Presented at the OECD expert meeting "Construction Risk Management in Infrastructure Procurement: The Loss of Appetite for Fixed-Price Contracts", held on 17 May 2023 at the OECD, Paris and online.
New Jersey Wind Port - J. Kennedy, New Jersey Economic Development Authority (US)
1. NEW JERSEY IS DEVELOPING THE NATION’S 1st PURPOSE-BUILT OFFSHORE WIND “HUB”
➢ Located in Salem County
(Southern NJ)
➢ Purpose-built for OSW
➢ >220-acres at full scale –
enabling “co-location” of
marshalling and manufacturing
➢ State funded and delivered
➢ >1,500 ongoing jobs
➢ $500M increase to NJ’s GDP
Further information is available at the NJ Wind Port website:
https://www.nj.gov/windport/
Visual illustration
2. MANUFACTURING
25 acres
Permits lodged.
<30% design completion
MANUFACTURING
65 acres
Permits lodged.
<30% design completion
MANUFACTURING
25-30 acres
Permits lodged.
<30% design completion
MARSHALLING
30-35 acres
Permitted.
In construction
CDF/DREDGE PLACEMENT
35 acres
Permits lodged.
<30% design completion
PORT ADMIN
<5 acres
Permits lodged.
<30% design
completion
(2023 – 2027/28)
(2021– 2025)
MARSHALLING
30-35 acres
Permits lodged.
<30% design completion
DEVELOPMENT IS BEING PHASED OVER 7 YEARS