SlideShare a Scribd company logo
1 of 39
Submitted To:-
Dr. Dinesh Birla
(Professor)
MR. Ashok Kumar Sharma
(Associate professor)
Submitted BY:-
Abhishek Dosaya
Roll no.- 13/003
7th sem,Btech,EE
Substation:- From where electricity is transmitted or
distributed.
Step up for long distance transmission
Step down for distribution purpose
A substation generally have switching, protection, & control
equipment & one or more transformers.
Purpose of substation:-
 Protection of transmission system.
 voltage control; reducing the reactive power flow by compensation of
reactive power.
 Ensuring the stability of the network.
 Determining the energy transfer through transmission line.
 Data transmission via power line carrier for the purpose of network
monitoring , control and protection.
 Fault analysis and recover
DEFINITION:- A bus bar is a conducting bar that
carries heavy currents to supply several electric
circuits.
When a no. of generators or feeders operating at the
same voltage level to be directly connected electrically,
Bus bar are used as the common electrical component.
Bus bars are copper rod or thin walled tubes and
operate at constant voltage.
TYPES OF BUSBARS:-
 Main Bus bar
 Auxiliary Bus bar
One Bus bar is main Bus bar & another is spare or
Auxiliary Bus bar.
When any apparatus become faulty which is directly
connected to main Bus bar then we use auxiliary bus bar
to keep supply continue.
 Lightning arrester is a
protective device which
provides protection against the
high voltage from lightning.
 A lightning arrestor has two
terminal one is the high
voltage terminal and one
terminal is ground.
 It is used only from overhead
line
 Zno type LA are mostly used.
Close Condition
Open Condition
A circuit breaker is a equipment which can:-
 break a ckt automatically under fault conditions.
 make a ckt either manually or by remote control .
PRINCIPLE:- A ckt breaker essentially consists of fixed
& moving contacts, called electrodes under normal
operating conditions, these contacts remain closed &
will not open automatically until & unless the systems
becomes faulty. When a fault occurs on any part of the
system, the trip coils of the breaker get Energised &
the moving contacts are pulled apart by some
mechanism. Thus opening the circuit.
It is generally used in on load condition.
CLASSIFICATION:-
 oil circuit breakers
 Sulphur Hexa Fluroide circuit breakers
 Air-Blast circuit breakers
 vaccum circuit breakers
Under training SF6 and oil circuit breaker were used
in the GSS.
Isolator is used When current is not
flowing into the line, because there is no
arc interrupting medium But Circuit
breaker is used on load condition
because arc interrupting medium is
available.
 Transformer is an electrical machine
which works on the principle of
electromagnetic induction.
 It transfers electric power from one electric
ckt to other with the help magnetic
path(flux) on constant frequency but
equal or different current voltages.
 For this purpose two sets of insulated
windings are wounded on a close
terminated steel core.
 The winding which is connected to the
supply is called primary winding & that
winding is connected to the load is called
secondary winding.
1. Three limb core
2. LV winding
3. HV winding
4. LV bushings
5. HV bushings
6. Transformer oil
7. Tap changer
8. Conservator
9. Breather
10. Buchholz relay
11. Radiator
Instrument transformers are used for measurement
and protective applications together with equipments
such as meters & relays.
The lines in a station are operated at high voltages and
carry currents of thousands of amperes. The
measuring and protective devices are designed for low
voltage generally 100v and currents about 5A, therefore
they will not work satisfactory if mounted on the
power lines. This difficulty can be overcome by using
instrument transformers, which will step down the
voltages and currents to the convenient level for the
operation of measuring instruments & relays.
 C.T. is an instrument transformer used for
protection & metering of high values of currents.
C.T. is used for reducing A.C. from higher to lower
value for measurement/protection/control.
 Turns Ratio normally 1:1000
 IS= IP * NP / NS
 CT rating 100/5 and 20/1 is not same because this is
the input/output rating(not turns ratio).
 Secondary of CT is short circuited due to following
reasons:-
1. If the secondary is open circuited , no current flow
secondary side, so no counter magnetic field , flux
in the core saturates and char. Of CT changes and
damage permanently
2. No of sec. turns high , so high voltage induce which
can harm the persons working on the panel
 CT consist of single core in high voltage side
and 3 0r 4 cores in low voltage side.
>
Potential transformer (voltage
transformer) is used for protection and
measurement.Voltage transformer is
necessary for directional, voltage, distance
protection.
 A PT or sometimes called VT is a step-
down transformer having many primary
turns but few secondary turns.
 In a step-down transformer the voltage
decreases and the current increases, thus
