“Comparative Study of E-tendering &
Traditional tendering in Construction
Projects”
By
Tejas C. Patil.
Under Guidance of
Prof. Ashish P. Waghmare.
Dr. D. Y. Patil School of Engineering and Technology, Lohgaon Pune
18th April 2016
Introduction
Literature Survey
Objectives
Recommendation, Outcomes from study & Learning's
Data Collection
Reason of late E-tendering process
Methodology
Theoretical Background
Conclusion
Outline of Presentation
2
Introduction
3
• To select a contractor for a construction project.
• To test the current market, especially where existing
contracts are of a long-term nature.
• To comply with regulations pertaining free and open
competition.
• Prequalification And Bid Evaluation Process
General information about the contractors,
Criteria for the prequalification process stage, and
Criteria for bid evaluation
Objective of Present Work
Time & cost saving process.
To reduce the inventory cost of tender process.
The security process.
Detail study & analysis of E-tendering process.
To free from corruption.
To differentiate private & public tender process.
The use all type of tender process by using E-tender process
4
LITERATURE
REVIEW
5
Wei-Chih Wang (2004) Using the electronic-based bidding approach allows
the procedure to more efficiently. The bidder-based practice of the procedure
allows the bidder to realize the benefits of accurate estimates, and eventually
enhances their estimation skills.
Laryea (2011) Studied the The difficulty in achieving a programmable bidding
process was caused by changes to the tender documents, poor quality of
tender documents, personnel problems and reliance on the supply chain for
information to price the bid.
Dr. Keith Hampton (2011) From the research The concept of partnering has
been practiced by building construction industry professionals aiming to
eliminate conflicts in the building construction industry by removing traditional
barriers between the client and contracting firm.
Simon Kerridge (2000) In this research, Existing systems is not providing
a solid collaboration platform which can support the formation of a
virtual consortium.
6
Brown D (2001) The security policies have to be drawn up with the
consideration of both the tendering business.The security mechanisms have to
be carefully integrated into the system to provide desirable security service for
the complex contract processes involved in an e-tendering system.
Geoff Tindsley (2008) The data obtained and analyzed indicated that ‘over-all
efficiencies’ were perceived to be the greatest benefit of e-tendering.The
research reflects an industry that is not yet sure whether to fully embrace new
technology.
7
METHODOLOGY
8
Overlook on the basic concept, Objective
Aims of study, and research of study
Steps in procurement public process
Difference between the public & private tender process.
Data Collection
Analysis of Result
Recommendations & Outcomes
IMP GR’s For E-tender Software’s Lists
Conclusion
Comparison of E-tender & traditional tender as per case studies
THEORETICAL
BACKGROUND
9
10
• Definition
The process of preparing and submitting for acceptance a conforming
offer to carry out work for a price, thus converting the estimate to a bid For
its improved behavior under tensile loading it is usually reinforced with
steel.
• TYPES OF TENDERING
 Negotiated Tendering
 Selective Tendering
 Open Tendering
11
• PRE-QUALIFICATION
 Financial assessment
 Technical assessment
 Other assessment
 Satisfaction assessment
• PRE-BID CONFERENCE
• INVITATION TO BID
 Publication in newspapers, which have a large circulation.
 Publication in journals of special interest.
 In international competitive bidding, bringing the invitations to the notice of
embassies of foreign countries.
 Letters to firms who have come to know of the likely purchase and have
made enquiries.
12
• PRE-QUALIFICATION DOCUMENTATION
 Balance sheet of the company giving years i.e. two years balance
sheet.
 Brief resume of the company with the details of board of directors.
 Projects executed over the past five years with special mention of the
similar
 Projects, if any.
 List of equipment’s, the company owns and the proposal of equipment
planning for this particular project
 Manpower available in the organization
Name of the bankers and references
13
• PREPARATION AND APPROVAL TO DRAFT BID DOCUMENTS
 There is no ambiguity, contradiction, or duplication in the nomenclature
of items, conditions of contract, specifications and drawings
 The specifications and drawings are capable of implementation at site
 The time stipulated to complete the job is adequate.
There is also a practice in some organizations for the official approving
the bid documents to affix his signature on every page of the bid
document as a token of approval and a certificate of approval
14
• PRE BID MEETING
• BID SECURITY (EMD)
• SUBMISSION AND OPENING OF BIDS
• ACCEPTANCE OF BIDS
• POST-QUALIFICATION
STEPS IN PROCUREMENT PUBLIC PROCESS
15
Preparation of Bid Documents
Approval of Bid Documents by Competent Authority
Invitation for Bids.
Issue of Bid documents to prospective bidders
