SCHOOL OF ARCHITECTURE, BUILDING AND
DESIGN
Bachelor of Quantity Surveying (Honours)
August 2017
BUILDING ECONOMICS ASSIGNMENT
Lecturer: Sr. Dianne Kok Hui Wei
Date of Submission: 21st November 2017
Student Name Student ID
Liu Wei Qian 0322969
Maybelle Wang Sze Kher 0327553
Mok Po Yi 0318207
Ng Seng He 0323037
Pan Lek Vun 0323164
Pang Khai Shuen 0318423
Sherlyn Ang Tse Yun 0317977
Siong Jia Yii 0318239
2
Table of Contents
1.0 Introduction....................................................................................................... 3
1.1 Benchmark Project........................................................................................ 4
1.2 Building Design Proposal .............................................................................. 7
1.3 Green Building Index................................................................................... 13
2.1 Gross Floor Area ............................................................................................ 20
2.2 Office........................................................................................................... 21
2.4 Basement Carpark ...................................................................................... 22
2.5 F&B – Food court........................................................................................ 23
2.6 Softscape & Hardscape (included water feature, park furniture & signage) 24
2.8 Covered Pedestrian Walkway ..................................................................... 29
2.9 Others (Allowance)...................................................................................... 32
2.10 GBI Platinum Rating Allowance .................................................................. 35
2.11 Benchmark Project Cost Allocation............................................................... 36
3.0 Conclusion...................................................................................................... 37
Appendix .................................................................................................................. 38
3
1.0 Introduction
Our site is designated to be in the heart of Kuala Lumpur, right next to the current
developing Tun Razak Exchange. It is strategically located near to the CBD as our
project consists of office tower and commercial retail spaces. This proposed project is
expected to be a vibrant, environmental friendly and economic development. Our
project will have a mix of commercial, office spaces and some entertainment. We plan
to have a plot ratio of 1:10 for this development as this has been proven to be a good
benchmark for commercial developments. This means that it will not be too crowded,
but also an efficient way of using the spaces that are available to us.
Around this area, there are many commercial office spaces and retail spaces across
the block as well as the proposed Tun Razak Exchange, which is expected to be
Malaysia’s most robust and innovative financial district. Since this area has been
definitively known as a financial precinct, we are also aiming to develop this land to
suit the requirements. We also intent to be the benchmark for future developments in
terms of green building and our efficiency. Our project complements the CBD and also
contributes to serve as a growth factor to many major companies.
This land parcel is strategically located between Telok Ayer Street and Cecil Street
which is one of the main roads towards the CBD. This location is easy to find and
offers a great variety of choices. This also gives the opportunity for the real estate
around the area to appreciate in value, hence encouraging more investors come in to
invest. There are a few landmarks which area Pavilion KL, Low Yat Plaza and Berjaya
Times Square just to name a few.
The site area is divided into 3 plots. Each of these plots have different area and
different usage. Plot A1 is 5990.80 sqm, which is designated for the building of
maximum 50 stories office tower and development of commercial retail spaces. Plot
A2 has an area of 1612.40 sqm, and it is open space area with F&B kiosk of less than
100 sqm. Plot A3 is only 180sqm, which is a subterranean space and it is to be
developed for part of a pedestrian walkway to the MRT station. This is done by
constructing an underground linkway passage for the ease of use. These 3 plots of
land will be used to their fullest potential in terms of green building and commercial
development.
4
1.1 Benchmark Project
The benchmark project set for this project is located at the centre of the city, Kuala
Lumpur, a corporate headquarter office tower comprising design and construction of
1 block of 32-storey office tower and 1 block of 9 storey carpark with 1 level of common
basement and external infrastructure works.
This high-rise building served as a landmark corporate headquarters designed for
business versatility with Grade-A intelligent features. A total of 25-feet high grand
lobby with spacious freedom with 9.5 feet floor-to-ceiling office space within 32 floors
with 3 distinctive zones that cater to multi-functional businesses. This building has
been certified by GBI as well as MSC compliant in recognition of their practice for
environmental design and construction. The office tower is complete with features that
provide fibre-optic backbone with 100% backup power supply with Building
Management System that ensures the optimal saving in energy and water usage and
real time monitoring of environmental changes including carbon monoxide levels.
Besides all the environmental features mentioned above, it is located at a strategic
location that have easy access to public transport like the bus, LRT, KTM and Monorail
stations.
5
6
7
1.2 Building Design Proposal
The land plot is divided in Plot A1, A2, & A3, each with distinctive functions and
purposes. Our team attempted to divide the usage of these plots accordingly to
achieve the maximum diversity and efficiency of land use.
Our proposed building design consists of several main elements:
1) Main Office Building
The main feature of this development, situated in Plot A1, is an approximately
100m high office tower, housing 25 floors of offices and the ground floor as
retails. The average GFA per floor is 2500m2. Floor to floor height is 3.6m per
floor, with ground floor being extended to 4.0m height.
The office floor area amount to 62,288m2, surpassing the required 61,730m2.
8
2) Retail Block
Located next to the main office building in Plot A1 is a 4-storey shopping centre.
It acts as a façade facing Telok Ayer Street. Approximately 20 meters in height,
this structure consists of 1200m2 GFA per floor, amounting to 4,800m2 of retail
space.
Combined with the ground floor of the office building, these two spaces provide
7,300m2 GFA of retail zones.
3) Cafeteria
The landscaping area in Plot A2 will hold a cafeteria, with a maximum GFA of
100m2. This building will be located at the top right corner of the plot as
demarcated in the drawing.
9
4) Basement
The basement level of this development will consist of underground parking and
pedestrian walkways. We have provided approximately 6,300m2 of parking
space, which translates to 418 total parking bays, out of which 311 serves for
office use, 37 for retail uses, and 70 additional bays for public use as requested
by the client.
There will also be an underground pedestrian walkway spanning from the end
of Plot A1 to Plot A3. It is estimated to be 95 meters in length and 6m wide.
An additional 30-meter long walkway is required to connect the proposed
development to the existing underground pedestrian walkway leading to an
existing MRT station.
5) Covered Pedestrian Walkways
10
Situated around the office and retail blocks is the covered pedestrian walkways.
Two different widths of walkways (3.6m and 5.0m) are required for different
locations. We provided steel structures with glass canopy to cover the
walkways.
5.0m wide covered walkway is provided in front of the office block, before the
building setback line.
3.6m wide covered walkway is provided for the sides facing Telok Ayer Street
and Cecil Street to promote walkability around the area. Another stretch is also
built to provide access to the existing Methodist Church.
11
6) Existing Methodist Church and its setback lines
The development is required to preserve the existing Methodist Church, and
adhere to the stated setback lines for at-grade and subterranean structures built
around it.
The existing Methodist church is located beside Plot A2 iof the development
land parcel.
Two distinct no-build and setback area need to be adhered while planning the
development.
12
Building Perspectives
13
1.3 Green Building Index
This project requires a platinum rating in Green Building Index which is the highest
rank in the classification of GBI. The assessment criteria of GBI includes energy
efficiency, indoor environmental quality, sustainable site planning and management,
material and resources, water efficiency and innovation. The building has to score at
least 86 points from all the criteria stated above in order to achieve a platinum grade
GBI.
14
Green Building Index benchmark project
Building: SP Setia corporate Headquarter
Client: Bandar Setia Alam Sdn Bhd
Location: Setia Alam (Malaysia)
Gross total surface area: 33,838 m2
Lot size: 12,300 m2
Commencement of work: 2012
Completion of work: 2014
Type of building: Office
SP Setia headquarter is the third building to achieve GBI’s platinum grade in Malaysia.
Besides, it has also achieved GreenRe Platinum and The Edge Malaysia-PAM Green
Excellence Award. We can know that it is a sustainable, high value and vibrant building
that encourages a balanced and green lifestyle. The office building is connected to a
shopping mall – Setia City Mall which achieved a silver rating in GBI. It is similar with
our project nature so this is the reason we refer our project to this benchmark project.
15
Green feature and initiatives
The proposal to score platinum grade in Green Building Index as following:
Energy Efficiency
Feature Extra information
 High-performance double
glazed windows and louvres to
reduce heat gain and
encourage natural lighting.
 Solar photovoltaic panels on
rooftop to harvest renewable
energy. In benchmark project,
the solar panel helps to
generate 55Kw of energy
which is 2% of the energy
consumption.
 Energy measurement system It is used to measure and manage the energy
and water usage of the building.
16
 Energy-efficient lighting, for
example T5 fluorescent
lighting with high frequency
ballast.
 Flexible lighting controls -
individually switched lighting
zones are less than 100 sq m
in the main building
Zoning – Zoning is the grouping of luminaires
into functional areas.
It enable the ease of controlling the usage of
lighting at each areas to prevent energy waste
when that area does not require lighting.
 Auto sensor-controlled lighting
strategy such as photo sensor
cells at perimeter zones and
motion sensors in less
frequent areas in our projects.
Artificial lighting will be
switched off when there is
sufficient daylight.
17
Water efficiency
Feature Extra information
 Rainwater harvesting from the
buildings for landscape
irrigation in plot A2 and
replenish water feature
Environmental protection
 Using GBI-certified architectural products and construction materials. For
example, the usage of fair face concrete to minimize long term maintenance and
improve aesthetic value. Low volatile organic compound paint is encouraged as
well.
 Promoting recycling by providing recycling bins in common areas.
 Sustainable construction will be implemented. Reusable and recyclable formwork
will be used and strict waste management and pollution control will be taken.
18
Indoor Environmental quality
Feature Extra information
 Efficient air-conditioning
system design, for example
raised floor for underfloor air-
conditioning distribution system
in the office building. Energy
wasted on delivering
conditioned air from ceiling to
floor slab will be reduced.
 Other features such as CO2 sensor, auto condeser tube cleaning system, heat
recovery wheel will be used in the building to control the environmental quality.
Sustainable site planning
Feature Extra information
 Open space – The open space
of our project is 27% of the total
development area.
There will be landscaping all over
the open space in plot A2 which
increase the greenery. Covered
pedestrian walkway and
underground walkway will have
connections with the building, open
space and MRT station.
 Quality assessment system for building construction work will be implemented
and achieve a minimum score of 70%
 Green vehicle priority – low emitting and fuel efficient vehicles will be
encouraged, for example hybrid car, car pool and bicycle. Parking for these
green vehicle will be provided as well.
19
 Public transport access – there
is an existing MRT station
nearby the project which is
Tanjong Pagar MRT station.
Underground pedestrian
walkway will be connected to the
MRT station from our project.
 Roof – roof garden to serve as a
functional space while
minimising solar heat gain.
Besides, the project will be using
the combination of solar energy
and roof garden which is
applicable to the roof of office
building and shopping mall at
Plot A1
Solar panel
Roof garden
20
2.1 Gross Floor Area
Total GFA = 76,560m2
Breakdown by functional elements:
