SlideShare a Scribd company logo
1 of 2
Unit V – Nagrath and Kothari Questions
1. A 50 Hz transmission line 500Km long with constants given below ties upto 2
   large power areas
   R = 0.11ohm/km;         L = 1.45mH/Km;           C = 0.009uF/Km;         G=0
   Find the steady state stability limit if |Vs| = |Vr| = 200KV(constant).
   What will be the steady state stability limit if line capacitance is also neglected?
   What will be the steady state stability limit if line resistance is also neglected?
   Comment on the results.                          [140.1MW,130.63MW, 175.67MW]

2. A power deficient area receives 50MW over a tie line from another area. The
   maximum steady state capacity of the line is 100MW. Find the allowable sudden
   load that can be switched on without loss of stability.          [72.54MW]

3. A synchronous motor is drawing 30% of the maximum steady state power from
   an infinite bus bar. If the load on the motor is suddenly increased by 100%, would
   the synchronism be lost? If not, what is the maximum excursion of torque angle
   about the new steady state rotor position?             [580]

4. The transfer reactances between a generator and an infinite bus bar operating at
   200KV under various conditions on the interconnector are:
   Prefault:         150ohm per phase
   During Fault: 400ohm/phase
   Post Fault:       200ohm/phase
   If the fault is cleared when the rotor has advanced 600 electrical from its prefault
   position, determine the maximum load that could be transferred without loss of
   stability.                                                    [127.3MW]

5. A synchronous generator is feeding 250MW to a large 50Hz n/w over a double
   circuit transmission line. The maximum steady state power that can be transmitted
   over the line with both circuits in operation is 500MW and is 300MW with any
   one of the circuits.
   A solid 3 phase fault occurring at the n/w end of one of the lines causes it to trip.
   Estimate the critical clearing angle in which the circuit breakers must trip so the
   synchronism is not lost.
   What further information is needed to estimate the critical clearing time?
                                                           [530, M is required to find tc]
6. A synchronous generator represented by a voltage source of 1.05pu in series with
   a transient reactance of j0.15 pu and an inertia constant H = 0.5sec, is connected
   to an infinite inertia system through a transmission line. The line has a series
   reactance of j0.30pu, while the infinite inertia system is represented by a voltage
   source of 1.0pu in series with a transient reactance of j0.20pu.
   The generator is transmitting an active power of 1.0pu when a 3 phase fault
   occurs at its terminals. If the fault is cleared in 100msec, determine if the system
   will remain stable by calculating the swing curve.                     [Stable]
7. A synchronous generator represented by a voltage source of 1.15pu in series with
   a transient reactance is connected to a large power system with voltage 1.0pu
   through a power n/w. The equivalent transient transfer reactance X between
   voltage sources is j0.50pu.
   After the occurrence of a 3 phase to ground fault on one of the lines of the power
   n/w, 2 of the line circuit breakers A and B operate sequentially as follows with
   corresponding transient transfer reactance given therein.
       • Short circuit occurs at delta= 300, A opens instantaneously to make X =
           3.0pu.
       • At delta= 600, A recloses, X = 6.0pu.
       • At delta= 750, A reopens.
       • At delta= 900, B also opens to clear the fault making X = 0.60pu.
   Check if the system will operate with stability.             [Unstable]

8.  A 50 Hz synchronous generator with inertia constant H = 2.5 msec and a
   transient reactance of 0.2pu feeds 0.80pu active power into an infinite bus(voltage
   1pu) at 0.8 lagging pf via a n/w with an equivalent reactance of 0.25pu.
   A 3 phase fault is sustained for 150msec across generator terminals. Determine
   through swing curve calculation the torque angle, 250msec, after fault initiation.
                                                                [63.360]
9. A 50Hz, 500MVA, 400KV generator(with transformer) is connected to a 400KV
   infinite bus bar through an interconnector. The generator has H = 2.5 MJ/MVA,
   voltage behind transient reactance of 450KV and is loaded 450MW. The transfer
   reactances between generator and bus bar under various conditions are:
   Prefault:       0.5pu
   During Fault: 1.0pu
   Post Fault:     0.75pu
   Calculate the swing curve using intervals of 0.05 sec and assuming that the fault
   is cleared at 0.15sec.                                              [Stable]

