SlideShare uma empresa Scribd logo
1 de 14
SCPX Project – Kura West Kazakh
Microtunel Construction
1. Guide Wall Construction
2. Secant Pile Construction
Reinforcement cage installation (only in male piles)
Placement of concrete & Extraction of Casing
Milestones
Guide Wall Construction
Scope of Guide Wall Construction is:
• Surveying & excavating trenches for guide walls;
• Levelling & Placing Lean Concrete;
• Reinforcement & formwork installation;
• Placement of concrete;
• Striking of formwork & Backfilling.
This construction element will act as reference points for pile centres. Please see figure for plan and cross sectional view of guide
wall. In order to resist drilling rig own weight and down force, guide wall height is decided as 1meter.
Backhoe loader will excavate trenches for the footprint of guide walls including working space for formwork
Guide Wall Construction
Port Baku Tower Project – Guide Wall Construction for Secant Pile
Secant Pile Construction
OPERATIONAL SEQUENCE
• Driving the Casing;
• Drilling of Piles;
• Reinforcement cage installation (only in male piles);
• Placement of concrete and Extraction of Casing.
Following casting of the guide wall a piling mat was constructed inside the shaft ring.
There are two different kinds of piles in SCPX Kure West River Crossing Shaft secant piles. These are
30pcs female piles which will be constructed with low grade bentonite added concrete (C12/15),
without reinforcement cage; and 30pcs male piles which will be constructed between two adjacent
female piles by cutting them through, with high grade concrete (C30/37) and with reinforcement cage.
Secant Pile Construction
OPERATIONAL SEQUENCE
In a secant piled design, there are two main types of elements to be constructed.
These are male piles and female piles. Main differences between these piles are
drilling conditions, reinforcement and concrete grade.
A. Female Pile Drilling
• Female piles will be drilled as ordinary piles. Pile boring (drilling) will be carried
out by using the piling drilling rig. Casing and drilling tools will advance in
natural soil until end of drilling. During pile boring operations, different drilling
tools/attachments (bucket, auger, rock auger, core barrel) will be used
depending on the nature of soil encountered. Depth of the pile borehole will be
checked manually by a measuring tape and automatically by drilling rig’s own
depth meter. Drilling will stop at the +179.60 el. Concreting will be done same as
explained below, but without reinforcement cage installation and with low
grade bentonite added concrete.
Secant Pile Construction
B. Male Pile Drilling
• A male pile will only be constructed between two
finished neighbour female piles by cutting both of
them through until pile bottom. Cutting of female
piles will be done by the casing cutting shoe and
diamond tooth augers. Concrete grade, type and age
of the female piles are very important factors
considering firm and vertical construction of male
piles. Optimum age for a female pile to be cut is 3 to
5 days after casting. After 5 to 10 days are the
possible days also, but after 10 days female pile
concrete become harder to cut and increase risk of
inclination. While female concrete strength
(resistance against abrasion, crushing) rises, tendency
of inclination in male piles rises because drilling tool
will always lean towards to more soft medium. To
balance the resistance as much as possible against
soil, female piles will be casted with bentonite added
concrete. Other than cutting concrete of female piles,
drilling will be continued and finished similar with
female piles.
Secant Pile Construction
Reinforcement cage installation (only in male piles)
Reinforcement cage will only be installed in
male piles. Female piles will be constructed
without reinforcement cage. All
reinforcement cages will be inspected by
Client prior to deem as completed.
. Two hooks as detailed in document CS-
MX1217-CV-DTL-0005-001 - Kura West (AZ)
River Crossing - Drive Shaft Secant Piles.
Whole cage will be suspended from here on
to the casing top via 2 pcs 32 mm rebar.
This fixing job is going to be repeated for all
cage parts until req. length of the cage is
achieved as shown in the drawings unless
drilled depth is more than designed depth.
Secant Pile Construction
Placement of concrete & Extraction of Casing
Concreting of the pile will start and continue without any
interruption to form a continuous full cross-section of the
pile.
The tremie pipe with watertight connections will be
lowered inside the pile borehole extending down to base
of the pile borehole. Tip of the reinforcement cage shall
be open and un-bended to lower the tremie until the end
of hole.
C30/37 concrete which has a slump value between 19cm
to 21cm to be placed by tremie in one continuous
operation and shall not be discharged freely into the
water. Concreting will be done by pump connected to
tremie and pile/casing will be filled with concrete up to
the top of casing level. Clean concrete (concrete with
coarse aggregates) will be seen to be overflow before
stopping concreting.
Secant Pile Construction
Placement of concrete & Extraction of Casing
Tremie will be lifted in parallel to concreting and during lifting min. Three meters tremie will be within concrete at all
times. After completion of concrete tremie will be dismounted from the pump, the casing will be lifted 2 m from
platform level and at this height casing extraction will be stopped. Concrete will be added from top by concrete pump
to fill the casing again to the top level of casing. This will provide enough head of concrete and will make sure that
when casing is removed the concrete will outflow and a proper level of top concrete level will be obtained. The exact
height should be confirmed with site performance and can be reduce/increased to achieve the target concrete
finishing level.
Secant Pile Construction
Placement of concrete & Extraction of Casing
• The casing will be removed in parts (4 meters and 5
meters) as concrete rises inside the casing. As nature of
the work, concrete level will drop as casing is removed. It
is critical not to let concrete level drop below casing
bottom. Before removing last part of the casing and
tremie, top of the pile will be filled with concrete from
mobile pump hose, from inside. This will ensure concrete
to remain above cut-off level after casing removal.
• Concreting of female piles has two differences from male
piles; concreting will be done without reinforcement
cage installation and concrete grade will be lower than
male pile’s concrete grade. Both intentions are for to
allow male piles to cut through female piles.
Secant Pile Construction
Placement of concrete & Extraction of Casing
• Fresh mixed bentonite slurry will be added in to the
mixer not more than 5% in weight of cement at the
concrete plant. Addition of bentonite in to the female
piles will not cause any degradation in water proofing in
female piles because slurry will be thoroughly mixed
with fresh concrete before placement to avoid
heterogeneous accumulation and concreting will be
done similar with the male piles using tremie pipe from
bottom to the top, in one continuous operation. Casing
will be extracted in two or more stage to ensure
sufficient concrete head to remain above cut-off level.
Secant Pile Construction
Placement of concrete & Extraction of Casing
THANK
YOU

