Criteria For The Load Flow
Study
1. Collection of all data about the Nablus network
including the one-line diagram, information about the
power stations, transformers, transmission lines and
loads.
2. Investigating the problems from which the Nablus
network suffers in max., min load & fault condition
3. Applying method of reactive power compensation to
improve the operation (using tap changer transformer,
capacitor bank)
4. Performing the economical analysis of the saving
achieved by the implementation of reactive power
compensation
CH:2 Existing System
The present load in the West Bank is supplied from
several points within the IEC network. There are supply
points at
22 KV supplying Qalailya and Tulkarm
33 KV feeders from Beisan (in
Israel)supplying Jenin ,Tubas and
Nablus as well as feeders from M.
Afraym and feeders from portable
substations.
Load Forcast
3.1: Element Of The Network
A. Sources
. Generators are one of the essential components of the power
systems. Synchronous generators are widely used in power
systems.
. Nablus are fed from 3 connection point by Israel Electrical
Company (IEC), at 33KV.
1.Asker (odeleh & Almeslekh) →→→30MVA namely
2.Quseen →→→18MVA namely
3.Innab →→→5MVA namely
B. Transformers & load
• There are two type of Transformer (power &
distribution Transformer ) which is ∆-y connected
• So, the source always balanced without looking to the
load since the P.T is ∆-y ground connected
• The distribution Transformer capacity & its voltage
are summarized in table (1)
• There are also 3 power Transformer with (10MVA
capacity,33/6.6KV& %Tap=±12 ;for 17 taps with1.5% for each step
changer)
• Note the impedance of each transformer are determined by the
typical value at ETAP program
• The loads will be seen later in the table of L.F of transformer
C.Transmission Line
• There are two type of conductor
1.O.H lines →→→ACSR
2.cables →→→ cu XLPE
which have these rating as in table (2)
. In Quseen they use double T.L (3*95mm2ACSR) for the
transmission of power since the current is above 400A in max
load
3.2 : Electrical Problem In The Network
1. High drop voltage
2. Low power factor
3. Low load factor at most of distribution transformer which
reduce the efficiency of transformer & so increase the losses
(the electrical losses in distribution network must not exceed
8-10 % from total active power)
4. Exceeding the permissible capacity of each connection point
MVA
Remedy
1. High drop voltage & low power factor problem
• It is important to keep the power factor above 0.92 on the
distribution transformer so as to minimize the electrical
losses in the network & do not paying penalties
• For max load the voltage of buses must rise to
(1.05Vnom<= Vbus <=1.1Vnom) as we can to decrease the
current & so to decrease the losses
• The first step for this improvement is done by using the taps ,
if not enough it can solve by adding capacitor banks
2. Low load factor problem
• Re-arrange the distribution transformer (if it can be) to
increase the load factor
• LF=[.65-.75] give the max. efficiency distribution transformer
• The engineers choose the transformer in distribution network
with load factor [.45-.55] expressed to the growth of the load
by years
3. Capacity problem
• For the fourth problem there is a study to get another
connection point or to move the connection to another point
as in Qussen
Taps
• Almost all transformers provide taps on windings to adjust
the ratio of transformation by changing taps down when we
need to raise the voltages up and vice versa
• There are two types of transformer taps:
1. Tap changing without loads (fixed tap) changer on either side
or both sides of transformers
2. Tap changing under load (LTC)
capacitor banks
• Shunt capacitor banks is very important method of controlling
voltage at the buses at both transmission and distribution
levels along lines or at substation and load .
• Essentially capacitor is a means of supplying mega-vars
(MVAR) at the point of installation.
• Capacitor banks may be permanently connected, or regulators
• Switching may be manually or automatically controlled either
by time clock or in response to voltage or reactive - power
requirement
• capacitor reduces the line current necessary to supply the load
and reduce the voltage drop in the line as the power factor is
improved
4.1: Etap Power Station Program
• It is a load flow program which can simulink the
power system receiving the input data (source
,transformer ,T.L & loads) as One Line Diagram
schematic And results output report that includes
bus voltage , branch losses , load factors power
factors …etc.
• It is also able to do the Fault analysis .. Harmonic
analysis .. Transient stability analysis.
4.2: Simulation For Max. Load Case
This step done by the following criteria
1. drawing the one line diagram (source ,transformer
T.L, buses & loads)
2. entering R&X in Ω or (Ω /any unit of length) & its
length. note (Y) value is not important since the T.L
is short (L<80Km)
3. entering the typical value (X/R & %Z) for each
transformer
4. entering the rated voltage for each bus
5. entering the actual MVA & P.F for each load
6. entering the source as a swing bus, for load flow
studies a swing power grid will take up the slack of
the power flows in the system, i.e., the voltage
magnitude and angle of the power grid terminals
will remain at the specified operating values ( V & δ
are given ,P & Q are unknown)
7. run the load flow analysis to get the output result
A: Max. load case results without
improvement
• The total demand for Qussen
Swing bus P= 20.27MW Q=14.846MVAr S=24.929MVA pf= 80.33 lagging
∆P=1.06 ∆Q=2.555 I=436A
∆P%=1.06/20.27=5.456%
• The total demand for Innab
Swing bus P= 5.702MW Q=3.741MVAr S=6.82MVA pf= 83.61 lagging
∆P=.075 ∆Q=.307 I=119A
∆P%=.075/5.695=1.31%
B: Qussen-with tap changer improvement
Swing bus P= 19.841MW Q=14.318MVAr S=24.467MVA pf= 81.09 lagging
∆P=.920 ∆Q=2.026 I=428A
∆P%=.92/19.841=4.63%
Method of iteration: Newton Raphson method Number of Iterations: 3
L.F for Quseen
L.F for Innab
P.F for Quseen
P.F for Quseen
P.F for Innab
V% for Quseen
V% for Quseen
V% for Innab
Problems In The Network
• we notice # of problems:
1. low load factor (L.F<.45) for the most of transformer
2. high load factor (L.F>1) for some transformer
{T82,T103 in Quseen}
3. The P.F for all buses are low (P.F<.92) except
{bus.33,34 in Quseen & bus 25,27,29,54 in Innab}
4. %V does not lies between(1.05Vnom-1.1Vnom) for any
bus
5. considerable losses in Quseen (∆P%=5.456)
V% for Quseen with Taps
V% for Quseen with Taps
V% for Quseen with Taps
For this case we notice the following result
1. there is a small increase in the P.F
2. 36% of buses lies between(1.05Vnom-
1.1Vnom) & the other is >95% Vnom
3. P.F of the swing bus increase from 80.33 to
81.09
4. The current decrease from 436A to 428 A
5. the losses decrease in Quseen .826% from the
original case
