 54. Copyright Lean Kanban Inc.dja@leankanban.com @lki_dja Enterprise Services Planning 3 Organizational Steps Foster a culture focused on continual fit-for-purpose service delivery Seeing Services “Kanban” each service Feedback Loop System Identify interdependent services in your organization Use the STATIK method to create a Kanban system for each service Implement a set of responsive feedback loops
  • 55. Copyright Lean Kanban Inc.dja@leankanban.com @lki_dja Enterprise Services Planning Step 1: Seeing Services Examples: HR provides services throughout the organization, but they also need services from IT Marketing provides services to product development but they need services from Sales and from IT IT provides services to Customer Support. There is an interdependency between Customer Support, QA, and IT Engineering. Different feature teams or product teams may have dependencies on each other Many groups are dependent upon specialist individuals
  • 56. Copyright Lean Kanban Inc.dja@leankanban.com @lki_dja Enterprise Services Planning Step 2: Kanban the Services Use STATIK (Systems Thinking Approach to Implementing Kanban) for each identified service… 1. Understand what makes the service “fit for purpose” 2. Understand sources of dissatisfaction regarding current delivery 3. Analyze sources of and nature of demand 4. Analyze current delivery capability 5. Model the service delivery workflow 6. Identify & define classes of service 7. Design the kanban system 8. Socialize design & negotiate implementation
  • 57. Copyright Lean Kanban Inc.dja@leankanban.com @lki_dja Enterprise Services Planning Step 3: Responsive Feedback Loops Strategy Review Risk Review Monthly Service Delivery Review Bi-WeeklyQuarterly Kanban Meeting Daily Operations Review Monthly Replenishment/ Commitment Meeting Weekly Delivery Planning Meeting Per delivery cadence change change change change change change change change change info info info info info info info info info change info
  • 58. Copyright Lean Kanban Inc.dja@leankanban.com @lki_dja Illustrates 4 Functions of Management in ESP Strategy Review Risk Review Monthly Service Delivery Review Bi-WeeklyQuarterly Kanban Meeting Daily Operations Review Monthly Replenishment/ Commitment Meeting Weekly Delivery Planning Meeting Per delivery cadence change change change change change change change change change info info info info info info info info info change info Focus on Service Delivery Driving improvement… Higher level management function
  • 59. Copyright Lean Kanban Inc.dja@leankanban.com @lki_dja Enterprise Services Planning Achieve “Fitness for Purpose” Product component (capability/brand/non- functional elements) Service delivery component demand /customer expectations/ customer satisfaction) + These must be balanced to deliver what your customers need and expect: to be “fit for purpose”
  • 60. Copyright Lean Kanban Inc.dja@leankanban.com @lki_dja Summary
  • 61. Copyright Lean Kanban Inc.dja@leankanban.com @lki_dja Enterprise Services Planning Curriculum
  • 62. Copyright Lean Kanban Inc.dja@leankanban.com @lki_dja Enterprise Services Planning Planning involves… Scheduling Sequencing Selecting Commitment Anticipating & Managing Dependencies Risk Management Understanding what is essential based on…  Business strategy  Fitness for purpose
  • 63. Copyright Lean Kanban Inc.dja@leankanban.com @lki_dja Enterprise Services Planning The Right Things At The Right Time Done The Right Way With Appropriate Risk Exposure
  • 64. Copyright Lean Kanban Inc.dja@leankanban.com @lki_dja
  • 65. Copyright Lean Kanban Inc.dja@leankanban.com @lki_dja Thank you!
  • 66. Copyright Lean Kanban Inc.dja@leankanban.com @lki_dja About David Anderson is an innovator in management of 21st Century businesses that employ creative people who “think for a living” . He leads a training, consulting, publishing and event planning business dedicated to developing, promoting and implementing new management thinking & methods… He has 30+ years experience in the high technology industry starting with computer games in the early 1980’s. He has led software organizations delivering superior productivity and quality using innovative methods at large companies such as Sprint and Motorola. David defined Enterprise Services Planning and originated Kanban Method an adaptive approach to improved service delivery. His latest book, published in June 2012, is, Lessons in Agile Management – On the Road to Kanban. David is Chairman & CEO of Lean Kanban Inc., a business operating globally, dedicated to providing quality training & events to bring Kanban and Enterprise Services Planning to businesses who employ those who must “think for a living.”
  • 67. Copyright Lean Kanban Inc.dja@leankanban.com @lki_dja Risk profile courtesy of BazaarVoice Acknowledgements
  • 68. Copyright Lean Kanban Inc.dja@leankanban.com @lki_dja

Notas do Editor

  1. We have walked through the Systems Thinking Approach to Introducing Kanban. This process tends to be iterative. Don’t be afraid to go back and adjust your kanban system as new information emerges or your needs change.
  2. There are 3 Change Management Principles designed to frame an evolutionary approach to improvement. Be aware that the Kanban Method is applied to the way you work now, and it will help you evolve the way you work gradually over time. [Briefly walk through each of the principles. See David’s blog at http://www.djaa.com/principles-general-practices-kanban-method if you want help with how to explain each.]
  3. The KMP II class is built around the 7 cadences of the Kanban Method. The focus is on institutionalizing the feedback loops and developing templates for each meeting or review including a list of who will attend and what information they must bring to the meetings. The objective is to drive improvement and evolutionary change through management feedback loops implemented as a series of rituals happening on cadences tailored to the specific needs of the business. Strategy Review is out-of-scope until the Portfolio Management module of the ESP class.
  4. Use the scheduling guidance from Day 2 coupled to the project planning from Day 4 to manage integration points together with a fixed delivery date class of service for the dependent parts
  5. There is a variety of ways you can communicate information on a kanban ticket. You don’t need to put too much on the ticket!
  6. The KMP II class is built around the 7 cadences of the Kanban Method. The focus is on institutionalizing the feedback loops and developing templates for each meeting or review including a list of who will attend and what information they must bring to the meetings. The objective is to drive improvement and evolutionary change through management feedback loops implemented as a series of rituals happening on cadences tailored to the specific needs of the business. Strategy Review is out-of-scope until the Portfolio Management module of the ESP class.
  7. Enterprise Services Planning