SlideShare uma empresa Scribd logo
1 de 57
Unit Commitment
© 2011 Daniel Kirschen and the University of Washington
1
OVERVIEW OF UNIT COMMITMENT
(Vertical System)
© 2011 Daniel Kirschen and the University of Washington 2
Economic Dispatch: Problem Definition
• Given load
• Given set of units on-line
• How much should each unit generate to meet this
load at minimum cost?
© 2011 Daniel Kirschen and the University of Washington 3
A B C
L
Typical summer and winter loads
© 2011 Daniel Kirschen and the University of Washington 4
Unit Commitment
• Given load profile
(e.g. values of the load for each hour of a day)
• Given set of units available
• When should each unit be started, stopped and
how much should it generate to meet the load at
minimum cost?
© 2011 Daniel Kirschen and the University of Washington 5
G G G
Load Profile
? ? ?
A Simple Example
• Unit 1:
• PMin = 250 MW, PMax = 600 MW
• C1 = 510.0 + 7.9 P1 + 0.00172 P1
2 $/h
• Unit 2:
• PMin = 200 MW, PMax = 400 MW
• C2 = 310.0 + 7.85 P2 + 0.00194 P2
2 $/h
• Unit 3:
• PMin = 150 MW, PMax = 500 MW
• C3 = 78.0 + 9.56 P3 + 0.00694 P3
2 $/h
• What combination of units 1, 2 and 3 will produce 550 MW at
minimum cost?
• How much should each unit in that combination generate?
© 2011 Daniel Kirschen and the University of Washington 6
Cost of the various combinations
© 2011 Daniel Kirschen and the University of Washington 7
Observations on the example:
• Far too few units committed:
Can’t meet the demand
• Not enough units committed:
Some units operate above optimum
• Too many units committed:
Some units below optimum
• Far too many units committed:
Minimum generation exceeds demand
• No-load cost affects choice of optimal
combination
© 2011 Daniel Kirschen and the University of Washington 8
A more ambitious example
• Optimal generation schedule for
a load profile
• Decompose the profile into a
set of period
• Assume load is constant over
each period
• For each time period, which
units should be committed to
generate at minimum cost
during that period?
© 2011 Daniel Kirschen and the University of Washington 9
Load
Time
12
6
0 18 24
500
1000
Optimal combination for each hour
© 2011 Daniel Kirschen and the University of Washington 10
Matching the combinations to the load
© 2011 Daniel Kirschen and the University of Washington 11
Load
Time
12
6
0 18 24
Unit 1
Unit 2
Unit 3
Issues
• Must consider constraints
– Unit constraints
– System constraints
• Some constraints create a link between periods
• Start-up costs
– Cost incurred when we start a generating unit
– Different units have different start-up costs
• Curse of dimensionality
© 2011 Daniel Kirschen and the University of Washington 12
Unit Constraints
• Constraints that affect each unit individually:
–Maximum generating capacity
–Minimum stable generation
–Minimum “up time”
–Minimum “down time”
–Ramp rate
© 2011 Daniel Kirschen and the University of Washington 13
Notations
© 2011 Daniel Kirschen and the University of Washington 14
u(i,t): Status of unit i at period t
x(i,t): Power produced by unit i during period t
Unit i is on during period t
u(i,t) =1:
Unit i is off during period t
u(i,t) = 0 :
Minimum up- and down-time
• Minimum up time
– Once a unit is running it may not be shut down
immediately:
• Minimum down time
– Once a unit is shut down, it may not be started
immediately
© 2011 Daniel Kirschen and the University of Washington 15
If u(i,t) =1 and ti
up
< ti
up,min
then u(i,t +1) =1
If u(i,t) = 0 and ti
down
< ti
down,min
then u(i,t +1) = 0
Ramp rates
• Maximum ramp rates
– To avoid damaging the turbine, the electrical output of a unit
cannot change by more than a certain amount over a period of
time:
© 2011 Daniel Kirschen and the University of Washington 16
x i,t +1
( )- x i,t
( )£ DPi
up,max
x(i,t)- x(i,t +1) £ DPi
down,max
Maximum ramp up rate constraint:
Maximum ramp down rate constraint:
System Constraints
• Constraints that affect more than one unit
– Load/generation balance
– Reserve generation capacity
– Emission constraints
– Network constraints
© 2011 Daniel Kirschen and the University of Washington 17
Load/Generation Balance Constraint
© 2011 Daniel Kirschen and the University of Washington 18
u(i,t)x(i,t)
i=1
N
å = L(t)
N : Set of available units
Reserve Capacity Constraint
• Unanticipated loss of a generating unit or an interconnection
causes unacceptable frequency drop if not corrected rapidly
• Need to increase production from other units to keep frequency
drop within acceptable limits
• Rapid increase in production only possible if committed units are
not all operating at their maximum capacity
© 2011 Daniel Kirschen and the University of Washington 19
u(i,t)
i=1
N
å Pi
max
³ L(t)+ R(t)
R(t): Reserve requirement at time t
How much reserve?
• Protect the system against “credible outages”
• Deterministic criteria:
– Capacity of largest unit or interconnection
– Percentage of peak load
• Probabilistic criteria:
– Takes into account the number and size of the
committed units as well as their outage rate
© 2011 Daniel Kirschen and the University of Washington 20
Types of Reserve
• Spinning reserve
– Primary
• Quick response for a short time
– Secondary
• Slower response for a longer time
• Tertiary reserve
– Replace primary and secondary reserve to protect
against another outage
– Provided by units that can start quickly (e.g. open cycle
gas turbines)
– Also called scheduled or off-line reserve
© 2011 Daniel Kirschen and the University of Washington 21
Types of Reserve
• Positive reserve
– Increase output when generation < load
• Negative reserve
– Decrease output when generation > load
• Other sources of reserve:
– Pumped hydro plants
– Demand reduction (e.g. voluntary load shedding)
• Reserve must be spread around the network
– Must be able to deploy reserve even if the network is
congested
© 2011 Daniel Kirschen and the University of Washington 22
Cost of Reserve
• Reserve has a cost even when it is not called
• More units scheduled than required
– Units not operated at their maximum efficiency
– Extra start up costs
• Must build units capable of rapid response
• Cost of reserve proportionally larger in small
systems
• Important driver for the creation of interconnections
between systems
© 2011 Daniel Kirschen and the University of Washington 23
Environmental constraints
• Scheduling of generating units may be affected by
environmental constraints
• Constraints on pollutants such SO2, NOx
– Various forms:
• Limit on each plant at each hour
• Limit on plant over a year
• Limit on a group of plants over a year
• Constraints on hydro generation
– Protection of wildlife
– Navigation, recreation
© 2011 Daniel Kirschen and the University of Washington 24
Network Constraints
• Transmission network may have an effect on the
commitment of units
– Some units must run to provide voltage support
– The output of some units may be limited because their
output would exceed the transmission capacity of the
network
© 2011 Daniel Kirschen and the University of Washington 25
Cheap generators
May be “constrained off”
More expensive generator
May be “constrained on”
A B
Start-up Costs
• Thermal units must be “warmed up” before they
can be brought on-line
• Warming up a unit costs money
• Start-up cost depends on time unit has been off
© 2011 Daniel Kirschen and the University of Washington 26
SCi (ti
OFF
) = ai + bi (1 - e
-
ti
OFF
t i
)
ti
OFF
αi
αi + βi
Start-up Costs
• Need to “balance” start-up costs and running costs
• Example:
– Diesel generator: low start-up cost, high running cost
– Coal plant: high start-up cost, low running cost
• Issues:
– How long should a unit run to “recover” its start-up cost?
– Start-up one more large unit or a diesel generator to cover
the peak?
– Shutdown one more unit at night or run several units part-
loaded?
© 2011 Daniel Kirschen and the University of Washington 27
Summary
• Some constraints link periods together
• Minimizing the total cost (start-up + running) must
be done over the whole period of study
• Generation scheduling or unit commitment is a
more general problem than economic dispatch
• Economic dispatch is a sub-problem of generation
scheduling
© 2011 Daniel Kirschen and the University of Washington 28
Flexible Plants
• Power output can be adjusted (within limits)
• Examples:
– Coal-fired
– Oil-fired
– Open cycle gas turbines
– Combined cycle gas turbines
– Hydro plants with storage
• Status and power output can be optimized
© 2011 Daniel Kirschen and the University of Washington 29
Thermal units
Inflexible Plants
• Power output cannot be adjusted for technical or
commercial reasons
• Examples:
– Nuclear
– Run-of-the-river hydro
– Renewables (wind, solar,…)
– Combined heat and power (CHP, cogeneration)
• Output treated as given when optimizing
© 2011 Daniel Kirschen and the University of Washington 30
Solving the Unit Commitment Problem
• Decision variables:
– Status of each unit at each period:
– Output of each unit at each period:
• Combination of integer and continuous variables
© 2011 Daniel Kirschen and the University of Washington 31
u(i,t) Î 0,1
{ } " i,t
x(i,t) Î 0, Pi
min
;Pi
max
é
ë ù
û
{ } " i,t
Optimization with integer variables
• Continuous variables
– Can follow the gradients or use LP
– Any value within the feasible set is OK
• Discrete variables
– There is no gradient
– Can only take a finite number of values
– Problem is not convex
– Must try combinations of discrete values
© 2011 Daniel Kirschen and the University of Washington 32
How many combinations are there?
© 2011 Daniel Kirschen and the University of Washington 33
• Examples
– 3 units: 8 possible states
– N units: 2N possible states
111
110
101
100
011
010
001
000
How many solutions are there anyway?
© 2011 Daniel Kirschen and the University of Washington 34
1 2 3 4 5 6
T=
• Optimization over a time
horizon divided into
intervals
• A solution is a path linking
one combination at each
interval
• How many such paths are
there?
How many solutions are there anyway?
© 2011 Daniel Kirschen and the University of Washington 35
1 2 3 4 5 6
T=
Optimization over a time
horizon divided into intervals
A solution is a path linking
one combination at each
interval
How many such path are
there?
Answer: 2N
( ) 2N
( )… 2N
( ) = 2N
( )T
The Curse of Dimensionality
• Example: 5 units, 24 hours
• Processing 109 combinations/second, this would
take 1.9 1019 years to solve
• There are 100’s of units in large power systems...
• Many of these combinations do not satisfy the
constraints
© 2011 Daniel Kirschen and the University of Washington 36
2N
( )
T
= 25
( )
24
= 6.21035
combinations
How do you Beat the Curse?
Brute force approach won’t work!
• Need to be smart
• Try only a small subset of all combinations
• Can’t guarantee optimality of the solution
• Try to get as close as possible within a reasonable
amount of time
© 2011 Daniel Kirschen and the University of Washington 37
Main Solution Techniques
• Characteristics of a good technique
– Solution close to the optimum
– Reasonable computing time
– Ability to model constraints
• Priority list / heuristic approach
• Dynamic programming
• Lagrangian relaxation
• Mixed Integer Programming
© 2011 Daniel Kirschen and the University of Washington 38
State of the art
A Simple Unit Commitment Example
© 2011 Daniel Kirschen and the University of Washington
39
Unit Data
© 2011 Daniel Kirschen and the University of Washington 40
Unit
Pmin
(MW)
Pmax
(MW)
Min
up
(h)
Min
down
(h)
No-load
cost
($)
Marginal
cost
($/MWh)
Start-up
cost
($)
Initial
status
A 150 250 3 3 0 10 1,000 ON
B 50 100 2 1 0 12 600 OFF
C 10 50 1 1 0 20 100 OFF
Demand Data
© 2011 Daniel Kirschen and the University of Washington 41
Hourly Demand
0
50
100
150
200
250
300
350
1 2 3
Hours
Load
Reserve requirements are not considered
Feasible Unit Combinations (states)
© 2011 Daniel Kirschen and the University of Washington 42
Combinations
Pmin Pmax
A B C
1 1 1 210 400
1 1 0 200 350
1 0 1 160 300
1 0 0 150 250
0 1 1 60 150
0 1 0 50 100
0 0 1 10 50
0 0 0 0 0
1 2 3
150 300 200
Transitions between feasible combinations
© 2011 Daniel Kirschen and the University of Washington 43
A B C
1 1 1
1 1 0
1 0 1
1 0 0
0 1 1
1 2 3
Initial State
Infeasible transitions: Minimum down time of unit A
© 2011 Daniel Kirschen and the University of Washington 44
A B C
1 1 1
1 1 0
1 0 1
1 0 0
0 1 1
1 2 3
Initial State
TD TU
A 3 3
B 1 2
C 1 1
Infeasible transitions: Minimum up time of unit B
© 2011 Daniel Kirschen and the University of Washington 45
A B C
1 1 1
1 1 0
1 0 1
1 0 0
0 1 1
1 2 3
Initial State
TD TU
A 3 3
B 1 2
C 1 1
Feasible transitions
© 2011 Daniel Kirschen and the University of Washington 46
A B C
1 1 1
1 1 0
1 0 1
1 0 0
0 1 1
1 2 3
Initial State
Operating costs
© 2011 Daniel Kirschen and the University of Washington 47
1 1 1
1 1 0
1 0 1
1 0 0 1
4
3
2
5
6
7
Economic dispatch
© 2011 Daniel Kirschen and the University of Washington 48
State Load PA PB PC Cost
1 150 150 0 0 1500
2 300 250 0 50 3500
3 300 250 50 0 3100
4 300 240 50 10 3200
5 200 200 0 0 2000
6 200 190 0 10 2100
7 200 150 50 0 2100
Unit Pmin Pmax No-load cost Marginal cost
A 150 250 0 10
B 50 100 0 12
C 10 50 0 20
Operating costs
© 2011 Daniel Kirschen and the University of Washington 49
1 1 1
1 1 0
1 0 1
1 0 0 1
4
3
2
5
6
7
$1500
$3500
$3100
$3200
$2000
$2100
$2100
Start-up costs
© 2011 Daniel Kirschen and the University of Washington 50
1 1 1
1 1 0
1 0 1
1 0 0 1
4
3
2
5
6
7
$1500
$3500
$3100
$3200
$2000
$2100
$2100
Unit Start-up cost
A 1000
B 600
C 100
$0
$0
$0
$0
$0
$600
$100
$600
$700
Accumulated costs
© 2011 Daniel Kirschen and the University of Washington 51
1 1 1
1 1 0
1 0 1
1 0 0 1
4
3
2
5
6
7
$1500
$3500
$3100
$3200
$2000
$2100
$2100
$1500
$5100
$5200
$5400
$7300
$7200
$7100
$0
$0
$0
$0
$0
$600
$100
$600
$700
Total costs
© 2011 Daniel Kirschen and the University of Washington 52
1 1 1
1 1 0
1 0 1
1 0 0 1
4
3
2
5
6
7
$7300
$7200
$7100
Lowest total cost
Optimal solution
© 2011 Daniel Kirschen and the University of Washington 53
1 1 1
1 1 0
1 0 1
1 0 0 1
2
5
$7100
Notes
• This example is intended to illustrate the principles of
unit commitment
• Some constraints have been ignored and others
artificially tightened to simplify the problem and make
it solvable by hand
• Therefore it does not illustrate the true complexity of
the problem
• The solution method used in this example is based on
dynamic programming. This technique is no longer
used in industry because it only works for small
systems (< 20 units)
© 2011 Daniel Kirschen and the University of Washington 54
OVERVIEW OF UNIT COMMITMENT
(Unbundled System)
© 2011 Daniel Kirschen and the University of Washington 55
Market-Clearing Price
Aggregate
Demand
Aggregate
Supply
Price
($)
MCP
Quantity (MW)
Stochastic Model of Market-Clearing Price:
MCP determined by load and availability of generating
units prevailing at a particular time.
Units are loaded in a predetermined Loading order
MCP is marginal cost of the last unit loaded to meet the
load.
Electricity Prices