More Related Content

What's hot

Voltage Stability Indices: Taxonomy, Formulation and Calculation algorithm
Voltage Stability Indices: Taxonomy, Formulation and Calculation algorithmVoltage Stability Indices: Taxonomy, Formulation and Calculation algorithm
Voltage Stability Indices: Taxonomy, Formulation and Calculation algorithmcimran15
 
60232804 ppt-compensation-techniques-in-ac-transmission-system-using-c
60232804 ppt-compensation-techniques-in-ac-transmission-system-using-c60232804 ppt-compensation-techniques-in-ac-transmission-system-using-c
60232804 ppt-compensation-techniques-in-ac-transmission-system-using-cABHISHEK RAI
 
Power system voltage stability
Power system voltage stabilityPower system voltage stability
Power system voltage stabilityAkash Choudhary
 
Power system analysis material -Mathankumar.s VMKVEC
Power system analysis material -Mathankumar.s  VMKVECPower system analysis material -Mathankumar.s  VMKVEC
Power system analysis material -Mathankumar.s VMKVECMathankumar S
 
Unit 1 Power System Stability
Unit 1 Power System Stability Unit 1 Power System Stability
Unit 1 Power System Stability SANTOSH GADEKAR
 
Three phase transformers
Three phase transformersThree phase transformers
Three phase transformersZiyaulhaq
 
Economic operation of power system
Economic operation of power systemEconomic operation of power system
Economic operation of power systemBalaram Das
 
static series synchronus compensator
static series synchronus compensatorstatic series synchronus compensator
static series synchronus compensatorbhupendra kumar
 
Answer assigment stabilitas & control
Answer assigment stabilitas & controlAnswer assigment stabilitas & control
Answer assigment stabilitas & controlsuparman unkhair
 
Unit 5 Economic Load Dispatch and Unit Commitment
Unit 5 Economic Load Dispatch and Unit CommitmentUnit 5 Economic Load Dispatch and Unit Commitment
Unit 5 Economic Load Dispatch and Unit CommitmentSANTOSH GADEKAR
 
Application of Capacitors to Distribution System and Voltage Regulation
Application of Capacitors to Distribution System and Voltage RegulationApplication of Capacitors to Distribution System and Voltage Regulation
Application of Capacitors to Distribution System and Voltage RegulationAmeen San
 
Per unit calculation
Per unit calculationPer unit calculation
Per unit calculationobaidurbd
 
Power angle curve calclation
Power angle curve calclationPower angle curve calclation
Power angle curve calclationSanthi Anumula
 
Symmetrical fault analysis problem
Symmetrical fault analysis problemSymmetrical fault analysis problem
Symmetrical fault analysis problemAsha Anu Kurian
 

What's hot (20)

Voltage Stability Indices: Taxonomy, Formulation and Calculation algorithm
Voltage Stability Indices: Taxonomy, Formulation and Calculation algorithmVoltage Stability Indices: Taxonomy, Formulation and Calculation algorithm
Voltage Stability Indices: Taxonomy, Formulation and Calculation algorithm
 
60232804 ppt-compensation-techniques-in-ac-transmission-system-using-c
60232804 ppt-compensation-techniques-in-ac-transmission-system-using-c60232804 ppt-compensation-techniques-in-ac-transmission-system-using-c
60232804 ppt-compensation-techniques-in-ac-transmission-system-using-c
 
Power system voltage stability
Power system voltage stabilityPower system voltage stability
Power system voltage stability
 
Power system analysis material -Mathankumar.s VMKVEC
Power system analysis material -Mathankumar.s  VMKVECPower system analysis material -Mathankumar.s  VMKVEC
Power system analysis material -Mathankumar.s VMKVEC
 
Unit 1 Power System Stability
Unit 1 Power System Stability Unit 1 Power System Stability
Unit 1 Power System Stability
 
Load flow studies
Load flow studiesLoad flow studies
Load flow studies
 
Introduction
IntroductionIntroduction
Introduction
 
Reactive power compensation
Reactive power compensationReactive power compensation
Reactive power compensation
 
Three phase transformers
Three phase transformersThree phase transformers
Three phase transformers
 
Power System Stablity
Power System StablityPower System Stablity
Power System Stablity
 