Element Office Retail Carpark Walkways
GFA (m2) 62,288 7,300 6,270 602
Percentage (%) 81 9 9 1
*Please refer to Appendix C for detailed GFA build up.
Office
81%
Retail
10%
Carpark
8%
Walkways
1%
Elemental Breakdown
Office
Retail
Carpark
Walkways
21
2.2 Office
Item Qty
(CFA)
Unit Calculation Rate
(RM/m2)
Total (RM) Source
Office 68,517 m2 (3,560 + 4,840)
2
4,200.00 287,770,000.00 JUBM
cost
handbook
Source from JUBM & Arcadis Construction Cost Handbook MALAYSIA 2017
2.3 Retail
Item Qty (CFA) Unit Calculation Rate (RM/m2) Total (RM) Source
Mall 8,030 m2 (2,760 + 3,515)
2
3,138.00 25,190,000.00 JUBM
cost
handbook
Source:
Source from JUBM & Arcadis Construction Cost Handbook MALAYSIA 2017
22
2.4 Basement Carpark
Item Qty (CFA) Unit Calculation Rate
(RM/m2)
Total (RM) Source
Basement
Carpark
(Office)
309 lots x
15m2
= 4,665m2
m2 (1,475 + 2,030)
2
1,753.00 8,180,000.00 JUBM
cost
handbook
Basement
Carpark
(Retail)
41 lots x
15m2
= 555m2
m2 (1,475 + 2,030)
2
1,753.00 970,000.00 JUBM
cost
handbook
Basement
Carpark
(Extra)
70 lots x
15m2
= 1,050m2
m2 (1,475 + 2,030)
2
1,753.00 1,840,000.00 JUBM
cost
handbook
Source from JUBM & Arcadis Construction Cost Handbook MALAYSIA 2017
23
2.5 F&B – Food court
Item Qty (CFA) Unit Calculation Rate (RM/m2) Total (RM) Source
Food
court
100 m2 1,463,752
2
1,823.00 180,000.00 BQ from
previous
project
Food Court concept – one storey food court, GFA = 100m2
24
2.6 Softscape & Hardscape (included water feature, park furniture & signage)
Item Qty
(m2)
Unit Calculation Rate
(RM/m2)
Total (RM) Source
Softscape
&
hardscape
1,356 m2 - 150.00 200,000.00 BQ from
previous
project
Softscape:
Based on the client’s requirement, there will be minimum 40% of lush landscaping.
These are the example items (trees, palm, shrubs and turfing) included:
Trees
Palm Turfing
Shrub
Xanthestemon chrysanthus Plumeria rubra
Cuphea hyssopifoliaLoropetalum chinense var.
rubrumAcalypha siamensis
Wodyetia bifurcataCyrtostachys renda Zoysia matrella
25
Hardscape:
These are the example items (excluding lighting):
Seating
Reflexology path Concrete walkway
Water feature
Concrete benchConcrete planter box with seating
Signage
26
Night lighting:
Night lighting are priced based on lump sum – RM 500,000. It is all over the
development area, not only in plot A2 landscape area.
Solar pole light Up light
27
2.7 Underground Pedestrian
No Item Unit Calculation
Qty Rate
(RM)
Total (RM)
Sources
1 Excavation <
6.00m deep
m³ (65.5 + 30 + 43.5) x
6 x 4.5
3753 45.00 168,885.00 BQ from
previous
project
2 Backfilling with
300mm thick
coarse aggregate
m² 139 x 6 834 40.00 33,360.00 BQ from
previous
project
3 Grade 35
reinforced
vibrated concrete
(floor)
m³ 139 x 6 x 0.5 287 253.70 72,685.05 CIDB
4 Grade 35
reinforced
vibrated concrete
(wall)
m³ 139 x 4.5 x 0.3 x 2 375 253.70 95,213.61 CIDB
5 Formwork (floor) m² (139 + 6) x 2 x 0.5 145 34.00 4,930.00 QS Online
6 Formwork (wall) m² (139 x 4.5 x 2 x 2) +
(4.5 x 0.3 x 4)
2507 34.00 85,251.60 QS Online
7 BRC Ref No. B10
(2 layers)
m² 139 x 6 x2 1668 34.70 57,879.60 BQ from
previous
project
8 Waterproofing
(floor)
m² 139 x 6 834 35.40 29,523.60 BQ from
previous
project
9 Waterproofing
(wall)
m² 139 x 4.5 x 2 1251 35.40 44,285.40 BQ from
previous
project
10 0.25mm thick
polythen sheet
damp proof
membrane
m² 139 x 6 834 5.00 4,170.00 BQ from
previous
project
11 600mm x 300mm
porcelain tiles
including
minimum 20mm
thick base screed
m² 139 x 6 834 74.80 62,383.20 QS Online
28
No Item Unit Calculation Qty Rate
(RM)
Total (RM) Sources
12 1220mm x
1220mm x 3.2mm
thick 'UAC'
Asbestos free
ceiling sheet fixed
to steel joist
m² 139 x 6 834 60.00 50,040.00 BQ from
previous
project
13 300mm x 600mm
Granite wall tiles
m² 139 x 4 x 2 1112 200.00 222,400.00 BQ from
previous
project
14 Lift/escalator m² 2 x 15 x 2 60 247.50 14,850.00 JUBM cost
handbook
15 Services m² 139 x 6 834 610.00 508,740.00 JUBM cost
handbook
TOTAL (RM) 1,454,597.06
UNIT COST
(RM/m2)
1744.12
29
2.8 Covered Pedestrian Walkway
*picture shown is for illustration purposes only
*Refer calculation below
**Marked up 10%
A) I-beam quantity calculation
No Item Unit Qty Rate
(RM)
Total (RM) Sources
1 Glass Canopy ft² 9311 85.80** 798,883.80 arrowhub.com
2 Hot rolled circular
hollow sections @
3m c/c*
tonne 6.225 3300.00** 20,542.50 quantitysurvey-
oronline.com
3 I-beam @ Linear* tonne 9.374 3300.00** 30,934.20 quantitysurvey-
oronline.com
4 I-beam @ 600mm
c/c*
tonne 20.350 3300.00** 67,155.00 quantitysurvey-
oronline.com
5 200mm x 200mm
Homogeneous
Floor Tiles
m² 865 145.88 126,186.20 Previous BQ
6 Lighting Nos 73 150.00 10,950.00 Cost Plan
TOTAL 1,054,561.70
Cost/m2 Total area = 865m2 1,219.15
30
 Total length of I-beam for 3.6m wide walkway (spans across columns)
= 135m + 15m = 150m
 Total length of I-beam for 5.0m wide walkway (spans across columns)
= 65m
 Total length of I-beam (spans across columns)
= 150m + 65m = 215m
B) I-beam quantity calculation (cont’d)
 Nos. of I-beam (spread out to hold glass canopy)
(150m/0.6m+1) = 251 nos @ 3.6m span
(65m/0.6+1) = 110 nos @ 5.0m span
 Total length of I-beam (spread out to hold glass canopy)
= (251x3.6) + (110x5.0) = 1453.6m
C) Hot-rolled circular hollow section calculation
 Nos of CHS = (215/3m) + 1 = 73 nos @ 3.2m high = 233.6m
D) Floor tiles and Glass canopy calculation
 Total area of 3.6m wide walkway = 3.6m x 150m = 540m²
 Total area of 5.0m wide walkway = 5.0m x 65m = 325m²
 Quantity of Glass Canopy = 865m² x 10.7639 = 9310.77ft²
Assumptions:
1) Hot rolled circular hollow sections is 177.8mm dia., 6.3mm thk @ 26.65kg/m,
surface area per metre 0.559
2) I-beam for spans across columns is 200mm x 175mm @ 43.6kg/m, surface
area per metre 1.15
3) I-beam spread out to hold glass canopy is 150mm x 75mm @ 14.0kg/m, surface
area per metre 0.576
31
Item Weight (kg/m) Length (m) Total weight
(kg)
Hot rolled circular hollow sections
177.8mm dia, 6.3mm thk
26.65 233.6 6225
I-beam 200mm x 175mm width 43.6 215.0 9374
I-beam 150mm x 75mm width 14.0 1453.6 20350
32
2.9 Others (Allowance)
a) Utilities Detection Works - RM 45,000.00
Utilities detection works determine the existing utilities of the site located at subsurface
or above ground. Any gas, electric, telephone, cable, water and sewer lines identified
will be used to design other utilities services of the new proposed buildings.
b) Site survey/investigation - RM 80,000.00
Site survey/investigation is carried out at the construction site to gather information on
physical conditions that will be encountered during the performance of the work. Site
survey should determine all the unusual circumstances of the site, the state of existing
buildings that are to be demolished and the conditions of the adjacent buildings and
sites. Thorough site survey is to be completed to identify the effect to demolition to
other existing buildings around the site.
c) Geotechnical Investigation Works - RM 220,000.00
Geotechnical investigation is below-ground work to obtain information on physical
properties of soil and rock around site that performed by geotechnical enginners.
Geotechnical investigation works including surface and subsurface exploration, soil
sampling and testing which used to design earthworks and foundations for proposed
structures. Besides that, geotechnical investigation also used to measure thermal
resistivity of soils or backfill materials required for underground transmission lines, oil
and gas pipelines, radioactive waste disposal and solar thermal storage facilities.
33
d) Hoarding and Signboard - RM 120,000.00
Hoarding is a temporary structure erected around perimeter of construction site to
secure them from view and prevent unauthorised access. It act as part of site security
system in ensuring health and safety for site workers, visitors and general public and
to prevent theft or vandalism. Signboard is a board that indicating both user and
corporate identity of professions which usually placed at the entrance of site.
e) Cadastral Survey (Plot A1, A2 & A3) (Allowance) - RM 50,000.00
34
Cadastral Survey is a survey to determine boundaries
and area of a lot of land or more. It can be categorized as title survey and demarcation
survey. Title survey is whereby the survey is for registering the final title while
demarcation survey is to determine the boundaries of a land for the purposes such as
the land's location, land's area, or clearance for building construction. Cadastral
surveys are controlled by law and the surveys within the meaning of Section 396 of
the National Land Code (Act 56 of 1965). The cadastral survey carried out will be
certified by the Department of Survey and Mapping Malaysia (JUPEM).
f) Utility Connection Charges - RM 120,000.00
Connection charges recover the cost of installing and maintaining assets that allow
parties to connect to the transmission system and which are not normally used by any
other party. The utility connection charges consist of electricity, water, sewage and
telephone.
35
g) Services diversion: electricity (Allowance) - RM 120,000.00
Moving the electricity cables or overhead power lines because they are affected during
construction work. For example, moving the meter and service cable when the
construction is completed or maybe alter the position of meter and service cable. We
can also move the service cable from internal to external position.
h) Traffic Impact Assessment - RM 50,000.00
Traffic impact assessment or TIA for short, is an important part of the preliminaries.
The officer of the assessment should be aware of the condition of traffic around the
area of construction. It is vital to engineers and transport planner to determine the
possible effects of development on the transportation and traffic system and to mitigate
and negative impacts. TIA will incur roughly RM 50,000 for this particular project.
i) Protection of Existing Roadside Trees - RM 150,000.00
On the other hand, protection of existing roadside trees is to maintain and preserve
the current trees around the construction site. This is especially important to us due to
the fact the client requires us to achieve a Platinum GBI standard. Hence, we think it
is justifiable to spend RM 150,000 for this item.
2.10 GBI Platinum Rating Allowance
The allowance for GBI Platinum Rating is 10% in this project, as from our
sources, we noted that the sum allocated for GBI purposes is usually 35% of the M&E
Works. As M&E Works usually substantiate 30% of the total contract sum, we decided
to apply 10% of the total contract sum after superimposing the two percentages.
36
2.11 Benchmark Project Cost Allocation
*kindly refer to separate Excel file
37
3.0 Conclusion
No. Item
GFA
(m2)
Rate
(RM/m2)
Total (RM)
1 A1-Office 62,288 5,227 325,550,000
2 A1-Retail 7,300 3,929 28,680,000
3 A2-Open Space 100 3,800 380,000
Sub Total (No.1 – 3) 69,688 5,089 354,610,000
4 Allowance for Land Parcel 76,560 131 10,050,000
5 GBI Requirements (10% of No.1 -3) 76,560 463 35,460,000
Sub Total (No.1 – 5) 76,560 5,226 400,120,000
6 Contingencies (5% of No.1 - 5) - - 20,010,000
Sub Total (No.1 – 6) 76,560 5,488 420,130,000
7 Cost Escalation (5% of No. 1 – 6) - - 21,010,000
Grand Total 76,560 5,762 441,140,000
A summary of our cost plan is shown in the table above. In Plot A1, we proposed
a 26 storey high-end commercial office tower with height of approximately 100m. A 4
storey shopping centre next to the main building is also provided. The basement area
of the land parcel is planned to provide parking bays of 15m2 per lot for these two
buildings, allocating 311 lots for office use and 37 lots for retail. These two
development amount to GFA of 62,288m2 for office area with rate of RM5,227/m2,
reaching a total of RM325,550,000. While for retail area, GFA of 7,300m2 is allowed
at a rate of RM3,929/m2 totalling at RM28,680,000.
Plot A2 is proposed to be an open space filled with park furniture and water
features. In addition, a single storey cafeteria with a maximum GFA of 100m2 is
provided. A total of RM380,000 is allowed for A2. Plot A3 will be used to develop an
underground pedestrian walkway spanning through A1 and A2. The walkway will be
connected to the nearby MRT station for public ease of access. We allocated
RM10,050,000 for development of the walkway and additional works to land parcel
such as demolition, covered walkway, roof garden, public car parks and site works.
To be able to meet GBI platinum rank requirement, there is an allowance of
RM35,460,000, constituting 10% of total building work cost. Besides that, a sum of
RM20,010,000 is provided for contingency, which is 5% of total cost including GBI
allowance. Finally, a cost escalation of RM21,010,000, consisting of 5% of total
amount including contingency, is allocated assuming that tender is called in one year.
To summarize, the total GFA for the whole development is 76,560m2. The final
amount totals up to RM441,140,000 with rate of RM5,762/m2. We consider the project
to be feasible and recommend the client to proceed as it has an advantageous location
to become a unique city attraction, providing great business opportunities.
38
Appendix
1. Glass Canopy – http://arrowhub.com/
2. Steel structure (Hot rolled circular hollow sections & I-beam)-
http://www.quantitysurveyoronline.com.my/
39
3. Grade 35 concrete (CIDB)
4. Formwork (quantity surveyors online)
5. 600mm x 300mm porcelain tiles (quantity surveyors online)
6. Lift/escalator (JUBM cost handbook)
7. Services (JUBM cost handbook)

