NYSE-MKT, TSX: NG | April 2015
2015 First Quarter & Project Update
Conference Call Attendees
2
▶ Introduction
Mélanie Hennessy (Vice President Corporate Communications)
▶ Corporate Update
Greg Lang (President & Chief Executive Officer)
▶ First Quarter Financials & 2015 Budget
David Ottewell (Vice President & Chief Financial Officer)
▶ Closing Remarks
Greg Lang (President & Chief Executive Officer)
▶ Question & Answer Session
Greg Lang & David Ottewell
Cautionary Statements
REGARDING FORWARD-LOOKING STATEMENTS
This presentation includes certain “forward-looking statements” within the meaning of applicable securities laws, including the United States Private Securities Litigation Reform Act of 1995. All
statements, other than statements of historical fact, included herein including, without limitation, statements relating to Donlin Gold’s future operating or financial performance, are forward-
looking statements. Forward-looking statements are frequently, but not always, identified by words such as “plans”, “expects”, “anticipates”, “believes”, “intends”, “estimates”, “potential”,
“possible” and similar expressions, or statements that events, conditions or results “will”, “may”, “could”, or “should” occur or be achieved. These forward-looking statements are set forth in the
slides pertaining to the implementation of the Donlin Gold second updated Feasibility Study and pertaining to the implementation of the Galore Creek Pre-Feasibility Study, the factors that may
influence future gold price performance, and the potential future value of gold, and may include statements regarding perceived merit of properties; exploration results and budgets; mineral
reserves and resource estimates; work programs; capital expenditures; timelines; strategic plans; completion of transactions; market price of precious or base metals; or other statements that
are not statements of fact. Forward-looking statements involve various risks and uncertainties. There can be no assurance that such statements will prove to be accurate, and actual results and
future events could differ materially from those anticipated in such statements. Important factors that could cause actual results to differ materially from our expectations include the
uncertainties involving the need for additional financing to explore and develop properties and availability of financing in the debt and capital markets; uncertainties involved in the interpretation
of drilling results and geological tests and the estimation of reserves and resources; the need for continued cooperation between NOVAGOLD and Barrick Gold in the exploration and
development of the Donlin Gold property; the need for continued cooperation between NOVAGOLD and Teck Resources Ltd. in the exploration and development of the Galore Creek property;
the need for cooperation of government agencies and native groups in the development and operation of properties; the need to obtain permits and governmental approvals; risks of
construction and mining projects such as accidents, equipment breakdowns, bad weather, non-compliance with environmental and permit requirements, unanticipated variation in geological
structures, ore grades or recovery rates; unexpected cost increases; fluctuations in metal prices and currency exchange rates; and other risks and uncertainties disclosed in reports and
documents filed by NOVAGOLD with applicable securities regulatory authorities from time to time. The forward-looking statements made herein reflect our beliefs, opinions and projections on
the date the statements are made. Except as required by law, we assume no obligation to update the forward-looking statements of beliefs, opinions, projections, or other factors, should they
change.
REGARDING SCIENTIFIC AND TECHNICAL INFORMATION
Unless otherwise indicated, all reserve and resource estimates included in this presentation have been prepared in accordance with Canadian National Instrument 43-101 Standards of
Disclosure for Mineral Projects (“NI 43-101”) and the Canadian Institute of Mining, Metallurgy and Petroleum Definition Standards for Mineral Resources and Mineral Reserves (“CIM Definition
Standards”). Canadian standards, including NI 43-101, differ significantly from the requirements of the United States Securities and Exchange Commission (“SEC”), and reserve and resource
information in this presentation may not be comparable to similar information disclosed by U.S. companies. In particular, and without limiting the generality of the foregoing, the term “resource”
does not equate to the term “‘reserves”. Under U.S. standards, mineralization may not be classified as a “reserve” unless the determination has been made that the mineralization could be
economically and legally produced or extracted at the time the reserve determination is made. At this time, both of Donlin Gold and Galore Creek projects are without known reserves, as
defined under SEC Industry Guide 7. The SEC’s disclosure standards normally do not permit the inclusion of information concerning “measured mineral resources”, “indicated mineral
resources” or “inferred mineral resources” or other descriptions of the amount of mineralization in mineral deposits that do not constitute “reserves” by U.S. standards in documents filed with the
SEC. U.S. investors should also understand that “inferred mineral resources” have a great amount of uncertainty as to their existence and great uncertainty as to their economic and legal
feasibility. It cannot be assumed that all or any part of an “inferred mineral resource” will ever be upgraded to a higher category. Under Canadian rules, estimated “inferred mineral resources”
may not form the basis of feasibility or pre-feasibility studies except in rare cases. Investors are cautioned not to assume that all or any part of an “inferred mineral resource” exists or is
economically or legally mineable. Disclosure of “contained ounces” in a resource is permitted disclosure under Canadian regulations; however, the SEC normally only permits issuers to report
mineralization that does not constitute “reserves” by SEC standards as in-place tonnage and grade without reference to unit measures. The requirements of NI 43-101 for identification of
“reserves” are also not the same as those of the SEC, and reserves reported in compliance with NI 43-101 may not qualify as “reserves” under SEC standards. Accordingly, information
concerning mineral deposits set forth herein may not be comparable to information made public by companies that report in accordance with United States standards.
All dollar amounts quoted in this report are in U.S. currency unless otherwise noted.
3
What Makes NOVAGOLD Unique?
Poised to become one of the
largest gold producers in the
world
DONLIN GOLD
GALORE CREEK
Expected to be the largest and
lowest cost copper mine in
Canada
50/50 with Barrick
50/50 with Teck
A DEVELOPMENT-STAGE COMPANY WITH TWO PROJECTS OF EXCEPTIONAL SCALE,
QUALITY, AND JURISDICTIONAL SAFETY
4
EXCELLENT PROGRESS MADE ON ALL FRONTS WHILE SAFEGUARDING OUR BALANCE SHEET
First Quarter Activities
5
ACHIEVEMENTS
▶ Excellent progress in permitting of Donlin Gold
• Submission of comments on initial draft EIS from six
cooperating agencies to the Corps, the lead agency
• Anticipate publishing the draft EIS by year-end 2015
▶ Advanced Galore Creek technical studies
• Focused on project mine planning and design to further
improve its value and marketability
▶ Released the opening segment of the Alaska Video Series –
Yup’ik Language and Culture
• Four-part video series on the way of life in Alaska
• Documenting the way of life in the remote communities of the
Y-K region, where the Donlin Gold project is located, and the
importance of subsistence living and traditional lifestyles
▶ Sponsored, volunteered and participated in local community
activities in Northern British Columbia and Alaska
• Iditarod Trail International Sled Dog Race
• Tahltan educational and healthy living initiatives
Q1-2015 Project Activity
▶ Donlin Gold
o Activities focused on the draft EIS and other major permit applications with state and
federal permitting agencies
o Joint optimization studies with Barrick ($1.5 million, NG 50% share)
o Continued community engagement and development initiatives
o Project funding (NG 50% share)
• Q1-2015: $2.4 million
• FY-2015: $12.6 million
▶ Galore Creek
o Technical studies with Teck, focusing on optimizing mine planning and project design
o Project funding (NG 50% share)
• Q1-2015: $0.1 million
• FY-2015: $1.6 million
6
Q1-2015 Operating Performance Analysis
Q1 Highlights
(US$ millions)
2015 2014
General and administrative expenses(1) $8.5 $7.7
Projects:
Donlin Gold 2.5 2.9
Galore Creek 0.1 0.7
Donlin Gold studies 0.2 --
Operating loss 11.3 11.3
Other income (expense) 2.0 0.6
Net loss $9.3 $10.7
(1) Includes share-based compensation expense of $5.3 and $4.7 million in 2015 and 2014, respectively. 7
Q1-2015 Cash Flow Highlights
(US$ millions) First Quarter Full Year Budget
Cash used in operating activities(1) $ (5.6) $ (14.8)
Project funding:
Donlin Gold (2.4) (12.6)
Galore Creek (0.1) (1.6)
Repayment of convertible notes -- (15.8)
Foreign exchange effect on cash (0.2) --
Decrease in cash and term deposits (8.3) (44.8)
Cash and term deposits
Beginning 165.3 164.8
Ending $157.0 $120.5
8(1) Includes $0.2 million and $1.5 million for the first quarter and full year budget, respectively, for joint Donlin studies with Barrick.
Notes:
1) Shown on 100% project basis, of which NOVAGOLD holds a 50% interest
2) Measured and indicated resources inclusive of proven and probable reserves.
See “Cautionary Note Concerning Reserve & Resource Estimates” and “Reserve & Resource
Base” with footnotes in the appendix.
RESERVES1
34Moz Proven & Probable
Grade: 2.09 g/t
RESOURCES1,2
39Moz Measured & Indicated
Grade: 2.24 g/t
6Moz Inferred
Grade: 2.02 g/t
(inclusive of P&P reserves)
AMONG THE WORLD’S MOST SIGNIFICANT AND HIGHEST-GRADE GOLD DEPOSITS
9
Donlin Gold: A Large High-Grade Gold Project
A REMARKABLE RESOURCE AMONG EMERGING OPEN-PIT GOLD DEPOSITS
Donlin Gold: The Emerging Top-Tier Producer in the Safest
Jurisdiction
0.00
0.20
0.40
0.60
0.80
1.00
1.20
1.40
1.60
Donlin Gold Metates Pascua
Lama
Livengood Blackwater Courageous
Lake
Mt. Todd Merian Morelos Stibnite Rainy River Cerro
Maricunga
Dublin
Gulch
Haile
1.102
0.66 0.64 0.58
0.41 0.39 0.37 0.35 0.34 0.34 0.23 0.23 0.21 0.13
1.501
ProjectedAnnualGoldProduction
(millionsofounces)
Notes:
• Peer group data as per latest company documents, public filings and websites. Comparison group based on large (M&I+P&P 4Moz cut off), North/South American and Oceanian gold-focused development projects where the
majority of the M&I resource is open-pit.
• Donlin Gold data as per the second updated feasibility study effective November 18, 2011, as amended January 20, 2012. Represents 100% of measured and indicated resources of which NOVAGOLD’s share represents
50%. Measured and indicated resources inclusive of proven and probable reserves. See “Cautionary Note Concerning Reserve & Resource Estimates” and “Reserve & Resource Base” with footnotes in the appendix.
(1) Projected annual gold production during first five full years of mine life; (2) Projected annual gold production during full life of mine.
0.0
5.0
10.0
15.0
20.0
25.0
30.0
35.0
40.0
Donlin Gold Pascua
Lama
Metates Livengood Blackwater Courageous
Lake
Mt. Todd Rainy River Stibnite Merian Cerro
Maricunga
Morelos Dublin Gulch Haile
39.0
21.8
19.0
15.7
9.2
8.0 7.8 6.4 5.5 5.5 5.2 5.0 4.9 4.0
M&IGoldResource
(millionsofounces)
▶ Donlin Gold’s size and production profile clearly
distinguish it from its peers
10
0.00
0.50
1.00
1.50
2.00
2.50
3.00
Morelos Courageous
Lake
Donlin Gold Haile Stibnite Pascua
Lama
Rainy River Merian Mt. Todd Blackwater Dublin Gulch Livengood Metates Cerro
Maricunga
2.79 2.31 2.24
1.77
1.63
1.41
1.14 1.13
0.81 0.74 0.68 0.61 0.50 0.38
▸ Grade compares well among peer group of emerging open-pit
gold deposits
M&IGoldGrade(g/t)
Notes:
• Development-stage peer group data as per latest company documents, public filings and websites. Comparison group based on large (M&I+P&P 4Moz cut off), North/South American and Oceanian gold-focused development
projects where the majority of the M&I resource is open-pit Top gold producers group data based on 2014 year-end reserve and resource grades (combined proven & probable reserves and measured & indicated resources)
for open-pit and underground material as per public filings.
1. 2014 average grade per tonne is not yet available for Gold Fields, AngloGold Ashanti and Polyus. Current figures represent reported 2013 year-end reserve and resource grades.
• Donlin Gold data as per the second updated feasibility study effective November 18, 2011, as amended January 20, 2012. Represents 100% of measured and indicated resources of which NOVAGOLD’s share represents
50%. Measured and indicated resources inclusive of proven and probable reserves. See “Cautionary Note Concerning Reserve & Resource Estimates” and “Reserve & Resource Base” with footnotes in the appendix.
0.00
0.50
1.00
1.50
2.00
2.50
Donlin Gold Gold Fields Polyus Agnico Eagle AngloGold
Ashanti
Barrick Goldcorp Newmont Yamana Kinross Newcrest
2.24 2.24
2.14 1.89 1.81
1.46
0.89 0.87 0.85
0.72 0.63
M&IGoldGrade(g/t)
DONLIN GOLD’S HIGH GRADE ENDOWMENT PROVIDES RESILIENCE TO GOLD PRICE CYCLES
Donlin Gold: Among the Highest-Quality Open-Pit
Development-Stage Gold Deposit
11
111
▸ Donlin Gold’s grade is one of the highest when compared to
the world’s biggest producers
MULTIPLE DRILL PROSPECTS AND TARGETS EXIST ALONG 8KM TREND
Donlin Gold: Excellent Exploration Potential
12
The next big gold discovery?
▶ Potential to expand current open-pit
resources along strike and at depth
▶ Good prospects to discover meaningful
deposits outside current mine footprint
• Reserves and resources are
contained within just 3 km of an 8 km
long trend
▶ Inferred mineral resource: 6 Moz of gold
mainly inside the reserve pit
• Upside potential to project economics
▶ In-pit area covers 1,600 acres (~2%) of
the 80,000 acres comprising the entire
land package
0
5,000
10,000
15,000
20,000
25,000
30,000
1,200 1,300 1,500 1,700 2,000 2,500
6.2B
8.2B
11.6B
14.6B
19.2B
27.0B
NPV(US$inmillions)
Gold Price (US$)
NPV INCREASES ~20X WITH ~2X INCREASE IN GOLD PRICE
Donlin Gold: Significant Value Upside with Higher Gold
Prices
13
Notes:
Donlin Gold estimates as per the second updated feasibility study effective November 18, 2011, as amended January 20, 2012 . All dollar figures are in USD and reflect after-tax net present value (at a 0% and 5% discount
rates) of the Donlin Gold project as of 1/1/2014. At a 5% discount rate, the net present value is: $547 m @ $1,200 gold; $1,465m @ $1,300 gold; $3,147m @ $1,500 gold; $4,581 m @ $1,700 gold; $6,722 m @ $2,000 gold;
and $10,243 m @ $2,500 gold. Project development costs prior to 1/1/2014 are treated as sunk costs.
27year
mine life
NPV at 0%NPV at 5%
▶ Project has a positive
return that increases
substantially with higher
gold prices
▶ Good payback at a
broad range of gold prices
▶ Significant exploration
upside on the mineralized
trend
▶ Long mine life offers high
likelihood of enjoying one
or more cyclical bull
markets over the period of
the mine’s operation
JURISDICTIONAL APPEAL IS COMPRISED OF FIVE CORNERSTONES:
1) MINERAL POTENTIAL
2) ESTABLISHED MINING PRACTICE
3) POLITICAL AND SOCIAL STABILITY
4) EXCELLENT LOCAL PARTNERSHIPS AND, OF “EXISTENTIAL IMPORTANCE”...
5) A FULL EMBRACE OF THE RULE OF LAW
Donlin Gold: Leverage in a Place WhereYou Can Keep the
Rewards – Location, Location, Location
14
Political Risk
Insignificant
Low
Medium
High
Extreme
Source: SNL Metals & Mining, Political Risk Assessment, March 16, 2015
Donlin Gold: Consistently Advancing the Project
0
10
20
30
40
50
60
2008 2009 2010 2011 2012 2013 2014 2015F
53
21
42
45
37
24
28
25
CO-OWNERS COMMITTED TO MOVING DONLIN GOLD THROUGH PERMITTING TO A
CONSTRUCTION DECISION AT A MEASURED PACE
15
ProjectFundingon100%basis(US$Millions)
Notes:
The data presented above is as per NOVAGOLD’s public disclosures. The Donlin Gold LLC, formed in December 2007, is owned 50/50 by Barrick Gold Corporation and NOVAGOLD. NOVAGOLD
contributed 50% of project funding shown above.
Filed Donlin
Gold FS adding
14.7Moz
Optimization
studies
completed,
reserves up
by 4.3Moz
Updated FS,
resources
increased
135% from
2006
FS approved,
permitting
commenced
Initial draft EIS
completed Anticipate
publishing
draft EIS
Donlin Gold
FS completed
Public
scoping
completed
Barrick Gold Fourth Quarter 2014 Results – Highlights
“The 50% owned Donlin Gold project located in Alaska is one of the largest