Pre Bid Meeting and Issue of Minutes, Clarifications and Common Set of Deviations
Receipt of Bids
Scrutiny
Negotiations, where warranted
Acceptance of Bids
Public Invitation for Pre-qualification (where relevant).
Issue of Instructions and
Pre-qualification criteria.
Pre-Application Meeting & Issue
of Clarifications to Applicants.
Receipt of PQ
applications & scrutiny
Approval to PQ
16
DATA COLLECTION
17
1. DIFFERENCE OF PUBLIC AND PRIVATE TENDER PROCESS.
2. COMPARISON OF E-TENDER AND TRADITIONAL TENDER
DIFFERENCE OF PUBLIC AND PRIVATE TENDER
PROCESS
18
Sr. No. Description Public Tender Process Private Tender Process
1 EMD Deposit Yes Yes
2 Envelope system Yes No
3 Evolution and comparison of bids No Yes
4 Performance Security After 24 months After 18 months
5 Bank guarantee No 5% of total contract price.
6 Form of contract agreement Yes Yes
7 Details of technical and administrative for work No Yes
8 Rejection of all tenders Yes Yes
9 Settlement of disputes No any provision Arbitrator appointed
10 Avoidance of delay No any provision Third Agency Appointed
11 Extension of complete projects Yes
No.
Work should be completed in
time.
12 Quality control Not check properly
Strictly check by company
engineers
13 Advance payment 5% of project cost
Depend upon contactor at the
interest of 12% p.a.
DIFFERENCE OF PUBLIC AND PRIVATE TENDER
PROCESS
19
Sr. No. Description Public Tender Process Private Tender Process
14 Insurance Not provided Provided
15 Currencies All payment in Rupees All payment in Rupees
16 Penalty for delay
Depends upon the Engineer in charge. Depends upon the Engineer in charge.
But it penalty up to 500 to 2000 /- Rs. Per
day.
But it penalty up to 500 to 5000 /- Rs.
Per day.
17 Environmental protection No any provision
Strictly follows the environmental
rules
18
Wastage of material
Cement Nil Nil
Steel 10-12% 5%
19 Safety provision No Yes
20 Canteen Not available Available
21 Temporary electric supply Available Available
22 Housing for labours Not available Available
23 Explosive material Not permit to site Strictly prohibited
24
Bonus to before complete the
work
No provision 2.5% of cost of project
DIFFERENCE OF PUBLIC AND PRIVATE TENDER
PROCESS
20
Sr. No. Description Public Tender Process Private Tender Process
25 Complete the process 2-3 months and above 1months
26 Description of material Yes given Yes given
27 Fire prevention No provision
Strictly fire prevention material
available
28 Transport for labours Not provided
Its available for all engineers and
labours
29
Manpower for complete
process
More required Less required
30 Buaracacy Possible in process Not possible
31 Transference to process Less More
32 Quality of work Less quality work done Accurate quality work done
33 Political interference It’s possible It’s not possible
COMPARISON OF E-TENDER AND TRADITIONAL
TENDER
21
E- TENDER TRADITIONAL TENDER
EMD deposit online process EMD deposit at manually process
Comparative statement automatically generated Comparative statement done by manually.
At any time within specified period upload
document.
At not possible to upload document.
Document saves in soft copy and in safe in
position.
Document in hard copy and not possible to safe at
time.
Free from corruption and no chance to alter the
quoted the rates.
Not possible to free from corruption and should be
possible to changes quoted rates.
Paper work is minimum. Paper work is maximum.
No deduction of tax Deduct the tax
No need of D.D. and deposited to manually. D.D. and deposited to manually.
Its transferring process Its non-transfer process
COMPARISON OF E-TENDER AND TRADITIONAL
TENDER
22
E- TENDER TRADITIONAL TENDER
Time saving process Time consuming process
Its speedy process. Its slow process.
No any interference of political persons. In this chance to interfere of political persons.
Non awarded persons the EMD will be transfer to
direct on his bank account.
In this process the EMD amount given after 2
months after opening of tender.
Tender not necessary to submit by hand Tender submit by hand and before time.
Privacy of rates and other important document is
possible.
In this no guaranty of privacy and to possible to lost
the documents.
Environmental friendly Paper Based
Anytime-Anywhere Restricted Mobility
Bidding possible on Holidays and after office
hours
No work in Holidays and after office hours
Automated and Accurate Prone to human errors
Foolproof Security Physical security
Lifelong storage on CD Wastage of space to store
One click access to bids Difficult to retrieve
REASONS OF LATE E-TENDER PROCESS
• In meeting all members don’t agree for contractor name.
• Funds not available in time.
• Election time.
• All contractors have not knowledge about the feeling the
online process of tender.
• In outside the one tender filling rate is, 3000/- per tender.
• If the contractor death.
• Website possible to crash.
23
GRs FOR E-tenders
24
 Gr For 50 lakhs –
 Gr For 10 lakhsResult-
 Gr For 3 lakhs no.1
 Gr. For 3 lakhs no.2
SOFTWARES CURRENTLY USED FOR
E-TENDERING PROCESS
25
 Coupa Procurement by Coupa Software.
 E Bid e Xchange by e Bid Systems.
