Procurement strategy in major infrastructure: The AS-IS and STEPS - D. Makovšek, OECD Public Governance Directorate

OECD Governance
OECD GovernanceOECD Governance
PROCUREMENT STRATEGY IN
MAJOR INFRASTRUCTURE:
The AS-IS and STEPS
17th May 2023
Dejan Makovšek, PhD
Infrastructure and Public Procurement Division
Public Governance Directorate
With an expert opinion by Andrea Chao LLM
Partner & Lawyer at Bird & Bird LLP
(Amsterdam)
How procurement strategy choices matter for project
outcomes
2
Blanc-Brude & Makovsek (2013):
• Analysed a bank’s database of project finance deals – 75 mega
projects.
• Observed median construction risk is zero, average is 2%. 54/75
projects were exactly on budget.
0
10
20
30
40
50
60
70
-55 -50 -45 -40 -35 -30 -25 -20 -15 -10 -5 0 5 10 15 20 25 30 35 40 45 50
Observations
Observed cost overruns
Example I: On-budget performance for major EPC
(lump-sum) infra contracts
4
Bolotny & Wasserman (2022):
• 44o small bridge projects empirically analyzed in a structural mathematical
model.
• The result (42% price hike) is the net outcome conceals two effects:
– I) bidders include an increased contingency [the effect increases cost];
– II) less efficient bidders get excluded
Example II: From DBB to lump sum contracts in small
projects
DBB (schedule of rates)
DBB (Lump-sum)
Total cost
Cost overrun
Cost at contract signature
+42%
A few contemplations:
5
Relevant should not be the price mentioned in the contract,
but the price eventually paid:
• A price that is too low may help getting the project
kickstarted internally
• But such price also creates a fundamental flaw in a
project: lack of profit that needs to be recouped – through
whichever means necessary
A few contemplations:
6
When looking at the price eventually paid, also look at:
• Internal costs/shift in focus
• Legal costs
• Social costs (incl. people leaving the sector)
… And your social obligations
A few contemplations:
7
What happens when allocating high level of risk at the market
side, esp. combined with award criteria focussed on lowest
price?
• Bid price increases to deal with this risk allocation
• Considered too risky: no bid
• Hoping for the best: going in eyes closed
What scenario would you prefer?
How do countries make choices about the procurement
strategy?
8
Context - The last thirty years…
• Lean public sector policy lead to reduced
capabilities (e.g. elimination of inhouse design
department at RWS in NL)
• Reduced capabilities => inability to manage
interfaces between contracts.
• Large projects => large contracts
• Large contracts + total risk transfer => low/no
competition.
9
Policymaker’s narrative:
• Complex project suffer cost
overruns – transfer more risk
• DB/EPC contracts transfer
too much risk
• De-risking needed to keep
procuring big contracts
Delivery model assignment for public works projects
and programmes – the global best practice
10
Frame the challenge
What are my objectives
What is the strategy of
my org
Identify … potential delivery models
Control offered?
Innovation potential?
Do I have capability to manage?
Will the market accept?
Who is best placed to manage risk?
Decide packaging
Into how many contracts should my
project be split
Engage the market
Will the market accept our
procurement strategy
Iterate if not digestible
The problems of the existing “state-of-the-art”
• A top-down approach in which defining the objectives/constraints directly identifies
the best delivery model. A self-contained process, which requires no external
evidence.
• The client’s capabilities are taken as a given and not informed by the nature of the
project.
• The packaging decision is made after the delivery model has been selected => one-
size-fits-all risk allocation. Again ignoring the nature of the project.
• The entire sequence of analysis/decision-making process is not grounded in any
empirically tested theory.
11
A few contemplations:
12
Money talks
… but:
- choices have consequences
- all tasks need to be done by someone, and nothing comes
for free
A few contemplations:
13
Quick
Good Cheap
Pick any 2
The approach the OECD is piloting
STEPS - Support Tool for Effective Procurement
Strategy®
14
The value proposition of STEPS
• Based on scientific insights (being “evidence-based” is not
sufficient), i.e. does not legitimize preconceived ideas
• Identifies the right unit of analysis/granularity
• Helps inform structure/capabilities of the client org
• Leads to less costly infra, without loss in innovation or
increase in conflict, compared to existing approaches
15
Breaking down a project into STEPS activities
• STEPS activity =
– economic activity (not detailed technical task)
– technologically bounded (skillsets)
– highest level of firm specialization
16
A B E
R
Market
(suppliers for
activity a, b, …)
A A A A A
B B B B B B
…
E E
R R
1 2 3 4 5 6
…
…
…
Example: Commercial implications of contract
packaging?
17
An activity with
many suppliers
An activity with one
(few) suppliers
Bidder
consortium 1
Bidder
consortium 2
Commercial implications of bargaining power shift