6. There is a saving in the capacity of .5MVA
C:Max.load with capacitor improvement
* Capacitor bank are used to solve P.F problem &
its penalties, we put these capacitor bank at the
load side (0.4Kv side)
* Qc=pold(tancos-1p.fold-tancos-1p.fnew)
Where standard capacitor are:-
0.4Kv→→→25,40,60,100KVAr
6.6or11Kv→3,6MVAr
1.Quseen
Qc=19.841*(tancos-1.8109-tancos-1.92)
=5.866MVAr
Qcact=5.476MVAr for P.F=.9202
2.Innab
Qc=5.702(tancos-1.8361-tancos-1.92)
=1.312MVAr
Qcact=1.3MVAr for P.F=.9221
for each load to
we use suitable rated capacitor bank
*
rise its p.f above .92,so to increase the overall p.f of
swing bus
PF for Quseen with cap
PF for Quseen with cap
PF for Inab
with cap
4.2: Simulation For Min. Load Case
A : Min. load case results without improvement
The total demand for Qussen
Swing bus P= 7.721MW Q=5.21MVAr
S=9.348MVA pf= 82.59 lagging
∆P=.152 ∆Q=.354 I=164A
∆P%=1.96%
The total demand for Innab
Swing bus P= 2.262MW Q=1.421MVAr
S=2.672MVA pf= 84.69 lagging
∆P=.012 ∆Q=.047 I=47A
∆P%=.53%
V% for Quseen without tap
V% for Quseen without tap
B: Qussen-with tap changer improvement
Swing bus P= 7.709MW Q=5.2MVAr
S=9.32MVA pf= 82.72 lagging
∆P=.141 ∆Q=.32 I=163A
∆P%=1.82%
At this case half turn of tap changer are used
*
to increase the voltage of the bus (vbus>=vnom)
[only Quseen region have under this value
Vbus=.95-.98.5Vnom] .tap changer have affect
to increase the voltage but less affect on p.f.
V% for Quseen with tap
V% for Quseen with tap
C: Min load using capacitor
1.Quseen
Qc=7.709*(tancos-1.8272-tanco-1.92)
=1.952MVAr
Qcact=1.995 MVAr for P.F=.9224
2.Innab
Qc=2.262(tancos-1.8469-tancos-1.92)
=.456MVAr
Qcact=.547 MVAr for P.F=.9209
PF for Quseen without cap
PF for Quseen without cap
PF for Inab
without cap
PF for Inab
with cap
PF for Quseen with cap
PF for Quseen with cap
At min load less capacitor bank are used to
*
rise the p.f at the load & so the overall p.f. the
losses in the network are become very low
since the currents is reduced .
Some of these capacitor bank are used at
*
max &min which is called fixed capacitor bank.
And other capacitor which only used at max or
at min are called regulated one. regulated
capacitor bank are more expensive than fixed
since it need to controller for use.
Changing of the switch gear & connection point
simultaneously
 change the switch gear from 33/6.6KV to 33/11KV except Jumblat
region
• Jumblat region will kept as it is to exploits the distribution
transformer which have two level voltage at primary side (11,
6.6KV/.4KV) at Jumblat with transformer have only 6.6/.4KV side at
other places ( East & West Mojeer aldeenregion )
• This operation will save the price of a new transformer with 11/.4KV
 The change of position of the connection point is from Qussen to
sarrah with 3Km double T.L
 The change is starting from replacing the distribution
transformer of 6.6/.4KV in East & West Mojeer aldeen
region to 11,6.6/.4KV(from Jumblat & East part region
from Nablus)
 This step also taken some case of the L.F distribution
rearrangement which are sumerize at the next table
from
New capacity
L.F
capacity
T#
Jumblat
630
58.6
630
62
Jumblat
400
29.5
630
63
Jumblat
630
69.1
630
64
Jumblat
630
91.6
400
68
East part
250
36.8
250
72
East part
160
47.3
160
74
East part
250
59.4
250
75
Jumblat
400
38.2
400
76
Jumblat
400
29.2
400
77
Jumblat
84
42.8
84
84
Jumblat
630
26.5
630
90
Jumblat
400
44.9
400
97
Jumblat
630
40.7
630
99
Jumblat
630
40.7
630
100
Jumblat
630
52.2
630
101
Jumblat
400
105.7
300
103
Jumblat
400
91.2
400
104
East part
1000
1000
108
 The transformer at Jumblat region which exchange are
T25,T26,T27,T28,T30,T38,T42,T45,T46,T47,T49,T50,T51
&T61
630KVA→→ T25,T26,T30,T42,T45&T50
400KVA→→ T27,T28,T39,T46,T47,T49, T51&T61
 the transformer of Jumblat are back as its default
capacity except
1)T39(400KVA) of L.F=18.3 with T103(300KVA)
2)exchange T47(400KVA) of L.F=80.4% with T25(630KVA)
of L.F=7.7%
The result of this case with taps:-
Swing bus P= 19.647MW Q=14.172MVAr S=24.225MVA
pf= 81.1 lagging
∆P=0.727 ∆Q=0.881 I=424A
∆P%=0.727/19.647=3.7%
From ETAP result we notice that:-
1. the current in The main T.L at Quseen is decreased in
widely range from 400 to 35A approximately due to change of
the position of connection point to Sarah.
at Sarah the power distribute directly for more branches. The
decrease in current will decrease the losses in The main T.L
(at the old case)
2. the change from 6.6 to 11KV also decrease the current in
the branches & so this mean decreasing in the losses
3. the voltage is slowly decreased at Quseen busses region
since the supply is exchange
4. the voltage is slowly increased at the region which the
switch gear is change
Quseen,old
case
 The first economical study is using capacitor bank &
this study followed by this criteria:-
∆∆P=∆Pbefore,cap - ∆Pafter,cap
∆∆P:saving in real power losses
∆Pbefore,cap : real power losses before adding capacitor
∆Pafter,cap : real power losses after adding capacitor
Z∆p=∆∆p*T*140
Z∆p : annual saving in real power cost
T=8760(0.124+0.0001tmax)^2
T≈3500hour
140:cost per MWh($/MWh)
Kc=C*Qc
Kc:cost of capacitor
C:cost of capacitor per KVAr($/KVAr)
Qc: capacitor KVAr
knowing that the cost of the capacitor are:-
Fixed Cap=5$/Kvar
Regulated Cap=22$/Kvar
The type of capacitors used are regulated only since the loads are vary every
time , increase by years & may be decrease under min. so the P.F become
leading & this will damage the transformer . also the P.F correction range is
considerable to use regulated capacitor.
Zc=0.22*Kc
Zc:annual capacitor running cost
.22: maintenance & life time of capacitor (depreciation factor)
∆Z=Z∆p-Zc
∆Z: annual saving
Saving of penalties=1% from the total bill for every 1% p.f <92%
∆Zt=∆Z+ Saving of penalties
∆Zt: total annual saving
S.P.B.P=investment(capacitors initial cost)/ total annual saving
S.P.B.P < 2year →→→project is visible
S.P.B.P > 2year →→→project is not visible
1)Quseen
∆∆P=∆Pbefore,cap-∆Pafter,cap
∆∆P=0.92-0.702=0.218
Z∆p=∆∆p*T*140
Z∆p=0.218*3500*140=106820
Kc=C*Qc
Kc=5.476*10^3*22=120472
Zc=0.22*Kc=26503.84
∆Z=Z∆p-Zc=106820-26503.84
=80316
Total Bill=19.841*10^3*3500=69443500kwh
Saving of penalties=1%*69443500 (92-81.09)*140*10^-3=1060680
∆Zt=80316.16+1060680=1140996(This is the annual saving)
2)Innab
∆∆P=∆Pbefore-∆Pafter
∆∆P=0.075-0.061=0.014
Z∆p=∆∆p*T*140
Z∆p=0.014*3500*140=6860
Kc=C*Qc
Kc=1.3*10^3*22=28600
Zc=0.22*Kc=6292
∆Z=Z∆p-Zc=6860-6292
=568
Total Bill=5.702*10^3*3500=19957000
Saving of penalties=1%*19957000 (92-83.61)*140*10^-3
= 234415
∆Zt=568+234415=234983 (This is the annual saving)
S.P.B.P=total investment/total annual saving
=(120472+28600) / (1140996+234983)
=.1083 year
=1.296 month
 The second economical study is changing of switch gear & the
connection point.this step will make saving in power without paying
money
Annual saving=saving in power*3500h*140$/MW
=Pold-Pnew *3500h*140
=(19.841-19.647) *3500*140
=95060$/year
CH1.ppt