Mais conteúdo relacionado

Semelhante a [2020.2] PSOC - Unit_Commitment.pptx

Electrical Plan Electrical System Electrical Design
Electrical Plan Electrical System Electrical Design Electrical Plan Electrical System Electrical Design
Electrical Plan Electrical System Electrical Design Marcep Inc.
 
Design and construction of wind turbine towers for maximum power generation
Design and construction of wind turbine towers for maximum power generationDesign and construction of wind turbine towers for maximum power generation
Design and construction of wind turbine towers for maximum power generationAakash Bagchi
 
Lecture 8 load duration curves
Lecture 8 load duration curvesLecture 8 load duration curves
Lecture 8 load duration curvesSwapnil Gadgune
 
Lecture 7 load duration curves
Lecture 7 load duration curvesLecture 7 load duration curves
Lecture 7 load duration curvesSwapnil Gadgune
 
Optimal Time-of-use Management for Utility Customers Using Behind-the-meter E...
Optimal Time-of-use Management for Utility Customers Using Behind-the-meter E...Optimal Time-of-use Management for Utility Customers Using Behind-the-meter E...
Optimal Time-of-use Management for Utility Customers Using Behind-the-meter E...Tu Nguyen
 
Ctws ocean energy lovely
Ctws ocean energy lovelyCtws ocean energy lovely
Ctws ocean energy lovelyblemon
 
Power Systems Training Course for Non-Engineers
Power Systems Training Course for Non-EngineersPower Systems Training Course for Non-Engineers
Power Systems Training Course for Non-EngineersTonex
 
Shreelakshmi(power).pptx
Shreelakshmi(power).pptxShreelakshmi(power).pptx
Shreelakshmi(power).pptxsurbhi agarwal
 
Water Lifts and Pumps
Water Lifts and PumpsWater Lifts and Pumps
Water Lifts and PumpsSuyog Khose
 
Lecture on Power Systems for large scale deployments and its considerations .ppt
Lecture on Power Systems for large scale deployments and its considerations .pptLecture on Power Systems for large scale deployments and its considerations .ppt
Lecture on Power Systems for large scale deployments and its considerations .pptSteveMartinez57
 
The smart grid - Supply and demand side equivalent solutions
The smart grid - Supply and demand side equivalent solutionsThe smart grid - Supply and demand side equivalent solutions
The smart grid - Supply and demand side equivalent solutionsSchneider Electric
 