voltage can be easily measured by using a
low-range voltmeter instrument.
Oil cooled PT
A VT is a "stepdown transformer" that steps down voltage from a very high voltage
level(200KV,...) to a lower level(110V). Since, the power(P=VI) in a
transformer(input and output) is same, the current rises to a very high level. Thus,
a very high resistance is maintained at the secondary terminal to limit the
current(which appears as open circuit)
A capacitor voltage
transformer (CVT or CCVT), is
a transformer used in power
systems to step down extra high
voltage signals and provide a low
voltage signal, for metering or
operating a protective relay.
Capacitor Voltage
Transformers also serve as coupling
capacitors for coupling high
frequency power line carrier signals
to the transmission line.
In practice, capacitor C1 is
often constructed as a stack
of smaller capacitors
connected in series. This
provides a large voltage
drop across C1 and a
relatively small voltage drop
across C2. As the majority of
the voltage drop is on C1,
this reduces the required
insulation level of the
voltage transformer. This
makes CVTs more
economical than the wound
voltage transformers under
high voltage (over 100kV)
 A relay is automatic device which senses an abnormal
condition of electrical circuit and closes its contacts. These
contacts in turns close and complete the circuit breaker trip
coil circuit hence make the circuit breaker tripped for
disconnecting the faulty portion of the electrical circuit from
rest of the healthy circuit.
 Based on application the protection relay can be categorized
as- Primary relay.
Backup relay.
 Primary relay or primary protection relay is the first line of
power system protection whereas backup relay is operated only
when primary relay fails to be operated during fault. Hence
backup relay is slower in action than primary relay.
1.
132 KV
Transmission Line
Main Protection :
Switched distance
scheme (fed from
bus PT).
Backup Protection:
3 Nos. directional
IDMT O/L Relays
and
1 No. Directional
IDMT E/L relay.
2. 33 KV lines
Non-directional
IDMT 3 O/L and 1
E/L relays.
3. 11 KV lines
Non-directional
IDMT 2 O/L and 1
E/L relays.
132/33KV,40/
50 MVA
3 nos
O/L
Relay
1 no
Directio
nal E/L
Relay
3 nos O/L Relay
1 no E/L Relay
Differential Relay
Over flux Relay
Buchholz Relay
OLTC Buchholz
Relay
PRV Relay
OT Trip Relay
WT Trip Relay
 For compensate the reactive power, we use capacitor
bank.
 Advantage-
 It reduces Line current of the system.
 It improves voltage level of the load.
 It improves power factor.
It is subdivided into two categories:-
1. Shunt capacitor
2. Series Capacitor
Inductive load increase,
Reactive power more absorb,
Q(+) increase, power factor
decrease
To deliver the required active
power, I increases so the
ampere burden increases and
more losses take place or
voltage dip(black out
situations)
The main reason for doing earthing in electrical
network is for the safety. When all metallic parts in
electrical equipments are grounded then if the
insulation inside the equipments fails there are no
dangerous voltages present in the equipment case.
To save human life from danger of electrical shock or
death i.e. To provide an alternative path for the fault
current to flow
To lightning overvoltage protection
Methods of earthing arrangments at 132 kv
GSS:
 pipe earthing
 plate earthing
 Control room is a place from where we control all the
actions on all equipment in the yard.
 The control room work on 110V Dc supply. These supply are
taken from the station transformer By convert ac to dc through the
rectifiers. In the case of failure of ac supply. DC supply voltage will
be available automatically from the lead acid battery.
 Control Panels: Control panels contain meters, control
switches and recorders. These are used to measure all
readings and to control the substation equipment, to send
power from one circuit to another or to open or shut down
circuits when needed.
 Relay Panels: In Which the different types of relays
are present for different fault protection, and
indicate that type of fault
The control room work on
110V Dc supply. These supply
are taken from the station
transformer By convert ac to
dc through the rectifiers. In
the case of failure of ac
supply. DC supply voltage will
be available automatically
from the lead acid battery.
In battery rooms 55 batteries
of each 2v is connected in
series to provide 110v.
 For exchange of dates and transfer
message between grid
substation,voice communication is
necesarry. for this purpose high
frequency carrier current is
transmitted on same transmission
line on which power is
transmitted.
 Hence such communication is
called “power line communication.
 High frequency signal is
transmitted and received Through
coupling capacitor and is trapped
by line trap unit(parallel
combination of L and C).
Its was great experience for me, I have more cleared my
theoretical knowledge with the practical knowledge and
learn that how do complex distribution be successful so
that we may get continuous power supply.
132kV GSS ppt