Economic operation of power system
Economic operation of power systemEconomic operation of power system
Economic operation of power system
 
static series synchronus compensator
static series synchronus compensatorstatic series synchronus compensator
static series synchronus compensator
 
Answer assigment stabilitas & control
Answer assigment stabilitas & controlAnswer assigment stabilitas & control
Answer assigment stabilitas & control
 
Unit 5 Economic Load Dispatch and Unit Commitment
Unit 5 Economic Load Dispatch and Unit CommitmentUnit 5 Economic Load Dispatch and Unit Commitment
Unit 5 Economic Load Dispatch and Unit Commitment
 
Sssc
SsscSssc
Sssc
 
Application of Capacitors to Distribution System and Voltage Regulation
Application of Capacitors to Distribution System and Voltage RegulationApplication of Capacitors to Distribution System and Voltage Regulation
Application of Capacitors to Distribution System and Voltage Regulation
 
Per unit calculation
Per unit calculationPer unit calculation
Per unit calculation
 
gauss seidel method
gauss seidel methodgauss seidel method
gauss seidel method
 
Power angle curve calclation
Power angle curve calclationPower angle curve calclation
Power angle curve calclation
 
Symmetrical fault analysis problem
Symmetrical fault analysis problemSymmetrical fault analysis problem
Symmetrical fault analysis problem
 

Viewers also liked

Questions practice unit iv
Questions practice unit ivQuestions practice unit iv
Questions practice unit ivAbha Tripathi
 
Unit 2 samplesolutions
Unit 2 samplesolutionsUnit 2 samplesolutions
Unit 2 samplesolutionsAbha Tripathi
 
Unit 2 Questions_Nagrath kothari
Unit 2 Questions_Nagrath kothariUnit 2 Questions_Nagrath kothari
Unit 2 Questions_Nagrath kothariAbha Tripathi
 
Practice questions for unit ii
Practice questions for unit iiPractice questions for unit ii
Practice questions for unit iiAbha Tripathi
 
Unit1 And 2 Sample Solutions
Unit1 And 2 Sample SolutionsUnit1 And 2 Sample Solutions
Unit1 And 2 Sample SolutionsAbha Tripathi
 
Step1 Single Line Diagram
Step1 Single Line DiagramStep1 Single Line Diagram
Step1 Single Line Diagramnanonon
 
TPs-TDs : Travaux Pratiques & Dérigés (version 2014-2017) Génie Electrique/Ex...
TPs-TDs : Travaux Pratiques & Dérigés (version 2014-2017) Génie Electrique/Ex...TPs-TDs : Travaux Pratiques & Dérigés (version 2014-2017) Génie Electrique/Ex...
TPs-TDs : Travaux Pratiques & Dérigés (version 2014-2017) Génie Electrique/Ex...Mohammed TAMALI
 
Problemas resueltos cortocircuito trifasico
Problemas resueltos cortocircuito trifasicoProblemas resueltos cortocircuito trifasico
Problemas resueltos cortocircuito trifasicopaulelrapido
 
Unit 1, Power system Analysis
Unit 1, Power system AnalysisUnit 1, Power system Analysis
Unit 1, Power system AnalysisAbha Tripathi
 
Newton Raphson method for load flow analysis
Newton Raphson method for load flow analysisNewton Raphson method for load flow analysis
Newton Raphson method for load flow analysisdivyanshuprakashrock
 
Ee 1351 power system analysis
Ee 1351 power system analysisEe 1351 power system analysis
Ee 1351 power system analysisHari Kumar
 
Fault Level Calculation
Fault Level CalculationFault Level Calculation
Fault Level CalculationDinesh Sarda
 
File 1 power system fault analysis
File 1 power system fault analysisFile 1 power system fault analysis
File 1 power system fault analysiskirkusawi
 

Viewers also liked (20)

Swing equation
Swing equationSwing equation
Swing equation
 
Questions practice unit iv
Questions practice unit ivQuestions practice unit iv
Questions practice unit iv
 
Questions unit4
Questions unit4Questions unit4
Questions unit4
 
Unit4questions
Unit4questionsUnit4questions
Unit4questions
 
Unit1questions
Unit1questionsUnit1questions
Unit1questions
 
Unit 2 samplesolutions
Unit 2 samplesolutionsUnit 2 samplesolutions
Unit 2 samplesolutions
 