Mais conteúdo relacionado

Semelhante a CH1.ppt

Transformerless DC-DC Converter Using Cockcroft-Walton Voltage Multiplier to ...
Transformerless DC-DC Converter Using Cockcroft-Walton Voltage Multiplier to ...Transformerless DC-DC Converter Using Cockcroft-Walton Voltage Multiplier to ...
Transformerless DC-DC Converter Using Cockcroft-Walton Voltage Multiplier to ...IJERA Editor
 
Reactive power management and voltage control by using statcom
Reactive power management and voltage control by using statcomReactive power management and voltage control by using statcom
Reactive power management and voltage control by using statcomHussain Ali
 
Fuzzy Logic Controller Based High Frequency Link AC-AC Converter For Voltage ...
Fuzzy Logic Controller Based High Frequency Link AC-AC Converter For Voltage ...Fuzzy Logic Controller Based High Frequency Link AC-AC Converter For Voltage ...
Fuzzy Logic Controller Based High Frequency Link AC-AC Converter For Voltage ...IJTET Journal
 
A New Single-Stage Multilevel Type Full-Bridge Converter Applied to closed lo...
A New Single-Stage Multilevel Type Full-Bridge Converter Applied to closed lo...A New Single-Stage Multilevel Type Full-Bridge Converter Applied to closed lo...
A New Single-Stage Multilevel Type Full-Bridge Converter Applied to closed lo...IOSR Journals
 
LOW CAPACITANCE CASCADED H BRIDGE MULTILEVEL BASED STATCOM
LOW CAPACITANCE CASCADED H BRIDGE MULTILEVEL BASED STATCOMLOW CAPACITANCE CASCADED H BRIDGE MULTILEVEL BASED STATCOM
LOW CAPACITANCE CASCADED H BRIDGE MULTILEVEL BASED STATCOMASWATHYSANAND1
 
uppcl training in moradabad report
uppcl training in moradabad reportuppcl training in moradabad report
uppcl training in moradabad reportMONU KUMAR
 
Soft power factor modification using static
Soft power factor modification using staticSoft power factor modification using static
Soft power factor modification using staticchodachude
 