More Related Content

What's hot

Training report-in-a-132-k-v-substation
Training report-in-a-132-k-v-substationTraining report-in-a-132-k-v-substation
Training report-in-a-132-k-v-substationankesh kumar
 
industrial training on 132 kv substation
industrial training on 132 kv substationindustrial training on 132 kv substation
industrial training on 132 kv substationpk130992
 
Substation Training presentation
Substation Training presentationSubstation Training presentation
Substation Training presentationKamal Mittal
 
Unit 03 Protective relays
Unit  03 Protective relaysUnit  03 Protective relays
Unit 03 Protective relaysPremanandDesai
 
Industrial summer training on 220 kv substation ppt
Industrial summer training on 220 kv substation pptIndustrial summer training on 220 kv substation ppt
Industrial summer training on 220 kv substation pptAshutosh Srivastava
 
Switchgear Equipment in a Substation
Switchgear Equipment in a SubstationSwitchgear Equipment in a Substation
Switchgear Equipment in a SubstationMd. Atiqur Rahman
 
PPt on 220 kV substation
PPt on 220 kV substationPPt on 220 kV substation
PPt on 220 kV substationIshank Ranjan
 
A training report on 132 KV GSS, BHADOTI, sawai madhopur
A training report on 132 KV GSS, BHADOTI, sawai madhopurA training report on 132 KV GSS, BHADOTI, sawai madhopur
A training report on 132 KV GSS, BHADOTI, sawai madhopurdilkhush009
 
Sub station training ppt
Sub station training pptSub station training ppt
Sub station training pptsitesh95074
 
Switchgear and protection 1
Switchgear and protection 1Switchgear and protection 1
Switchgear and protection 1Md Irshad Ahmad
 
132 kv substation
132 kv substation132 kv substation
132 kv substationWipro
 
substation 220 kv
substation 220 kv substation 220 kv
substation 220 kv student
 
Electrical 132kv substation project .. shakir
Electrical 132kv substation project .. shakirElectrical 132kv substation project .. shakir
Electrical 132kv substation project .. shakirSheikh Shakir
 
Substation protection devices
Substation protection devicesSubstation protection devices
Substation protection devicesRahul Aman
 
Protection & switchgear
Protection & switchgear   Protection & switchgear
Protection & switchgear johny renoald
 
SUBSTATION OVERVIEW - A presentation on substation
SUBSTATION OVERVIEW - A presentation on substationSUBSTATION OVERVIEW - A presentation on substation
SUBSTATION OVERVIEW - A presentation on substationraiamitesh8
 
substation internship report
substation internship report substation internship report
substation internship report Arun Thapa
 
Power Transformer Differential protection
Power Transformer Differential protectionPower Transformer Differential protection
Power Transformer Differential protectionRishi Tandon
 

What's hot (20)

Training report-in-a-132-k-v-substation
Training report-in-a-132-k-v-substationTraining report-in-a-132-k-v-substation
Training report-in-a-132-k-v-substation
 
BUSBAR PROTECTION
BUSBAR PROTECTIONBUSBAR PROTECTION
BUSBAR PROTECTION
 
industrial training on 132 kv substation
industrial training on 132 kv substationindustrial training on 132 kv substation
industrial training on 132 kv substation
 
Substation Training presentation
Substation Training presentationSubstation Training presentation
Substation Training presentation
 
Unit 03 Protective relays
Unit  03 Protective relaysUnit  03 Protective relays
Unit 03 Protective relays
 
Industrial summer training on 220 kv substation ppt
Industrial summer training on 220 kv substation pptIndustrial summer training on 220 kv substation ppt
Industrial summer training on 220 kv substation ppt
 
Switchgear Equipment in a Substation
Switchgear Equipment in a SubstationSwitchgear Equipment in a Substation
Switchgear Equipment in a Substation
 
PPt on 220 kV substation
PPt on 220 kV substationPPt on 220 kV substation
PPt on 220 kV substation
 
A training report on 132 KV GSS, BHADOTI, sawai madhopur
A training report on 132 KV GSS, BHADOTI, sawai madhopurA training report on 132 KV GSS, BHADOTI, sawai madhopur
A training report on 132 KV GSS, BHADOTI, sawai madhopur
 
Sub station training ppt
Sub station training pptSub station training ppt
Sub station training ppt
 
Switchgear and protection 1
Switchgear and protection 1Switchgear and protection 1
Switchgear and protection 1
 
132 kv substation
132 kv substation132 kv substation
132 kv substation
 
substation 220 kv
substation 220 kv substation 220 kv
substation 220 kv
 
Electrical 132kv substation project .. shakir
Electrical 132kv substation project .. shakirElectrical 132kv substation project .. shakir
Electrical 132kv substation project .. shakir
 
Substation protection devices
Substation protection devicesSubstation protection devices
Substation protection devices
 
Protection & switchgear
Protection & switchgear   Protection & switchgear
Protection & switchgear
 