 Panacea by Panacea Software.
 Promena e-Sourcing by Promena e-Sourcing Solutions.
 Sourceit by sourceit.
 Bid Sync e Procurement by BidSync.
 Web Req by GT Management.
 Buyer Quest e Procurement by Buyer Quest.
 Procurement Software and e Invoicing by Xeeva.
 Basware Procurement by Basware.
 Ariba Spend Management Suite by Ariba.
26
RECOMMENDATIONS
 E-tender should apply at cost one lakh.
 The appoint the third party for the observation.
 E-tender process will do the with the help of private companies for
security and efficient process.
 The use of the latest software's and technology for E-tender process
will be complete earlier and fast.
 For the less corruption in tender process the compulsory to all
departments to apply the E-tender process for the all type of tender
27
OUTCOMES FROM STUDY
 In the traditional private tender process the process completed at
two months. The security this process is better than the government
process.
 In case study seen that the traditional process is long process.
 In the study found at the private E-tender process the completed the
fast and security.
 All the documents are scan are the save at one time only, and no
chance to lost.
 Time and cost are the most saving the both parties.
 The detail instruction of the tender process are available at online so
the waste of the paper are saving.
28
LEARNINGS
 E-tender is efficiency than the traditional process.
 In this process bidder can submit their project at any time and any place.
 In the secure the important documents in soft copy then no chance for missing
documents or misuse.
 The saves time & cost of both the parties.
 In this process used the latest technology that cause the fast speed, less mistakes,
efficiency, & economically.
 It’s the totally eco-friendly process.
 The bidder can secure his identity, bid quote, digital signature etc.
 The bidder has login id & password. He can change password for safety.
 This process is totally free from the corruption & no interference of any person in office
staff.
 In the information saves in CD in lifelong with safely.
 No chance of political pressure to bidder and also office staff.
•Document save in soft copy and in safe in position, free from corruption and no
chance to alter the quoted the rates,
•Paper work reduced, bidding possible on Holidays and after office hours, automated
and accurate, Privacy of rates and other important document is possible
•E tender having 3 lakh amount which can be reduced up to 1 lakh
tender and bidding process used the technology they have the great change in
the process
Private tender process is more accurate, time and cost saving over the
traditional tender process
Conclusion
29
30
1) An Analysis of the Selection of Project Contractor in the Construction
Management Process Xiao Hong Huang Shandong Lumei Construction Cost
Consultancy Co. Ltd., Jinan 250031, China
2) Andrews, R. and Boyne, G.A. (2009) Size, Structure and Administrative
Overheads: An empirical analysis of English Local Authorities. Urban Studies,
46(4), 739-759.
3) Baker, E. and Champion, R. (2008) Tendering and procurement in
construction. Coventry: Royal Institution of Chartered Surveyors.
4) Barton, R.F. (1969) an Experimental Study of the Impact of Competitive
Pressures on Overhead Allocation Bids. Journal of Accounting Research, 7(1),
p116-122.
5)Chao, L. (2010) Estimating project overheads rate in bidding: DSS approach
using neural networks. Construction Management and Economics, 28(1), 287-
299.
References
31
6) Dr. Keith Hampson, “Strategic Alliances in Building Construction: A Tender
Evaluation Tool for the Public Sector” Journal of Construction Procurement, 3(1).
pp. 28 41, August 2011.
7) Estimating future bidding performance of competitor bidders in capped tenders
Pablo ballesteros-perez, m. Carmen gonzález-cruz b, Marta fernández-dieg.
Gandhi, K. (1996) Controlling Overhead Costs. Journal of Management in
Engineering, 12(4)18-22.
9)Griffith, A.; Knight, A. and King, A. (2003) Best practice tendering for Design and
Build projects. London: Thomas Telford.
10) Gunnar Alexanderson, Staffan Hulten, “Predatory bidding in competitive
tenders: A Swedish case study” Springer Science, Business Media, LLC, 2006
11) Hackett, M., Robinson, I. and Statam, G. (2007) Procurement, tendering, and
contract administration, Oxford: Blackwell.
12) Hatush, Zedan and Skitmore, Martin R. “Criteria for contractor selection”
Construction Management and Economics, 15(1):pp. 19-38, 1997.
13) IrtishadAhmad,IssamMinkarah,“Questionnaire Survey On Bidding In
Construction’’ Journal of Management in Engineering, Vol. 4, No. 3, (ASCE) July,
1988.
List Of Publications
International Journal of Engineering Research and
Applications (IJERA ) 2014
• “Tender and Bidding in Construction Project”, ISSN 2248-
9622,Vol.4,Issue 12,December 2014.
International Journal of Innovative Science Engineering
and Technology (IJISET) 2016
• “Tender and Bidding Process in Construction Projects”, ISSN
2348-7968, Vol.3, Issue 3, March 2016.
CIVIL PGCON 2015
• “Tender and Bidding in Construction Projects, CIVIL PGCON
2016, Pune.
32
33