undeveloped gold deposits in the world. In terms of size, grade, and jurisdictional
safety, Donlin Gold is an excellent asset in Barrick's portfolio with significant
leverage to the price of gold...
In addition to its already large mineral endowment, the project also has exploration
potential which could expand the current open pit resource....
Donlin Gold has substantial leverage to gold prices and has the potential to add
significant value to Barrick and its future growth pipeline in a higher gold price
environment...”
Donlin Gold: Perfect Alignment between Partners
16
Notes:
As per Barrick Gold’s Fourth Quarter and Full Year 2014 Results disclosed on February 18, 2015.
Emphasis added by NOVAGOLD
Barrick’s full Donlin Gold disclosure on slide 23 of the appendix
COLLABORATING WITH OUR PARTNER TO MAXIMIZE PROJECT RETURN
Donlin Gold: Partnerships & Activities
Barrick and NOVAGOLD are jointly committed to working together to create
shareholder value from Donlin Gold’s unique optionality
▶ Project activities continue to progress as planned
▶ After further de-risking, we are encouraged by Donlin Gold’s prospects
▶ Focused on advancing Donlin Gold through permitting to a record of decision
▶ Working together with Barrick to evaluate development scenarios
▶ Neither partner has a build at any gold price mentality
“Both companies are happy to take a sober and constructive view. We don't
want to subsidize the world's consumption of gold by squandering the treasures
that Mother Nature has given us and we're happy to wait for the higher gold
prices that will make the project's economics sing.”
– Thomas S. Kaplan, Chairman of NOVAGOLD
RETAINING THE GREATEST VALUE WHILE ENSURING CAPITAL EFFICIENCY
17
Notice of Intent
to Prepare EIS Draft EIS
Final EIS
Record of Decision
Initial permit applications
Submitted: 08/12
Notice of intent
Issued: 12/14/12
Public scoping period
Ended: 03/29/13
Scoping summary document
Completed: 08/13
Development of alternatives
Completed: Q2/14
Initial drafts of EIS chapters
Completed: Q4/14
Agency & Donlin Gold review
Completed: Q4/14
Prepare draft EIS
Publish draft EIS
Public comment period
Prepare draft final EIS
Agency review
Publish final EIS
Record of decision
2012-2013 2013-2015 2015-2017
PAST THE HALFWAY MARK IN THE EIS PROCESS
Donlin Gold: Permitting Milestones
18
CONTINUE TO EXECUTE AND DELIVER ON OUR BUSINESS PLAN
2015 Outlook
1 2 3 4 5
PRIORITY PRIORITY PRIORITY PRIORITY PRIORITY
Advance
Donlin Gold
permitting
to a
construction
decision
Advance
Galore Creek
mine
planning
and project
design
Evaluate
opportunities
to monetize
the value of
Galore Creek
Safeguard
our cash
position
Maintain
strong
relationships
with all
stakeholders
COMMITTED TO GOLD THROUGH VARIOUS
MARKET CYCLES 19
NOVAGOLD
focused on execution and
delivery of our business plan
NOVAGOLD Highlights
Safe Geo-Political Environment:
Alaska and British Columbia,
top-rated mining jurisdictions
Accomplished Team:
185 years cumulative
experience
Prolific Production Profile:
Donlin Gold expected to be one of industry’s
top producing assets; strong leverage to gold
Supportive Stakeholders:
Long standing shareholders and
engaged partners
Strong Balance Sheet:
$157m cash + term deposits
as of February 28, 2015
Top Tier Assets:
Donlin Gold: Large, high-
grade deposit past 50%
mark in permitting; great
additional exploration
potential
20
Congratulations to the Yukon-Kuskokwim Mushers
21
novagold.com
Appendix
Barrick Gold Fourth Quarter 2014 Results – Full Donlin Gold Disclosure
“The 50% owned Donlin Gold project located in Alaska is one of the largest undeveloped gold deposits in the
world. In terms of size, grade, and jurisdictional safety, Donlin Gold is an excellent asset in Barrick's portfolio
with significant leverage to the price of gold. The Donlin Gold project has approximately 39 million ounces of
contained gold (100% basis) in the measured and indicated resource categories (approximately 8 million
tonnes grading 2.52 g/t (measured) and 533 million tonnes grading 2.24 g/t (indicated)). In addition to its
already large mineral endowment, the project also has exploration potential which could expand the current
open pit resource.
Under our disciplined capital allocation framework, we have continued to work with our partner, Novagold
Resources, to advance the Donlin Gold project. Current activities, by which we maintain and enhance the
option value of this project at a modest cost, are focused on permitting, community outreach and workforce
development. In 2014, Donlin Gold secured long-term surface use rights and significantly advanced the
permitting of the Donlin Gold project which is now about halfway complete.
Barrick is working closely with its partner on alternatives designed to minimize initial capital outlay. The
outcome of that effort may include engagement of third party operators and exploring possibilities for third
party financing of some capital intensive infrastructure. Collectively, we are also investing about $3 million
(100% basis) on technical studies to identify potential design and execution enhancements. Donlin Gold has
substantial leverage to gold prices and has the potential to add significant value to Barrick and its future
growth pipeline in a higher gold price environment. Any decision to proceed with development, either as
currently envisaged, or in an optimized scenario, will depend on the project meeting Barrick's minimum
hurdle rate which will depend in large part on the prevailing gold prices and market conditions.”
Donlin Gold: Perfect Alignment between Partners
23
Notes:
As per Barrick Gold’s Fourth Quarter and Full Year 2014 Results disclosed on February 18, 2015.
NOVAGOLD: Reserve/Resource Table
24
Donlin Gold (100% basis)* Tonnage Grade Metal content
GOLD Kt g/t Au Koz Au
Reserves1
Proven 7,683 2.32 573
Probable 497,128 2.08 33,276
P&P 504,811 2.09 33,849
Resources3, inclusive of Reserves
Measured 7,731 2.52 626
Indicated 533,607 2.24 38,380
M&I 541,337 2.24 39,007
Inferred 92,216 2.02 5,993
Galore Creek (100% basis)* Tonnage Grade Metal content
COPPER Mt % Cu Blb Cu
Reserves2
Proven 69.0 0.606 0.9
Probable 459.1 0.582 5.9
P&P 528.0 0.585 6.8
Resources4, exclusive of Reserves
Measured 39.5 0.25 0.22
Indicated 247.2 0.34 1.85
M&I 286.7 0.33 2.07
Inferred 346.6 0.42 3.23
GOLD Mt g/t Au Moz Au
Reserves2
Proven 69.0 0.520 1.15
Probable 459.1 0.291 4.30
P&P 528.0 0.321 5.45
Resources4, exclusive of Reserves
Measured 39.5 0.39 0.50
Indicated 247.2 0.26 2.04
M&I 286.7 0.27 2.53
Inferred 346.6 0.24 2.70
SILVER Mt g/t Ag Moz Ag
Reserves2
Proven 69.0 4.94 11.0
Probable 459.1 6.18 91.2
P&P 528.0 6.02 102.1
Resources4, exclusive of Reserves
Measured 39.5 2.58 3.27
Indicated 247.2 3.81 30.26
M&I 286.7 3.64 33.54
Inferred 346.6 4.28 47.73
* Mineral reserves are reported
on a 100% basis. NOVAGOLD and
Barrick each own 50% of the
Donlin Gold project. NOVAGOLD
and Teck each own 50% of the
Galore Creek project.
t = metric tonne
oz = ounce
lb = pound
K = thousand
M = million
B = billion
g/t = grams/tonne
Approximate cut-off grades
(see Resource Footnotes):
Donlin Gold Reserves1: 0.57 g/t gold
Resources3: 0.46 g/t gold
Galore Creek Reserves2: C$10.08 NSR
Resources4: C$10.08 NSR
Notes:
a. These resource estimates have been prepared in accordance with NI43-101 and the CIM Definition Standard, unless otherwise noted.
b. See numbered footnotes below on resource information.
c. Rounding as required by reporting guidelines may result in apparent summation differences between tonnes, grade and contained metal content
d. Tonnage and grade measurements are in metric units. Contained gold and silver ounces are reported as troy ounces, contained copper pounds as imperial pounds
Resource Footnotes:
1) Mineral Reserves are contained within Measured and Indicated pit designs, and supported by a mine plan, featuring variable throughput rates, stockpiling and cut-off optimization. The pit designs and mine plan were optimized on diluted
grades using the following economic and technical parameters: Metal price for gold of US$975/oz; reference mining cost of US$1.67/t incremented US$0.0031/t/m with depth from the 220 m elevation (equates to an average mining cost of
US$2.14/t), variable processing cost based on the formula 2.1874 x (S%) + 10.65 for each US$/t processed; general and administrative cost of US$2.27/t processed; stockpile rehandle costs of US$0.19/t processed assuming that 45% of
mill feed is rehandled; variable recoveries by rock type, ranging from 86.66% in shale to 94.17% in intrusive rocks in the Akivik domain; refining and freight charges of US$1.78/oz gold; royalty considerations of 4.5%; and variable pit slope
angles, ranging from 23º to 43º. Mineral Reserves are reported using an optimized net sales return value based on the following equation: Net Sales Return = Au grade * Recovery * (US$975/oz – (1.78 + (US$975/oz – 1.78) * 0.045)) -
(10.65 + 2.1874 * (S%) + 2.27 + 0.19) and reported in US$/tonne. Assuming an average recovery of 89.54% and an average S% grade of 1.07%, the marginal gold cutoff grade would be approximately 0.57 g/t, or the gold grade that would
equate to a 0.001 NSR cutoff at these same values. The life of mine strip ratio is 5.48. The assumed life-of-mine throughput rate is 53.5 kt/d.
2) Mineral Reserves are contained within Measured and Indicated pit designs using metal prices for copper, gold and silver of US$2.50/lb, US$1,050/oz, and US$16.85/oz, respectively. Appropriate mining costs, processing costs, metal
recoveries and inter ramp pit slope angles varying from 42º to 55º were used to generate the pit phase designs. Mineral Reserves have been calculated using a 'cashflow grade' ($NSR/SAG mill hr) cut-off which was varied from year to year
to optimize NPV. The net smelter return (NSR) was calculated as follows: NSR = Recoverable Revenue – TCRC (on a per tonne basis), where: NSR = Net Smelter Return; TCRC = Transportation and Refining Costs; Recoverable
Revenue = Revenue in Canadian dollars for recoverable copper, recoverable gold, and recoverable silver using metal prices of US$2.50/lb, US$1,050/oz, and US$16.85/oz for copper, gold, and silver, respectively, at an exchange rate of
CDN$1.1 to US$1.0; Cu Recovery = Recovery for copper based on mineral zone and total copper grade; for Mineral Reserves this NSR calculation includes mining dilution. SAG throughputs were modeled by correlation with alteration
types. Cash flow grades were calculated as the product of NSR value in $/t and throughput in t/hr. The life of mine strip ratio is 2.16.
3) Mineral Resources are contained within a conceptual Measured, Indicated and Inferred optimized pit shell using the following assumptions: gold price of US$1,200/oz; variable process cost based on 2.1874 * (sulphur grade) + 10.6485;
administration cost of US$2.29/t; refining, freight & marketing (selling costs) of US$1.85/oz recovered; stockpile rehandle costs of US$0.20/t processed assuming that 45% of mill feed is rehandled; variable royalty rate, based on royalty of
4.5% * (Au price – selling cost). Mineral Resources have been estimated using a constant Net Sales Return cut-off of US$0.001/t milled. The Net Sales Return was calculated using the formula: Net Sales Return = Au grade * Recovery *
(US$1200/oz – (1.85 + ((US$1200/oz – 1.85) * 0.045)) - (10.65 + 2.1874 * (S%) + 2.29 + 0.20)) and reported in US$/tonne. Mineral Resources are inclusive of Mineral Reserves. Mineral Resources that are not Mineral Reserves do not have
demonstrated economic viability. Inferred Resources are in addition to Measured and Indicated Resources. Inferred Resources have a great amount of uncertainty as to their existence and whether they can be mined legally or
economically. It cannot be assumed that all or any part of the Inferred Resources will ever be upgraded to a higher category. See "Cautionary Note Concerning Reserve & Resource Estimates".
4) Mineral resources are contained within a conceptual Measured, Indicated and Inferred optimized pit shell using the same economic and technical parameters as used for Mineral Reserves. Tonnages are assigned based on proportion of
the block below topography. The overburden/bedrock boundary has been assigned on a whole block basis. Mineral resources have been estimated using a constant NSR cut-off of C$10.08/t milled. The Net Smelter Return (NSR) was
calculated as follows: NSR = Recoverable Revenue – TCRC (on a per tonne basis), where: NSR = Diluted Net Smelter Return; TCRC = Transportation and Refining Costs; Recoverable Revenue = Revenue in Canadian dollars for
recoverable copper, recoverable gold, and recoverable silver using silver using the economic and technical parameters mentioned above. The mineral resource includes material within the conceptual M,I&I pit that is not scheduled for
processing in the mine plan but is above cutoff. Mineral Resources are inclusive of Mineral Reserves. Mineral Resources that are not Mineral Reserves do not have demonstrated economic viability. Inferred Resources are in addition to
Measured and Indicated Resources. Inferred Resources have a great amount of uncertainty as to their existence and whether they can be mined legally or economically. It cannot be assumed that all or any part of the Inferred Resources
will ever be upgraded to a higher category. See "Cautionary Note Concerning Reserve & Resource Estimates".
Cautionary Note Concerning Reserve & Resource Estimates
This summary table uses the term “resources”, “measured resources”, “indicated resources” and “inferred resources”. United States investors are advised that, while such terms are recognized and required by Canadian securities laws, the
United States Securities and Exchange Commission (the “SEC”) does not recognize them. Under United States standards, mineralization may not be classified as a “reserve” unless the determination has been made that the mineralization
could be economically and legally produced or extracted at the time the reserve determination is made. Mineral resources that are not mineral reserves do not have demonstrated economic viability. United States investors are cautioned not to
assume that all or any part of measured or indicated resources will ever be converted into reserves. Further, inferred resources have a great amount of uncertainty as to their existence and as to whether they can be mined legally or
economically. It cannot be assumed that all or any part of the inferred resources will ever be upgraded to a higher category. Therefore, United States investors are also cautioned not to assume that all or any part of the inferred resources
exist, or that they can be mined legally or economically. Disclosure of “contained ounces” is permitted disclosure under Canadian regulations, however, the SEC normally only permits issuers to report “resources” as in place tonnage and
grade without reference to unit measures. Accordingly, information concerning descriptions of mineralization and resources contained in this release may not be comparable to information made public by United States companies subject to
the reporting and disclosure requirements of the SEC.
NI 43-101 is a rule developed by the Canadian Securities Administrators, which established standards for all public disclosure an issuer makes of scientific and technical information concerning mineral projects. Unless otherwise indicated, all
resource estimates contained in this circular have been prepared in accordance with NI 43-101 and the CIM Definition Standards.
Technical Reports and Qualified Persons
The documents referenced below provide supporting technical information for each of NOVAGOLD's projects.
Project Qualified Person(s) Most Recent Disclosure & Filing Date
Donlin Gold Gordon Seibel R.M. SME, AMEC “Donlin Creek Gold Project Alaska, USA, NI 43-101 Technical Report on Second Updated Feasibility Study” effective November 18, 2011, amended January 20, 2012.
Kirk Hanson P.E., AMEC
Galore Creek Jay Melnyk, P.Eng., AMEC “Galore Creek Copper-Gold Project NI 43-101 Technical Report on Pre-Feasibility Study, British Columbia – Canada” effective July 27, 2011.
Greg Kulla, P.Geo., AMEC
Heather White, B.Sc., P.Eng., who is a consultant to NOVAGOLD and a “qualified person” under NI 43-101, has approved the scientific and technical information included in this Reserve and Resource Table.
NOVAGOLD: Reserve/Resource Table (con’t)
25
NOVAGOLD RESOURCES INC.
Suite 720 – 789 West Pender Street
Vancouver, BC
Canada V6C 1H2
T 604 669 6227 TF 1 866 669 6227 F 604 669 6272
www.novagold.com
info@novagold.com
Mélanie Hennessey
VP, Corporate Communications
melanie.hennessey@novagold.com
Erin O’Toole
Analyst, Investor Relations
erin.otoole@novagold.com
Contact Us
26