220 kv gss
220 kv gss220 kv gss
220 kv gss
 
SUBSTATION OVERVIEW - A presentation on substation
SUBSTATION OVERVIEW - A presentation on substationSUBSTATION OVERVIEW - A presentation on substation
SUBSTATION OVERVIEW - A presentation on substation
 
substation internship report
substation internship report substation internship report
substation internship report
 
Power Transformer Differential protection
Power Transformer Differential protectionPower Transformer Differential protection
Power Transformer Differential protection
 

Viewers also liked

eco friendly power generation through Speed breaker using water pressure
  eco friendly power generation through Speed breaker using water pressure  eco friendly power generation through Speed breaker using water pressure
eco friendly power generation through Speed breaker using water pressureSamir9064
 
Power generation through speed breaker
Power generation through speed breakerPower generation through speed breaker
Power generation through speed breakervaibhav patel
 
electricity generation from speed breaker
electricity generation from speed breakerelectricity generation from speed breaker
electricity generation from speed breakerFeroz Ahmed
 
Power Generation from Speed Breakers
Power Generation from Speed BreakersPower Generation from Speed Breakers
Power Generation from Speed BreakersMahim Srivastava
 
power generation through speed breaker
power generation through speed breaker power generation through speed breaker
power generation through speed breaker Ranjan Kumar Thakur
 
power generation through speed breaker
power generation through speed breakerpower generation through speed breaker
power generation through speed breakerShifa Nadeem
 
power generation by speed breaker
power generation by speed breakerpower generation by speed breaker
power generation by speed breakerIftekhar Alam
 
Generation of electricity through speed breaker mechanism(AVANTHI CLG MAKAVAR...
Generation of electricity through speed breaker mechanism(AVANTHI CLG MAKAVAR...Generation of electricity through speed breaker mechanism(AVANTHI CLG MAKAVAR...
Generation of electricity through speed breaker mechanism(AVANTHI CLG MAKAVAR...Aditya Guna
 

Viewers also liked (10)

MHD power generation
MHD power generationMHD power generation
MHD power generation
 
eco friendly power generation through Speed breaker using water pressure
  eco friendly power generation through Speed breaker using water pressure  eco friendly power generation through Speed breaker using water pressure
eco friendly power generation through Speed breaker using water pressure
 
Power generation through speed breaker
Power generation through speed breakerPower generation through speed breaker
Power generation through speed breaker
 
132 KV GSS CHAMBAL JAIPUR
132 KV GSS CHAMBAL JAIPUR132 KV GSS CHAMBAL JAIPUR
132 KV GSS CHAMBAL JAIPUR
 
electricity generation from speed breaker
electricity generation from speed breakerelectricity generation from speed breaker
electricity generation from speed breaker
 
Power Generation from Speed Breakers
Power Generation from Speed BreakersPower Generation from Speed Breakers
Power Generation from Speed Breakers
 
power generation through speed breaker
power generation through speed breaker power generation through speed breaker
power generation through speed breaker
 
power generation through speed breaker
power generation through speed breakerpower generation through speed breaker
power generation through speed breaker
 
power generation by speed breaker
power generation by speed breakerpower generation by speed breaker
power generation by speed breaker
 
Generation of electricity through speed breaker mechanism(AVANTHI CLG MAKAVAR...
Generation of electricity through speed breaker mechanism(AVANTHI CLG MAKAVAR...Generation of electricity through speed breaker mechanism(AVANTHI CLG MAKAVAR...
Generation of electricity through speed breaker mechanism(AVANTHI CLG MAKAVAR...
 

Similar to 132kV GSS ppt

Uttar pradesh power corporation limited
Uttar pradesh power corporation limitedUttar pradesh power corporation limited
Uttar pradesh power corporation limitedVSRAGHU
 
Substation equipment and its function 2
Substation equipment and its function 2Substation equipment and its function 2
Substation equipment and its function 2Zulfiqar Mangrio
 
ELECTRIC SUB-STATION IN BRIEF
ELECTRIC SUB-STATION IN BRIEFELECTRIC SUB-STATION IN BRIEF
ELECTRIC SUB-STATION IN BRIEFjang041
 
DISTRIBUTION SYSTEM OPERATION AND CONTROL
DISTRIBUTION SYSTEM OPERATION AND CONTROLDISTRIBUTION SYSTEM OPERATION AND CONTROL
DISTRIBUTION SYSTEM OPERATION AND CONTROLyohannes feleke
 
Rajasthan Rajya Vidyut Prasaran Nigam.pptx
Rajasthan Rajya Vidyut Prasaran Nigam.pptxRajasthan Rajya Vidyut Prasaran Nigam.pptx
Rajasthan Rajya Vidyut Prasaran Nigam.pptxsohaib268827
 
