SlideShare uma empresa Scribd logo
1 de 20
NATIONAL INSTITUTE OF TECHNOLOGY
           WARANGAL.




       PRESENTATION BY….
                      R.RAGHAVENDRA
                           CTM, 12568
CONTENTS
    :
 1.   INTRODUCTION TO fORm wORk
 2.   DesIgN ReqUIRemeNTs
 3.   ClassIfICaTION CRITeRIa
 4.   JUmp fORm
 5.   TYpes Of JUmp fORm
 6.   pROCess effICIeNCY
 7.   safeTY & sUsTaINaBle feaTURes
 8.   CONsIDeRaTIONs
 9.   RefeReNCes
INTRODUCTION
      :
 For the different construction activities like
      Brick work above 5 ft
      Surface finishing works like plastering, painting, walling etc.
      Renovation, repair and alteration works.
      Roof and slab pouring

   Some temporary nature supports and structures are required like

      Formwork       (Supporting Structure)
      Scaffoldings (arrangement for working plate forms)
      Shoring       (supporting method for unsafe structure)
      Underpinning (Method of strengthening an existing structure’s
                footing)
WHAT IS
          FORMWORK:
         Formwork are temporary structures that are built to
    support parts or the whole of a permanent structure until
    it is self-supporting.

       Formwork means the surface, support and framing
    used to define the shape of concrete until it is self-
    supporting.
Design Requirements:
 • Strength

 • Speedy erection and dismantling

 • Tightness of joints

 • Rigidity

 • Reuse

 • Ease of handling
Classification Criteria for
Formwork :-
 o Classification according to size

 o Classification according to the location of use

 o Classification according to materials of construction

 o Classification according to nature of operation

 o Classification according to brand name of the product
TYPES OF WALL
   FORMWORK
  (Based on nature of operation)



 JUMP FORM

 SLIP FORM

 TUNNEL FORM
JUMP FORM:
        Generally, jump form systems comprise the
    formwork and working platforms for cleaning/fixing of
    the formwork, steel fixing and concreting.

    Jump form, often described as climbing form. It is
    suitable for construction of multi-storey vertical concrete
    elements in high-rise structures, such as shear walls, core
    walls, lift shafts, stair shafts and bridge pylons.

       It is a highly productive system designed to increase
    speed and efficiency while minimizing labor and time.
TYPES OF JUMP
    FORMWORK

 Normal jump/climbing form

 Guided-climbing jump form

 Self-climbing jump form
WALL FORMING – JUMP FORM
SELF CLIMBING JUMP FORM
PROCESS EFFICIENCY :

 Fast construction can be achieved by careful planning of the
  construction process. Crane availability is critical for normal jump
  form.
 Self-climbing formwork cuts down the requirement for crane time
  considerably. By allowing the crane to be used for other
  construction work this may reduce the total number of cranes
  needed on site.
 The formwork is independently supported, so the shear walls and
  core walls can be completed ahead of the rest of the main building
  structure. This can help to provide stability to the main structure
  during its construction and can have the beneficial effect of taking
  the jump form core off the project critical path.
CONTINUED…

 High quality surface finishes are possible.
 Climbing forms can be designed to operate in high winds (when
  the use of a crane is less viable). This allows construction work to
  be carried out at reduced risk from adverse weather.
 The highly engineered nature of jump form systems allows quick
  and precise adjustment of the formwork in all planes.
 Some formwork systems can be used at an inclined angle, which
  is particularly useful on bridge pylons or where walls vary in
  thickness.
 A small but skilled workforce is required on site.
 It is easier to plan construction activities due to the repetitive
  nature of the work.
SAFETY :
 Working platforms, guard rails, and ladders are built into the
  completed units of market-leading formwork systems. Complete
  wind-shield protection on platform edges is also possible.
 Self-climbing formwork systems are provided with integral free-
  fall braking devices.
 The completed formwork assembly is robust and provides a stable
  working platform.
 The reduced use of scaffolding and temporary work platforms
  results in less congestion on site.
 The setting rate of concrete in those parts of the structure
  supporting the form is critical in determining the rate at which
  construction can safely proceed.
 The repetitive nature of the work means that site operatives can
  quickly become familiar with health and safety aspects of their
  job. Formwork suppliers provide materials and resources to help
  train the labour force.
SUSTAINABILITY
          FEATURES :
 The formwork system is easy to clean and reuse with little
  formwork waste generated compared to traditional formwork.