Mais conteúdo relacionado

Mais procurados

NOVAGOLD Second Quarter Results & Project Update
NOVAGOLD Second Quarter Results & Project UpdateNOVAGOLD Second Quarter Results & Project Update
NOVAGOLD Second Quarter Results & Project UpdateJasonMercier11
 
NOVAGOLD's Q1 2019 Financials & Project Update
NOVAGOLD's Q1 2019 Financials & Project UpdateNOVAGOLD's Q1 2019 Financials & Project Update
NOVAGOLD's Q1 2019 Financials & Project UpdateNOVAGOLD
 
NOVAGOLD Corporate Presentation – October 2016
NOVAGOLD Corporate Presentation – October 2016NOVAGOLD Corporate Presentation – October 2016
NOVAGOLD Corporate Presentation – October 2016NOVAGOLD
 
2021 03-22 ngppt-swiss mining institute conference_final
2021 03-22 ngppt-swiss mining institute conference_final2021 03-22 ngppt-swiss mining institute conference_final
2021 03-22 ngppt-swiss mining institute conference_finalNOVAGOLD
 
NOVAGOLD 2018 Third Quarter & Project Updates
NOVAGOLD 2018 Third Quarter & Project UpdatesNOVAGOLD 2018 Third Quarter & Project Updates
NOVAGOLD 2018 Third Quarter & Project UpdatesNOVAGOLD
 
Vancouver Investment Resource Conference 2016
Vancouver Investment Resource Conference 2016 Vancouver Investment Resource Conference 2016
Vancouver Investment Resource Conference 2016 NOVAGOLD
 
NOVAGOLD First Quarter 2020 Results & Project Update
NOVAGOLD First Quarter 2020 Results & Project UpdateNOVAGOLD First Quarter 2020 Results & Project Update
NOVAGOLD First Quarter 2020 Results & Project UpdateNOVAGOLD
 
Vancouver Resource Investment Conference 2014
Vancouver Resource Investment Conference 2014Vancouver Resource Investment Conference 2014
Vancouver Resource Investment Conference 2014NOVAGOLD
 
121 Mining Investment London
121 Mining Investment London 121 Mining Investment London
121 Mining Investment London NOVAGOLD
 
NOVAGOLD reports third quarter 2019 results
NOVAGOLD reports third quarter 2019 resultsNOVAGOLD reports third quarter 2019 results
NOVAGOLD reports third quarter 2019 resultsJasonMercier11
 
NOVAGOLD 2021 First-Quarter Financial Results & Project Update
NOVAGOLD 2021 First-Quarter Financial Results & Project UpdateNOVAGOLD 2021 First-Quarter Financial Results & Project Update
NOVAGOLD 2021 First-Quarter Financial Results & Project UpdateNOVAGOLD
 
NOVAGOLD Corporate Presentation - February 2017
NOVAGOLD Corporate Presentation - February 2017 NOVAGOLD Corporate Presentation - February 2017
NOVAGOLD Corporate Presentation - February 2017 NOVAGOLD
 
Cowen and Company 4th Annual Global Metals, Mining and Materials Conference
Cowen and Company 4th Annual Global Metals, Mining and Materials ConferenceCowen and Company 4th Annual Global Metals, Mining and Materials Conference
Cowen and Company 4th Annual Global Metals, Mining and Materials ConferenceNOVAGOLD
 
2013 Metals & Minerals Investment Conference, San Francisco
2013 Metals & Minerals Investment Conference, San Francisco2013 Metals & Minerals Investment Conference, San Francisco
2013 Metals & Minerals Investment Conference, San FranciscoNOVAGOLD
 
JTVIR Metals & Mining Conference
JTVIR Metals & Mining ConferenceJTVIR Metals & Mining Conference
JTVIR Metals & Mining ConferenceNOVAGOLD
 
NOVAGOLD - 2021 PDAC Convention (virtual)
NOVAGOLD - 2021 PDAC Convention (virtual)NOVAGOLD - 2021 PDAC Convention (virtual)
NOVAGOLD - 2021 PDAC Convention (virtual)NOVAGOLD
 

Mais procurados (16)

NOVAGOLD Second Quarter Results & Project Update
NOVAGOLD Second Quarter Results & Project UpdateNOVAGOLD Second Quarter Results & Project Update
NOVAGOLD Second Quarter Results & Project Update
 
NOVAGOLD's Q1 2019 Financials & Project Update
NOVAGOLD's Q1 2019 Financials & Project UpdateNOVAGOLD's Q1 2019 Financials & Project Update
NOVAGOLD's Q1 2019 Financials & Project Update
 
NOVAGOLD Corporate Presentation – October 2016
NOVAGOLD Corporate Presentation – October 2016NOVAGOLD Corporate Presentation – October 2016
NOVAGOLD Corporate Presentation – October 2016
 