(hold-up)?
18
An activity with no
hold-up
An activity with
hold-up
Why do we assume that major projects are
homogenous in terms of risk and uncertainty?
19
Procurement strategy solution for project X
20
DBB with schedule of rates
A collaborative delivery
model
DB contract
Persistent post-contract
uncertainties causing
hold-up risk
Competition failure risk
Hold-up risk
Procurement failures
21
Contract
signature
Pre-contract failures
• Competition failure
(Too few bidders)
• Hold-up
• Inadequate risk allocation
(e.g. one size fits all
commercial arrangement)
Post-contract failures
A few contemplations:
22
Hold up - during the tender (or even before)
- Level of competition available?
- Further limiting competition by:
- Work packages – too large
- Tender requirements – too many, too harsh
- Risk allocation – too harsh
A few contemplations:
23
Hold up after the tender
- A construction project is a moving train
- Stopping takes a long time
- Getting of while moving is dangerous
- Restarting takes a long time
- Once the project has started, there is a shift in balance
A few contemplations:
24
Risk of hold up for future projects is influenced by decisions
made on a current project
- Promoting new market parties to arise?
- Sticking to the usual suspects?
- One project approach, or framework approach?
What are your tender requirements driving?
25
The end result of a complete procurement strategy
Bidder selection
Incentive power
(competition vs
collaboration)
(scientific& enshrined in legislation)
(scientific)
Steps in a procurement strategy How a decision is made
Contract scoping (scientific)
(scientific)
Make-or-buy
The delivery
model
Delivery
entity
(capabilities
organisation,
leadership,
…)
Iteration of
solutions
Repository of post contract
procurement failures from all
projects (the red dots)
Market structure -
capabilities data
(the red dots)
Towards a holistic risk management framework as
well as STEPS Digitalisation
Using AI to predict procurement
failures…
Category managers checking
supply chain
STEPS
(the commercial
implications)
Standard Initial
detailed risk analysis
(the tech. reasons)
Execution of
procurement
strategy
Other risk dimensions
(OECD/UCL/MBS)
Affecting risk and therefore
management strategy
26
Planning/
appraisal
and value
distribution
THANK YOU
DEJAN.MAKOVSEK@OECD.ORG
& GUEST COMMENTATOR
ANDREA.CHAO@TWOBIRDS.COM
27
Where does procurement strategy fit when compared
to standard project risk management?
28
Risk identification
…technical failures, third
party interfaces, permit
issues…
Risk mitigation
…build contingency for
technical failure, get
permit…
Commercial/contracting
implications
…opportunism of suppliers
in contracts, changes in
their bargaining power…
STEPS
Steps and main cognitive lenses behind the STEPS
(Support Tool for Effective Procurement Strategies)
29
Theory applied to issue/decision in step
in Tool
Theory Leading scholar examples
Step 1.
Project activity break-down
Division of Labour/ Specialisation Adam Smith
Transaction Costs Economics Oliver Williamson (Nobel Prize 2009)
Step 2.
Project Specific-or-Network Analysis
Economics of Scale Adam Smith
Step 3.
Activity analysis
Uses theories listed under steps 4-6 to inform the economic characteristics of activities, making the
analysis in those steps possible
Step 4.
What Capabilities do I need in-house
(Make-or-Buy Analysis)
Transaction Costs Economics Oliver Williamson (Nobel Prize 2009)
Transaction Costs Economics Ronald Coase (Nobel Prize 1991)
Resource-Based Theory (competence and capabilities) Jay Barney
Step 5.
Into how many contracts should I package
(Activity bundling analysis)
Economies of Scope John Panzar and Robert Willig
Transaction Costs Economics Oliver Williamson (Nobel Prize 2009)
Resource-Based Theory (competence and capabilities) Jay Barney
Step 6.
Competition or collaboration? What payment
mechanism?
(Exchange Relationship Analysis)
Transaction Costs Economics Oliver Williamson (Nobel Prize 2009)
Principal-Agent Theory (contract theory)
Oliver Hart & Bengt Holmström (Nobel Prize
2016), Michael C. Jensen & William Meckling
Resource-Based Theory (competence and capabilities) Jay Barney
Example III: Similar result in major contracts (EIB
Motorways)
30
• Construction risk: risk premium in 57 DB/EPC (in a PPP) road
contracts ~20% above ex-post risk in 101 DBB contracts (LCC does
not explain diff.); based on Blanc-Brude et al 2009.
DBB
Public-Private Partnership (DB/OM)
Total cost
Cost overrun
Cost at contract signature
24%
Source: Makovšek & Moszoro 2018.
What the existing approach boils down to…
• The procurement strategy is a methodology to legitimise
preconceived ideas about project objectives.
• It is not a method that would inform trade-offs, possibly
leading to an adjustment of the project objectives or the
approach how to achieve them.
• The result can be a bias towards larger contracts, one-size-
fits-all risk allocation ... and much more expensive infra.
31
Take this slide out and just deliver orally? –
Question Bjorn can ask
1 de 31