 Climbing formwork systems offer simplicity, safety and cost
  effectiveness for certain high-rise building structures.

 The repetitive nature of the work, combined with the engineered
  nature of the formwork, allows fine tuning of the construction
  operations, which in turn leads to minimal concrete wastage.

 Many repeated uses of formwork are possible before maintenance
  or replacement is needed, the number of uses depending on the
  quality of the surface finish of concrete specified.
CONSIDERATIONS :
       Jump form is typically used on buildings of 5 storey's or
    more; fully self-climbing systems are generally used on structures
    with more than 20 floor levels.


        Assembly and lifting operations for self-climbing formwork
    systems require personnel to be comprehensively trained to ensure
    competence.


        The raising operation must be carefully planned and
    coordinated, and access to the working area during lifting should
    be restricted to essential personnel.
REFERENCES
     :
 “FORMWORK FOR MODERN, EFFICIENT
  CONCRETE CONSTRUCTION” BY Rohan
  Rupasinghe and Éanna Nolan, BRE


 WWW.YOUTUBE.COM


 HTTP://EN.WIKIPEDIA.ORG
?



R.RAGHAVENDRA
Jump Formwork

Mais conteúdo relacionado

Mais procurados

Building Construction
Building ConstructionBuilding Construction
Building ConstructionWilden How
 
Basement construction report
Basement construction reportBasement construction report
Basement construction reportANKITAARORA85
 
Alternate Building Materials,Alternative Construction Technology and Rain Wat...
Alternate Building Materials,Alternative Construction Technology and Rain Wat...Alternate Building Materials,Alternative Construction Technology and Rain Wat...
Alternate Building Materials,Alternative Construction Technology and Rain Wat...Rajesh Kolli
 
Earthquake resistant building technologies
Earthquake resistant building technologiesEarthquake resistant building technologies
Earthquake resistant building technologiesMyo Zin Aung
 
Slip form Construction Technology
Slip form Construction TechnologySlip form Construction Technology
Slip form Construction TechnologyDarshit
 
Precast construction
Precast constructionPrecast construction
Precast constructionDivya Vishnoi
 
high rise building construction
high rise building constructionhigh rise building construction
high rise building constructionAditya Sanyal
 
High-rise structural systems
High-rise structural systemsHigh-rise structural systems
High-rise structural systemsAkshay Revekar
 
Underground construction
Underground constructionUnderground construction
Underground constructionPavan Kumar N
 
Earthquake resistance in buildings
Earthquake resistance in buildingsEarthquake resistance in buildings
Earthquake resistance in buildingsRithika Ravishankar
 
High rise buildings
High rise buildingsHigh rise buildings
High rise buildingsAnas Adel
 
Diaphragm wall construction
Diaphragm wall constructionDiaphragm wall construction
Diaphragm wall constructionABHISHEK THAKKAE
 
Slipform construction
Slipform constructionSlipform construction
Slipform constructiontivar rose
 
Prefabrication construction
Prefabrication constructionPrefabrication construction
Prefabrication constructionDivya Vishnoi
 
Temporary Work in Building Construction
Temporary Work in Building ConstructionTemporary Work in Building Construction
Temporary Work in Building ConstructionEr.Karan Chauhan
 
ADVANCED TECHNIQUES IN CONSTRUCTIONS IN HIGH RISE BUILDINGS
ADVANCED TECHNIQUES IN CONSTRUCTIONS IN HIGH RISE BUILDINGSADVANCED TECHNIQUES IN CONSTRUCTIONS IN HIGH RISE BUILDINGS
ADVANCED TECHNIQUES IN CONSTRUCTIONS IN HIGH RISE BUILDINGSASHOK KUMAR TIWARY
 

Mais procurados (20)

Reinforced brickwork
Reinforced brickworkReinforced brickwork
Reinforced brickwork
 
Building Construction
Building ConstructionBuilding Construction
Building Construction
 
Basement construction report
Basement construction reportBasement construction report
Basement construction report
 
Alternate Building Materials,Alternative Construction Technology and Rain Wat...
Alternate Building Materials,Alternative Construction Technology and Rain Wat...Alternate Building Materials,Alternative Construction Technology and Rain Wat...
Alternate Building Materials,Alternative Construction Technology and Rain Wat...
 