2021 03-22 ngppt-swiss mining institute conference_final
2021 03-22 ngppt-swiss mining institute conference_final2021 03-22 ngppt-swiss mining institute conference_final
2021 03-22 ngppt-swiss mining institute conference_final
 
NOVAGOLD 2018 Third Quarter & Project Updates
NOVAGOLD 2018 Third Quarter & Project UpdatesNOVAGOLD 2018 Third Quarter & Project Updates
NOVAGOLD 2018 Third Quarter & Project Updates
 
Vancouver Investment Resource Conference 2016
Vancouver Investment Resource Conference 2016 Vancouver Investment Resource Conference 2016
Vancouver Investment Resource Conference 2016
 
NOVAGOLD First Quarter 2020 Results & Project Update
NOVAGOLD First Quarter 2020 Results & Project UpdateNOVAGOLD First Quarter 2020 Results & Project Update
NOVAGOLD First Quarter 2020 Results & Project Update
 
Vancouver Resource Investment Conference 2014
Vancouver Resource Investment Conference 2014Vancouver Resource Investment Conference 2014
Vancouver Resource Investment Conference 2014
 
121 Mining Investment London
121 Mining Investment London 121 Mining Investment London
121 Mining Investment London
 
NOVAGOLD reports third quarter 2019 results
NOVAGOLD reports third quarter 2019 resultsNOVAGOLD reports third quarter 2019 results
NOVAGOLD reports third quarter 2019 results
 
NOVAGOLD 2021 First-Quarter Financial Results & Project Update
NOVAGOLD 2021 First-Quarter Financial Results & Project UpdateNOVAGOLD 2021 First-Quarter Financial Results & Project Update
NOVAGOLD 2021 First-Quarter Financial Results & Project Update
 
NOVAGOLD Corporate Presentation - February 2017
NOVAGOLD Corporate Presentation - February 2017 NOVAGOLD Corporate Presentation - February 2017
NOVAGOLD Corporate Presentation - February 2017
 
Cowen and Company 4th Annual Global Metals, Mining and Materials Conference
Cowen and Company 4th Annual Global Metals, Mining and Materials ConferenceCowen and Company 4th Annual Global Metals, Mining and Materials Conference
Cowen and Company 4th Annual Global Metals, Mining and Materials Conference
 
2013 Metals & Minerals Investment Conference, San Francisco
2013 Metals & Minerals Investment Conference, San Francisco2013 Metals & Minerals Investment Conference, San Francisco
2013 Metals & Minerals Investment Conference, San Francisco
 
JTVIR Metals & Mining Conference
JTVIR Metals & Mining ConferenceJTVIR Metals & Mining Conference
JTVIR Metals & Mining Conference
 
NOVAGOLD - 2021 PDAC Convention (virtual)
NOVAGOLD - 2021 PDAC Convention (virtual)NOVAGOLD - 2021 PDAC Convention (virtual)
NOVAGOLD - 2021 PDAC Convention (virtual)
 

Destaque

Anisimova VV vnutrennya energia 8klass
Anisimova VV vnutrennya energia 8klassAnisimova VV vnutrennya energia 8klass
Anisimova VV vnutrennya energia 8klassvichenka
 
Residential water users' modeling SOTA
Residential water users' modeling SOTAResidential water users' modeling SOTA
Residential water users' modeling SOTASmartH2O
 
 Esercizi Allungamento Del Pene O Jelqing
 Esercizi Allungamento Del Pene O Jelqing 
 Esercizi Allungamento Del Pene O Jelqing
 Esercizi Allungamento Del Pene O Jelqing jitterydeformit22
 
Modeling and simulation of solar photovoltaic module using matlab simulink
Modeling and simulation of solar photovoltaic module using matlab   simulinkModeling and simulation of solar photovoltaic module using matlab   simulink
Modeling and simulation of solar photovoltaic module using matlab simulinkeSAT Journals
 
Branding jak malowany [BrandPRO]
Branding jak malowany [BrandPRO]Branding jak malowany [BrandPRO]
Branding jak malowany [BrandPRO]BrandPRO
 

Destaque (9)

Anisimova VV vnutrennya energia 8klass
Anisimova VV vnutrennya energia 8klassAnisimova VV vnutrennya energia 8klass
Anisimova VV vnutrennya energia 8klass
 
Wqb 3
Wqb 3Wqb 3
Wqb 3
 
アメブロはSEOに強いのか?
アメブロはSEOに強いのか?アメブロはSEOに強いのか?
アメブロはSEOに強いのか?
 
Residential water users' modeling SOTA
Residential water users' modeling SOTAResidential water users' modeling SOTA
Residential water users' modeling SOTA
 
MY RESUME AUG 2016
MY RESUME AUG 2016MY RESUME AUG 2016
MY RESUME AUG 2016
 
 Esercizi Allungamento Del Pene O Jelqing
 Esercizi Allungamento Del Pene O Jelqing 
 Esercizi Allungamento Del Pene O Jelqing
 Esercizi Allungamento Del Pene O Jelqing
 
Comparativa luminica
Comparativa luminicaComparativa luminica
Comparativa luminica
 
Modeling and simulation of solar photovoltaic module using matlab simulink
Modeling and simulation of solar photovoltaic module using matlab   simulinkModeling and simulation of solar photovoltaic module using matlab   simulink
Modeling and simulation of solar photovoltaic module using matlab simulink
 
Branding jak malowany [BrandPRO]
Branding jak malowany [BrandPRO]Branding jak malowany [BrandPRO]
Branding jak malowany [BrandPRO]
 

Semelhante a NOVAGOLD Q1-2015 Financial Results Conference Call & Webcast

NOVAGOLD Q2-2015 Financials and Project Update
NOVAGOLD Q2-2015 Financials and Project Update NOVAGOLD Q2-2015 Financials and Project Update
NOVAGOLD Q2-2015 Financials and Project Update NOVAGOLD
 
NOVAGOLD - 2014 Third Quarter & Project Update
NOVAGOLD - 2014 Third Quarter & Project UpdateNOVAGOLD - 2014 Third Quarter & Project Update
NOVAGOLD - 2014 Third Quarter & Project UpdateCompany Spotlight
 
NOVAGOLD 2016 First Quarter Financials & Project Update
NOVAGOLD 2016 First Quarter Financials & Project UpdateNOVAGOLD 2016 First Quarter Financials & Project Update
NOVAGOLD 2016 First Quarter Financials & Project UpdateNOVAGOLD
 
NOVAGOLD 2015 Year-End Financials & Project Update
NOVAGOLD 2015 Year-End Financials & Project UpdateNOVAGOLD 2015 Year-End Financials & Project Update
NOVAGOLD 2015 Year-End Financials & Project UpdateNOVAGOLD
 
2014 04-08 ngppt-q1-2014_final
2014 04-08 ngppt-q1-2014_final2014 04-08 ngppt-q1-2014_final
2014 04-08 ngppt-q1-2014_finalCompany Spotlight
 
Q3-2016 Financials & Project Update
Q3-2016 Financials & Project UpdateQ3-2016 Financials & Project Update
Q3-2016 Financials & Project UpdateNOVAGOLD
 
2013 Year-End Financials & Project Update
2013 Year-End Financials & Project Update2013 Year-End Financials & Project Update
2013 Year-End Financials & Project UpdateCompany Spotlight
 
2013 year-end financial results & project update
2013 year-end financial results & project update2013 year-end financial results & project update
2013 year-end financial results & project updateNOVAGOLD
 
NOVAGOLD Corporate Presentation - October 2015
NOVAGOLD Corporate Presentation - October 2015 NOVAGOLD Corporate Presentation - October 2015
NOVAGOLD Corporate Presentation - October 2015 NOVAGOLD
 
NOVAGOLD Precious Metals Summit, Zurich
NOVAGOLD Precious Metals Summit, Zurich NOVAGOLD Precious Metals Summit, Zurich
NOVAGOLD Precious Metals Summit, Zurich NOVAGOLD
 
2014 Annual & Special Meeting of Shareholders
2014 Annual & Special Meeting of Shareholders2014 Annual & Special Meeting of Shareholders
2014 Annual & Special Meeting of ShareholdersNOVAGOLD
 
2020 01-23 ngppt-q4_2019_final
2020 01-23 ngppt-q4_2019_final2020 01-23 ngppt-q4_2019_final
2020 01-23 ngppt-q4_2019_finalNOVAGOLD
 
Vancouver Resource Investment Conference
Vancouver Resource Investment ConferenceVancouver Resource Investment Conference
Vancouver Resource Investment ConferenceNOVAGOLD
 
Jefferies Industrials Conference, NYC
Jefferies Industrials Conference, NYC Jefferies Industrials Conference, NYC
Jefferies Industrials Conference, NYC NOVAGOLD
 
NOVAGOLD 2018 Year-End Financials & Project Update
NOVAGOLD 2018 Year-End Financials & Project UpdateNOVAGOLD 2018 Year-End Financials & Project Update
NOVAGOLD 2018 Year-End Financials & Project UpdateNOVAGOLD
 
NOVAGOLD Second Quarter Results & Project Update
NOVAGOLD Second Quarter Results & Project UpdateNOVAGOLD Second Quarter Results & Project Update
NOVAGOLD Second Quarter Results & Project UpdateNOVAGOLD
 
Cowen & Company 5th Annual Global Metals, Mining and Materials Conference
Cowen & Company 5th Annual Global Metals, Mining and Materials ConferenceCowen & Company 5th Annual Global Metals, Mining and Materials Conference
Cowen & Company 5th Annual Global Metals, Mining and Materials ConferenceNOVAGOLD
 
Sprott-Stansberry Vancouver Natural Resources Symposium
Sprott-Stansberry Vancouver Natural Resources Symposium Sprott-Stansberry Vancouver Natural Resources Symposium
Sprott-Stansberry Vancouver Natural Resources Symposium NOVAGOLD
 
NOVAGOLD Q3 2013 Conference Call & Webcast
NOVAGOLD Q3 2013 Conference Call & Webcast  NOVAGOLD Q3 2013 Conference Call & Webcast
NOVAGOLD Q3 2013 Conference Call & Webcast NOVAGOLD
 
Ngppt jtvir conference_final
Ngppt jtvir conference_finalNgppt jtvir conference_final
Ngppt jtvir conference_finalCompany Spotlight
 

Semelhante a NOVAGOLD Q1-2015 Financial Results Conference Call & Webcast (20)

NOVAGOLD Q2-2015 Financials and Project Update
NOVAGOLD Q2-2015 Financials and Project Update NOVAGOLD Q2-2015 Financials and Project Update
NOVAGOLD Q2-2015 Financials and Project Update
 
NOVAGOLD - 2014 Third Quarter & Project Update
NOVAGOLD - 2014 Third Quarter & Project UpdateNOVAGOLD - 2014 Third Quarter & Project Update
NOVAGOLD - 2014 Third Quarter & Project Update
 
NOVAGOLD 2016 First Quarter Financials & Project Update
NOVAGOLD 2016 First Quarter Financials & Project UpdateNOVAGOLD 2016 First Quarter Financials & Project Update
NOVAGOLD 2016 First Quarter Financials & Project Update
 
NOVAGOLD 2015 Year-End Financials & Project Update
NOVAGOLD 2015 Year-End Financials & Project UpdateNOVAGOLD 2015 Year-End Financials & Project Update
NOVAGOLD 2015 Year-End Financials & Project Update
 
2014 04-08 ngppt-q1-2014_final
2014 04-08 ngppt-q1-2014_final2014 04-08 ngppt-q1-2014_final
2014 04-08 ngppt-q1-2014_final
 
Q3-2016 Financials & Project Update
Q3-2016 Financials & Project UpdateQ3-2016 Financials & Project Update
Q3-2016 Financials & Project Update
 
2013 Year-End Financials & Project Update
2013 Year-End Financials & Project Update2013 Year-End Financials & Project Update
2013 Year-End Financials & Project Update
 
2013 year-end financial results & project update
2013 year-end financial results & project update2013 year-end financial results & project update
2013 year-end financial results & project update
 
NOVAGOLD Corporate Presentation - October 2015
NOVAGOLD Corporate Presentation - October 2015 NOVAGOLD Corporate Presentation - October 2015
NOVAGOLD Corporate Presentation - October 2015
 
NOVAGOLD Precious Metals Summit, Zurich
NOVAGOLD Precious Metals Summit, Zurich NOVAGOLD Precious Metals Summit, Zurich
NOVAGOLD Precious Metals Summit, Zurich
 
2014 Annual & Special Meeting of Shareholders
2014 Annual & Special Meeting of Shareholders2014 Annual & Special Meeting of Shareholders
2014 Annual & Special Meeting of Shareholders
 
2020 01-23 ngppt-q4_2019_final
2020 01-23 ngppt-q4_2019_final2020 01-23 ngppt-q4_2019_final
2020 01-23 ngppt-q4_2019_final
 
