SlideShare uma empresa Scribd logo
1 de 32
Page | 1 Copyright 2014, Simplilearn, All rights reserved.
Full length ACP Classroom Simulation Test
1. Forecasting the financial value of a theme is the responsibility of:
a. Analysts
b. Product Owner
c. Project Manager
d. Sponsor
Correct Answer: b) Forecasting the financial value of a theme is the responsibility of the product owner.
2. Which of the following explains 'Retained Revenue'?
a. Revenue due to a new opportunity
b. Additional incremental revenue from existing customers
c. Revenue, an organization will lose if the project is not performed
d. Revenue due to streamlining a process
Correct Answer: (c) Retained revenue refers to the revenue an organization will lose if the project is not
performed.
3. You are part of the team that developed software for the organization's own use in serving the
hospital customers. At one point, the CEO realizes that with some enhancements the software could
be used to provide the same services to health insurers. The team is asked to make the changes and
is able to bring an entirely new source of revenue into the company because of the new software
enabled. Under what revenue stream is this feature classified?
a. New Revenue
b. Incremental Revenue
c. Retained Revenue
d. Operational Efficiencies
Correct Answer: a) New Revenue is the revenue from a new opportunity after a project is completed.
4. Which of the following are the responsibilities of the Scrum Master?
a. Achieving initial and ongoing funding for the project
b. Teaching the Product Owner how to maximize ROI and the objectives
c. Being responsible for developing the functionality of the product
d. Removing the barriers between the customer and the Product Owner
Correct Answer: b) The Scrum Master is responsible for teaching the Product Owner how to maximize
ROI and the objectives.
Page | 2 Copyright 2014, Simplilearn, All rights reserved.
5. In agile, which of the following defines the splitting of a story or a feature into smaller, easier-to-
estimate pieces?
a. Decomposition
b. Disaggregation
c. Theme
d. Epic
Correct Answer: b) Disaggregation refers to splitting a story or feature into smaller, easier-to-estimate
pieces.
6. Which one of the following phases of project management includes developing a capability and/or
feature-based release plan to deliver the vision?
a. Envision
b. Speculate
c. Explore
d. Adapt
Correct Answer: b) Speculate phase includes developing a capability and/or feature based release plan
to deliver the vision.
7. A story point is a unit of measure to express the estimated difficulty or effort of a user story. What is
the unit of measure used here?
a. Days
b. Years
c. Points
d. Iterations
Correct Answer: a) A story point is a unit of measure to express the estimated difficulty or effort of a
user story and might be estimated using days.
8. In a complete Product Planning structure, which of the following denotes the product planning
structure with a medium range timeframe, story level of detail, and capability commitment?
a. Release
b. Story
c. Roadmap
d. Wave
Correct Answer: d) Wave is the Product Planning structure with Medium range time frame (3 months)
with Story level capability and Capability commitment.
Page | 3 Copyright 2014, Simplilearn, All rights reserved.
9. According to DeMarco, fragmented knowledge workers may look busy but a lot of their business is
just thrashing. The minimum cost penalty is –
a. 15%
b. 10%
c. 5%
d. 25%
Correct Answer: a) According to research performed by DeMarco, the minimum cost penalty of
thrashing is 15%.
10. In a project, all of the user stories are estimated and the sum of those estimates is 100 story points.
Based on past experience, it is known that the team’s velocity is 9 story
points per two-week iteration. How many iterations does the project need to complete the user
stories?
a. 9
b. 11
c. 1
d. 90
Correct Answer: b) Iterations = 100/9 = 11.1
11. Who should participate in Iteration Planning?
a. Customer, Iteration Manager, Developers, and Testers
b. Product Manager, Iteration Manager, Developers, and Testers
c. Entire Project Team
d. Product Specialists, Customer, Iteration Manager, Developers, and Testers
Correct Answer: c) The entire project team—product manager, product specialists, customers,
developers, testers, iteration manager, project leader—should participate in the iteration planning
session as it provides everyone with the context for work to be accomplished during the iteration.
Functional manager participation can help the team better understand strategic priority issues. The
functional manager demonstrates commitment to and support of the project.
12. Which of the following statements is false regarding Agility?
a. Agility is the ability to balance flexibility and stability
b. Agility is the ability to both create and respond to change to profit in a turbulent business
environment
c. Agility is avoiding planning and lack of structure
Page | 4 Copyright 2014, Simplilearn, All rights reserved.
d. "Agility is ability to deliver customer value while dealing with the unpredictability and dynamism
of an inherent project "
Correct Answer: c) Agility is not an excuse to avoid planning or not having structure.
13. Technical debt is the gap between a product's actual Cost of Change (CoC) and its optimal CoC.
Managing technical debt helps ensure reliable delivery today and ready adaptation to tomorrow's
customer needs. When would technical debt not occur?
a. During Initial Development
b. Ongoing Maintenance
c. During Enhancement
d. During closing
Correct Answer: d) Technical debt can arise during initial development, ongoing maintenance (keeping a
product at its original state), or enhancement (adding functionality) and not during closing.
14. The Levels of Listening by Whitworth states 3 Levels of listening. What does the third level, viz.
Global listening refer to?
a. A hardwired connection is established between the coach and the speaker
b. The coach uses everything in the environment, viz. speaker's tone of voice, posture, etc., when
listening at this level
c. The coach hears the speaker's words attentively
d. The coach only hears the global sounds and not the speaker's words
Correct Answer: b) The coach uses everything in the environment when listening at Level III. The
speaker’s tone of voice, posture, changes in the room temperature, noises—all of these things are
noticed and used by the coach.
15. Team 1 has been asked to complete work on Item 10 story and deliver it to Team 2 so that they can
initiate work on Item 12 story, which is dependent on completion of Item 10 story. The leader of
Team 1 decides to add a buffer that protects the start date on Item 12 story against delays in the
completion of Item 10 story. This buffer is known as
a. Feeding Buffer
b. Iteration Buffer
c. Story Buffer
d. Release Buffer
Correct Answer: a) The Feeding buffer protects the start date on Item 12 story against delays in the
completion of Item 10 story.
Page | 5 Copyright 2014, Simplilearn, All rights reserved.
16. A meeting where a team reflects and looks back to adapt and learn to do future projects better is
popularly known as:
a. Retrospective
b. Planning
c. Review session
d. Status Meeting
Correct Answer: a) Retrospective is the meeting where a team reflects and looks back to adapt and learn
to do future projects better.
17. In the agile methodology, decisions are framed focusing on which of the following?
a. Identifying the types of decisions that need to be made
b. A team of stakeholders involved in the decision making process
c. Delegating the decision making process to the developers only
d. Senior manager making the decision
Correct Answer: b) In agile methodology, decisions are framed by a team of stakeholders involved in the
decision making process.
18. When should be the BEST time for the team to estimate a task?
a. Throughout the Iteration
b. During Iteration Planning
c. Task estimates are decided by the Scrum Master
d. At the time of Iteration Planning as well as during the iteration
Correct Answer: d) Project Team will estimate a task at the time of Iteration Planning as well as during
the iteration planning.
19. Which of the following charts shows the number of tasks completed each day of the iteration to
monitor the progress?
a. Progression charts
b. Task Burn down chart
c. Task check off charts
d. Task charts
Page | 6 Copyright 2014, Simplilearn, All rights reserved.
Correct Answer: b) Many agile practitioners use a task burn down chart, which shows the number of
tasks completed each day of the iteration to monitor progress.
20. Self-organization implies a reliance on internal motivation of the team rather than external
motivation. This is referred to as:
a. Delegatory management
b. Measurement based management
c. Democratic management
d. Autocratic management
Correct Answer: a) Self-organization implies a reliance on internal motivation of the team rather than
external motivation (i.e., a measurement target). Author Austin calls this delegatory management as
contrasted with measurement-based management. He goes on to say, "measurement-based
management is in conflict with delegatory management. There is a negative interaction because of the
implicit message of distrust that a measurement system conveys by the fact of its existence."
21. Which of the following describes error-feedback ratio?
a. Time spent to fix the hard bugs
b. Number of defects detected in an iterative cycle
c. Number of errors predicted
d. Number of new defects created when fixing existing known defects
Correct Answer: d) Error-feedback ratio is the number of new defects created when fixing existing
known defects.
22. Which is the Japanese term for thin slices of raw fish, a Scrum technique that requires every piece of
functionality be completed fully by the developers?
a. Lean
b. Sashimi
c. Ishikawa diagram
d. Ability
Correct Answer: b) Sashimi is the Japanese term that requires every piece of functionality be completed
fully by the developers.
Page | 7 Copyright 2014, Simplilearn, All rights reserved.
23. How would risk be managed on an Agile project?
a. Decision tree
b. Risk-adjusted backlog
c. Risk assessment matrix
d. Risk management plan
Correct Answer: b) On an Agile project, risk would be managed using the risk-adjusted backlog.
24. Which methodology attempts to remove project uncertainty?
a. Waterfall
b. XP
c. Kanban
d. Scrum
Correct Answer: a) Agile embraces uncertainty, but waterfall tries to manage it by removing it.
25. Which of the following charts shows how much work remains on an iteration and how much work
has been completed so far?
a. Iteration burn down chart
b. Combined burn-down chart
c. Daily burn down chart
d. Burn up chart
Correct Answer: b) A Combined burn-down chart shows how much work remains on an iteration and
how much work has been completed so far.
26. A story that was planned as one story point, actually took two days to complete. How much does it
contribute to the velocity when calculated at the end of the iteration?
a. One Point
b. Three Points
c. Two Points
d. Cannot be calculated
Correct Answer: a) Only the original planned effort of one story point is used to calculate the velocity at
the end of the iteration.
27. A good approach for small stories is to combine them into larger stories that represent from about a
half-day to several days of work. The combined story is given a name and is scheduled and worked
on just like any other story. Which of the following is an example of a small story?
Page | 8 Copyright 2014, Simplilearn, All rights reserved.
a. Major database architecture changes
b. Updating over one hundred automated reports
c. User interface changes
d. Status updates
Correct Answer: c) Bug reports and user interface changes are common examples of stories that are too
small for an individual story.
28. Who specifies Acceptance Tests in an Agile Project?
a. Customer
b. Programmer
c. Developer
d. Product Manager
Correct Answer: a) As the software is being written to fulfil a vision held by the customer, the
acceptance tests need to be specified by the customer. The customer can work with a programmer or
tester to actually create the tests, but minimally the customer needs to specify the tests that will be
used to know when a story has been correctly developed.
29. Which methodology uses the idea of amplifying learning?
a. Kanban
b. Scrum
c. XP
d. Lean
Correct Answer: d) Lean is based on the principles "eliminate waste, amplify learning, decide as late as
possible, deliver as fast as possible, empower the team, build integrity in, and see the whole".
30. When can a plan be changed in Agile Management?
a. At the end of the Iteration
b. When we have learned something new
c. At the Daily Meeting
d. You cannot change once the plan is prepared
Correct Answer: b) In Agile, you can change the plan when something new is learned or when it is
known that a mistake is to be avoided.
Page | 9 Copyright 2014, Simplilearn, All rights reserved.
31. You have been assigned a New Project that is large, complex, and uncertain. As a Project Manager,
you will be using agile project management. Which of the following will you select while creating
your team?
a. Team is expandable with the project
b. Large team
c. Functional manager is responsible for the team
d. Small experienced team
Correct Answer: d) As per Agile methodology, it is best to work with small teams staffed by talented and
experienced people and increase the number of team members only when necessary.
32. Assuming one-week iterations and a team of four developers, how many iterations will it take for
the team to complete a project with 27 story points if they have a velocity of 4?
a. 4
b. 6
c. 7
d. 24
Correct Answer: c) Number of Iterations = 27/4 = 6.75 ~7
33. Which of the following defines a complex story?
a. A user story that contains multiple stories
b. A user story that users can mark as inactive
c. A user story that is large by nature and cannot easily be dissected into smaller stories
d. A user story that is not executable
Correct Answer: c) A complex story is a user story that is large by nature and cannot easily be dissected
into smaller stories.
34. Which of the following is NOT an attribute of a Good Story?
a. Testable
b. Large
c. Independent
d. Negotiable
Correct Answer: b) A good story has six attributes - Independent, Negotiable, Valuable to users or
customers, Estimable, Small, and Testable.
Page | 10 Copyright 2014, Simplilearn, All rights reserved.
35. When a team of people work together, the team goes through a specific sequence of group
dynamics called the Tuckman model. Which of the following depicts the correct sequence of this
process?
a. Forming, norming, performing, storming
b. Forming, storming, norming, performing
c. Forming, performing, storming, norming
d. Storming, norming, performing, forming
Correct Answer: b) The Tuckman model has the following stages: forming, storming, norming,
performing.
36. Name the XP technique where two people work: one person who codes is the driver and the other
person who thinks is the navigator?
a. Pair Programming
b. Planning Poker
c. Planning Technique
d. Coding Technique
Correct Answer: a) Pair Programming is when two developers work on the same code together to
improve efficiency.
37. An informative and collaborative workspace makes information easily communicated by just being
in the room. Of the following, which would not be found in an informative workspace?
a. Big Visible Charts
b. Process Improvement Charts
c. Hand Drawn Charts
d. Project Charter
Correct Answer: d) Big Visible Charts, Process Improvement Charts, Hand Drawn Charts are all examples
that might be found in an informative workspace. A project charter would be a project document that
would be stored in the project archive and not visible to the team in a workspace.
38. There are different types of Retrospectives. These are Release Retrospectives, Project
Retrospectives, Iteration Retrospectives, and Surprise Retrospectives. What are Surprise
Retrospectives?
a. Are conducted when an unplanned event changes the situation
Page | 11 Copyright 2014, Simplilearn, All rights reserved.
b. Are conducted at the end of each iteration
c. Are conducted half way of each project
d. Are suggested by the Scrum Master
Correct Answer: a) Surprise Retrospective is conducted when an unplanned event changes the situation.
39. The red team finished 38 story points in their last two-week iteration. The blue team has half as
many developers on a different project and completed 38 story points in their last two-week
iteration. What can be determined from this information?
a. The story points of one team are not comparable to the story points of any other team
b. Team A is twice as productive as Team B
c. Team A should have more people in the team
d. Team B has the management support
Correct Answer: a) The story points of one team are not comparable to the story points of any other
team.
40. Four developers are estimating a story. The estimates provided are two, three, six, and ten story
points. Which estimate should be used?
a. 2 story point
b. 6 story point
c. 10 story point
d. None of the present estimates until the team discusses how to get the estimates closer together
Correct Answer: d) None of the present estimates, two, three, six, or ten, until the team discusses how
to get the estimates closer together.
41. A stand-up meeting is conducted in the morning every day. Each person describes the new
information that the team should know. What is NOT discussed?
a. What did I do yesterday?
b. What are my tasks for the coming week?
c. What do I plan to do today?
d. What issues are preventing my progress?
Correct Answer: b) In the daily stand-up meeting, the tasks for next week would not be discussed, only
yesterday's activity, today's activity, and current issues are discussed.
42. Which of the following describes a task board?
Page | 12 Copyright 2014, Simplilearn, All rights reserved.
a. Is on a white board
b. Is a tool to show the project trends
c. Organizes work and communicates what work is left
d. Displays the velocity
Correct Answer: c) The task board organizes work and communicates what work is left.
43. Some stakeholders are interested in viewing the project progress, but are not interested in the
details. Which of the following should you share with these stakeholders?
a. Weekly demo
b. Vision Statement
c. Release plan
d. Burn up chart
Correct Answer: d) The burn up chart shows progress towards project completion and the expected
completion date.
44. Which of the following is NOT included in the story cards information'?
a. Estimated Value Points
b. Story description
c. Story dependencies
d. Velocity
Correct Answer: d) Story cards information includes story name, story description, estimated work
effort, estimated value points, requirements uncertainty, story dependencies, and acceptance tests.
Velocity is the number of user stories that are delivered in iteration.
45. Which of the following will NOT assist in Critical Problem solving during the project?
a. Ask probing questions
b. Use active listening
c. Use reflective listening
d. Injecting ideas
Correct Answer: d) During critical problem solving, you can ask probing questions, use active and
reflective listening. Lead to an answer but one should avoid injecting their ideas.
46. One of your stakeholders wants more detail than the vision statement provides, but not the
overwhelming detail of the release and iteration plans. Which of the following progress report will
you share with this stakeholder?
Page | 13 Copyright 2014, Simplilearn, All rights reserved.
a. Roadmap
b. Status email
c. Iteration plan
d. Productivity chart
Correct Answer: a) Some stakeholders may want more detail than the vision statement provides, but not
the overwhelming detail of the release and iteration plans. For these stakeholders, consider maintaining
a document or slide deck that summarizes planned releases and the significant features in each one."
47. Every team needs to constantly evaluate and make appropriate adaptations in the following four
areas:
a. Product value, Product quality, Team performance, Project status
b. Product value, Product quality, Team performance, Organization status
c. Product quality, Team performance, Project status, Project deliverables
d. Product value, Product Features, Team performance, Project status
Correct Answer: a) Every team needs to constantly evaluate and make appropriate adaptations in the
following four areas: product value, product quality, team performance, and project status.
48. Which of the following is NOT true about the Iteration Demos?
a. Demonstrate the team’s progress
b. Realistically report progress
c. Shown only to a select set of stakeholders
d. Solicit feedback from customers
Correct Answer: c) Iteration demos are not shown only to select set of stakeholders, but all stakeholders
and are invited to provide feedback.
49. During which project management phase are the product stories delivered?
a. Envision
b. Speculate
c. Explore
d. Adapt
Correct Answer: c) It is during the Explore phase, the product stories are delivered. This phase involves
planning and delivering tested stories in a short iteration, constantly seeking to reduce the risk, and
uncertainty of the project.
50. What do you mean by Throughput?
Page | 14 Copyright 2014, Simplilearn, All rights reserved.
a. The amount of production over time
b. The number of features the team can develop in a particular amount of time.
c. The number of features released during a Release
d. The number of defects rectified during a Release
Correct Answer: b) Throughput is the number of features the team can develop in a particular amount
of time.
51. Which of the following does NOT explain Refactoring?
a. Organizes the working code
b. Improves code quality
c. Makes the code more maintainable
d. Reduces bugs dramatically
Correct Answer: d) Refactoring is the reorganization of code to make it more organized, of higher
quality, and more maintainable.
52. If your release is 12 iterations away, your velocity is 14 points, your risk exposure is 1 iteration and
with a 10% chance, how many points will you have finished?
a. 154
b. 110
c. 86
d. 92
Correct Answer: a) Using the following formula, risk_adjusted_points_remaining = (iterations_remaining
- risk_exposure) * velocity / risk_multiplier --> points remaining = (12 - 1) * 14 = 154 points
10 percent chance: 154 / 1 = 154 points.
53. The retrospective meeting on previous iteration should last not more than
a. 30 minutes
b. 60 minutes
c. 10 minutes
d. 5 minutes
Correct Answer: b) The retrospective meeting on previous iteration should be maximum of one hour.
54. Which of the following describes a story?
Page | 15 Copyright 2014, Simplilearn, All rights reserved.
a. "Full-screen demo option for a job fair"
b. "Automate integration build"
c. "Deploy to staging server outside the firewall"
d. "Improve performance"
Correct Answer: a) "Full-screen demo option for a job fair" is a story. “Automate integration build” does
not represent customer value, hence not a story. “Deploy to staging server outside the firewall”
describes implementation details rather than an end result, and it doesn’t use customer terminology,
hence not a story. “Improve performance” has no clear completion criteria, hence not a story.
55. Which of the following is NOT a principle from the Agile Manifesto?
a. Responding to change
b. Customer collaboration
c. Technical excellence
d. Working software
Correct Answer: c) Technical excellence is not a principle from the Agile Manifesto.
56. In a design-the-box activity, the objective is to design the product box—front and back. Which of the
following would not be included in the activity?
a. Graphic design
b. Feature description
c. Operating requirements
d. Competitor's product name and features
Correct Answer: d) In a design-the-box activity, the objective is to design the product box—front and
back and would include the graphic design, feature description, and operating requirements.
57. In XP, the code goes through four levels of completion. Which of the following states the right
sequence?
a. Broken, Build, Ready for demo, Ready to release
b. Build, Ready for demo, Broken, Ready to release
c. Build, Ready for demo, Ready to release, Broken