Power(2)-EPM320-L01-16 Lectures of Power System Analysis.pdf
Power(2)-EPM320-L01-16 Lectures of Power System Analysis.pdfPower(2)-EPM320-L01-16 Lectures of Power System Analysis.pdf
Power(2)-EPM320-L01-16 Lectures of Power System Analysis.pdfssuser621d9d
 
NEW APPROACH OF DESIGNING AND EXPLOATATION OF ELECTRICAL TRACTION SUBSTATIONS
NEW APPROACH OF DESIGNING AND EXPLOATATION OF ELECTRICAL TRACTION SUBSTATIONSNEW APPROACH OF DESIGNING AND EXPLOATATION OF ELECTRICAL TRACTION SUBSTATIONS
NEW APPROACH OF DESIGNING AND EXPLOATATION OF ELECTRICAL TRACTION SUBSTATIONSDženan Ćelić
 
Power system voltage stability
Power system voltage stabilityPower system voltage stability
Power system voltage stabilityAkash Choudhary
 
Power system voltage stability
Power system voltage stabilityPower system voltage stability
Power system voltage stabilityAkash Choudhary
 
NMRC Summer Tanning/Internship PPT(Anand Mohan )
NMRC Summer Tanning/Internship PPT(Anand Mohan )NMRC Summer Tanning/Internship PPT(Anand Mohan )
NMRC Summer Tanning/Internship PPT(Anand Mohan )AnandMohan271812
 
Speed Control Of Separately Excited Dc Motor Using A High Efficiency Flyback ...
Speed Control Of Separately Excited Dc Motor Using A High Efficiency Flyback ...Speed Control Of Separately Excited Dc Motor Using A High Efficiency Flyback ...
Speed Control Of Separately Excited Dc Motor Using A High Efficiency Flyback ...IJERA Editor
 
Voltage Profile Improvement using Switched Capacitors: Case of Single Wire Ea...
Voltage Profile Improvement using Switched Capacitors: Case of Single Wire Ea...Voltage Profile Improvement using Switched Capacitors: Case of Single Wire Ea...
Voltage Profile Improvement using Switched Capacitors: Case of Single Wire Ea...IJMERJOURNAL
 
Power-System-Slide-1.pptx
Power-System-Slide-1.pptxPower-System-Slide-1.pptx
Power-System-Slide-1.pptxssuser99d6551
 

Semelhante a CH1.ppt (20)

C04721623
C04721623C04721623
C04721623
 
Transformerless DC-DC Converter Using Cockcroft-Walton Voltage Multiplier to ...
Transformerless DC-DC Converter Using Cockcroft-Walton Voltage Multiplier to ...Transformerless DC-DC Converter Using Cockcroft-Walton Voltage Multiplier to ...
Transformerless DC-DC Converter Using Cockcroft-Walton Voltage Multiplier to ...
 
Reactive power management and voltage control by using statcom
Reactive power management and voltage control by using statcomReactive power management and voltage control by using statcom
Reactive power management and voltage control by using statcom
 
Fuzzy Logic Controller Based High Frequency Link AC-AC Converter For Voltage ...
Fuzzy Logic Controller Based High Frequency Link AC-AC Converter For Voltage ...Fuzzy Logic Controller Based High Frequency Link AC-AC Converter For Voltage ...
Fuzzy Logic Controller Based High Frequency Link AC-AC Converter For Voltage ...
 
A New Single-Stage Multilevel Type Full-Bridge Converter Applied to closed lo...
A New Single-Stage Multilevel Type Full-Bridge Converter Applied to closed lo...A New Single-Stage Multilevel Type Full-Bridge Converter Applied to closed lo...
A New Single-Stage Multilevel Type Full-Bridge Converter Applied to closed lo...
 
LOW CAPACITANCE CASCADED H BRIDGE MULTILEVEL BASED STATCOM
LOW CAPACITANCE CASCADED H BRIDGE MULTILEVEL BASED STATCOMLOW CAPACITANCE CASCADED H BRIDGE MULTILEVEL BASED STATCOM
LOW CAPACITANCE CASCADED H BRIDGE MULTILEVEL BASED STATCOM
 
uppcl training in moradabad report
uppcl training in moradabad reportuppcl training in moradabad report
uppcl training in moradabad report
 
project.pptx
project.pptxproject.pptx
project.pptx
 
Soft power factor modification using static
Soft power factor modification using staticSoft power factor modification using static
Soft power factor modification using static
 
Power(2)-EPM320-L01-16 Lectures of Power System Analysis.pdf
Power(2)-EPM320-L01-16 Lectures of Power System Analysis.pdfPower(2)-EPM320-L01-16 Lectures of Power System Analysis.pdf
Power(2)-EPM320-L01-16 Lectures of Power System Analysis.pdf
 
NEW APPROACH OF DESIGNING AND EXPLOATATION OF ELECTRICAL TRACTION SUBSTATIONS
NEW APPROACH OF DESIGNING AND EXPLOATATION OF ELECTRICAL TRACTION SUBSTATIONSNEW APPROACH OF DESIGNING AND EXPLOATATION OF ELECTRICAL TRACTION SUBSTATIONS
NEW APPROACH OF DESIGNING AND EXPLOATATION OF ELECTRICAL TRACTION SUBSTATIONS
 
Power system voltage stability
Power system voltage stabilityPower system voltage stability
Power system voltage stability
 
Power system voltage stability
Power system voltage stabilityPower system voltage stability
Power system voltage stability
 
A03540109
A03540109A03540109
A03540109
 
NMRC Summer Tanning/Internship PPT(Anand Mohan )
NMRC Summer Tanning/Internship PPT(Anand Mohan )NMRC Summer Tanning/Internship PPT(Anand Mohan )
NMRC Summer Tanning/Internship PPT(Anand Mohan )
 
Speed Control Of Separately Excited Dc Motor Using A High Efficiency Flyback ...
Speed Control Of Separately Excited Dc Motor Using A High Efficiency Flyback ...Speed Control Of Separately Excited Dc Motor Using A High Efficiency Flyback ...
Speed Control Of Separately Excited Dc Motor Using A High Efficiency Flyback ...
 