Vancouver Resource Investment Conference
Vancouver Resource Investment ConferenceVancouver Resource Investment Conference
Vancouver Resource Investment Conference
 
Jefferies Industrials Conference, NYC
Jefferies Industrials Conference, NYC Jefferies Industrials Conference, NYC
Jefferies Industrials Conference, NYC
 
NOVAGOLD 2018 Year-End Financials & Project Update
NOVAGOLD 2018 Year-End Financials & Project UpdateNOVAGOLD 2018 Year-End Financials & Project Update
NOVAGOLD 2018 Year-End Financials & Project Update
 
NOVAGOLD Second Quarter Results & Project Update
NOVAGOLD Second Quarter Results & Project UpdateNOVAGOLD Second Quarter Results & Project Update
NOVAGOLD Second Quarter Results & Project Update
 
Cowen & Company 5th Annual Global Metals, Mining and Materials Conference
Cowen & Company 5th Annual Global Metals, Mining and Materials ConferenceCowen & Company 5th Annual Global Metals, Mining and Materials Conference
Cowen & Company 5th Annual Global Metals, Mining and Materials Conference
 
Sprott-Stansberry Vancouver Natural Resources Symposium
Sprott-Stansberry Vancouver Natural Resources Symposium Sprott-Stansberry Vancouver Natural Resources Symposium
Sprott-Stansberry Vancouver Natural Resources Symposium
 
NOVAGOLD Q3 2013 Conference Call & Webcast
NOVAGOLD Q3 2013 Conference Call & Webcast  NOVAGOLD Q3 2013 Conference Call & Webcast
NOVAGOLD Q3 2013 Conference Call & Webcast
 
Ngppt jtvir conference_final
Ngppt jtvir conference_finalNgppt jtvir conference_final
Ngppt jtvir conference_final
 

Mais de NOVAGOLD

NOVAGOLD - Canaccord Genuity presentation, April 2021
NOVAGOLD - Canaccord Genuity presentation, April 2021NOVAGOLD - Canaccord Genuity presentation, April 2021
NOVAGOLD - Canaccord Genuity presentation, April 2021NOVAGOLD
 
NOVAGOLD - World Gold Forum, April 2021
NOVAGOLD - World Gold Forum, April 2021NOVAGOLD - World Gold Forum, April 2021
NOVAGOLD - World Gold Forum, April 2021NOVAGOLD
 
NOVAGOLD - BMO Global Metals and Mining Conference, March 2021
NOVAGOLD - BMO Global Metals and Mining Conference, March 2021NOVAGOLD - BMO Global Metals and Mining Conference, March 2021
NOVAGOLD - BMO Global Metals and Mining Conference, March 2021NOVAGOLD
 
NOVAGOLD - 2020 Year-End Financial Results and Project Update
NOVAGOLD - 2020 Year-End Financial Results and Project UpdateNOVAGOLD - 2020 Year-End Financial Results and Project Update
NOVAGOLD - 2020 Year-End Financial Results and Project UpdateNOVAGOLD
 
NOVAGOLD - RBC Global Mining Conference, November 2020
NOVAGOLD - RBC Global Mining Conference, November 2020NOVAGOLD - RBC Global Mining Conference, November 2020
NOVAGOLD - RBC Global Mining Conference, November 2020NOVAGOLD
 
NOVAGOLD - Amvest Capital Webinar Presentation, November 2020
NOVAGOLD - Amvest Capital Webinar Presentation, November 2020NOVAGOLD - Amvest Capital Webinar Presentation, November 2020
NOVAGOLD - Amvest Capital Webinar Presentation, November 2020NOVAGOLD
 
NOVAGOLD - Precious Metals Summit Europe 2020
NOVAGOLD - Precious Metals Summit Europe 2020NOVAGOLD - Precious Metals Summit Europe 2020
NOVAGOLD - Precious Metals Summit Europe 2020NOVAGOLD
 
NOVAGOLD - Bloor Street Capital Presentation, October 2020
NOVAGOLD - Bloor Street Capital Presentation, October 2020NOVAGOLD - Bloor Street Capital Presentation, October 2020
NOVAGOLD - Bloor Street Capital Presentation, October 2020NOVAGOLD
 
2020-10-01 NOVAGOLD Q3 2020 Results and Project Update
2020-10-01 NOVAGOLD Q3 2020 Results and Project Update2020-10-01 NOVAGOLD Q3 2020 Results and Project Update
2020-10-01 NOVAGOLD Q3 2020 Results and Project UpdateNOVAGOLD
 
NOVAGOLD Gold Forum Americas Conference 2020
NOVAGOLD Gold Forum Americas Conference 2020NOVAGOLD Gold Forum Americas Conference 2020
NOVAGOLD Gold Forum Americas Conference 2020NOVAGOLD
 
NOVAGOLD - Precious Metals Summit 2020
NOVAGOLD - Precious Metals Summit 2020NOVAGOLD - Precious Metals Summit 2020
NOVAGOLD - Precious Metals Summit 2020NOVAGOLD
 
2020-07-23 ngppt-novagold corporate presentation_amvest capital_final
2020-07-23 ngppt-novagold corporate presentation_amvest capital_final2020-07-23 ngppt-novagold corporate presentation_amvest capital_final
2020-07-23 ngppt-novagold corporate presentation_amvest capital_finalNOVAGOLD
 
2020 06-25 ngppt-novagold q2 2020 results and project update_final
2020 06-25 ngppt-novagold q2 2020 results and project update_final2020 06-25 ngppt-novagold q2 2020 results and project update_final
2020 06-25 ngppt-novagold q2 2020 results and project update_finalNOVAGOLD
 
NOVAGOLD Annual Meeting of Shareholders 2020 presentation
NOVAGOLD Annual Meeting of Shareholders 2020 presentationNOVAGOLD Annual Meeting of Shareholders 2020 presentation
NOVAGOLD Annual Meeting of Shareholders 2020 presentationNOVAGOLD
 
NOVAGOLD presentation at the World Gold Forum 2020
NOVAGOLD presentation at the World Gold Forum 2020NOVAGOLD presentation at the World Gold Forum 2020
NOVAGOLD presentation at the World Gold Forum 2020NOVAGOLD
 
2020 02-26 ngppt-bmo global metals conference_final
2020 02-26 ngppt-bmo global metals conference_final2020 02-26 ngppt-bmo global metals conference_final
2020 02-26 ngppt-bmo global metals conference_finalNOVAGOLD
 
NOVAGOLD - 2019 European Gold Forum
NOVAGOLD - 2019 European Gold ForumNOVAGOLD - 2019 European Gold Forum
NOVAGOLD - 2019 European Gold ForumNOVAGOLD
 
NOVAGOLD's Corporate Presentation - March 2019
NOVAGOLD's Corporate Presentation - March 2019NOVAGOLD's Corporate Presentation - March 2019
NOVAGOLD's Corporate Presentation - March 2019NOVAGOLD
 
NOVAGOLD - 2019 BMO Capital Global Metals & Mining Conference
NOVAGOLD - 2019 BMO Capital Global Metals & Mining ConferenceNOVAGOLD - 2019 BMO Capital Global Metals & Mining Conference
NOVAGOLD - 2019 BMO Capital Global Metals & Mining ConferenceNOVAGOLD
 
NOVAGOLD's November 2018 Corporate Presentation
NOVAGOLD's November 2018 Corporate PresentationNOVAGOLD's November 2018 Corporate Presentation
NOVAGOLD's November 2018 Corporate PresentationNOVAGOLD
 

Mais de NOVAGOLD (20)

NOVAGOLD - Canaccord Genuity presentation, April 2021
NOVAGOLD - Canaccord Genuity presentation, April 2021NOVAGOLD - Canaccord Genuity presentation, April 2021
NOVAGOLD - Canaccord Genuity presentation, April 2021
 
NOVAGOLD - World Gold Forum, April 2021
NOVAGOLD - World Gold Forum, April 2021NOVAGOLD - World Gold Forum, April 2021
NOVAGOLD - World Gold Forum, April 2021
 
NOVAGOLD - BMO Global Metals and Mining Conference, March 2021
NOVAGOLD - BMO Global Metals and Mining Conference, March 2021NOVAGOLD - BMO Global Metals and Mining Conference, March 2021
NOVAGOLD - BMO Global Metals and Mining Conference, March 2021
 
NOVAGOLD - 2020 Year-End Financial Results and Project Update
NOVAGOLD - 2020 Year-End Financial Results and Project UpdateNOVAGOLD - 2020 Year-End Financial Results and Project Update
NOVAGOLD - 2020 Year-End Financial Results and Project Update
 
NOVAGOLD - RBC Global Mining Conference, November 2020
NOVAGOLD - RBC Global Mining Conference, November 2020NOVAGOLD - RBC Global Mining Conference, November 2020
NOVAGOLD - RBC Global Mining Conference, November 2020
 
NOVAGOLD - Amvest Capital Webinar Presentation, November 2020
NOVAGOLD - Amvest Capital Webinar Presentation, November 2020NOVAGOLD - Amvest Capital Webinar Presentation, November 2020
NOVAGOLD - Amvest Capital Webinar Presentation, November 2020
 
NOVAGOLD - Precious Metals Summit Europe 2020
NOVAGOLD - Precious Metals Summit Europe 2020NOVAGOLD - Precious Metals Summit Europe 2020
NOVAGOLD - Precious Metals Summit Europe 2020
 
NOVAGOLD - Bloor Street Capital Presentation, October 2020
NOVAGOLD - Bloor Street Capital Presentation, October 2020NOVAGOLD - Bloor Street Capital Presentation, October 2020
NOVAGOLD - Bloor Street Capital Presentation, October 2020
 
2020-10-01 NOVAGOLD Q3 2020 Results and Project Update
2020-10-01 NOVAGOLD Q3 2020 Results and Project Update2020-10-01 NOVAGOLD Q3 2020 Results and Project Update
2020-10-01 NOVAGOLD Q3 2020 Results and Project Update
 
NOVAGOLD Gold Forum Americas Conference 2020
NOVAGOLD Gold Forum Americas Conference 2020NOVAGOLD Gold Forum Americas Conference 2020
NOVAGOLD Gold Forum Americas Conference 2020
 
NOVAGOLD - Precious Metals Summit 2020
NOVAGOLD - Precious Metals Summit 2020NOVAGOLD - Precious Metals Summit 2020
NOVAGOLD - Precious Metals Summit 2020
 
2020-07-23 ngppt-novagold corporate presentation_amvest capital_final
2020-07-23 ngppt-novagold corporate presentation_amvest capital_final2020-07-23 ngppt-novagold corporate presentation_amvest capital_final
2020-07-23 ngppt-novagold corporate presentation_amvest capital_final
 
2020 06-25 ngppt-novagold q2 2020 results and project update_final
2020 06-25 ngppt-novagold q2 2020 results and project update_final2020 06-25 ngppt-novagold q2 2020 results and project update_final
2020 06-25 ngppt-novagold q2 2020 results and project update_final
 
NOVAGOLD Annual Meeting of Shareholders 2020 presentation
NOVAGOLD Annual Meeting of Shareholders 2020 presentationNOVAGOLD Annual Meeting of Shareholders 2020 presentation
NOVAGOLD Annual Meeting of Shareholders 2020 presentation
 
NOVAGOLD presentation at the World Gold Forum 2020
NOVAGOLD presentation at the World Gold Forum 2020NOVAGOLD presentation at the World Gold Forum 2020
NOVAGOLD presentation at the World Gold Forum 2020
 
2020 02-26 ngppt-bmo global metals conference_final
2020 02-26 ngppt-bmo global metals conference_final2020 02-26 ngppt-bmo global metals conference_final
2020 02-26 ngppt-bmo global metals conference_final
 
NOVAGOLD - 2019 European Gold Forum
NOVAGOLD - 2019 European Gold ForumNOVAGOLD - 2019 European Gold Forum
NOVAGOLD - 2019 European Gold Forum
 
NOVAGOLD's Corporate Presentation - March 2019
NOVAGOLD's Corporate Presentation - March 2019NOVAGOLD's Corporate Presentation - March 2019
NOVAGOLD's Corporate Presentation - March 2019
 
NOVAGOLD - 2019 BMO Capital Global Metals & Mining Conference
NOVAGOLD - 2019 BMO Capital Global Metals & Mining ConferenceNOVAGOLD - 2019 BMO Capital Global Metals & Mining Conference
NOVAGOLD - 2019 BMO Capital Global Metals & Mining Conference
 
NOVAGOLD's November 2018 Corporate Presentation
NOVAGOLD's November 2018 Corporate PresentationNOVAGOLD's November 2018 Corporate Presentation
NOVAGOLD's November 2018 Corporate Presentation
 