d. Broken, Build, Ready to release, Ready for demo
Correct Answer: a) The four levels of completion are broken, build, ready for demo, and ready to
release.
58. Which of the following factors will not assist in improving the project velocity?
Page | 16 Copyright 2014, Simplilearn, All rights reserved.
a. Pay down technical debt
b. Offload programmer duties
c. Reduce customer involvement
d. Provide needed resources
Correct Answer: c) Improving customer involvement will assist in improving the project velocity.
59. What financial return parameter will be BEST for comparing the values of two different cash flow
streams?
a. Internal Rate of Return
b. Payback Period
c. Discounted Payback Period
d. Compound Interest
Correct Answer: a) Internal Rate of Return (IRR) is used to express the return on project in % when
comparing the two different cash flow streams.
60. What is the relative contribution of feature X to the project if it has a value of 12 and the total value
of all features is 35?
a. 0.38
b. 0.34
c. 2.91
d. 14.91
Correct Answer: b) To calculate the relative contribution of each feature, divide its value by the sum of
the Total Value of all features. Hence, relative contribution of feature X = 12/35 = 0.34.
61. Which of the following is NOT true about Retrospective?
e. Decides how the team will work together to complete the project
f. Reflects on past work and learn from the project history
g. Development process is driven by the team
h. Selects team members for the next project
Correct Answer: d) Retrospective is a meeting where a team learns from the project history, how the
team worked together so far, and what can be learned from the progress on the project do far to
continue a success development process driven by the team.
Page | 17 Copyright 2014, Simplilearn, All rights reserved.
62. Feature X has a value of 12 and the total value of all features is 35. If the feature is estimated to
cost 56%, what is the priority of this feature using relative weighting?
a. 0.34
b. 0.61
c. 1.64
d. 0.625
Correct Answer: b) The priority of the feature is determined by dividing the priority % by the cost %.
Hence the answer = (12/35)/(0.56) = 0.61.
63. What is MOST true about participatory decision making?
a. It is a technique that involves all the affected parties
b. It is just a meeting with no outcomes
c. It only involves the customer and the Product Manager
d. It is a technique based on the wishes of the Scrum Master
Correct Answer: a) Participatory decision making is a technique that involves all the affected parties.
64. If we plan to work in a two-week iteration with thirteen iterations during the project and with the
team velocity twenty story points or ideal days per iterations, what will the size of the total project
in story points be?
a. 13
b. 20
c. 260
d. 200
Correct Answer: c) The size of the total project will be 13 x 20 = 260 story points
65. Which of the following is NOT true regarding scope in Agile projects?
a. Scope in Agile is primarily a function of "rolling wave" planning
b. "Scope creep" doesn't exist in Agile projects
c. Scope is controlled through the use of the product backlog
d. Scope is validated by the Product Manager
Correct Answer: d) Scope is validated by the customer, not the product manager.
66. How is the Retrospective meeting BEST conducted?
Page | 18 Copyright 2014, Simplilearn, All rights reserved.
a. Set the stage, Gather data, Generate Insights, Decide on what to do, Close the Retrospective
b. Gather data, Generate Insights, Decide on what to do, Set the stage, Close the Retrospective
c. Set the stage, Gather data, Decide on what to do, Generate Insights, Close the Retrospective
d. Decide on what to do, Set the stage, Gather data, Generate Insights, Close the Retrospective
Correct Answer: a) The correct sequence is set the stage, gather data, generate Insights, decide on what
to do, and close the retrospective.
67. In an Agile project, what are the horizons in the planning onion that the agile teams are involved
with during the project?
a. Strategy, Portfolio, Product
b. Product, Release, Iteration
c. Release, Iteration, Day
d. Product, Iteration, Day
Correct Answer: c) Agile teams should be concerned with the horizons of release, iteration, and day.
68. What is the main purpose of a group of stories, an iteration, or a release known as:
a. Theme
b. Epic
c. Story
d. Combined Story
Correct Answer: a) Theme is the main purpose behind a group of stories, an iteration, or a release.
69. A project uses a version control system to mediate changes, which includes updating codes, testing
the code, and then checking-in the changes, which may occur several times in a day. This process is
known as?
a. Version Control Management
b. Continuous Integration
c. Simple Integration
d. Configuration Management
Correct Answer: b) Continuous integration includes updating codes, testing the code, and then checking-
in the changes, which may occur several times in a day.
70. Which of the following is NOT a technique for estimating a story?
Page | 19 Copyright 2014, Simplilearn, All rights reserved.
a. Expert Opinion
b. Analogy
c. Disaggregation
d. Decomposition
Correct Answer: d) Decomposition is not a technique for estimating.
71. Agile teams may use Planning Poker for estimation. Which of the following is NOT true about
Planning Poker?
a. It combines expert opinion, analogy, and disaggregation to obtain reliable estimates
b. Participants include all the developers in the team
c. The team for Planning Poker should not exceed more than 10 participants
d. The highest estimate is considered the final estimate
Correct Answer: d) The high estimate is not necessarily considered the final estimate because the
players with high and low estimates must explain their estimates and then a decision is taken by the
players as to the final estimate value.
72. Wideband Delphi is a repeatable process that can be used:
a. To generate estimation
b. To create a story
c. For implementation purpose
d. To motivate the team
Correct Answer: a) Wideband Delphi is a technique that is used to generate estimation.
73. Which of the following reports visually shows the remaining estimated workload over the course of
the project?
a. Product Backlog Burn down Report
b. Gantt Chart
c. Product Backlog
d. Sprint Chart
Correct Answer: a) The Product Backlog Burn down report visually shows the remaining estimated
workload over the course of the project.
74. When using affinity estimating, the minimum size for the number of items in the Product Backlog
is?
Page | 20 Copyright 2014, Simplilearn, All rights reserved.
a. 20
b. 40
c. 8
d. 5
Correct Answer: a) When using affinity estimating, the minimum size for the number of items in the
Product Backlog is 20 items.
75. Which of the following defines Elapsed Time?
a. The same as ideal time
b. The amount of time on a clock
c. The amount of time without any interruptions
d. The amount of time the team spent on the iteration
Correct Answer: b) Elapsed time is the amount of time on a clock.
76. Which of the following is NOT true about Kanban?
a. Is a visual system
b. Uses Work In Process (WIP)
c. Is a task board
d. Used in Lean Manufacturing
Correct Answer: c) A Kanban is a visual system using Work in Process (WIP with the Lean Manufacturing
process). A task-board visualizes current tasks.
77. The MoSCoW technique is used to create a prioritized requirements list. In MoSCoW technique, 'M'
stands for:
a. Medium
b. Must
c. Must Not Have
d. Minimum Marketable Features
Correct Answer: b) The MoSCoW prioritization scheme derived its name from the first letters of its
labels: “Must…”, “Should…”, “Could…”, “Won't.”
Page | 21 Copyright 2014, Simplilearn, All rights reserved.
78. What is a voting scheme where each stakeholder is given 100 points to use for voting in favor of the
most important requirements and can distribute the 100 points in any way desired?
a. Monopoly Money
b. 100-Point Method
c. Requirements Prioritization Money
d. Agile Prioritization
Correct Answer: b) The 100-Point Method is a voting scheme where each stakeholder is given 100 points
to use for voting in favor of the most important requirements and can distribute the 100 points in any
way desired.
79. In a Fixed Price contract, the risk is mostly assumed by the :
a. Supplier
b. Customer
c. Product Owner
d. Project Team
Correct Answer: a) In a Fixed Price contract, the risk is mostly assumed by the supplier, because if the
estimate is incorrect the supplier must still honor the fixed price to the customer.
80. Teams utilizing unfamiliar technology may need time for training prior to a project's launch and time
to establish a development environment. This training may be included:
a. In Iteration 0
b. As a new story
c. But is out of scope
d. In the functional manager's scope
Correct Answer: a) Iteration 0 is used to prepare the team for the project, including training and
doesn't deliver direct customer value.
81. Which of the following is NOT a Closed Story?
a. A recruiter can review resumes from applicants to one of her ads.
b. A recruiter can delete an application that is not a good match for a job.
c. A recruiter can manage the ads she has placed
d. A recruiter can change the expiration date of an ad
Page | 22 Copyright 2014, Simplilearn, All rights reserved.
Correct Answer: c) "A recruiter can manage the ads she has placed" is not a closed story because it is an
ongoing activity.
82. The primary task in release planning is assigning stories to iterations, chiefly on the basis of
_______________________
a. Value and Risk
b. Risk and Priority
c. Customer Requirements
d. Team ability and Value
Correct Answer: a) The primary task in release planning is assigning stories to iterations, chiefly on the
basis of value and risk.
83. In the Agile Team Stages of Shu Ha Ri, what does 'Ha' stand for?
a. Break the rule
b. Follow the rule
c. Be the rule
d. None of the above
Correct Answer: a) Shu Ha Ri means - 'Shu' to follow the rule, 'Ha' to break the rule, and 'Ri' to be the
rule.
84. "Having problems does not indicate a problem in itself, so welcome problems because they bring
with them the chance for the team to overcome, grow, and become stronger together." As an Agile
coach, which of the following is not one of the multiple perspectives to analyze or detect the
symptoms for the problem?
a. Process Level
b. Quality and Performance Level
c. Team dynamics dimension
d. Team members' management
Correct Answer: d) The multiple perspectives to analyze are the process level, the quality and
performance angle, and the team dynamics dimension, not the team members' management.
85. Which of the following documents all of the known features that are to be implemented throughout
the project?
Page | 23 Copyright 2014, Simplilearn, All rights reserved.
a. Prioritized Sprint
b. Vision Box
c. Product Backlog
d. Sprint Review Meet
Correct Answer: c) The Product Backlog documents all the known features that are to be implemented
throughout the project.
86. During the second level of conflict, disagreement, the team members distance themselves from one
another, except in one-on-one conversations to obtain advice and support. What becomes as
important as solving the problem?
a. Self-protection
b. Satisfy self-ego
c. Aim to win
d. None of the above
Correct Answer: a) During disagreement, self-protection becomes as important as solving the problem
or conflict situation.
87. John and Joseph are working in the same room. John is programming and Joseph is discussing with
Kim. John gets to hear their conversation and gets enough information to know that Joseph has
talked about some idea with Kim. What kind of communication is this referred to as?
a. Push Communication
b. Osmotic Communication
c. Pull Communication
d. Active Listening
Correct Answer: b) Osmotic communication occurs when people in the same environment hear and
comprehends information without being communicated to directly.
88. Which of the following is NOT included on Information Radiators?
a. Displaying Work Breakdown
b. Displaying Project Status
c. Automated Build Report
Page | 24 Copyright 2014, Simplilearn, All rights reserved.
d. Iteration Planning
Correct Answer: d) Information radiators may display the work breakdown, project status, and
automated build report, but not the iteration planning.
89. Spike solutions are small experiments to answer a question and determine a path forward. Which of
the following types of spike will you use if you need to test an approach to your production code?
a. Development Spike
b. Design Spike
c. Scheduling Spikes
d. Iteration Spikes
Correct Answer: b) A design spike would be used to test the production code for readiness to move
forward.
90. Of the listed options, which best describes User Stories?
a. Support tools for analysis
b. IEEE 830
c. Use Cases
d. Interaction Design Scenarios
Correct Answer: a) User stories are support tools for analysis.
91. What is the successful response option at Conflict Level 1: Problem to Solve?
a. Collaboration
b. Consensus
c. Safety
d. Root case analysis
Correct Answer: a) Successful response options at Level 1 are collaboration and consensus.
92. As per the Kano Model of customer satisfaction, which features are MOST important for the product
to be successful?
a. Exciters
b. Linear Features
c. Delighters
d. Threshold
Page | 25 Copyright 2014, Simplilearn, All rights reserved.
Correct Answer: d) Threshold features are the must-have features present in the product.
93. A methodology that is based on solutions or sequences of steps that is known to work for the
discipline is known as:
a. Normative
b. Rational
c. Heuristic
d. Participative
Correct Answer: a) Normative methodologies are based on solutions or steps known to work for a
certain discipline or industry.
94. What does acronym DRY stand for?
a. Don't Repeat Yourself
b. Don't Reject Yourself
c. Do Repeat Yourself
d. None of the above
Correct Answer: a) DRY stands for "Don’t Repeat Yourself" meaning not doing work that is not
necessary.
95. When a team member approaches the Coach with a complaint about another team member, what
conflict resolution technique should the Coach use?
a. Compromise
b. Face to Face
c. Three-step intervention
d. Confronting
Correct Answer: c) When a team member approaches the Coach with a complaint about another team
member, the three-step intervention path is the conflict resolution technique that the Coach should use.
96. A path of action to achieve a long-term goal is referred to as:
a. Tactical Planning
b. Strategic Planning
c. Goal Planning
d. Roadmap Planning
Correct Answer: b) A path of action to achieve a long-term goal is referred to as strategic planning.
Page | 26 Copyright 2014, Simplilearn, All rights reserved.
97. To detect problems at the process level, the team uses a questionnaire that lists required elements
and qualities that are the basic ingredients of Agile. From this, we consider the maturity of the Agile
process in the organization and how well the team follows the agile process. This questionnaire is
referred to as:
a. Health Check
b. Form
c. Questionnaire
d. Checklist
Correct Answer: a) The questionnaire is referred to as a health check.
98. Which of the following techniques would you use to detect problems within a process?
a. Sprints
b. Burn Up charts
c. Burn Down charts
d. Health checks
Correct Answer: d) Health checks, often in the form of a questionnaire, lists required elements and
qualities that jog our minds to help us remember the basic ingredients of Agile. They help us determine
how well the team is adhering to Agile methods.
99. What is the output of the Sprint Planning Meeting?
a. Sprint Backlog
b. Product Backlog
c. Iteration Backlog
d. None of the above
Correct Answer: a) The outcome of the Sprint Planning meeting is the Sprint Backlog.
100. A verbal communication to multiple people that a milestone was completed is known as:
a. Declaration Milestone
b. Publication
c. Announcement
d. Circular
Page | 27 Copyright 2014, Simplilearn, All rights reserved.
Correct Answer: a) A declaration milestone is a verbal communication to multiple people that a
milestone was completed.
101. At a Retrospective meeting, few issues are highlighted by the team. Who is responsible for
solving these issues?
a. The Scrum Master
b. Product Owner
c. Stakeholders
d. Team
Correct Answer: d) Agile teams are self-organizing and can find solutions to their problems with ease.
102. Which of the following is NOT done as part of Planning in Agile Project Management?
a. Risk Management
b. Product Vision
c. Slack
d. Done-Done
Correct Answer: d) Done-Done is part of releasing.
103. Which of the following BEST describes Horizontal Market Software?
a. Developed for many organizations
b. Developed and used across many industries
c. Developed for a dedicated customer
d. Developed for one organization
Correct Answer: b) Horizontal Market Software is intended to be used across a wide range of industries.
104. What is the BEST tool for tracking the progress of the project and evaluating the ROI on an Agile
project?
a. Sprint
b. Product Backlog
c. Iteration Backlog
d. Releases
Correct Answer: b) The Product Backlog is the BEST tool for tracking the progress of the project and
evaluating the ROI on an Agile project.
105. What are the four key terms by which the iterative part of Agile is defined?
Page | 28 Copyright 2014, Simplilearn, All rights reserved.
a. Time boxed, releasable, agility and incremental
b. Iterative, feature-based, time boxed, and incremental
c. Feature-based, time boxed, agility and incremental
d. Iterative, release-based, time boxed, and incremental
Correct Answer: b) The four key terms by which the iterative part of Agile is defined are iterative,
feature-based, time boxed, and incremental.
106. What is the process of planning in waves as project details become more defined called?
a. Burn down chart
b. Release
c. Rolling wave
d. Roadmap
Correct Answer: c) The process of planning in waves as project details become more defined is called
rolling wave.
107. What is definition and prioritization of the nonfunctional requirements by scaling called?
a. Decomposition
b. Staging
c. Stanking
d. Prioritizing
Correct Answer: b) Definition and prioritization of the nonfunctional requirements by scaling is called
staging.
108. Which report should NOT be shared with your stakeholders?
a. Defect reports
b. Status reports
c. Throughput reports
d. SLOC reports
Correct Answer: d) Source Lines of Code (SLOC) reports should not be shared with the stakeholders, as
they are flawed productivity metrics.
109. Which of the following tests verify that units and combinations of units work together to
perform the desired operations?
a. Unit tests
Page | 29 Copyright 2014, Simplilearn, All rights reserved.
b. Component tests
c. Exploratory tests
d. Usability tests
Correct Answer: b) Component tests verify that units and combinations of units work together to
perform the desired operations.
110. A Retrospective can be as short as 15 minutes or as long as 1 hour. The duration of the
Retrospective can be dependent on all of the following EXCEPT:
a. Length of the iteration
b. Level of conflict or controversy
c. Size of the team
d. Seniority of the product owner
Correct Answer: d) Of all the listed options, the length of the retrospective is not dependent on the
seniority of the product owner. The length of the retrospective can be dependent on the length of
iteration, level of conflict or controversy, size of the team, and complexity (of technology, organization
of the team, and relationships with external department).
111. What does 'R' stand for in ARCS, a criterion for evaluating Instructional designs by J.M. Keller?
a. Relevance
b. Repeatable
c. Recording
d. Right
Correct Answer: a) J. M. Keller, an expert in motivation and learning, developed criteria for evaluating
instructional designs. The criteria are Attention, Relevance, Confidence/Competence, Satisfaction—
ARCS for short. Choose activities that help people stay engaged so they don’t drift off (Attention) and
that are relevant to the goal (Relevance). You want activities that people can accomplish successfully
(Confident/Competence). Finally, make sure activities fit into the overall design so people think the
retrospective is a good use of their time (Satisfaction).
112. Which are the three coach styles?
a. Teaching, Coaching, and Advising
b. Coaching, Mentoring, and Advising
c. Coaching, Informing, Advising
d. Mentoring, Teaching, and Advising
Correct Answer: a) The three coach styles are Teaching, Coaching, and Advising.
Page | 30 Copyright 2014, Simplilearn, All rights reserved.
113. Activities are time boxed processes that help the team move through the phases of
retrospective. Activities provide structure to help your team think together and have several
advantages over freewheeling discussion. Activities don’t have to be elaborate or involved to be
effective. Which of the following are NOT examples of activities that are useful in retrospectives?
a. Brainstorming
b. Voting with Dots
c. Pair Interviews
d. Synergy
Correct Answer: d) Activities don’t have to be elaborate or involved to be effective. Examples of
activities that are useful in retrospectives include brainstorming, voting with dots, doing check-ins,
and performing pair interviews.
114. For a Retrospective meeting, the seating arrangement should be such that there is enough
space for people to move comfortably. Which of the following is a preferable seating arrangement
for a retrospective meeting?
a. Circle or semicircle of chairs
b. Theatre style arrangement
c. Tables arranged in U-shape
d. Meeting Room
Correct Answer: a) A circle or semicircle of chairs encourages participation because people can see each
other. Classroom or theater-style arrangements stifle participation. Staring at the back of someone
else’s head isn’t conducive to conversation. Tables can be a physical barrier that becomes a
psychological barrier. Avoid rooms with an immovable conference table in the middle. That big old’
table will inhibit creative collaboration. This isn’t a board meeting, after all. Tables arranged in a U-shape
with a big gulf in the middle create distance and make it hard to move around.
115. Which of the following are MOST helpful in implementing collective code ownership in a team?
a. Version control
b. Pair programming
c. Continuous integration
d. Probability distribution
Page | 31 Copyright 2014, Simplilearn, All rights reserved.
Correct Answer: b) Pair programming is helpful in implementing collective code ownership in a
team.
116. How do you best describe the primary role of an Agile leader?
a. Manage WBS, schedule, and cost of project
b. Manage stakeholders
c. Manage work allocation to team members
d. Manage teams without managing their tasks
Correct Answer: d) Agile leaders do not have to manage the tasks of the team members.
117. Which of the following BEST describes ROTI?
a. Measure of product backlogs remaining
b. Measure of quality of features delivered in an iteration
c. Measure of required effort to deliver in an iteration
d. Measure of effectiveness of the retrospective meeting
Correct Answer: d) Return on Time Invested (ROTI) is used to measure the effectiveness of the
retrospective meetings from the team members' perspective.
118. Which of the following is NOT a characteristic of Agile project manager?
a. Manages daily tasks of the team members
b. Assumes different leadership styles for different stages of team formation
c. Allows team to self-manage
d. Facilitates collaboration
Correct Answer: a) Agile Project Manager does not manage the daily tasks of team members as teams in
Agile are self-organizing.
119. Who performs value point estimating?
a. Finance Team
b. Scrum Team
c. Product Team
d. Development Team
Correct Answer: c) Value point estimation is done by the Product Team.
Page | 32 Copyright 2014, Simplilearn, All rights reserved.
120. In the absence of the Product Owner, who should assume the Product Owner's responsibilities
at the Sprint planning meeting?
a. Scrum Master
b. Team
c. Person selected by the Product Owner
d. Person selected by the team
Correct Answer: a) When the Product Owner is not present, the Scrum Master will take the
responsibility to prepare Product Backlog for the Sprint planning meeting.

