Anúncio
Anúncio

Mais conteúdo relacionado

Similar a Work Sampling, Process Mapping and Crew Balance Chart(20)

Anúncio

Work Sampling, Process Mapping and Crew Balance Chart

  1. Lean Project Delivery Group 7 Mohammad Jaseer – CE21M009 B. Chiranjeevi – CE21M108 Sourabh Kumar Singh – CE21M126 Tejaswini K – CE21M128
  2. Site Locations 1. Sarayu Hostel • Tour Based Work Sampling • Process Mapping of Carpentry work
  3. Site Locations 2. Open AirTheater • Crew Balance Chart of Concreting of floor • Crew Based Work Sampling of Concreting of floor
  4. 1. WORK SAMPLING
  5. 1.1Tour basedWork Sampling • Location – Sarayu Hostel • Date of sampling – 15th April 2022 • Time – 04:35 PM to 5:45 PM • No. of workers – 53 • Type of sampling – Random Category Nos. VA 21 NVAN 12 NVA 20 Total 53 VA, 39.62% NVAN, 22.64% NVA, 37.74% Percent Distribution ofVA, NVAN and NVA
  6. VA Finishing - applying Plaster of Paris (PoP) 13 Finishing - Grinding 2 Carpentry 4 Electrical wiring 2 Total 21 NVAN Scarping -waste cement 4 Brooming 3 Material shifting 5 Total 12 Carpentry Scrapping and Brooming Material Shifting Applying PoP Grinding
  7. NVA Standing idle 6 Waiting for materials 4 Sleeping 1 Using mobile 2 Talking 5 Walking 2 Total 20 Waiting for material Walking Sleeping Standing idle Talking Using mobile
  8. 62% 9% 19% 10% Value Added Activities Finishing - applying Plaster of Paris (PoP) Finishing - Grinding Carpentary Electrical wiring 33% 25% 42% NonValue Added but Necessary Activities Scarping -waste cement Brooming Material shifting 30% 20% 5% 10% 25% 10% NonValue Added Activities Standing idle Waiting for materials Sleeping Using mobile Talking Walking
  9. 1.2 Crew basedWork Sampling • Location – OAT • Date of sampling – 15th April 2022 • Time – 10:20 PM • No. of workers in the crew– 10 • Type of sampling – Random • 75 samples taken from video Work categorization for Masons VA - Spreading and leveling concrete NVAN - Minor leveling of concrete at the edge NVA - Idling Work categorization for Helpers VA -Transporting, pouring, and spreading concrete NVAN - Cleaning and handing over tools NVA - Idling
  10. Worker’s Identification Crew – 10 Workers 3 Masons 7 Helpers Crew 1 – Mason #1 Crew 2 – Mason #2 Crew 3 – Mason #3 Crew 7 – Helper #4 Crew 8 – Helper #5 Crew 5 – Helper #2 Crew 10 – Helper #7 Crew 4 – Hel Crew 6 – Helper #3 Crew 9 – Helper #6
  11. Levelling of concrete Spreading of concrete Transportation of concrete Pouring of concrete Minor levelling Idling
  12. 85% 8% 7% Mason#1 69% 8% 23% Mason#2 79% 7% 15% Mason #3 VA - Spreading and leveling concrete NVAN - Minor leveling of concrete at the edge NVA - Idling
  13. 23% 33% 44% Mason Helper#1 28% 19% 53% Mason Helper#2 40% 32% 28% Mason Helper#3 VA - Transporting, pouring, and spreading concrete NVAN - Cleaning and handing over tools NVA - Idling 100% Mason Helper#4 49% 51% Mason Helper#5 48% 52% Mason Helper#6 47% 53% Mason Helper#7
  14. Summary ofVA, NVAN & NVA activities 32% 25% 43% Percent Distribution of overallVA, NVAN & NVA VA NVAN NVA 78% 7% 15% Distribution ofVA, NVAN & NVA activities for all Masons VA NVAN NVA 13% 33% 54% Distribution ofVA, NVAN & NVA activities for all Helpers VA NVAN NVA
  15. Observation Recommendation Tour based WS Standing idle and talking contributed 55% of NVA activities as there was lack of supervisors. Deployment of 2 supervisors. Waiting for materials contributed 20% of NVA activities. To minimize waiting for materials, preplanning of activities is required by accessing daily and weekly schedules. Crew based WS More workers were deployed that lead to 43% idle time Reduce the number of helpers. Monitoring of productivity.
  16. 2. PROCESS MAPPING
  17. 2 Process Mapping • Location – Sarayu Hostel • Process– Carpentry work of wardrobe doors and main doors of room • Objective – optimize the flow