Mais conteúdo relacionado

Mais procurados

Managementscienceassignment final
Managementscienceassignment finalManagementscienceassignment final
Managementscienceassignment finalArissa Loh
 
Project Management and Development Economics Project (Slides)
Project Management and Development Economics Project (Slides)Project Management and Development Economics Project (Slides)
Project Management and Development Economics Project (Slides)Pang Khai Shuen
 
Pm assignment-2-report
Pm assignment-2-reportPm assignment-2-report
Pm assignment-2-reportChong Yu Xuan
 
Project Management Group Assignment Final Report
Project Management Group Assignment Final ReportProject Management Group Assignment Final Report
Project Management Group Assignment Final ReportArissa Loh
 
Value Management Assignment (Slides)
Value Management Assignment (Slides)Value Management Assignment (Slides)
Value Management Assignment (Slides)Pang Khai Shuen
 
Assignment - S Hotel
Assignment - S HotelAssignment - S Hotel
Assignment - S HotelKai Yun Pang
 
Project management report project 1
Project management report project 1Project management report project 1
Project management report project 1Afiq Knick
 
Value Management Assignment (Report)
Value Management Assignment (Report)Value Management Assignment (Report)
Value Management Assignment (Report)Pang Khai Shuen
 
Design Engineer Construct Level 2 Unit 1_1.1-4.4.pptm
Design Engineer Construct Level 2 Unit 1_1.1-4.4.pptmDesign Engineer Construct Level 2 Unit 1_1.1-4.4.pptm
Design Engineer Construct Level 2 Unit 1_1.1-4.4.pptmSamuel Boone
 
Project background (1)(1)
Project background (1)(1)Project background (1)(1)
Project background (1)(1)JamesMoy7
 
Project management (1)
Project management (1)Project management (1)
Project management (1)aarenneoone
 
Project Management (Project 1 - Defining and documenting a project) Presentat...
Project Management (Project 1 - Defining and documenting a project) Presentat...Project Management (Project 1 - Defining and documenting a project) Presentat...
Project Management (Project 1 - Defining and documenting a project) Presentat...Tan Jaden
 
ARC 3612 PROJECT MANAGEMENT- PROJECT 1- DEFINING AND DOCUMENTING A RESIDENTIA...
ARC 3612 PROJECT MANAGEMENT- PROJECT 1- DEFINING AND DOCUMENTING A RESIDENTIA...ARC 3612 PROJECT MANAGEMENT- PROJECT 1- DEFINING AND DOCUMENTING A RESIDENTIA...
ARC 3612 PROJECT MANAGEMENT- PROJECT 1- DEFINING AND DOCUMENTING A RESIDENTIA...Angeline KH
 
Project management Report - GROUP
Project management Report - GROUPProject management Report - GROUP
Project management Report - GROUPKeshav Seewraz
 
PROJECT MANAGEMENT - ASSIGNMENT ON BRIDGE CONSTRUCTION PLAYS A ROLE OF PROJEC...
PROJECT MANAGEMENT - ASSIGNMENT ON BRIDGE CONSTRUCTION PLAYS A ROLE OF PROJEC...PROJECT MANAGEMENT - ASSIGNMENT ON BRIDGE CONSTRUCTION PLAYS A ROLE OF PROJEC...
PROJECT MANAGEMENT - ASSIGNMENT ON BRIDGE CONSTRUCTION PLAYS A ROLE OF PROJEC...Yamini Kahaliya
 
Project management assignment 1
Project management assignment 1 Project management assignment 1
Project management assignment 1 Weng Chuan
 
Project management
Project managementProject management
Project managementBenjamin Tan
 
Project Management.Project 1
Project Management.Project 1Project Management.Project 1
Project Management.Project 1suzzanekan
 
Report on Lot 2C2 - Malaysia [BSC]
Report on Lot 2C2 - Malaysia [BSC]Report on Lot 2C2 - Malaysia [BSC]
Report on Lot 2C2 - Malaysia [BSC]Esther Lau
 

Mais procurados (20)

Managementscienceassignment final
Managementscienceassignment finalManagementscienceassignment final
Managementscienceassignment final
 