Earthquake resistant building technologies
Earthquake resistant building technologiesEarthquake resistant building technologies
Earthquake resistant building technologies
 
Slip form Construction Technology
Slip form Construction TechnologySlip form Construction Technology
Slip form Construction Technology
 
Precast construction
Precast constructionPrecast construction
Precast construction
 
Staircase
StaircaseStaircase
Staircase
 
high rise building construction
high rise building constructionhigh rise building construction
high rise building construction
 
PreCast Construction
PreCast ConstructionPreCast Construction
PreCast Construction
 
High-rise structural systems
High-rise structural systemsHigh-rise structural systems
High-rise structural systems
 
Underground construction
Underground constructionUnderground construction
Underground construction
 
Earthquake resistance in buildings
Earthquake resistance in buildingsEarthquake resistance in buildings
Earthquake resistance in buildings
 
High rise buildings
High rise buildingsHigh rise buildings
High rise buildings
 
Diaphragm wall construction
Diaphragm wall constructionDiaphragm wall construction
Diaphragm wall construction
 
Slipform construction
Slipform constructionSlipform construction
Slipform construction
 
Prefabrication construction
Prefabrication constructionPrefabrication construction
Prefabrication construction
 
Temporary Work in Building Construction
Temporary Work in Building ConstructionTemporary Work in Building Construction
Temporary Work in Building Construction
 
ADVANCED TECHNIQUES IN CONSTRUCTIONS IN HIGH RISE BUILDINGS
ADVANCED TECHNIQUES IN CONSTRUCTIONS IN HIGH RISE BUILDINGSADVANCED TECHNIQUES IN CONSTRUCTIONS IN HIGH RISE BUILDINGS
ADVANCED TECHNIQUES IN CONSTRUCTIONS IN HIGH RISE BUILDINGS
 
Steel formwork
Steel formworkSteel formwork
Steel formwork
 

Semelhante a Jump Formwork

Super Structure Construction.pptx
Super Structure Construction.pptxSuper Structure Construction.pptx
Super Structure Construction.pptxAnanthakumar75
 
Chapters-3,4,5.pptx
Chapters-3,4,5.pptxChapters-3,4,5.pptx
Chapters-3,4,5.pptxssuserc0bf9b
 
Building construction report
Building construction  reportBuilding construction  report
Building construction reportAprajeeta Singh
 
Case Study: High Rise Buildings
Case Study: High Rise BuildingsCase Study: High Rise Buildings
Case Study: High Rise BuildingsPrasad Thanthratey
 
Construction Technology
Construction TechnologyConstruction Technology
Construction TechnologySwapnilGorade1
 
Slip formwork for chimney
Slip formwork for chimneySlip formwork for chimney
Slip formwork for chimneyAxay Sharma
 
Slipform construction
Slipform constructionSlipform construction
Slipform constructionErankajKumar
 
Presentation on MIVAN -- A versatile aluminum formwork construction technique
Presentation on MIVAN -- A versatile aluminum formwork construction techniquePresentation on MIVAN -- A versatile aluminum formwork construction technique
Presentation on MIVAN -- A versatile aluminum formwork construction techniqueIEI GSC
 
BQS Site Visit Report
BQS Site Visit ReportBQS Site Visit Report
BQS Site Visit ReportHasif Alias
 
MIVAN_An Aluminum Formwork Construction Technique
MIVAN_An Aluminum Formwork Construction TechniqueMIVAN_An Aluminum Formwork Construction Technique
MIVAN_An Aluminum Formwork Construction TechniqueSandeep Jain
 
PREFAB CONSTRUCTION .pdf
PREFAB CONSTRUCTION .pdfPREFAB CONSTRUCTION .pdf
PREFAB CONSTRUCTION .pdfGourhariBiswas1
 
Speedy construction- FORMS AND MATERIALS
Speedy construction- FORMS AND MATERIALSSpeedy construction- FORMS AND MATERIALS
Speedy construction- FORMS AND MATERIALSSOUMYA KHANDELWAL
 
MODERN CONSTRUCTION TECHNOLOGIES IN ENGINEERING PERSPECTIVE
MODERN CONSTRUCTION TECHNOLOGIES IN ENGINEERING PERSPECTIVEMODERN CONSTRUCTION TECHNOLOGIES IN ENGINEERING PERSPECTIVE
MODERN CONSTRUCTION TECHNOLOGIES IN ENGINEERING PERSPECTIVEDr K M SONI
 
Form-woks-additional.pptx
Form-woks-additional.pptxForm-woks-additional.pptx
Form-woks-additional.pptxssuserc0bf9b
 

Semelhante a Jump Formwork (20)

