SlideShare uma empresa Scribd logo
1 de 6
Baixar para ler offline
METHOD STATEMENT HVAC AIR HANDLING UNIT
P a g e 1 | 6
METHOD STATEMENT
FOR
AHU INSTALLATION
METHOD STATEMENT HVAC AIR HANDLING UNIT
P a g e 2 | 6
INTRODUCTION
This Method statement describes in details the onsite installation of AHU. AHU shall be
installed as per approved material submittal.
SCOPE OF WORKS
The Method Statement shall cover all works related to the installation of AHU as per
approved shop drawing and approved material submittal for the project.
REFERENCE DOCUMENTS
3.1. Specification – Section 15855
3.2. Recommendation of approved material submittal
.
ORGANIZATION & RESPONSIBILITIES
Project Manager:
It is the Project Manager duty to ensure that all necessary safety and protective equipment are
provided along with properly trained and qualified personnel. Moreover, to ensure that all
survey works are carried out in accordance with this method statement.
Quality Engineer’s:
It is the Quality Engineer’s responsibility to ensure that all surveying equipment is being
calibrated. Ensure that all inspections and tests are carried out as per Project requirements and
that all are recorded. Maintaining all quality records relevant to verification of records.
Site Engineer / Site Supervisor’s:
It is the Site Engineer / Site Supervisor’s duty to organize the work force in a safe manner and to
ensure that safety and protective equipment are being properly utilized. He must also ensure
that the method statement procedure is followed and notify the HAC Q.C / EHAF International
for inspection.
Surveyor’s:
It is the Surveyor’s duty to obtain all data and information required for surveys. Determine
methods to establish survey control. Use appropriate equipment to complete assigned task.
Keep accurate notes and records to describe and certify work performed. Abide by all Site Safety
and Quality Requirements.
Safety Engineer / Officer’s:
METHOD STATEMENT HVAC AIR HANDLING UNIT
P a g e 3 | 6
 The Safety Engineer is responsible for devising and implementing programmers and plans
to safeguard, health and safety of all employees, and to prevent loss or damage to the
existing assets and projects, He is responsible for the implementing of the safety
programs. He is also responsible to:
 Provide support to site safety officers advising them on safe working methods and
assisting with training of personnel.
 Carryout regular site safety audits and reports and correct unsafe work practices and
potential hazards.
 Investigate and report all accidents near misses and recommend prevention measures.
Ensure maintenances of good hygienic standards and availability of safety equipment and
first aid treatment.
 Present monthly safety reports and required documents.
Safety Officers are responsible for:
 The day to day activities of maintaining safety on project site, they must: Understand and
comply with requirements of the safety manual.
 Cooperate with the safety engineer to create and maintain safe working conditions.
 Assist the site engineers and foremen to organize the work area so that the men can
perform their duties with maximum efficiency and minimize risk to themselves or to
equipment.
 Inspect equipment and tools before use to ensure correct storage and properly
utilization. Maintain record of all injuries and damages on site, submit reports as
required.
RESOURCES
Equipment & Machinery:
The following equipment will be used to carry out the installation of FANS.
 Mechanical hand tool
 Mobile Crane
 Fork Lift
METHODOLOGY
Storage
 AHU shall be stored in such a manner as to preserve its quality condition.
 AHU are to be as per manufacturer recommendations but at the same time it should be
accessible.
METHOD STATEMENT HVAC AIR HANDLING UNIT
P a g e 4 | 6
 The quantity to be delivered at site for installation shall be consistent with the necessary
required quantity of the work to perform.
Setting Out
 Check the readiness of reference and coordinates.
 Check the other activates works related with the installations.
 Arrange all necessary work permit, check and verify the actual site condition.
Unloading and Shifting:
 AHU shall be transported by a delivery truck and mechanical crane / fork lift to the specific
work place.
 Safety Officer will be present during loading and unloading of.
 Two lifting point will be used during the loading and unloading of AHU to ensure safety
that no incident will occurs. Traffic Aide will be present during loading and unloading of
Unit for maintaining the traffic in the project site if needed.
 All lifting equipment will be inspected daily before operating. Any parts detected damages
must be replaced immediately before operating.
Installation for AHU at Concrete roof
 Mech. Installation: -
 Set and fix AHU steel frame at Unit location at roof.
 Connect Unit with duct through duct reducer.
 Installation manual attached.
 Electrical Installation: -
 Connect power cable from MCC Panel to disconnecting switch.
 Connect Power Cable from disconnecting switch to Unit motor.
QUALITY ASSURANCE
Material : Approved submittal.
Location : As per approved shop drawings
HEALTH, SAFETY AND ENVIRONMENT
METHOD STATEMENT HVAC AIR HANDLING UNIT
P a g e 5 | 6
PPE Requirements
As a minimum the following PPE should be used by staff / Labors
 Hard hat.
 Safety shoes.
 Safety eye glasses.
 Hand gloves.
 High visibility vest.
Any additional PPE as required by local rules or mandatory requirement shall be used.
Safety Accessories
 Traffic Cones.
 Warning /barricade/barrier tape.
 Safety signs.
 Cooled water container for drinking.
 First Aid box.
 Workers rest area
 Portable toilet
 Fire extinguishers
 Sign boards of Emergency contact details/persons
Information to Personnel.
 Safety Induction will be done in accordance with HSE Policy prior to start work in site.
 Safety toolbox meetings to be carried out prior to work.
 Before job start checklist of protective & safety equipment to be use are in order.
 Personal protective & safety equipment as per requirement to be performed by
personnel to do the task.
 Toolbox talk to be convened & attended by all personnel assigned to do the task.
Work crew will be given instruction on site surveying procedure & all risk associated
with the works and registered attendance.
 Safety personnel & designated responsible person will ensure that all above is carried
out & any other statutory requirements are complied with before any work takes.
 Hazard analysis to be done.
METHOD STATEMENT HVAC AIR HANDLING UNIT
P a g e 6 | 6
 Personnel who have been briefed in the correct equipment set up.
 Personnel will wear gloves, footwear, head & eye protection during work.
 Use the correct tools to do the task.
 Removal of any obstructive / protruding materials.
APPENDICES
1. Risk assessment.