Energy Storage: New Capabilities for the Electric Grid – The Tehachapi Energy...
Energy Storage: New Capabilities for the Electric Grid – The Tehachapi Energy...Energy Storage: New Capabilities for the Electric Grid – The Tehachapi Energy...
Energy Storage: New Capabilities for the Electric Grid – The Tehachapi Energy...kevinfok
 
Wind and Solar Power - Renewable Energy Technologies
Wind and Solar Power - Renewable Energy TechnologiesWind and Solar Power - Renewable Energy Technologies
Wind and Solar Power - Renewable Energy TechnologiesLiving Online
 

Semelhante a [2020.2] PSOC - Unit_Commitment.pptx (20)

CH-2_PPEE.ppt
CH-2_PPEE.pptCH-2_PPEE.ppt
CH-2_PPEE.ppt
 
Electrical Plan Electrical System Electrical Design
Electrical Plan Electrical System Electrical Design Electrical Plan Electrical System Electrical Design
Electrical Plan Electrical System Electrical Design
 
Design and construction of wind turbine towers for maximum power generation
Design and construction of wind turbine towers for maximum power generationDesign and construction of wind turbine towers for maximum power generation
Design and construction of wind turbine towers for maximum power generation
 
Lecture 8 load duration curves
Lecture 8 load duration curvesLecture 8 load duration curves
Lecture 8 load duration curves
 
Lecture 7 load duration curves
Lecture 7 load duration curvesLecture 7 load duration curves
Lecture 7 load duration curves
 
OPAL-RT & Hydro-Quebec - HYPERSIM
OPAL-RT & Hydro-Quebec - HYPERSIMOPAL-RT & Hydro-Quebec - HYPERSIM
OPAL-RT & Hydro-Quebec - HYPERSIM
 
Securing Australia's Energy Future: The Challenge - Simon Gamble, Hydro Tasmania
Securing Australia's Energy Future: The Challenge - Simon Gamble, Hydro TasmaniaSecuring Australia's Energy Future: The Challenge - Simon Gamble, Hydro Tasmania
Securing Australia's Energy Future: The Challenge - Simon Gamble, Hydro Tasmania
 
Optimal Time-of-use Management for Utility Customers Using Behind-the-meter E...
Optimal Time-of-use Management for Utility Customers Using Behind-the-meter E...Optimal Time-of-use Management for Utility Customers Using Behind-the-meter E...
Optimal Time-of-use Management for Utility Customers Using Behind-the-meter E...
 
Ctws ocean energy lovely
Ctws ocean energy lovelyCtws ocean energy lovely
Ctws ocean energy lovely
 
Wireless charge - Steven Mitchell
Wireless charge - Steven MitchellWireless charge - Steven Mitchell
Wireless charge - Steven Mitchell
 
Power Systems Training Course for Non-Engineers
Power Systems Training Course for Non-EngineersPower Systems Training Course for Non-Engineers
Power Systems Training Course for Non-Engineers
 
UNIT 1 CLASS1.pdf
UNIT 1 CLASS1.pdfUNIT 1 CLASS1.pdf
UNIT 1 CLASS1.pdf
 
Shreelakshmi(power).pptx
Shreelakshmi(power).pptxShreelakshmi(power).pptx
Shreelakshmi(power).pptx
 
Water Lifts and Pumps
Water Lifts and PumpsWater Lifts and Pumps
Water Lifts and Pumps
 
Lecture on Power Systems for large scale deployments and its considerations .ppt
Lecture on Power Systems for large scale deployments and its considerations .pptLecture on Power Systems for large scale deployments and its considerations .ppt
Lecture on Power Systems for large scale deployments and its considerations .ppt
 
Lecture_1.ppt
Lecture_1.pptLecture_1.ppt
Lecture_1.ppt
 
UNIT-III-WIND ENERGY.pptx
UNIT-III-WIND ENERGY.pptxUNIT-III-WIND ENERGY.pptx
UNIT-III-WIND ENERGY.pptx
 
The smart grid - Supply and demand side equivalent solutions
The smart grid - Supply and demand side equivalent solutionsThe smart grid - Supply and demand side equivalent solutions
The smart grid - Supply and demand side equivalent solutions
 
Energy Storage: New Capabilities for the Electric Grid – The Tehachapi Energy...
Energy Storage: New Capabilities for the Electric Grid – The Tehachapi Energy...Energy Storage: New Capabilities for the Electric Grid – The Tehachapi Energy...
Energy Storage: New Capabilities for the Electric Grid – The Tehachapi Energy...
 
Wind and Solar Power - Renewable Energy Technologies
Wind and Solar Power - Renewable Energy TechnologiesWind and Solar Power - Renewable Energy Technologies
Wind and Solar Power - Renewable Energy Technologies
 

Último

Virtual memory management in Operating System
Virtual memory management in Operating SystemVirtual memory management in Operating System
Virtual memory management in Operating SystemRashmi Bhat
 
2022 AWS DNA Hackathon 장애 대응 솔루션 jarvis.
2022 AWS DNA Hackathon 장애 대응 솔루션 jarvis.2022 AWS DNA Hackathon 장애 대응 솔루션 jarvis.
2022 AWS DNA Hackathon 장애 대응 솔루션 jarvis.elesangwon
 
『澳洲文凭』买麦考瑞大学毕业证书成绩单办理澳洲Macquarie文凭学位证书
『澳洲文凭』买麦考瑞大学毕业证书成绩单办理澳洲Macquarie文凭学位证书『澳洲文凭』买麦考瑞大学毕业证书成绩单办理澳洲Macquarie文凭学位证书
『澳洲文凭』买麦考瑞大学毕业证书成绩单办理澳洲Macquarie文凭学位证书rnrncn29
 
System Simulation and Modelling with types and Event Scheduling
System Simulation and Modelling with types and Event SchedulingSystem Simulation and Modelling with types and Event Scheduling
System Simulation and Modelling with types and Event SchedulingBootNeck1
 
OOP concepts -in-Python programming language
OOP concepts -in-Python programming languageOOP concepts -in-Python programming language
OOP concepts -in-Python programming languageSmritiSharma901052
 