Mais conteúdo relacionado

Mais procurados

Diaphragm wall: Construction and Design
Diaphragm wall: Construction and DesignDiaphragm wall: Construction and Design
Diaphragm wall: Construction and DesignUmer Farooq
 
APPLIED USE OF PVC & RUBBER WATER-STOPS ON CONCRETE STRUCTURES
APPLIED USE OF PVC & RUBBER WATER-STOPS ON CONCRETE STRUCTURESAPPLIED USE OF PVC & RUBBER WATER-STOPS ON CONCRETE STRUCTURES
APPLIED USE OF PVC & RUBBER WATER-STOPS ON CONCRETE STRUCTURESVladimir Popovic
 
Pull out test for concrete
Pull out test for concretePull out test for concrete
Pull out test for concreteAyaz khan
 
Construction dewatering
Construction dewateringConstruction dewatering
Construction dewateringShubham Parab
 
Structural design of tunnel lining
Structural design of tunnel liningStructural design of tunnel lining
Structural design of tunnel liningMahesh Raj Bhatt
 
Introduction & under ground water tank problem
Introduction & under ground water tank problemIntroduction & under ground water tank problem
Introduction & under ground water tank problemdhineshkumar002
 
Dewatering techniques
Dewatering techniquesDewatering techniques
Dewatering techniquesjamali husain
 
Goetech. engg. Ch# 03 settlement analysis signed
Goetech. engg. Ch# 03 settlement analysis signedGoetech. engg. Ch# 03 settlement analysis signed
Goetech. engg. Ch# 03 settlement analysis signedIrfan Malik
 
Secant piled walls dsign - تصميم خوازيق الجدران الساندة - ميكرو بايل
Secant piled walls  dsign - تصميم خوازيق الجدران الساندة - ميكرو بايلSecant piled walls  dsign - تصميم خوازيق الجدران الساندة - ميكرو بايل
Secant piled walls dsign - تصميم خوازيق الجدران الساندة - ميكرو بايلDr.youssef hamida
 