Project Management and Development Economics Project (Slides)
Project Management and Development Economics Project (Slides)Project Management and Development Economics Project (Slides)
Project Management and Development Economics Project (Slides)
 
Pm assignment-2-report
Pm assignment-2-reportPm assignment-2-report
Pm assignment-2-report
 
Project Management Group Assignment Final Report
Project Management Group Assignment Final ReportProject Management Group Assignment Final Report
Project Management Group Assignment Final Report
 
Value Management Assignment (Slides)
Value Management Assignment (Slides)Value Management Assignment (Slides)
Value Management Assignment (Slides)
 
Assignment - S Hotel
Assignment - S HotelAssignment - S Hotel
Assignment - S Hotel
 
Project management report project 1
Project management report project 1Project management report project 1
Project management report project 1
 
Value Management Assignment (Report)
Value Management Assignment (Report)Value Management Assignment (Report)
Value Management Assignment (Report)
 
Design Engineer Construct Level 2 Unit 1_1.1-4.4.pptm
Design Engineer Construct Level 2 Unit 1_1.1-4.4.pptmDesign Engineer Construct Level 2 Unit 1_1.1-4.4.pptm
Design Engineer Construct Level 2 Unit 1_1.1-4.4.pptm
 
Project background (1)(1)
Project background (1)(1)Project background (1)(1)
Project background (1)(1)
 
Project management (1)
Project management (1)Project management (1)
Project management (1)
 
Project Management (Project 1 - Defining and documenting a project) Presentat...
Project Management (Project 1 - Defining and documenting a project) Presentat...Project Management (Project 1 - Defining and documenting a project) Presentat...
Project Management (Project 1 - Defining and documenting a project) Presentat...
 
ARC 3612 PROJECT MANAGEMENT- PROJECT 1- DEFINING AND DOCUMENTING A RESIDENTIA...
ARC 3612 PROJECT MANAGEMENT- PROJECT 1- DEFINING AND DOCUMENTING A RESIDENTIA...ARC 3612 PROJECT MANAGEMENT- PROJECT 1- DEFINING AND DOCUMENTING A RESIDENTIA...
ARC 3612 PROJECT MANAGEMENT- PROJECT 1- DEFINING AND DOCUMENTING A RESIDENTIA...
 
Project management Report - GROUP
Project management Report - GROUPProject management Report - GROUP
Project management Report - GROUP
 
PROJECT MANAGEMENT - ASSIGNMENT ON BRIDGE CONSTRUCTION PLAYS A ROLE OF PROJEC...
PROJECT MANAGEMENT - ASSIGNMENT ON BRIDGE CONSTRUCTION PLAYS A ROLE OF PROJEC...PROJECT MANAGEMENT - ASSIGNMENT ON BRIDGE CONSTRUCTION PLAYS A ROLE OF PROJEC...
PROJECT MANAGEMENT - ASSIGNMENT ON BRIDGE CONSTRUCTION PLAYS A ROLE OF PROJEC...
 
Project management assignment 1
Project management assignment 1 Project management assignment 1
Project management assignment 1
 
Project management
Project managementProject management
Project management
 
Project Management.Project 1
Project Management.Project 1Project Management.Project 1
Project Management.Project 1
 
Project background
Project backgroundProject background
Project background
 
Report on Lot 2C2 - Malaysia [BSC]
Report on Lot 2C2 - Malaysia [BSC]Report on Lot 2C2 - Malaysia [BSC]
Report on Lot 2C2 - Malaysia [BSC]
 

Semelhante a BE Compiled

Building economics final assignment report
Building economics final assignment reportBuilding economics final assignment report
Building economics final assignment reportlucaschinsheng
 
Be cost appraisal
Be cost appraisalBe cost appraisal
Be cost appraisalLwj Welson
 
BE cost appraisal
BE cost appraisalBE cost appraisal
BE cost appraisalDoreen Yeo
 
DE/BE Workshop Presentation Slides
DE/BE Workshop Presentation SlidesDE/BE Workshop Presentation Slides
DE/BE Workshop Presentation SlidesMelvin Lim
 
De &amp; be final workshop submission
De &amp; be final workshop submissionDe &amp; be final workshop submission
De &amp; be final workshop submissionArthur Wilson
 
Mesiniaga final
Mesiniaga finalMesiniaga final
Mesiniaga finaladamtys
 
Mesiniaga final
Mesiniaga finalMesiniaga final
Mesiniaga finalYq Chong
 
Building Economics Report
Building Economics Report Building Economics Report
Building Economics Report Lin Hui
 
Be final report (1)
Be final report (1)Be final report (1)
Be final report (1)Jessyca Than
 
Building economic
Building economicBuilding economic
Building economictfkc1212
 
2016-0116_JShim Personal
2016-0116_JShim Personal2016-0116_JShim Personal
2016-0116_JShim PersonalJai Seong Shim
 
Be Report Finalize
Be Report FinalizeBe Report Finalize
Be Report FinalizeShze Hwa Lee
 
Building Economics Assignment Report
Building Economics Assignment ReportBuilding Economics Assignment Report
Building Economics Assignment Reportashleyyeap
 
CAPITAL GATE CASE STUDY -regional case study.pdf
CAPITAL GATE CASE STUDY -regional case study.pdfCAPITAL GATE CASE STUDY -regional case study.pdf
CAPITAL GATE CASE STUDY -regional case study.pdfAlasAlthaher
 
Compiled report
Compiled reportCompiled report
Compiled reportlohwenjun
 
BE Assignment
BE AssignmentBE Assignment
BE Assignmentkohwenqi
 
Final wisma lee rubber compilation (new)
Final wisma lee rubber compilation (new)Final wisma lee rubber compilation (new)
Final wisma lee rubber compilation (new)WC Yan
 
Final submission be 2.0
Final submission be 2.0Final submission be 2.0
Final submission be 2.0ahmong4
 

Semelhante a BE Compiled (20)

Building economics final assignment report
Building economics final assignment reportBuilding economics final assignment report
Building economics final assignment report
 
Be cost appraisal
Be cost appraisalBe cost appraisal
Be cost appraisal
 
BE cost appraisal
BE cost appraisalBE cost appraisal
BE cost appraisal
 
DE/BE Workshop Presentation Slides
DE/BE Workshop Presentation SlidesDE/BE Workshop Presentation Slides
DE/BE Workshop Presentation Slides
 
De &amp; be final workshop submission
De &amp; be final workshop submissionDe &amp; be final workshop submission
De &amp; be final workshop submission
 
Mesiniaga final
Mesiniaga finalMesiniaga final
Mesiniaga final
 
Mesiniaga final
Mesiniaga finalMesiniaga final
Mesiniaga final
 
Building Economics Report
Building Economics Report Building Economics Report
Building Economics Report
 
Be final report (1)
Be final report (1)Be final report (1)
Be final report (1)
 
Building economic
Building economicBuilding economic
Building economic
 
2016-0116_JShim Personal
2016-0116_JShim Personal2016-0116_JShim Personal
2016-0116_JShim Personal
 
Be Report Finalize
Be Report FinalizeBe Report Finalize
Be Report Finalize
 
Building Economics Assignment Report
Building Economics Assignment ReportBuilding Economics Assignment Report
Building Economics Assignment Report
 
CAPITAL GATE CASE STUDY -regional case study.pdf
CAPITAL GATE CASE STUDY -regional case study.pdfCAPITAL GATE CASE STUDY -regional case study.pdf
CAPITAL GATE CASE STUDY -regional case study.pdf
 
Compiled report
Compiled reportCompiled report
Compiled report
 
Compiled report
Compiled reportCompiled report
Compiled report
 
Ch report
Ch reportCh report
Ch report
 
BE Assignment
BE AssignmentBE Assignment
BE Assignment
 
Final wisma lee rubber compilation (new)
Final wisma lee rubber compilation (new)Final wisma lee rubber compilation (new)
Final wisma lee rubber compilation (new)
 
Final submission be 2.0
Final submission be 2.0Final submission be 2.0
Final submission be 2.0
 

Mais de Pang Khai Shuen

Project Management and Development Economics Project (DE)
Project Management and Development Economics Project (DE)Project Management and Development Economics Project (DE)
Project Management and Development Economics Project (DE)Pang Khai Shuen
 
Construction Law Assignment BQS Taylor's University
Construction Law Assignment BQS Taylor's UniversityConstruction Law Assignment BQS Taylor's University
Construction Law Assignment BQS Taylor's UniversityPang Khai Shuen
 
Construction Law - Remedies for Breach of Contract
Construction Law - Remedies for Breach of ContractConstruction Law - Remedies for Breach of Contract
Construction Law - Remedies for Breach of ContractPang Khai Shuen
 
BE benchmark project cost allocation
BE benchmark project cost allocationBE benchmark project cost allocation
BE benchmark project cost allocationPang Khai Shuen
 
BE Assignment brief aug 17
BE Assignment brief aug 17BE Assignment brief aug 17
BE Assignment brief aug 17Pang Khai Shuen
 
CSI Personal reflective journal
CSI Personal reflective journalCSI Personal reflective journal
CSI Personal reflective journalPang Khai Shuen
 
Pp2 coursework 2 BRIEF 201708
Pp2 coursework 2  BRIEF  201708Pp2 coursework 2  BRIEF  201708
Pp2 coursework 2 BRIEF 201708Pang Khai Shuen
 
PP1 - Presentation Slides
PP1 - Presentation Slides PP1 - Presentation Slides
PP1 - Presentation Slides Pang Khai Shuen
 
A Report on Procurement Strategies - PP1
A Report on Procurement Strategies - PP1 A Report on Procurement Strategies - PP1
A Report on Procurement Strategies - PP1 Pang Khai Shuen
 
A Report on Procurement Strategies - PP1
A Report on Procurement Strategies - PP1 A Report on Procurement Strategies - PP1
A Report on Procurement Strategies - PP1 Pang Khai Shuen
 