Recomendados

The Support Tool for Effective Procurement Strategies (STEPS) por
 The Support Tool for Effective Procurement Strategies (STEPS) The Support Tool for Effective Procurement Strategies (STEPS)
The Support Tool for Effective Procurement Strategies (STEPS)OECD Governance
3.1K visualizações14 slides
Pm chapter 2 por
Pm chapter 2Pm chapter 2
Pm chapter 2Golam Bitonsir
402 visualizações56 slides
Pm chapter 2... por
Pm chapter 2...Pm chapter 2...
Pm chapter 2...Golam Bitonsir
1.2K visualizações57 slides
Eric van Heck - Congres 'Data gedreven Beleidsontwikkeling' por
Eric van Heck - Congres 'Data gedreven Beleidsontwikkeling'Eric van Heck - Congres 'Data gedreven Beleidsontwikkeling'
Eric van Heck - Congres 'Data gedreven Beleidsontwikkeling'ScienceWorks
190 visualizações39 slides
2.requirements management por
2.requirements management2.requirements management
2.requirements managementPanos Fitsilis
821 visualizações111 slides
Capítulo disponibilizado na Internet pela editora..pdf por
Capítulo disponibilizado na Internet pela editora..pdfCapítulo disponibilizado na Internet pela editora..pdf
Capítulo disponibilizado na Internet pela editora..pdfPrakharDwivedi30
74 visualizações36 slides