Mais conteúdo relacionado

Semelhante a AHU.pdf (20)

Cv reguieg h last update
Cv reguieg h last updateCv reguieg h last update
Cv reguieg h last update
 
ROGEL resume up date as of AUG.
ROGEL resume up date as of AUG.ROGEL resume up date as of AUG.
ROGEL resume up date as of AUG.
 
Turn Key Group Services - OHS Toolkit
Turn Key Group Services - OHS ToolkitTurn Key Group Services - OHS Toolkit
Turn Key Group Services - OHS Toolkit
 
Safe work procedure1
Safe work procedure1Safe work procedure1
Safe work procedure1
 
MARS NOLAN RESUME 2
MARS NOLAN RESUME 2MARS NOLAN RESUME 2
MARS NOLAN RESUME 2
 
kenneth lester Pedroche (UPDATED)
kenneth lester Pedroche (UPDATED)kenneth lester Pedroche (UPDATED)
kenneth lester Pedroche (UPDATED)
 
Touseef cv
Touseef cvTouseef cv
Touseef cv
 
Full H&S policy
Full H&S policyFull H&S policy
Full H&S policy
 
Full HS policy
Full HS policyFull HS policy
Full HS policy
 
update 20feb1
update 20feb1update 20feb1
update 20feb1
 
Method_Statement_for_Excavation_and_Back.pdf
Method_Statement_for_Excavation_and_Back.pdfMethod_Statement_for_Excavation_and_Back.pdf
Method_Statement_for_Excavation_and_Back.pdf
 
CV 2016
CV 2016CV 2016
CV 2016
 
Methodstatement welding
Methodstatement weldingMethodstatement welding
Methodstatement welding
 
Gobi resume
Gobi resumeGobi resume
Gobi resume
 
CV Oil and Gas Field Operator Nishanth P Joy
CV Oil and Gas Field Operator Nishanth P JoyCV Oil and Gas Field Operator Nishanth P Joy
CV Oil and Gas Field Operator Nishanth P Joy
 
