Transcript: New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024
Geosynthetics Applications in Civil Engineering by Sirmoi_Geosynthetics EA Ltd
1. Geosynthetics Applications in Civil Engineering; An
Introduction to value Engineering (VE) Technologies
Solutions that Last
GEOSYNTHETICS EAST AFRICA Ltd
TEXTILE AND LEATHER CONFERENCE 2013
ORGANIZED BY KENYA BUREAU OF STANDARDS
VENUE :BOMA HOTEL
DATES: Thursday, 29th August 2013
Presentation:
Sirmoi Wekesa
Technical Director
Geosynthetics EA Ltd
2. Introduction to Geosynthetics
Part I
ASTM (2006) D 4439 defines a geosynthetic as a
planar product manufactured from a polymeric
material used with soil, rock, earth, or other
geotechnical-related material as an integral part of
a civil engineering project, structure, or system.
A number of geosynthetics are available, including
geotextiles, geogrids, geomembranes, geonets,
geomeshes, geowebs, and geocomposites.
3. DIFFERENT TYPES OF GEOSYNTHETICS
Geotextile Geonet Geocell Geogrids
Geocomposite Erosion Control Geosynthetics
4. GEOGRID TYPES
Different Types of Geogrids used for ground
Improvement:;; and
(a) Triaxial
(b) Biaxial (c) Uniaxial
New Four-axial
New Quaxial
17. VALUE ENGINEERING
BENEFITS
Construction cost-time savings
through the reduction of required
pavement material quantities, whilst
maintaining enhanced structural
performance.
Elongated pavement structural life –
span particularly as a result of
incorporating the filtration/separation
geotextile.
Reduction in maintenance
requirements as a result of enhanced
structural performance.
Environmental conservation -
mainly due to reduction in material
quantities and erosion control.
Appropriate application of
geosynthetics can realize the
following benefits.
19. VALUE ENGINEERED BENEFITS
Description Quantity placed per day
[m3]
Area [m2] Layer thickness[m] Quantity in volume [m3] Time taken in Days [in
weeks]
Import place and
compact ground
stabilization material
[cement]
300 311,550 0.2 62,310 200 days [28weeks]
Import place and
compact granular
material for sub-base
193 311,550 0.4 124,620 646 days
[92 weeks]
Excavation to spoil of
poor quality material
1000 51,031 1.5 76,546.50 77 days
[11 weeks]
Import, place and
compact capping layer or
backfill material
578 51,031 2.0 102,062 177 days
[25 weeks]
TOTAL DURATION TAKEN TO CONSTRUCT THE PAVEMENT* 156 weeks
20. VALUE ENGINEERED BENEFITS
Description Quantity placed
per day [m3]
Area [m2] Layer
thickness[m]
Quantity in
volume [m3]
Time taken in
Days [in weeks]
Import place
and compact
granular
material for
sub-base
193 311,550 0.3 93,465 484 days
[69 weeks]
Top Soil
stripping and
disposal or
grading*
680 51,031 0.15 7,654.65 12 days
[2 weeks]
TOTAL DURATION TAKEN TO CONSTRUCT THE PAVEMENT* 71 weeks
*This might not be necessary especially if the water table is very high. Grading normally
helps to create the platform for grid placement.
• Time saved is approximately 50%.
22. VE BENEFITS – ROAD OVER SWAMP CROSSING
The proposed road was crossing a 1.2km swampy stretch.
The soils were peat with low bearing capacities with CBRs of
about 0.5%.
The design assumed the peat thickness to be 1.0m before getting
on to hard ground.
The actual thickness was deeper than 1.0m; instead it went
beyond 3m.
The contractor wanted to finish the section before the rains
started.
23. VE BENEFITS – ROAD OVER SWAMP CROSSING
COST AS PER CONVENTIONAL DESIGN
DESCRIPTION UNITS LENGTH[m] WIDTH[m] DEPTH[m] QUANTITY RATE TOTAL
Excavate 1m thick to spoil m3 1200 15 1 18000 $ 5.33 $ 96,000.00
Fill 1m thick of rock m3 1200 15 1 18000 $ 16.00 $ 288,000.00
TOTAL AMOUNT $ 384,000.00
24. VE BENEFITS – ROAD OVER SWAMP CROSSING
COST AS PER THE GEOSYNTHETICS DESIGN
DESCRIPTION
UNI
TS
LENGT
H[m]
WIDTH
[m]
DEPTH
[m] QITY RATE TOTAL
Tensar TX 170 Geogrids
[Supply and Placement] m2 1200 15 - 18000 $ 13.26 $ 238,653.60
TOTAL AMOUNT AS PER THE TENSAR PROPOSAL
$ 238,653.60
AMOUNT SAVED $ 145,346.40
PERCENTAGE OF AMOUNT SAVED [%] 37.85 %
29. Comparison of Unreinforced and Reinforced UCS for
swampy BCS for Drilling Project of White Nile Oil in
Jonglei State, Southern Sudan
No. Unreinforced
[Mpa]
Reinforced
[Mpa]
Description % Increase Remarks
1 1.45 No soil reinforcement
2 1.45 2.1 Geogrid SS20G, 1/3H 45 >30<100
3 1.45 2.15 Geogrid SS20G, 1/5H 48 >30<100
4 1.45 2.2 Double Geogrid SS20G,
1/3H, 2/3H
52 >30<100
5 1.45 1.55 Mat 1/3H 7 >30<100
6 1.45 1.85 Mat 1/5H 28 ≈30<100
7 1.45 2.1 Double Mat 1/3H, 1/5H 45 >30<100
30. NEAT BLACK COTTON SOIL
SAMPLES
Comparison of Unreinforced and
Reinforced UCS for swampy BCS for
Drilling Project of White Nile Oil in
Jonglei State, Southern Sudan