Estimating Presentation Slides - To Client
Estimating Presentation Slides - To ClientEstimating Presentation Slides - To Client
Estimating Presentation Slides - To ClientPang Khai Shuen
 
Procurement Strategies: A Seminar
Procurement Strategies: A SeminarProcurement Strategies: A Seminar
Procurement Strategies: A SeminarPang Khai Shuen
 
Software Application in Quantity Surveying - Slides
Software Application in Quantity Surveying - SlidesSoftware Application in Quantity Surveying - Slides
Software Application in Quantity Surveying - SlidesPang Khai Shuen
 

Mais de Pang Khai Shuen (20)

Project Management and Development Economics Project (DE)
Project Management and Development Economics Project (DE)Project Management and Development Economics Project (DE)
Project Management and Development Economics Project (DE)
 
Construction Law Assignment BQS Taylor's University
Construction Law Assignment BQS Taylor's UniversityConstruction Law Assignment BQS Taylor's University
Construction Law Assignment BQS Taylor's University
 
Construction Law - Remedies for Breach of Contract
Construction Law - Remedies for Breach of ContractConstruction Law - Remedies for Breach of Contract
Construction Law - Remedies for Breach of Contract
 
BE Slides updated
 BE Slides updated BE Slides updated
BE Slides updated
 
BE Presentation Slides
BE Presentation SlidesBE Presentation Slides
BE Presentation Slides
 
BE COST APPRAISAL
BE COST APPRAISALBE COST APPRAISAL
BE COST APPRAISAL
 
BE benchmark project cost allocation
BE benchmark project cost allocationBE benchmark project cost allocation
BE benchmark project cost allocation
 
BE Assignment brief aug 17
BE Assignment brief aug 17BE Assignment brief aug 17
BE Assignment brief aug 17
 
CSI Personal reflective journal
CSI Personal reflective journalCSI Personal reflective journal
CSI Personal reflective journal
 
pp2 Final account-1
pp2 Final account-1pp2 Final account-1
pp2 Final account-1
 
Pp2 coursework 2 BRIEF 201708
Pp2 coursework 2  BRIEF  201708Pp2 coursework 2  BRIEF  201708
Pp2 coursework 2 BRIEF 201708
 
PP2 COMPILCATION
PP2 COMPILCATIONPP2 COMPILCATION
PP2 COMPILCATION
 
M4 presentation slides
M4 presentation slidesM4 presentation slides
M4 presentation slides
 
PP1 - Presentation Slides
PP1 - Presentation Slides PP1 - Presentation Slides
PP1 - Presentation Slides
 
A Report on Procurement Strategies - PP1
A Report on Procurement Strategies - PP1 A Report on Procurement Strategies - PP1
A Report on Procurement Strategies - PP1
 
A Report on Procurement Strategies - PP1
A Report on Procurement Strategies - PP1 A Report on Procurement Strategies - PP1
A Report on Procurement Strategies - PP1
 
Estimating Presentation Slides - To Client
Estimating Presentation Slides - To ClientEstimating Presentation Slides - To Client
Estimating Presentation Slides - To Client
 
Elemental Cost Analysis
Elemental Cost AnalysisElemental Cost Analysis
Elemental Cost Analysis
 
Procurement Strategies: A Seminar
Procurement Strategies: A SeminarProcurement Strategies: A Seminar
Procurement Strategies: A Seminar
 
Software Application in Quantity Surveying - Slides
Software Application in Quantity Surveying - SlidesSoftware Application in Quantity Surveying - Slides
Software Application in Quantity Surveying - Slides
 

Último

Oppenheimer Film Discussion for Philosophy and Film
Oppenheimer Film Discussion for Philosophy and FilmOppenheimer Film Discussion for Philosophy and Film
Oppenheimer Film Discussion for Philosophy and FilmStan Meyer
 
Reading and Writing Skills 11 quarter 4 melc 1
Reading and Writing Skills 11 quarter 4 melc 1Reading and Writing Skills 11 quarter 4 melc 1
Reading and Writing Skills 11 quarter 4 melc 1GloryAnnCastre1
 
4.16.24 Poverty and Precarity--Desmond.pptx
4.16.24 Poverty and Precarity--Desmond.pptx4.16.24 Poverty and Precarity--Desmond.pptx
4.16.24 Poverty and Precarity--Desmond.pptxmary850239
 
Visit to a blind student's school🧑‍🦯🧑‍🦯(community medicine)
Visit to a blind student's school🧑‍🦯🧑‍🦯(community medicine)Visit to a blind student's school🧑‍🦯🧑‍🦯(community medicine)
Visit to a blind student's school🧑‍🦯🧑‍🦯(community medicine)lakshayb543
 
Daily Lesson Plan in Mathematics Quarter 4
Daily Lesson Plan in Mathematics Quarter 4Daily Lesson Plan in Mathematics Quarter 4
Daily Lesson Plan in Mathematics Quarter 4JOYLYNSAMANIEGO
 
INTRODUCTION TO CATHOLIC CHRISTOLOGY.pptx
INTRODUCTION TO CATHOLIC CHRISTOLOGY.pptxINTRODUCTION TO CATHOLIC CHRISTOLOGY.pptx
INTRODUCTION TO CATHOLIC CHRISTOLOGY.pptxHumphrey A Beña
 
Man or Manufactured_ Redefining Humanity Through Biopunk Narratives.pptx
Man or Manufactured_ Redefining Humanity Through Biopunk Narratives.pptxMan or Manufactured_ Redefining Humanity Through Biopunk Narratives.pptx
Man or Manufactured_ Redefining Humanity Through Biopunk Narratives.pptxDhatriParmar
 
Blowin' in the Wind of Caste_ Bob Dylan's Song as a Catalyst for Social Justi...
Blowin' in the Wind of Caste_ Bob Dylan's Song as a Catalyst for Social Justi...Blowin' in the Wind of Caste_ Bob Dylan's Song as a Catalyst for Social Justi...
Blowin' in the Wind of Caste_ Bob Dylan's Song as a Catalyst for Social Justi...DhatriParmar
 
Scientific Writing :Research Discourse
Scientific  Writing :Research  DiscourseScientific  Writing :Research  Discourse
Scientific Writing :Research DiscourseAnita GoswamiGiri
 
Decoding the Tweet _ Practical Criticism in the Age of Hashtag.pptx
Decoding the Tweet _ Practical Criticism in the Age of Hashtag.pptxDecoding the Tweet _ Practical Criticism in the Age of Hashtag.pptx
Decoding the Tweet _ Practical Criticism in the Age of Hashtag.pptxDhatriParmar
 
Mental Health Awareness - a toolkit for supporting young minds
Mental Health Awareness - a toolkit for supporting young mindsMental Health Awareness - a toolkit for supporting young minds
Mental Health Awareness - a toolkit for supporting young mindsPooky Knightsmith
 
Textual Evidence in Reading and Writing of SHS
Textual Evidence in Reading and Writing of SHSTextual Evidence in Reading and Writing of SHS
Textual Evidence in Reading and Writing of SHSMae Pangan
 
BIOCHEMISTRY-CARBOHYDRATE METABOLISM CHAPTER 2.pptx
BIOCHEMISTRY-CARBOHYDRATE METABOLISM CHAPTER 2.pptxBIOCHEMISTRY-CARBOHYDRATE METABOLISM CHAPTER 2.pptx
BIOCHEMISTRY-CARBOHYDRATE METABOLISM CHAPTER 2.pptxSayali Powar
 
Beauty Amidst the Bytes_ Unearthing Unexpected Advantages of the Digital Wast...
Beauty Amidst the Bytes_ Unearthing Unexpected Advantages of the Digital Wast...Beauty Amidst the Bytes_ Unearthing Unexpected Advantages of the Digital Wast...
Beauty Amidst the Bytes_ Unearthing Unexpected Advantages of the Digital Wast...DhatriParmar
 
Measures of Position DECILES for ungrouped data
Measures of Position DECILES for ungrouped dataMeasures of Position DECILES for ungrouped data
Measures of Position DECILES for ungrouped dataBabyAnnMotar
 
Student Profile Sample - We help schools to connect the data they have, with ...
Student Profile Sample - We help schools to connect the data they have, with ...Student Profile Sample - We help schools to connect the data they have, with ...
Student Profile Sample - We help schools to connect the data they have, with ...Seán Kennedy
 
Multi Domain Alias In the Odoo 17 ERP Module
Multi Domain Alias In the Odoo 17 ERP ModuleMulti Domain Alias In the Odoo 17 ERP Module
Multi Domain Alias In the Odoo 17 ERP ModuleCeline George
 
Using Grammatical Signals Suitable to Patterns of Idea Development
Using Grammatical Signals Suitable to Patterns of Idea DevelopmentUsing Grammatical Signals Suitable to Patterns of Idea Development
Using Grammatical Signals Suitable to Patterns of Idea Developmentchesterberbo7
 

Último (20)

Oppenheimer Film Discussion for Philosophy and Film
Oppenheimer Film Discussion for Philosophy and FilmOppenheimer Film Discussion for Philosophy and Film
Oppenheimer Film Discussion for Philosophy and Film
 
Reading and Writing Skills 11 quarter 4 melc 1
Reading and Writing Skills 11 quarter 4 melc 1Reading and Writing Skills 11 quarter 4 melc 1
Reading and Writing Skills 11 quarter 4 melc 1
 
4.16.24 Poverty and Precarity--Desmond.pptx
4.16.24 Poverty and Precarity--Desmond.pptx4.16.24 Poverty and Precarity--Desmond.pptx
4.16.24 Poverty and Precarity--Desmond.pptx
 
INCLUSIVE EDUCATION PRACTICES FOR TEACHERS AND TRAINERS.pptx
INCLUSIVE EDUCATION PRACTICES FOR TEACHERS AND TRAINERS.pptxINCLUSIVE EDUCATION PRACTICES FOR TEACHERS AND TRAINERS.pptx
INCLUSIVE EDUCATION PRACTICES FOR TEACHERS AND TRAINERS.pptx
 