Paper Tube : Shigeru Ban projects and Case Study of Cardboard Cathedral .pdf
Paper Tube : Shigeru Ban projects and Case Study of Cardboard Cathedral .pdfPaper Tube : Shigeru Ban projects and Case Study of Cardboard Cathedral .pdf
Paper Tube : Shigeru Ban projects and Case Study of Cardboard Cathedral .pdfNainaShrivastava14
 
Levelling - Rise and fall - Height of instrument method
Levelling - Rise and fall - Height of instrument methodLevelling - Rise and fall - Height of instrument method
Levelling - Rise and fall - Height of instrument methodManicka Mamallan Andavar
 
Comparative study of High-rise Building Using ETABS,SAP200 and SAFE., SAFE an...
Comparative study of High-rise Building Using ETABS,SAP200 and SAFE., SAFE an...Comparative study of High-rise Building Using ETABS,SAP200 and SAFE., SAFE an...
Comparative study of High-rise Building Using ETABS,SAP200 and SAFE., SAFE an...Erbil Polytechnic University
 
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catchers
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor CatchersTechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catchers
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catcherssdickerson1
 
FUNCTIONAL AND NON FUNCTIONAL REQUIREMENT
FUNCTIONAL AND NON FUNCTIONAL REQUIREMENTFUNCTIONAL AND NON FUNCTIONAL REQUIREMENT
FUNCTIONAL AND NON FUNCTIONAL REQUIREMENTSneha Padhiar
 
Robotics-Asimov's Laws, Mechanical Subsystems, Robot Kinematics, Robot Dynami...
Robotics-Asimov's Laws, Mechanical Subsystems, Robot Kinematics, Robot Dynami...Robotics-Asimov's Laws, Mechanical Subsystems, Robot Kinematics, Robot Dynami...
Robotics-Asimov's Laws, Mechanical Subsystems, Robot Kinematics, Robot Dynami...Sumanth A
 
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTION
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTIONTHE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTION
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTIONjhunlian
 
Katarzyna Lipka-Sidor - BIM School Course
Katarzyna Lipka-Sidor - BIM School CourseKatarzyna Lipka-Sidor - BIM School Course
Katarzyna Lipka-Sidor - BIM School Coursebim.edu.pl
 
Immutable Image-Based Operating Systems - EW2024.pdf
Immutable Image-Based Operating Systems - EW2024.pdfImmutable Image-Based Operating Systems - EW2024.pdf
Immutable Image-Based Operating Systems - EW2024.pdfDrew Moseley
 
Novel 3D-Printed Soft Linear and Bending Actuators
Novel 3D-Printed Soft Linear and Bending ActuatorsNovel 3D-Printed Soft Linear and Bending Actuators
Novel 3D-Printed Soft Linear and Bending ActuatorsResearcher Researcher
 
Energy Awareness training ppt for manufacturing process.pptx
Energy Awareness training ppt for manufacturing process.pptxEnergy Awareness training ppt for manufacturing process.pptx
Energy Awareness training ppt for manufacturing process.pptxsiddharthjain2303
 
Engineering Drawing section of solid
Engineering Drawing     section of solidEngineering Drawing     section of solid
Engineering Drawing section of solidnamansinghjarodiya
 
CME 397 - SURFACE ENGINEERING - UNIT 1 FULL NOTES
CME 397 - SURFACE ENGINEERING - UNIT 1 FULL NOTESCME 397 - SURFACE ENGINEERING - UNIT 1 FULL NOTES
CME 397 - SURFACE ENGINEERING - UNIT 1 FULL NOTESkarthi keyan
 
SOFTWARE ESTIMATION COCOMO AND FP CALCULATION
SOFTWARE ESTIMATION COCOMO AND FP CALCULATIONSOFTWARE ESTIMATION COCOMO AND FP CALCULATION
SOFTWARE ESTIMATION COCOMO AND FP CALCULATIONSneha Padhiar
 

Último (20)

Virtual memory management in Operating System
Virtual memory management in Operating SystemVirtual memory management in Operating System
Virtual memory management in Operating System
 
2022 AWS DNA Hackathon 장애 대응 솔루션 jarvis.
2022 AWS DNA Hackathon 장애 대응 솔루션 jarvis.2022 AWS DNA Hackathon 장애 대응 솔루션 jarvis.
2022 AWS DNA Hackathon 장애 대응 솔루션 jarvis.
 
『澳洲文凭』买麦考瑞大学毕业证书成绩单办理澳洲Macquarie文凭学位证书
『澳洲文凭』买麦考瑞大学毕业证书成绩单办理澳洲Macquarie文凭学位证书『澳洲文凭』买麦考瑞大学毕业证书成绩单办理澳洲Macquarie文凭学位证书
『澳洲文凭』买麦考瑞大学毕业证书成绩单办理澳洲Macquarie文凭学位证书
 
System Simulation and Modelling with types and Event Scheduling
System Simulation and Modelling with types and Event SchedulingSystem Simulation and Modelling with types and Event Scheduling
System Simulation and Modelling with types and Event Scheduling
 
Designing pile caps according to ACI 318-19.pptx
Designing pile caps according to ACI 318-19.pptxDesigning pile caps according to ACI 318-19.pptx
Designing pile caps according to ACI 318-19.pptx
 
OOP concepts -in-Python programming language
OOP concepts -in-Python programming languageOOP concepts -in-Python programming language
OOP concepts -in-Python programming language
 
Paper Tube : Shigeru Ban projects and Case Study of Cardboard Cathedral .pdf
Paper Tube : Shigeru Ban projects and Case Study of Cardboard Cathedral .pdfPaper Tube : Shigeru Ban projects and Case Study of Cardboard Cathedral .pdf
Paper Tube : Shigeru Ban projects and Case Study of Cardboard Cathedral .pdf
 
Levelling - Rise and fall - Height of instrument method
Levelling - Rise and fall - Height of instrument methodLevelling - Rise and fall - Height of instrument method
Levelling - Rise and fall - Height of instrument method
 
Comparative study of High-rise Building Using ETABS,SAP200 and SAFE., SAFE an...
Comparative study of High-rise Building Using ETABS,SAP200 and SAFE., SAFE an...Comparative study of High-rise Building Using ETABS,SAP200 and SAFE., SAFE an...
Comparative study of High-rise Building Using ETABS,SAP200 and SAFE., SAFE an...
 