More Related Content

What's hot

Tendering in Construction
Tendering in ConstructionTendering in Construction
Tendering in Construction
shillier38
 
Quantity Surveying
Quantity SurveyingQuantity Surveying
Quantity Surveying
geddolan
 
Tenders contract -arti
Tenders contract -artiTenders contract -arti
Tenders contract -arti
jagadish108
 
3.0 Common Types of Construction Contracts & Standard Conditions of Contract ...
3.0 Common Types of Construction Contracts & Standard Conditions of Contract ...3.0 Common Types of Construction Contracts & Standard Conditions of Contract ...
3.0 Common Types of Construction Contracts & Standard Conditions of Contract ...
Praveen Premkumar
 
M3 Lecture 11 provisional sum prime cost sum
M3 Lecture 11 provisional sum  prime cost sumM3 Lecture 11 provisional sum  prime cost sum
M3 Lecture 11 provisional sum prime cost sum
Est
 

What's hot (20)

Types of tenders & stages for successful tendering
Types of tenders & stages for successful tenderingTypes of tenders & stages for successful tendering
Types of tenders & stages for successful tendering
 
Procurement Methods
Procurement MethodsProcurement Methods
Procurement Methods
 
Tendering
TenderingTendering
Tendering
 
contract procedure
contract procedurecontract procedure
contract procedure
 
Lecture 4 - selection of contract forms
Lecture 4 - selection of contract formsLecture 4 - selection of contract forms
Lecture 4 - selection of contract forms
 
Tendering in construction introduction
Tendering in construction introductionTendering in construction introduction
Tendering in construction introduction
 
Tendering in Construction
Tendering in ConstructionTendering in Construction
Tendering in Construction
 
Contracts
ContractsContracts
Contracts
 
TENDER DOCUMENT
TENDER DOCUMENTTENDER DOCUMENT
TENDER DOCUMENT
 
Classification of contracts
Classification of contractsClassification of contracts
Classification of contracts
 
Lecture 2 tender process n documentation
Lecture 2 tender process n documentationLecture 2 tender process n documentation
Lecture 2 tender process n documentation
 
Construction contract
Construction contractConstruction contract
Construction contract
 
Types of Contract in Construction Management
Types of Contract in Construction ManagementTypes of Contract in Construction Management
Types of Contract in Construction Management
 
Quantity Surveying
Quantity SurveyingQuantity Surveying
Quantity Surveying
 
Module 4 lecture 1
Module  4 lecture 1Module  4 lecture 1
Module 4 lecture 1
 
Tenders contract -arti
Tenders contract -artiTenders contract -arti
Tenders contract -arti
 
Construction Contracts: Basics of Contracts and Contract Administration
Construction Contracts:  Basics of Contracts and Contract AdministrationConstruction Contracts:  Basics of Contracts and Contract Administration
Construction Contracts: Basics of Contracts and Contract Administration
 
3.0 Common Types of Construction Contracts & Standard Conditions of Contract ...
3.0 Common Types of Construction Contracts & Standard Conditions of Contract ...3.0 Common Types of Construction Contracts & Standard Conditions of Contract ...
3.0 Common Types of Construction Contracts & Standard Conditions of Contract ...
 
Tender evaluation procedure
Tender evaluation procedureTender evaluation procedure
Tender evaluation procedure
 
M3 Lecture 11 provisional sum prime cost sum
M3 Lecture 11 provisional sum  prime cost sumM3 Lecture 11 provisional sum  prime cost sum
M3 Lecture 11 provisional sum prime cost sum
 

Similar to Tender & bidding in construction projects

Procurement Methods and their Application.
Procurement Methods and their Application.Procurement Methods and their Application.
Procurement Methods and their Application.
Lilian Nwachukwu
 
Urban Local Bodies Case Study
Urban Local Bodies Case StudyUrban Local Bodies Case Study
Urban Local Bodies Case Study
Sandra Ahn
 

Similar to Tender & bidding in construction projects (20)

Tendering documentation
Tendering documentationTendering documentation
Tendering documentation
 
Partners in Technology (PiT) - GITC Framework Review Outcomes - 23 October 2015
Partners in Technology (PiT) - GITC Framework Review Outcomes - 23 October 2015Partners in Technology (PiT) - GITC Framework Review Outcomes - 23 October 2015
Partners in Technology (PiT) - GITC Framework Review Outcomes - 23 October 2015
 
IRJET- Android Application for Service by using Bidding and Ratings in nearby...
IRJET- Android Application for Service by using Bidding and Ratings in nearby...IRJET- Android Application for Service by using Bidding and Ratings in nearby...
IRJET- Android Application for Service by using Bidding and Ratings in nearby...
 
Presentation, SIGMA workshop on tendering of PPP projects and contract signat...
Presentation, SIGMA workshop on tendering of PPP projects and contract signat...Presentation, SIGMA workshop on tendering of PPP projects and contract signat...
Presentation, SIGMA workshop on tendering of PPP projects and contract signat...
 
eTendering in 2018: Tenders & Entrepreneurship
eTendering in 2018: Tenders & EntrepreneurshipeTendering in 2018: Tenders & Entrepreneurship
eTendering in 2018: Tenders & Entrepreneurship
 
PROSES ESTIMASI.ppt
PROSES ESTIMASI.pptPROSES ESTIMASI.ppt
PROSES ESTIMASI.ppt
 
Study of Influencing Factors of Tender Evaluation: An Evidential Reasoning Ap...
Study of Influencing Factors of Tender Evaluation: An Evidential Reasoning Ap...Study of Influencing Factors of Tender Evaluation: An Evidential Reasoning Ap...
Study of Influencing Factors of Tender Evaluation: An Evidential Reasoning Ap...
 