Voltage Profile Improvement using Switched Capacitors: Case of Single Wire Ea...
Voltage Profile Improvement using Switched Capacitors: Case of Single Wire Ea...Voltage Profile Improvement using Switched Capacitors: Case of Single Wire Ea...
Voltage Profile Improvement using Switched Capacitors: Case of Single Wire Ea...
 
220 66 kv nrs sub report
220 66 kv nrs sub report220 66 kv nrs sub report
220 66 kv nrs sub report
 
Power-System-Slide-1.pptx
Power-System-Slide-1.pptxPower-System-Slide-1.pptx
Power-System-Slide-1.pptx
 
Hvdc dad
Hvdc dadHvdc dad
Hvdc dad
 

Mais de said Touati

Examen_02_math de mathamatique pour .pdf
Examen_02_math de mathamatique pour .pdfExamen_02_math de mathamatique pour .pdf
Examen_02_math de mathamatique pour .pdfsaid Touati
 
ch2+ok+Health+information+management+2014+secand+symester.ppt
ch2+ok+Health+information+management+2014+secand+symester.pptch2+ok+Health+information+management+2014+secand+symester.ppt
ch2+ok+Health+information+management+2014+secand+symester.pptsaid Touati
 
msalternance.ppt
msalternance.pptmsalternance.ppt
msalternance.pptsaid Touati
 
11-17-1686-00-00lc-use-cases-for-lc.ppt
11-17-1686-00-00lc-use-cases-for-lc.ppt11-17-1686-00-00lc-use-cases-for-lc.ppt
11-17-1686-00-00lc-use-cases-for-lc.pptsaid Touati
 
condition-monitoring.ppt
condition-monitoring.pptcondition-monitoring.ppt
condition-monitoring.pptsaid Touati
 
introduction.pptx
introduction.pptxintroduction.pptx
introduction.pptxsaid Touati
 

Mais de said Touati (10)

Examen_02_math de mathamatique pour .pdf
Examen_02_math de mathamatique pour .pdfExamen_02_math de mathamatique pour .pdf
Examen_02_math de mathamatique pour .pdf
 
ch2+ok+Health+information+management+2014+secand+symester.ppt
ch2+ok+Health+information+management+2014+secand+symester.pptch2+ok+Health+information+management+2014+secand+symester.ppt
ch2+ok+Health+information+management+2014+secand+symester.ppt
 
32261.ppt
32261.ppt32261.ppt
32261.ppt
 
lecture-1.ppt
lecture-1.pptlecture-1.ppt
lecture-1.ppt
 
msalternance.ppt
msalternance.pptmsalternance.ppt
msalternance.ppt
 
Module 336.ppt
Module 336.pptModule 336.ppt
Module 336.ppt
 
11-17-1686-00-00lc-use-cases-for-lc.ppt
11-17-1686-00-00lc-use-cases-for-lc.ppt11-17-1686-00-00lc-use-cases-for-lc.ppt
11-17-1686-00-00lc-use-cases-for-lc.ppt
 
condition-monitoring.ppt
condition-monitoring.pptcondition-monitoring.ppt
condition-monitoring.ppt
 
sainz_en.ppt
sainz_en.pptsainz_en.ppt
sainz_en.ppt
 
introduction.pptx
introduction.pptxintroduction.pptx
introduction.pptx
 

Último

Instrumentation, measurement and control of bio process parameters ( Temperat...
Instrumentation, measurement and control of bio process parameters ( Temperat...Instrumentation, measurement and control of bio process parameters ( Temperat...
Instrumentation, measurement and control of bio process parameters ( Temperat...121011101441
 
Correctly Loading Incremental Data at Scale
Correctly Loading Incremental Data at ScaleCorrectly Loading Incremental Data at Scale
Correctly Loading Incremental Data at ScaleAlluxio, Inc.
 
System Simulation and Modelling with types and Event Scheduling
System Simulation and Modelling with types and Event SchedulingSystem Simulation and Modelling with types and Event Scheduling
System Simulation and Modelling with types and Event SchedulingBootNeck1
 
Steel Structures - Building technology.pptx
Steel Structures - Building technology.pptxSteel Structures - Building technology.pptx
Steel Structures - Building technology.pptxNikhil Raut
 
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsyncWhy does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsyncssuser2ae721
 
Concrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxConcrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxKartikeyaDwivedi3
 
Vishratwadi & Ghorpadi Bridge Tender documents
Vishratwadi & Ghorpadi Bridge Tender documentsVishratwadi & Ghorpadi Bridge Tender documents
Vishratwadi & Ghorpadi Bridge Tender documentsSachinPawar510423
 
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catchers
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor CatchersTechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catchers
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catcherssdickerson1
 
Internet of things -Arshdeep Bahga .pptx
Internet of things -Arshdeep Bahga .pptxInternet of things -Arshdeep Bahga .pptx
Internet of things -Arshdeep Bahga .pptxVelmuruganTECE
 
Arduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.pptArduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.pptSAURABHKUMAR892774
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort servicejennyeacort
 
National Level Hackathon Participation Certificate.pdf
National Level Hackathon Participation Certificate.pdfNational Level Hackathon Participation Certificate.pdf
National Level Hackathon Participation Certificate.pdfRajuKanojiya4
 
Main Memory Management in Operating System
Main Memory Management in Operating SystemMain Memory Management in Operating System
Main Memory Management in Operating SystemRashmi Bhat
 
Class 1 | NFPA 72 | Overview Fire Alarm System
Class 1 | NFPA 72 | Overview Fire Alarm SystemClass 1 | NFPA 72 | Overview Fire Alarm System
Class 1 | NFPA 72 | Overview Fire Alarm Systemirfanmechengr
 