Well foundations
Well foundationsWell foundations
Well foundationsganesh6561
 

Mais procurados (20)

Diaphragm wall: Construction and Design
Diaphragm wall: Construction and DesignDiaphragm wall: Construction and Design
Diaphragm wall: Construction and Design
 
APPLIED USE OF PVC & RUBBER WATER-STOPS ON CONCRETE STRUCTURES
APPLIED USE OF PVC & RUBBER WATER-STOPS ON CONCRETE STRUCTURESAPPLIED USE OF PVC & RUBBER WATER-STOPS ON CONCRETE STRUCTURES
APPLIED USE OF PVC & RUBBER WATER-STOPS ON CONCRETE STRUCTURES
 
Method Statement D Wall
Method Statement D WallMethod Statement D Wall
Method Statement D Wall
 
Diaphragm wall
Diaphragm wallDiaphragm wall
Diaphragm wall
 
Pull out test for concrete
Pull out test for concretePull out test for concrete
Pull out test for concrete
 
Diaphragm wall construction
Diaphragm wall constructionDiaphragm wall construction
Diaphragm wall construction
 
Diaphragm wall
Diaphragm wallDiaphragm wall
Diaphragm wall
 
Lining in tunnels
Lining in tunnelsLining in tunnels
Lining in tunnels
 
Retaining wall
Retaining wallRetaining wall
Retaining wall
 
Construction dewatering
Construction dewateringConstruction dewatering
Construction dewatering
 
Structural design of tunnel lining
Structural design of tunnel liningStructural design of tunnel lining
Structural design of tunnel lining
 
Grouting
GroutingGrouting
Grouting
 
Deep excavation
Deep excavationDeep excavation
Deep excavation
 
Introduction & under ground water tank problem
Introduction & under ground water tank problemIntroduction & under ground water tank problem
Introduction & under ground water tank problem
 
Dewatering techniques
Dewatering techniquesDewatering techniques
Dewatering techniques
 
BCT MODULE 2 - Caisson
BCT MODULE 2 - CaissonBCT MODULE 2 - Caisson
BCT MODULE 2 - Caisson
 
Goetech. engg. Ch# 03 settlement analysis signed
Goetech. engg. Ch# 03 settlement analysis signedGoetech. engg. Ch# 03 settlement analysis signed
Goetech. engg. Ch# 03 settlement analysis signed
 
Secant piled walls dsign - تصميم خوازيق الجدران الساندة - ميكرو بايل
Secant piled walls  dsign - تصميم خوازيق الجدران الساندة - ميكرو بايلSecant piled walls  dsign - تصميم خوازيق الجدران الساندة - ميكرو بايل
Secant piled walls dsign - تصميم خوازيق الجدران الساندة - ميكرو بايل
 
Deep excavation report
Deep excavation reportDeep excavation report
Deep excavation report
 
Well foundations
Well foundationsWell foundations
Well foundations
 

Destaque

Anchored pile retaining wall embedded, by Dr. sachpazis
Anchored pile retaining wall embedded, by Dr. sachpazisAnchored pile retaining wall embedded, by Dr. sachpazis
Anchored pile retaining wall embedded, by Dr. sachpazisDr.Costas Sachpazis
 
Design and construction of auger cast piles by Dr. Malek Smadi of GEOTILL
Design and construction of auger cast piles by Dr. Malek Smadi of GEOTILLDesign and construction of auger cast piles by Dr. Malek Smadi of GEOTILL
Design and construction of auger cast piles by Dr. Malek Smadi of GEOTILLDr. Malek Smadi
 
Under reamed pile construction (usefulsearch.org) (useful search)
Under reamed pile construction (usefulsearch.org)  (useful search)Under reamed pile construction (usefulsearch.org)  (useful search)
Under reamed pile construction (usefulsearch.org) (useful search)Make Mannan
 
Temeltas Bored Piling 25.06
Temeltas Bored Piling 25.06Temeltas Bored Piling 25.06
Temeltas Bored Piling 25.06Can Cihan Cankat
 