Tender and Bidding in Construction Projects
Tender and Bidding in Construction ProjectsTender and Bidding in Construction Projects
Tender and Bidding in Construction Projects
 
e-Procurement in Indian Government
e-Procurement in Indian Governmente-Procurement in Indian Government
e-Procurement in Indian Government
 
Smart Process Design: Continuous Improvement to Leverage the Right Technology...
Smart Process Design: Continuous Improvement to Leverage the Right Technology...Smart Process Design: Continuous Improvement to Leverage the Right Technology...
Smart Process Design: Continuous Improvement to Leverage the Right Technology...
 
Supplier Assessment Sample Report: What You Can Expect
Supplier Assessment Sample Report: What You Can ExpectSupplier Assessment Sample Report: What You Can Expect
Supplier Assessment Sample Report: What You Can Expect
 
Diet y mci presentation
Diet y mci presentationDiet y mci presentation
Diet y mci presentation
 
Estimating Seminar (QS)
Estimating Seminar (QS)Estimating Seminar (QS)
Estimating Seminar (QS)
 
Tender Preparation & Bid Management
Tender Preparation & Bid ManagementTender Preparation & Bid Management
Tender Preparation & Bid Management
 
Procurement Methods and their Application.
Procurement Methods and their Application.Procurement Methods and their Application.
Procurement Methods and their Application.
 
A Review of Cost overruns in Construction Project Management
A Review of Cost overruns in Construction Project ManagementA Review of Cost overruns in Construction Project Management
A Review of Cost overruns in Construction Project Management
 
Credicon Introduction
Credicon  IntroductionCredicon  Introduction
Credicon Introduction
 
Urban Local Bodies Case Study
Urban Local Bodies Case StudyUrban Local Bodies Case Study
Urban Local Bodies Case Study
 
Pittsburgh case study midfield energy system
Pittsburgh case study midfield energy systemPittsburgh case study midfield energy system
Pittsburgh case study midfield energy system
 
Making it happen: Procurement and contracting, Anna Spenceley
Making it happen: Procurement and contracting, Anna SpenceleyMaking it happen: Procurement and contracting, Anna Spenceley
Making it happen: Procurement and contracting, Anna Spenceley
 

Recently uploaded

DeepFakes presentation : brief idea of DeepFakes
DeepFakes presentation : brief idea of DeepFakesDeepFakes presentation : brief idea of DeepFakes
DeepFakes presentation : brief idea of DeepFakes
MayuraD1
 
"Lesotho Leaps Forward: A Chronicle of Transformative Developments"
"Lesotho Leaps Forward: A Chronicle of Transformative Developments""Lesotho Leaps Forward: A Chronicle of Transformative Developments"
"Lesotho Leaps Forward: A Chronicle of Transformative Developments"
mphochane1998
 
notes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.pptnotes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.ppt
MsecMca
 
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills KuwaitKuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
jaanualu31
 
Integrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - NeometrixIntegrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - Neometrix
Neometrix_Engineering_Pvt_Ltd
 

Recently uploaded (20)

DeepFakes presentation : brief idea of DeepFakes
DeepFakes presentation : brief idea of DeepFakesDeepFakes presentation : brief idea of DeepFakes
DeepFakes presentation : brief idea of DeepFakes
 
"Lesotho Leaps Forward: A Chronicle of Transformative Developments"
"Lesotho Leaps Forward: A Chronicle of Transformative Developments""Lesotho Leaps Forward: A Chronicle of Transformative Developments"
"Lesotho Leaps Forward: A Chronicle of Transformative Developments"
 
Thermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VThermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - V
 
Hostel management system project report..pdf
Hostel management system project report..pdfHostel management system project report..pdf
Hostel management system project report..pdf
 
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptxHOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
 
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced LoadsFEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
 
Employee leave management system project.
Employee leave management system project.Employee leave management system project.
Employee leave management system project.
 