Último

Leveraging USDA Rural Development Grants for Community Growth and Sustainabil...
Leveraging USDA Rural Development Grants for Community Growth and Sustainabil...Leveraging USDA Rural Development Grants for Community Growth and Sustainabil...
Leveraging USDA Rural Development Grants for Community Growth and Sustainabil...USDAReapgrants.com
 
slideshare_2404_presentation materials_en.pdf
slideshare_2404_presentation materials_en.pdfslideshare_2404_presentation materials_en.pdf
slideshare_2404_presentation materials_en.pdfsansanir
 
WheelTug PLC Pitch Deck | Investor Insights | April 2024
WheelTug PLC Pitch Deck | Investor Insights | April 2024WheelTug PLC Pitch Deck | Investor Insights | April 2024
WheelTug PLC Pitch Deck | Investor Insights | April 2024Hector Del Castillo, CPM, CPMM
 
Q1 Quarterly Update - April 16, 2024.pdf
Q1 Quarterly Update - April 16, 2024.pdfQ1 Quarterly Update - April 16, 2024.pdf
Q1 Quarterly Update - April 16, 2024.pdfProbe Gold
 
Collective Mining | Corporate Presentation - April 2024
Collective Mining | Corporate Presentation - April 2024Collective Mining | Corporate Presentation - April 2024
Collective Mining | Corporate Presentation - April 2024CollectiveMining1
 
Corporate Presentation Probe April 2024.pdf
Corporate Presentation Probe April 2024.pdfCorporate Presentation Probe April 2024.pdf
Corporate Presentation Probe April 2024.pdfProbe Gold
 
Corporate Presentation Probe April 2024.pdf
Corporate Presentation Probe April 2024.pdfCorporate Presentation Probe April 2024.pdf
Corporate Presentation Probe April 2024.pdfProbe Gold
 
9654467111 Call Girls In Katwaria Sarai Short 1500 Night 6000
9654467111 Call Girls In Katwaria Sarai Short 1500 Night 60009654467111 Call Girls In Katwaria Sarai Short 1500 Night 6000
9654467111 Call Girls In Katwaria Sarai Short 1500 Night 6000Sapana Sha
 
the 25 most beautiful words for a loving and lasting relationship.pdf
the 25 most beautiful words for a loving and lasting relationship.pdfthe 25 most beautiful words for a loving and lasting relationship.pdf
the 25 most beautiful words for a loving and lasting relationship.pdfFrancenel Paul
 

Último (11)

Leveraging USDA Rural Development Grants for Community Growth and Sustainabil...
Leveraging USDA Rural Development Grants for Community Growth and Sustainabil...Leveraging USDA Rural Development Grants for Community Growth and Sustainabil...
Leveraging USDA Rural Development Grants for Community Growth and Sustainabil...
 
slideshare_2404_presentation materials_en.pdf
slideshare_2404_presentation materials_en.pdfslideshare_2404_presentation materials_en.pdf
slideshare_2404_presentation materials_en.pdf
 
WheelTug PLC Pitch Deck | Investor Insights | April 2024
WheelTug PLC Pitch Deck | Investor Insights | April 2024WheelTug PLC Pitch Deck | Investor Insights | April 2024
WheelTug PLC Pitch Deck | Investor Insights | April 2024
 
Q1 Quarterly Update - April 16, 2024.pdf
Q1 Quarterly Update - April 16, 2024.pdfQ1 Quarterly Update - April 16, 2024.pdf
Q1 Quarterly Update - April 16, 2024.pdf
 
Collective Mining | Corporate Presentation - April 2024
Collective Mining | Corporate Presentation - April 2024Collective Mining | Corporate Presentation - April 2024
Collective Mining | Corporate Presentation - April 2024
 
young call girls in Hauz Khas,🔝 9953056974 🔝 escort Service
young call girls in Hauz Khas,🔝 9953056974 🔝 escort Serviceyoung call girls in Hauz Khas,🔝 9953056974 🔝 escort Service
young call girls in Hauz Khas,🔝 9953056974 🔝 escort Service
 
Corporate Presentation Probe April 2024.pdf
Corporate Presentation Probe April 2024.pdfCorporate Presentation Probe April 2024.pdf
Corporate Presentation Probe April 2024.pdf
 
Corporate Presentation Probe April 2024.pdf
Corporate Presentation Probe April 2024.pdfCorporate Presentation Probe April 2024.pdf
Corporate Presentation Probe April 2024.pdf
 
9654467111 Call Girls In Katwaria Sarai Short 1500 Night 6000
9654467111 Call Girls In Katwaria Sarai Short 1500 Night 60009654467111 Call Girls In Katwaria Sarai Short 1500 Night 6000
9654467111 Call Girls In Katwaria Sarai Short 1500 Night 6000
 
the 25 most beautiful words for a loving and lasting relationship.pdf
the 25 most beautiful words for a loving and lasting relationship.pdfthe 25 most beautiful words for a loving and lasting relationship.pdf
the 25 most beautiful words for a loving and lasting relationship.pdf
 
Call Girls in South Ex⎝⎝9953056974⎝⎝ Escort Delhi NCR
Call Girls in South Ex⎝⎝9953056974⎝⎝ Escort Delhi NCRCall Girls in South Ex⎝⎝9953056974⎝⎝ Escort Delhi NCR
Call Girls in South Ex⎝⎝9953056974⎝⎝ Escort Delhi NCR
 