Faculty Profile prashantha K EEE dept Sri Sairam college of Engineering
Faculty Profile prashantha K EEE dept Sri Sairam college of EngineeringFaculty Profile prashantha K EEE dept Sri Sairam college of Engineering
Faculty Profile prashantha K EEE dept Sri Sairam college of Engineering
 
Visit to a blind student's school🧑‍🦯🧑‍🦯(community medicine)
Visit to a blind student's school🧑‍🦯🧑‍🦯(community medicine)Visit to a blind student's school🧑‍🦯🧑‍🦯(community medicine)
Visit to a blind student's school🧑‍🦯🧑‍🦯(community medicine)
 
Daily Lesson Plan in Mathematics Quarter 4
Daily Lesson Plan in Mathematics Quarter 4Daily Lesson Plan in Mathematics Quarter 4
Daily Lesson Plan in Mathematics Quarter 4
 
INTRODUCTION TO CATHOLIC CHRISTOLOGY.pptx
INTRODUCTION TO CATHOLIC CHRISTOLOGY.pptxINTRODUCTION TO CATHOLIC CHRISTOLOGY.pptx
INTRODUCTION TO CATHOLIC CHRISTOLOGY.pptx
 
Man or Manufactured_ Redefining Humanity Through Biopunk Narratives.pptx
Man or Manufactured_ Redefining Humanity Through Biopunk Narratives.pptxMan or Manufactured_ Redefining Humanity Through Biopunk Narratives.pptx
Man or Manufactured_ Redefining Humanity Through Biopunk Narratives.pptx
 
Blowin' in the Wind of Caste_ Bob Dylan's Song as a Catalyst for Social Justi...
Blowin' in the Wind of Caste_ Bob Dylan's Song as a Catalyst for Social Justi...Blowin' in the Wind of Caste_ Bob Dylan's Song as a Catalyst for Social Justi...
Blowin' in the Wind of Caste_ Bob Dylan's Song as a Catalyst for Social Justi...
 
Scientific Writing :Research Discourse
Scientific  Writing :Research  DiscourseScientific  Writing :Research  Discourse
Scientific Writing :Research Discourse
 
Decoding the Tweet _ Practical Criticism in the Age of Hashtag.pptx
Decoding the Tweet _ Practical Criticism in the Age of Hashtag.pptxDecoding the Tweet _ Practical Criticism in the Age of Hashtag.pptx
Decoding the Tweet _ Practical Criticism in the Age of Hashtag.pptx
 
Mental Health Awareness - a toolkit for supporting young minds
Mental Health Awareness - a toolkit for supporting young mindsMental Health Awareness - a toolkit for supporting young minds
Mental Health Awareness - a toolkit for supporting young minds
 
Textual Evidence in Reading and Writing of SHS
Textual Evidence in Reading and Writing of SHSTextual Evidence in Reading and Writing of SHS
Textual Evidence in Reading and Writing of SHS
 
BIOCHEMISTRY-CARBOHYDRATE METABOLISM CHAPTER 2.pptx
BIOCHEMISTRY-CARBOHYDRATE METABOLISM CHAPTER 2.pptxBIOCHEMISTRY-CARBOHYDRATE METABOLISM CHAPTER 2.pptx
BIOCHEMISTRY-CARBOHYDRATE METABOLISM CHAPTER 2.pptx
 
Beauty Amidst the Bytes_ Unearthing Unexpected Advantages of the Digital Wast...
Beauty Amidst the Bytes_ Unearthing Unexpected Advantages of the Digital Wast...Beauty Amidst the Bytes_ Unearthing Unexpected Advantages of the Digital Wast...
Beauty Amidst the Bytes_ Unearthing Unexpected Advantages of the Digital Wast...
 
Measures of Position DECILES for ungrouped data
Measures of Position DECILES for ungrouped dataMeasures of Position DECILES for ungrouped data
Measures of Position DECILES for ungrouped data
 
Student Profile Sample - We help schools to connect the data they have, with ...
Student Profile Sample - We help schools to connect the data they have, with ...Student Profile Sample - We help schools to connect the data they have, with ...
Student Profile Sample - We help schools to connect the data they have, with ...
 
Multi Domain Alias In the Odoo 17 ERP Module
Multi Domain Alias In the Odoo 17 ERP ModuleMulti Domain Alias In the Odoo 17 ERP Module
Multi Domain Alias In the Odoo 17 ERP Module
 
Using Grammatical Signals Suitable to Patterns of Idea Development
Using Grammatical Signals Suitable to Patterns of Idea DevelopmentUsing Grammatical Signals Suitable to Patterns of Idea Development
Using Grammatical Signals Suitable to Patterns of Idea Development
 