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catchers
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor CatchersTechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catchers
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catchers
 
FUNCTIONAL AND NON FUNCTIONAL REQUIREMENT
FUNCTIONAL AND NON FUNCTIONAL REQUIREMENTFUNCTIONAL AND NON FUNCTIONAL REQUIREMENT
FUNCTIONAL AND NON FUNCTIONAL REQUIREMENT
 
Robotics-Asimov's Laws, Mechanical Subsystems, Robot Kinematics, Robot Dynami...
Robotics-Asimov's Laws, Mechanical Subsystems, Robot Kinematics, Robot Dynami...Robotics-Asimov's Laws, Mechanical Subsystems, Robot Kinematics, Robot Dynami...
Robotics-Asimov's Laws, Mechanical Subsystems, Robot Kinematics, Robot Dynami...
 
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTION
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTIONTHE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTION
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTION
 
Katarzyna Lipka-Sidor - BIM School Course
Katarzyna Lipka-Sidor - BIM School CourseKatarzyna Lipka-Sidor - BIM School Course
Katarzyna Lipka-Sidor - BIM School Course
 
Immutable Image-Based Operating Systems - EW2024.pdf
Immutable Image-Based Operating Systems - EW2024.pdfImmutable Image-Based Operating Systems - EW2024.pdf
Immutable Image-Based Operating Systems - EW2024.pdf
 
Novel 3D-Printed Soft Linear and Bending Actuators
Novel 3D-Printed Soft Linear and Bending ActuatorsNovel 3D-Printed Soft Linear and Bending Actuators
Novel 3D-Printed Soft Linear and Bending Actuators
 
Energy Awareness training ppt for manufacturing process.pptx
Energy Awareness training ppt for manufacturing process.pptxEnergy Awareness training ppt for manufacturing process.pptx
Energy Awareness training ppt for manufacturing process.pptx
 
Engineering Drawing section of solid
Engineering Drawing     section of solidEngineering Drawing     section of solid
Engineering Drawing section of solid
 
CME 397 - SURFACE ENGINEERING - UNIT 1 FULL NOTES
CME 397 - SURFACE ENGINEERING - UNIT 1 FULL NOTESCME 397 - SURFACE ENGINEERING - UNIT 1 FULL NOTES
CME 397 - SURFACE ENGINEERING - UNIT 1 FULL NOTES
 
SOFTWARE ESTIMATION COCOMO AND FP CALCULATION
SOFTWARE ESTIMATION COCOMO AND FP CALCULATIONSOFTWARE ESTIMATION COCOMO AND FP CALCULATION
SOFTWARE ESTIMATION COCOMO AND FP CALCULATION
 