Minimum and Maximum Modes of microprocessor 8086
Minimum and Maximum Modes of microprocessor 8086Minimum and Maximum Modes of microprocessor 8086
Minimum and Maximum Modes of microprocessor 8086
 
notes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.pptnotes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.ppt
 
School management system project Report.pdf
School management system project Report.pdfSchool management system project Report.pdf
School management system project Report.pdf
 
Online electricity billing project report..pdf
Online electricity billing project report..pdfOnline electricity billing project report..pdf
Online electricity billing project report..pdf
 
Introduction to Serverless with AWS Lambda
Introduction to Serverless with AWS LambdaIntroduction to Serverless with AWS Lambda
Introduction to Serverless with AWS Lambda
 
Online food ordering system project report.pdf
Online food ordering system project report.pdfOnline food ordering system project report.pdf
Online food ordering system project report.pdf
 
Air Compressor reciprocating single stage
Air Compressor reciprocating single stageAir Compressor reciprocating single stage
Air Compressor reciprocating single stage
 
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills KuwaitKuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
 
Unleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapUnleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leap
 
Generative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPTGenerative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPT
 
Bridge Jacking Design Sample Calculation.pptx
Bridge Jacking Design Sample Calculation.pptxBridge Jacking Design Sample Calculation.pptx
Bridge Jacking Design Sample Calculation.pptx
 
Integrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - NeometrixIntegrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - Neometrix
 
Design For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the startDesign For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the start
 