Table formwork
Table formwork Table formwork
Table formwork
 
Super Structure Construction.pptx
Super Structure Construction.pptxSuper Structure Construction.pptx
Super Structure Construction.pptx
 
Chapters-3,4,5.pptx
Chapters-3,4,5.pptxChapters-3,4,5.pptx
Chapters-3,4,5.pptx
 
Building construction report
Building construction  reportBuilding construction  report
Building construction report
 
Case Study: High Rise Buildings
Case Study: High Rise BuildingsCase Study: High Rise Buildings
Case Study: High Rise Buildings
 
Construction Technology
Construction TechnologyConstruction Technology
Construction Technology
 
Slip formwork for chimney
Slip formwork for chimneySlip formwork for chimney
Slip formwork for chimney
 
Slipform construction
Slipform constructionSlipform construction
Slipform construction
 
Presentation on MIVAN -- A versatile aluminum formwork construction technique
Presentation on MIVAN -- A versatile aluminum formwork construction techniquePresentation on MIVAN -- A versatile aluminum formwork construction technique
Presentation on MIVAN -- A versatile aluminum formwork construction technique
 
Slip form
Slip formSlip form
Slip form
 
BQS Site Visit Report
BQS Site Visit ReportBQS Site Visit Report
BQS Site Visit Report
 
MIVAN_An Aluminum Formwork Construction Technique
MIVAN_An Aluminum Formwork Construction TechniqueMIVAN_An Aluminum Formwork Construction Technique
MIVAN_An Aluminum Formwork Construction Technique
 
PREFAB CONSTRUCTION .pdf
PREFAB CONSTRUCTION .pdfPREFAB CONSTRUCTION .pdf
PREFAB CONSTRUCTION .pdf
 
Precast concrete
Precast concretePrecast concrete
Precast concrete
 
Speedy construction- FORMS AND MATERIALS
Speedy construction- FORMS AND MATERIALSSpeedy construction- FORMS AND MATERIALS
Speedy construction- FORMS AND MATERIALS
 
Ct report
Ct reportCt report
Ct report
 
Ct report
Ct reportCt report
Ct report
 
Ct report
Ct reportCt report
Ct report
 
MODERN CONSTRUCTION TECHNOLOGIES IN ENGINEERING PERSPECTIVE
MODERN CONSTRUCTION TECHNOLOGIES IN ENGINEERING PERSPECTIVEMODERN CONSTRUCTION TECHNOLOGIES IN ENGINEERING PERSPECTIVE
MODERN CONSTRUCTION TECHNOLOGIES IN ENGINEERING PERSPECTIVE
 
Form-woks-additional.pptx
Form-woks-additional.pptxForm-woks-additional.pptx
Form-woks-additional.pptx
 

Mais de Raghavendra Rachamadugu

The Implementation of QMS in construction industry
The Implementation of QMS in construction industryThe Implementation of QMS in construction industry
The Implementation of QMS in construction industryRaghavendra Rachamadugu
 
PORTER’s five forces model for MARUTI SUZUKI
PORTER’s five forces model for MARUTI SUZUKIPORTER’s five forces model for MARUTI SUZUKI
PORTER’s five forces model for MARUTI SUZUKIRaghavendra Rachamadugu
 
GREEN BUILDING STRATEGIES & PROJECT MANAGEMENT PRACTICES FOR A SUSTAINABLE FU...
GREEN BUILDING STRATEGIES & PROJECT MANAGEMENT PRACTICES FOR A SUSTAINABLE FU...GREEN BUILDING STRATEGIES & PROJECT MANAGEMENT PRACTICES FOR A SUSTAINABLE FU...
GREEN BUILDING STRATEGIES & PROJECT MANAGEMENT PRACTICES FOR A SUSTAINABLE FU...Raghavendra Rachamadugu
 
Designing buildings to meet climate change challenges
Designing buildings to meet climate change challengesDesigning buildings to meet climate change challenges
Designing buildings to meet climate change challengesRaghavendra Rachamadugu
 
Case study of G+2 Structure located at railway quarters, warangal
Case study of G+2 Structure located at railway quarters, warangalCase study of G+2 Structure located at railway quarters, warangal
Case study of G+2 Structure located at railway quarters, warangalRaghavendra Rachamadugu
 
Presentation on using industrial waste water in making of plain concrete @ in...
Presentation on using industrial waste water in making of plain concrete @ in...Presentation on using industrial waste water in making of plain concrete @ in...
Presentation on using industrial waste water in making of plain concrete @ in...Raghavendra Rachamadugu
 