  18. Process Chart – Current State Location Symbol Activity Location 1 Transfer of plywood fromTruck Storage of plywood till the requirement at Ground floor Location 2 Transfer to the storage location of individual floor storage room Storage of plywood till the cutting operation Location 3 Transportation to cutting, finishing workplace Processing of plywood for fitting Location 4 Transfer of finished plywood Temporary storage till the rooms are ready for fitting Location 5 Transfer of finished works for fitting location Fitting and finishing operation
  19. Process Chart – Future state Location Symbol Activity Location 1 (CentralWorkplace) Transfer of plywood fromTruck Storage of plywood til the requirement Processing of plywood for fitting Location 2 Transfer of finished plywood TemporaryStorage of finished plywood till the rooms are ready for fitting Location 3 Transfer of finished works for fitting location Fitting and finishing operation
  20. 1. Temporary storage in Ground floor 2. Manual shifting of plywood to individual floors 3.Temporary storage in Individual floors
  21. 4. Processing of plywood for fitting 5.Temporary storage of finished plywood
  22. 6. Fitting Location 7. Central workshop area proposed.
  23. Observation Recommendation Process mapping The intermediate storage of plywood at individual floor and operation location was redundant The single transfer of materials from central work location to fitting location The setting up of central work place at courtyard wherein all carpentry work can be streamlined The workplace was distributed all over the building Inventory management issue as the plywood was kept at so many locations
  24. Comparison of Process Chart – Present vs Future state Process A B Savings Operation 2 2 0 Transporatation 5 3 2 Storage 3 2 1 10 7 3
  25. 3. CREW BALANCE CHART
  26. Activity :- Concreting @ Open Air Auditorium 1 Cycle :- Completion of 1 section of concrete work Cycle Time :- 7 min 28 sec (448 sec) Manpower in as-in condition, • No of masons :- 3 • No of helpers :- 7 Main Activities observed, • Levelling • Pouring • Spreading • Transporting • Idling • Waiting Activity Details Crew 1 – Mason #1 Crew 2 – Mason #2 Crew 3 – Mason #3 Crew 7 – Helper #4 Crew 8 – Helper #5 Crew 5 – Helper #2 Crew 10 – Helper #7 Crew 4 – Helper # Crew 6 – Helper #3 Crew 9 – Helper #6
  27. Crew based chart for as-is condition Detection phase- • The workers were idle most of the time (39% of total time) due to unclear sequence of activities. • The workers are not assigned with clear roles as evident from the CBC. • The M4 is idle for most of the time. • M9 & M10 were idle and waiting for most of the time. Observation from As-Is Condition
  28. • Workers were idle for almost 39% of the cycle time. • From the table, it is observed that M4. M9 & M10 seem to be more idle, mostly waiting for the mixed concrete. Duration distribution of various activities in as-in condition Observation from As-Is Condition
  29. Crew based chart after 1st iteration Improvement phase- • The M4 was completely idle, hence he was removed. • M9 & M10 whose major work was transporting was removed and assigned the same activity to M8. • Clear roles has been assigned to Masons M6 & M7 in sequence to spread the Concrete. • Masons M1, M2 & M5 starts levelling in a sequence after the spreading is done. • The Pouring activity is completed with in seconds, so it was not considered in CBC. After 1st iteration
  30. Cost Improvement after 1st Iteration
  31. Crew based chart after 2nd iteration Improvement phase- • The works of Mason M1 was removed and the same activity was distributed to M2 & M5 in a sequence. • The main activity of Mason M3 was spreading and the same activity was assigned to M7 in continuous manner. in such a way that there is no idle time for M7. After 2nd iteration
  32. Cost Improvement after 2nd Iteration
  33. Crew based chart after 1st iteration Crew based chart after 2nd iteration Crew based chart for as-in condition COST SAVED- 48% COST SAVED - 27% Crew Based Charts - Summary
  34. THANK YOU.
Anúncio