Unit 2 Questions_Nagrath kothari
Unit 2 Questions_Nagrath kothariUnit 2 Questions_Nagrath kothari
Unit 2 Questions_Nagrath kothari
 
Practice questions for unit ii
Practice questions for unit iiPractice questions for unit ii
Practice questions for unit ii
 
Unit1 And 2 Sample Solutions
Unit1 And 2 Sample SolutionsUnit1 And 2 Sample Solutions
Unit1 And 2 Sample Solutions
 
Solutions -unit4
Solutions  -unit4Solutions  -unit4
Solutions -unit4
 
Practice questions
Practice questionsPractice questions
Practice questions
 
Step1 Single Line Diagram
Step1 Single Line DiagramStep1 Single Line Diagram
Step1 Single Line Diagram
 
TPs-TDs : Travaux Pratiques & Dérigés (version 2014-2017) Génie Electrique/Ex...
TPs-TDs : Travaux Pratiques & Dérigés (version 2014-2017) Génie Electrique/Ex...TPs-TDs : Travaux Pratiques & Dérigés (version 2014-2017) Génie Electrique/Ex...
TPs-TDs : Travaux Pratiques & Dérigés (version 2014-2017) Génie Electrique/Ex...
 
Problemas resueltos cortocircuito trifasico
Problemas resueltos cortocircuito trifasicoProblemas resueltos cortocircuito trifasico
Problemas resueltos cortocircuito trifasico
 
Unit 1, Power system Analysis
Unit 1, Power system AnalysisUnit 1, Power system Analysis
Unit 1, Power system Analysis
 
Newton Raphson method for load flow analysis
Newton Raphson method for load flow analysisNewton Raphson method for load flow analysis
Newton Raphson method for load flow analysis
 
Ee 1351 power system analysis
Ee 1351 power system analysisEe 1351 power system analysis
Ee 1351 power system analysis
 
Fault Level Calculation
Fault Level CalculationFault Level Calculation
Fault Level Calculation
 
load flow 1
 load flow 1 load flow 1
load flow 1
 
File 1 power system fault analysis
File 1 power system fault analysisFile 1 power system fault analysis
File 1 power system fault analysis
 

Similar to Unit v

Power system Stability, Equal area criteria
Power system Stability, Equal area criteriaPower system Stability, Equal area criteria
Power system Stability, Equal area criteriaAbha Tripathi
 
Assignment & solution (selected)
Assignment & solution (selected)Assignment & solution (selected)
Assignment & solution (selected)efrataderebe
 
Power system stability
Power  system  stabilityPower  system  stability
Power system stabilityrohit kumar
 
Three phase balanced load circuits and synchronous generators
Three phase balanced load circuits and synchronous generatorsThree phase balanced load circuits and synchronous generators
Three phase balanced load circuits and synchronous generatorsIsham Rashik
 
Emec 1 bank nee 301
Emec 1 bank nee 301Emec 1 bank nee 301
Emec 1 bank nee 301Ravi Anand
 
EE6501 Power System Analysis Rejinpaul_Important_Questions
EE6501 Power System Analysis Rejinpaul_Important_QuestionsEE6501 Power System Analysis Rejinpaul_Important_Questions
EE6501 Power System Analysis Rejinpaul_Important_QuestionsSanthosh Kumar
 
Tugas stabilitas dan sistem kontrol (prof.lomi
Tugas stabilitas dan sistem kontrol (prof.lomiTugas stabilitas dan sistem kontrol (prof.lomi
Tugas stabilitas dan sistem kontrol (prof.lomiDavid Suban Koten
 
NEW APPROACH OF DESIGNING AND EXPLOATATION OF ELECTRICAL TRACTION SUBSTATIONS
NEW APPROACH OF DESIGNING AND EXPLOATATION OF ELECTRICAL TRACTION SUBSTATIONSNEW APPROACH OF DESIGNING AND EXPLOATATION OF ELECTRICAL TRACTION SUBSTATIONS
NEW APPROACH OF DESIGNING AND EXPLOATATION OF ELECTRICAL TRACTION SUBSTATIONSDženan Ćelić
 
Fractional frequency Transmission System
Fractional frequency Transmission SystemFractional frequency Transmission System
Fractional frequency Transmission SystemSidharth Goyal
 