Mais conteúdo relacionado

Mais procurados (20)

Pmp4
Pmp4Pmp4
Pmp4
 
Pmp Questions Complete
Pmp Questions CompletePmp Questions Complete
Pmp Questions Complete
 
AXELOS - PRINCE2 Agile® Practitioner
AXELOS - PRINCE2 Agile® PractitionerAXELOS - PRINCE2 Agile® Practitioner
AXELOS - PRINCE2 Agile® Practitioner
 
06 pmp time management exam
06 pmp time  management exam06 pmp time  management exam
06 pmp time management exam
 
An Introduction to Agile
An Introduction to AgileAn Introduction to Agile
An Introduction to Agile
 
07 pmp cost management exam
07 pmp cost management exam07 pmp cost management exam
07 pmp cost management exam
 
Pmp2
Pmp2Pmp2
Pmp2
 
Pmp6
Pmp6Pmp6
Pmp6
 
08 pmp quality management exam
08 pmp quality management exam08 pmp quality management exam
08 pmp quality management exam
 
Waterfall vs Agile : A Beginner's Guide in Project Management
Waterfall vs Agile : A Beginner's Guide in Project ManagementWaterfall vs Agile : A Beginner's Guide in Project Management
Waterfall vs Agile : A Beginner's Guide in Project Management
 
Software Development with Agile Waterfall Hybrid Method
Software Development with Agile Waterfall Hybrid MethodSoftware Development with Agile Waterfall Hybrid Method
Software Development with Agile Waterfall Hybrid Method
 
Why Do So Many Software Projects Fail?
Why Do So Many Software Projects Fail?Why Do So Many Software Projects Fail?
Why Do So Many Software Projects Fail?
 