Earthing details of Electrical Substation
Earthing details of Electrical SubstationEarthing details of Electrical Substation
Earthing details of Electrical Substationstephanwindworld
 
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)Dr SOUNDIRARAJ N
 
Solving The Right Triangles PowerPoint 2.ppt
Solving The Right Triangles PowerPoint 2.pptSolving The Right Triangles PowerPoint 2.ppt
Solving The Right Triangles PowerPoint 2.pptJasonTagapanGulla
 
The SRE Report 2024 - Great Findings for the teams
The SRE Report 2024 - Great Findings for the teamsThe SRE Report 2024 - Great Findings for the teams
The SRE Report 2024 - Great Findings for the teamsDILIPKUMARMONDAL6
 

Último (20)

Instrumentation, measurement and control of bio process parameters ( Temperat...
Instrumentation, measurement and control of bio process parameters ( Temperat...Instrumentation, measurement and control of bio process parameters ( Temperat...
Instrumentation, measurement and control of bio process parameters ( Temperat...
 
POWER SYSTEMS-1 Complete notes examples
POWER SYSTEMS-1 Complete notes  examplesPOWER SYSTEMS-1 Complete notes  examples
POWER SYSTEMS-1 Complete notes examples
 
Correctly Loading Incremental Data at Scale
Correctly Loading Incremental Data at ScaleCorrectly Loading Incremental Data at Scale
Correctly Loading Incremental Data at Scale
 
System Simulation and Modelling with types and Event Scheduling
System Simulation and Modelling with types and Event SchedulingSystem Simulation and Modelling with types and Event Scheduling
System Simulation and Modelling with types and Event Scheduling
 
Steel Structures - Building technology.pptx
Steel Structures - Building technology.pptxSteel Structures - Building technology.pptx
Steel Structures - Building technology.pptx
 
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
 
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsyncWhy does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
 
Concrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxConcrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptx
 
Vishratwadi & Ghorpadi Bridge Tender documents
Vishratwadi & Ghorpadi Bridge Tender documentsVishratwadi & Ghorpadi Bridge Tender documents
Vishratwadi & Ghorpadi Bridge Tender documents
 
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catchers
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor CatchersTechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catchers
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catchers
 
Internet of things -Arshdeep Bahga .pptx
Internet of things -Arshdeep Bahga .pptxInternet of things -Arshdeep Bahga .pptx
Internet of things -Arshdeep Bahga .pptx
 
Arduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.pptArduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.ppt
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
 
National Level Hackathon Participation Certificate.pdf
National Level Hackathon Participation Certificate.pdfNational Level Hackathon Participation Certificate.pdf
National Level Hackathon Participation Certificate.pdf
 
Main Memory Management in Operating System
Main Memory Management in Operating SystemMain Memory Management in Operating System
Main Memory Management in Operating System
 
Class 1 | NFPA 72 | Overview Fire Alarm System
Class 1 | NFPA 72 | Overview Fire Alarm SystemClass 1 | NFPA 72 | Overview Fire Alarm System
Class 1 | NFPA 72 | Overview Fire Alarm System
 
Earthing details of Electrical Substation
Earthing details of Electrical SubstationEarthing details of Electrical Substation
Earthing details of Electrical Substation
 
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
 
Solving The Right Triangles PowerPoint 2.ppt
Solving The Right Triangles PowerPoint 2.pptSolving The Right Triangles PowerPoint 2.ppt
Solving The Right Triangles PowerPoint 2.ppt
 
The SRE Report 2024 - Great Findings for the teams
The SRE Report 2024 - Great Findings for the teamsThe SRE Report 2024 - Great Findings for the teams
The SRE Report 2024 - Great Findings for the teams
 