Hv module 3 Impulse voltage generation
Hv module 3 Impulse voltage generationHv module 3 Impulse voltage generation
Hv module 3 Impulse voltage generationAsha Anu Kurian
 
Infinite bus bar in power system
Infinite bus bar in power systemInfinite bus bar in power system
Infinite bus bar in power systemEklavya Sharma
 
Electrical Power Systems Synchronous Generator
Electrical Power Systems Synchronous GeneratorElectrical Power Systems Synchronous Generator
Electrical Power Systems Synchronous GeneratorMubarek Kurt
 
A high voltage power supply operating under a magnetic field
A high voltage power supply operating under a magnetic fieldA high voltage power supply operating under a magnetic field
A high voltage power supply operating under a magnetic fieldLove Kiss
 
Symmetrical Fault Analysis
Symmetrical Fault AnalysisSymmetrical Fault Analysis
Symmetrical Fault AnalysisSANTOSH GADEKAR
 
Unit 2 Reactive Power Management
Unit 2 Reactive Power ManagementUnit 2 Reactive Power Management
Unit 2 Reactive Power ManagementSANTOSH GADEKAR
 

Similar to Unit v (20)

Power system Stability, Equal area criteria
Power system Stability, Equal area criteriaPower system Stability, Equal area criteria
Power system Stability, Equal area criteria
 
Assignment & solution (selected)
Assignment & solution (selected)Assignment & solution (selected)
Assignment & solution (selected)
 
Power system stability
Power  system  stabilityPower  system  stability
Power system stability
 
Three phase balanced load circuits and synchronous generators
Three phase balanced load circuits and synchronous generatorsThree phase balanced load circuits and synchronous generators
Three phase balanced load circuits and synchronous generators
 
Emec 1 bank nee 301
Emec 1 bank nee 301Emec 1 bank nee 301
Emec 1 bank nee 301
 
EE6501 Power System Analysis Rejinpaul_Important_Questions
EE6501 Power System Analysis Rejinpaul_Important_QuestionsEE6501 Power System Analysis Rejinpaul_Important_Questions
EE6501 Power System Analysis Rejinpaul_Important_Questions
 
Tugas stabilitas dan sistem kontrol (prof.lomi
Tugas stabilitas dan sistem kontrol (prof.lomiTugas stabilitas dan sistem kontrol (prof.lomi
Tugas stabilitas dan sistem kontrol (prof.lomi
 
NEW APPROACH OF DESIGNING AND EXPLOATATION OF ELECTRICAL TRACTION SUBSTATIONS
NEW APPROACH OF DESIGNING AND EXPLOATATION OF ELECTRICAL TRACTION SUBSTATIONSNEW APPROACH OF DESIGNING AND EXPLOATATION OF ELECTRICAL TRACTION SUBSTATIONS
NEW APPROACH OF DESIGNING AND EXPLOATATION OF ELECTRICAL TRACTION SUBSTATIONS
 
Fractional frequency Transmission System
Fractional frequency Transmission SystemFractional frequency Transmission System
Fractional frequency Transmission System
 
A
AA
A
 
EMEC-II, unit 1
EMEC-II, unit 1EMEC-II, unit 1
EMEC-II, unit 1
 
Hv module 3 Impulse voltage generation
Hv module 3 Impulse voltage generationHv module 3 Impulse voltage generation
Hv module 3 Impulse voltage generation
 
Lecture 02.pptx
Lecture 02.pptxLecture 02.pptx
Lecture 02.pptx
 
Infinite bus bar in power system
Infinite bus bar in power systemInfinite bus bar in power system
Infinite bus bar in power system
 
Electrical Power Systems Synchronous Generator
Electrical Power Systems Synchronous GeneratorElectrical Power Systems Synchronous Generator
Electrical Power Systems Synchronous Generator
 
A high voltage power supply operating under a magnetic field
A high voltage power supply operating under a magnetic fieldA high voltage power supply operating under a magnetic field
A high voltage power supply operating under a magnetic field
 
ALL DAY EFFICIENCY
ALL DAY EFFICIENCYALL DAY EFFICIENCY
ALL DAY EFFICIENCY
 
Symmetrical Fault Analysis
Symmetrical Fault AnalysisSymmetrical Fault Analysis
Symmetrical Fault Analysis
 
3 phase current source inverter
3 phase  current  source  inverter3 phase  current  source  inverter
3 phase current source inverter
 