1
11
1
 
12 pmp procurement management exam
12 pmp procurement management exam12 pmp procurement management exam
12 pmp procurement management exam
 
Pmi sp questions with answers
Pmi sp questions with answersPmi sp questions with answers
Pmi sp questions with answers
 
PMP / Framework 1 2-3
PMP / Framework 1 2-3PMP / Framework 1 2-3
PMP / Framework 1 2-3
 
Pmp test 02
Pmp test 02Pmp test 02
Pmp test 02
 
11 pmp risk management exam
11 pmp risk management exam11 pmp risk management exam
11 pmp risk management exam
 
Pmp3
Pmp3Pmp3
Pmp3
 
Pg mp study notes (updated)
Pg mp study notes (updated)Pg mp study notes (updated)
Pg mp study notes (updated)
 

Destaque

The Power of the Junior
The Power of the JuniorThe Power of the Junior
The Power of the JuniorYves Hanoulle
 
Agile quiz answers
Agile quiz answersAgile quiz answers
Agile quiz answersAltimetrik
 
PMI ACP Classroom Question Paper
PMI ACP Classroom Question PaperPMI ACP Classroom Question Paper
PMI ACP Classroom Question PaperThanh Nguyen
 
PMI-ACP Training Deck
PMI-ACP Training DeckPMI-ACP Training Deck
PMI-ACP Training Deckwjperez0629
 
TCS IT QUIZ QUESTIONS(tcstechbytes2012.blogspot.in)
TCS IT QUIZ QUESTIONS(tcstechbytes2012.blogspot.in)TCS IT QUIZ QUESTIONS(tcstechbytes2012.blogspot.in)
TCS IT QUIZ QUESTIONS(tcstechbytes2012.blogspot.in)Pooja Shankar
 
HD thue server sunflower phong phu
HD thue server sunflower phong phuHD thue server sunflower phong phu
HD thue server sunflower phong phuThanh Nguyen
 
PMI-ACP Case Study
PMI-ACP Case StudyPMI-ACP Case Study
PMI-ACP Case StudyThanh Nguyen
 
Rapid Software Development Process
Rapid Software Development ProcessRapid Software Development Process
Rapid Software Development ProcessThanh Nguyen
 
ISTQB - Foundation Level Syllabus 2011
ISTQB - Foundation Level Syllabus 2011ISTQB - Foundation Level Syllabus 2011
ISTQB - Foundation Level Syllabus 2011Professional Testing
 
PMI-ACP Certifcation Overview
PMI-ACP Certifcation OverviewPMI-ACP Certifcation Overview
PMI-ACP Certifcation OverviewAleem Khan
 
PMI-ACP Lesson 12 Knowledge and Skills Nugget 4
PMI-ACP Lesson 12 Knowledge and Skills Nugget 4PMI-ACP Lesson 12 Knowledge and Skills Nugget 4
PMI-ACP Lesson 12 Knowledge and Skills Nugget 4Thanh Nguyen
 
Agile methodologies in_project_management
Agile methodologies in_project_managementAgile methodologies in_project_management
Agile methodologies in_project_managementPravin Asar
 
PMI-ACP - Agile Framework
PMI-ACP - Agile FrameworkPMI-ACP - Agile Framework
PMI-ACP - Agile FrameworkWafi Mohtaseb
 
Agile project management framework
Agile project management frameworkAgile project management framework
Agile project management frameworkstefanhenry
 

Destaque (20)

Agile Project LifeCycle
Agile Project LifeCycleAgile Project LifeCycle
Agile Project LifeCycle
 
The Power of the Junior
The Power of the JuniorThe Power of the Junior
The Power of the Junior
 
Agile quiz answers
Agile quiz answersAgile quiz answers
Agile quiz answers
 
PMI ACP Classroom Question Paper
PMI ACP Classroom Question PaperPMI ACP Classroom Question Paper
PMI ACP Classroom Question Paper
 
PMI-ACP Training Deck
PMI-ACP Training DeckPMI-ACP Training Deck
PMI-ACP Training Deck
 
TCS IT QUIZ QUESTIONS(tcstechbytes2012.blogspot.in)
TCS IT QUIZ QUESTIONS(tcstechbytes2012.blogspot.in)TCS IT QUIZ QUESTIONS(tcstechbytes2012.blogspot.in)
TCS IT QUIZ QUESTIONS(tcstechbytes2012.blogspot.in)
 
HD thue server sunflower phong phu
HD thue server sunflower phong phuHD thue server sunflower phong phu
HD thue server sunflower phong phu
 
PMI-ACP Case Study
PMI-ACP Case StudyPMI-ACP Case Study
PMI-ACP Case Study
 
Subir a blogger
Subir a bloggerSubir a blogger
Subir a blogger
 
Rapid Software Development Process
Rapid Software Development ProcessRapid Software Development Process
Rapid Software Development Process
 
ISTQB - Foundation Level Syllabus 2011
ISTQB - Foundation Level Syllabus 2011ISTQB - Foundation Level Syllabus 2011
ISTQB - Foundation Level Syllabus 2011
 
PMI-ACP Study Guide
PMI-ACP Study GuidePMI-ACP Study Guide
PMI-ACP Study Guide
 
PMI-ACP Certifcation Overview
PMI-ACP Certifcation OverviewPMI-ACP Certifcation Overview
PMI-ACP Certifcation Overview
 
PMI-ACP Lesson 12 Knowledge and Skills Nugget 4
PMI-ACP Lesson 12 Knowledge and Skills Nugget 4PMI-ACP Lesson 12 Knowledge and Skills Nugget 4
PMI-ACP Lesson 12 Knowledge and Skills Nugget 4
 
Agile methodologies in_project_management
Agile methodologies in_project_managementAgile methodologies in_project_management
Agile methodologies in_project_management
 
ISTQB REX BLACK book
ISTQB REX BLACK bookISTQB REX BLACK book
ISTQB REX BLACK book
 
PMI-ACP - Agile Framework
PMI-ACP - Agile FrameworkPMI-ACP - Agile Framework
PMI-ACP - Agile Framework
 
Agile project management framework
Agile project management frameworkAgile project management framework
Agile project management framework
 
Introduction to Scrum for Project Managers
Introduction to Scrum for Project ManagersIntroduction to Scrum for Project Managers
Introduction to Scrum for Project Managers
 
Programación anual 2016 pfrh
Programación anual 2016 pfrh Programación anual 2016 pfrh
Programación anual 2016 pfrh
 

Semelhante a PMI ACP Classroom Question Paper with Answers

1.A cumulative effort curve for a project generally has an S-shap.docx
1.A cumulative effort curve for a project generally has an S-shap.docx1.A cumulative effort curve for a project generally has an S-shap.docx
1.A cumulative effort curve for a project generally has an S-shap.docxjackiewalcutt
 
Retake Test (toolstest_intro.phptid=6408)Final Score 3.docx
Retake Test (toolstest_intro.phptid=6408)Final Score 3.docxRetake Test (toolstest_intro.phptid=6408)Final Score 3.docx
Retake Test (toolstest_intro.phptid=6408)Final Score 3.docxronak56
 
910 - Questions.pdf
910 - Questions.pdf910 - Questions.pdf
910 - Questions.pdfNguyen Hai
 
ICFAI Projects and Operations Management - Solved assignments and case study ...
ICFAI Projects and Operations Management - Solved assignments and case study ...ICFAI Projects and Operations Management - Solved assignments and case study ...
ICFAI Projects and Operations Management - Solved assignments and case study ...smumbahelp
 
Workbook answers
Workbook answersWorkbook answers
Workbook answersqtntpam
 
Risk 2 simplelearn-exam1-ans
Risk 2 simplelearn-exam1-ansRisk 2 simplelearn-exam1-ans
Risk 2 simplelearn-exam1-ansMohamed Saeed
 
2016 bookmatter ace_thepmi-acp_exam
2016 bookmatter ace_thepmi-acp_exam2016 bookmatter ace_thepmi-acp_exam
2016 bookmatter ace_thepmi-acp_examNguyen Hai
 
Dont Miss these DRI CBCP Dumps
Dont Miss these DRI CBCP DumpsDont Miss these DRI CBCP Dumps
Dont Miss these DRI CBCP DumpsRicherdMie
 
01 pmp introduct to project management exam
01 pmp introduct to project management exam01 pmp introduct to project management exam
01 pmp introduct to project management examJamil Faraj , PMP
 
Pmi acp-q&a-demo-cert magic
Pmi acp-q&a-demo-cert magicPmi acp-q&a-demo-cert magic
Pmi acp-q&a-demo-cert magicEllina Beckman
 
PMP assessment exam 1.1
PMP assessment exam 1.1PMP assessment exam 1.1
PMP assessment exam 1.1Daniel Hucks
 
Question 1  Doing procurement functions electronically is termed.docx
Question 1  Doing procurement functions electronically is termed.docxQuestion 1  Doing procurement functions electronically is termed.docx
Question 1  Doing procurement functions electronically is termed.docxIRESH3
 
Question 1 Artifacts” in the Scrum terminology are the equiva.docx
Question 1 Artifacts” in the Scrum terminology are the equiva.docxQuestion 1 Artifacts” in the Scrum terminology are the equiva.docx
Question 1 Artifacts” in the Scrum terminology are the equiva.docxIRESH3
 
1440 pmp exam question bank
1440 pmp exam question bank1440 pmp exam question bank
1440 pmp exam question bankBaskar El
 
Pmi acp exa- pmi agile certified practitioner
Pmi acp exa- pmi agile certified practitionerPmi acp exa- pmi agile certified practitioner
Pmi acp exa- pmi agile certified practitionerIsabella789
 
Ops 571 ops/571 final exam 100% correct answers
Ops 571 ops/571 final exam 100% correct answersOps 571 ops/571 final exam 100% correct answers
Ops 571 ops/571 final exam 100% correct answersGliven
 

Semelhante a PMI ACP Classroom Question Paper with Answers (20)

1.A cumulative effort curve for a project generally has an S-shap.docx
1.A cumulative effort curve for a project generally has an S-shap.docx1.A cumulative effort curve for a project generally has an S-shap.docx
1.A cumulative effort curve for a project generally has an S-shap.docx
 
Retake Test (toolstest_intro.phptid=6408)Final Score 3.docx
Retake Test (toolstest_intro.phptid=6408)Final Score 3.docxRetake Test (toolstest_intro.phptid=6408)Final Score 3.docx
Retake Test (toolstest_intro.phptid=6408)Final Score 3.docx
 
910 - Questions.pdf
910 - Questions.pdf910 - Questions.pdf
910 - Questions.pdf
 
ICFAI Projects and Operations Management - Solved assignments and case study ...
ICFAI Projects and Operations Management - Solved assignments and case study ...ICFAI Projects and Operations Management - Solved assignments and case study ...
ICFAI Projects and Operations Management - Solved assignments and case study ...
 
Workbook answers
Workbook answersWorkbook answers
Workbook answers
 
Risk 2 simplelearn-exam1-ans
Risk 2 simplelearn-exam1-ansRisk 2 simplelearn-exam1-ans
Risk 2 simplelearn-exam1-ans
 
Pmp sample qa3
Pmp sample qa3Pmp sample qa3
Pmp sample qa3
 
2016 bookmatter ace_thepmi-acp_exam
2016 bookmatter ace_thepmi-acp_exam2016 bookmatter ace_thepmi-acp_exam
2016 bookmatter ace_thepmi-acp_exam
 
Dont Miss these DRI CBCP Dumps
Dont Miss these DRI CBCP DumpsDont Miss these DRI CBCP Dumps
Dont Miss these DRI CBCP Dumps
 
01 pmp introduct to project management exam
01 pmp introduct to project management exam01 pmp introduct to project management exam
01 pmp introduct to project management exam
 
Ctfl at - questões - ingles (1)
Ctfl   at - questões - ingles (1)Ctfl   at - questões - ingles (1)
Ctfl at - questões - ingles (1)
 
Pmi acp-q&a-demo-cert magic
Pmi acp-q&a-demo-cert magicPmi acp-q&a-demo-cert magic
Pmi acp-q&a-demo-cert magic
 
Sad quiz
Sad quizSad quiz
Sad quiz
 
PMP assessment exam 1.1
PMP assessment exam 1.1PMP assessment exam 1.1
PMP assessment exam 1.1
 
Question 1  Doing procurement functions electronically is termed.docx
Question 1  Doing procurement functions electronically is termed.docxQuestion 1  Doing procurement functions electronically is termed.docx
Question 1  Doing procurement functions electronically is termed.docx
 
Question 1 Artifacts” in the Scrum terminology are the equiva.docx
Question 1 Artifacts” in the Scrum terminology are the equiva.docxQuestion 1 Artifacts” in the Scrum terminology are the equiva.docx
Question 1 Artifacts” in the Scrum terminology are the equiva.docx
 
1440 pmp exam question bank
1440 pmp exam question bank1440 pmp exam question bank
1440 pmp exam question bank
 
Pmi acp exa- pmi agile certified practitioner
Pmi acp exa- pmi agile certified practitionerPmi acp exa- pmi agile certified practitioner
Pmi acp exa- pmi agile certified practitioner
 
15 Free PMP Exam Questions
15 Free PMP Exam Questions15 Free PMP Exam Questions
15 Free PMP Exam Questions
 
Ops 571 ops/571 final exam 100% correct answers
Ops 571 ops/571 final exam 100% correct answersOps 571 ops/571 final exam 100% correct answers
Ops 571 ops/571 final exam 100% correct answers
 

Mais de Thanh Nguyen

Building a NFT Marketplace DApp
Building a NFT Marketplace DAppBuilding a NFT Marketplace DApp
Building a NFT Marketplace DAppThanh Nguyen
 
Serverless Architecture 101 ⚡
Serverless Architecture 101 ⚡Serverless Architecture 101 ⚡
Serverless Architecture 101 ⚡Thanh Nguyen
 
The fundamentals of AWS Cloud Security 🛠⛅️🚀
The fundamentals of AWS Cloud Security 🛠⛅️🚀The fundamentals of AWS Cloud Security 🛠⛅️🚀
The fundamentals of AWS Cloud Security 🛠⛅️🚀Thanh Nguyen
 
Migrating Monolithic Applications with the Strangler Pattern
Migrating Monolithic Applications with the Strangler Pattern Migrating Monolithic Applications with the Strangler Pattern
Migrating Monolithic Applications with the Strangler Pattern Thanh Nguyen
 
E301 Elastic Beanstalk PaaS
E301 Elastic Beanstalk PaaSE301 Elastic Beanstalk PaaS
E301 Elastic Beanstalk PaaSThanh Nguyen
 
Serverless Data Lake on AWS
Serverless Data Lake on AWSServerless Data Lake on AWS
Serverless Data Lake on AWSThanh Nguyen
 
SmartChat WhatsApp-clone using AWS Amplify AppSync
SmartChat WhatsApp-clone using AWS Amplify AppSyncSmartChat WhatsApp-clone using AWS Amplify AppSync
SmartChat WhatsApp-clone using AWS Amplify AppSyncThanh Nguyen
 
Introduction to Ethereum Blockchain & Smart Contract
Introduction to Ethereum Blockchain & Smart ContractIntroduction to Ethereum Blockchain & Smart Contract
Introduction to Ethereum Blockchain & Smart ContractThanh Nguyen
 