Presentation on liquefation @ pvkk by raghavendra
Presentation on liquefation @ pvkk by raghavendraPresentation on liquefation @ pvkk by raghavendra
Presentation on liquefation @ pvkk by raghavendraRaghavendra Rachamadugu
 
Presentation on robosand @ crit by raghavendra
Presentation on robosand @ crit by raghavendraPresentation on robosand @ crit by raghavendra
Presentation on robosand @ crit by raghavendraRaghavendra Rachamadugu
 
Presentation on rating & strengthening of bridges @ jntu hyd by raghavendra
Presentation on rating & strengthening of bridges @ jntu hyd by raghavendraPresentation on rating & strengthening of bridges @ jntu hyd by raghavendra
Presentation on rating & strengthening of bridges @ jntu hyd by raghavendraRaghavendra Rachamadugu
 

Mais de Raghavendra Rachamadugu (13)

The Implementation of QMS in construction industry
The Implementation of QMS in construction industryThe Implementation of QMS in construction industry
The Implementation of QMS in construction industry
 
PORTER’s five forces model for MARUTI SUZUKI
PORTER’s five forces model for MARUTI SUZUKIPORTER’s five forces model for MARUTI SUZUKI
PORTER’s five forces model for MARUTI SUZUKI
 
GREEN BUILDING STRATEGIES & PROJECT MANAGEMENT PRACTICES FOR A SUSTAINABLE FU...
GREEN BUILDING STRATEGIES & PROJECT MANAGEMENT PRACTICES FOR A SUSTAINABLE FU...GREEN BUILDING STRATEGIES & PROJECT MANAGEMENT PRACTICES FOR A SUSTAINABLE FU...
GREEN BUILDING STRATEGIES & PROJECT MANAGEMENT PRACTICES FOR A SUSTAINABLE FU...
 
Designing buildings to meet climate change challenges
Designing buildings to meet climate change challengesDesigning buildings to meet climate change challenges
Designing buildings to meet climate change challenges
 
Case study of G+2 Structure located at railway quarters, warangal
Case study of G+2 Structure located at railway quarters, warangalCase study of G+2 Structure located at railway quarters, warangal
Case study of G+2 Structure located at railway quarters, warangal
 
CASE STUDY OF WAKOTA BRIDGE
CASE STUDY OF WAKOTA BRIDGECASE STUDY OF WAKOTA BRIDGE
CASE STUDY OF WAKOTA BRIDGE
 
Presentation on using industrial waste water in making of plain concrete @ in...
Presentation on using industrial waste water in making of plain concrete @ in...Presentation on using industrial waste water in making of plain concrete @ in...
Presentation on using industrial waste water in making of plain concrete @ in...
 
Construction Equipment Management
Construction Equipment ManagementConstruction Equipment Management
Construction Equipment Management
 
Emmar
EmmarEmmar
Emmar
 
Feasibility Report of Hyd Metro
Feasibility Report of Hyd MetroFeasibility Report of Hyd Metro
Feasibility Report of Hyd Metro
 
Presentation on liquefation @ pvkk by raghavendra
Presentation on liquefation @ pvkk by raghavendraPresentation on liquefation @ pvkk by raghavendra
Presentation on liquefation @ pvkk by raghavendra
 
Presentation on robosand @ crit by raghavendra
Presentation on robosand @ crit by raghavendraPresentation on robosand @ crit by raghavendra
Presentation on robosand @ crit by raghavendra
 
Presentation on rating & strengthening of bridges @ jntu hyd by raghavendra
Presentation on rating & strengthening of bridges @ jntu hyd by raghavendraPresentation on rating & strengthening of bridges @ jntu hyd by raghavendra
Presentation on rating & strengthening of bridges @ jntu hyd by raghavendra
 