Mais conteúdo relacionado

Similar a Procurement strategy in major infrastructure: The AS-IS and STEPS - D. Makovšek, OECD Public Governance Directorate

Preparing Detailed Project Report and Presenting Business Plan to Investors por
Preparing Detailed Project Report  and Presenting Business Plan to InvestorsPreparing Detailed Project Report  and Presenting Business Plan to Investors
Preparing Detailed Project Report and Presenting Business Plan to InvestorsRahul Sharma
86.7K visualizações57 slides
Vskills project finance sample material por
Vskills project finance sample materialVskills project finance sample material
Vskills project finance sample materialVskills
65 visualizações9 slides
APM Presents - Why Value Management might reveal just what managing projects... por
APM Presents - Why Value Management might reveal just what managing  projects...APM Presents - Why Value Management might reveal just what managing  projects...
APM Presents - Why Value Management might reveal just what managing projects...Association for Project Management
4.2K visualizações30 slides
M6 Toll Road Construction por
M6 Toll Road ConstructionM6 Toll Road Construction
M6 Toll Road ConstructionHeidi Owens
2 visualizações80 slides
Extended Business Model Canvas (OOP 2021) por
Extended Business Model Canvas (OOP 2021)Extended Business Model Canvas (OOP 2021)
Extended Business Model Canvas (OOP 2021)Kurt Cotoaga
79 visualizações41 slides
Aftermarket2012 cargotec malcolmyoull por
Aftermarket2012 cargotec malcolmyoullAftermarket2012 cargotec malcolmyoull
Aftermarket2012 cargotec malcolmyoullCopperberg
491 visualizações26 slides

Similar a Procurement strategy in major infrastructure: The AS-IS and STEPS - D. Makovšek, OECD Public Governance Directorate(20)

Preparing Detailed Project Report and Presenting Business Plan to Investors por Rahul Sharma
Preparing Detailed Project Report  and Presenting Business Plan to InvestorsPreparing Detailed Project Report  and Presenting Business Plan to Investors
Preparing Detailed Project Report and Presenting Business Plan to Investors
Rahul Sharma86.7K visualizações
Vskills project finance sample material por Vskills
Vskills project finance sample materialVskills project finance sample material
Vskills project finance sample material
Vskills65 visualizações
M6 Toll Road Construction por Heidi Owens
M6 Toll Road ConstructionM6 Toll Road Construction
M6 Toll Road Construction
Heidi Owens2 visualizações
Extended Business Model Canvas (OOP 2021) por Kurt Cotoaga
Extended Business Model Canvas (OOP 2021)Extended Business Model Canvas (OOP 2021)
Extended Business Model Canvas (OOP 2021)
Kurt Cotoaga79 visualizações
Aftermarket2012 cargotec malcolmyoull por Copperberg
Aftermarket2012 cargotec malcolmyoullAftermarket2012 cargotec malcolmyoull
Aftermarket2012 cargotec malcolmyoull
Copperberg491 visualizações
Introduction to Engineering economics por Dr. C.V. Suresh Babu
Introduction to Engineering economicsIntroduction to Engineering economics
Introduction to Engineering economics
Dr. C.V. Suresh Babu1.7K visualizações
Auctioning RE projects: Lessons learned from auction design for renewable ele... por Leonardo ENERGY
Auctioning RE projects: Lessons learned from auction design for renewable ele...Auctioning RE projects: Lessons learned from auction design for renewable ele...
Auctioning RE projects: Lessons learned from auction design for renewable ele...
Leonardo ENERGY62 visualizações
Auctioning RE projects: Lessons learned from auction design for renewable ele... por Leonardo ENERGY
Auctioning RE projects: Lessons learned from auction design for renewable ele...Auctioning RE projects: Lessons learned from auction design for renewable ele...
Auctioning RE projects: Lessons learned from auction design for renewable ele...
Leonardo ENERGY1.2K visualizações
Nes cba summary 2012 por Rupert Greenhalgh
Nes cba summary 2012Nes cba summary 2012
Nes cba summary 2012
Rupert Greenhalgh200 visualizações
Procurement evaluation-vivich por PhDLogisticsandEngin
Procurement evaluation-vivichProcurement evaluation-vivich
Procurement evaluation-vivich
PhDLogisticsandEngin148 visualizações
Planning and preparing Infrastructure plans and projects - Jose Viegas, ITF, ... por OECD Governance
Planning and preparing Infrastructure plans and projects - Jose Viegas, ITF, ...Planning and preparing Infrastructure plans and projects - Jose Viegas, ITF, ...
Planning and preparing Infrastructure plans and projects - Jose Viegas, ITF, ...
OECD Governance642 visualizações
4. PAE AcFn621Ch-4a Project Alaysis and Selection.ppt por ProfDrAnbalaganChinn
4. PAE AcFn621Ch-4a Project Alaysis and Selection.ppt4. PAE AcFn621Ch-4a Project Alaysis and Selection.ppt
4. PAE AcFn621Ch-4a Project Alaysis and Selection.ppt
ProfDrAnbalaganChinn6 visualizações
Project Selection por Ian Cammack
Project SelectionProject Selection
Project Selection
Ian Cammack2.1K visualizações
The Role of the Business Case in Public Investment Management and Project Por... por Dr Rupert Booth
The Role of the Business Case in Public Investment Management and Project Por...The Role of the Business Case in Public Investment Management and Project Por...
The Role of the Business Case in Public Investment Management and Project Por...
Dr Rupert Booth304 visualizações
Pm0011 project planning and scheduling por smumbahelp
Pm0011  project planning and schedulingPm0011  project planning and scheduling
Pm0011 project planning and scheduling
smumbahelp301 visualizações
GAP Analysis por Lakshmi-BA
GAP AnalysisGAP Analysis
GAP Analysis
Lakshmi-BA1.8K visualizações
M&E Module 4.docx por swamy62
M&E Module 4.docxM&E Module 4.docx
M&E Module 4.docx
swamy628 visualizações