Amazon AWS Free-Tier
Amazon AWS Free-TierAmazon AWS Free-Tier
Amazon AWS Free-TierThanh Nguyen
 
PMI-ACP Lesson 12 Knowledge and Skills Nugget 3
PMI-ACP Lesson 12 Knowledge and Skills Nugget 3PMI-ACP Lesson 12 Knowledge and Skills Nugget 3
PMI-ACP Lesson 12 Knowledge and Skills Nugget 3Thanh Nguyen
 
PMI-ACP Lesson 12 Knowledge and Skills Nugget 2
PMI-ACP Lesson 12 Knowledge and Skills Nugget 2PMI-ACP Lesson 12 Knowledge and Skills Nugget 2
PMI-ACP Lesson 12 Knowledge and Skills Nugget 2Thanh Nguyen
 
PMI-ACP Lesson 12 Knowledge and Skills Nugget 1
PMI-ACP Lesson 12 Knowledge and Skills Nugget 1PMI-ACP Lesson 12 Knowledge and Skills Nugget 1
PMI-ACP Lesson 12 Knowledge and Skills Nugget 1Thanh Nguyen
 
PMI-ACP Lesson 11 Agile Value Stream Analysis
PMI-ACP Lesson 11 Agile Value Stream AnalysisPMI-ACP Lesson 11 Agile Value Stream Analysis
PMI-ACP Lesson 11 Agile Value Stream AnalysisThanh Nguyen
 
PMI-ACP Lesson 10 Agile Metrics
PMI-ACP Lesson 10 Agile MetricsPMI-ACP Lesson 10 Agile Metrics
PMI-ACP Lesson 10 Agile MetricsThanh Nguyen
 
PMI-ACP Lesson 9 Agile Risk Management
PMI-ACP Lesson 9 Agile Risk ManagementPMI-ACP Lesson 9 Agile Risk Management
PMI-ACP Lesson 9 Agile Risk ManagementThanh Nguyen
 
PMI-ACP Lesson 08 Nugget 2 Agile & Scrum - Value-Based Prioritization
PMI-ACP Lesson 08 Nugget 2 Agile & Scrum - Value-Based PrioritizationPMI-ACP Lesson 08 Nugget 2 Agile & Scrum - Value-Based Prioritization
PMI-ACP Lesson 08 Nugget 2 Agile & Scrum - Value-Based PrioritizationThanh Nguyen
 
PMI-ACP Lesson 08 Nugget 1 Agile & Scrum Value-based Prioritization
PMI-ACP Lesson 08 Nugget 1 Agile & Scrum Value-based PrioritizationPMI-ACP Lesson 08 Nugget 1 Agile & Scrum Value-based Prioritization
PMI-ACP Lesson 08 Nugget 1 Agile & Scrum Value-based PrioritizationThanh Nguyen
 
PMI-ACP Lesson 07 Soft Skills Negotiation
PMI-ACP Lesson 07 Soft Skills NegotiationPMI-ACP Lesson 07 Soft Skills Negotiation
PMI-ACP Lesson 07 Soft Skills NegotiationThanh Nguyen
 
PMI-ACP Lesson 06 Quality
PMI-ACP Lesson 06 QualityPMI-ACP Lesson 06 Quality
PMI-ACP Lesson 06 QualityThanh Nguyen
 
PMI-ACP Lesson 05 Agile Analysis and Design
PMI-ACP Lesson 05 Agile Analysis and DesignPMI-ACP Lesson 05 Agile Analysis and Design
PMI-ACP Lesson 05 Agile Analysis and DesignThanh Nguyen
 

Mais de Thanh Nguyen (20)

Building a NFT Marketplace DApp
Building a NFT Marketplace DAppBuilding a NFT Marketplace DApp
Building a NFT Marketplace DApp
 
Serverless Architecture 101 ⚡
Serverless Architecture 101 ⚡Serverless Architecture 101 ⚡
Serverless Architecture 101 ⚡
 
The fundamentals of AWS Cloud Security 🛠⛅️🚀
The fundamentals of AWS Cloud Security 🛠⛅️🚀The fundamentals of AWS Cloud Security 🛠⛅️🚀
The fundamentals of AWS Cloud Security 🛠⛅️🚀
 
Migrating Monolithic Applications with the Strangler Pattern
Migrating Monolithic Applications with the Strangler Pattern Migrating Monolithic Applications with the Strangler Pattern
Migrating Monolithic Applications with the Strangler Pattern
 
E301 Elastic Beanstalk PaaS
E301 Elastic Beanstalk PaaSE301 Elastic Beanstalk PaaS
E301 Elastic Beanstalk PaaS
 
Serverless Data Lake on AWS
Serverless Data Lake on AWSServerless Data Lake on AWS
Serverless Data Lake on AWS
 
SmartChat WhatsApp-clone using AWS Amplify AppSync
SmartChat WhatsApp-clone using AWS Amplify AppSyncSmartChat WhatsApp-clone using AWS Amplify AppSync
SmartChat WhatsApp-clone using AWS Amplify AppSync
 
Introduction to Ethereum Blockchain & Smart Contract
Introduction to Ethereum Blockchain & Smart ContractIntroduction to Ethereum Blockchain & Smart Contract
Introduction to Ethereum Blockchain & Smart Contract
 
Amazon AWS Free-Tier
Amazon AWS Free-TierAmazon AWS Free-Tier
Amazon AWS Free-Tier
 
PMI-ACP Lesson 12 Knowledge and Skills Nugget 3
PMI-ACP Lesson 12 Knowledge and Skills Nugget 3PMI-ACP Lesson 12 Knowledge and Skills Nugget 3
PMI-ACP Lesson 12 Knowledge and Skills Nugget 3
 
PMI-ACP Lesson 12 Knowledge and Skills Nugget 2
PMI-ACP Lesson 12 Knowledge and Skills Nugget 2PMI-ACP Lesson 12 Knowledge and Skills Nugget 2
PMI-ACP Lesson 12 Knowledge and Skills Nugget 2
 
PMI-ACP Lesson 12 Knowledge and Skills Nugget 1
PMI-ACP Lesson 12 Knowledge and Skills Nugget 1PMI-ACP Lesson 12 Knowledge and Skills Nugget 1
PMI-ACP Lesson 12 Knowledge and Skills Nugget 1
 
PMI-ACP Lesson 11 Agile Value Stream Analysis
PMI-ACP Lesson 11 Agile Value Stream AnalysisPMI-ACP Lesson 11 Agile Value Stream Analysis
PMI-ACP Lesson 11 Agile Value Stream Analysis
 
PMI-ACP Lesson 10 Agile Metrics
PMI-ACP Lesson 10 Agile MetricsPMI-ACP Lesson 10 Agile Metrics
PMI-ACP Lesson 10 Agile Metrics
 
PMI-ACP Lesson 9 Agile Risk Management
PMI-ACP Lesson 9 Agile Risk ManagementPMI-ACP Lesson 9 Agile Risk Management
PMI-ACP Lesson 9 Agile Risk Management
 
PMI-ACP Lesson 08 Nugget 2 Agile & Scrum - Value-Based Prioritization
PMI-ACP Lesson 08 Nugget 2 Agile & Scrum - Value-Based PrioritizationPMI-ACP Lesson 08 Nugget 2 Agile & Scrum - Value-Based Prioritization
PMI-ACP Lesson 08 Nugget 2 Agile & Scrum - Value-Based Prioritization
 
PMI-ACP Lesson 08 Nugget 1 Agile & Scrum Value-based Prioritization
PMI-ACP Lesson 08 Nugget 1 Agile & Scrum Value-based PrioritizationPMI-ACP Lesson 08 Nugget 1 Agile & Scrum Value-based Prioritization
PMI-ACP Lesson 08 Nugget 1 Agile & Scrum Value-based Prioritization
 
PMI-ACP Lesson 07 Soft Skills Negotiation
PMI-ACP Lesson 07 Soft Skills NegotiationPMI-ACP Lesson 07 Soft Skills Negotiation
PMI-ACP Lesson 07 Soft Skills Negotiation
 
PMI-ACP Lesson 06 Quality
PMI-ACP Lesson 06 QualityPMI-ACP Lesson 06 Quality
PMI-ACP Lesson 06 Quality
 
PMI-ACP Lesson 05 Agile Analysis and Design
PMI-ACP Lesson 05 Agile Analysis and DesignPMI-ACP Lesson 05 Agile Analysis and Design
PMI-ACP Lesson 05 Agile Analysis and Design
 

Último

Leveraging Gap Analysis for Continuous Improvement
Leveraging Gap Analysis for Continuous ImprovementLeveraging Gap Analysis for Continuous Improvement
Leveraging Gap Analysis for Continuous ImprovementCIToolkit
 
From Red to Green: Enhancing Decision-Making with Traffic Light Assessment
From Red to Green: Enhancing Decision-Making with Traffic Light AssessmentFrom Red to Green: Enhancing Decision-Making with Traffic Light Assessment
From Red to Green: Enhancing Decision-Making with Traffic Light AssessmentCIToolkit
 
Digital PR Summit - Leadership Lessons: Myths, Mistakes, & Toxic Traits
Digital PR Summit - Leadership Lessons: Myths, Mistakes, & Toxic TraitsDigital PR Summit - Leadership Lessons: Myths, Mistakes, & Toxic Traits
Digital PR Summit - Leadership Lessons: Myths, Mistakes, & Toxic TraitsHannah Smith
 
The Final Activity in Project Management
The Final Activity in Project ManagementThe Final Activity in Project Management
The Final Activity in Project ManagementCIToolkit
 
How Technologies will change the relationship with Human Resources
How Technologies will change the relationship with Human ResourcesHow Technologies will change the relationship with Human Resources
How Technologies will change the relationship with Human ResourcesMassimo Canducci
 
Mind Mapping: A Visual Approach to Organize Ideas and Thoughts
Mind Mapping: A Visual Approach to Organize Ideas and ThoughtsMind Mapping: A Visual Approach to Organize Ideas and Thoughts
Mind Mapping: A Visual Approach to Organize Ideas and ThoughtsCIToolkit
 
Advancing Enterprise Risk Management Practices- A Strategic Framework by Naga...
Advancing Enterprise Risk Management Practices- A Strategic Framework by Naga...Advancing Enterprise Risk Management Practices- A Strategic Framework by Naga...
Advancing Enterprise Risk Management Practices- A Strategic Framework by Naga...Nagarjuna Reddy Aturi
 
Exploring Variable Relationships with Scatter Diagram Analysis
Exploring Variable Relationships with Scatter Diagram AnalysisExploring Variable Relationships with Scatter Diagram Analysis
Exploring Variable Relationships with Scatter Diagram AnalysisCIToolkit
 
Flowcharting: The Three Common Types of Flowcharts
Flowcharting: The Three Common Types of FlowchartsFlowcharting: The Three Common Types of Flowcharts
Flowcharting: The Three Common Types of FlowchartsCIToolkit
 
The Role of Box Plots in Comparing Multiple Data Sets
The Role of Box Plots in Comparing Multiple Data SetsThe Role of Box Plots in Comparing Multiple Data Sets
The Role of Box Plots in Comparing Multiple Data SetsCIToolkit
 
BoSUSA23 | Chris Spiek & Justin Dickow | Autobooks Product & Engineering
BoSUSA23 | Chris Spiek & Justin Dickow | Autobooks Product & EngineeringBoSUSA23 | Chris Spiek & Justin Dickow | Autobooks Product & Engineering
BoSUSA23 | Chris Spiek & Justin Dickow | Autobooks Product & EngineeringBusiness of Software Conference
 
The Role of Histograms in Exploring Data Insights
The Role of Histograms in Exploring Data InsightsThe Role of Histograms in Exploring Data Insights
The Role of Histograms in Exploring Data InsightsCIToolkit
 
HOTEL MANAGEMENT SYSTEM PPT PRESENTATION
HOTEL MANAGEMENT SYSTEM PPT PRESENTATIONHOTEL MANAGEMENT SYSTEM PPT PRESENTATION
HOTEL MANAGEMENT SYSTEM PPT PRESENTATIONsivani14565220
 
Adapting to Change: Using PEST Analysis for Better Decision-Making
Adapting to Change: Using PEST Analysis for Better Decision-MakingAdapting to Change: Using PEST Analysis for Better Decision-Making
Adapting to Change: Using PEST Analysis for Better Decision-MakingCIToolkit
 
Operations Management -- Sustainability and Supply Chain Management.pdf
Operations Management -- Sustainability and Supply Chain Management.pdfOperations Management -- Sustainability and Supply Chain Management.pdf
Operations Management -- Sustainability and Supply Chain Management.pdfcoolsnoopy1
 
Characteristics of professional in professional ethics
Characteristics of professional in professional ethicsCharacteristics of professional in professional ethics
Characteristics of professional in professional ethicsmourale176
 
Overview PMI Infinity - UK Chapter presentation
Overview PMI Infinity - UK Chapter presentationOverview PMI Infinity - UK Chapter presentation
Overview PMI Infinity - UK Chapter presentationPMIUKChapter
 
Hajra Karrim: Transformative Leadership Driving Innovation and Efficiency in ...
Hajra Karrim: Transformative Leadership Driving Innovation and Efficiency in ...Hajra Karrim: Transformative Leadership Driving Innovation and Efficiency in ...
Hajra Karrim: Transformative Leadership Driving Innovation and Efficiency in ...dsnow9802
 
Management 11th Edition - Chapter 11 - Adaptive Organizational Design
Management 11th Edition - Chapter 11 - Adaptive Organizational DesignManagement 11th Edition - Chapter 11 - Adaptive Organizational Design
Management 11th Edition - Chapter 11 - Adaptive Organizational Designshakkardaddy
 

Último (19)

Leveraging Gap Analysis for Continuous Improvement
Leveraging Gap Analysis for Continuous ImprovementLeveraging Gap Analysis for Continuous Improvement
Leveraging Gap Analysis for Continuous Improvement
 
From Red to Green: Enhancing Decision-Making with Traffic Light Assessment
From Red to Green: Enhancing Decision-Making with Traffic Light AssessmentFrom Red to Green: Enhancing Decision-Making with Traffic Light Assessment
From Red to Green: Enhancing Decision-Making with Traffic Light Assessment
 
Digital PR Summit - Leadership Lessons: Myths, Mistakes, & Toxic Traits
Digital PR Summit - Leadership Lessons: Myths, Mistakes, & Toxic TraitsDigital PR Summit - Leadership Lessons: Myths, Mistakes, & Toxic Traits
Digital PR Summit - Leadership Lessons: Myths, Mistakes, & Toxic Traits
 
The Final Activity in Project Management
The Final Activity in Project ManagementThe Final Activity in Project Management
The Final Activity in Project Management
 
How Technologies will change the relationship with Human Resources
How Technologies will change the relationship with Human ResourcesHow Technologies will change the relationship with Human Resources
How Technologies will change the relationship with Human Resources
 
Mind Mapping: A Visual Approach to Organize Ideas and Thoughts
Mind Mapping: A Visual Approach to Organize Ideas and ThoughtsMind Mapping: A Visual Approach to Organize Ideas and Thoughts
Mind Mapping: A Visual Approach to Organize Ideas and Thoughts
 
Advancing Enterprise Risk Management Practices- A Strategic Framework by Naga...
Advancing Enterprise Risk Management Practices- A Strategic Framework by Naga...Advancing Enterprise Risk Management Practices- A Strategic Framework by Naga...
Advancing Enterprise Risk Management Practices- A Strategic Framework by Naga...
 