Module 3 pile types and construction
Module 3   pile types and constructionModule 3   pile types and construction
Module 3 pile types and constructionAmelie P
 
Pile Foundation presentation
Pile Foundation presentationPile Foundation presentation
Pile Foundation presentationSevar Dilkhaz
 
PILE FOUNDATION-INDIA
PILE FOUNDATION-INDIAPILE FOUNDATION-INDIA
PILE FOUNDATION-INDIAaditya singh
 
Simplified design of reinforced concrete buildings
Simplified design of reinforced concrete buildings Simplified design of reinforced concrete buildings
Simplified design of reinforced concrete buildings Sarmed Shukur
 

Destaque (16)

Certificate of Appreciation
Certificate of Appreciation Certificate of Appreciation
Certificate of Appreciation
 
Anchored pile retaining wall embedded, by Dr. sachpazis
Anchored pile retaining wall embedded, by Dr. sachpazisAnchored pile retaining wall embedded, by Dr. sachpazis
Anchored pile retaining wall embedded, by Dr. sachpazis
 
Cmh bp profile 2013
Cmh bp profile 2013Cmh bp profile 2013
Cmh bp profile 2013
 
Design and construction of auger cast piles by Dr. Malek Smadi of GEOTILL
Design and construction of auger cast piles by Dr. Malek Smadi of GEOTILLDesign and construction of auger cast piles by Dr. Malek Smadi of GEOTILL
Design and construction of auger cast piles by Dr. Malek Smadi of GEOTILL
 
ADSC Presentation - 11.30.12
ADSC Presentation - 11.30.12ADSC Presentation - 11.30.12
ADSC Presentation - 11.30.12
 
Under reamed pile construction (usefulsearch.org) (useful search)
Under reamed pile construction (usefulsearch.org)  (useful search)Under reamed pile construction (usefulsearch.org)  (useful search)
Under reamed pile construction (usefulsearch.org) (useful search)
 
Sheet pile presentation
Sheet pile presentationSheet pile presentation
Sheet pile presentation
 
Temeltas Bored Piling 25.06
Temeltas Bored Piling 25.06Temeltas Bored Piling 25.06
Temeltas Bored Piling 25.06
 
Module 3 pile types and construction
Module 3   pile types and constructionModule 3   pile types and construction
Module 3 pile types and construction
 
Different types of pile
Different types of pile Different types of pile
Different types of pile
 
Deep excavation
Deep excavationDeep excavation
Deep excavation
 
Pile Foundation presentation
Pile Foundation presentationPile Foundation presentation
Pile Foundation presentation
 
PILE FOUNDATION-INDIA
PILE FOUNDATION-INDIAPILE FOUNDATION-INDIA
PILE FOUNDATION-INDIA
 
Pile foundation ppt
Pile foundation pptPile foundation ppt
Pile foundation ppt
 
Pile foundation
Pile foundationPile foundation
Pile foundation
 
Simplified design of reinforced concrete buildings
Simplified design of reinforced concrete buildings Simplified design of reinforced concrete buildings
Simplified design of reinforced concrete buildings
 

Semelhante a Microtunel Construction / Secant Pile

Sample copy of IT PPT.pptx
Sample copy of IT PPT.pptxSample copy of IT PPT.pptx
Sample copy of IT PPT.pptxHimanshumangal12
 
Bored cast insitu
Bored cast insituBored cast insitu
Bored cast insituLingWei11
 
Construction Sequence.pptx
Construction Sequence.pptxConstruction Sequence.pptx
Construction Sequence.pptxssuser480182
 
ppt on sub structure construction.pptx
ppt on sub structure construction.pptxppt on sub structure construction.pptx
ppt on sub structure construction.pptxRaviUraiya1
 
civil enginnering industrial training report
civil enginnering industrial training report civil enginnering industrial training report
civil enginnering industrial training report KRISHNA MURARI
 
civil enginnering industrial training report
civil enginnering industrial training report civil enginnering industrial training report
civil enginnering industrial training report KRISHNA MURARI
 
signature bridge short presentation
signature bridge short presentationsignature bridge short presentation
signature bridge short presentationPravin Gaurav
 