Abid mahmood --hse
Abid mahmood --hseAbid mahmood --hse
Abid mahmood --hse
 
Module 4 pre construction
Module 4 pre constructionModule 4 pre construction
Module 4 pre construction
 
CURRENT SAFETY ENGINNER CV2
CURRENT SAFETY ENGINNER CV2CURRENT SAFETY ENGINNER CV2
CURRENT SAFETY ENGINNER CV2
 
Mawaz CV
Mawaz CVMawaz CV
Mawaz CV
 
CV - HSE Specialist new
CV - HSE Specialist newCV - HSE Specialist new
CV - HSE Specialist new
 

Mais de SyedMoazzamAliAli1 (14)

pptonsmartcity-160421014045.pdf
pptonsmartcity-160421014045.pdfpptonsmartcity-160421014045.pdf
pptonsmartcity-160421014045.pdf
 
VALVE AND TESTING.pdf
VALVE AND TESTING.pdfVALVE AND TESTING.pdf
VALVE AND TESTING.pdf
 
Boiler Maintenance and Safety PPT.pdf
Boiler Maintenance and Safety PPT.pdfBoiler Maintenance and Safety PPT.pdf
Boiler Maintenance and Safety PPT.pdf
 
NPSH.pdf
NPSH.pdfNPSH.pdf
NPSH.pdf
 
EXTINGUISHER Training.pdf
EXTINGUISHER Training.pdfEXTINGUISHER Training.pdf
EXTINGUISHER Training.pdf
 
Piping Design ppt.pdf
Piping Design ppt.pdfPiping Design ppt.pdf
Piping Design ppt.pdf
 
Control Valve.pdf
Control Valve.pdfControl Valve.pdf
Control Valve.pdf
 
SCADA PPT.pdf
SCADA PPT.pdfSCADA PPT.pdf
SCADA PPT.pdf
 
Compressor PPT.pdf
Compressor PPT.pdfCompressor PPT.pdf
Compressor PPT.pdf
 
Job websites.pdf
Job websites.pdfJob websites.pdf
Job websites.pdf
 
BMS1.pdf
BMS1.pdfBMS1.pdf
BMS1.pdf
 
UP in Air with CO2.pdf
UP in Air with CO2.pdfUP in Air with CO2.pdf
UP in Air with CO2.pdf
 
Organic Wate Converter .pdf
Organic Wate Converter .pdfOrganic Wate Converter .pdf
Organic Wate Converter .pdf
 
Plumbing Design Course.pdf
Plumbing Design Course.pdfPlumbing Design Course.pdf
Plumbing Design Course.pdf
 

Último

Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx959SahilShah
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girlsssuser7cb4ff
 
Piping Basic stress analysis by engineering
Piping Basic stress analysis by engineeringPiping Basic stress analysis by engineering
Piping Basic stress analysis by engineeringJuanCarlosMorales19600
 
US Department of Education FAFSA Week of Action
US Department of Education FAFSA Week of ActionUS Department of Education FAFSA Week of Action
US Department of Education FAFSA Week of ActionMebane Rash
 
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsyncWhy does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsyncssuser2ae721
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...VICTOR MAESTRE RAMIREZ
 
Indian Dairy Industry Present Status and.ppt
Indian Dairy Industry Present Status and.pptIndian Dairy Industry Present Status and.ppt
Indian Dairy Industry Present Status and.pptMadan Karki
 
Electronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfElectronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfme23b1001
 
welding defects observed during the welding
welding defects observed during the weldingwelding defects observed during the welding
welding defects observed during the weldingMuhammadUzairLiaqat
 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...asadnawaz62
 
Transport layer issues and challenges - Guide
Transport layer issues and challenges - GuideTransport layer issues and challenges - Guide
Transport layer issues and challenges - GuideGOPINATHS437943
 
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfCCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfAsst.prof M.Gokilavani
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerAnamika Sarkar
 
Arduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.pptArduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.pptSAURABHKUMAR892774
 
Class 1 | NFPA 72 | Overview Fire Alarm System
Class 1 | NFPA 72 | Overview Fire Alarm SystemClass 1 | NFPA 72 | Overview Fire Alarm System
Class 1 | NFPA 72 | Overview Fire Alarm Systemirfanmechengr
 