Exploring Variable Relationships with Scatter Diagram Analysis
Exploring Variable Relationships with Scatter Diagram AnalysisExploring Variable Relationships with Scatter Diagram Analysis
Exploring Variable Relationships with Scatter Diagram Analysis
 
Flowcharting: The Three Common Types of Flowcharts
Flowcharting: The Three Common Types of FlowchartsFlowcharting: The Three Common Types of Flowcharts
Flowcharting: The Three Common Types of Flowcharts
 
The Role of Box Plots in Comparing Multiple Data Sets
The Role of Box Plots in Comparing Multiple Data SetsThe Role of Box Plots in Comparing Multiple Data Sets
The Role of Box Plots in Comparing Multiple Data Sets
 
BoSUSA23 | Chris Spiek & Justin Dickow | Autobooks Product & Engineering
BoSUSA23 | Chris Spiek & Justin Dickow | Autobooks Product & EngineeringBoSUSA23 | Chris Spiek & Justin Dickow | Autobooks Product & Engineering
BoSUSA23 | Chris Spiek & Justin Dickow | Autobooks Product & Engineering
 
The Role of Histograms in Exploring Data Insights
The Role of Histograms in Exploring Data InsightsThe Role of Histograms in Exploring Data Insights
The Role of Histograms in Exploring Data Insights
 
HOTEL MANAGEMENT SYSTEM PPT PRESENTATION
HOTEL MANAGEMENT SYSTEM PPT PRESENTATIONHOTEL MANAGEMENT SYSTEM PPT PRESENTATION
HOTEL MANAGEMENT SYSTEM PPT PRESENTATION
 
Adapting to Change: Using PEST Analysis for Better Decision-Making
Adapting to Change: Using PEST Analysis for Better Decision-MakingAdapting to Change: Using PEST Analysis for Better Decision-Making
Adapting to Change: Using PEST Analysis for Better Decision-Making
 
Operations Management -- Sustainability and Supply Chain Management.pdf
Operations Management -- Sustainability and Supply Chain Management.pdfOperations Management -- Sustainability and Supply Chain Management.pdf
Operations Management -- Sustainability and Supply Chain Management.pdf
 
Characteristics of professional in professional ethics
Characteristics of professional in professional ethicsCharacteristics of professional in professional ethics
Characteristics of professional in professional ethics
 
Overview PMI Infinity - UK Chapter presentation
Overview PMI Infinity - UK Chapter presentationOverview PMI Infinity - UK Chapter presentation
Overview PMI Infinity - UK Chapter presentation
 
Hajra Karrim: Transformative Leadership Driving Innovation and Efficiency in ...
Hajra Karrim: Transformative Leadership Driving Innovation and Efficiency in ...Hajra Karrim: Transformative Leadership Driving Innovation and Efficiency in ...
Hajra Karrim: Transformative Leadership Driving Innovation and Efficiency in ...
 
Management 11th Edition - Chapter 11 - Adaptive Organizational Design
Management 11th Edition - Chapter 11 - Adaptive Organizational DesignManagement 11th Edition - Chapter 11 - Adaptive Organizational Design
Management 11th Edition - Chapter 11 - Adaptive Organizational Design
 