Mais de OECD Governance

Public Integrity Indicators Slides por
Public Integrity Indicators SlidesPublic Integrity Indicators Slides
Public Integrity Indicators SlidesOECD Governance
228 visualizações10 slides
Summary of the OECD expert meeting: Construction Risk Management in Infrastru... por
Summary of the OECD expert meeting: Construction Risk Management in Infrastru...Summary of the OECD expert meeting: Construction Risk Management in Infrastru...
Summary of the OECD expert meeting: Construction Risk Management in Infrastru...OECD Governance
339 visualizações8 slides
Using AI led assurance to deliver projects on time and on budget - D. Amratia... por
Using AI led assurance to deliver projects on time and on budget - D. Amratia...Using AI led assurance to deliver projects on time and on budget - D. Amratia...
Using AI led assurance to deliver projects on time and on budget - D. Amratia...OECD Governance
58 visualizações24 slides
ECI in Sweden - A. Kadefors, KTH Royal Institute of Technology, Stockholm (SE) por
 ECI in Sweden - A. Kadefors, KTH Royal Institute of Technology, Stockholm (SE) ECI in Sweden - A. Kadefors, KTH Royal Institute of Technology, Stockholm (SE)
ECI in Sweden - A. Kadefors, KTH Royal Institute of Technology, Stockholm (SE)OECD Governance
33 visualizações18 slides
Building Client Capability to Deliver Megaprojects - J. Denicol, professor at... por
Building Client Capability to Deliver Megaprojects - J. Denicol, professor at...Building Client Capability to Deliver Megaprojects - J. Denicol, professor at...
Building Client Capability to Deliver Megaprojects - J. Denicol, professor at...OECD Governance
13 visualizações22 slides
Procurement of major infrastructure projects 2017-22 - B. Hasselgren, Senior ... por
Procurement of major infrastructure projects 2017-22 - B. Hasselgren, Senior ...Procurement of major infrastructure projects 2017-22 - B. Hasselgren, Senior ...
Procurement of major infrastructure projects 2017-22 - B. Hasselgren, Senior ...OECD Governance
45 visualizações4 slides

Mais de OECD Governance(20)