Earthing details of Electrical Substation
Earthing details of Electrical SubstationEarthing details of Electrical Substation
Earthing details of Electrical Substationstephanwindworld
 
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)Dr SOUNDIRARAJ N
 
Concrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxConcrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxKartikeyaDwivedi3
 
lifi-technology with integration of IOT.pptx
lifi-technology with integration of IOT.pptxlifi-technology with integration of IOT.pptx
lifi-technology with integration of IOT.pptxsomshekarkn64
 

Último (20)

POWER SYSTEMS-1 Complete notes examples
POWER SYSTEMS-1 Complete notes  examplesPOWER SYSTEMS-1 Complete notes  examples
POWER SYSTEMS-1 Complete notes examples
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girls
 
Piping Basic stress analysis by engineering
Piping Basic stress analysis by engineeringPiping Basic stress analysis by engineering
Piping Basic stress analysis by engineering
 
US Department of Education FAFSA Week of Action
US Department of Education FAFSA Week of ActionUS Department of Education FAFSA Week of Action
US Department of Education FAFSA Week of Action
 
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsyncWhy does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...
 
Indian Dairy Industry Present Status and.ppt
Indian Dairy Industry Present Status and.pptIndian Dairy Industry Present Status and.ppt
Indian Dairy Industry Present Status and.ppt
 
Electronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfElectronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdf
 
welding defects observed during the welding
welding defects observed during the weldingwelding defects observed during the welding
welding defects observed during the welding
 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...
 
Transport layer issues and challenges - Guide
Transport layer issues and challenges - GuideTransport layer issues and challenges - Guide
Transport layer issues and challenges - Guide
 
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfCCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
 
Arduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.pptArduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.ppt
 
Class 1 | NFPA 72 | Overview Fire Alarm System
Class 1 | NFPA 72 | Overview Fire Alarm SystemClass 1 | NFPA 72 | Overview Fire Alarm System
Class 1 | NFPA 72 | Overview Fire Alarm System
 
Earthing details of Electrical Substation
Earthing details of Electrical SubstationEarthing details of Electrical Substation
Earthing details of Electrical Substation
 
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
 
Concrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxConcrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptx
 
lifi-technology with integration of IOT.pptx
lifi-technology with integration of IOT.pptxlifi-technology with integration of IOT.pptx
lifi-technology with integration of IOT.pptx
 