Chapter 5 formwork
Chapter 5 formworkChapter 5 formwork
Chapter 5 formworkKHUSHBU SHAH
 
pile foundation and pile cap presentation
pile foundation and pile cap presentationpile foundation and pile cap presentation
pile foundation and pile cap presentationRahul bhatnagar
 
Summer training report
Summer training reportSummer training report
Summer training reportaki8872233
 
Placing and compaction of cement concrete
Placing and compaction of cement concretePlacing and compaction of cement concrete
Placing and compaction of cement concretePramod GK
 
Diaphragm wall construction
Diaphragm wall constructionDiaphragm wall construction
Diaphragm wall constructionABHISHEK THAKKAE
 
Industrial Training Report-(2012-13)
Industrial Training Report-(2012-13)Industrial Training Report-(2012-13)
Industrial Training Report-(2012-13)AJAY SHAHU
 
Running Head BRIDGE DESIGN1BRIDGE DESIGN31.docx
Running Head BRIDGE DESIGN1BRIDGE DESIGN31.docxRunning Head BRIDGE DESIGN1BRIDGE DESIGN31.docx
Running Head BRIDGE DESIGN1BRIDGE DESIGN31.docxtoddr4
 

Semelhante a Microtunel Construction / Secant Pile (20)

Board pile method
Board pile methodBoard pile method
Board pile method
 
Concrete
ConcreteConcrete
Concrete
 
Sample copy of IT PPT.pptx
Sample copy of IT PPT.pptxSample copy of IT PPT.pptx
Sample copy of IT PPT.pptx
 
Bored cast insitu
Bored cast insituBored cast insitu
Bored cast insitu
 
Construction Sequence.pptx
Construction Sequence.pptxConstruction Sequence.pptx
Construction Sequence.pptx
 
ppt on sub structure construction.pptx
ppt on sub structure construction.pptxppt on sub structure construction.pptx
ppt on sub structure construction.pptx
 
civil enginnering industrial training report
civil enginnering industrial training report civil enginnering industrial training report
civil enginnering industrial training report
 
civil enginnering industrial training report
civil enginnering industrial training report civil enginnering industrial training report
civil enginnering industrial training report
 
Form Work
Form Work Form Work
Form Work
 
signature bridge short presentation
signature bridge short presentationsignature bridge short presentation
signature bridge short presentation
 
Chapter 5 formwork
Chapter 5 formworkChapter 5 formwork
Chapter 5 formwork
 
pile foundation and pile cap presentation
pile foundation and pile cap presentationpile foundation and pile cap presentation
pile foundation and pile cap presentation
 
Cast in situ Pile
Cast in situ PileCast in situ Pile
Cast in situ Pile
 
Well Foundation
Well FoundationWell Foundation
Well Foundation
 
Summer training report
Summer training reportSummer training report
Summer training report
 
training1 (1).pptx
training1 (1).pptxtraining1 (1).pptx
training1 (1).pptx
 
Placing and compaction of cement concrete
Placing and compaction of cement concretePlacing and compaction of cement concrete
Placing and compaction of cement concrete
 
Diaphragm wall construction
Diaphragm wall constructionDiaphragm wall construction
Diaphragm wall construction
 
Industrial Training Report-(2012-13)
Industrial Training Report-(2012-13)Industrial Training Report-(2012-13)
Industrial Training Report-(2012-13)
 
Running Head BRIDGE DESIGN1BRIDGE DESIGN31.docx
Running Head BRIDGE DESIGN1BRIDGE DESIGN31.docxRunning Head BRIDGE DESIGN1BRIDGE DESIGN31.docx
Running Head BRIDGE DESIGN1BRIDGE DESIGN31.docx
 

Mais de Togrul Mukhtarov, MSc. MICE, Aff.M.ASCE (8)

Togrul Mukhtarov PMP
Togrul Mukhtarov PMPTogrul Mukhtarov PMP
Togrul Mukhtarov PMP
 
Certificate of Completion: Project management professional (PMP)
Certificate of Completion: Project management professional (PMP)Certificate of Completion: Project management professional (PMP)
Certificate of Completion: Project management professional (PMP)
 