Public Integrity Indicators Slides por OECD Governance
Public Integrity Indicators SlidesPublic Integrity Indicators Slides
Public Integrity Indicators Slides
OECD Governance228 visualizações
Summary of the OECD expert meeting: Construction Risk Management in Infrastru... por OECD Governance
Summary of the OECD expert meeting: Construction Risk Management in Infrastru...Summary of the OECD expert meeting: Construction Risk Management in Infrastru...
Summary of the OECD expert meeting: Construction Risk Management in Infrastru...
OECD Governance339 visualizações
Using AI led assurance to deliver projects on time and on budget - D. Amratia... por OECD Governance
Using AI led assurance to deliver projects on time and on budget - D. Amratia...Using AI led assurance to deliver projects on time and on budget - D. Amratia...
Using AI led assurance to deliver projects on time and on budget - D. Amratia...
OECD Governance58 visualizações
ECI in Sweden - A. Kadefors, KTH Royal Institute of Technology, Stockholm (SE) por OECD Governance
 ECI in Sweden - A. Kadefors, KTH Royal Institute of Technology, Stockholm (SE) ECI in Sweden - A. Kadefors, KTH Royal Institute of Technology, Stockholm (SE)
ECI in Sweden - A. Kadefors, KTH Royal Institute of Technology, Stockholm (SE)
OECD Governance33 visualizações
Building Client Capability to Deliver Megaprojects - J. Denicol, professor at... por OECD Governance
Building Client Capability to Deliver Megaprojects - J. Denicol, professor at...Building Client Capability to Deliver Megaprojects - J. Denicol, professor at...
Building Client Capability to Deliver Megaprojects - J. Denicol, professor at...
OECD Governance13 visualizações
Procurement of major infrastructure projects 2017-22 - B. Hasselgren, Senior ... por OECD Governance
Procurement of major infrastructure projects 2017-22 - B. Hasselgren, Senior ...Procurement of major infrastructure projects 2017-22 - B. Hasselgren, Senior ...
Procurement of major infrastructure projects 2017-22 - B. Hasselgren, Senior ...
OECD Governance45 visualizações
ECI Dutch Experience - A. Chao, Partner, Bird&Bird & J. de Koning, Head of Co... por OECD Governance
ECI Dutch Experience - A. Chao, Partner, Bird&Bird & J. de Koning, Head of Co...ECI Dutch Experience - A. Chao, Partner, Bird&Bird & J. de Koning, Head of Co...
ECI Dutch Experience - A. Chao, Partner, Bird&Bird & J. de Koning, Head of Co...
OECD Governance30 visualizações
ECI in Sweden - A. Kadefors, KTH Royal Institute of Technology, Stockholm por OECD Governance
ECI in Sweden - A. Kadefors, KTH Royal Institute of Technology, StockholmECI in Sweden - A. Kadefors, KTH Royal Institute of Technology, Stockholm
ECI in Sweden - A. Kadefors, KTH Royal Institute of Technology, Stockholm
OECD Governance28 visualizações
EPEC's perception of market developments - E. Farquharson, Principal Adviser,... por OECD Governance
EPEC's perception of market developments - E. Farquharson, Principal Adviser,...EPEC's perception of market developments - E. Farquharson, Principal Adviser,...
EPEC's perception of market developments - E. Farquharson, Principal Adviser,...
OECD Governance28 visualizações
Geographical scope of the lines in Design and Build - B.Dupuis, Executive Dir... por OECD Governance
Geographical scope of the lines in Design and Build - B.Dupuis, Executive Dir...Geographical scope of the lines in Design and Build - B.Dupuis, Executive Dir...
Geographical scope of the lines in Design and Build - B.Dupuis, Executive Dir...
OECD Governance26 visualizações
New Jersey Wind Port - J. Kennedy, New Jersey Economic Development Authority ... por OECD Governance
New Jersey Wind Port - J. Kennedy, New Jersey Economic Development Authority ...New Jersey Wind Port - J. Kennedy, New Jersey Economic Development Authority ...
New Jersey Wind Port - J. Kennedy, New Jersey Economic Development Authority ...
OECD Governance23 visualizações
Executive Agency of the Dutch Ministry of Infrastructure and Water Management... por OECD Governance
Executive Agency of the Dutch Ministry of Infrastructure and Water Management...Executive Agency of the Dutch Ministry of Infrastructure and Water Management...
Executive Agency of the Dutch Ministry of Infrastructure and Water Management...
OECD Governance28 visualizações
Presentation of OECD Government at a Glance 2023 por OECD Governance
Presentation of OECD Government at a Glance 2023Presentation of OECD Government at a Glance 2023
Presentation of OECD Government at a Glance 2023
OECD Governance325 visualizações
The Protection and Promotion of Civic Space: Strengthening Alignment with Int... por OECD Governance
The Protection and Promotion of Civic Space: Strengthening Alignment with Int...The Protection and Promotion of Civic Space: Strengthening Alignment with Int...
The Protection and Promotion of Civic Space: Strengthening Alignment with Int...
OECD Governance3K visualizações
Digital Government Review Türkiye - Assessment and Recommendations por OECD Governance
Digital Government Review Türkiye - Assessment and RecommendationsDigital Government Review Türkiye - Assessment and Recommendations
Digital Government Review Türkiye - Assessment and Recommendations
OECD Governance2.5K visualizações
Buliding-Financial-Resilience-to climate-Impacts.pdf por OECD Governance
Buliding-Financial-Resilience-to climate-Impacts.pdfBuliding-Financial-Resilience-to climate-Impacts.pdf
Buliding-Financial-Resilience-to climate-Impacts.pdf
OECD Governance45 visualizações
Session-7-OECD-Strengthening-climate.pptx por OECD Governance
Session-7-OECD-Strengthening-climate.pptxSession-7-OECD-Strengthening-climate.pptx
Session-7-OECD-Strengthening-climate.pptx
OECD Governance8 visualizações
Session-6-Building-Financial-Resilience.pptx por OECD Governance
Session-6-Building-Financial-Resilience.pptxSession-6-Building-Financial-Resilience.pptx
Session-6-Building-Financial-Resilience.pptx
OECD Governance59 visualizações
Session-5-Assurance-on-sustainability-Peter-Welch.pptx por OECD Governance
Session-5-Assurance-on-sustainability-Peter-Welch.pptxSession-5-Assurance-on-sustainability-Peter-Welch.pptx
Session-5-Assurance-on-sustainability-Peter-Welch.pptx
OECD Governance17 visualizações
Session-4-Sovereign-green-bonds-Fatos-Koc.pptx por OECD Governance
Session-4-Sovereign-green-bonds-Fatos-Koc.pptxSession-4-Sovereign-green-bonds-Fatos-Koc.pptx
Session-4-Sovereign-green-bonds-Fatos-Koc.pptx
OECD Governance103 visualizações