PMI ACP Classroom Question Paper with Answers

  • 1. Page | 1 Copyright 2014, Simplilearn, All rights reserved. Full length ACP Classroom Simulation Test 1. Forecasting the financial value of a theme is the responsibility of: a. Analysts b. Product Owner c. Project Manager d. Sponsor Correct Answer: b) Forecasting the financial value of a theme is the responsibility of the product owner. 2. Which of the following explains 'Retained Revenue'? a. Revenue due to a new opportunity b. Additional incremental revenue from existing customers c. Revenue, an organization will lose if the project is not performed d. Revenue due to streamlining a process Correct Answer: (c) Retained revenue refers to the revenue an organization will lose if the project is not performed. 3. You are part of the team that developed software for the organization's own use in serving the hospital customers. At one point, the CEO realizes that with some enhancements the software could be used to provide the same services to health insurers. The team is asked to make the changes and is able to bring an entirely new source of revenue into the company because of the new software enabled. Under what revenue stream is this feature classified? a. New Revenue b. Incremental Revenue c. Retained Revenue d. Operational Efficiencies Correct Answer: a) New Revenue is the revenue from a new opportunity after a project is completed. 4. Which of the following are the responsibilities of the Scrum Master? a. Achieving initial and ongoing funding for the project b. Teaching the Product Owner how to maximize ROI and the objectives c. Being responsible for developing the functionality of the product d. Removing the barriers between the customer and the Product Owner Correct Answer: b) The Scrum Master is responsible for teaching the Product Owner how to maximize ROI and the objectives.
  • 2. Page | 2 Copyright 2014, Simplilearn, All rights reserved. 5. In agile, which of the following defines the splitting of a story or a feature into smaller, easier-to- estimate pieces? a. Decomposition b. Disaggregation c. Theme d. Epic Correct Answer: b) Disaggregation refers to splitting a story or feature into smaller, easier-to-estimate pieces. 6. Which one of the following phases of project management includes developing a capability and/or feature-based release plan to deliver the vision? a. Envision b. Speculate c. Explore d. Adapt Correct Answer: b) Speculate phase includes developing a capability and/or feature based release plan to deliver the vision. 7. A story point is a unit of measure to express the estimated difficulty or effort of a user story. What is the unit of measure used here? a. Days b. Years c. Points d. Iterations Correct Answer: a) A story point is a unit of measure to express the estimated difficulty or effort of a user story and might be estimated using days. 8. In a complete Product Planning structure, which of the following denotes the product planning structure with a medium range timeframe, story level of detail, and capability commitment? a. Release b. Story c. Roadmap d. Wave Correct Answer: d) Wave is the Product Planning structure with Medium range time frame (3 months) with Story level capability and Capability commitment.
  • 3. Page | 3 Copyright 2014, Simplilearn, All rights reserved. 9. According to DeMarco, fragmented knowledge workers may look busy but a lot of their business is just thrashing. The minimum cost penalty is – a. 15% b. 10% c. 5% d. 25% Correct Answer: a) According to research performed by DeMarco, the minimum cost penalty of thrashing is 15%. 10. In a project, all of the user stories are estimated and the sum of those estimates is 100 story points. Based on past experience, it is known that the team’s velocity is 9 story points per two-week iteration. How many iterations does the project need to complete the user stories? a. 9 b. 11 c. 1 d. 90 Correct Answer: b) Iterations = 100/9 = 11.1 11. Who should participate in Iteration Planning? a. Customer, Iteration Manager, Developers, and Testers b. Product Manager, Iteration Manager, Developers, and Testers c. Entire Project Team d. Product Specialists, Customer, Iteration Manager, Developers, and Testers Correct Answer: c) The entire project team—product manager, product specialists, customers, developers, testers, iteration manager, project leader—should participate in the iteration planning session as it provides everyone with the context for work to be accomplished during the iteration. Functional manager participation can help the team better understand strategic priority issues. The functional manager demonstrates commitment to and support of the project. 12. Which of the following statements is false regarding Agility? a. Agility is the ability to balance flexibility and stability b. Agility is the ability to both create and respond to change to profit in a turbulent business environment c. Agility is avoiding planning and lack of structure
  • 4. Page | 4 Copyright 2014, Simplilearn, All rights reserved. d. "Agility is ability to deliver customer value while dealing with the unpredictability and dynamism of an inherent project " Correct Answer: c) Agility is not an excuse to avoid planning or not having structure. 13. Technical debt is the gap between a product's actual Cost of Change (CoC) and its optimal CoC. Managing technical debt helps ensure reliable delivery today and ready adaptation to tomorrow's customer needs. When would technical debt not occur? a. During Initial Development b. Ongoing Maintenance c. During Enhancement d. During closing Correct Answer: d) Technical debt can arise during initial development, ongoing maintenance (keeping a product at its original state), or enhancement (adding functionality) and not during closing. 14. The Levels of Listening by Whitworth states 3 Levels of listening. What does the third level, viz. Global listening refer to? a. A hardwired connection is established between the coach and the speaker b. The coach uses everything in the environment, viz. speaker's tone of voice, posture, etc., when listening at this level c. The coach hears the speaker's words attentively d. The coach only hears the global sounds and not the speaker's words Correct Answer: b) The coach uses everything in the environment when listening at Level III. The speaker’s tone of voice, posture, changes in the room temperature, noises—all of these things are noticed and used by the coach. 15. Team 1 has been asked to complete work on Item 10 story and deliver it to Team 2 so that they can initiate work on Item 12 story, which is dependent on completion of Item 10 story. The leader of Team 1 decides to add a buffer that protects the start date on Item 12 story against delays in the completion of Item 10 story. This buffer is known as a. Feeding Buffer b. Iteration Buffer c. Story Buffer d. Release Buffer Correct Answer: a) The Feeding buffer protects the start date on Item 12 story against delays in the completion of Item 10 story.
  • 5. Page | 5 Copyright 2014, Simplilearn, All rights reserved. 16. A meeting where a team reflects and looks back to adapt and learn to do future projects better is popularly known as: a. Retrospective b. Planning c. Review session d. Status Meeting Correct Answer: a) Retrospective is the meeting where a team reflects and looks back to adapt and learn to do future projects better. 17. In the agile methodology, decisions are framed focusing on which of the following? a. Identifying the types of decisions that need to be made b. A team of stakeholders involved in the decision making process c. Delegating the decision making process to the developers only d. Senior manager making the decision Correct Answer: b) In agile methodology, decisions are framed by a team of stakeholders involved in the decision making process. 18. When should be the BEST time for the team to estimate a task? a. Throughout the Iteration b. During Iteration Planning c. Task estimates are decided by the Scrum Master d. At the time of Iteration Planning as well as during the iteration Correct Answer: d) Project Team will estimate a task at the time of Iteration Planning as well as during the iteration planning. 19. Which of the following charts shows the number of tasks completed each day of the iteration to monitor the progress? a. Progression charts b. Task Burn down chart c. Task check off charts d. Task charts
  • 6. Page | 6 Copyright 2014, Simplilearn, All rights reserved. Correct Answer: b) Many agile practitioners use a task burn down chart, which shows the number of tasks completed each day of the iteration to monitor progress. 20. Self-organization implies a reliance on internal motivation of the team rather than external motivation. This is referred to as: a. Delegatory management b. Measurement based management c. Democratic management d. Autocratic management Correct Answer: a) Self-organization implies a reliance on internal motivation of the team rather than external motivation (i.e., a measurement target). Author Austin calls this delegatory management as contrasted with measurement-based management. He goes on to say, "measurement-based management is in conflict with delegatory management. There is a negative interaction because of the implicit message of distrust that a measurement system conveys by the fact of its existence." 21. Which of the following describes error-feedback ratio? a. Time spent to fix the hard bugs b. Number of defects detected in an iterative cycle c. Number of errors predicted d. Number of new defects created when fixing existing known defects Correct Answer: d) Error-feedback ratio is the number of new defects created when fixing existing known defects. 22. Which is the Japanese term for thin slices of raw fish, a Scrum technique that requires every piece of functionality be completed fully by the developers? a. Lean b. Sashimi c. Ishikawa diagram d. Ability Correct Answer: b) Sashimi is the Japanese term that requires every piece of functionality be completed fully by the developers.
  • 7. Page | 7 Copyright 2014, Simplilearn, All rights reserved. 23. How would risk be managed on an Agile project? a. Decision tree b. Risk-adjusted backlog c. Risk assessment matrix d. Risk management plan Correct Answer: b) On an Agile project, risk would be managed using the risk-adjusted backlog. 24. Which methodology attempts to remove project uncertainty? a. Waterfall b. XP c. Kanban d. Scrum Correct Answer: a) Agile embraces uncertainty, but waterfall tries to manage it by removing it. 25. Which of the following charts shows how much work remains on an iteration and how much work has been completed so far? a. Iteration burn down chart b. Combined burn-down chart c. Daily burn down chart d. Burn up chart Correct Answer: b) A Combined burn-down chart shows how much work remains on an iteration and how much work has been completed so far. 26. A story that was planned as one story point, actually took two days to complete. How much does it contribute to the velocity when calculated at the end of the iteration? a. One Point b. Three Points c. Two Points d. Cannot be calculated Correct Answer: a) Only the original planned effort of one story point is used to calculate the velocity at the end of the iteration. 27. A good approach for small stories is to combine them into larger stories that represent from about a half-day to several days of work. The combined story is given a name and is scheduled and worked on just like any other story. Which of the following is an example of a small story?
  • 8. Page | 8 Copyright 2014, Simplilearn, All rights reserved. a. Major database architecture changes b. Updating over one hundred automated reports c. User interface changes d. Status updates Correct Answer: c) Bug reports and user interface changes are common examples of stories that are too small for an individual story. 28. Who specifies Acceptance Tests in an Agile Project? a. Customer b. Programmer c. Developer d. Product Manager Correct Answer: a) As the software is being written to fulfil a vision held by the customer, the acceptance tests need to be specified by the customer. The customer can work with a programmer or tester to actually create the tests, but minimally the customer needs to specify the tests that will be used to know when a story has been correctly developed. 29. Which methodology uses the idea of amplifying learning? a. Kanban b. Scrum c. XP d. Lean Correct Answer: d) Lean is based on the principles "eliminate waste, amplify learning, decide as late as possible, deliver as fast as possible, empower the team, build integrity in, and see the whole". 30. When can a plan be changed in Agile Management? a. At the end of the Iteration b. When we have learned something new c. At the Daily Meeting d. You cannot change once the plan is prepared Correct Answer: b) In Agile, you can change the plan when something new is learned or when it is known that a mistake is to be avoided.
  • 9. Page | 9 Copyright 2014, Simplilearn, All rights reserved. 31. You have been assigned a New Project that is large, complex, and uncertain. As a Project Manager, you will be using agile project management. Which of the following will you select while creating your team? a. Team is expandable with the project b. Large team c. Functional manager is responsible for the team d. Small experienced team Correct Answer: d) As per Agile methodology, it is best to work with small teams staffed by talented and experienced people and increase the number of team members only when necessary. 32. Assuming one-week iterations and a team of four developers, how many iterations will it take for the team to complete a project with 27 story points if they have a velocity of 4? a. 4 b. 6 c. 7 d. 24 Correct Answer: c) Number of Iterations = 27/4 = 6.75 ~7 33. Which of the following defines a complex story? a. A user story that contains multiple stories b. A user story that users can mark as inactive c. A user story that is large by nature and cannot easily be dissected into smaller stories d. A user story that is not executable Correct Answer: c) A complex story is a user story that is large by nature and cannot easily be dissected into smaller stories. 34. Which of the following is NOT an attribute of a Good Story? a. Testable b. Large c. Independent d. Negotiable Correct Answer: b) A good story has six attributes - Independent, Negotiable, Valuable to users or customers, Estimable, Small, and Testable.
  • 10. Page | 10 Copyright 2014, Simplilearn, All rights reserved. 35. When a team of people work together, the team goes through a specific sequence of group dynamics called the Tuckman model. Which of the following depicts the correct sequence of this process? a. Forming, norming, performing, storming b. Forming, storming, norming, performing c. Forming, performing, storming, norming d. Storming, norming, performing, forming Correct Answer: b) The Tuckman model has the following stages: forming, storming, norming, performing. 36. Name the XP technique where two people work: one person who codes is the driver and the other person who thinks is the navigator? a. Pair Programming b. Planning Poker c. Planning Technique d. Coding Technique Correct Answer: a) Pair Programming is when two developers work on the same code together to improve efficiency. 37. An informative and collaborative workspace makes information easily communicated by just being in the room. Of the following, which would not be found in an informative workspace? a. Big Visible Charts b. Process Improvement Charts c. Hand Drawn Charts d. Project Charter Correct Answer: d) Big Visible Charts, Process Improvement Charts, Hand Drawn Charts are all examples that might be found in an informative workspace. A project charter would be a project document that would be stored in the project archive and not visible to the team in a workspace. 38. There are different types of Retrospectives. These are Release Retrospectives, Project Retrospectives, Iteration Retrospectives, and Surprise Retrospectives. What are Surprise Retrospectives? a. Are conducted when an unplanned event changes the situation
  • 11. Page | 11 Copyright 2014, Simplilearn, All rights reserved. b. Are conducted at the end of each iteration c. Are conducted half way of each project d. Are suggested by the Scrum Master Correct Answer: a) Surprise Retrospective is conducted when an unplanned event changes the situation. 39. The red team finished 38 story points in their last two-week iteration. The blue team has half as many developers on a different project and completed 38 story points in their last two-week iteration. What can be determined from this information? a. The story points of one team are not comparable to the story points of any other team b. Team A is twice as productive as Team B c. Team A should have more people in the team d. Team B has the management support Correct Answer: a) The story points of one team are not comparable to the story points of any other team. 40. Four developers are estimating a story. The estimates provided are two, three, six, and ten story points. Which estimate should be used? a. 2 story point b. 6 story point c. 10 story point d. None of the present estimates until the team discusses how to get the estimates closer together Correct Answer: d) None of the present estimates, two, three, six, or ten, until the team discusses how to get the estimates closer together. 41. A stand-up meeting is conducted in the morning every day. Each person describes the new information that the team should know. What is NOT discussed? a. What did I do yesterday? b. What are my tasks for the coming week? c. What do I plan to do today? d. What issues are preventing my progress? Correct Answer: b) In the daily stand-up meeting, the tasks for next week would not be discussed, only yesterday's activity, today's activity, and current issues are discussed. 42. Which of the following describes a task board?
  • 12. Page | 12 Copyright 2014, Simplilearn, All rights reserved. a. Is on a white board b. Is a tool to show the project trends c. Organizes work and communicates what work is left d. Displays the velocity Correct Answer: c) The task board organizes work and communicates what work is left. 43. Some stakeholders are interested in viewing the project progress, but are not interested in the details. Which of the following should you share with these stakeholders? a. Weekly demo b. Vision Statement c. Release plan d. Burn up chart Correct Answer: d) The burn up chart shows progress towards project completion and the expected completion date. 44. Which of the following is NOT included in the story cards information'? a. Estimated Value Points b. Story description c. Story dependencies d. Velocity Correct Answer: d) Story cards information includes story name, story description, estimated work effort, estimated value points, requirements uncertainty, story dependencies, and acceptance tests. Velocity is the number of user stories that are delivered in iteration. 45. Which of the following will NOT assist in Critical Problem solving during the project? a. Ask probing questions b. Use active listening c. Use reflective listening d. Injecting ideas Correct Answer: d) During critical problem solving, you can ask probing questions, use active and reflective listening. Lead to an answer but one should avoid injecting their ideas. 46. One of your stakeholders wants more detail than the vision statement provides, but not the overwhelming detail of the release and iteration plans. Which of the following progress report will you share with this stakeholder?
  • 13. Page | 13 Copyright 2014, Simplilearn, All rights reserved. a. Roadmap b. Status email c. Iteration plan d. Productivity chart Correct Answer: a) Some stakeholders may want more detail than the vision statement provides, but not the overwhelming detail of the release and iteration plans. For these stakeholders, consider maintaining a document or slide deck that summarizes planned releases and the significant features in each one." 47. Every team needs to constantly evaluate and make appropriate adaptations in the following four areas: a. Product value, Product quality, Team performance, Project status b. Product value, Product quality, Team performance, Organization status c. Product quality, Team performance, Project status, Project deliverables d. Product value, Product Features, Team performance, Project status Correct Answer: a) Every team needs to constantly evaluate and make appropriate adaptations in the following four areas: product value, product quality, team performance, and project status. 48. Which of the following is NOT true about the Iteration Demos? a. Demonstrate the team’s progress b. Realistically report progress c. Shown only to a select set of stakeholders d. Solicit feedback from customers Correct Answer: c) Iteration demos are not shown only to select set of stakeholders, but all stakeholders and are invited to provide feedback. 49. During which project management phase are the product stories delivered? a. Envision b. Speculate c. Explore d. Adapt Correct Answer: c) It is during the Explore phase, the product stories are delivered. This phase involves planning and delivering tested stories in a short iteration, constantly seeking to reduce the risk, and uncertainty of the project. 50. What do you mean by Throughput?
  • 14. Page | 14 Copyright 2014, Simplilearn, All rights reserved. a. The amount of production over time b. The number of features the team can develop in a particular amount of time. c. The number of features released during a Release d. The number of defects rectified during a Release Correct Answer: b) Throughput is the number of features the team can develop in a particular amount of time. 51. Which of the following does NOT explain Refactoring? a. Organizes the working code b. Improves code quality c. Makes the code more maintainable d. Reduces bugs dramatically Correct Answer: d) Refactoring is the reorganization of code to make it more organized, of higher quality, and more maintainable. 52. If your release is 12 iterations away, your velocity is 14 points, your risk exposure is 1 iteration and with a 10% chance, how many points will you have finished? a. 154 b. 110 c. 86 d. 92 Correct Answer: a) Using the following formula, risk_adjusted_points_remaining = (iterations_remaining - risk_exposure) * velocity / risk_multiplier --> points remaining = (12 - 1) * 14 = 154 points 10 percent chance: 154 / 1 = 154 points. 53. The retrospective meeting on previous iteration should last not more than a. 30 minutes b. 60 minutes c. 10 minutes d. 5 minutes Correct Answer: b) The retrospective meeting on previous iteration should be maximum of one hour. 54. Which of the following describes a story?
  • 15. Page | 15 Copyright 2014, Simplilearn, All rights reserved. a. "Full-screen demo option for a job fair" b. "Automate integration build" c. "Deploy to staging server outside the firewall" d. "Improve performance" Correct Answer: a) "Full-screen demo option for a job fair" is a story. “Automate integration build” does not represent customer value, hence not a story. “Deploy to staging server outside the firewall” describes implementation details rather than an end result, and it doesn’t use customer terminology, hence not a story. “Improve performance” has no clear completion criteria, hence not a story. 55. Which of the following is NOT a principle from the Agile Manifesto? a. Responding to change b. Customer collaboration c. Technical excellence d. Working software Correct Answer: c) Technical excellence is not a principle from the Agile Manifesto. 56. In a design-the-box activity, the objective is to design the product box—front and back. Which of the following would not be included in the activity? a. Graphic design b. Feature description c. Operating requirements d. Competitor's product name and features Correct Answer: d) In a design-the-box activity, the objective is to design the product box—front and back and would include the graphic design, feature description, and operating requirements. 57. In XP, the code goes through four levels of completion. Which of the following states the right sequence? a. Broken, Build, Ready for demo, Ready to release b. Build, Ready for demo, Broken, Ready to release c. Build, Ready for demo, Ready to release, Broken d. Broken, Build, Ready to release, Ready for demo Correct Answer: a) The four levels of completion are broken, build, ready for demo, and ready to release. 58. Which of the following factors will not assist in improving the project velocity?