Construction Management: Safety & Health
Construction Management: Safety & HealthConstruction Management: Safety & Health
Construction Management: Safety & Health
 
Construction Project Management
Construction Project ManagementConstruction Project Management
Construction Project Management
 
Conscious leadership
Conscious leadershipConscious leadership
Conscious leadership
 
Emotional intelligence for business
Emotional intelligence for businessEmotional intelligence for business
Emotional intelligence for business
 
Affiliate Member ASCE
Affiliate Member ASCEAffiliate Member ASCE
Affiliate Member ASCE
 
Twi certificate of satisfactory attendance cswip 3.1
Twi   certificate of satisfactory attendance cswip 3.1Twi   certificate of satisfactory attendance cswip 3.1
Twi certificate of satisfactory attendance cswip 3.1
 

Último

CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfCCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfAsst.prof M.Gokilavani
 
Input Output Management in Operating System
Input Output Management in Operating SystemInput Output Management in Operating System
Input Output Management in Operating SystemRashmi Bhat
 
Gravity concentration_MI20612MI_________
Gravity concentration_MI20612MI_________Gravity concentration_MI20612MI_________
Gravity concentration_MI20612MI_________Romil Mishra
 
Instrumentation, measurement and control of bio process parameters ( Temperat...
Instrumentation, measurement and control of bio process parameters ( Temperat...Instrumentation, measurement and control of bio process parameters ( Temperat...
Instrumentation, measurement and control of bio process parameters ( Temperat...121011101441
 
multiple access in wireless communication
multiple access in wireless communicationmultiple access in wireless communication
multiple access in wireless communicationpanditadesh123
 
Main Memory Management in Operating System
Main Memory Management in Operating SystemMain Memory Management in Operating System
Main Memory Management in Operating SystemRashmi Bhat
 
Research Methodology for Engineering pdf
Research Methodology for Engineering pdfResearch Methodology for Engineering pdf
Research Methodology for Engineering pdfCaalaaAbdulkerim
 
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catchers
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor CatchersTechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catchers
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catcherssdickerson1
 
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTION
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTIONTHE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTION
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTIONjhunlian
 
Arduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.pptArduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.pptSAURABHKUMAR892774
 
Crushers to screens in aggregate production
Crushers to screens in aggregate productionCrushers to screens in aggregate production
Crushers to screens in aggregate productionChinnuNinan
 
Earthing details of Electrical Substation
Earthing details of Electrical SubstationEarthing details of Electrical Substation
Earthing details of Electrical Substationstephanwindworld
 
Immutable Image-Based Operating Systems - EW2024.pdf
Immutable Image-Based Operating Systems - EW2024.pdfImmutable Image-Based Operating Systems - EW2024.pdf
Immutable Image-Based Operating Systems - EW2024.pdfDrew Moseley
 
Autonomous emergency braking system (aeb) ppt.ppt
Autonomous emergency braking system (aeb) ppt.pptAutonomous emergency braking system (aeb) ppt.ppt
Autonomous emergency braking system (aeb) ppt.pptbibisarnayak0
 
BSNL Internship Training presentation.pptx
BSNL Internship Training presentation.pptxBSNL Internship Training presentation.pptx
BSNL Internship Training presentation.pptxNiranjanYadav41
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AIabhishek36461
 
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfg
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfgUnit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfg
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfgsaravananr517913
 
Crystal Structure analysis and detailed information pptx
Crystal Structure analysis and detailed information pptxCrystal Structure analysis and detailed information pptx
Crystal Structure analysis and detailed information pptxachiever3003
 

Último (20)

CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfCCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
 
young call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Serviceyoung call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Service
 
Input Output Management in Operating System
Input Output Management in Operating SystemInput Output Management in Operating System
Input Output Management in Operating System
 
Gravity concentration_MI20612MI_________
Gravity concentration_MI20612MI_________Gravity concentration_MI20612MI_________
Gravity concentration_MI20612MI_________
 
Instrumentation, measurement and control of bio process parameters ( Temperat...
Instrumentation, measurement and control of bio process parameters ( Temperat...Instrumentation, measurement and control of bio process parameters ( Temperat...
Instrumentation, measurement and control of bio process parameters ( Temperat...
 