CH1.ppt

  • 1.
  • 2. Criteria For The Load Flow Study 1. Collection of all data about the Nablus network including the one-line diagram, information about the power stations, transformers, transmission lines and loads. 2. Investigating the problems from which the Nablus network suffers in max., min load & fault condition 3. Applying method of reactive power compensation to improve the operation (using tap changer transformer, capacitor bank) 4. Performing the economical analysis of the saving achieved by the implementation of reactive power compensation
  • 3. CH:2 Existing System The present load in the West Bank is supplied from several points within the IEC network. There are supply points at 22 KV supplying Qalailya and Tulkarm 33 KV feeders from Beisan (in Israel)supplying Jenin ,Tubas and Nablus as well as feeders from M. Afraym and feeders from portable substations.
  • 5. 3.1: Element Of The Network A. Sources . Generators are one of the essential components of the power systems. Synchronous generators are widely used in power systems. . Nablus are fed from 3 connection point by Israel Electrical Company (IEC), at 33KV. 1.Asker (odeleh & Almeslekh) →→→30MVA namely 2.Quseen →→→18MVA namely 3.Innab →→→5MVA namely
  • 6. B. Transformers & load • There are two type of Transformer (power & distribution Transformer ) which is ∆-y connected • So, the source always balanced without looking to the load since the P.T is ∆-y ground connected • The distribution Transformer capacity & its voltage are summarized in table (1)
  • 7. • There are also 3 power Transformer with (10MVA capacity,33/6.6KV& %Tap=±12 ;for 17 taps with1.5% for each step changer) • Note the impedance of each transformer are determined by the typical value at ETAP program • The loads will be seen later in the table of L.F of transformer
  • 8. C.Transmission Line • There are two type of conductor 1.O.H lines →→→ACSR 2.cables →→→ cu XLPE which have these rating as in table (2) . In Quseen they use double T.L (3*95mm2ACSR) for the transmission of power since the current is above 400A in max load
  • 9. 3.2 : Electrical Problem In The Network 1. High drop voltage 2. Low power factor 3. Low load factor at most of distribution transformer which reduce the efficiency of transformer & so increase the losses (the electrical losses in distribution network must not exceed 8-10 % from total active power) 4. Exceeding the permissible capacity of each connection point MVA
  • 10. Remedy 1. High drop voltage & low power factor problem • It is important to keep the power factor above 0.92 on the distribution transformer so as to minimize the electrical losses in the network & do not paying penalties • For max load the voltage of buses must rise to (1.05Vnom<= Vbus <=1.1Vnom) as we can to decrease the current & so to decrease the losses • The first step for this improvement is done by using the taps , if not enough it can solve by adding capacitor banks
  • 11. 2. Low load factor problem • Re-arrange the distribution transformer (if it can be) to increase the load factor • LF=[.65-.75] give the max. efficiency distribution transformer • The engineers choose the transformer in distribution network with load factor [.45-.55] expressed to the growth of the load by years 3. Capacity problem • For the fourth problem there is a study to get another connection point or to move the connection to another point as in Qussen
  • 12. Taps • Almost all transformers provide taps on windings to adjust the ratio of transformation by changing taps down when we need to raise the voltages up and vice versa • There are two types of transformer taps: 1. Tap changing without loads (fixed tap) changer on either side or both sides of transformers 2. Tap changing under load (LTC)
  • 13. capacitor banks • Shunt capacitor banks is very important method of controlling voltage at the buses at both transmission and distribution levels along lines or at substation and load . • Essentially capacitor is a means of supplying mega-vars (MVAR) at the point of installation. • Capacitor banks may be permanently connected, or regulators • Switching may be manually or automatically controlled either by time clock or in response to voltage or reactive - power requirement • capacitor reduces the line current necessary to supply the load and reduce the voltage drop in the line as the power factor is improved
  • 14. 4.1: Etap Power Station Program • It is a load flow program which can simulink the power system receiving the input data (source ,transformer ,T.L & loads) as One Line Diagram schematic And results output report that includes bus voltage , branch losses , load factors power factors …etc. • It is also able to do the Fault analysis .. Harmonic analysis .. Transient stability analysis.
  • 15. 4.2: Simulation For Max. Load Case This step done by the following criteria 1. drawing the one line diagram (source ,transformer T.L, buses & loads) 2. entering R&X in Ω or (Ω /any unit of length) & its length. note (Y) value is not important since the T.L is short (L<80Km) 3. entering the typical value (X/R & %Z) for each transformer 4. entering the rated voltage for each bus 5. entering the actual MVA & P.F for each load 6. entering the source as a swing bus, for load flow studies a swing power grid will take up the slack of the power flows in the system, i.e., the voltage magnitude and angle of the power grid terminals will remain at the specified operating values ( V & δ are given ,P & Q are unknown) 7. run the load flow analysis to get the output result
  • 16. A: Max. load case results without improvement • The total demand for Qussen Swing bus P= 20.27MW Q=14.846MVAr S=24.929MVA pf= 80.33 lagging ∆P=1.06 ∆Q=2.555 I=436A ∆P%=1.06/20.27=5.456% • The total demand for Innab Swing bus P= 5.702MW Q=3.741MVAr S=6.82MVA pf= 83.61 lagging ∆P=.075 ∆Q=.307 I=119A ∆P%=.075/5.695=1.31% B: Qussen-with tap changer improvement Swing bus P= 19.841MW Q=14.318MVAr S=24.467MVA pf= 81.09 lagging ∆P=.920 ∆Q=2.026 I=428A ∆P%=.92/19.841=4.63% Method of iteration: Newton Raphson method Number of Iterations: 3
  • 25. Problems In The Network • we notice # of problems: 1. low load factor (L.F<.45) for the most of transformer 2. high load factor (L.F>1) for some transformer {T82,T103 in Quseen} 3. The P.F for all buses are low (P.F<.92) except {bus.33,34 in Quseen & bus 25,27,29,54 in Innab} 4. %V does not lies between(1.05Vnom-1.1Vnom) for any bus 5. considerable losses in Quseen (∆P%=5.456)
  • 26. V% for Quseen with Taps
  • 27. V% for Quseen with Taps
  • 28. V% for Quseen with Taps
