BT1	
Concurrent	Session	
11/9/17	10:00	AM	
	
	
	
	
The	NoEstimates	Game:	Improve	
Predictability	with	Less	Effort	
	
Prese...
Matthew	Phillip	
ThoughtWorks	
	
Matthew	Philip	is	the	director	of	learning	and	development	at	ThoughtWorks.	As	
a	coach,	...
# b e t t e r s o f t w a r e c o n | @ m a t t p h i l i p
TO ESTIMATE OR 

NOT TO ESTIMATE
Is that the Question?
@mattph...
Anúncio
Anúncio
Anúncio
Anúncio
Anúncio

Confira estes a seguir

1 de 27 Anúncio

To Estimate or Not to Estimate, is that the Question?

Baixar para ler offline

Wondering what NoEstimates means in practice, or why you would want to move toward NoEstimates? Perhaps you’ve heard the buzz or read Vasco Duarte’s book. Maybe you simply want to understand how you can spend less time estimating and more time delivering working software—all while providing your customers with some understanding of predictability. If so, Matthew Phillip will help you understand through lessons learned with NoEstimates what and to what degree different factors influence delivery time. Join Matthew to learn how to move from upfront intuition-based estimates to create a data-based probabilistic forecast that provides a more reliable way to talk about when stuff will be done—and expend less effort to do so. Learn to forecast when things will be done -- with less effort and more accuracy!

Wondering what NoEstimates means in practice, or why you would want to move toward NoEstimates? Perhaps you’ve heard the buzz or read Vasco Duarte’s book. Maybe you simply want to understand how you can spend less time estimating and more time delivering working software—all while providing your customers with some understanding of predictability. If so, Matthew Phillip will help you understand through lessons learned with NoEstimates what and to what degree different factors influence delivery time. Join Matthew to learn how to move from upfront intuition-based estimates to create a data-based probabilistic forecast that provides a more reliable way to talk about when stuff will be done—and expend less effort to do so. Learn to forecast when things will be done -- with less effort and more accuracy!

Anúncio
Anúncio

Mais Conteúdo rRelacionado

Diapositivos para si (20)

Semelhante a To Estimate or Not to Estimate, is that the Question? (20)

Anúncio

Mais de TechWell (20)

Mais recentes (20)

Anúncio

To Estimate or Not to Estimate, is that the Question?