NOVAGOLD Q1-2015 Financial Results Conference Call & Webcast

  • 1. novagold.com NYSE-MKT, TSX: NG | April 2015 2015 First Quarter & Project Update
  • 2. Conference Call Attendees 2 ▶ Introduction Mélanie Hennessy (Vice President Corporate Communications) ▶ Corporate Update Greg Lang (President & Chief Executive Officer) ▶ First Quarter Financials & 2015 Budget David Ottewell (Vice President & Chief Financial Officer) ▶ Closing Remarks Greg Lang (President & Chief Executive Officer) ▶ Question & Answer Session Greg Lang & David Ottewell
  • 3. Cautionary Statements REGARDING FORWARD-LOOKING STATEMENTS This presentation includes certain “forward-looking statements” within the meaning of applicable securities laws, including the United States Private Securities Litigation Reform Act of 1995. All statements, other than statements of historical fact, included herein including, without limitation, statements relating to Donlin Gold’s future operating or financial performance, are forward- looking statements. Forward-looking statements are frequently, but not always, identified by words such as “plans”, “expects”, “anticipates”, “believes”, “intends”, “estimates”, “potential”, “possible” and similar expressions, or statements that events, conditions or results “will”, “may”, “could”, or “should” occur or be achieved. These forward-looking statements are set forth in the slides pertaining to the implementation of the Donlin Gold second updated Feasibility Study and pertaining to the implementation of the Galore Creek Pre-Feasibility Study, the factors that may influence future gold price performance, and the potential future value of gold, and may include statements regarding perceived merit of properties; exploration results and budgets; mineral reserves and resource estimates; work programs; capital expenditures; timelines; strategic plans; completion of transactions; market price of precious or base metals; or other statements that are not statements of fact. Forward-looking statements involve various risks and uncertainties. There can be no assurance that such statements will prove to be accurate, and actual results and future events could differ materially from those anticipated in such statements. Important factors that could cause actual results to differ materially from our expectations include the uncertainties involving the need for additional financing to explore and develop properties and availability of financing in the debt and capital markets; uncertainties involved in the interpretation of drilling results and geological tests and the estimation of reserves and resources; the need for continued cooperation between NOVAGOLD and Barrick Gold in the exploration and development of the Donlin Gold property; the need for continued cooperation between NOVAGOLD and Teck Resources Ltd. in the exploration and development of the Galore Creek property; the need for cooperation of government agencies and native groups in the development and operation of properties; the need to obtain permits and governmental approvals; risks of construction and mining projects such as accidents, equipment breakdowns, bad weather, non-compliance with environmental and permit requirements, unanticipated variation in geological structures, ore grades or recovery rates; unexpected cost increases; fluctuations in metal prices and currency exchange rates; and other risks and uncertainties disclosed in reports and documents filed by NOVAGOLD with applicable securities regulatory authorities from time to time. The forward-looking statements made herein reflect our beliefs, opinions and projections on the date the statements are made. Except as required by law, we assume no obligation to update the forward-looking statements of beliefs, opinions, projections, or other factors, should they change. REGARDING SCIENTIFIC AND TECHNICAL INFORMATION Unless otherwise indicated, all reserve and resource estimates included in this presentation have been prepared in accordance with Canadian National Instrument 43-101 Standards of Disclosure for Mineral Projects (“NI 43-101”) and the Canadian Institute of Mining, Metallurgy and Petroleum Definition Standards for Mineral Resources and Mineral Reserves (“CIM Definition Standards”). Canadian standards, including NI 43-101, differ significantly from the requirements of the United States Securities and Exchange Commission (“SEC”), and reserve and resource information in this presentation may not be comparable to similar information disclosed by U.S. companies. In particular, and without limiting the generality of the foregoing, the term “resource” does not equate to the term “‘reserves”. Under U.S. standards, mineralization may not be classified as a “reserve” unless the determination has been made that the mineralization could be economically and legally produced or extracted at the time the reserve determination is made. At this time, both of Donlin Gold and Galore Creek projects are without known reserves, as defined under SEC Industry Guide 7. The SEC’s disclosure standards normally do not permit the inclusion of information concerning “measured mineral resources”, “indicated mineral resources” or “inferred mineral resources” or other descriptions of the amount of mineralization in mineral deposits that do not constitute “reserves” by U.S. standards in documents filed with the SEC. U.S. investors should also understand that “inferred mineral resources” have a great amount of uncertainty as to their existence and great uncertainty as to their economic and legal feasibility. It cannot be assumed that all or any part of an “inferred mineral resource” will ever be upgraded to a higher category. Under Canadian rules, estimated “inferred mineral resources” may not form the basis of feasibility or pre-feasibility studies except in rare cases. Investors are cautioned not to assume that all or any part of an “inferred mineral resource” exists or is economically or legally mineable. Disclosure of “contained ounces” in a resource is permitted disclosure under Canadian regulations; however, the SEC normally only permits issuers to report mineralization that does not constitute “reserves” by SEC standards as in-place tonnage and grade without reference to unit measures. The requirements of NI 43-101 for identification of “reserves” are also not the same as those of the SEC, and reserves reported in compliance with NI 43-101 may not qualify as “reserves” under SEC standards. Accordingly, information concerning mineral deposits set forth herein may not be comparable to information made public by companies that report in accordance with United States standards. All dollar amounts quoted in this report are in U.S. currency unless otherwise noted. 3
  • 4. What Makes NOVAGOLD Unique? Poised to become one of the largest gold producers in the world DONLIN GOLD GALORE CREEK Expected to be the largest and lowest cost copper mine in Canada 50/50 with Barrick 50/50 with Teck A DEVELOPMENT-STAGE COMPANY WITH TWO PROJECTS OF EXCEPTIONAL SCALE, QUALITY, AND JURISDICTIONAL SAFETY 4
  • 5. EXCELLENT PROGRESS MADE ON ALL FRONTS WHILE SAFEGUARDING OUR BALANCE SHEET First Quarter Activities 5 ACHIEVEMENTS ▶ Excellent progress in permitting of Donlin Gold • Submission of comments on initial draft EIS from six cooperating agencies to the Corps, the lead agency • Anticipate publishing the draft EIS by year-end 2015 ▶ Advanced Galore Creek technical studies • Focused on project mine planning and design to further improve its value and marketability ▶ Released the opening segment of the Alaska Video Series – Yup’ik Language and Culture • Four-part video series on the way of life in Alaska • Documenting the way of life in the remote communities of the Y-K region, where the Donlin Gold project is located, and the importance of subsistence living and traditional lifestyles ▶ Sponsored, volunteered and participated in local community activities in Northern British Columbia and Alaska • Iditarod Trail International Sled Dog Race • Tahltan educational and healthy living initiatives
  • 6. Q1-2015 Project Activity ▶ Donlin Gold o Activities focused on the draft EIS and other major permit applications with state and federal permitting agencies o Joint optimization studies with Barrick ($1.5 million, NG 50% share) o Continued community engagement and development initiatives o Project funding (NG 50% share) • Q1-2015: $2.4 million • FY-2015: $12.6 million ▶ Galore Creek o Technical studies with Teck, focusing on optimizing mine planning and project design o Project funding (NG 50% share) • Q1-2015: $0.1 million • FY-2015: $1.6 million 6
  • 7. Q1-2015 Operating Performance Analysis Q1 Highlights (US$ millions) 2015 2014 General and administrative expenses(1) $8.5 $7.7 Projects: Donlin Gold 2.5 2.9 Galore Creek 0.1 0.7 Donlin Gold studies 0.2 -- Operating loss 11.3 11.3 Other income (expense) 2.0 0.6 Net loss $9.3 $10.7 (1) Includes share-based compensation expense of $5.3 and $4.7 million in 2015 and 2014, respectively. 7
  • 8. Q1-2015 Cash Flow Highlights (US$ millions) First Quarter Full Year Budget Cash used in operating activities(1) $ (5.6) $ (14.8) Project funding: Donlin Gold (2.4) (12.6) Galore Creek (0.1) (1.6) Repayment of convertible notes -- (15.8) Foreign exchange effect on cash (0.2) -- Decrease in cash and term deposits (8.3) (44.8) Cash and term deposits Beginning 165.3 164.8 Ending $157.0 $120.5 8(1) Includes $0.2 million and $1.5 million for the first quarter and full year budget, respectively, for joint Donlin studies with Barrick.
  • 9. Notes: 1) Shown on 100% project basis, of which NOVAGOLD holds a 50% interest 2) Measured and indicated resources inclusive of proven and probable reserves. See “Cautionary Note Concerning Reserve & Resource Estimates” and “Reserve & Resource Base” with footnotes in the appendix. RESERVES1 34Moz Proven & Probable Grade: 2.09 g/t RESOURCES1,2 39Moz Measured & Indicated Grade: 2.24 g/t 6Moz Inferred Grade: 2.02 g/t (inclusive of P&P reserves) AMONG THE WORLD’S MOST SIGNIFICANT AND HIGHEST-GRADE GOLD DEPOSITS 9 Donlin Gold: A Large High-Grade Gold Project
  • 10. A REMARKABLE RESOURCE AMONG EMERGING OPEN-PIT GOLD DEPOSITS Donlin Gold: The Emerging Top-Tier Producer in the Safest Jurisdiction 0.00 0.20 0.40 0.60 0.80 1.00 1.20 1.40 1.60 Donlin Gold Metates Pascua Lama Livengood Blackwater Courageous Lake Mt. Todd Merian Morelos Stibnite Rainy River Cerro Maricunga Dublin Gulch Haile 1.102 0.66 0.64 0.58 0.41 0.39 0.37 0.35 0.34 0.34 0.23 0.23 0.21 0.13 1.501 ProjectedAnnualGoldProduction (millionsofounces) Notes: • Peer group data as per latest company documents, public filings and websites. Comparison group based on large (M&I+P&P 4Moz cut off), North/South American and Oceanian gold-focused development projects where the majority of the M&I resource is open-pit. • Donlin Gold data as per the second updated feasibility study effective November 18, 2011, as amended January 20, 2012. Represents 100% of measured and indicated resources of which NOVAGOLD’s share represents 50%. Measured and indicated resources inclusive of proven and probable reserves. See “Cautionary Note Concerning Reserve & Resource Estimates” and “Reserve & Resource Base” with footnotes in the appendix. (1) Projected annual gold production during first five full years of mine life; (2) Projected annual gold production during full life of mine. 0.0 5.0 10.0 15.0 20.0 25.0 30.0 35.0 40.0 Donlin Gold Pascua Lama Metates Livengood Blackwater Courageous Lake Mt. Todd Rainy River Stibnite Merian Cerro Maricunga Morelos Dublin Gulch Haile 39.0 21.8 19.0 15.7 9.2 8.0 7.8 6.4 5.5 5.5 5.2 5.0 4.9 4.0 M&IGoldResource (millionsofounces) ▶ Donlin Gold’s size and production profile clearly distinguish it from its peers 10
  • 11. 0.00 0.50 1.00 1.50 2.00 2.50 3.00 Morelos Courageous Lake Donlin Gold Haile Stibnite Pascua Lama Rainy River Merian Mt. Todd Blackwater Dublin Gulch Livengood Metates Cerro Maricunga 2.79 2.31 2.24 1.77 1.63 1.41 1.14 1.13 0.81 0.74 0.68 0.61 0.50 0.38 ▸ Grade compares well among peer group of emerging open-pit gold deposits M&IGoldGrade(g/t) Notes: • Development-stage peer group data as per latest company documents, public filings and websites. Comparison group based on large (M&I+P&P 4Moz cut off), North/South American and Oceanian gold-focused development projects where the majority of the M&I resource is open-pit Top gold producers group data based on 2014 year-end reserve and resource grades (combined proven & probable reserves and measured & indicated resources) for open-pit and underground material as per public filings. 1. 2014 average grade per tonne is not yet available for Gold Fields, AngloGold Ashanti and Polyus. Current figures represent reported 2013 year-end reserve and resource grades. • Donlin Gold data as per the second updated feasibility study effective November 18, 2011, as amended January 20, 2012. Represents 100% of measured and indicated resources of which NOVAGOLD’s share represents 50%. Measured and indicated resources inclusive of proven and probable reserves. See “Cautionary Note Concerning Reserve & Resource Estimates” and “Reserve & Resource Base” with footnotes in the appendix. 0.00 0.50 1.00 1.50 2.00 2.50 Donlin Gold Gold Fields Polyus Agnico Eagle AngloGold Ashanti Barrick Goldcorp Newmont Yamana Kinross Newcrest 2.24 2.24 2.14 1.89 1.81 1.46 0.89 0.87 0.85 0.72 0.63 M&IGoldGrade(g/t) DONLIN GOLD’S HIGH GRADE ENDOWMENT PROVIDES RESILIENCE TO GOLD PRICE CYCLES Donlin Gold: Among the Highest-Quality Open-Pit Development-Stage Gold Deposit 11 111 ▸ Donlin Gold’s grade is one of the highest when compared to the world’s biggest producers
  • 12. MULTIPLE DRILL PROSPECTS AND TARGETS EXIST ALONG 8KM TREND Donlin Gold: Excellent Exploration Potential 12 The next big gold discovery? ▶ Potential to expand current open-pit resources along strike and at depth ▶ Good prospects to discover meaningful deposits outside current mine footprint • Reserves and resources are contained within just 3 km of an 8 km long trend ▶ Inferred mineral resource: 6 Moz of gold mainly inside the reserve pit • Upside potential to project economics ▶ In-pit area covers 1,600 acres (~2%) of the 80,000 acres comprising the entire land package
  • 13. 0 5,000 10,000 15,000 20,000 25,000 30,000 1,200 1,300 1,500 1,700 2,000 2,500 6.2B 8.2B 11.6B 14.6B 19.2B 27.0B NPV(US$inmillions) Gold Price (US$) NPV INCREASES ~20X WITH ~2X INCREASE IN GOLD PRICE Donlin Gold: Significant Value Upside with Higher Gold Prices 13 Notes: Donlin Gold estimates as per the second updated feasibility study effective November 18, 2011, as amended January 20, 2012 . All dollar figures are in USD and reflect after-tax net present value (at a 0% and 5% discount rates) of the Donlin Gold project as of 1/1/2014. At a 5% discount rate, the net present value is: $547 m @ $1,200 gold; $1,465m @ $1,300 gold; $3,147m @ $1,500 gold; $4,581 m @ $1,700 gold; $6,722 m @ $2,000 gold; and $10,243 m @ $2,500 gold. Project development costs prior to 1/1/2014 are treated as sunk costs. 27year mine life NPV at 0%NPV at 5% ▶ Project has a positive return that increases substantially with higher gold prices ▶ Good payback at a broad range of gold prices ▶ Significant exploration upside on the mineralized trend ▶ Long mine life offers high likelihood of enjoying one or more cyclical bull markets over the period of the mine’s operation
  • 14. JURISDICTIONAL APPEAL IS COMPRISED OF FIVE CORNERSTONES: 1) MINERAL POTENTIAL 2) ESTABLISHED MINING PRACTICE 3) POLITICAL AND SOCIAL STABILITY 4) EXCELLENT LOCAL PARTNERSHIPS AND, OF “EXISTENTIAL IMPORTANCE”... 5) A FULL EMBRACE OF THE RULE OF LAW Donlin Gold: Leverage in a Place WhereYou Can Keep the Rewards – Location, Location, Location 14 Political Risk Insignificant Low Medium High Extreme Source: SNL Metals & Mining, Political Risk Assessment, March 16, 2015
  • 15. Donlin Gold: Consistently Advancing the Project 0 10 20 30 40 50 60 2008 2009 2010 2011 2012 2013 2014 2015F 53 21 42 45 37 24 28 25 CO-OWNERS COMMITTED TO MOVING DONLIN GOLD THROUGH PERMITTING TO A CONSTRUCTION DECISION AT A MEASURED PACE 15 ProjectFundingon100%basis(US$Millions) Notes: The data presented above is as per NOVAGOLD’s public disclosures. The Donlin Gold LLC, formed in December 2007, is owned 50/50 by Barrick Gold Corporation and NOVAGOLD. NOVAGOLD contributed 50% of project funding shown above. Filed Donlin Gold FS adding 14.7Moz Optimization studies completed, reserves up by 4.3Moz Updated FS, resources increased 135% from 2006 FS approved, permitting commenced Initial draft EIS completed Anticipate publishing draft EIS Donlin Gold FS completed Public scoping completed