multiple access in wireless communication
multiple access in wireless communicationmultiple access in wireless communication
multiple access in wireless communication
 
Main Memory Management in Operating System
Main Memory Management in Operating SystemMain Memory Management in Operating System
Main Memory Management in Operating System
 
Designing pile caps according to ACI 318-19.pptx
Designing pile caps according to ACI 318-19.pptxDesigning pile caps according to ACI 318-19.pptx
Designing pile caps according to ACI 318-19.pptx
 
Research Methodology for Engineering pdf
Research Methodology for Engineering pdfResearch Methodology for Engineering pdf
Research Methodology for Engineering pdf
 
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catchers
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor CatchersTechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catchers
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catchers
 
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTION
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTIONTHE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTION
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTION
 
Arduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.pptArduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.ppt
 
Crushers to screens in aggregate production
Crushers to screens in aggregate productionCrushers to screens in aggregate production
Crushers to screens in aggregate production
 
Earthing details of Electrical Substation
Earthing details of Electrical SubstationEarthing details of Electrical Substation
Earthing details of Electrical Substation
 
Immutable Image-Based Operating Systems - EW2024.pdf
Immutable Image-Based Operating Systems - EW2024.pdfImmutable Image-Based Operating Systems - EW2024.pdf
Immutable Image-Based Operating Systems - EW2024.pdf
 
Autonomous emergency braking system (aeb) ppt.ppt
Autonomous emergency braking system (aeb) ppt.pptAutonomous emergency braking system (aeb) ppt.ppt
Autonomous emergency braking system (aeb) ppt.ppt
 
BSNL Internship Training presentation.pptx
BSNL Internship Training presentation.pptxBSNL Internship Training presentation.pptx
BSNL Internship Training presentation.pptx
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AI
 
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfg
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfgUnit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfg
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfg
 
Crystal Structure analysis and detailed information pptx
Crystal Structure analysis and detailed information pptxCrystal Structure analysis and detailed information pptx
Crystal Structure analysis and detailed information pptx
 