[2020.2] PSOC - Unit_Commitment.pptx

  • 1. Unit Commitment © 2011 Daniel Kirschen and the University of Washington 1
  • 2. OVERVIEW OF UNIT COMMITMENT (Vertical System) © 2011 Daniel Kirschen and the University of Washington 2
  • 3. Economic Dispatch: Problem Definition • Given load • Given set of units on-line • How much should each unit generate to meet this load at minimum cost? © 2011 Daniel Kirschen and the University of Washington 3 A B C L
  • 4. Typical summer and winter loads © 2011 Daniel Kirschen and the University of Washington 4
  • 5. Unit Commitment • Given load profile (e.g. values of the load for each hour of a day) • Given set of units available • When should each unit be started, stopped and how much should it generate to meet the load at minimum cost? © 2011 Daniel Kirschen and the University of Washington 5 G G G Load Profile ? ? ?
  • 6. A Simple Example • Unit 1: • PMin = 250 MW, PMax = 600 MW • C1 = 510.0 + 7.9 P1 + 0.00172 P1 2 $/h • Unit 2: • PMin = 200 MW, PMax = 400 MW • C2 = 310.0 + 7.85 P2 + 0.00194 P2 2 $/h • Unit 3: • PMin = 150 MW, PMax = 500 MW • C3 = 78.0 + 9.56 P3 + 0.00694 P3 2 $/h • What combination of units 1, 2 and 3 will produce 550 MW at minimum cost? • How much should each unit in that combination generate? © 2011 Daniel Kirschen and the University of Washington 6
  • 7. Cost of the various combinations © 2011 Daniel Kirschen and the University of Washington 7
  • 8. Observations on the example: • Far too few units committed: Can’t meet the demand • Not enough units committed: Some units operate above optimum • Too many units committed: Some units below optimum • Far too many units committed: Minimum generation exceeds demand • No-load cost affects choice of optimal combination © 2011 Daniel Kirschen and the University of Washington 8
  • 9. A more ambitious example • Optimal generation schedule for a load profile • Decompose the profile into a set of period • Assume load is constant over each period • For each time period, which units should be committed to generate at minimum cost during that period? © 2011 Daniel Kirschen and the University of Washington 9 Load Time 12 6 0 18 24 500 1000
  • 10. Optimal combination for each hour © 2011 Daniel Kirschen and the University of Washington 10
  • 11. Matching the combinations to the load © 2011 Daniel Kirschen and the University of Washington 11 Load Time 12 6 0 18 24 Unit 1 Unit 2 Unit 3
  • 12. Issues • Must consider constraints – Unit constraints – System constraints • Some constraints create a link between periods • Start-up costs – Cost incurred when we start a generating unit – Different units have different start-up costs • Curse of dimensionality © 2011 Daniel Kirschen and the University of Washington 12
  • 13. Unit Constraints • Constraints that affect each unit individually: –Maximum generating capacity –Minimum stable generation –Minimum “up time” –Minimum “down time” –Ramp rate © 2011 Daniel Kirschen and the University of Washington 13
  • 14. Notations © 2011 Daniel Kirschen and the University of Washington 14 u(i,t): Status of unit i at period t x(i,t): Power produced by unit i during period t Unit i is on during period t u(i,t) =1: Unit i is off during period t u(i,t) = 0 :
  • 15. Minimum up- and down-time • Minimum up time – Once a unit is running it may not be shut down immediately: • Minimum down time – Once a unit is shut down, it may not be started immediately © 2011 Daniel Kirschen and the University of Washington 15 If u(i,t) =1 and ti up < ti up,min then u(i,t +1) =1 If u(i,t) = 0 and ti down < ti down,min then u(i,t +1) = 0
  • 16. Ramp rates • Maximum ramp rates – To avoid damaging the turbine, the electrical output of a unit cannot change by more than a certain amount over a period of time: © 2011 Daniel Kirschen and the University of Washington 16 x i,t +1 ( )- x i,t ( )£ DPi up,max x(i,t)- x(i,t +1) £ DPi down,max Maximum ramp up rate constraint: Maximum ramp down rate constraint:
  • 17. System Constraints • Constraints that affect more than one unit – Load/generation balance – Reserve generation capacity – Emission constraints – Network constraints © 2011 Daniel Kirschen and the University of Washington 17
  • 18. Load/Generation Balance Constraint © 2011 Daniel Kirschen and the University of Washington 18 u(i,t)x(i,t) i=1 N å = L(t) N : Set of available units
  • 19. Reserve Capacity Constraint • Unanticipated loss of a generating unit or an interconnection causes unacceptable frequency drop if not corrected rapidly • Need to increase production from other units to keep frequency drop within acceptable limits • Rapid increase in production only possible if committed units are not all operating at their maximum capacity © 2011 Daniel Kirschen and the University of Washington 19 u(i,t) i=1 N å Pi max ³ L(t)+ R(t) R(t): Reserve requirement at time t
  • 20. How much reserve? • Protect the system against “credible outages” • Deterministic criteria: – Capacity of largest unit or interconnection – Percentage of peak load • Probabilistic criteria: – Takes into account the number and size of the committed units as well as their outage rate © 2011 Daniel Kirschen and the University of Washington 20
  • 21. Types of Reserve • Spinning reserve – Primary • Quick response for a short time – Secondary • Slower response for a longer time • Tertiary reserve – Replace primary and secondary reserve to protect against another outage – Provided by units that can start quickly (e.g. open cycle gas turbines) – Also called scheduled or off-line reserve © 2011 Daniel Kirschen and the University of Washington 21
  • 22. Types of Reserve • Positive reserve – Increase output when generation < load • Negative reserve – Decrease output when generation > load • Other sources of reserve: – Pumped hydro plants – Demand reduction (e.g. voluntary load shedding) • Reserve must be spread around the network – Must be able to deploy reserve even if the network is congested © 2011 Daniel Kirschen and the University of Washington 22
  • 23. Cost of Reserve • Reserve has a cost even when it is not called • More units scheduled than required – Units not operated at their maximum efficiency – Extra start up costs • Must build units capable of rapid response • Cost of reserve proportionally larger in small systems • Important driver for the creation of interconnections between systems © 2011 Daniel Kirschen and the University of Washington 23
  • 24. Environmental constraints • Scheduling of generating units may be affected by environmental constraints • Constraints on pollutants such SO2, NOx – Various forms: • Limit on each plant at each hour • Limit on plant over a year • Limit on a group of plants over a year • Constraints on hydro generation – Protection of wildlife – Navigation, recreation © 2011 Daniel Kirschen and the University of Washington 24
  • 25. Network Constraints • Transmission network may have an effect on the commitment of units – Some units must run to provide voltage support – The output of some units may be limited because their output would exceed the transmission capacity of the network © 2011 Daniel Kirschen and the University of Washington 25 Cheap generators May be “constrained off” More expensive generator May be “constrained on” A B
  • 26. Start-up Costs • Thermal units must be “warmed up” before they can be brought on-line • Warming up a unit costs money • Start-up cost depends on time unit has been off © 2011 Daniel Kirschen and the University of Washington 26 SCi (ti OFF ) = ai + bi (1 - e - ti OFF t i ) ti OFF αi αi + βi