Tender & bidding in construction projects

  • 1. “Comparative Study of E-tendering & Traditional tendering in Construction Projects” By Tejas C. Patil. Under Guidance of Prof. Ashish P. Waghmare. Dr. D. Y. Patil School of Engineering and Technology, Lohgaon Pune 18th April 2016
  • 2. Introduction Literature Survey Objectives Recommendation, Outcomes from study & Learning's Data Collection Reason of late E-tendering process Methodology Theoretical Background Conclusion Outline of Presentation 2
  • 3. Introduction 3 • To select a contractor for a construction project. • To test the current market, especially where existing contracts are of a long-term nature. • To comply with regulations pertaining free and open competition. • Prequalification And Bid Evaluation Process General information about the contractors, Criteria for the prequalification process stage, and Criteria for bid evaluation
  • 4. Objective of Present Work Time & cost saving process. To reduce the inventory cost of tender process. The security process. Detail study & analysis of E-tendering process. To free from corruption. To differentiate private & public tender process. The use all type of tender process by using E-tender process 4
  • 6. Wei-Chih Wang (2004) Using the electronic-based bidding approach allows the procedure to more efficiently. The bidder-based practice of the procedure allows the bidder to realize the benefits of accurate estimates, and eventually enhances their estimation skills. Laryea (2011) Studied the The difficulty in achieving a programmable bidding process was caused by changes to the tender documents, poor quality of tender documents, personnel problems and reliance on the supply chain for information to price the bid. Dr. Keith Hampton (2011) From the research The concept of partnering has been practiced by building construction industry professionals aiming to eliminate conflicts in the building construction industry by removing traditional barriers between the client and contracting firm. Simon Kerridge (2000) In this research, Existing systems is not providing a solid collaboration platform which can support the formation of a virtual consortium. 6
  • 7. Brown D (2001) The security policies have to be drawn up with the consideration of both the tendering business.The security mechanisms have to be carefully integrated into the system to provide desirable security service for the complex contract processes involved in an e-tendering system. Geoff Tindsley (2008) The data obtained and analyzed indicated that ‘over-all efficiencies’ were perceived to be the greatest benefit of e-tendering.The research reflects an industry that is not yet sure whether to fully embrace new technology. 7
  • 8. METHODOLOGY 8 Overlook on the basic concept, Objective Aims of study, and research of study Steps in procurement public process Difference between the public & private tender process. Data Collection Analysis of Result Recommendations & Outcomes IMP GR’s For E-tender Software’s Lists Conclusion Comparison of E-tender & traditional tender as per case studies
  • 10. 10 • Definition The process of preparing and submitting for acceptance a conforming offer to carry out work for a price, thus converting the estimate to a bid For its improved behavior under tensile loading it is usually reinforced with steel. • TYPES OF TENDERING  Negotiated Tendering  Selective Tendering  Open Tendering
  • 11. 11 • PRE-QUALIFICATION  Financial assessment  Technical assessment  Other assessment  Satisfaction assessment • PRE-BID CONFERENCE • INVITATION TO BID  Publication in newspapers, which have a large circulation.  Publication in journals of special interest.  In international competitive bidding, bringing the invitations to the notice of embassies of foreign countries.  Letters to firms who have come to know of the likely purchase and have made enquiries.
  • 12. 12 • PRE-QUALIFICATION DOCUMENTATION  Balance sheet of the company giving years i.e. two years balance sheet.  Brief resume of the company with the details of board of directors.  Projects executed over the past five years with special mention of the similar  Projects, if any.  List of equipment’s, the company owns and the proposal of equipment planning for this particular project  Manpower available in the organization Name of the bankers and references
  • 13. 13 • PREPARATION AND APPROVAL TO DRAFT BID DOCUMENTS  There is no ambiguity, contradiction, or duplication in the nomenclature of items, conditions of contract, specifications and drawings  The specifications and drawings are capable of implementation at site  The time stipulated to complete the job is adequate. There is also a practice in some organizations for the official approving the bid documents to affix his signature on every page of the bid document as a token of approval and a certificate of approval
  • 14. 14 • PRE BID MEETING • BID SECURITY (EMD) • SUBMISSION AND OPENING OF BIDS • ACCEPTANCE OF BIDS • POST-QUALIFICATION
  • 15. STEPS IN PROCUREMENT PUBLIC PROCESS 15 Preparation of Bid Documents Approval of Bid Documents by Competent Authority Invitation for Bids. Issue of Bid documents to prospective bidders Pre Bid Meeting and Issue of Minutes, Clarifications and Common Set of Deviations Receipt of Bids Scrutiny Negotiations, where warranted Acceptance of Bids Public Invitation for Pre-qualification (where relevant). Issue of Instructions and Pre-qualification criteria. Pre-Application Meeting & Issue of Clarifications to Applicants. Receipt of PQ applications & scrutiny Approval to PQ
  • 17. 17 1. DIFFERENCE OF PUBLIC AND PRIVATE TENDER PROCESS. 2. COMPARISON OF E-TENDER AND TRADITIONAL TENDER
  • 18. DIFFERENCE OF PUBLIC AND PRIVATE TENDER PROCESS 18 Sr. No. Description Public Tender Process Private Tender Process 1 EMD Deposit Yes Yes 2 Envelope system Yes No 3 Evolution and comparison of bids No Yes 4 Performance Security After 24 months After 18 months 5 Bank guarantee No 5% of total contract price. 6 Form of contract agreement Yes Yes 7 Details of technical and administrative for work No Yes 8 Rejection of all tenders Yes Yes 9 Settlement of disputes No any provision Arbitrator appointed 10 Avoidance of delay No any provision Third Agency Appointed 11 Extension of complete projects Yes No. Work should be completed in time. 12 Quality control Not check properly Strictly check by company engineers 13 Advance payment 5% of project cost Depend upon contactor at the interest of 12% p.a.
  • 19. DIFFERENCE OF PUBLIC AND PRIVATE TENDER PROCESS 19 Sr. No. Description Public Tender Process Private Tender Process 14 Insurance Not provided Provided 15 Currencies All payment in Rupees All payment in Rupees 16 Penalty for delay Depends upon the Engineer in charge. Depends upon the Engineer in charge. But it penalty up to 500 to 2000 /- Rs. Per day. But it penalty up to 500 to 5000 /- Rs. Per day. 17 Environmental protection No any provision Strictly follows the environmental rules 18 Wastage of material Cement Nil Nil Steel 10-12% 5% 19 Safety provision No Yes 20 Canteen Not available Available 21 Temporary electric supply Available Available 22 Housing for labours Not available Available 23 Explosive material Not permit to site Strictly prohibited 24 Bonus to before complete the work No provision 2.5% of cost of project
  • 20. DIFFERENCE OF PUBLIC AND PRIVATE TENDER PROCESS 20 Sr. No. Description Public Tender Process Private Tender Process 25 Complete the process 2-3 months and above 1months 26 Description of material Yes given Yes given 27 Fire prevention No provision Strictly fire prevention material available 28 Transport for labours Not provided Its available for all engineers and labours 29 Manpower for complete process More required Less required 30 Buaracacy Possible in process Not possible 31 Transference to process Less More 32 Quality of work Less quality work done Accurate quality work done 33 Political interference It’s possible It’s not possible