Microtunel Construction / Secant Pile

  • 1. SCPX Project – Kura West Kazakh Microtunel Construction
  • 2.
  • 3. 1. Guide Wall Construction 2. Secant Pile Construction Reinforcement cage installation (only in male piles) Placement of concrete & Extraction of Casing Milestones
  • 4. Guide Wall Construction Scope of Guide Wall Construction is: • Surveying & excavating trenches for guide walls; • Levelling & Placing Lean Concrete; • Reinforcement & formwork installation; • Placement of concrete; • Striking of formwork & Backfilling. This construction element will act as reference points for pile centres. Please see figure for plan and cross sectional view of guide wall. In order to resist drilling rig own weight and down force, guide wall height is decided as 1meter. Backhoe loader will excavate trenches for the footprint of guide walls including working space for formwork
  • 5. Guide Wall Construction Port Baku Tower Project – Guide Wall Construction for Secant Pile
  • 6. Secant Pile Construction OPERATIONAL SEQUENCE • Driving the Casing; • Drilling of Piles; • Reinforcement cage installation (only in male piles); • Placement of concrete and Extraction of Casing. Following casting of the guide wall a piling mat was constructed inside the shaft ring. There are two different kinds of piles in SCPX Kure West River Crossing Shaft secant piles. These are 30pcs female piles which will be constructed with low grade bentonite added concrete (C12/15), without reinforcement cage; and 30pcs male piles which will be constructed between two adjacent female piles by cutting them through, with high grade concrete (C30/37) and with reinforcement cage.
  • 7. Secant Pile Construction OPERATIONAL SEQUENCE In a secant piled design, there are two main types of elements to be constructed. These are male piles and female piles. Main differences between these piles are drilling conditions, reinforcement and concrete grade. A. Female Pile Drilling • Female piles will be drilled as ordinary piles. Pile boring (drilling) will be carried out by using the piling drilling rig. Casing and drilling tools will advance in natural soil until end of drilling. During pile boring operations, different drilling tools/attachments (bucket, auger, rock auger, core barrel) will be used depending on the nature of soil encountered. Depth of the pile borehole will be checked manually by a measuring tape and automatically by drilling rig’s own depth meter. Drilling will stop at the +179.60 el. Concreting will be done same as explained below, but without reinforcement cage installation and with low grade bentonite added concrete.
  • 8. Secant Pile Construction B. Male Pile Drilling • A male pile will only be constructed between two finished neighbour female piles by cutting both of them through until pile bottom. Cutting of female piles will be done by the casing cutting shoe and diamond tooth augers. Concrete grade, type and age of the female piles are very important factors considering firm and vertical construction of male piles. Optimum age for a female pile to be cut is 3 to 5 days after casting. After 5 to 10 days are the possible days also, but after 10 days female pile concrete become harder to cut and increase risk of inclination. While female concrete strength (resistance against abrasion, crushing) rises, tendency of inclination in male piles rises because drilling tool will always lean towards to more soft medium. To balance the resistance as much as possible against soil, female piles will be casted with bentonite added concrete. Other than cutting concrete of female piles, drilling will be continued and finished similar with female piles.
  • 9. Secant Pile Construction Reinforcement cage installation (only in male piles) Reinforcement cage will only be installed in male piles. Female piles will be constructed without reinforcement cage. All reinforcement cages will be inspected by Client prior to deem as completed. . Two hooks as detailed in document CS- MX1217-CV-DTL-0005-001 - Kura West (AZ) River Crossing - Drive Shaft Secant Piles. Whole cage will be suspended from here on to the casing top via 2 pcs 32 mm rebar. This fixing job is going to be repeated for all cage parts until req. length of the cage is achieved as shown in the drawings unless drilled depth is more than designed depth.
  • 10. Secant Pile Construction Placement of concrete & Extraction of Casing Concreting of the pile will start and continue without any interruption to form a continuous full cross-section of the pile. The tremie pipe with watertight connections will be lowered inside the pile borehole extending down to base of the pile borehole. Tip of the reinforcement cage shall be open and un-bended to lower the tremie until the end of hole. C30/37 concrete which has a slump value between 19cm to 21cm to be placed by tremie in one continuous operation and shall not be discharged freely into the water. Concreting will be done by pump connected to tremie and pile/casing will be filled with concrete up to the top of casing level. Clean concrete (concrete with coarse aggregates) will be seen to be overflow before stopping concreting.
  • 11. Secant Pile Construction Placement of concrete & Extraction of Casing Tremie will be lifted in parallel to concreting and during lifting min. Three meters tremie will be within concrete at all times. After completion of concrete tremie will be dismounted from the pump, the casing will be lifted 2 m from platform level and at this height casing extraction will be stopped. Concrete will be added from top by concrete pump to fill the casing again to the top level of casing. This will provide enough head of concrete and will make sure that when casing is removed the concrete will outflow and a proper level of top concrete level will be obtained. The exact height should be confirmed with site performance and can be reduce/increased to achieve the target concrete finishing level.
  • 12. Secant Pile Construction Placement of concrete & Extraction of Casing • The casing will be removed in parts (4 meters and 5 meters) as concrete rises inside the casing. As nature of the work, concrete level will drop as casing is removed. It is critical not to let concrete level drop below casing bottom. Before removing last part of the casing and tremie, top of the pile will be filled with concrete from mobile pump hose, from inside. This will ensure concrete to remain above cut-off level after casing removal. • Concreting of female piles has two differences from male piles; concreting will be done without reinforcement cage installation and concrete grade will be lower than male pile’s concrete grade. Both intentions are for to allow male piles to cut through female piles.
  • 13. Secant Pile Construction Placement of concrete & Extraction of Casing • Fresh mixed bentonite slurry will be added in to the mixer not more than 5% in weight of cement at the concrete plant. Addition of bentonite in to the female piles will not cause any degradation in water proofing in female piles because slurry will be thoroughly mixed with fresh concrete before placement to avoid heterogeneous accumulation and concreting will be done similar with the male piles using tremie pipe from bottom to the top, in one continuous operation. Casing will be extracted in two or more stage to ensure sufficient concrete head to remain above cut-off level.
  • 14. Secant Pile Construction Placement of concrete & Extraction of Casing THANK YOU