BE Compiled

  • 1. SCHOOL OF ARCHITECTURE, BUILDING AND DESIGN Bachelor of Quantity Surveying (Honours) August 2017 BUILDING ECONOMICS ASSIGNMENT Lecturer: Sr. Dianne Kok Hui Wei Date of Submission: 21st November 2017 Student Name Student ID Liu Wei Qian 0322969 Maybelle Wang Sze Kher 0327553 Mok Po Yi 0318207 Ng Seng He 0323037 Pan Lek Vun 0323164 Pang Khai Shuen 0318423 Sherlyn Ang Tse Yun 0317977 Siong Jia Yii 0318239
  • 2. 2 Table of Contents 1.0 Introduction....................................................................................................... 3 1.1 Benchmark Project........................................................................................ 4 1.2 Building Design Proposal .............................................................................. 7 1.3 Green Building Index................................................................................... 13 2.1 Gross Floor Area ............................................................................................ 20 2.2 Office........................................................................................................... 21 2.4 Basement Carpark ...................................................................................... 22 2.5 F&B – Food court........................................................................................ 23 2.6 Softscape & Hardscape (included water feature, park furniture & signage) 24 2.8 Covered Pedestrian Walkway ..................................................................... 29 2.9 Others (Allowance)...................................................................................... 32 2.10 GBI Platinum Rating Allowance .................................................................. 35 2.11 Benchmark Project Cost Allocation............................................................... 36 3.0 Conclusion...................................................................................................... 37 Appendix .................................................................................................................. 38
  • 3. 3 1.0 Introduction Our site is designated to be in the heart of Kuala Lumpur, right next to the current developing Tun Razak Exchange. It is strategically located near to the CBD as our project consists of office tower and commercial retail spaces. This proposed project is expected to be a vibrant, environmental friendly and economic development. Our project will have a mix of commercial, office spaces and some entertainment. We plan to have a plot ratio of 1:10 for this development as this has been proven to be a good benchmark for commercial developments. This means that it will not be too crowded, but also an efficient way of using the spaces that are available to us. Around this area, there are many commercial office spaces and retail spaces across the block as well as the proposed Tun Razak Exchange, which is expected to be Malaysia’s most robust and innovative financial district. Since this area has been definitively known as a financial precinct, we are also aiming to develop this land to suit the requirements. We also intent to be the benchmark for future developments in terms of green building and our efficiency. Our project complements the CBD and also contributes to serve as a growth factor to many major companies. This land parcel is strategically located between Telok Ayer Street and Cecil Street which is one of the main roads towards the CBD. This location is easy to find and offers a great variety of choices. This also gives the opportunity for the real estate around the area to appreciate in value, hence encouraging more investors come in to invest. There are a few landmarks which area Pavilion KL, Low Yat Plaza and Berjaya Times Square just to name a few. The site area is divided into 3 plots. Each of these plots have different area and different usage. Plot A1 is 5990.80 sqm, which is designated for the building of maximum 50 stories office tower and development of commercial retail spaces. Plot A2 has an area of 1612.40 sqm, and it is open space area with F&B kiosk of less than 100 sqm. Plot A3 is only 180sqm, which is a subterranean space and it is to be developed for part of a pedestrian walkway to the MRT station. This is done by constructing an underground linkway passage for the ease of use. These 3 plots of land will be used to their fullest potential in terms of green building and commercial development.
  • 4. 4 1.1 Benchmark Project The benchmark project set for this project is located at the centre of the city, Kuala Lumpur, a corporate headquarter office tower comprising design and construction of 1 block of 32-storey office tower and 1 block of 9 storey carpark with 1 level of common basement and external infrastructure works. This high-rise building served as a landmark corporate headquarters designed for business versatility with Grade-A intelligent features. A total of 25-feet high grand lobby with spacious freedom with 9.5 feet floor-to-ceiling office space within 32 floors with 3 distinctive zones that cater to multi-functional businesses. This building has been certified by GBI as well as MSC compliant in recognition of their practice for environmental design and construction. The office tower is complete with features that provide fibre-optic backbone with 100% backup power supply with Building Management System that ensures the optimal saving in energy and water usage and real time monitoring of environmental changes including carbon monoxide levels. Besides all the environmental features mentioned above, it is located at a strategic location that have easy access to public transport like the bus, LRT, KTM and Monorail stations.
  • 5. 5
  • 6. 6
  • 7. 7 1.2 Building Design Proposal The land plot is divided in Plot A1, A2, & A3, each with distinctive functions and purposes. Our team attempted to divide the usage of these plots accordingly to achieve the maximum diversity and efficiency of land use. Our proposed building design consists of several main elements: 1) Main Office Building The main feature of this development, situated in Plot A1, is an approximately 100m high office tower, housing 25 floors of offices and the ground floor as retails. The average GFA per floor is 2500m2. Floor to floor height is 3.6m per floor, with ground floor being extended to 4.0m height. The office floor area amount to 62,288m2, surpassing the required 61,730m2.
  • 8. 8 2) Retail Block Located next to the main office building in Plot A1 is a 4-storey shopping centre. It acts as a façade facing Telok Ayer Street. Approximately 20 meters in height, this structure consists of 1200m2 GFA per floor, amounting to 4,800m2 of retail space. Combined with the ground floor of the office building, these two spaces provide 7,300m2 GFA of retail zones. 3) Cafeteria The landscaping area in Plot A2 will hold a cafeteria, with a maximum GFA of 100m2. This building will be located at the top right corner of the plot as demarcated in the drawing.
  • 9. 9 4) Basement The basement level of this development will consist of underground parking and pedestrian walkways. We have provided approximately 6,300m2 of parking space, which translates to 418 total parking bays, out of which 311 serves for office use, 37 for retail uses, and 70 additional bays for public use as requested by the client. There will also be an underground pedestrian walkway spanning from the end of Plot A1 to Plot A3. It is estimated to be 95 meters in length and 6m wide. An additional 30-meter long walkway is required to connect the proposed development to the existing underground pedestrian walkway leading to an existing MRT station. 5) Covered Pedestrian Walkways
  • 10. 10 Situated around the office and retail blocks is the covered pedestrian walkways. Two different widths of walkways (3.6m and 5.0m) are required for different locations. We provided steel structures with glass canopy to cover the walkways. 5.0m wide covered walkway is provided in front of the office block, before the building setback line. 3.6m wide covered walkway is provided for the sides facing Telok Ayer Street and Cecil Street to promote walkability around the area. Another stretch is also built to provide access to the existing Methodist Church.
  • 11. 11 6) Existing Methodist Church and its setback lines The development is required to preserve the existing Methodist Church, and adhere to the stated setback lines for at-grade and subterranean structures built around it. The existing Methodist church is located beside Plot A2 iof the development land parcel. Two distinct no-build and setback area need to be adhered while planning the development.
  • 13. 13 1.3 Green Building Index This project requires a platinum rating in Green Building Index which is the highest rank in the classification of GBI. The assessment criteria of GBI includes energy efficiency, indoor environmental quality, sustainable site planning and management, material and resources, water efficiency and innovation. The building has to score at least 86 points from all the criteria stated above in order to achieve a platinum grade GBI.
  • 14. 14 Green Building Index benchmark project Building: SP Setia corporate Headquarter Client: Bandar Setia Alam Sdn Bhd Location: Setia Alam (Malaysia) Gross total surface area: 33,838 m2 Lot size: 12,300 m2 Commencement of work: 2012 Completion of work: 2014 Type of building: Office SP Setia headquarter is the third building to achieve GBI’s platinum grade in Malaysia. Besides, it has also achieved GreenRe Platinum and The Edge Malaysia-PAM Green Excellence Award. We can know that it is a sustainable, high value and vibrant building that encourages a balanced and green lifestyle. The office building is connected to a shopping mall – Setia City Mall which achieved a silver rating in GBI. It is similar with our project nature so this is the reason we refer our project to this benchmark project.
  • 15. 15 Green feature and initiatives The proposal to score platinum grade in Green Building Index as following: Energy Efficiency Feature Extra information  High-performance double glazed windows and louvres to reduce heat gain and encourage natural lighting.  Solar photovoltaic panels on rooftop to harvest renewable energy. In benchmark project, the solar panel helps to generate 55Kw of energy which is 2% of the energy consumption.  Energy measurement system It is used to measure and manage the energy and water usage of the building.
  • 16. 16  Energy-efficient lighting, for example T5 fluorescent lighting with high frequency ballast.  Flexible lighting controls - individually switched lighting zones are less than 100 sq m in the main building Zoning – Zoning is the grouping of luminaires into functional areas. It enable the ease of controlling the usage of lighting at each areas to prevent energy waste when that area does not require lighting.  Auto sensor-controlled lighting strategy such as photo sensor cells at perimeter zones and motion sensors in less frequent areas in our projects. Artificial lighting will be switched off when there is sufficient daylight.
  • 17. 17 Water efficiency Feature Extra information  Rainwater harvesting from the buildings for landscape irrigation in plot A2 and replenish water feature Environmental protection  Using GBI-certified architectural products and construction materials. For example, the usage of fair face concrete to minimize long term maintenance and improve aesthetic value. Low volatile organic compound paint is encouraged as well.  Promoting recycling by providing recycling bins in common areas.  Sustainable construction will be implemented. Reusable and recyclable formwork will be used and strict waste management and pollution control will be taken.
  • 18. 18 Indoor Environmental quality Feature Extra information  Efficient air-conditioning system design, for example raised floor for underfloor air- conditioning distribution system in the office building. Energy wasted on delivering conditioned air from ceiling to floor slab will be reduced.  Other features such as CO2 sensor, auto condeser tube cleaning system, heat recovery wheel will be used in the building to control the environmental quality. Sustainable site planning Feature Extra information  Open space – The open space of our project is 27% of the total development area. There will be landscaping all over the open space in plot A2 which increase the greenery. Covered pedestrian walkway and underground walkway will have connections with the building, open space and MRT station.  Quality assessment system for building construction work will be implemented and achieve a minimum score of 70%  Green vehicle priority – low emitting and fuel efficient vehicles will be encouraged, for example hybrid car, car pool and bicycle. Parking for these green vehicle will be provided as well.
  • 19. 19  Public transport access – there is an existing MRT station nearby the project which is Tanjong Pagar MRT station. Underground pedestrian walkway will be connected to the MRT station from our project.  Roof – roof garden to serve as a functional space while minimising solar heat gain. Besides, the project will be using the combination of solar energy and roof garden which is applicable to the roof of office building and shopping mall at Plot A1 Solar panel Roof garden