AHU.pdf

  • 1. METHOD STATEMENT HVAC AIR HANDLING UNIT P a g e 1 | 6 METHOD STATEMENT FOR AHU INSTALLATION
  • 2. METHOD STATEMENT HVAC AIR HANDLING UNIT P a g e 2 | 6 INTRODUCTION This Method statement describes in details the onsite installation of AHU. AHU shall be installed as per approved material submittal. SCOPE OF WORKS The Method Statement shall cover all works related to the installation of AHU as per approved shop drawing and approved material submittal for the project. REFERENCE DOCUMENTS 3.1. Specification – Section 15855 3.2. Recommendation of approved material submittal . ORGANIZATION & RESPONSIBILITIES Project Manager: It is the Project Manager duty to ensure that all necessary safety and protective equipment are provided along with properly trained and qualified personnel. Moreover, to ensure that all survey works are carried out in accordance with this method statement. Quality Engineer’s: It is the Quality Engineer’s responsibility to ensure that all surveying equipment is being calibrated. Ensure that all inspections and tests are carried out as per Project requirements and that all are recorded. Maintaining all quality records relevant to verification of records. Site Engineer / Site Supervisor’s: It is the Site Engineer / Site Supervisor’s duty to organize the work force in a safe manner and to ensure that safety and protective equipment are being properly utilized. He must also ensure that the method statement procedure is followed and notify the HAC Q.C / EHAF International for inspection. Surveyor’s: It is the Surveyor’s duty to obtain all data and information required for surveys. Determine methods to establish survey control. Use appropriate equipment to complete assigned task. Keep accurate notes and records to describe and certify work performed. Abide by all Site Safety and Quality Requirements. Safety Engineer / Officer’s:
  • 3. METHOD STATEMENT HVAC AIR HANDLING UNIT P a g e 3 | 6  The Safety Engineer is responsible for devising and implementing programmers and plans to safeguard, health and safety of all employees, and to prevent loss or damage to the existing assets and projects, He is responsible for the implementing of the safety programs. He is also responsible to:  Provide support to site safety officers advising them on safe working methods and assisting with training of personnel.  Carryout regular site safety audits and reports and correct unsafe work practices and potential hazards.  Investigate and report all accidents near misses and recommend prevention measures. Ensure maintenances of good hygienic standards and availability of safety equipment and first aid treatment.  Present monthly safety reports and required documents. Safety Officers are responsible for:  The day to day activities of maintaining safety on project site, they must: Understand and comply with requirements of the safety manual.  Cooperate with the safety engineer to create and maintain safe working conditions.  Assist the site engineers and foremen to organize the work area so that the men can perform their duties with maximum efficiency and minimize risk to themselves or to equipment.  Inspect equipment and tools before use to ensure correct storage and properly utilization. Maintain record of all injuries and damages on site, submit reports as required. RESOURCES Equipment & Machinery: The following equipment will be used to carry out the installation of FANS.  Mechanical hand tool  Mobile Crane  Fork Lift METHODOLOGY Storage  AHU shall be stored in such a manner as to preserve its quality condition.  AHU are to be as per manufacturer recommendations but at the same time it should be accessible.
  • 4. METHOD STATEMENT HVAC AIR HANDLING UNIT P a g e 4 | 6  The quantity to be delivered at site for installation shall be consistent with the necessary required quantity of the work to perform. Setting Out  Check the readiness of reference and coordinates.  Check the other activates works related with the installations.  Arrange all necessary work permit, check and verify the actual site condition. Unloading and Shifting:  AHU shall be transported by a delivery truck and mechanical crane / fork lift to the specific work place.  Safety Officer will be present during loading and unloading of.  Two lifting point will be used during the loading and unloading of AHU to ensure safety that no incident will occurs. Traffic Aide will be present during loading and unloading of Unit for maintaining the traffic in the project site if needed.  All lifting equipment will be inspected daily before operating. Any parts detected damages must be replaced immediately before operating. Installation for AHU at Concrete roof  Mech. Installation: -  Set and fix AHU steel frame at Unit location at roof.  Connect Unit with duct through duct reducer.  Installation manual attached.  Electrical Installation: -  Connect power cable from MCC Panel to disconnecting switch.  Connect Power Cable from disconnecting switch to Unit motor. QUALITY ASSURANCE Material : Approved submittal. Location : As per approved shop drawings HEALTH, SAFETY AND ENVIRONMENT
  • 5. METHOD STATEMENT HVAC AIR HANDLING UNIT P a g e 5 | 6 PPE Requirements As a minimum the following PPE should be used by staff / Labors  Hard hat.  Safety shoes.  Safety eye glasses.  Hand gloves.  High visibility vest. Any additional PPE as required by local rules or mandatory requirement shall be used. Safety Accessories  Traffic Cones.  Warning /barricade/barrier tape.  Safety signs.  Cooled water container for drinking.  First Aid box.  Workers rest area  Portable toilet  Fire extinguishers  Sign boards of Emergency contact details/persons Information to Personnel.  Safety Induction will be done in accordance with HSE Policy prior to start work in site.  Safety toolbox meetings to be carried out prior to work.  Before job start checklist of protective & safety equipment to be use are in order.  Personal protective & safety equipment as per requirement to be performed by personnel to do the task.  Toolbox talk to be convened & attended by all personnel assigned to do the task. Work crew will be given instruction on site surveying procedure & all risk associated with the works and registered attendance.  Safety personnel & designated responsible person will ensure that all above is carried out & any other statutory requirements are complied with before any work takes.  Hazard analysis to be done.
  • 6. METHOD STATEMENT HVAC AIR HANDLING UNIT P a g e 6 | 6  Personnel who have been briefed in the correct equipment set up.  Personnel will wear gloves, footwear, head & eye protection during work.  Use the correct tools to do the task.  Removal of any obstructive / protruding materials. APPENDICES 1. Risk assessment.