  • 27. Start-up Costs • Need to “balance” start-up costs and running costs • Example: – Diesel generator: low start-up cost, high running cost – Coal plant: high start-up cost, low running cost • Issues: – How long should a unit run to “recover” its start-up cost? – Start-up one more large unit or a diesel generator to cover the peak? – Shutdown one more unit at night or run several units part- loaded? © 2011 Daniel Kirschen and the University of Washington 27
  • 28. Summary • Some constraints link periods together • Minimizing the total cost (start-up + running) must be done over the whole period of study • Generation scheduling or unit commitment is a more general problem than economic dispatch • Economic dispatch is a sub-problem of generation scheduling © 2011 Daniel Kirschen and the University of Washington 28
  • 29. Flexible Plants • Power output can be adjusted (within limits) • Examples: – Coal-fired – Oil-fired – Open cycle gas turbines – Combined cycle gas turbines – Hydro plants with storage • Status and power output can be optimized © 2011 Daniel Kirschen and the University of Washington 29 Thermal units
  • 30. Inflexible Plants • Power output cannot be adjusted for technical or commercial reasons • Examples: – Nuclear – Run-of-the-river hydro – Renewables (wind, solar,…) – Combined heat and power (CHP, cogeneration) • Output treated as given when optimizing © 2011 Daniel Kirschen and the University of Washington 30
  • 31. Solving the Unit Commitment Problem • Decision variables: – Status of each unit at each period: – Output of each unit at each period: • Combination of integer and continuous variables © 2011 Daniel Kirschen and the University of Washington 31 u(i,t) Î 0,1 { } " i,t x(i,t) Î 0, Pi min ;Pi max é ë ù û { } " i,t
  • 32. Optimization with integer variables • Continuous variables – Can follow the gradients or use LP – Any value within the feasible set is OK • Discrete variables – There is no gradient – Can only take a finite number of values – Problem is not convex – Must try combinations of discrete values © 2011 Daniel Kirschen and the University of Washington 32
  • 33. How many combinations are there? © 2011 Daniel Kirschen and the University of Washington 33 • Examples – 3 units: 8 possible states – N units: 2N possible states 111 110 101 100 011 010 001 000
  • 34. How many solutions are there anyway? © 2011 Daniel Kirschen and the University of Washington 34 1 2 3 4 5 6 T= • Optimization over a time horizon divided into intervals • A solution is a path linking one combination at each interval • How many such paths are there?
  • 35. How many solutions are there anyway? © 2011 Daniel Kirschen and the University of Washington 35 1 2 3 4 5 6 T= Optimization over a time horizon divided into intervals A solution is a path linking one combination at each interval How many such path are there? Answer: 2N ( ) 2N ( )… 2N ( ) = 2N ( )T
  • 36. The Curse of Dimensionality • Example: 5 units, 24 hours • Processing 109 combinations/second, this would take 1.9 1019 years to solve • There are 100’s of units in large power systems... • Many of these combinations do not satisfy the constraints © 2011 Daniel Kirschen and the University of Washington 36 2N ( ) T = 25 ( ) 24 = 6.21035 combinations
  • 37. How do you Beat the Curse? Brute force approach won’t work! • Need to be smart • Try only a small subset of all combinations • Can’t guarantee optimality of the solution • Try to get as close as possible within a reasonable amount of time © 2011 Daniel Kirschen and the University of Washington 37
  • 38. Main Solution Techniques • Characteristics of a good technique – Solution close to the optimum – Reasonable computing time – Ability to model constraints • Priority list / heuristic approach • Dynamic programming • Lagrangian relaxation • Mixed Integer Programming © 2011 Daniel Kirschen and the University of Washington 38 State of the art
  • 39. A Simple Unit Commitment Example © 2011 Daniel Kirschen and the University of Washington 39
  • 40. Unit Data © 2011 Daniel Kirschen and the University of Washington 40 Unit Pmin (MW) Pmax (MW) Min up (h) Min down (h) No-load cost ($) Marginal cost ($/MWh) Start-up cost ($) Initial status A 150 250 3 3 0 10 1,000 ON B 50 100 2 1 0 12 600 OFF C 10 50 1 1 0 20 100 OFF
  • 41. Demand Data © 2011 Daniel Kirschen and the University of Washington 41 Hourly Demand 0 50 100 150 200 250 300 350 1 2 3 Hours Load Reserve requirements are not considered
  • 42. Feasible Unit Combinations (states) © 2011 Daniel Kirschen and the University of Washington 42 Combinations Pmin Pmax A B C 1 1 1 210 400 1 1 0 200 350 1 0 1 160 300 1 0 0 150 250 0 1 1 60 150 0 1 0 50 100 0 0 1 10 50 0 0 0 0 0 1 2 3 150 300 200
  • 43. Transitions between feasible combinations © 2011 Daniel Kirschen and the University of Washington 43 A B C 1 1 1 1 1 0 1 0 1 1 0 0 0 1 1 1 2 3 Initial State
  • 44. Infeasible transitions: Minimum down time of unit A © 2011 Daniel Kirschen and the University of Washington 44 A B C 1 1 1 1 1 0 1 0 1 1 0 0 0 1 1 1 2 3 Initial State TD TU A 3 3 B 1 2 C 1 1
  • 45. Infeasible transitions: Minimum up time of unit B © 2011 Daniel Kirschen and the University of Washington 45 A B C 1 1 1 1 1 0 1 0 1 1 0 0 0 1 1 1 2 3 Initial State TD TU A 3 3 B 1 2 C 1 1
  • 46. Feasible transitions © 2011 Daniel Kirschen and the University of Washington 46 A B C 1 1 1 1 1 0 1 0 1 1 0 0 0 1 1 1 2 3 Initial State
  • 47. Operating costs © 2011 Daniel Kirschen and the University of Washington 47 1 1 1 1 1 0 1 0 1 1 0 0 1 4 3 2 5 6 7
  • 48. Economic dispatch © 2011 Daniel Kirschen and the University of Washington 48 State Load PA PB PC Cost 1 150 150 0 0 1500 2 300 250 0 50 3500 3 300 250 50 0 3100 4 300 240 50 10 3200 5 200 200 0 0 2000 6 200 190 0 10 2100 7 200 150 50 0 2100 Unit Pmin Pmax No-load cost Marginal cost A 150 250 0 10 B 50 100 0 12 C 10 50 0 20
  • 49. Operating costs © 2011 Daniel Kirschen and the University of Washington 49 1 1 1 1 1 0 1 0 1 1 0 0 1 4 3 2 5 6 7 $1500 $3500 $3100 $3200 $2000 $2100 $2100
  • 50. Start-up costs © 2011 Daniel Kirschen and the University of Washington 50 1 1 1 1 1 0 1 0 1 1 0 0 1 4 3 2 5 6 7 $1500 $3500 $3100 $3200 $2000 $2100 $2100 Unit Start-up cost A 1000 B 600 C 100 $0 $0 $0 $0 $0 $600 $100 $600 $700
  • 51. Accumulated costs © 2011 Daniel Kirschen and the University of Washington 51 1 1 1 1 1 0 1 0 1 1 0 0 1 4 3 2 5 6 7 $1500 $3500 $3100 $3200 $2000 $2100 $2100 $1500 $5100 $5200 $5400 $7300 $7200 $7100 $0 $0 $0 $0 $0 $600 $100 $600 $700
  • 52. Total costs © 2011 Daniel Kirschen and the University of Washington 52 1 1 1 1 1 0 1 0 1 1 0 0 1 4 3 2 5 6 7 $7300 $7200 $7100 Lowest total cost
  • 53. Optimal solution © 2011 Daniel Kirschen and the University of Washington 53 1 1 1 1 1 0 1 0 1 1 0 0 1 2 5 $7100
  • 54. Notes • This example is intended to illustrate the principles of unit commitment • Some constraints have been ignored and others artificially tightened to simplify the problem and make it solvable by hand • Therefore it does not illustrate the true complexity of the problem • The solution method used in this example is based on dynamic programming. This technique is no longer used in industry because it only works for small systems (< 20 units) © 2011 Daniel Kirschen and the University of Washington 54
  • 55. OVERVIEW OF UNIT COMMITMENT (Unbundled System) © 2011 Daniel Kirschen and the University of Washington 55
  • 56. Market-Clearing Price Aggregate Demand Aggregate Supply Price ($) MCP Quantity (MW) Stochastic Model of Market-Clearing Price: MCP determined by load and availability of generating units prevailing at a particular time. Units are loaded in a predetermined Loading order MCP is marginal cost of the last unit loaded to meet the load.