66%20Industrial%20Visit%20Report.docx
66%20Industrial%20Visit%20Report.docx66%20Industrial%20Visit%20Report.docx
66%20Industrial%20Visit%20Report.docxdnyaneshwarvidhate2
 
sub subsation seminar ppt.pptx
sub subsation seminar ppt.pptxsub subsation seminar ppt.pptx
sub subsation seminar ppt.pptxfallinhay
 
PPT ON 33/11KV SUBSTATION
PPT ON 33/11KV SUBSTATIONPPT ON 33/11KV SUBSTATION
PPT ON 33/11KV SUBSTATIONRavi Phadtare
 
Load Distribution
Load DistributionLoad Distribution
Load DistributionArpit Gupta
 
pptravi-191011011024 (1).pdf
pptravi-191011011024 (1).pdfpptravi-191011011024 (1).pdf
pptravi-191011011024 (1).pdfHariomgupta90
 
Indusrtrial training ppt (1).pptx
Indusrtrial training ppt (1).pptxIndusrtrial training ppt (1).pptx
Indusrtrial training ppt (1).pptxSNEHAKANWAR1
 
132 kv g.s.s chambal jaipur
132 kv g.s.s chambal jaipur132 kv g.s.s chambal jaipur
132 kv g.s.s chambal jaipurmonga786
 
Powergrid Corporation India Limited industrial training
Powergrid Corporation India Limited industrial trainingPowergrid Corporation India Limited industrial training
Powergrid Corporation India Limited industrial trainingAkriti Gupta
 
powergrid presentation
powergrid presentationpowergrid presentation
powergrid presentationAkriti Gupta
 
Instrumentation transformers, Types of Instrumentation Transformer & Relays
Instrumentation transformers, Types of Instrumentation Transformer & RelaysInstrumentation transformers, Types of Instrumentation Transformer & Relays
Instrumentation transformers, Types of Instrumentation Transformer & RelaysUrooj Abid
 

Similar to 132kV GSS ppt (20)

Uttar pradesh power corporation limited
Uttar pradesh power corporation limitedUttar pradesh power corporation limited
Uttar pradesh power corporation limited
 
Substation equipment and its function 2
Substation equipment and its function 2Substation equipment and its function 2
Substation equipment and its function 2
 
Gss ppt by kanhaiya
Gss ppt  by kanhaiyaGss ppt  by kanhaiya
Gss ppt by kanhaiya
 
ELECTRIC SUB-STATION IN BRIEF
ELECTRIC SUB-STATION IN BRIEFELECTRIC SUB-STATION IN BRIEF
ELECTRIC SUB-STATION IN BRIEF
 
DISTRIBUTION SYSTEM OPERATION AND CONTROL
DISTRIBUTION SYSTEM OPERATION AND CONTROLDISTRIBUTION SYSTEM OPERATION AND CONTROL
DISTRIBUTION SYSTEM OPERATION AND CONTROL
 
Rajasthan Rajya Vidyut Prasaran Nigam.pptx
Rajasthan Rajya Vidyut Prasaran Nigam.pptxRajasthan Rajya Vidyut Prasaran Nigam.pptx
Rajasthan Rajya Vidyut Prasaran Nigam.pptx
 
66%20Industrial%20Visit%20Report.docx
66%20Industrial%20Visit%20Report.docx66%20Industrial%20Visit%20Report.docx
66%20Industrial%20Visit%20Report.docx
 
sub subsation seminar ppt.pptx
sub subsation seminar ppt.pptxsub subsation seminar ppt.pptx
sub subsation seminar ppt.pptx
 
PPT ON 33/11KV SUBSTATION
PPT ON 33/11KV SUBSTATIONPPT ON 33/11KV SUBSTATION
PPT ON 33/11KV SUBSTATION
 
Load Distribution
Load DistributionLoad Distribution
Load Distribution
 
pptravi-191011011024 (1).pdf
pptravi-191011011024 (1).pdfpptravi-191011011024 (1).pdf
pptravi-191011011024 (1).pdf
 
Indusrtrial training ppt (1).pptx
Indusrtrial training ppt (1).pptxIndusrtrial training ppt (1).pptx
Indusrtrial training ppt (1).pptx
 
Ashwani kumar
Ashwani kumarAshwani kumar
Ashwani kumar
 
132 kv g.s.s chambal jaipur
132 kv g.s.s chambal jaipur132 kv g.s.s chambal jaipur
132 kv g.s.s chambal jaipur
 
Powergrid Corporation India Limited industrial training
Powergrid Corporation India Limited industrial trainingPowergrid Corporation India Limited industrial training
Powergrid Corporation India Limited industrial training
 
powergrid presentation
powergrid presentationpowergrid presentation
powergrid presentation
 