Jump Formwork

  • 1. NATIONAL INSTITUTE OF TECHNOLOGY WARANGAL. PRESENTATION BY…. R.RAGHAVENDRA CTM, 12568
  • 2. CONTENTS : 1. INTRODUCTION TO fORm wORk 2. DesIgN ReqUIRemeNTs 3. ClassIfICaTION CRITeRIa 4. JUmp fORm 5. TYpes Of JUmp fORm 6. pROCess effICIeNCY 7. safeTY & sUsTaINaBle feaTURes 8. CONsIDeRaTIONs 9. RefeReNCes
  • 3. INTRODUCTION :  For the different construction activities like  Brick work above 5 ft  Surface finishing works like plastering, painting, walling etc.  Renovation, repair and alteration works.  Roof and slab pouring Some temporary nature supports and structures are required like  Formwork (Supporting Structure)  Scaffoldings (arrangement for working plate forms)  Shoring (supporting method for unsafe structure)  Underpinning (Method of strengthening an existing structure’s footing)
  • 4. WHAT IS FORMWORK:  Formwork are temporary structures that are built to support parts or the whole of a permanent structure until it is self-supporting.  Formwork means the surface, support and framing used to define the shape of concrete until it is self- supporting.
  • 5. Design Requirements: • Strength • Speedy erection and dismantling • Tightness of joints • Rigidity • Reuse • Ease of handling
  • 6. Classification Criteria for Formwork :- o Classification according to size o Classification according to the location of use o Classification according to materials of construction o Classification according to nature of operation o Classification according to brand name of the product
  • 7. TYPES OF WALL FORMWORK (Based on nature of operation)  JUMP FORM  SLIP FORM  TUNNEL FORM
  • 8. JUMP FORM:  Generally, jump form systems comprise the formwork and working platforms for cleaning/fixing of the formwork, steel fixing and concreting. Jump form, often described as climbing form. It is suitable for construction of multi-storey vertical concrete elements in high-rise structures, such as shear walls, core walls, lift shafts, stair shafts and bridge pylons.  It is a highly productive system designed to increase speed and efficiency while minimizing labor and time.
  • 9.
  • 10. TYPES OF JUMP FORMWORK  Normal jump/climbing form  Guided-climbing jump form  Self-climbing jump form
  • 11. WALL FORMING – JUMP FORM
  • 13. PROCESS EFFICIENCY :  Fast construction can be achieved by careful planning of the construction process. Crane availability is critical for normal jump form.  Self-climbing formwork cuts down the requirement for crane time considerably. By allowing the crane to be used for other construction work this may reduce the total number of cranes needed on site.  The formwork is independently supported, so the shear walls and core walls can be completed ahead of the rest of the main building structure. This can help to provide stability to the main structure during its construction and can have the beneficial effect of taking the jump form core off the project critical path.
  • 14. CONTINUED…  High quality surface finishes are possible.  Climbing forms can be designed to operate in high winds (when the use of a crane is less viable). This allows construction work to be carried out at reduced risk from adverse weather.  The highly engineered nature of jump form systems allows quick and precise adjustment of the formwork in all planes.  Some formwork systems can be used at an inclined angle, which is particularly useful on bridge pylons or where walls vary in thickness.  A small but skilled workforce is required on site.  It is easier to plan construction activities due to the repetitive nature of the work.
  • 15. SAFETY :  Working platforms, guard rails, and ladders are built into the completed units of market-leading formwork systems. Complete wind-shield protection on platform edges is also possible.  Self-climbing formwork systems are provided with integral free- fall braking devices.  The completed formwork assembly is robust and provides a stable working platform.  The reduced use of scaffolding and temporary work platforms results in less congestion on site.  The setting rate of concrete in those parts of the structure supporting the form is critical in determining the rate at which construction can safely proceed.  The repetitive nature of the work means that site operatives can quickly become familiar with health and safety aspects of their job. Formwork suppliers provide materials and resources to help train the labour force.
  • 16. SUSTAINABILITY FEATURES :  The formwork system is easy to clean and reuse with little formwork waste generated compared to traditional formwork.  Climbing formwork systems offer simplicity, safety and cost effectiveness for certain high-rise building structures.  The repetitive nature of the work, combined with the engineered nature of the formwork, allows fine tuning of the construction operations, which in turn leads to minimal concrete wastage.  Many repeated uses of formwork are possible before maintenance or replacement is needed, the number of uses depending on the quality of the surface finish of concrete specified.
  • 17. CONSIDERATIONS :  Jump form is typically used on buildings of 5 storey's or more; fully self-climbing systems are generally used on structures with more than 20 floor levels.  Assembly and lifting operations for self-climbing formwork systems require personnel to be comprehensively trained to ensure competence.  The raising operation must be carefully planned and coordinated, and access to the working area during lifting should be restricted to essential personnel.
  • 18. REFERENCES :  “FORMWORK FOR MODERN, EFFICIENT CONCRETE CONSTRUCTION” BY Rohan Rupasinghe and Éanna Nolan, BRE  WWW.YOUTUBE.COM  HTTP://EN.WIKIPEDIA.ORG