  • 20. 20 2.1 Gross Floor Area Total GFA = 76,560m2 Breakdown by functional elements: Element Office Retail Carpark Walkways GFA (m2) 62,288 7,300 6,270 602 Percentage (%) 81 9 9 1 *Please refer to Appendix C for detailed GFA build up. Office 81% Retail 10% Carpark 8% Walkways 1% Elemental Breakdown Office Retail Carpark Walkways
  • 21. 21 2.2 Office Item Qty (CFA) Unit Calculation Rate (RM/m2) Total (RM) Source Office 68,517 m2 (3,560 + 4,840) 2 4,200.00 287,770,000.00 JUBM cost handbook Source from JUBM & Arcadis Construction Cost Handbook MALAYSIA 2017 2.3 Retail Item Qty (CFA) Unit Calculation Rate (RM/m2) Total (RM) Source Mall 8,030 m2 (2,760 + 3,515) 2 3,138.00 25,190,000.00 JUBM cost handbook Source: Source from JUBM & Arcadis Construction Cost Handbook MALAYSIA 2017
  • 22. 22 2.4 Basement Carpark Item Qty (CFA) Unit Calculation Rate (RM/m2) Total (RM) Source Basement Carpark (Office) 309 lots x 15m2 = 4,665m2 m2 (1,475 + 2,030) 2 1,753.00 8,180,000.00 JUBM cost handbook Basement Carpark (Retail) 41 lots x 15m2 = 555m2 m2 (1,475 + 2,030) 2 1,753.00 970,000.00 JUBM cost handbook Basement Carpark (Extra) 70 lots x 15m2 = 1,050m2 m2 (1,475 + 2,030) 2 1,753.00 1,840,000.00 JUBM cost handbook Source from JUBM & Arcadis Construction Cost Handbook MALAYSIA 2017
  • 23. 23 2.5 F&B – Food court Item Qty (CFA) Unit Calculation Rate (RM/m2) Total (RM) Source Food court 100 m2 1,463,752 2 1,823.00 180,000.00 BQ from previous project Food Court concept – one storey food court, GFA = 100m2
  • 24. 24 2.6 Softscape & Hardscape (included water feature, park furniture & signage) Item Qty (m2) Unit Calculation Rate (RM/m2) Total (RM) Source Softscape & hardscape 1,356 m2 - 150.00 200,000.00 BQ from previous project Softscape: Based on the client’s requirement, there will be minimum 40% of lush landscaping. These are the example items (trees, palm, shrubs and turfing) included: Trees Palm Turfing Shrub Xanthestemon chrysanthus Plumeria rubra Cuphea hyssopifoliaLoropetalum chinense var. rubrumAcalypha siamensis Wodyetia bifurcataCyrtostachys renda Zoysia matrella
  • 25. 25 Hardscape: These are the example items (excluding lighting): Seating Reflexology path Concrete walkway Water feature Concrete benchConcrete planter box with seating Signage
  • 26. 26 Night lighting: Night lighting are priced based on lump sum – RM 500,000. It is all over the development area, not only in plot A2 landscape area. Solar pole light Up light
  • 27. 27 2.7 Underground Pedestrian No Item Unit Calculation Qty Rate (RM) Total (RM) Sources 1 Excavation < 6.00m deep m³ (65.5 + 30 + 43.5) x 6 x 4.5 3753 45.00 168,885.00 BQ from previous project 2 Backfilling with 300mm thick coarse aggregate m² 139 x 6 834 40.00 33,360.00 BQ from previous project 3 Grade 35 reinforced vibrated concrete (floor) m³ 139 x 6 x 0.5 287 253.70 72,685.05 CIDB 4 Grade 35 reinforced vibrated concrete (wall) m³ 139 x 4.5 x 0.3 x 2 375 253.70 95,213.61 CIDB 5 Formwork (floor) m² (139 + 6) x 2 x 0.5 145 34.00 4,930.00 QS Online 6 Formwork (wall) m² (139 x 4.5 x 2 x 2) + (4.5 x 0.3 x 4) 2507 34.00 85,251.60 QS Online 7 BRC Ref No. B10 (2 layers) m² 139 x 6 x2 1668 34.70 57,879.60 BQ from previous project 8 Waterproofing (floor) m² 139 x 6 834 35.40 29,523.60 BQ from previous project 9 Waterproofing (wall) m² 139 x 4.5 x 2 1251 35.40 44,285.40 BQ from previous project 10 0.25mm thick polythen sheet damp proof membrane m² 139 x 6 834 5.00 4,170.00 BQ from previous project 11 600mm x 300mm porcelain tiles including minimum 20mm thick base screed m² 139 x 6 834 74.80 62,383.20 QS Online
  • 28. 28 No Item Unit Calculation Qty Rate (RM) Total (RM) Sources 12 1220mm x 1220mm x 3.2mm thick 'UAC' Asbestos free ceiling sheet fixed to steel joist m² 139 x 6 834 60.00 50,040.00 BQ from previous project 13 300mm x 600mm Granite wall tiles m² 139 x 4 x 2 1112 200.00 222,400.00 BQ from previous project 14 Lift/escalator m² 2 x 15 x 2 60 247.50 14,850.00 JUBM cost handbook 15 Services m² 139 x 6 834 610.00 508,740.00 JUBM cost handbook TOTAL (RM) 1,454,597.06 UNIT COST (RM/m2) 1744.12
  • 29. 29 2.8 Covered Pedestrian Walkway *picture shown is for illustration purposes only *Refer calculation below **Marked up 10% A) I-beam quantity calculation No Item Unit Qty Rate (RM) Total (RM) Sources 1 Glass Canopy ft² 9311 85.80** 798,883.80 arrowhub.com 2 Hot rolled circular hollow sections @ 3m c/c* tonne 6.225 3300.00** 20,542.50 quantitysurvey- oronline.com 3 I-beam @ Linear* tonne 9.374 3300.00** 30,934.20 quantitysurvey- oronline.com 4 I-beam @ 600mm c/c* tonne 20.350 3300.00** 67,155.00 quantitysurvey- oronline.com 5 200mm x 200mm Homogeneous Floor Tiles m² 865 145.88 126,186.20 Previous BQ 6 Lighting Nos 73 150.00 10,950.00 Cost Plan TOTAL 1,054,561.70 Cost/m2 Total area = 865m2 1,219.15
  • 30. 30  Total length of I-beam for 3.6m wide walkway (spans across columns) = 135m + 15m = 150m  Total length of I-beam for 5.0m wide walkway (spans across columns) = 65m  Total length of I-beam (spans across columns) = 150m + 65m = 215m B) I-beam quantity calculation (cont’d)  Nos. of I-beam (spread out to hold glass canopy) (150m/0.6m+1) = 251 nos @ 3.6m span (65m/0.6+1) = 110 nos @ 5.0m span  Total length of I-beam (spread out to hold glass canopy) = (251x3.6) + (110x5.0) = 1453.6m C) Hot-rolled circular hollow section calculation  Nos of CHS = (215/3m) + 1 = 73 nos @ 3.2m high = 233.6m D) Floor tiles and Glass canopy calculation  Total area of 3.6m wide walkway = 3.6m x 150m = 540m²  Total area of 5.0m wide walkway = 5.0m x 65m = 325m²  Quantity of Glass Canopy = 865m² x 10.7639 = 9310.77ft² Assumptions: 1) Hot rolled circular hollow sections is 177.8mm dia., 6.3mm thk @ 26.65kg/m, surface area per metre 0.559 2) I-beam for spans across columns is 200mm x 175mm @ 43.6kg/m, surface area per metre 1.15 3) I-beam spread out to hold glass canopy is 150mm x 75mm @ 14.0kg/m, surface area per metre 0.576
  • 31. 31 Item Weight (kg/m) Length (m) Total weight (kg) Hot rolled circular hollow sections 177.8mm dia, 6.3mm thk 26.65 233.6 6225 I-beam 200mm x 175mm width 43.6 215.0 9374 I-beam 150mm x 75mm width 14.0 1453.6 20350
  • 32. 32 2.9 Others (Allowance) a) Utilities Detection Works - RM 45,000.00 Utilities detection works determine the existing utilities of the site located at subsurface or above ground. Any gas, electric, telephone, cable, water and sewer lines identified will be used to design other utilities services of the new proposed buildings. b) Site survey/investigation - RM 80,000.00 Site survey/investigation is carried out at the construction site to gather information on physical conditions that will be encountered during the performance of the work. Site survey should determine all the unusual circumstances of the site, the state of existing buildings that are to be demolished and the conditions of the adjacent buildings and sites. Thorough site survey is to be completed to identify the effect to demolition to other existing buildings around the site. c) Geotechnical Investigation Works - RM 220,000.00 Geotechnical investigation is below-ground work to obtain information on physical properties of soil and rock around site that performed by geotechnical enginners. Geotechnical investigation works including surface and subsurface exploration, soil sampling and testing which used to design earthworks and foundations for proposed structures. Besides that, geotechnical investigation also used to measure thermal resistivity of soils or backfill materials required for underground transmission lines, oil and gas pipelines, radioactive waste disposal and solar thermal storage facilities.
  • 33. 33 d) Hoarding and Signboard - RM 120,000.00 Hoarding is a temporary structure erected around perimeter of construction site to secure them from view and prevent unauthorised access. It act as part of site security system in ensuring health and safety for site workers, visitors and general public and to prevent theft or vandalism. Signboard is a board that indicating both user and corporate identity of professions which usually placed at the entrance of site. e) Cadastral Survey (Plot A1, A2 & A3) (Allowance) - RM 50,000.00
  • 34. 34 Cadastral Survey is a survey to determine boundaries and area of a lot of land or more. It can be categorized as title survey and demarcation survey. Title survey is whereby the survey is for registering the final title while demarcation survey is to determine the boundaries of a land for the purposes such as the land's location, land's area, or clearance for building construction. Cadastral surveys are controlled by law and the surveys within the meaning of Section 396 of the National Land Code (Act 56 of 1965). The cadastral survey carried out will be certified by the Department of Survey and Mapping Malaysia (JUPEM). f) Utility Connection Charges - RM 120,000.00 Connection charges recover the cost of installing and maintaining assets that allow parties to connect to the transmission system and which are not normally used by any other party. The utility connection charges consist of electricity, water, sewage and telephone.
  • 35. 35 g) Services diversion: electricity (Allowance) - RM 120,000.00 Moving the electricity cables or overhead power lines because they are affected during construction work. For example, moving the meter and service cable when the construction is completed or maybe alter the position of meter and service cable. We can also move the service cable from internal to external position. h) Traffic Impact Assessment - RM 50,000.00 Traffic impact assessment or TIA for short, is an important part of the preliminaries. The officer of the assessment should be aware of the condition of traffic around the area of construction. It is vital to engineers and transport planner to determine the possible effects of development on the transportation and traffic system and to mitigate and negative impacts. TIA will incur roughly RM 50,000 for this particular project. i) Protection of Existing Roadside Trees - RM 150,000.00 On the other hand, protection of existing roadside trees is to maintain and preserve the current trees around the construction site. This is especially important to us due to the fact the client requires us to achieve a Platinum GBI standard. Hence, we think it is justifiable to spend RM 150,000 for this item. 2.10 GBI Platinum Rating Allowance The allowance for GBI Platinum Rating is 10% in this project, as from our sources, we noted that the sum allocated for GBI purposes is usually 35% of the M&E Works. As M&E Works usually substantiate 30% of the total contract sum, we decided to apply 10% of the total contract sum after superimposing the two percentages.
  • 36. 36 2.11 Benchmark Project Cost Allocation *kindly refer to separate Excel file
  • 37. 37 3.0 Conclusion No. Item GFA (m2) Rate (RM/m2) Total (RM) 1 A1-Office 62,288 5,227 325,550,000 2 A1-Retail 7,300 3,929 28,680,000 3 A2-Open Space 100 3,800 380,000 Sub Total (No.1 – 3) 69,688 5,089 354,610,000 4 Allowance for Land Parcel 76,560 131 10,050,000 5 GBI Requirements (10% of No.1 -3) 76,560 463 35,460,000 Sub Total (No.1 – 5) 76,560 5,226 400,120,000 6 Contingencies (5% of No.1 - 5) - - 20,010,000 Sub Total (No.1 – 6) 76,560 5,488 420,130,000 7 Cost Escalation (5% of No. 1 – 6) - - 21,010,000 Grand Total 76,560 5,762 441,140,000 A summary of our cost plan is shown in the table above. In Plot A1, we proposed a 26 storey high-end commercial office tower with height of approximately 100m. A 4 storey shopping centre next to the main building is also provided. The basement area of the land parcel is planned to provide parking bays of 15m2 per lot for these two buildings, allocating 311 lots for office use and 37 lots for retail. These two development amount to GFA of 62,288m2 for office area with rate of RM5,227/m2, reaching a total of RM325,550,000. While for retail area, GFA of 7,300m2 is allowed at a rate of RM3,929/m2 totalling at RM28,680,000. Plot A2 is proposed to be an open space filled with park furniture and water features. In addition, a single storey cafeteria with a maximum GFA of 100m2 is provided. A total of RM380,000 is allowed for A2. Plot A3 will be used to develop an underground pedestrian walkway spanning through A1 and A2. The walkway will be connected to the nearby MRT station for public ease of access. We allocated RM10,050,000 for development of the walkway and additional works to land parcel such as demolition, covered walkway, roof garden, public car parks and site works. To be able to meet GBI platinum rank requirement, there is an allowance of RM35,460,000, constituting 10% of total building work cost. Besides that, a sum of RM20,010,000 is provided for contingency, which is 5% of total cost including GBI allowance. Finally, a cost escalation of RM21,010,000, consisting of 5% of total amount including contingency, is allocated assuming that tender is called in one year. To summarize, the total GFA for the whole development is 76,560m2. The final amount totals up to RM441,140,000 with rate of RM5,762/m2. We consider the project to be feasible and recommend the client to proceed as it has an advantageous location to become a unique city attraction, providing great business opportunities.
  • 38. 38 Appendix 1. Glass Canopy – http://arrowhub.com/ 2. Steel structure (Hot rolled circular hollow sections & I-beam)- http://www.quantitysurveyoronline.com.my/
  • 39. 39 3. Grade 35 concrete (CIDB) 4. Formwork (quantity surveyors online) 5. 600mm x 300mm porcelain tiles (quantity surveyors online) 6. Lift/escalator (JUBM cost handbook) 7. Services (JUBM cost handbook)