Instrumentation transformers, Types of Instrumentation Transformer & Relays
Instrumentation transformers, Types of Instrumentation Transformer & RelaysInstrumentation transformers, Types of Instrumentation Transformer & Relays
Instrumentation transformers, Types of Instrumentation Transformer & Relays
 
Substation
SubstationSubstation
Substation
 
Electrical basics
Electrical basicsElectrical basics
Electrical basics
 
rough.pptx
rough.pptxrough.pptx
rough.pptx
 

Recently uploaded

Thermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VThermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VDineshKumar4165
 
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdfAldoGarca30
 
Thermal Engineering Unit - I & II . ppt
Thermal Engineering  Unit - I & II . pptThermal Engineering  Unit - I & II . ppt
Thermal Engineering Unit - I & II . pptDineshKumar4165
 
Generative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPTGenerative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPTbhaskargani46
 
Double Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torqueDouble Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torqueBhangaleSonal
 
kiln thermal load.pptx kiln tgermal load
kiln thermal load.pptx kiln tgermal loadkiln thermal load.pptx kiln tgermal load
kiln thermal load.pptx kiln tgermal loadhamedmustafa094
 
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...Call Girls Mumbai
 
Unleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapUnleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapRishantSharmaFr
 
School management system project Report.pdf
School management system project Report.pdfSchool management system project Report.pdf
School management system project Report.pdfKamal Acharya
 
Moment Distribution Method For Btech Civil
Moment Distribution Method For Btech CivilMoment Distribution Method For Btech Civil
Moment Distribution Method For Btech CivilVinayVitekari
 
Online electricity billing project report..pdf
Online electricity billing project report..pdfOnline electricity billing project report..pdf
Online electricity billing project report..pdfKamal Acharya
 
Thermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptThermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptDineshKumar4165
 
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
COST-EFFETIVE  and Energy Efficient BUILDINGS ptxCOST-EFFETIVE  and Energy Efficient BUILDINGS ptx
COST-EFFETIVE and Energy Efficient BUILDINGS ptxJIT KUMAR GUPTA
 
Hospital management system project report.pdf
Hospital management system project report.pdfHospital management system project report.pdf
Hospital management system project report.pdfKamal Acharya
 
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptxS1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptxSCMS School of Architecture
 
Verification of thevenin's theorem for BEEE Lab (1).pptx
Verification of thevenin's theorem for BEEE Lab (1).pptxVerification of thevenin's theorem for BEEE Lab (1).pptx
Verification of thevenin's theorem for BEEE Lab (1).pptxchumtiyababu
 
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...drmkjayanthikannan
 
Orlando’s Arnold Palmer Hospital Layout Strategy-1.pptx
Orlando’s Arnold Palmer Hospital Layout Strategy-1.pptxOrlando’s Arnold Palmer Hospital Layout Strategy-1.pptx
Orlando’s Arnold Palmer Hospital Layout Strategy-1.pptxMuhammadAsimMuhammad6
 
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXssuser89054b
 

Recently uploaded (20)

Thermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VThermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - V
 
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
 
Thermal Engineering Unit - I & II . ppt
Thermal Engineering  Unit - I & II . pptThermal Engineering  Unit - I & II . ppt
Thermal Engineering Unit - I & II . ppt
 
Generative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPTGenerative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPT
 
Double Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torqueDouble Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torque
 
kiln thermal load.pptx kiln tgermal load
kiln thermal load.pptx kiln tgermal loadkiln thermal load.pptx kiln tgermal load
kiln thermal load.pptx kiln tgermal load
 
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
 
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak HamilCara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
 
Unleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapUnleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leap
 
School management system project Report.pdf
School management system project Report.pdfSchool management system project Report.pdf
School management system project Report.pdf
 
Moment Distribution Method For Btech Civil
Moment Distribution Method For Btech CivilMoment Distribution Method For Btech Civil
Moment Distribution Method For Btech Civil
 
Online electricity billing project report..pdf
Online electricity billing project report..pdfOnline electricity billing project report..pdf
Online electricity billing project report..pdf
 
Thermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptThermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.ppt
 
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
COST-EFFETIVE  and Energy Efficient BUILDINGS ptxCOST-EFFETIVE  and Energy Efficient BUILDINGS ptx
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
 
Hospital management system project report.pdf
Hospital management system project report.pdfHospital management system project report.pdf
Hospital management system project report.pdf
 
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptxS1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
 
Verification of thevenin's theorem for BEEE Lab (1).pptx
Verification of thevenin's theorem for BEEE Lab (1).pptxVerification of thevenin's theorem for BEEE Lab (1).pptx
Verification of thevenin's theorem for BEEE Lab (1).pptx
 