Unit 2 Reactive Power Management
Unit 2 Reactive Power ManagementUnit 2 Reactive Power Management
Unit 2 Reactive Power Management
 

More from Abha Tripathi

Unit1 and 2 sample solutions
Unit1 and 2 sample solutionsUnit1 and 2 sample solutions
Unit1 and 2 sample solutionsAbha Tripathi
 
Non Conventional (Renewable) Energy Sources 01
Non Conventional (Renewable) Energy Sources 01Non Conventional (Renewable) Energy Sources 01
Non Conventional (Renewable) Energy Sources 01Abha Tripathi
 
Conventional sources of energy (power generation) 01
Conventional sources of energy (power generation) 01Conventional sources of energy (power generation) 01
Conventional sources of energy (power generation) 01Abha Tripathi
 
Symmetrical components
Symmetrical componentsSymmetrical components
Symmetrical componentsAbha Tripathi
 
Representation of power system components
Representation of power system componentsRepresentation of power system components
Representation of power system componentsAbha Tripathi
 
Gas and diesel Plant
Gas and diesel PlantGas and diesel Plant
Gas and diesel PlantAbha Tripathi
 
NPP, Nuclear Power Plant,
NPP, Nuclear Power Plant, NPP, Nuclear Power Plant,
NPP, Nuclear Power Plant, Abha Tripathi
 
Questions From 1st Unit Nagrath
Questions From 1st Unit NagrathQuestions From 1st Unit Nagrath
Questions From 1st Unit NagrathAbha Tripathi
 
Grading The Insulator Problem
Grading The Insulator ProblemGrading The Insulator Problem
Grading The Insulator ProblemAbha Tripathi
 

More from Abha Tripathi (17)

Questions unit3
Questions unit3Questions unit3
Questions unit3
 
Unit1 and 2 sample solutions
Unit1 and 2 sample solutionsUnit1 and 2 sample solutions
Unit1 and 2 sample solutions
 
Non Conventional (Renewable) Energy Sources 01
Non Conventional (Renewable) Energy Sources 01Non Conventional (Renewable) Energy Sources 01
Non Conventional (Renewable) Energy Sources 01
 
Conventional sources of energy (power generation) 01
Conventional sources of energy (power generation) 01Conventional sources of energy (power generation) 01
Conventional sources of energy (power generation) 01
 
Symmetrical components
Symmetrical componentsSymmetrical components
Symmetrical components
 
Representation of power system components
Representation of power system componentsRepresentation of power system components
Representation of power system components
 
Questions unit2 ch3
Questions unit2 ch3Questions unit2 ch3
Questions unit2 ch3
 
Renewable Sor
Renewable SorRenewable Sor
Renewable Sor
 
Gas and diesel Plant
Gas and diesel PlantGas and diesel Plant
Gas and diesel Plant
 
NPP, Nuclear Power Plant,
NPP, Nuclear Power Plant, NPP, Nuclear Power Plant,
NPP, Nuclear Power Plant,
 
Hydro E
Hydro EHydro E
Hydro E
 
Thermal power plant
Thermal power plantThermal power plant
Thermal power plant
 
Questions From 1st Unit Nagrath
Questions From 1st Unit NagrathQuestions From 1st Unit Nagrath
Questions From 1st Unit Nagrath
 
Unit 3 Part 1
Unit 3 Part 1Unit 3 Part 1
Unit 3 Part 1
 
Grading The Insulator Problem
Grading The Insulator ProblemGrading The Insulator Problem
Grading The Insulator Problem
 
Dc Distribution
Dc DistributionDc Distribution
Dc Distribution
 
Dc Distributed Load
Dc Distributed LoadDc Distributed Load
Dc Distributed Load
 

Recently uploaded

SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxSOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxiammrhaywood
 
Q4-W6-Restating Informational Text Grade 3
Q4-W6-Restating Informational Text Grade 3Q4-W6-Restating Informational Text Grade 3
Q4-W6-Restating Informational Text Grade 3JemimahLaneBuaron
 
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in DelhiRussian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhikauryashika82
 
The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13Steve Thomason
 
Interactive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communicationInteractive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communicationnomboosow
 