Último

Arrow Adoption Training for Kinship Families por
Arrow Adoption Training for Kinship FamiliesArrow Adoption Training for Kinship Families
Arrow Adoption Training for Kinship FamiliesArrowMarketing
41 visualizações46 slides
November-2023 PPT roadsafetysuperoheros full slides.ppt por
November-2023 PPT roadsafetysuperoheros full slides.pptNovember-2023 PPT roadsafetysuperoheros full slides.ppt
November-2023 PPT roadsafetysuperoheros full slides.pptINDIAN YOUTH SECURED ORGANISATION
6 visualizações30 slides
Research - Asrayan Project of BD por
Research  - Asrayan Project of BDResearch  - Asrayan Project of BD
Research - Asrayan Project of BDMd. Masudur Rahman, PMP
11 visualizações25 slides
Functioning of Single Village Drinking Water Supply Schemes in Rural Odisha_G... por
Functioning of Single Village Drinking Water Supply Schemes in Rural Odisha_G...Functioning of Single Village Drinking Water Supply Schemes in Rural Odisha_G...
Functioning of Single Village Drinking Water Supply Schemes in Rural Odisha_G...India Water Portal
6 visualizações28 slides
Dr Jean Paul Latyr FAYE - 2023 ReSAKSS Conference.pptx por
Dr Jean Paul Latyr FAYE - 2023 ReSAKSS Conference.pptxDr Jean Paul Latyr FAYE - 2023 ReSAKSS Conference.pptx
Dr Jean Paul Latyr FAYE - 2023 ReSAKSS Conference.pptxAKADEMIYA2063
9 visualizações24 slides
ΕΚΘΕΣΗ ΚΟΜΙΣΙΟΝ ΓΙΑ ΤΟΥΡΚΙΑ por
ΕΚΘΕΣΗ ΚΟΜΙΣΙΟΝ ΓΙΑ ΤΟΥΡΚΙΑΕΚΘΕΣΗ ΚΟΜΙΣΙΟΝ ΓΙΑ ΤΟΥΡΚΙΑ
ΕΚΘΕΣΗ ΚΟΜΙΣΙΟΝ ΓΙΑ ΤΟΥΡΚΙΑssuser9e6212
172 visualizações18 slides

Último(20)

Arrow Adoption Training for Kinship Families por ArrowMarketing
Arrow Adoption Training for Kinship FamiliesArrow Adoption Training for Kinship Families
Arrow Adoption Training for Kinship Families
ArrowMarketing41 visualizações
Functioning of Single Village Drinking Water Supply Schemes in Rural Odisha_G... por India Water Portal
Functioning of Single Village Drinking Water Supply Schemes in Rural Odisha_G...Functioning of Single Village Drinking Water Supply Schemes in Rural Odisha_G...
Functioning of Single Village Drinking Water Supply Schemes in Rural Odisha_G...
India Water Portal6 visualizações
Dr Jean Paul Latyr FAYE - 2023 ReSAKSS Conference.pptx por AKADEMIYA2063
Dr Jean Paul Latyr FAYE - 2023 ReSAKSS Conference.pptxDr Jean Paul Latyr FAYE - 2023 ReSAKSS Conference.pptx
Dr Jean Paul Latyr FAYE - 2023 ReSAKSS Conference.pptx
AKADEMIYA20639 visualizações
ΕΚΘΕΣΗ ΚΟΜΙΣΙΟΝ ΓΙΑ ΤΟΥΡΚΙΑ por ssuser9e6212
ΕΚΘΕΣΗ ΚΟΜΙΣΙΟΝ ΓΙΑ ΤΟΥΡΚΙΑΕΚΘΕΣΗ ΚΟΜΙΣΙΟΝ ΓΙΑ ΤΟΥΡΚΙΑ
ΕΚΘΕΣΗ ΚΟΜΙΣΙΟΝ ΓΙΑ ΤΟΥΡΚΙΑ
ssuser9e6212172 visualizações
Taking care of the elders por SERUDS INDIA
Taking care of the eldersTaking care of the elders
Taking care of the elders
SERUDS INDIA9 visualizações
Dr Getaw Tadesse - 2023 ReSAKSS Conference .pptx por AKADEMIYA2063
Dr Getaw Tadesse - 2023 ReSAKSS Conference .pptxDr Getaw Tadesse - 2023 ReSAKSS Conference .pptx
Dr Getaw Tadesse - 2023 ReSAKSS Conference .pptx
AKADEMIYA206313 visualizações
AABS project overview por WorldFish
AABS project overviewAABS project overview
AABS project overview
WorldFish26 visualizações
ecb.sp231121_1~8df317dc17.en.pdf por Société Tripalio
ecb.sp231121_1~8df317dc17.en.pdfecb.sp231121_1~8df317dc17.en.pdf
ecb.sp231121_1~8df317dc17.en.pdf
Société Tripalio415 visualizações
COP28 President Launches Global Decarbonization Accelerator por Energy for One World
COP28 President Launches Global Decarbonization AcceleratorCOP28 President Launches Global Decarbonization Accelerator
COP28 President Launches Global Decarbonization Accelerator
Energy for One World30 visualizações
Financial sustainability of schemes managed by PHED in Punjab_Krishnakumar Th... por India Water Portal
Financial sustainability of schemes managed by PHED in Punjab_Krishnakumar Th...Financial sustainability of schemes managed by PHED in Punjab_Krishnakumar Th...
Financial sustainability of schemes managed by PHED in Punjab_Krishnakumar Th...
India Water Portal5 visualizações
Dr. Ousmane Badiane - 2023 ReSAKSS Conference.pptx por AKADEMIYA2063
Dr. Ousmane Badiane - 2023 ReSAKSS Conference.pptxDr. Ousmane Badiane - 2023 ReSAKSS Conference.pptx
Dr. Ousmane Badiane - 2023 ReSAKSS Conference.pptx
AKADEMIYA206328 visualizações
Support Girl students with Education por SERUDS INDIA
Support Girl students with EducationSupport Girl students with Education
Support Girl students with Education
SERUDS INDIA6 visualizações
Case study of Gokarna Multi-village scheme, Kumta, Karnataka_IIM-B_2023.pdf por India Water Portal
Case study of Gokarna Multi-village scheme, Kumta, Karnataka_IIM-B_2023.pdfCase study of Gokarna Multi-village scheme, Kumta, Karnataka_IIM-B_2023.pdf
Case study of Gokarna Multi-village scheme, Kumta, Karnataka_IIM-B_2023.pdf
India Water Portal7 visualizações
Dr. Fatima Kareem - 2023 ReSAKSS Conference.pptx por AKADEMIYA2063
Dr. Fatima Kareem - 2023 ReSAKSS Conference.pptxDr. Fatima Kareem - 2023 ReSAKSS Conference.pptx
Dr. Fatima Kareem - 2023 ReSAKSS Conference.pptx
AKADEMIYA20635 visualizações
Taking care for elders por SERUDS INDIA
Taking care for eldersTaking care for elders
Taking care for elders
SERUDS INDIA15 visualizações