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
 
Orlando’s Arnold Palmer Hospital Layout Strategy-1.pptx
Orlando’s Arnold Palmer Hospital Layout Strategy-1.pptxOrlando’s Arnold Palmer Hospital Layout Strategy-1.pptx
Orlando’s Arnold Palmer Hospital Layout Strategy-1.pptx
 
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
 

132kV GSS ppt

  • 1. Submitted To:- Dr. Dinesh Birla (Professor) MR. Ashok Kumar Sharma (Associate professor) Submitted BY:- Abhishek Dosaya Roll no.- 13/003 7th sem,Btech,EE
  • 2.
  • 3. Substation:- From where electricity is transmitted or distributed. Step up for long distance transmission Step down for distribution purpose A substation generally have switching, protection, & control equipment & one or more transformers. Purpose of substation:-  Protection of transmission system.  voltage control; reducing the reactive power flow by compensation of reactive power.  Ensuring the stability of the network.  Determining the energy transfer through transmission line.  Data transmission via power line carrier for the purpose of network monitoring , control and protection.  Fault analysis and recover
  • 4.
  • 5. DEFINITION:- A bus bar is a conducting bar that carries heavy currents to supply several electric circuits. When a no. of generators or feeders operating at the same voltage level to be directly connected electrically, Bus bar are used as the common electrical component. Bus bars are copper rod or thin walled tubes and operate at constant voltage. TYPES OF BUSBARS:-  Main Bus bar  Auxiliary Bus bar One Bus bar is main Bus bar & another is spare or Auxiliary Bus bar.
  • 6. When any apparatus become faulty which is directly connected to main Bus bar then we use auxiliary bus bar to keep supply continue.
  • 7.  Lightning arrester is a protective device which provides protection against the high voltage from lightning.  A lightning arrestor has two terminal one is the high voltage terminal and one terminal is ground.  It is used only from overhead line  Zno type LA are mostly used.
  • 8.
  • 10. A circuit breaker is a equipment which can:-  break a ckt automatically under fault conditions.  make a ckt either manually or by remote control . PRINCIPLE:- A ckt breaker essentially consists of fixed & moving contacts, called electrodes under normal operating conditions, these contacts remain closed & will not open automatically until & unless the systems becomes faulty. When a fault occurs on any part of the system, the trip coils of the breaker get Energised & the moving contacts are pulled apart by some mechanism. Thus opening the circuit.
  • 11. It is generally used in on load condition. CLASSIFICATION:-  oil circuit breakers  Sulphur Hexa Fluroide circuit breakers  Air-Blast circuit breakers  vaccum circuit breakers Under training SF6 and oil circuit breaker were used in the GSS.
  • 12.
  • 13. Isolator is used When current is not flowing into the line, because there is no arc interrupting medium But Circuit breaker is used on load condition because arc interrupting medium is available.
  • 14.  Transformer is an electrical machine which works on the principle of electromagnetic induction.  It transfers electric power from one electric ckt to other with the help magnetic path(flux) on constant frequency but equal or different current voltages.  For this purpose two sets of insulated windings are wounded on a close terminated steel core.  The winding which is connected to the supply is called primary winding & that winding is connected to the load is called secondary winding.
  • 15. 1. Three limb core 2. LV winding 3. HV winding 4. LV bushings 5. HV bushings 6. Transformer oil 7. Tap changer 8. Conservator 9. Breather 10. Buchholz relay 11. Radiator
  • 16. Instrument transformers are used for measurement and protective applications together with equipments such as meters & relays. The lines in a station are operated at high voltages and carry currents of thousands of amperes. The measuring and protective devices are designed for low voltage generally 100v and currents about 5A, therefore they will not work satisfactory if mounted on the power lines. This difficulty can be overcome by using instrument transformers, which will step down the voltages and currents to the convenient level for the operation of measuring instruments & relays.
  • 17.  C.T. is an instrument transformer used for protection & metering of high values of currents. C.T. is used for reducing A.C. from higher to lower value for measurement/protection/control.  Turns Ratio normally 1:1000  IS= IP * NP / NS  CT rating 100/5 and 20/1 is not same because this is the input/output rating(not turns ratio).  Secondary of CT is short circuited due to following reasons:- 1. If the secondary is open circuited , no current flow secondary side, so no counter magnetic field , flux in the core saturates and char. Of CT changes and damage permanently 2. No of sec. turns high , so high voltage induce which can harm the persons working on the panel  CT consist of single core in high voltage side and 3 0r 4 cores in low voltage side.
  • 18.
  • 19. >