  • 16. Barrick Gold Fourth Quarter 2014 Results – Highlights “The 50% owned Donlin Gold project located in Alaska is one of the largest undeveloped gold deposits in the world. In terms of size, grade, and jurisdictional safety, Donlin Gold is an excellent asset in Barrick's portfolio with significant leverage to the price of gold... In addition to its already large mineral endowment, the project also has exploration potential which could expand the current open pit resource.... Donlin Gold has substantial leverage to gold prices and has the potential to add significant value to Barrick and its future growth pipeline in a higher gold price environment...” Donlin Gold: Perfect Alignment between Partners 16 Notes: As per Barrick Gold’s Fourth Quarter and Full Year 2014 Results disclosed on February 18, 2015. Emphasis added by NOVAGOLD Barrick’s full Donlin Gold disclosure on slide 23 of the appendix
  • 17. COLLABORATING WITH OUR PARTNER TO MAXIMIZE PROJECT RETURN Donlin Gold: Partnerships & Activities Barrick and NOVAGOLD are jointly committed to working together to create shareholder value from Donlin Gold’s unique optionality ▶ Project activities continue to progress as planned ▶ After further de-risking, we are encouraged by Donlin Gold’s prospects ▶ Focused on advancing Donlin Gold through permitting to a record of decision ▶ Working together with Barrick to evaluate development scenarios ▶ Neither partner has a build at any gold price mentality “Both companies are happy to take a sober and constructive view. We don't want to subsidize the world's consumption of gold by squandering the treasures that Mother Nature has given us and we're happy to wait for the higher gold prices that will make the project's economics sing.” – Thomas S. Kaplan, Chairman of NOVAGOLD RETAINING THE GREATEST VALUE WHILE ENSURING CAPITAL EFFICIENCY 17
  • 18. Notice of Intent to Prepare EIS Draft EIS Final EIS Record of Decision Initial permit applications Submitted: 08/12 Notice of intent Issued: 12/14/12 Public scoping period Ended: 03/29/13 Scoping summary document Completed: 08/13 Development of alternatives Completed: Q2/14 Initial drafts of EIS chapters Completed: Q4/14 Agency & Donlin Gold review Completed: Q4/14 Prepare draft EIS Publish draft EIS Public comment period Prepare draft final EIS Agency review Publish final EIS Record of decision 2012-2013 2013-2015 2015-2017 PAST THE HALFWAY MARK IN THE EIS PROCESS Donlin Gold: Permitting Milestones 18
  • 19. CONTINUE TO EXECUTE AND DELIVER ON OUR BUSINESS PLAN 2015 Outlook 1 2 3 4 5 PRIORITY PRIORITY PRIORITY PRIORITY PRIORITY Advance Donlin Gold permitting to a construction decision Advance Galore Creek mine planning and project design Evaluate opportunities to monetize the value of Galore Creek Safeguard our cash position Maintain strong relationships with all stakeholders COMMITTED TO GOLD THROUGH VARIOUS MARKET CYCLES 19
  • 20. NOVAGOLD focused on execution and delivery of our business plan NOVAGOLD Highlights Safe Geo-Political Environment: Alaska and British Columbia, top-rated mining jurisdictions Accomplished Team: 185 years cumulative experience Prolific Production Profile: Donlin Gold expected to be one of industry’s top producing assets; strong leverage to gold Supportive Stakeholders: Long standing shareholders and engaged partners Strong Balance Sheet: $157m cash + term deposits as of February 28, 2015 Top Tier Assets: Donlin Gold: Large, high- grade deposit past 50% mark in permitting; great additional exploration potential 20
  • 21. Congratulations to the Yukon-Kuskokwim Mushers 21
  • 23. Barrick Gold Fourth Quarter 2014 Results – Full Donlin Gold Disclosure “The 50% owned Donlin Gold project located in Alaska is one of the largest undeveloped gold deposits in the world. In terms of size, grade, and jurisdictional safety, Donlin Gold is an excellent asset in Barrick's portfolio with significant leverage to the price of gold. The Donlin Gold project has approximately 39 million ounces of contained gold (100% basis) in the measured and indicated resource categories (approximately 8 million tonnes grading 2.52 g/t (measured) and 533 million tonnes grading 2.24 g/t (indicated)). In addition to its already large mineral endowment, the project also has exploration potential which could expand the current open pit resource. Under our disciplined capital allocation framework, we have continued to work with our partner, Novagold Resources, to advance the Donlin Gold project. Current activities, by which we maintain and enhance the option value of this project at a modest cost, are focused on permitting, community outreach and workforce development. In 2014, Donlin Gold secured long-term surface use rights and significantly advanced the permitting of the Donlin Gold project which is now about halfway complete. Barrick is working closely with its partner on alternatives designed to minimize initial capital outlay. The outcome of that effort may include engagement of third party operators and exploring possibilities for third party financing of some capital intensive infrastructure. Collectively, we are also investing about $3 million (100% basis) on technical studies to identify potential design and execution enhancements. Donlin Gold has substantial leverage to gold prices and has the potential to add significant value to Barrick and its future growth pipeline in a higher gold price environment. Any decision to proceed with development, either as currently envisaged, or in an optimized scenario, will depend on the project meeting Barrick's minimum hurdle rate which will depend in large part on the prevailing gold prices and market conditions.” Donlin Gold: Perfect Alignment between Partners 23 Notes: As per Barrick Gold’s Fourth Quarter and Full Year 2014 Results disclosed on February 18, 2015.
  • 24. NOVAGOLD: Reserve/Resource Table 24 Donlin Gold (100% basis)* Tonnage Grade Metal content GOLD Kt g/t Au Koz Au Reserves1 Proven 7,683 2.32 573 Probable 497,128 2.08 33,276 P&P 504,811 2.09 33,849 Resources3, inclusive of Reserves Measured 7,731 2.52 626 Indicated 533,607 2.24 38,380 M&I 541,337 2.24 39,007 Inferred 92,216 2.02 5,993 Galore Creek (100% basis)* Tonnage Grade Metal content COPPER Mt % Cu Blb Cu Reserves2 Proven 69.0 0.606 0.9 Probable 459.1 0.582 5.9 P&P 528.0 0.585 6.8 Resources4, exclusive of Reserves Measured 39.5 0.25 0.22 Indicated 247.2 0.34 1.85 M&I 286.7 0.33 2.07 Inferred 346.6 0.42 3.23 GOLD Mt g/t Au Moz Au Reserves2 Proven 69.0 0.520 1.15 Probable 459.1 0.291 4.30 P&P 528.0 0.321 5.45 Resources4, exclusive of Reserves Measured 39.5 0.39 0.50 Indicated 247.2 0.26 2.04 M&I 286.7 0.27 2.53 Inferred 346.6 0.24 2.70 SILVER Mt g/t Ag Moz Ag Reserves2 Proven 69.0 4.94 11.0 Probable 459.1 6.18 91.2 P&P 528.0 6.02 102.1 Resources4, exclusive of Reserves Measured 39.5 2.58 3.27 Indicated 247.2 3.81 30.26 M&I 286.7 3.64 33.54 Inferred 346.6 4.28 47.73 * Mineral reserves are reported on a 100% basis. NOVAGOLD and Barrick each own 50% of the Donlin Gold project. NOVAGOLD and Teck each own 50% of the Galore Creek project. t = metric tonne oz = ounce lb = pound K = thousand M = million B = billion g/t = grams/tonne Approximate cut-off grades (see Resource Footnotes): Donlin Gold Reserves1: 0.57 g/t gold Resources3: 0.46 g/t gold Galore Creek Reserves2: C$10.08 NSR Resources4: C$10.08 NSR
  • 25. Notes: a. These resource estimates have been prepared in accordance with NI43-101 and the CIM Definition Standard, unless otherwise noted. b. See numbered footnotes below on resource information. c. Rounding as required by reporting guidelines may result in apparent summation differences between tonnes, grade and contained metal content d. Tonnage and grade measurements are in metric units. Contained gold and silver ounces are reported as troy ounces, contained copper pounds as imperial pounds Resource Footnotes: 1) Mineral Reserves are contained within Measured and Indicated pit designs, and supported by a mine plan, featuring variable throughput rates, stockpiling and cut-off optimization. The pit designs and mine plan were optimized on diluted grades using the following economic and technical parameters: Metal price for gold of US$975/oz; reference mining cost of US$1.67/t incremented US$0.0031/t/m with depth from the 220 m elevation (equates to an average mining cost of US$2.14/t), variable processing cost based on the formula 2.1874 x (S%) + 10.65 for each US$/t processed; general and administrative cost of US$2.27/t processed; stockpile rehandle costs of US$0.19/t processed assuming that 45% of mill feed is rehandled; variable recoveries by rock type, ranging from 86.66% in shale to 94.17% in intrusive rocks in the Akivik domain; refining and freight charges of US$1.78/oz gold; royalty considerations of 4.5%; and variable pit slope angles, ranging from 23º to 43º. Mineral Reserves are reported using an optimized net sales return value based on the following equation: Net Sales Return = Au grade * Recovery * (US$975/oz – (1.78 + (US$975/oz – 1.78) * 0.045)) - (10.65 + 2.1874 * (S%) + 2.27 + 0.19) and reported in US$/tonne. Assuming an average recovery of 89.54% and an average S% grade of 1.07%, the marginal gold cutoff grade would be approximately 0.57 g/t, or the gold grade that would equate to a 0.001 NSR cutoff at these same values. The life of mine strip ratio is 5.48. The assumed life-of-mine throughput rate is 53.5 kt/d. 2) Mineral Reserves are contained within Measured and Indicated pit designs using metal prices for copper, gold and silver of US$2.50/lb, US$1,050/oz, and US$16.85/oz, respectively. Appropriate mining costs, processing costs, metal recoveries and inter ramp pit slope angles varying from 42º to 55º were used to generate the pit phase designs. Mineral Reserves have been calculated using a 'cashflow grade' ($NSR/SAG mill hr) cut-off which was varied from year to year to optimize NPV. The net smelter return (NSR) was calculated as follows: NSR = Recoverable Revenue – TCRC (on a per tonne basis), where: NSR = Net Smelter Return; TCRC = Transportation and Refining Costs; Recoverable Revenue = Revenue in Canadian dollars for recoverable copper, recoverable gold, and recoverable silver using metal prices of US$2.50/lb, US$1,050/oz, and US$16.85/oz for copper, gold, and silver, respectively, at an exchange rate of CDN$1.1 to US$1.0; Cu Recovery = Recovery for copper based on mineral zone and total copper grade; for Mineral Reserves this NSR calculation includes mining dilution. SAG throughputs were modeled by correlation with alteration types. Cash flow grades were calculated as the product of NSR value in $/t and throughput in t/hr. The life of mine strip ratio is 2.16. 3) Mineral Resources are contained within a conceptual Measured, Indicated and Inferred optimized pit shell using the following assumptions: gold price of US$1,200/oz; variable process cost based on 2.1874 * (sulphur grade) + 10.6485; administration cost of US$2.29/t; refining, freight & marketing (selling costs) of US$1.85/oz recovered; stockpile rehandle costs of US$0.20/t processed assuming that 45% of mill feed is rehandled; variable royalty rate, based on royalty of 4.5% * (Au price – selling cost). Mineral Resources have been estimated using a constant Net Sales Return cut-off of US$0.001/t milled. The Net Sales Return was calculated using the formula: Net Sales Return = Au grade * Recovery * (US$1200/oz – (1.85 + ((US$1200/oz – 1.85) * 0.045)) - (10.65 + 2.1874 * (S%) + 2.29 + 0.20)) and reported in US$/tonne. Mineral Resources are inclusive of Mineral Reserves. Mineral Resources that are not Mineral Reserves do not have demonstrated economic viability. Inferred Resources are in addition to Measured and Indicated Resources. Inferred Resources have a great amount of uncertainty as to their existence and whether they can be mined legally or economically. It cannot be assumed that all or any part of the Inferred Resources will ever be upgraded to a higher category. See "Cautionary Note Concerning Reserve & Resource Estimates". 4) Mineral resources are contained within a conceptual Measured, Indicated and Inferred optimized pit shell using the same economic and technical parameters as used for Mineral Reserves. Tonnages are assigned based on proportion of the block below topography. The overburden/bedrock boundary has been assigned on a whole block basis. Mineral resources have been estimated using a constant NSR cut-off of C$10.08/t milled. The Net Smelter Return (NSR) was calculated as follows: NSR = Recoverable Revenue – TCRC (on a per tonne basis), where: NSR = Diluted Net Smelter Return; TCRC = Transportation and Refining Costs; Recoverable Revenue = Revenue in Canadian dollars for recoverable copper, recoverable gold, and recoverable silver using silver using the economic and technical parameters mentioned above. The mineral resource includes material within the conceptual M,I&I pit that is not scheduled for processing in the mine plan but is above cutoff. Mineral Resources are inclusive of Mineral Reserves. Mineral Resources that are not Mineral Reserves do not have demonstrated economic viability. Inferred Resources are in addition to Measured and Indicated Resources. Inferred Resources have a great amount of uncertainty as to their existence and whether they can be mined legally or economically. It cannot be assumed that all or any part of the Inferred Resources will ever be upgraded to a higher category. See "Cautionary Note Concerning Reserve & Resource Estimates". Cautionary Note Concerning Reserve & Resource Estimates This summary table uses the term “resources”, “measured resources”, “indicated resources” and “inferred resources”. United States investors are advised that, while such terms are recognized and required by Canadian securities laws, the United States Securities and Exchange Commission (the “SEC”) does not recognize them. Under United States standards, mineralization may not be classified as a “reserve” unless the determination has been made that the mineralization could be economically and legally produced or extracted at the time the reserve determination is made. Mineral resources that are not mineral reserves do not have demonstrated economic viability. United States investors are cautioned not to assume that all or any part of measured or indicated resources will ever be converted into reserves. Further, inferred resources have a great amount of uncertainty as to their existence and as to whether they can be mined legally or economically. It cannot be assumed that all or any part of the inferred resources will ever be upgraded to a higher category. Therefore, United States investors are also cautioned not to assume that all or any part of the inferred resources exist, or that they can be mined legally or economically. Disclosure of “contained ounces” is permitted disclosure under Canadian regulations, however, the SEC normally only permits issuers to report “resources” as in place tonnage and grade without reference to unit measures. Accordingly, information concerning descriptions of mineralization and resources contained in this release may not be comparable to information made public by United States companies subject to the reporting and disclosure requirements of the SEC. NI 43-101 is a rule developed by the Canadian Securities Administrators, which established standards for all public disclosure an issuer makes of scientific and technical information concerning mineral projects. Unless otherwise indicated, all resource estimates contained in this circular have been prepared in accordance with NI 43-101 and the CIM Definition Standards. Technical Reports and Qualified Persons The documents referenced below provide supporting technical information for each of NOVAGOLD's projects. Project Qualified Person(s) Most Recent Disclosure & Filing Date Donlin Gold Gordon Seibel R.M. SME, AMEC “Donlin Creek Gold Project Alaska, USA, NI 43-101 Technical Report on Second Updated Feasibility Study” effective November 18, 2011, amended January 20, 2012. Kirk Hanson P.E., AMEC Galore Creek Jay Melnyk, P.Eng., AMEC “Galore Creek Copper-Gold Project NI 43-101 Technical Report on Pre-Feasibility Study, British Columbia – Canada” effective July 27, 2011. Greg Kulla, P.Geo., AMEC Heather White, B.Sc., P.Eng., who is a consultant to NOVAGOLD and a “qualified person” under NI 43-101, has approved the scientific and technical information included in this Reserve and Resource Table. NOVAGOLD: Reserve/Resource Table (con’t) 25
  • 26. NOVAGOLD RESOURCES INC. Suite 720 – 789 West Pender Street Vancouver, BC Canada V6C 1H2 T 604 669 6227 TF 1 866 669 6227 F 604 669 6272 www.novagold.com info@novagold.com Mélanie Hennessey VP, Corporate Communications melanie.hennessey@novagold.com Erin O’Toole Analyst, Investor Relations erin.otoole@novagold.com Contact Us 26