Procurement strategy in major infrastructure: The AS-IS and STEPS - D. Makovšek, OECD Public Governance Directorate

  • 1. PROCUREMENT STRATEGY IN MAJOR INFRASTRUCTURE: The AS-IS and STEPS 17th May 2023 Dejan Makovšek, PhD Infrastructure and Public Procurement Division Public Governance Directorate With an expert opinion by Andrea Chao LLM Partner & Lawyer at Bird & Bird LLP (Amsterdam)
  • 2. How procurement strategy choices matter for project outcomes 2
  • 3. Blanc-Brude & Makovsek (2013): • Analysed a bank’s database of project finance deals – 75 mega projects. • Observed median construction risk is zero, average is 2%. 54/75 projects were exactly on budget. 0 10 20 30 40 50 60 70 -55 -50 -45 -40 -35 -30 -25 -20 -15 -10 -5 0 5 10 15 20 25 30 35 40 45 50 Observations Observed cost overruns Example I: On-budget performance for major EPC (lump-sum) infra contracts
  • 4. 4 Bolotny & Wasserman (2022): • 44o small bridge projects empirically analyzed in a structural mathematical model. • The result (42% price hike) is the net outcome conceals two effects: – I) bidders include an increased contingency [the effect increases cost]; – II) less efficient bidders get excluded Example II: From DBB to lump sum contracts in small projects DBB (schedule of rates) DBB (Lump-sum) Total cost Cost overrun Cost at contract signature +42%
  • 5. A few contemplations: 5 Relevant should not be the price mentioned in the contract, but the price eventually paid: • A price that is too low may help getting the project kickstarted internally • But such price also creates a fundamental flaw in a project: lack of profit that needs to be recouped – through whichever means necessary
  • 6. A few contemplations: 6 When looking at the price eventually paid, also look at: • Internal costs/shift in focus • Legal costs • Social costs (incl. people leaving the sector) … And your social obligations
  • 7. A few contemplations: 7 What happens when allocating high level of risk at the market side, esp. combined with award criteria focussed on lowest price? • Bid price increases to deal with this risk allocation • Considered too risky: no bid • Hoping for the best: going in eyes closed What scenario would you prefer?
  • 8. How do countries make choices about the procurement strategy? 8
  • 9. Context - The last thirty years… • Lean public sector policy lead to reduced capabilities (e.g. elimination of inhouse design department at RWS in NL) • Reduced capabilities => inability to manage interfaces between contracts. • Large projects => large contracts • Large contracts + total risk transfer => low/no competition. 9 Policymaker’s narrative: • Complex project suffer cost overruns – transfer more risk • DB/EPC contracts transfer too much risk • De-risking needed to keep procuring big contracts
  • 10. Delivery model assignment for public works projects and programmes – the global best practice 10 Frame the challenge What are my objectives What is the strategy of my org Identify … potential delivery models Control offered? Innovation potential? Do I have capability to manage? Will the market accept? Who is best placed to manage risk? Decide packaging Into how many contracts should my project be split Engage the market Will the market accept our procurement strategy Iterate if not digestible
  • 11. The problems of the existing “state-of-the-art” • A top-down approach in which defining the objectives/constraints directly identifies the best delivery model. A self-contained process, which requires no external evidence. • The client’s capabilities are taken as a given and not informed by the nature of the project. • The packaging decision is made after the delivery model has been selected => one- size-fits-all risk allocation. Again ignoring the nature of the project. • The entire sequence of analysis/decision-making process is not grounded in any empirically tested theory. 11
  • 12. A few contemplations: 12 Money talks … but: - choices have consequences - all tasks need to be done by someone, and nothing comes for free
  • 14. The approach the OECD is piloting STEPS - Support Tool for Effective Procurement Strategy® 14
  • 15. The value proposition of STEPS • Based on scientific insights (being “evidence-based” is not sufficient), i.e. does not legitimize preconceived ideas • Identifies the right unit of analysis/granularity • Helps inform structure/capabilities of the client org • Leads to less costly infra, without loss in innovation or increase in conflict, compared to existing approaches 15
  • 16. Breaking down a project into STEPS activities • STEPS activity = – economic activity (not detailed technical task) – technologically bounded (skillsets) – highest level of firm specialization 16 A B E R Market (suppliers for activity a, b, …) A A A A A B B B B B B … E E R R 1 2 3 4 5 6 … … …
  • 17. Example: Commercial implications of contract packaging? 17 An activity with many suppliers An activity with one (few) suppliers Bidder consortium 1 Bidder consortium 2
  • 18. Commercial implications of bargaining power shift (hold-up)? 18 An activity with no hold-up An activity with hold-up
  • 19. Why do we assume that major projects are homogenous in terms of risk and uncertainty? 19
  • 20. Procurement strategy solution for project X 20 DBB with schedule of rates A collaborative delivery model DB contract Persistent post-contract uncertainties causing hold-up risk Competition failure risk Hold-up risk
  • 21. Procurement failures 21 Contract signature Pre-contract failures • Competition failure (Too few bidders) • Hold-up • Inadequate risk allocation (e.g. one size fits all commercial arrangement) Post-contract failures
  • 22. A few contemplations: 22 Hold up - during the tender (or even before) - Level of competition available? - Further limiting competition by: - Work packages – too large - Tender requirements – too many, too harsh - Risk allocation – too harsh
  • 23. A few contemplations: 23 Hold up after the tender - A construction project is a moving train - Stopping takes a long time - Getting of while moving is dangerous - Restarting takes a long time - Once the project has started, there is a shift in balance
  • 24. A few contemplations: 24 Risk of hold up for future projects is influenced by decisions made on a current project - Promoting new market parties to arise? - Sticking to the usual suspects? - One project approach, or framework approach? What are your tender requirements driving?
  • 25. 25 The end result of a complete procurement strategy Bidder selection Incentive power (competition vs collaboration) (scientific& enshrined in legislation) (scientific) Steps in a procurement strategy How a decision is made Contract scoping (scientific) (scientific) Make-or-buy The delivery model
  • 26. Delivery entity (capabilities organisation, leadership, …) Iteration of solutions Repository of post contract procurement failures from all projects (the red dots) Market structure - capabilities data (the red dots) Towards a holistic risk management framework as well as STEPS Digitalisation Using AI to predict procurement failures… Category managers checking supply chain STEPS (the commercial implications) Standard Initial detailed risk analysis (the tech. reasons) Execution of procurement strategy Other risk dimensions (OECD/UCL/MBS) Affecting risk and therefore management strategy 26 Planning/ appraisal and value distribution
  • 27. THANK YOU DEJAN.MAKOVSEK@OECD.ORG & GUEST COMMENTATOR ANDREA.CHAO@TWOBIRDS.COM 27
  • 28. Where does procurement strategy fit when compared to standard project risk management? 28 Risk identification …technical failures, third party interfaces, permit issues… Risk mitigation …build contingency for technical failure, get permit… Commercial/contracting implications …opportunism of suppliers in contracts, changes in their bargaining power… STEPS
  • 29. Steps and main cognitive lenses behind the STEPS (Support Tool for Effective Procurement Strategies) 29 Theory applied to issue/decision in step in Tool Theory Leading scholar examples Step 1. Project activity break-down Division of Labour/ Specialisation Adam Smith Transaction Costs Economics Oliver Williamson (Nobel Prize 2009) Step 2. Project Specific-or-Network Analysis Economics of Scale Adam Smith Step 3. Activity analysis Uses theories listed under steps 4-6 to inform the economic characteristics of activities, making the analysis in those steps possible Step 4. What Capabilities do I need in-house (Make-or-Buy Analysis) Transaction Costs Economics Oliver Williamson (Nobel Prize 2009) Transaction Costs Economics Ronald Coase (Nobel Prize 1991) Resource-Based Theory (competence and capabilities) Jay Barney Step 5. Into how many contracts should I package (Activity bundling analysis) Economies of Scope John Panzar and Robert Willig Transaction Costs Economics Oliver Williamson (Nobel Prize 2009) Resource-Based Theory (competence and capabilities) Jay Barney Step 6. Competition or collaboration? What payment mechanism? (Exchange Relationship Analysis) Transaction Costs Economics Oliver Williamson (Nobel Prize 2009) Principal-Agent Theory (contract theory) Oliver Hart & Bengt Holmström (Nobel Prize 2016), Michael C. Jensen & William Meckling Resource-Based Theory (competence and capabilities) Jay Barney
  • 30. Example III: Similar result in major contracts (EIB Motorways) 30 • Construction risk: risk premium in 57 DB/EPC (in a PPP) road contracts ~20% above ex-post risk in 101 DBB contracts (LCC does not explain diff.); based on Blanc-Brude et al 2009. DBB Public-Private Partnership (DB/OM) Total cost Cost overrun Cost at contract signature 24% Source: Makovšek & Moszoro 2018.
  • 31. What the existing approach boils down to… • The procurement strategy is a methodology to legitimise preconceived ideas about project objectives. • It is not a method that would inform trade-offs, possibly leading to an adjustment of the project objectives or the approach how to achieve them. • The result can be a bias towards larger contracts, one-size- fits-all risk allocation ... and much more expensive infra. 31 Take this slide out and just deliver orally? – Question Bjorn can ask