  • 20. Potential transformer (voltage transformer) is used for protection and measurement.Voltage transformer is necessary for directional, voltage, distance protection.  A PT or sometimes called VT is a step- down transformer having many primary turns but few secondary turns.  In a step-down transformer the voltage decreases and the current increases, thus voltage can be easily measured by using a low-range voltmeter instrument. Oil cooled PT A VT is a "stepdown transformer" that steps down voltage from a very high voltage level(200KV,...) to a lower level(110V). Since, the power(P=VI) in a transformer(input and output) is same, the current rises to a very high level. Thus, a very high resistance is maintained at the secondary terminal to limit the current(which appears as open circuit)
  • 21.
  • 22.
  • 23. A capacitor voltage transformer (CVT or CCVT), is a transformer used in power systems to step down extra high voltage signals and provide a low voltage signal, for metering or operating a protective relay. Capacitor Voltage Transformers also serve as coupling capacitors for coupling high frequency power line carrier signals to the transmission line.
  • 24. In practice, capacitor C1 is often constructed as a stack of smaller capacitors connected in series. This provides a large voltage drop across C1 and a relatively small voltage drop across C2. As the majority of the voltage drop is on C1, this reduces the required insulation level of the voltage transformer. This makes CVTs more economical than the wound voltage transformers under high voltage (over 100kV)
  • 25.  A relay is automatic device which senses an abnormal condition of electrical circuit and closes its contacts. These contacts in turns close and complete the circuit breaker trip coil circuit hence make the circuit breaker tripped for disconnecting the faulty portion of the electrical circuit from rest of the healthy circuit.  Based on application the protection relay can be categorized as- Primary relay. Backup relay.  Primary relay or primary protection relay is the first line of power system protection whereas backup relay is operated only when primary relay fails to be operated during fault. Hence backup relay is slower in action than primary relay.
  • 26. 1. 132 KV Transmission Line Main Protection : Switched distance scheme (fed from bus PT). Backup Protection: 3 Nos. directional IDMT O/L Relays and 1 No. Directional IDMT E/L relay. 2. 33 KV lines Non-directional IDMT 3 O/L and 1 E/L relays. 3. 11 KV lines Non-directional IDMT 2 O/L and 1 E/L relays.
  • 27. 132/33KV,40/ 50 MVA 3 nos O/L Relay 1 no Directio nal E/L Relay 3 nos O/L Relay 1 no E/L Relay Differential Relay Over flux Relay Buchholz Relay OLTC Buchholz Relay PRV Relay OT Trip Relay WT Trip Relay
  • 28.  For compensate the reactive power, we use capacitor bank.  Advantage-  It reduces Line current of the system.  It improves voltage level of the load.  It improves power factor. It is subdivided into two categories:- 1. Shunt capacitor 2. Series Capacitor
  • 29. Inductive load increase, Reactive power more absorb, Q(+) increase, power factor decrease To deliver the required active power, I increases so the ampere burden increases and more losses take place or voltage dip(black out situations)
  • 30. The main reason for doing earthing in electrical network is for the safety. When all metallic parts in electrical equipments are grounded then if the insulation inside the equipments fails there are no dangerous voltages present in the equipment case. To save human life from danger of electrical shock or death i.e. To provide an alternative path for the fault current to flow To lightning overvoltage protection Methods of earthing arrangments at 132 kv GSS:  pipe earthing  plate earthing
  • 31.
  • 32.
  • 33.  Control room is a place from where we control all the actions on all equipment in the yard.  The control room work on 110V Dc supply. These supply are taken from the station transformer By convert ac to dc through the rectifiers. In the case of failure of ac supply. DC supply voltage will be available automatically from the lead acid battery.  Control Panels: Control panels contain meters, control switches and recorders. These are used to measure all readings and to control the substation equipment, to send power from one circuit to another or to open or shut down circuits when needed.  Relay Panels: In Which the different types of relays are present for different fault protection, and indicate that type of fault
  • 34.
  • 35. The control room work on 110V Dc supply. These supply are taken from the station transformer By convert ac to dc through the rectifiers. In the case of failure of ac supply. DC supply voltage will be available automatically from the lead acid battery. In battery rooms 55 batteries of each 2v is connected in series to provide 110v.
  • 36.  For exchange of dates and transfer message between grid substation,voice communication is necesarry. for this purpose high frequency carrier current is transmitted on same transmission line on which power is transmitted.  Hence such communication is called “power line communication.  High frequency signal is transmitted and received Through coupling capacitor and is trapped by line trap unit(parallel combination of L and C).
  • 37.
  • 38. Its was great experience for me, I have more cleared my theoretical knowledge with the practical knowledge and learn that how do complex distribution be successful so that we may get continuous power supply.