2. Ch #-2
Allocating Resources to the Project
Allocation of physical resources to one or multiple
projects.
At any given time, the firm may have fixed level of
various resources like
- labor-hours of various types of professionals
- machine hours of various types of machinery
- hours of computing time
- specialized locations
The project schedule should be adjusted to
smooth the use of the resources
3. Critical Path Method—Crashing a
Project
Time and cost are interrelated
The faster an activity is completed, the
more it costs
Change the schedule and you change
the budget
Thus many activities can be speeded up
by spending more money
4. What is Crashing / Crunching?
To speed up, or expedite, a project
Of course, the resources to do this must be
available
Crunching a project changes the schedule for
all activities
This will have an impact on schedules for all
the subcontractors
Crunching a project often introduces
unanticipated problems
5. Direct Cost vs. Indirect Cost
Direct cost increases if the activity
duration is to be reduced.
The Indirect cost decreases if the activity
duration is to be reduced.
8. Activity Slopes—Cost per Period for
Crashing
Table 9-2
Negative slope: as the time required for a project or task is decreased,
the cost is increased.
9. Ch #-9
Crashing the Project
When crashing a project, first task is to
develop a table or graph of the cost of a
project as a function of the project’s various
possible completion dates.
Crash selected activities, one at a time, to
decrease the project duration.
10. Ch #-10
Crashing the Project
Two principles:
•Focus on the critical path(s) when trying to
shorten the duration of a project. (Crashing
a noncritical activity will not influence project
duration.)
•When shortening a project’s duration, select
the least expensive way to do it.
15. The Resource Allocation
Problem
As discussed, CPM/PERT ignore resource
utilization and availability
With external resources, this may not be a
problem
It is, however, a concern with internal
resources
Schedules need to be evaluated in terms of
both time and resources
16. Resource Allocation
It is common to see the resource allocation
problem in terms of manpower, but it can apply
to equipment and capital as well
Resource allocation in project management is
very similar to capacity planning in production
management
Both the approaches to the problem and
potential solutions to the problem are very
similar
17. Resource Loading
Resource loading describes the amount
of resources an existing schedule
requires
Gives an understanding of the demands
a project will make of a firm’s resources
20. Resource Leveling
Less hands-on management is required
May be able to use just-in-time inventory
Improves morale
Fewer personnel problems
21. Resource Leveling Continued
When an activity has slack, we can move that
activity to shift its resource usage
May also be possible to alter the sequence of
activities to levelize resources
Small projects can be levelized by hand
Software can levelize resources for larger
projects
Large projects with multiple resources are very
complex to levelize
22. Constrained Resource Scheduling
Heuristic
Approach
An approach, such as a
rule of thumb, that yields
a good solution that may
or may not be optimal.
Optimization
Approach
An approach, such as
linear programming, that
yields the one best
solution.
23. Heuristic Methods
The only feasible way on large projects
While not optimal, the schedules are very
good
Take the CPM/PERT schedule as a baseline
They sequentially step through the schedule
trying to move resource requirements around
to levelize them
Resources are moved around based on one or
more priority rules
24. Common Priority Rules
As soon as possible
As late as possible
Shortest task first
Most resources first
Minimum slack first
Most critical followers
Most successors
Arbitrary
25. Heuristic Methods Continued
These are just the common ones
There are many more
The heuristic can either start at the
beginning and work forwards
Or it can start at the end and work
backwards
26. Optimization Methods
Finds the one best solution
Uses either linear programming or
enumeration
Not all projects can be optimized
Approaches only work with small to
medium projects
27. Multi-Project Scheduling and
Resource Allocation
Scheduling and resource allocation problems increase
with more than one project
The greater the number of projects, the greater the
problems
One way is to consider each project as part of a much
larger project
However, different projects have different goals so
combining may not make sense
Must also tell us if there are resources to tackle new
projects we are considering
29. Schedule Slippage
The time past a project’s due date when the
project is completed
Slippage may cause penalties
Different projects will have different penalties
Expediting one project can cause others to slip
Taking on a new project can cause existing
projects to slip
30. Resource Utilization
The percentage of a resource that is
actually used
We want a schedule that smoothes out
the dips and peaks of resource utilization
This is especially true of labor, where
hiring and firing is expensive
31. In-Process Inventory
This is the amount of work waiting to be
processed because there is a shortage
of some resource
Similar to WIP in manufacturing
The cost here is holding cost
32. Heuristic Techniques
Multi-projects are too complex for
optimization approaches
Many of the heuristics are extensions of
the ones used for one project
33. Additional Priority Rules
Resource scheduling method
Minimum late finish time
Greatest resource demand
Greatest resource utilization
Most possible jobs
34. Goldratt’s Critical Chain
1. Optimism
2. Capacity should be equal to demand
3. The “Student Syndrome”
4. Multitasking to reduce idle time
5. Assuming network complexity makes no difference
6. Management cutting time to “motivate” workers
7. Game playing
8. Early finishes not canceling out late finishes