  • 29. For this case we notice the following result 1. there is a small increase in the P.F 2. 36% of buses lies between(1.05Vnom- 1.1Vnom) & the other is >95% Vnom 3. P.F of the swing bus increase from 80.33 to 81.09 4. The current decrease from 436A to 428 A 5. the losses decrease in Quseen .826% from the original case 6. There is a saving in the capacity of .5MVA
  • 30. C:Max.load with capacitor improvement * Capacitor bank are used to solve P.F problem & its penalties, we put these capacitor bank at the load side (0.4Kv side) * Qc=pold(tancos-1p.fold-tancos-1p.fnew) Where standard capacitor are:- 0.4Kv→→→25,40,60,100KVAr 6.6or11Kv→3,6MVAr
  • 31. 1.Quseen Qc=19.841*(tancos-1.8109-tancos-1.92) =5.866MVAr Qcact=5.476MVAr for P.F=.9202 2.Innab Qc=5.702(tancos-1.8361-tancos-1.92) =1.312MVAr Qcact=1.3MVAr for P.F=.9221 for each load to we use suitable rated capacitor bank * rise its p.f above .92,so to increase the overall p.f of swing bus
  • 32. PF for Quseen with cap
  • 33. PF for Quseen with cap
  • 35. 4.2: Simulation For Min. Load Case A : Min. load case results without improvement The total demand for Qussen Swing bus P= 7.721MW Q=5.21MVAr S=9.348MVA pf= 82.59 lagging ∆P=.152 ∆Q=.354 I=164A ∆P%=1.96% The total demand for Innab Swing bus P= 2.262MW Q=1.421MVAr S=2.672MVA pf= 84.69 lagging ∆P=.012 ∆Q=.047 I=47A ∆P%=.53%
  • 36. V% for Quseen without tap
  • 37. V% for Quseen without tap
  • 38. B: Qussen-with tap changer improvement Swing bus P= 7.709MW Q=5.2MVAr S=9.32MVA pf= 82.72 lagging ∆P=.141 ∆Q=.32 I=163A ∆P%=1.82% At this case half turn of tap changer are used * to increase the voltage of the bus (vbus>=vnom) [only Quseen region have under this value Vbus=.95-.98.5Vnom] .tap changer have affect to increase the voltage but less affect on p.f.
  • 39. V% for Quseen with tap
  • 40. V% for Quseen with tap
  • 41. C: Min load using capacitor 1.Quseen Qc=7.709*(tancos-1.8272-tanco-1.92) =1.952MVAr Qcact=1.995 MVAr for P.F=.9224 2.Innab Qc=2.262(tancos-1.8469-tancos-1.92) =.456MVAr Qcact=.547 MVAr for P.F=.9209
  • 42. PF for Quseen without cap
  • 43. PF for Quseen without cap
  • 46. PF for Quseen with cap
  • 47. PF for Quseen with cap
  • 48. At min load less capacitor bank are used to * rise the p.f at the load & so the overall p.f. the losses in the network are become very low since the currents is reduced . Some of these capacitor bank are used at * max &min which is called fixed capacitor bank. And other capacitor which only used at max or at min are called regulated one. regulated capacitor bank are more expensive than fixed since it need to controller for use.
  • 49. Changing of the switch gear & connection point simultaneously  change the switch gear from 33/6.6KV to 33/11KV except Jumblat region • Jumblat region will kept as it is to exploits the distribution transformer which have two level voltage at primary side (11, 6.6KV/.4KV) at Jumblat with transformer have only 6.6/.4KV side at other places ( East & West Mojeer aldeenregion ) • This operation will save the price of a new transformer with 11/.4KV  The change of position of the connection point is from Qussen to sarrah with 3Km double T.L
  • 50.  The change is starting from replacing the distribution transformer of 6.6/.4KV in East & West Mojeer aldeen region to 11,6.6/.4KV(from Jumblat & East part region from Nablus)  This step also taken some case of the L.F distribution rearrangement which are sumerize at the next table
  • 51. from New capacity L.F capacity T# Jumblat 630 58.6 630 62 Jumblat 400 29.5 630 63 Jumblat 630 69.1 630 64 Jumblat 630 91.6 400 68 East part 250 36.8 250 72 East part 160 47.3 160 74 East part 250 59.4 250 75 Jumblat 400 38.2 400 76 Jumblat 400 29.2 400 77 Jumblat 84 42.8 84 84 Jumblat 630 26.5 630 90 Jumblat 400 44.9 400 97 Jumblat 630 40.7 630 99 Jumblat 630 40.7 630 100 Jumblat 630 52.2 630 101 Jumblat 400 105.7 300 103 Jumblat 400 91.2 400 104 East part 1000 1000 108
  • 52.  The transformer at Jumblat region which exchange are T25,T26,T27,T28,T30,T38,T42,T45,T46,T47,T49,T50,T51 &T61 630KVA→→ T25,T26,T30,T42,T45&T50 400KVA→→ T27,T28,T39,T46,T47,T49, T51&T61  the transformer of Jumblat are back as its default capacity except 1)T39(400KVA) of L.F=18.3 with T103(300KVA) 2)exchange T47(400KVA) of L.F=80.4% with T25(630KVA) of L.F=7.7% The result of this case with taps:- Swing bus P= 19.647MW Q=14.172MVAr S=24.225MVA pf= 81.1 lagging ∆P=0.727 ∆Q=0.881 I=424A ∆P%=0.727/19.647=3.7%
  • 53. From ETAP result we notice that:- 1. the current in The main T.L at Quseen is decreased in widely range from 400 to 35A approximately due to change of the position of connection point to Sarah. at Sarah the power distribute directly for more branches. The decrease in current will decrease the losses in The main T.L (at the old case) 2. the change from 6.6 to 11KV also decrease the current in the branches & so this mean decreasing in the losses 3. the voltage is slowly decreased at Quseen busses region since the supply is exchange 4. the voltage is slowly increased at the region which the switch gear is change
  • 55.
  • 56.
  • 57.
  • 58.  The first economical study is using capacitor bank & this study followed by this criteria:- ∆∆P=∆Pbefore,cap - ∆Pafter,cap ∆∆P:saving in real power losses ∆Pbefore,cap : real power losses before adding capacitor ∆Pafter,cap : real power losses after adding capacitor Z∆p=∆∆p*T*140 Z∆p : annual saving in real power cost T=8760(0.124+0.0001tmax)^2 T≈3500hour 140:cost per MWh($/MWh) Kc=C*Qc Kc:cost of capacitor C:cost of capacitor per KVAr($/KVAr) Qc: capacitor KVAr
  • 59. knowing that the cost of the capacitor are:- Fixed Cap=5$/Kvar Regulated Cap=22$/Kvar The type of capacitors used are regulated only since the loads are vary every time , increase by years & may be decrease under min. so the P.F become leading & this will damage the transformer . also the P.F correction range is considerable to use regulated capacitor. Zc=0.22*Kc Zc:annual capacitor running cost .22: maintenance & life time of capacitor (depreciation factor) ∆Z=Z∆p-Zc ∆Z: annual saving Saving of penalties=1% from the total bill for every 1% p.f <92% ∆Zt=∆Z+ Saving of penalties ∆Zt: total annual saving S.P.B.P=investment(capacitors initial cost)/ total annual saving S.P.B.P < 2year →→→project is visible S.P.B.P > 2year →→→project is not visible
  • 62. S.P.B.P=total investment/total annual saving =(120472+28600) / (1140996+234983) =.1083 year =1.296 month  The second economical study is changing of switch gear & the connection point.this step will make saving in power without paying money Annual saving=saving in power*3500h*140$/MW =Pold-Pnew *3500h*140 =(19.841-19.647) *3500*140 =95060$/year