  1. 1. BT1 Concurrent Session 11/9/17 10:00 AM The NoEstimates Game: Improve Predictability with Less Effort Presented by: Matthew Phillip ThoughtWorks Brought to you by: 350 Corporate Way, Suite 400, Orange Park, FL 32073 888---268---8770 ·· 904---278---0524 - info@techwell.com - https://www.techwell.com/
  2. 2. Matthew Phillip ThoughtWorks Matthew Philip is the director of learning and development at ThoughtWorks. As a coach, trainer, quality advocate, and facilitator, Matt helps organizations and teams become fit for their purpose through continuous learning. He draws on lean and agile values, principles, and practices (kanban method, XP, Scrum) to offer experience, models, and options to customers and teammates. He tweets at @mattphilip, blogs, and shares his presentations. Passionate about building learning organizations, Matt has designed games for fun and learning, including the NoEstimates game, which he has presented at conferences worldwide.
  3. 3. # b e t t e r s o f t w a r e c o n | @ m a t t p h i l i p TO ESTIMATE OR 
 NOT TO ESTIMATE Is that the Question? @mattphilip #bettersoftwarecon HOFSTADTER’S LAW “It always takes longer than you expect, even when you take into account Hofstadter’s Law.”
  4. 4. @mattphilip #bettersoftwarecon PARKINSON’S LAW Work expands so as to fill the time available for its completion. @mattphilip #bettersoftwarecon “POOR ESTIMATION SKILLS”
  5. 5. @mattphilip #bettersoftwarecon THE SPECTRUM OF ESTIMATING NeverEstimateAnything AlwaysEstimateEverything Estimate Default Behavior Don’t estimate Effort Factors All sources of variation Intuition Approach Data Deterministic Forecast Type Probabilistic Tasks in hours Level of Detail Work items in days High Effort Spent Low Estimating better Improvement Aim Reducing variation Commitment Management Service Expectations @mattphilip #bettersoftwarecon MANIFESTO RELEVANCE
  6. 6. @mattphilip #bettersoftwarecon MANIFESTO RELEVANCE @mattphilip #bettersoftwarecon WHAT NOESTIMATES IS NOT SAYING ▫︎ You are evil if you estimate ▫︎ All estimates are totally useless ▫︎ Stop doing your successful estimating practice ▫︎ Stop having the conversations to understand/analyze/ break down work ▫︎ Work items must be the same size ▫︎ You must place your full faith and confidence in Monte Carlo forecasts
  7. 7. @mattphilip #bettersoftwarecon WHAT NOESTIMATES IS SAYING ▫︎ Know why you are estimating ▫︎ Discover for yourself how good you are at estimating (measure) ▫︎ Keep doing the things that help you understand the work ▫︎ Upfront estimates need to be held loosely ▫︎ If you focus on delivering value quickly, you obviate the need for Iron Triangle considerations @mattphilip #bettersoftwarecon MY NOESTIMATES MANIFESTO … We have come to value: Reducing sources of variation over Improving estimating Data over Intuition* Probabilistic over Deterministic MVP scope over Full scope That is, while there is value in the items on the right, we value the items on the left more. *Neil Killick uses “empiricism over guesswork”
  8. 8. REDUCING SOURCES OF VARIATION @mattphilip #bettersoftwarecon DO YOU ASSUME CORRELATION? Is the initial sizing a good predictor for when you can get your stuff? In our case, the surprising truth was ”no.” — Mattias Skarin, Real-World Kanban
  9. 9. @mattphilip #bettersoftwarecon WHAT WE ESTIMATE Code @mattphilip #bettersoftwarecon WHAT WE ESTIMATE Analyze+Design+Code+Test+Deploy
  10. 10. @mattphilip #bettersoftwarecon WHAT ACTUALLY HAPPENS Analyze Code Test DeployDesign Wait for approval Wait for staff availability Wait for 
 rework Wait for API availability Wait for 
 higher-priority work to finish Wait for approval Wait for 
 blocker 
 removal @mattphilip #bettersoftwarecon WHAT’S GOING ON? Value-added time _________________________ Total elapsed delivery time Flow efficiency =
  11. 11. @mattphilip #bettersoftwarecon WHAT’S GOING ON? Low process efficiency (typically 5-15% in software delivery) means that even if we nailed the effort estimates … we would be accurately predicting 5-15% of elapsed delivery time!
 — Troy Magennis @mattphilip #bettersoftwarecon SOURCES OF VARIATION How many can you name?
  12. 12. @mattphilip #bettersoftwarecon SOURCES OF VARIATION Waiting for 
 availability Rework Team 
 dependencies Stages in team development (Tuckman) Steps/
 handoffs Selection 
 policy Essential 
 complication Accidental 
 complication System 
 dependencies Work In 
 Progress Technology/
 domain/
 product Specialization Team 
 composition Multitasking/
 context 
 switching Collaboration
 policy Blockers @mattphilip #bettersoftwarecon WHAT CAN YOU DO ABOUT VARIATION How many remedies
 can you name?
  13. 13. @mattphilip #bettersoftwarecon WHAT YOU CAN DO ABOUT VARIATION ▫︎Lower WIP ▫︎ConWIP/System WIP ▫︎Five Focusing Steps ▫︎Blocker clustering ▫︎Reduce workflow stages ▫︎Explicit policies ▫︎Cost of Delay scheduling, sequencing and selection ▫︎Reduce “expedites” Lean-Kanban @mattphilip #bettersoftwarecon WHAT YOU CAN DO ABOUT VARIATION ▫︎“Agile 101” (simple, decoupled design; thin vertical slices; pairing) ▫︎Identify/make visible/measure dependencies ▫︎Collaborate/Share work (Dimitar Bakardzhiev) ▫︎Spike and stabilize (Dan North) ▫︎Reduce accidental complexity (Liz Keogh) Team Why?