  • 16. Page | 16 Copyright 2014, Simplilearn, All rights reserved. a. Pay down technical debt b. Offload programmer duties c. Reduce customer involvement d. Provide needed resources Correct Answer: c) Improving customer involvement will assist in improving the project velocity. 59. What financial return parameter will be BEST for comparing the values of two different cash flow streams? a. Internal Rate of Return b. Payback Period c. Discounted Payback Period d. Compound Interest Correct Answer: a) Internal Rate of Return (IRR) is used to express the return on project in % when comparing the two different cash flow streams. 60. What is the relative contribution of feature X to the project if it has a value of 12 and the total value of all features is 35? a. 0.38 b. 0.34 c. 2.91 d. 14.91 Correct Answer: b) To calculate the relative contribution of each feature, divide its value by the sum of the Total Value of all features. Hence, relative contribution of feature X = 12/35 = 0.34. 61. Which of the following is NOT true about Retrospective? e. Decides how the team will work together to complete the project f. Reflects on past work and learn from the project history g. Development process is driven by the team h. Selects team members for the next project Correct Answer: d) Retrospective is a meeting where a team learns from the project history, how the team worked together so far, and what can be learned from the progress on the project do far to continue a success development process driven by the team.
  • 17. Page | 17 Copyright 2014, Simplilearn, All rights reserved. 62. Feature X has a value of 12 and the total value of all features is 35. If the feature is estimated to cost 56%, what is the priority of this feature using relative weighting? a. 0.34 b. 0.61 c. 1.64 d. 0.625 Correct Answer: b) The priority of the feature is determined by dividing the priority % by the cost %. Hence the answer = (12/35)/(0.56) = 0.61. 63. What is MOST true about participatory decision making? a. It is a technique that involves all the affected parties b. It is just a meeting with no outcomes c. It only involves the customer and the Product Manager d. It is a technique based on the wishes of the Scrum Master Correct Answer: a) Participatory decision making is a technique that involves all the affected parties. 64. If we plan to work in a two-week iteration with thirteen iterations during the project and with the team velocity twenty story points or ideal days per iterations, what will the size of the total project in story points be? a. 13 b. 20 c. 260 d. 200 Correct Answer: c) The size of the total project will be 13 x 20 = 260 story points 65. Which of the following is NOT true regarding scope in Agile projects? a. Scope in Agile is primarily a function of "rolling wave" planning b. "Scope creep" doesn't exist in Agile projects c. Scope is controlled through the use of the product backlog d. Scope is validated by the Product Manager Correct Answer: d) Scope is validated by the customer, not the product manager. 66. How is the Retrospective meeting BEST conducted?
  • 18. Page | 18 Copyright 2014, Simplilearn, All rights reserved. a. Set the stage, Gather data, Generate Insights, Decide on what to do, Close the Retrospective b. Gather data, Generate Insights, Decide on what to do, Set the stage, Close the Retrospective c. Set the stage, Gather data, Decide on what to do, Generate Insights, Close the Retrospective d. Decide on what to do, Set the stage, Gather data, Generate Insights, Close the Retrospective Correct Answer: a) The correct sequence is set the stage, gather data, generate Insights, decide on what to do, and close the retrospective. 67. In an Agile project, what are the horizons in the planning onion that the agile teams are involved with during the project? a. Strategy, Portfolio, Product b. Product, Release, Iteration c. Release, Iteration, Day d. Product, Iteration, Day Correct Answer: c) Agile teams should be concerned with the horizons of release, iteration, and day. 68. What is the main purpose of a group of stories, an iteration, or a release known as: a. Theme b. Epic c. Story d. Combined Story Correct Answer: a) Theme is the main purpose behind a group of stories, an iteration, or a release. 69. A project uses a version control system to mediate changes, which includes updating codes, testing the code, and then checking-in the changes, which may occur several times in a day. This process is known as? a. Version Control Management b. Continuous Integration c. Simple Integration d. Configuration Management Correct Answer: b) Continuous integration includes updating codes, testing the code, and then checking- in the changes, which may occur several times in a day. 70. Which of the following is NOT a technique for estimating a story?
  • 19. Page | 19 Copyright 2014, Simplilearn, All rights reserved. a. Expert Opinion b. Analogy c. Disaggregation d. Decomposition Correct Answer: d) Decomposition is not a technique for estimating. 71. Agile teams may use Planning Poker for estimation. Which of the following is NOT true about Planning Poker? a. It combines expert opinion, analogy, and disaggregation to obtain reliable estimates b. Participants include all the developers in the team c. The team for Planning Poker should not exceed more than 10 participants d. The highest estimate is considered the final estimate Correct Answer: d) The high estimate is not necessarily considered the final estimate because the players with high and low estimates must explain their estimates and then a decision is taken by the players as to the final estimate value. 72. Wideband Delphi is a repeatable process that can be used: a. To generate estimation b. To create a story c. For implementation purpose d. To motivate the team Correct Answer: a) Wideband Delphi is a technique that is used to generate estimation. 73. Which of the following reports visually shows the remaining estimated workload over the course of the project? a. Product Backlog Burn down Report b. Gantt Chart c. Product Backlog d. Sprint Chart Correct Answer: a) The Product Backlog Burn down report visually shows the remaining estimated workload over the course of the project. 74. When using affinity estimating, the minimum size for the number of items in the Product Backlog is?
  • 20. Page | 20 Copyright 2014, Simplilearn, All rights reserved. a. 20 b. 40 c. 8 d. 5 Correct Answer: a) When using affinity estimating, the minimum size for the number of items in the Product Backlog is 20 items. 75. Which of the following defines Elapsed Time? a. The same as ideal time b. The amount of time on a clock c. The amount of time without any interruptions d. The amount of time the team spent on the iteration Correct Answer: b) Elapsed time is the amount of time on a clock. 76. Which of the following is NOT true about Kanban? a. Is a visual system b. Uses Work In Process (WIP) c. Is a task board d. Used in Lean Manufacturing Correct Answer: c) A Kanban is a visual system using Work in Process (WIP with the Lean Manufacturing process). A task-board visualizes current tasks. 77. The MoSCoW technique is used to create a prioritized requirements list. In MoSCoW technique, 'M' stands for: a. Medium b. Must c. Must Not Have d. Minimum Marketable Features Correct Answer: b) The MoSCoW prioritization scheme derived its name from the first letters of its labels: “Must…”, “Should…”, “Could…”, “Won't.”
  • 21. Page | 21 Copyright 2014, Simplilearn, All rights reserved. 78. What is a voting scheme where each stakeholder is given 100 points to use for voting in favor of the most important requirements and can distribute the 100 points in any way desired? a. Monopoly Money b. 100-Point Method c. Requirements Prioritization Money d. Agile Prioritization Correct Answer: b) The 100-Point Method is a voting scheme where each stakeholder is given 100 points to use for voting in favor of the most important requirements and can distribute the 100 points in any way desired. 79. In a Fixed Price contract, the risk is mostly assumed by the : a. Supplier b. Customer c. Product Owner d. Project Team Correct Answer: a) In a Fixed Price contract, the risk is mostly assumed by the supplier, because if the estimate is incorrect the supplier must still honor the fixed price to the customer. 80. Teams utilizing unfamiliar technology may need time for training prior to a project's launch and time to establish a development environment. This training may be included: a. In Iteration 0 b. As a new story c. But is out of scope d. In the functional manager's scope Correct Answer: a) Iteration 0 is used to prepare the team for the project, including training and doesn't deliver direct customer value. 81. Which of the following is NOT a Closed Story? a. A recruiter can review resumes from applicants to one of her ads. b. A recruiter can delete an application that is not a good match for a job. c. A recruiter can manage the ads she has placed d. A recruiter can change the expiration date of an ad
  • 22. Page | 22 Copyright 2014, Simplilearn, All rights reserved. Correct Answer: c) "A recruiter can manage the ads she has placed" is not a closed story because it is an ongoing activity. 82. The primary task in release planning is assigning stories to iterations, chiefly on the basis of _______________________ a. Value and Risk b. Risk and Priority c. Customer Requirements d. Team ability and Value Correct Answer: a) The primary task in release planning is assigning stories to iterations, chiefly on the basis of value and risk. 83. In the Agile Team Stages of Shu Ha Ri, what does 'Ha' stand for? a. Break the rule b. Follow the rule c. Be the rule d. None of the above Correct Answer: a) Shu Ha Ri means - 'Shu' to follow the rule, 'Ha' to break the rule, and 'Ri' to be the rule. 84. "Having problems does not indicate a problem in itself, so welcome problems because they bring with them the chance for the team to overcome, grow, and become stronger together." As an Agile coach, which of the following is not one of the multiple perspectives to analyze or detect the symptoms for the problem? a. Process Level b. Quality and Performance Level c. Team dynamics dimension d. Team members' management Correct Answer: d) The multiple perspectives to analyze are the process level, the quality and performance angle, and the team dynamics dimension, not the team members' management. 85. Which of the following documents all of the known features that are to be implemented throughout the project?
  • 23. Page | 23 Copyright 2014, Simplilearn, All rights reserved. a. Prioritized Sprint b. Vision Box c. Product Backlog d. Sprint Review Meet Correct Answer: c) The Product Backlog documents all the known features that are to be implemented throughout the project. 86. During the second level of conflict, disagreement, the team members distance themselves from one another, except in one-on-one conversations to obtain advice and support. What becomes as important as solving the problem? a. Self-protection b. Satisfy self-ego c. Aim to win d. None of the above Correct Answer: a) During disagreement, self-protection becomes as important as solving the problem or conflict situation. 87. John and Joseph are working in the same room. John is programming and Joseph is discussing with Kim. John gets to hear their conversation and gets enough information to know that Joseph has talked about some idea with Kim. What kind of communication is this referred to as? a. Push Communication b. Osmotic Communication c. Pull Communication d. Active Listening Correct Answer: b) Osmotic communication occurs when people in the same environment hear and comprehends information without being communicated to directly. 88. Which of the following is NOT included on Information Radiators? a. Displaying Work Breakdown b. Displaying Project Status c. Automated Build Report
  • 24. Page | 24 Copyright 2014, Simplilearn, All rights reserved. d. Iteration Planning Correct Answer: d) Information radiators may display the work breakdown, project status, and automated build report, but not the iteration planning. 89. Spike solutions are small experiments to answer a question and determine a path forward. Which of the following types of spike will you use if you need to test an approach to your production code? a. Development Spike b. Design Spike c. Scheduling Spikes d. Iteration Spikes Correct Answer: b) A design spike would be used to test the production code for readiness to move forward. 90. Of the listed options, which best describes User Stories? a. Support tools for analysis b. IEEE 830 c. Use Cases d. Interaction Design Scenarios Correct Answer: a) User stories are support tools for analysis. 91. What is the successful response option at Conflict Level 1: Problem to Solve? a. Collaboration b. Consensus c. Safety d. Root case analysis Correct Answer: a) Successful response options at Level 1 are collaboration and consensus. 92. As per the Kano Model of customer satisfaction, which features are MOST important for the product to be successful? a. Exciters b. Linear Features c. Delighters d. Threshold
  • 25. Page | 25 Copyright 2014, Simplilearn, All rights reserved. Correct Answer: d) Threshold features are the must-have features present in the product. 93. A methodology that is based on solutions or sequences of steps that is known to work for the discipline is known as: a. Normative b. Rational c. Heuristic d. Participative Correct Answer: a) Normative methodologies are based on solutions or steps known to work for a certain discipline or industry. 94. What does acronym DRY stand for? a. Don't Repeat Yourself b. Don't Reject Yourself c. Do Repeat Yourself d. None of the above Correct Answer: a) DRY stands for "Don’t Repeat Yourself" meaning not doing work that is not necessary. 95. When a team member approaches the Coach with a complaint about another team member, what conflict resolution technique should the Coach use? a. Compromise b. Face to Face c. Three-step intervention d. Confronting Correct Answer: c) When a team member approaches the Coach with a complaint about another team member, the three-step intervention path is the conflict resolution technique that the Coach should use. 96. A path of action to achieve a long-term goal is referred to as: a. Tactical Planning b. Strategic Planning c. Goal Planning d. Roadmap Planning Correct Answer: b) A path of action to achieve a long-term goal is referred to as strategic planning.
  • 26. Page | 26 Copyright 2014, Simplilearn, All rights reserved. 97. To detect problems at the process level, the team uses a questionnaire that lists required elements and qualities that are the basic ingredients of Agile. From this, we consider the maturity of the Agile process in the organization and how well the team follows the agile process. This questionnaire is referred to as: a. Health Check b. Form c. Questionnaire d. Checklist Correct Answer: a) The questionnaire is referred to as a health check. 98. Which of the following techniques would you use to detect problems within a process? a. Sprints b. Burn Up charts c. Burn Down charts d. Health checks Correct Answer: d) Health checks, often in the form of a questionnaire, lists required elements and qualities that jog our minds to help us remember the basic ingredients of Agile. They help us determine how well the team is adhering to Agile methods. 99. What is the output of the Sprint Planning Meeting? a. Sprint Backlog b. Product Backlog c. Iteration Backlog d. None of the above Correct Answer: a) The outcome of the Sprint Planning meeting is the Sprint Backlog. 100. A verbal communication to multiple people that a milestone was completed is known as: a. Declaration Milestone b. Publication c. Announcement d. Circular
  • 27. Page | 27 Copyright 2014, Simplilearn, All rights reserved. Correct Answer: a) A declaration milestone is a verbal communication to multiple people that a milestone was completed. 101. At a Retrospective meeting, few issues are highlighted by the team. Who is responsible for solving these issues? a. The Scrum Master b. Product Owner c. Stakeholders d. Team Correct Answer: d) Agile teams are self-organizing and can find solutions to their problems with ease. 102. Which of the following is NOT done as part of Planning in Agile Project Management? a. Risk Management b. Product Vision c. Slack d. Done-Done Correct Answer: d) Done-Done is part of releasing. 103. Which of the following BEST describes Horizontal Market Software? a. Developed for many organizations b. Developed and used across many industries c. Developed for a dedicated customer d. Developed for one organization Correct Answer: b) Horizontal Market Software is intended to be used across a wide range of industries. 104. What is the BEST tool for tracking the progress of the project and evaluating the ROI on an Agile project? a. Sprint b. Product Backlog c. Iteration Backlog d. Releases Correct Answer: b) The Product Backlog is the BEST tool for tracking the progress of the project and evaluating the ROI on an Agile project. 105. What are the four key terms by which the iterative part of Agile is defined?
  • 28. Page | 28 Copyright 2014, Simplilearn, All rights reserved. a. Time boxed, releasable, agility and incremental b. Iterative, feature-based, time boxed, and incremental c. Feature-based, time boxed, agility and incremental d. Iterative, release-based, time boxed, and incremental Correct Answer: b) The four key terms by which the iterative part of Agile is defined are iterative, feature-based, time boxed, and incremental. 106. What is the process of planning in waves as project details become more defined called? a. Burn down chart b. Release c. Rolling wave d. Roadmap Correct Answer: c) The process of planning in waves as project details become more defined is called rolling wave. 107. What is definition and prioritization of the nonfunctional requirements by scaling called? a. Decomposition b. Staging c. Stanking d. Prioritizing Correct Answer: b) Definition and prioritization of the nonfunctional requirements by scaling is called staging. 108. Which report should NOT be shared with your stakeholders? a. Defect reports b. Status reports c. Throughput reports d. SLOC reports Correct Answer: d) Source Lines of Code (SLOC) reports should not be shared with the stakeholders, as they are flawed productivity metrics. 109. Which of the following tests verify that units and combinations of units work together to perform the desired operations? a. Unit tests
  • 29. Page | 29 Copyright 2014, Simplilearn, All rights reserved. b. Component tests c. Exploratory tests d. Usability tests Correct Answer: b) Component tests verify that units and combinations of units work together to perform the desired operations. 110. A Retrospective can be as short as 15 minutes or as long as 1 hour. The duration of the Retrospective can be dependent on all of the following EXCEPT: a. Length of the iteration b. Level of conflict or controversy c. Size of the team d. Seniority of the product owner Correct Answer: d) Of all the listed options, the length of the retrospective is not dependent on the seniority of the product owner. The length of the retrospective can be dependent on the length of iteration, level of conflict or controversy, size of the team, and complexity (of technology, organization of the team, and relationships with external department). 111. What does 'R' stand for in ARCS, a criterion for evaluating Instructional designs by J.M. Keller? a. Relevance b. Repeatable c. Recording d. Right Correct Answer: a) J. M. Keller, an expert in motivation and learning, developed criteria for evaluating instructional designs. The criteria are Attention, Relevance, Confidence/Competence, Satisfaction— ARCS for short. Choose activities that help people stay engaged so they don’t drift off (Attention) and that are relevant to the goal (Relevance). You want activities that people can accomplish successfully (Confident/Competence). Finally, make sure activities fit into the overall design so people think the retrospective is a good use of their time (Satisfaction). 112. Which are the three coach styles? a. Teaching, Coaching, and Advising b. Coaching, Mentoring, and Advising c. Coaching, Informing, Advising d. Mentoring, Teaching, and Advising Correct Answer: a) The three coach styles are Teaching, Coaching, and Advising.
  • 30. Page | 30 Copyright 2014, Simplilearn, All rights reserved. 113. Activities are time boxed processes that help the team move through the phases of retrospective. Activities provide structure to help your team think together and have several advantages over freewheeling discussion. Activities don’t have to be elaborate or involved to be effective. Which of the following are NOT examples of activities that are useful in retrospectives? a. Brainstorming b. Voting with Dots c. Pair Interviews d. Synergy Correct Answer: d) Activities don’t have to be elaborate or involved to be effective. Examples of activities that are useful in retrospectives include brainstorming, voting with dots, doing check-ins, and performing pair interviews. 114. For a Retrospective meeting, the seating arrangement should be such that there is enough space for people to move comfortably. Which of the following is a preferable seating arrangement for a retrospective meeting? a. Circle or semicircle of chairs b. Theatre style arrangement c. Tables arranged in U-shape d. Meeting Room Correct Answer: a) A circle or semicircle of chairs encourages participation because people can see each other. Classroom or theater-style arrangements stifle participation. Staring at the back of someone else’s head isn’t conducive to conversation. Tables can be a physical barrier that becomes a psychological barrier. Avoid rooms with an immovable conference table in the middle. That big old’ table will inhibit creative collaboration. This isn’t a board meeting, after all. Tables arranged in a U-shape with a big gulf in the middle create distance and make it hard to move around. 115. Which of the following are MOST helpful in implementing collective code ownership in a team? a. Version control b. Pair programming c. Continuous integration d. Probability distribution
  • 31. Page | 31 Copyright 2014, Simplilearn, All rights reserved. Correct Answer: b) Pair programming is helpful in implementing collective code ownership in a team. 116. How do you best describe the primary role of an Agile leader? a. Manage WBS, schedule, and cost of project b. Manage stakeholders c. Manage work allocation to team members d. Manage teams without managing their tasks Correct Answer: d) Agile leaders do not have to manage the tasks of the team members. 117. Which of the following BEST describes ROTI? a. Measure of product backlogs remaining b. Measure of quality of features delivered in an iteration c. Measure of required effort to deliver in an iteration d. Measure of effectiveness of the retrospective meeting Correct Answer: d) Return on Time Invested (ROTI) is used to measure the effectiveness of the retrospective meetings from the team members' perspective. 118. Which of the following is NOT a characteristic of Agile project manager? a. Manages daily tasks of the team members b. Assumes different leadership styles for different stages of team formation c. Allows team to self-manage d. Facilitates collaboration Correct Answer: a) Agile Project Manager does not manage the daily tasks of team members as teams in Agile are self-organizing. 119. Who performs value point estimating? a. Finance Team b. Scrum Team c. Product Team d. Development Team Correct Answer: c) Value point estimation is done by the Product Team.
  • 32. Page | 32 Copyright 2014, Simplilearn, All rights reserved. 120. In the absence of the Product Owner, who should assume the Product Owner's responsibilities at the Sprint planning meeting? a. Scrum Master b. Team c. Person selected by the Product Owner d. Person selected by the team Correct Answer: a) When the Product Owner is not present, the Scrum Master will take the responsibility to prepare Product Backlog for the Sprint planning meeting.