9548086042 for call girls in Indira Nagar with room service
9548086042  for call girls in Indira Nagar  with room service9548086042  for call girls in Indira Nagar  with room service
9548086042 for call girls in Indira Nagar with room servicediscovermytutordmt
 
1029 - Danh muc Sach Giao Khoa 10 . pdf
1029 -  Danh muc Sach Giao Khoa 10 . pdf1029 -  Danh muc Sach Giao Khoa 10 . pdf
1029 - Danh muc Sach Giao Khoa 10 . pdfQucHHunhnh
 
Class 11th Physics NEET formula sheet pdf
Class 11th Physics NEET formula sheet pdfClass 11th Physics NEET formula sheet pdf
Class 11th Physics NEET formula sheet pdfAyushMahapatra5
 
Student login on Anyboli platform.helpin
Student login on Anyboli platform.helpinStudent login on Anyboli platform.helpin
Student login on Anyboli platform.helpinRaunakKeshri1
 
Disha NEET Physics Guide for classes 11 and 12.pdf
Disha NEET Physics Guide for classes 11 and 12.pdfDisha NEET Physics Guide for classes 11 and 12.pdf
Disha NEET Physics Guide for classes 11 and 12.pdfchloefrazer622
 
Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17Celine George
 
Web & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdfWeb & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdfJayanti Pande
 
Introduction to Nonprofit Accounting: The Basics
Introduction to Nonprofit Accounting: The BasicsIntroduction to Nonprofit Accounting: The Basics
Introduction to Nonprofit Accounting: The BasicsTechSoup
 
Sanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfSanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfsanyamsingh5019
 
Accessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactAccessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactdawncurless
 
1029-Danh muc Sach Giao Khoa khoi 6.pdf
1029-Danh muc Sach Giao Khoa khoi  6.pdf1029-Danh muc Sach Giao Khoa khoi  6.pdf
1029-Danh muc Sach Giao Khoa khoi 6.pdfQucHHunhnh
 
Z Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot GraphZ Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot GraphThiyagu K
 

Recently uploaded (20)

SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxSOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
 
Q4-W6-Restating Informational Text Grade 3
Q4-W6-Restating Informational Text Grade 3Q4-W6-Restating Informational Text Grade 3
Q4-W6-Restating Informational Text Grade 3
 
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in DelhiRussian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
 
The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13
 
Interactive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communicationInteractive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communication
 
INDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptx
INDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptxINDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptx
INDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptx
 
9548086042 for call girls in Indira Nagar with room service
9548086042  for call girls in Indira Nagar  with room service9548086042  for call girls in Indira Nagar  with room service
9548086042 for call girls in Indira Nagar with room service
 
Mattingly "AI & Prompt Design: The Basics of Prompt Design"
Mattingly "AI & Prompt Design: The Basics of Prompt Design"Mattingly "AI & Prompt Design: The Basics of Prompt Design"
Mattingly "AI & Prompt Design: The Basics of Prompt Design"
 
1029 - Danh muc Sach Giao Khoa 10 . pdf
1029 -  Danh muc Sach Giao Khoa 10 . pdf1029 -  Danh muc Sach Giao Khoa 10 . pdf
1029 - Danh muc Sach Giao Khoa 10 . pdf
 
Class 11th Physics NEET formula sheet pdf
Class 11th Physics NEET formula sheet pdfClass 11th Physics NEET formula sheet pdf
Class 11th Physics NEET formula sheet pdf
 
Student login on Anyboli platform.helpin
Student login on Anyboli platform.helpinStudent login on Anyboli platform.helpin
Student login on Anyboli platform.helpin
 
Disha NEET Physics Guide for classes 11 and 12.pdf
Disha NEET Physics Guide for classes 11 and 12.pdfDisha NEET Physics Guide for classes 11 and 12.pdf
Disha NEET Physics Guide for classes 11 and 12.pdf
 
Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17
 
Web & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdfWeb & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdf
 
Código Creativo y Arte de Software | Unidad 1
Código Creativo y Arte de Software | Unidad 1Código Creativo y Arte de Software | Unidad 1
Código Creativo y Arte de Software | Unidad 1
 
Introduction to Nonprofit Accounting: The Basics
Introduction to Nonprofit Accounting: The BasicsIntroduction to Nonprofit Accounting: The Basics
Introduction to Nonprofit Accounting: The Basics
 
Sanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfSanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdf
 
Accessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactAccessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impact
 
1029-Danh muc Sach Giao Khoa khoi 6.pdf
1029-Danh muc Sach Giao Khoa khoi  6.pdf1029-Danh muc Sach Giao Khoa khoi  6.pdf
1029-Danh muc Sach Giao Khoa khoi 6.pdf
 
Z Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot GraphZ Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot Graph
 

Unit v

  • 1. Unit V – Nagrath and Kothari Questions 1. A 50 Hz transmission line 500Km long with constants given below ties upto 2 large power areas R = 0.11ohm/km; L = 1.45mH/Km; C = 0.009uF/Km; G=0 Find the steady state stability limit if |Vs| = |Vr| = 200KV(constant). What will be the steady state stability limit if line capacitance is also neglected? What will be the steady state stability limit if line resistance is also neglected? Comment on the results. [140.1MW,130.63MW, 175.67MW] 2. A power deficient area receives 50MW over a tie line from another area. The maximum steady state capacity of the line is 100MW. Find the allowable sudden load that can be switched on without loss of stability. [72.54MW] 3. A synchronous motor is drawing 30% of the maximum steady state power from an infinite bus bar. If the load on the motor is suddenly increased by 100%, would the synchronism be lost? If not, what is the maximum excursion of torque angle about the new steady state rotor position? [580] 4. The transfer reactances between a generator and an infinite bus bar operating at 200KV under various conditions on the interconnector are: Prefault: 150ohm per phase During Fault: 400ohm/phase Post Fault: 200ohm/phase If the fault is cleared when the rotor has advanced 600 electrical from its prefault position, determine the maximum load that could be transferred without loss of stability. [127.3MW] 5. A synchronous generator is feeding 250MW to a large 50Hz n/w over a double circuit transmission line. The maximum steady state power that can be transmitted over the line with both circuits in operation is 500MW and is 300MW with any one of the circuits. A solid 3 phase fault occurring at the n/w end of one of the lines causes it to trip. Estimate the critical clearing angle in which the circuit breakers must trip so the synchronism is not lost. What further information is needed to estimate the critical clearing time? [530, M is required to find tc] 6. A synchronous generator represented by a voltage source of 1.05pu in series with a transient reactance of j0.15 pu and an inertia constant H = 0.5sec, is connected to an infinite inertia system through a transmission line. The line has a series reactance of j0.30pu, while the infinite inertia system is represented by a voltage source of 1.0pu in series with a transient reactance of j0.20pu. The generator is transmitting an active power of 1.0pu when a 3 phase fault occurs at its terminals. If the fault is cleared in 100msec, determine if the system will remain stable by calculating the swing curve. [Stable]
  • 2. 7. A synchronous generator represented by a voltage source of 1.15pu in series with a transient reactance is connected to a large power system with voltage 1.0pu through a power n/w. The equivalent transient transfer reactance X between voltage sources is j0.50pu. After the occurrence of a 3 phase to ground fault on one of the lines of the power n/w, 2 of the line circuit breakers A and B operate sequentially as follows with corresponding transient transfer reactance given therein. • Short circuit occurs at delta= 300, A opens instantaneously to make X = 3.0pu. • At delta= 600, A recloses, X = 6.0pu. • At delta= 750, A reopens. • At delta= 900, B also opens to clear the fault making X = 0.60pu. Check if the system will operate with stability. [Unstable] 8. A 50 Hz synchronous generator with inertia constant H = 2.5 msec and a transient reactance of 0.2pu feeds 0.80pu active power into an infinite bus(voltage 1pu) at 0.8 lagging pf via a n/w with an equivalent reactance of 0.25pu. A 3 phase fault is sustained for 150msec across generator terminals. Determine through swing curve calculation the torque angle, 250msec, after fault initiation. [63.360] 9. A 50Hz, 500MVA, 400KV generator(with transformer) is connected to a 400KV infinite bus bar through an interconnector. The generator has H = 2.5 MJ/MVA, voltage behind transient reactance of 450KV and is loaded 450MW. The transfer reactances between generator and bus bar under various conditions are: Prefault: 0.5pu During Fault: 1.0pu Post Fault: 0.75pu Calculate the swing curve using intervals of 0.05 sec and assuming that the fault is cleared at 0.15sec. [Stable]