  14. 14. @mattphilip #bettersoftwarecon WHAT YOU CAN DO ABOUT VARIATION ▫︎Determine what actions would be different based on the estimate ▫︎Customer-based fitness criteria ▫︎Budgeting: Team run rate ▫︎Focus conversation on value, not cost ▫︎MVP and product ownership ▫︎Create probabilistic forecast ASAP (as soon as you have data) – together! ▫︎Service-Delivery Reviews ▫︎Teams: Keep teams together, dedicated (reduces context-switching, Tuckman stages) Business @mattphilip #bettersoftwarecon POLICIES TO REDUCE VARIATION ▫︎We will only start new work at about the same rate that we finish old work. ▫︎We will make every reasonable effort to finish all work that is started and minimize wasted effort due to discarded work items ▫︎If work becomes blocked, we will do everything we can do unblock that work as expeditiously as possible. ▫︎We will closely monitor our policies around the order in which we pull items through our system so that some work items do not sit and age unnecessarily. — Daniel Vacanti, When Will It Be Done?
  15. 15. DATA OVER INTUITION @mattphilip #bettersoftwarecon HUMAN BIAS ▫︎Recency ▫︎Availability ▫︎Gambler’s conceit ▫︎Anchoring ▫︎Halo effect ▫︎Motivational ▫︎Confirmation
  16. 16. @mattphilip #bettersoftwarecon FIRST, KNOW WHERE YOU ARE @mattphilip #bettersoftwarecon KEOGH’S “SCALE OF IGNORANCE” 1. Just about everyone in the world has done this. 2. Lots of people have done this, including someone on our team. 3. Someone in our company has done this, or we have access to expertise. 4. Someone in the world did this, but not in our organization (and probably at a competitor). 5. Nobody in the world has ever done this before.
  17. 17. @mattphilip #bettersoftwarecon DATA OVER INTUITION @mattphilip #bettersoftwarecon LET’S PRACTICE!
  18. 18. 31 PROBABILISTIC OVER DETERMINISTIC @mattphilip #bettersoftwarecon PROBABILISTIC OVER DETERMINISTIC Dec 28 — graphic courtesy of Larry Maccherone, (maccherone.com/lumenize)
  19. 19. @mattphilip #bettersoftwarecon VACANTI’S VERITY When making a forecast (predicting the future), you have to accept that there is more than one possible outcome. Therefore… A forecast is a calculation about the future that includes both a range and a probability of that range occurring. @mattphilip #bettersoftwarecon PROBABILISTIC OVER DETERMINISTIC
  20. 20. @mattphilip #bettersoftwarecon PROBABILISTIC OVER DETERMINISTIC @mattphilip #bettersoftwarecon PROBABILISTIC OVER DETERMINISTIC
  21. 21. @mattphilip #bettersoftwarecon PROBABILISTIC OVER DETERMINISTIC 2% 20% 21% 3% 16% 16% 9% 7% 2% 2% 2% Dec 28 Feb 17Nov 30 Jan 20 @mattphilip #bettersoftwarecon PROBABILISTIC FORECASTING
  22. 22. @mattphilip #bettersoftwarecon PROBABILISTIC FORECASTING: ONE ITEM @mattphilip #bettersoftwarecon BACK TO YOUR SCATTERPLOT
  23. 23. @mattphilip #bettersoftwarecon STRAIGHT-LINE (AVERAGE) FORECASTS Team A Team B Work item #1 5 days 3 days Work item #2 1 day 3 days Work item #3 3 days 3 days Average 3 days 3 days 3-day delivery time 
 expectancy 66% 100% @mattphilip #bettersoftwarecon EXPECTATIONS, NOT COMMITMENTS
  24. 24. @mattphilip #bettersoftwarecon SERVICE-DELIVERY EXPECTATIONS Expectation Performance Expedite 90% 3 days or less Standard Urgency 85% 10 days or less Fixed-Date 90% On-time 44 IN SUMMARY
  25. 25. @mattphilip #bettersoftwarecon TO ESTIMATE OR NOT TO ESTIMATE? NeverEstimateAnything AlwaysEstimateEverything Estimate Default Behavior Don’t estimate Effort Factors All sources of variation Intuition Approach Data Deterministic Forecast Type Probabilistic Tasks in hours Level of Detail Work items in days High Effort Spent Low Estimating better Improvement Aim Reducing variation Commitment Management Service Expectations @mattphilip #bettersoftwarecon BETTER QUESTIONS TO ASK @mattphilip ▫︎In what context would estimates bring value, and what are we willing to do about it when they don’t? – Woody Zuill ▫︎How much time do we want to invest in this? – Matt Wynne ▫︎What can you do to maximize value and reduce risk in planning and delivery? – Vasco Duarte ▫︎Can we build a minimal set of functionality and then learn what else we must build? ▫︎Would we/you not invest in this work? If not, at what order-of-magnitude estimate would we/you take that action? ▫︎What actions would be different based on an estimate?
  26. 26. @mattphilip #bettersoftwarecon HOW TO GET STARTED (PROJECT IN PROGRESS) 1. Continue to discuss the work to analyze it and break it into thin vertical slices. 2. Start tracking two pieces of data for each work item: commit date and delivery date. 3. After accumulating 10 data points, run a Monte Carlo simulation to provide a probabilistic forecast. 4. Begin answering the “When” question using data, either at the project level or individual work-item level. 5. Validate whether the probabilistic forecasts match what actually occurs. 6. If the forecasts are helpful, wean your team off estimating. 7. Focus improvement efforts on reducing the sources of variation. @mattphilip #bettersoftwarecon HOW TO GET STARTED (NEW PROJECT) 1. Ask the “better questions” above about the use and importance of estimates. 2. Use reference-class data (similar delivery times from other projects in similar tech stacks with similar teams) to provide an initial probabilistic forecast 3. As soon as you accumulate 10 data points, run a Monte Carlo simulation to provide an updated probabilistic forecast. 4. Continually reforecast when you get more information.
  27. 27. @mattphilip #bettersoftwarecon REFERENCES AND FURTHER EXPLORATION ▫︎ noestimatesbook.com (Vasco Duarte) ▫︎ infoq.com/articles/noestimates-monte-carlo (Dimitar Bakardzhiev) ▫︎ priceonomics.com/why-are-projects-always-behind-schedule ▫︎ http://scrumandkanban.co.uk/estimation-meets-cynefin/ ▫︎ ronjeffries.com ▫︎ Lizkeogh.com ▫︎ https://neilkillick.wordpress.com/ ▫︎ http://zuill.us/WoodyZuill/ ▫︎ mattphilip.wordpress.com/noestimates-game ▫︎ When Will It Be Done? (Dan Vacanti) ▫︎ focusedobjective.com (Troy Magennis) ▫︎ actionableagile.com (Dan Vacanti) ▫︎ kanbanize.com ▫︎ scrum.org @mattphilip #bettersoftwarecon Questions? THANK YOU

×