  • 21. COMPARISON OF E-TENDER AND TRADITIONAL TENDER 21 E- TENDER TRADITIONAL TENDER EMD deposit online process EMD deposit at manually process Comparative statement automatically generated Comparative statement done by manually. At any time within specified period upload document. At not possible to upload document. Document saves in soft copy and in safe in position. Document in hard copy and not possible to safe at time. Free from corruption and no chance to alter the quoted the rates. Not possible to free from corruption and should be possible to changes quoted rates. Paper work is minimum. Paper work is maximum. No deduction of tax Deduct the tax No need of D.D. and deposited to manually. D.D. and deposited to manually. Its transferring process Its non-transfer process
  • 22. COMPARISON OF E-TENDER AND TRADITIONAL TENDER 22 E- TENDER TRADITIONAL TENDER Time saving process Time consuming process Its speedy process. Its slow process. No any interference of political persons. In this chance to interfere of political persons. Non awarded persons the EMD will be transfer to direct on his bank account. In this process the EMD amount given after 2 months after opening of tender. Tender not necessary to submit by hand Tender submit by hand and before time. Privacy of rates and other important document is possible. In this no guaranty of privacy and to possible to lost the documents. Environmental friendly Paper Based Anytime-Anywhere Restricted Mobility Bidding possible on Holidays and after office hours No work in Holidays and after office hours Automated and Accurate Prone to human errors Foolproof Security Physical security Lifelong storage on CD Wastage of space to store One click access to bids Difficult to retrieve
  • 23. REASONS OF LATE E-TENDER PROCESS • In meeting all members don’t agree for contractor name. • Funds not available in time. • Election time. • All contractors have not knowledge about the feeling the online process of tender. • In outside the one tender filling rate is, 3000/- per tender. • If the contractor death. • Website possible to crash. 23
  • 24. GRs FOR E-tenders 24  Gr For 50 lakhs –  Gr For 10 lakhsResult-  Gr For 3 lakhs no.1  Gr. For 3 lakhs no.2
  • 25. SOFTWARES CURRENTLY USED FOR E-TENDERING PROCESS 25  Coupa Procurement by Coupa Software.  E Bid e Xchange by e Bid Systems.  Panacea by Panacea Software.  Promena e-Sourcing by Promena e-Sourcing Solutions.  Sourceit by sourceit.  Bid Sync e Procurement by BidSync.  Web Req by GT Management.  Buyer Quest e Procurement by Buyer Quest.  Procurement Software and e Invoicing by Xeeva.  Basware Procurement by Basware.  Ariba Spend Management Suite by Ariba.
  • 26. 26 RECOMMENDATIONS  E-tender should apply at cost one lakh.  The appoint the third party for the observation.  E-tender process will do the with the help of private companies for security and efficient process.  The use of the latest software's and technology for E-tender process will be complete earlier and fast.  For the less corruption in tender process the compulsory to all departments to apply the E-tender process for the all type of tender
  • 27. 27 OUTCOMES FROM STUDY  In the traditional private tender process the process completed at two months. The security this process is better than the government process.  In case study seen that the traditional process is long process.  In the study found at the private E-tender process the completed the fast and security.  All the documents are scan are the save at one time only, and no chance to lost.  Time and cost are the most saving the both parties.  The detail instruction of the tender process are available at online so the waste of the paper are saving.
  • 28. 28 LEARNINGS  E-tender is efficiency than the traditional process.  In this process bidder can submit their project at any time and any place.  In the secure the important documents in soft copy then no chance for missing documents or misuse.  The saves time & cost of both the parties.  In this process used the latest technology that cause the fast speed, less mistakes, efficiency, & economically.  It’s the totally eco-friendly process.  The bidder can secure his identity, bid quote, digital signature etc.  The bidder has login id & password. He can change password for safety.  This process is totally free from the corruption & no interference of any person in office staff.  In the information saves in CD in lifelong with safely.  No chance of political pressure to bidder and also office staff.
  • 29. •Document save in soft copy and in safe in position, free from corruption and no chance to alter the quoted the rates, •Paper work reduced, bidding possible on Holidays and after office hours, automated and accurate, Privacy of rates and other important document is possible •E tender having 3 lakh amount which can be reduced up to 1 lakh tender and bidding process used the technology they have the great change in the process Private tender process is more accurate, time and cost saving over the traditional tender process Conclusion 29
  • 30. 30 1) An Analysis of the Selection of Project Contractor in the Construction Management Process Xiao Hong Huang Shandong Lumei Construction Cost Consultancy Co. Ltd., Jinan 250031, China 2) Andrews, R. and Boyne, G.A. (2009) Size, Structure and Administrative Overheads: An empirical analysis of English Local Authorities. Urban Studies, 46(4), 739-759. 3) Baker, E. and Champion, R. (2008) Tendering and procurement in construction. Coventry: Royal Institution of Chartered Surveyors. 4) Barton, R.F. (1969) an Experimental Study of the Impact of Competitive Pressures on Overhead Allocation Bids. Journal of Accounting Research, 7(1), p116-122. 5)Chao, L. (2010) Estimating project overheads rate in bidding: DSS approach using neural networks. Construction Management and Economics, 28(1), 287- 299. References
  • 31. 31 6) Dr. Keith Hampson, “Strategic Alliances in Building Construction: A Tender Evaluation Tool for the Public Sector” Journal of Construction Procurement, 3(1). pp. 28 41, August 2011. 7) Estimating future bidding performance of competitor bidders in capped tenders Pablo ballesteros-perez, m. Carmen gonzález-cruz b, Marta fernández-dieg. Gandhi, K. (1996) Controlling Overhead Costs. Journal of Management in Engineering, 12(4)18-22. 9)Griffith, A.; Knight, A. and King, A. (2003) Best practice tendering for Design and Build projects. London: Thomas Telford. 10) Gunnar Alexanderson, Staffan Hulten, “Predatory bidding in competitive tenders: A Swedish case study” Springer Science, Business Media, LLC, 2006 11) Hackett, M., Robinson, I. and Statam, G. (2007) Procurement, tendering, and contract administration, Oxford: Blackwell. 12) Hatush, Zedan and Skitmore, Martin R. “Criteria for contractor selection” Construction Management and Economics, 15(1):pp. 19-38, 1997. 13) IrtishadAhmad,IssamMinkarah,“Questionnaire Survey On Bidding In Construction’’ Journal of Management in Engineering, Vol. 4, No. 3, (ASCE) July, 1988.
  • 32. List Of Publications International Journal of Engineering Research and Applications (IJERA ) 2014 • “Tender and Bidding in Construction Project”, ISSN 2248- 9622,Vol.4,Issue 12,December 2014. International Journal of Innovative Science Engineering and Technology (IJISET) 2016 • “Tender and Bidding Process in Construction Projects”, ISSN 2348-7968, Vol.3, Issue 3, March 2016. CIVIL PGCON 2015 • “Tender and Bidding in Construction Projects, CIVIL PGCON 2016, Pune. 32